KR102593946B1 - A two-arch tunnel having a dedicate drainage case inside the upper girder of the central wall and its construction method - Google Patents

A two-arch tunnel having a dedicate drainage case inside the upper girder of the central wall and its construction method Download PDF

Info

Publication number
KR102593946B1
KR102593946B1 KR1020210134853A KR20210134853A KR102593946B1 KR 102593946 B1 KR102593946 B1 KR 102593946B1 KR 1020210134853 A KR1020210134853 A KR 1020210134853A KR 20210134853 A KR20210134853 A KR 20210134853A KR 102593946 B1 KR102593946 B1 KR 102593946B1
Authority
KR
South Korea
Prior art keywords
tunnel
drainage
central
case
central wall
Prior art date
Application number
KR1020210134853A
Other languages
Korean (ko)
Other versions
KR20230051904A (en
Inventor
전영권
이상교
이종호
Original Assignee
전영권
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 전영권 filed Critical 전영권
Priority to KR1020210134853A priority Critical patent/KR102593946B1/en
Publication of KR20230051904A publication Critical patent/KR20230051904A/en
Application granted granted Critical
Publication of KR102593946B1 publication Critical patent/KR102593946B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/381Setting apparatus or devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/383Waterproofing; Heat insulating; Soundproofing; Electric insulating by applying waterproof flexible sheets; Means for fixing the sheets to the tunnel or cavity wall
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Civil Engineering (AREA)
  • Architecture (AREA)
  • Environmental & Geological Engineering (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

본 발명은 2아치터널의 시공시 중앙터널(25) 시공한 후에 중앙벽체를 시공하고 본선터널(10,20) 굴착·시공 후 라이닝콘크리트(11)를 시공하게 되는데 중앙벽체의 양쪽의 상부 거더(30)와 좌·우측 본선터널(10, 20)의 굴착면이 만나는 시공접합부(50)가 중앙터널 천단부와 본선터널의 천단부에 비해 위치가 낮아 이 좌·우측의 시공접합부(50)에 터널 상부에서 발생되는 지하수가 집중하여 모이게 되고 이로 인하여 좌·우측의 중앙벽체 상부 거더(30)와 본선터널의 라이닝콘크리트(11)가 만나는 부분인 시공이음부(100)에 항상 누수가 문제가 되고 있다.
이러한 누수에 취약한 2아치터널의 배수구조에 대하여 중앙벽체 양쪽 상부 거더(30)의 내부에 지하수 배수 전용 케이스(150)를 설치하고 좌·우측 본선터널(10, 20)에 설치되는 드레인 보드(200)와 방수시트(210)를 배수 전용 케이스(150) 내부에 삽입한 후 본선 좌·우측 콘크리트라이닝(11)을 시공함으로서 중앙벽체와 본선터널(10, 20)이 만나는 시공접합부(50)에 모이는 지하수를 배수 전용 케이스(150) 완벽하게 내부로 유도하여 효율적으로 배수시켜 누수를 완벽하게 차단하여 대칭2아치터널 또는 비대칭2아치터널의 시공성을 향상시켜 중앙벽체의 품질관리가 용이하며 향후 발생되는 유지관리비를 절감하는 효과가 있다.
In the present invention, when constructing a two-arch tunnel, the central wall is constructed after constructing the central tunnel (25), and the lining concrete (11) is constructed after excavating and constructing the main tunnel (10, 20). The upper girders on both sides of the central wall ( 30) and the construction joint 50 where the excavation surfaces of the left and right main tunnels 10 and 20 meet are located lower than the top end of the central tunnel and the top end of the main tunnel, so that the construction joint 50 on the left and right Groundwater generated at the top of the tunnel concentrates and collects, and as a result, water leakage always becomes a problem at the construction joint (100), which is the part where the upper girder (30) of the left and right central walls and the lining concrete (11) of the main tunnel meet. there is.
Regarding the drainage structure of the two-arch tunnel, which is vulnerable to such water leaks, a groundwater drainage case (150) is installed inside the upper girders (30) on both sides of the central wall, and a drain board (200) is installed on the left and right main tunnels (10, 20). ) and the waterproofing sheet 210 are inserted into the drainage case 150 and then the concrete linings 11 on the left and right sides of the main line are constructed, so that the water collected at the construction joint 50 where the central wall and the main line tunnel 10, 20 meet. Groundwater is completely guided inside the drainage-only case (150) and drained efficiently, completely blocking leaks and improving the constructability of the symmetrical 2-arch tunnel or asymmetrical 2-arch tunnel, making quality control of the central wall easy and future maintenance. It has the effect of reducing management costs.

Description

중앙벽체 상부 거더 내부에 배수 전용 케이스를 갖는 2아치터널 및 그 시공방법{A two-arch tunnel having a dedicate drainage case inside the upper girder of the central wall and its construction method}A two-arch tunnel having a dedicated drainage case inside the upper girder of the central wall and its construction method}

본 발명은 중앙터널(25) 굴착·시공 후, 중앙터널(25)의 내부에 중앙벽체 기초(45), 중앙벽체(40) 및 중앙벽체 상부 거더(30)로 구성되는 중앙벽체를 시공하고, 중앙벽체 좌·우측에 본선터널(10, 20)을 굴착·시공한 후에 중앙벽체 거더부(30)의 좌·우측에 본선터널 콘크리트라이닝(11) 구조물이 시공되는 2아치터널에서 중앙터널(25)과 본선터널이 만나는 접합부(50)가 중앙터널(25)과 본선터널(10, 20)의 천단부 보다 낮은 위치에 있어 터널의 상부에서 발생되는 지하수가 접합부(50)를 통하여 중앙벽체 상부거더(30)와 본선터널의 라이닝콘크리트(11)가 만나는 시공이음부(100)에서 발생되는 누수를 완벽하게 방지하기 위하여 중앙벽체 상부 거더부(30) 내부에 배수 전용 케이스(150)를 설치하는 2아치터널 및 그 시공방법에 관한 것이다.In the present invention, after excavating and constructing the central tunnel (25), a central wall consisting of a central wall foundation (45), a central wall (40), and a central wall upper girder (30) is constructed inside the central tunnel (25), After excavating and constructing the main tunnel (10, 20) on the left and right sides of the central wall, the central tunnel (25) is constructed in the 2-arch tunnel where the main tunnel concrete lining (11) structure is constructed on the left and right sides of the central wall girder portion (30). ) and the main line tunnel meet at a lower location than the ceiling of the central tunnel (25) and the main tunnel (10, 20), so groundwater generated at the top of the tunnel flows through the joint (50) to the upper girder of the central wall. In order to completely prevent water leakage occurring at the construction joint (100) where (30) meets the lining concrete (11) of the main tunnel, a drainage case (150) is installed inside the upper girder part (30) of the central wall. It relates to arch tunnels and their construction methods.

도 1, 도 2 및 도 3은 종래 2아치터널의 시공을 나타낸 것으로, 먼저 중앙터널(25)을 굴착·시공한 후, 중앙벽체의 기초(45) 및 중앙벽체(40)를 시공하고, 중앙벽체(40)의 상부 거더(30)를 시공한 다음 중앙터널(25)의 좌·우측 본선터널(10, 20)을 굴착·시공하고 라이닝콘크리트(11) 등을 타설하여 2아치터널 시공을 완료하는 것이 일반적이다.Figures 1, 2, and 3 show the construction of a conventional two-arch tunnel. First, the central tunnel 25 is excavated and constructed, then the foundation 45 and the central wall 40 of the central wall are constructed, and the central tunnel 25 is excavated and constructed. After constructing the upper girder (30) of the wall (40), the left and right main tunnels (10, 20) of the central tunnel (25) are excavated and constructed, and the lining concrete (11) is poured to complete the construction of the two-arch tunnel. It is common to do so.

여기서, 이후에 별도로 구분하지 않고 중앙벽체라고 칭할 때는 중앙벽체 기초(45), 중앙벽체(40), 상부 거더(30)까지 전체를 통상적으로 표현되는 명칭을 일컫는 표현이다.Hereinafter, when it is referred to as a central wall without separate distinction, it is an expression referring to the commonly expressed name for the entire central wall foundation (45), central wall (40), and upper girder (30).

도 2는 종래 2아치터널의 중앙벽체 상부(30)를 확대하여 도시한 것으로 중앙터널(25)을 굴착·시공한 후 중앙터널(25) 내부에 시공되는 중앙벽체(40)의 상부 거더(30)의 양쪽에 좌·우측 본선터널(10, 20)의 라이닝콘크리트(11) 단부와 연결된다.Figure 2 is an enlarged view of the upper part of the central wall (30) of a conventional two-arch tunnel, and shows the upper girder (30) of the central wall (40) constructed inside the central tunnel (25) after excavating and constructing the central tunnel (25). ) is connected to the ends of the lining concrete (11) of the left and right main tunnels (10, 20) on both sides.

상기 2아치터널의 상부 거더(30)는 좌·우측 본선터널(10, 20)의 라이닝콘크리트(11) 단부가 접하는 사다리꼴 형태의 하부구체(30a)와 하부구체(30a) 상단에 형성되는 부채꼴 형태의 상부구체(30b)로 시공되고 중앙벽체 상부 거더(30)의 좌·우측부에 본선터널(10, 20)의 좌·우측 터널 라이닝콘크리트(11) 단부가 만나는 시공이음부(100)가 발생되어 중앙터널(25)과 좌·우측 본선터널(10, 20)의 접합부(50)가 중앙터널(25)과 본선터널(10, 20)의 천단부 보다 높이가 낮아 접합부(50)에 터널상부에서 발생되는 지하수가 모이게 되고 이 지하수가 시공 이음부(100)로 배출되는 구조적으로 누수에 취약한 부분이다.The upper girder 30 of the two-arch tunnel has a trapezoidal lower sphere 30a in contact with the ends of the lining concrete 11 of the left and right main tunnels 10 and 20, and a fan shape formed on the top of the lower sphere 30a. It is constructed with the upper sphere (30b), and a construction joint (100) is created on the left and right sides of the central wall upper girder (30) where the ends of the left and right tunnel lining concrete (11) of the main tunnel (10, 20) meet. As a result, the junction 50 of the central tunnel 25 and the left and right main tunnels 10 and 20 is lower in height than the ceiling of the central tunnel 25 and the main tunnels 10 and 20, so that the upper part of the tunnel is attached to the junction 50. This is a part that is structurally vulnerable to water leaks, where groundwater generated from there collects and is discharged to the construction joint (100).

상기 중앙벽체(40) 상부 거더부(30)에서의 누수를 방지하기 위해 종방향 배수유공관(90)을 설치하는 등 접합부(50)의 방수시공이 복잡하고 어려워 주로 좌·우측 본선터널(10, 20)의 라이닝콘크리트(11)의 시공이음부(100)를 통해 누수가 발생하게 된다.In order to prevent water leakage from the upper girder part 30 of the central wall 40, waterproofing construction of the joint 50, such as installing a longitudinal drain pipe 90, is complicated and difficult, so it is mainly used in the left and right main tunnels 10, Water leakage occurs through the construction joint 100 of the lining concrete 11 of 20).

도 3은 종방향 배수 유공관(90) 및 상부거더 횡방향 배수관(80)을 사시도로 표현한 것으로 중앙터널 방수시트(91)를 설치하고 중앙벽체(40)와 중앙벽체 상부 거더(30)를 시공한 후에 좌·우측 본선터널(10, 20)의 발파·굴착 작업과 좌·우측 본선터널(10, 20)의 지보재(93)(도 2 참조)를 중앙터널 지보재(92)(도 2 참조)와 연결하기 위해서 중앙터널(25)의 강지보재(92)를 절단할 때 선시공된 중앙터널의 방수시트(91)가 손상되는 구조적인 문제점이 있었다.Figure 3 is a perspective view of the longitudinal drainage perforated pipe 90 and the upper girder transverse drainage pipe 80, where the central tunnel waterproofing sheet 91 is installed and the central wall 40 and the central wall upper girder 30 are constructed. Later, the blasting and excavation work of the left and right main tunnels (10, 20) and the support materials (93) (see FIG. 2) of the left and right main tunnels (10, 20) are replaced with the central tunnel support materials (92) (see FIG. 2). There was a structural problem in that the waterproofing sheet 91 of the pre-constructed central tunnel was damaged when cutting the steel support 92 of the central tunnel 25 for connection.

또, 중앙터널(25)과 본선터널(10, 20)의 시공접합부(50)에 있어 터널의 종방향으로 종방향 배수 유공관(90)을 설치한 후 상부거더 횡방향 배수관(80)의 설치를 위해서 방수시트(91)를 절단하고 배수관 연결부를 감싸는 등의 작업으로 2아치터널 상부거더부(30)에서 누수에 대한 취약부분이 추가로 발생하여 추가로 누수가 발생되는 문제점이 있었다.In addition, in the construction joint 50 of the central tunnel 25 and the main tunnel 10, 20, the vertical drainage perforated pipe 90 is installed in the longitudinal direction of the tunnel, and then the upper girder horizontal drainage pipe 80 is installed. For this purpose, work such as cutting the waterproof sheet 91 and wrapping the drain pipe connection caused an additional vulnerable part to water leakage in the upper girder portion 30 of the 2 arch tunnel, causing a problem of additional water leakage.

이러한 상기의 문제점인 2아치터널의 중앙벽체 상부 거더(30)의 누수는 터널의 부실시공으로 이어지고 이후에 발생되는 하자보수, 이로 인한 터널통행 서비스 불량, 유지관리비의 증가뿐만 아니라 2아치터널의 기술적 불신을 초래하게 되는 문제점으로 이어지게 된다.The above-mentioned problem, water leakage of the upper girder 30 of the central wall of the 2-arch tunnel, leads to poor construction of the tunnel, subsequent defect repairs, poor tunnel traffic service, and increased maintenance costs, as well as technical problems of the 2-arch tunnel. This leads to problems that lead to distrust.

본 발명이 해결하려는 과제는, 중앙벽체의 상부 거더(30)의 좌·우측 내부에 삽입된 배수유입부(250)(도 6a 참조)를 가진 삼각형 단면의 배수 전용 케이스(150)로 중앙터널(25)과 좌·우측 본선터널(10, 20)의 시공접합부(50)에 모이는 지하수를 효과적으로 배수하여 중앙벽체 상부 거더(30)와 좌·우측 본선터널(10, 20)의 라이닝콘크리트(11)가 만나는 시공이음부(100)에 누수 발생을 완벽하게 차단하는 중앙벽체 상부 거더(30)의 누수방지 방법을 제공하는 것이며, 중앙터널(25) 굴착시공 단계; 중앙벽체 기초(45) 및 벽체 시공(40) 단계; 배수 전용 케이스(150) 설치와 연결 배수관(110, 140, 160) 시공 단계; 중앙벽체 상부 거더(30) 시공 단계; 좌·우측 본선터널(10, 20) 라이닝콘크리트 시공 단계로 완성되는 2아치터널의 시공방법을 그 기술적 과제로 한다.The problem to be solved by the present invention is to use a central tunnel ( 25) and the construction joints (50) of the left and right main tunnels (10, 20) are effectively drained to drain the central wall upper girder (30) and the lining concrete (11) of the left and right main tunnels (10, 20). To provide a water leak prevention method for the central wall upper girder (30) that completely blocks water leaks at the construction joint (100) where the meets, the central tunnel (25) excavation construction step; Central wall foundation (45) and wall construction (40) steps; Installation of the drainage case (150) and construction of the connected drain pipes (110, 140, 160); Central wall upper girder (30) construction stage; The technical task is the construction method of the two-arch tunnel, which is completed in the lining concrete construction stage for the left and right main tunnels (10, 20).

본 발명은 상기 기술적 과제를 달성하기 위하여, 중앙벽체(40) 상부 거더(30)의 상부면과 만나는 중앙터널(25)의 천단부에 방수시트(91)를 설치한 후, 중앙벽체 기초와(45) 중앙벽체(40)를 시공하고 중앙벽체 상부 거더(30)의 내부에 도 5와 같이 배수전용 케이스(150)와 배수 연결관(110, 140, 160)(도 6 참조)을 설치한 후에 상부 거더(30)의 하부구체(30a)와 부채꼴 형태의 상부 구체(30b)를 콘크리트 타설하여 중앙벽체의 시공을 완료한 후에 도 6과 같이 본선터널(10, 20)의 드레인 보드(200)와 방수시트(210)를 배수 전용 케이스(150)의 배수유입부(250)(도 6a 참조)의 아래 지하수 차단단부(180)를 열어 케이스 내부 바닥까지 삽입하고 열린 배수 전용 케이스(150)의 배수유입부(250)(도 6b 참조)의 아래 배수유입부(250)를 원 위치한 다음 라이닝콘크리트(11)를 타설 시공함으로서 상부 거더(30)와 본선터널 라이닝콘크리트(11)의 단부가 만나는 시공이음부(100)에 완벽한 누수 방지가 되게 된다.In order to achieve the above technical problem, the present invention installs a waterproofing sheet 91 at the ceiling end of the central tunnel 25 where it meets the upper surface of the upper girder 30 of the central wall 40, and then installs a waterproofing sheet 91 on the central wall foundation and ( 45) After constructing the central wall 40 and installing the drainage case 150 and drainage connection pipes 110, 140, and 160 (see Fig. 6) as shown in Fig. 5 inside the central wall upper girder 30. After completing the construction of the central wall by pouring concrete into the lower sphere (30a) of the upper girder (30) and the fan-shaped upper sphere (30b), the drain board (200) of the main tunnel (10, 20) and Open the groundwater blocking end 180 below the drainage inlet 250 (see Fig. 6a) of the drainage-only case 150, insert the waterproof sheet 210 to the bottom inside the case, and drain the drainage inflow of the open drainage-only case 150. A construction joint where the end of the upper girder 30 and the main tunnel lining concrete 11 meets by placing the drainage inlet 250 below the part 250 (see FIG. 6b) and then pouring the lining concrete 11. At (100), water leakage is completely prevented.

상기 배수 전용 케이스(150)에 유입되는 지하수를 배수 전용 케이스(150)의 종방향에 설치되는 중앙벽체 상부 거더(30) 내부로 경사지게 설치된 배수관(160)이 연결되는데 이러한 배수관(160)을 배수 전용 케이스(150) 내에서 일정한 간격으로 설치하여 효과적으로 배수처리가 될 수 있도록 하여 이후에 연속되는 2아치터널의 시공이 간단하고 원활하게 되도록 중앙벽체 상부 거더(30) 내부에 배수 전용 케이스(150)를 갖는 2아치터널 및 그 시공방법을 제공한다.Groundwater flowing into the drainage-only case 150 is connected to a drain pipe 160 installed at an angle inside the central wall upper girder 30 installed in the longitudinal direction of the drainage-only case 150. This drain pipe 160 is used only for drainage. A drainage-only case (150) is installed inside the upper girder (30) of the central wall to ensure effective drainage by installing it at regular intervals within the case (150) and to make the subsequent construction of the two-arch tunnel simple and smooth. A two-arch tunnel and its construction method are provided.

본 발명의 제 1 양태에 있어서, 중앙터널(25)을 형성시킨 후, 중앙터널(25)의 내부에 중앙벽체를 형성시키고 중앙벽체 좌·우측에 본선터널(10, 20)을 형성시키는 중앙벽체의 상부에 상부 거더(30)를 형성시키는 2아치터널 시공방법으로서, 상기 중앙터널(25)의 천단부에 방수시트(91)를 중앙터널(25)과 좌·우측 본선터널(10, 20)의 굴착면과의 접합부(50)까지 방수시트(91)를 연장 설치하는 단계와, 상기 상부 거더(30)의 좌·우측의 내부에 배수 전용 케이스(150)와 배수관(110, 160)과 Y형 배수관 연결관(140)을 삽입·설치하고 상기 상부 거더부(30)에 콘크리트로 타설하여 중앙벽체의 상부거더 상면이 중앙터널 천단부와 접하여 형성되도록 하는 단계와, 상기 상부 거더(30) 내부에 설치된 배수 전용 케이스(150)의 배수유입부(250)(도 6 참조)를 열어 본선터널용 드레인보드(200)와 방수시트(210)를 케이스(150) 내부 바닥까지 설치한 후에 본선터널 라이닝콘크리트(11)를 형성시키는 단계를 포함하는 하는 것을 특징으로 한다.In the first aspect of the present invention, after forming the central tunnel 25, a central wall is formed inside the central tunnel 25, and main tunnels 10 and 20 are formed on the left and right sides of the central wall. A two-arch tunnel construction method for forming an upper girder (30) on the upper part of the central tunnel (25) and the left and right main tunnels (10, 20) by attaching a waterproof sheet (91) to the upper end of the central tunnel (25). A step of extending and installing the waterproof sheet 91 up to the junction 50 with the excavation surface, and installing a drainage case 150, drain pipes 110, 160, and Inserting and installing a type drain pipe connector 140 and pouring concrete into the upper girder portion 30 so that the upper surface of the upper girder of the central wall is formed in contact with the ceiling of the central tunnel, and the inside of the upper girder 30 Open the drainage inlet 250 (see FIG. 6) of the drainage case 150 installed in the main line tunnel drain board 200 and waterproof sheet 210 to the inside floor of the case 150, then install the main line tunnel lining. It is characterized by comprising the step of forming concrete (11).

본 발명의 다른 양태에 있어서, 중앙터널(25) 내부에 설치되는 중앙벽체의 상부 거더(30) 내부에 설치되는 배수 전용 케이스(150)는 배수 전용 케이스(150)의 배수유입부(250)(도 6a 참조)에서 양쪽 바깥쪽으로 90°로 꺾어진 지하수 차단 단부(170, 180)와 배수유입부(250)(도 6a 참조)를 갖는 삼각형 단면을 갖는 것으로 특징으로 한다.In another aspect of the present invention, the drainage-only case 150 installed inside the upper girder 30 of the central wall installed inside the central tunnel 25 includes the drainage inlet 250 of the drainage-only case 150 ( It is characterized as having a triangular cross-section with groundwater blocking ends (170, 180) bent at 90° outward on both sides and a drainage inlet (250) (see FIG. 6a).

본 발명의 또 다른 하나의 양태에 있어서, 배수 전용 케이스(150)에 배수관을 설치하기 위하여 배수 전용 케이스(150) 바닥을 타공(315)한 곳에 배수 전용 케이스(150) 내부에서 고무패킹(310)을 끼운 배수관 연결본체(300)를 배수 전용 케이스(150) 바깥방향으로 삽입하고 배수 전용 케이스(150)의 외부에서 연결본체(300)에 고무패킹(311)을 끼우고 연결본체(300)를 고정시키는 암나사 홀더(320)로 배수 전용 케이스(150)에 완전하게 밀착시켜 배수관 이음관(330)으로 연결본체와 배수관(160)을 연결하고 상기 중앙벽체 상부 거더(30) 양쪽에 설치된 배수 전용 케이스(150)에 연결된 배수관(160)을 Y형 배수관 연결관(140)으로 연결하여 중앙벽체 상부 거더(30)의 하부에 일정 길이로 배수관(110)을 설치하고 배수관의 하부에는 배수관 유지관리를 용이하게 하기 위하여 집수통(120)을 설치하고 집수통 하부에 배수관(130)을 연결한 것을 특징으로 한다.In another aspect of the present invention, in order to install a drain pipe in the drainage-only case 150, a rubber packing 310 is installed inside the drainage-only case 150 where a hole 315 is made in the bottom of the drainage-only case 150. Insert the drain pipe connection body 300 with the insert in the outer direction of the drainage case 150, insert the rubber packing 311 into the connection body 300 from the outside of the drainage case 150, and fix the connection body 300. Shiki is completely adhered to the drainage case 150 with a female screw holder 320, connects the connection body and the drain pipe 160 with a drain pipe joint 330, and installs a drainage case on both sides of the central wall upper girder 30 ( The drain pipe 160 connected to 150) is connected to the Y-type drain pipe connector 140 to install a drain pipe 110 at a certain length in the lower part of the central wall upper girder 30, and to facilitate drain pipe maintenance at the lower part of the drain pipe. To do this, a water collection tank 120 is installed and a drain pipe 130 is connected to the lower part of the water collection tank.

본 발명의 또 다른 하나의 양태에 있어서, 비대칭2아치터널 시공방법으로서, 중앙터널(25) 내부에 설치되는 중앙벽체를 상기 중앙터널(25) 중심부에서 편측으로 이격 설치하여 중앙벽체와 상기 중앙터널(25) 측벽간 넓은 구간에 시공기술자의 이동 및 통행, 공사용 자재운반, 공사용 차량의 통행이 가능하도록 설치되는 중앙벽체의 상부거더(30) 내부에 배수 전용 케이스(150)를 갖는 것을 특징으로 한다.In another aspect of the present invention, as an asymmetric two-arch tunnel construction method, the central wall installed inside the central tunnel 25 is installed spaced apart from the center of the central tunnel 25 on one side to form a structure between the central wall and the central tunnel. (25) It is characterized by having a drainage-only case (150) inside the upper girder (30) of the central wall, which is installed to allow movement and passage of construction engineers, transportation of construction materials, and passage of construction vehicles in the wide section between side walls. .

본 발명은 2아치터널에 있어서, 상부 거더(30) 내부에 배수유입부(250)(도 6a 참조)를 가진 삼각형 단면의 배수 전용 케이스(150)를 설치하고 배수 전용 케이스(150)에 연결되는 유입수 배출 배수관(110, 1300, 160)을 설치한 후에 중앙벽체 시공을 완료한 다음 본선터널(10, 20)을 굴착·시공 후에 본선터널(10, 20)에 설치되는 드레인보드(200)와 방수시트(210)를 배수유입부(250)(도 6a 참조)로 통과하여 배수 전용 케이스(150) 내부의 바닥까지 삽입·설치하여 중앙터널(25)과 좌·우측 본선터널(10, 20)의 시공접합부(50)에 모이는 지하수를 효과적으로 배수하여 시공이음부(100)에 지하수가 유출되지 않도록 차단함으로서 시공이음부(100)의 누수를 보다 완벽하게 제어할 수 있어 하자발생 원인이 되는 2아치터널 방수방법의 적극적인 개선이 가능하게 하는 효과가 있다.In the present invention, in a two-arch tunnel, a drainage-only case 150 of a triangular cross-section with a drainage inlet 250 (see Figure 6a) is installed inside the upper girder 30 and connected to the drainage-only case 150. After installing the inflow water discharge drain pipes (110, 1300, 160), complete the construction of the central wall, and then excavate and construct the main tunnel (10, 20), then drain board (200) and waterproofing installed in the main tunnel (10, 20). The sheet 210 passes through the drainage inlet 250 (see Figure 6a) and is inserted and installed to the bottom inside the drainage case 150, thereby sealing the central tunnel 25 and the left and right main tunnels 10 and 20. By effectively draining the groundwater that collects in the construction joint (50) and preventing groundwater from leaking into the construction joint (100), water leakage in the construction joint (100) can be more completely controlled, which causes defects in the two-arch tunnel. It has the effect of enabling active improvement of waterproofing methods.

본 발명의 범위는 상기 상세한 설명보다는 후술하는 특허청구범위에 의하여 나타내어지며 특허청구범위의 의미 및 범위 그리고 그 균등 개념으로부터 도출되는 모든 변경 또는 변형된 형태가 본 발명의 범위에 포함되는 것으로 해석되어야 한다.The scope of the present invention is indicated by the claims described below rather than the detailed description above, and all changes or modified forms derived from the meaning and scope of the claims and their equivalent concepts should be construed as being included in the scope of the present invention. .

도 1은 종래의 2아치터널의 시공 단면도를 도시한 도면이다.
도 2는 도 1의 "A" 부분 상세도이다.
도 3은 도 1의 "A" 부분 상세도로서, 도 2의 시공 단면을 개략적으로 도시한 도면이다.
도 4는 본 발명의 2아치터널의 시공 단면도이다.
도 5는 도 4의 "B" 부분 상세도이다.
도 6은 도 5의 "C" 부분 상세도이다.
도 7은 도 4의 "B" 부분 상세도로서, 도 5의 시공 단면을 개략적으로 도시한 도면이다.
도 8은 도 6의 "D" 부분 중앙벽체 상부거더의 내부에 설치되는 배수 전용 케이스에 설치되는 배수관의 분해 사시도이다.
도 9는 도 4의 "B"부분 중앙벽체 상부거더의 내부에 설치되는 배수 전용 케이스를 포함한 시공 순서도이다.
도 10은 본 발명에 의한 대칭형 2아치터널의 시공 순서도이다.
도 11은 본 발명에 의한 비대칭형 2아치터널의 시공 순서도이다.
Figure 1 is a construction cross-sectional view of a conventional two-arch tunnel.
FIG. 2 is a detailed view of portion “A” of FIG. 1.
FIG. 3 is a detailed view of portion “A” of FIG. 1 and schematically shows the construction cross-section of FIG. 2.
Figure 4 is a construction cross-sectional view of the two-arch tunnel of the present invention.
FIG. 5 is a detailed view of portion “B” of FIG. 4.
Figure 6 is a detailed view of portion "C" of Figure 5.
FIG. 7 is a detailed view of portion “B” of FIG. 4 and schematically shows the construction cross-section of FIG. 5.
Figure 8 is an exploded perspective view of a drain pipe installed in a drainage-only case installed inside the upper girder of the central wall in portion "D" of Figure 6.
FIG. 9 is a construction flow chart including a drainage-only case installed inside the upper girder of the central wall in portion “B” of FIG. 4.
Figure 10 is a construction flow chart of a symmetrical two-arch tunnel according to the present invention.
Figure 11 is a construction flow chart of an asymmetrical two-arch tunnel according to the present invention.

본 발명에 대하여 첨부한 도면을 참조하여 본 기술분야에서 통상의 지식을 가진 자가 용이하게 실시할 수 있도록 본 발명의 실시 예를 상세히 설명한다.With reference to the accompanying drawings, embodiments of the present invention will be described in detail so that those skilled in the art can easily implement it.

그러나, 본 발명은 여러 가지 상이한 형태로 구현될 수 있으며, 여기에서 설명하는 실시 예에 한정되지 않으며, 도면에서 본 발명을 명확하게 설명하기 위해서 설명과 관계없는 부분은 생략하였으며 명세서 전체를 통하여 유사한 부분에 대해서는 유사한 도면 부호를 붙였다.However, the present invention can be implemented in various different forms, and is not limited to the embodiments described herein. In order to clearly explain the present invention in the drawings, parts not related to the description have been omitted, and similar parts throughout the specification have been omitted. Similar reference numerals are given for .

도 4와 같이, 2아치터널의 시공에 있어서, 중앙터널(25)을 먼저 시공하게 되는데 중앙터널(25)은 발파에 의한 NATM공법으로 굴착·시공되는 것이 통상적이다. 이러한 NATM공법은 발파에 의하여 일정한 아치형태의 터널굴착면이 형성되면 1차 숏크리트(94)와 지보재(92)를 터널굴착면에 타설·시공하여 원지반의 암반거동을 조기에 정착시키고 록볼트(5)를 터널굴착면 배면의 원지반에 방사형으로 삽입·설치하여 터널굴착면 주변지반의 이완방지와 암반간의 봉합효과 등을 확보할 수 있도록 하게 된다. 이후에 2차 지보재(92)를 록볼트(5)와 숏크리트(94)가 형성된 터널 굴착면에 설치하여 중앙터널(25)을 완성시키게 된다.As shown in Figure 4, in the construction of a two-arch tunnel, the central tunnel 25 is constructed first, and the central tunnel 25 is usually excavated and constructed using the NATM method by blasting. In this NATM method, when a tunnel excavation surface of a certain arch shape is formed by blasting, primary shotcrete (94) and support material (92) are poured and constructed on the tunnel excavation surface to establish the rock behavior of the original ground at an early stage and to install rock bolts (5). ) is radially inserted and installed into the original ground on the back of the tunnel excavation surface to prevent loosening of the ground around the tunnel excavation surface and secure the sealing effect between rock masses. Afterwards, the secondary support material 92 is installed on the tunnel excavation surface where the rock bolt 5 and the shotcrete 94 are formed to complete the central tunnel 25.

여기서, 중앙터널(25)이 완성되면 도 5와 같이 숏크리트(94) 면을 정리한 다음 중앙벽체 상부 거더(30)의 상단부와 중앙터널(25) 천단부 사이에 방수시트(91)를 시공하게 되는데 방수시트(91)를 설치한 목적의 첫 번째 이유는 중앙벽체 거더(30)의 헌치 상부 천단부의 방수를 위해 설치하는 것이며, 두 번째 이유는 중앙벽체 상부 거더(30)의 천단부에서 발생되는 지하수를 좌·우측 본선터널(10, 20)에 설치되는 드레인 보드(200)와 방수시트(210)로 유도하는 용도로 설치한 것이다.Here, when the central tunnel (25) is completed, the shotcrete (94) surface is cleaned as shown in FIG. 5, and then a waterproof sheet (91) is constructed between the upper part of the central wall upper girder (30) and the ceiling of the central tunnel (25). The first reason for installing the waterproof sheet (91) is to waterproof the upper ceiling part of the haunch of the central wall girder (30), and the second reason is to prevent water damage occurring at the upper ceiling part of the central wall girder (30). It is installed to guide groundwater to the drain board (200) and waterproof sheet (210) installed in the left and right main tunnels (10, 20).

상기 방수시트(91)는 중앙터널(25)과 본선터널(10, 20)의 시공접합부(50)까지 연장되도록 배치한 다음 중앙벽체 기초(45) 및 중앙벽체(40)를 시공하고 상부 거더(30)의 내부에 배수관(110,140,160)과 배수 전용 케이스(150)를 배치한 후에 상부 거더(30)를 콘크리트 타설하여 시공이 완료되면 중앙벽체(25) 상부에 본선터널(10, 20)의 라이닝콘크리트(11)의 연결부인 하부구체(30a) 및 상부 천단부인 상부구체(30b)가 완성되어 중앙벽체 전체가 시공 완료되게 된다.The waterproof sheet 91 is arranged to extend to the construction joint 50 of the central tunnel 25 and the main tunnel 10, 20, and then the central wall foundation 45 and the central wall 40 are constructed, and the upper girder ( After placing the drain pipes (110, 140, 160) and the drainage case (150) inside the 30), the upper girder (30) is poured with concrete. When construction is completed, the lining concrete of the main tunnel (10, 20) is placed on the upper part of the central wall (25). The lower sphere (30a), which is the connection part of (11), and the upper sphere (30b), which is the upper ceiling part, are completed, and construction of the entire central wall is completed.

중앙터널(25) 내부에 시공이 완료된 중양벽체의 좌·우측 본선터널(10, 20)도 발파에 의한 NATM공법으로 시공되는 것이 통상적이다. 이러한 NATM공법은 발파에 의하여 일정한 아치형태의 터널 굴착면이 형성되면 1차 숏크리트(94)와 지보재(93)를 터널 굴착면에 타설·설치하여 원지반 암반의 거동을 조기에 정착시키고 록볼트(6)를 터널 굴착면 배면의 원지반에 방사형으로 삽입·설치하여 터널굴착면 주변지반의 이완방지 및 암반간의 봉합효과 등을 확보할 수 있도록 하게 된다. 이후에 2차 숏크리트(94)가 형성된 터널굴착면에 설치하여 본선터널 굴착면을 완성시키게 된다.The left and right main tunnels (10, 20) of the central wall that have been completed inside the central tunnel (25) are also typically constructed using the NATM method by blasting. In this NATM method, when a tunnel excavation surface of a certain arch shape is formed by blasting, primary shotcrete (94) and support material (93) are cast and installed on the tunnel excavation surface to establish the behavior of the original ground rock at an early stage and to use rock bolts (6). ) is radially inserted and installed into the original ground on the back of the tunnel excavation surface to prevent loosening of the ground around the tunnel excavation surface and secure the sealing effect between rock masses. Afterwards, the secondary shotcrete (94) is installed on the formed tunnel excavation surface to complete the main tunnel excavation surface.

다음으로는 본선터널(10, 20)에 방수시트(210)의 시공 전에 중앙벽체 상부 거더(30) 내부에 미리 설치되는 배수 차단 단부(170, 180)를 포함하는 배수유입부(250)(도 6a 참조)를 갖는 배수 전용 케이스 재료의 탄력성을 이용하여 도 6b와 같이 아랫방향으로 일정폭으로 열어서 중앙터널(25)과 본선터널(10, 20)의 시공접합부(50)에서 본선터널 쪽 상부 약 30~50cm 높이에서 배수 전용 케이스(150) 안쪽 바닥까지 드레인보드(200)를 삽입하고 본선터널(10, 20) 방수시트(210)를 드레인보드(200) 아래에 나란히 배수 전용 케이스(150) 안쪽 바닥까지 삽입한 다음 드레인보드(200)와 방수시트(210)를 삽입하기 위해서 열었던 배수유입부(250)(도 6a 참조)를 원위치하여 본선터널(10, 20)의 방수시트(210) 시공을 완료한 후에 좌·우측 본선터널(10, 20) 라이닝콘크리트(11)를 타설·시공하여 도 4와 같이 2아치터널을 완성하게 된다.Next, the drainage inlet 250 (Figure Using the elasticity of the drainage-only case material (see 6a), it is opened downward to a certain width as shown in FIG. 6b, and the construction joint 50 of the central tunnel 25 and the main line tunnels 10 and 20 is approximately upper part of the main line tunnel side. Insert the drain board (200) from a height of 30 to 50 cm to the bottom inside the drainage case (150), and place the main tunnel (10, 20) waterproof sheets (210) side by side under the drain board (200) inside the drainage case (150). After inserting the drain board 200 and the waterproof sheet 210, insert it to the bottom and return the drain inlet 250 (see Figure 6a), which was opened to insert the drain board 200 and the waterproof sheet 210, to construct the waterproof sheet 210 of the main tunnel 10, 20. After completion, the lining concrete (11) of the left and right main tunnels (10, 20) is poured and constructed to complete the two-arch tunnel as shown in Figure 4.

여기서, 본선터널(10, 20)에 지보재(93) 설치 시공시 중앙터널(25)의 지보재(92)에 본선터널(10, 20)의 지보재(93)를 연결하고 2차 숏크리트를 타설하여 최종 2아치터널의 굴착단면을 완성시키게 된다. 이때, 중앙터널(25) 천단부에 기시공된 방수시트(91)가 본선터널(10, 20)의 발파·시공과 지보재(92, 93) 절단·연결 등의 작업으로 인하여 구조적인 문제로 손상이 발생된다. 이와 같이 손상이 발생되어 누수가 발생되더라도 누수된 지하수가 아래로 흘러 방수 전용 케이스(150)로 유도되어 배수관(110, 140, 160)을 통하여 밖으로 배출된다.Here, when installing the support material 93 in the main tunnel (10, 20), the support material 93 of the main tunnel (10, 20) is connected to the support material 92 of the central tunnel 25, and secondary shotcrete is poured to achieve the final result. 2 The excavated section of the arch tunnel will be completed. At this time, the waterproofing sheet 91 previously installed at the top of the central tunnel 25 was damaged due to structural problems due to work such as blasting and construction of the main tunnel 10 and 20 and cutting and connecting support materials 92 and 93. This occurs. Even if damage occurs in this way and a water leak occurs, the leaked groundwater flows downward and is guided to the waterproof case 150 and discharged outside through the drain pipes 110, 140, and 160.

중앙벽체와 상부 거더(30) 등 중앙벽체 전체 구조물은 지중 또는 수중 구조물로 철근피복두께를 60mm 이상으로 적용되어 시공연결부(50)에서 상기와 같은 작업으로 방수시트(91)의 손상과 관계없이 지하수는 상기에서 서술된 본선터널(10, 20)에서 시공되는 드레인보드(200)와 방수시트(210)로 터널 상부에서 내려오는 지하수가 배수유입부(250)(도 6 참조)를 통하여 배수 전용 케이스(150)로 유도된다.The entire structure of the central wall, including the central wall and the upper girder (30), is an underground or underwater structure, and the reinforcing bar covering thickness is applied at 60 mm or more, so that ground water is discharged regardless of damage to the waterproof sheet (91) through the above operation at the construction connection portion (50). This is a case dedicated to drainage of groundwater coming down from the upper part of the tunnel with the drain board 200 and waterproof sheet 210 constructed in the main tunnels 10 and 20 described above through the drainage inlet 250 (see FIG. 6). It is derived as (150).

특히, 중앙벽체 상부 거더(30)와 본선터널(10, 20) 라이닝콘크리트(11)와 방수시트(210) 사이로 타고 흐르는 지하수가 있어도 배수 전용 케이스(150)의 배수유입부(250)(도 6a 참조)에 양쪽으로 90도로 꺾어진 지하수 차단 단부(170, 180)가 중앙벽체 상부 거더(30)의 하부구체(30a) 콘크리트 및 본선터널(10, 20)의 라이닝콘크리트(11) 내부에 삽입되어 있어 지하수 차단 단부(170, 180)로 인하여 배수유입부(250)(도 6b 참조)로 통과하여 배수 전용 케이스(150) 내부로 지하수가 유도된다.In particular, even if there is groundwater flowing between the central wall upper girder 30, the main tunnel 10, 20 lining concrete 11 and the waterproof sheet 210, the drainage inlet 250 of the drainage case 150 (Figure 6a) (Reference), the groundwater blocking ends (170, 180) bent at 90 degrees on both sides are inserted into the concrete of the lower sphere (30a) of the upper girder (30) of the central wall and the lining concrete (11) of the main tunnel (10, 20). Due to the groundwater blocking ends (170, 180), groundwater is induced into the drainage-only case (150) by passing through the drainage inlet (250) (see FIG. 6B).

배수 전용 케이스(150)와 배수관(110, 140, 160)의 설치는 중앙벽체 상부 거더(30)의 철근 배근 시 배수 전용 케이스(150)와 배수관(110, 140, 160)의 설치를 고려하여 시공되고 배수 전용 케이스(150)의 내부에 일정한 간격으로 설치하기 위한 배수 전용 케이스(150) 바닥을 타공(315)한 곳에 도 8과 같이 배수 전용 케이스(150) 내부에서 고무패킹(310) 끼운 배수관 연결본체(300)를 배수 전용 케이스(150) 바깥방향으로 삽입하고 배수 전용 케이스(150)의 외부에서 연결본체(300)에 고무패킹(311)을 끼우고 연결본체(300)를 고정시키는 암나사 홀더(320)로 배수 전용 케이스(150)에 완전하게 밀착시켜 도 6과 같이 고정한 다음 도 5의 배수관 이음관(330)으로 연결본체와 배수관(160)을 연결한다.The installation of the drainage case (150) and the drain pipes (110, 140, 160) is performed by considering the installation of the drainage case (150) and the drain pipes (110, 140, 160) when placing the reinforcement of the central wall upper girder (30). A drain pipe with rubber packing 310 is connected inside the drainage case 150 as shown in FIG. Insert the main body 300 toward the outside of the drainage-only case 150, insert the rubber packing 311 into the connection main body 300 from the outside of the drainage-only case 150, and secure the connection main body 300 with a female screw holder ( 320), it is completely adhered to the drainage case 150 and fixed as shown in FIG. 6, and then the connection body and the drain pipe 160 are connected with the drain pipe fitting 330 of FIG. 5.

상기 배수 전용 케이스(150)에 배수관을 설치하기 위하여, 배수 전용 케이스(150) 바닥을 타공(315)한 곳에 배수 전용 케이스(150) 내부에서 고무패킹(310)을 끼운 배수관 연결본체(300)를 베수 전용 케이스(150) 바깥방향으로 삽입하고 배수 전용 케이스(150)의 외부에서 연결본체(300)에 고무패킹(311)을 끼우고 연결본체(300)를 고정시키는 암나사 홀더(320)로 배수 전용 케이스(150)에 완전하게 밀착시켜 배수관 이음관(330)으로 연결본체와 배수관(160)을 연결하고 상기 중앙벽체 상부 거더(30) 양쪽에 설치된 배수 전용 케이스(150)에 연결된 배수관(160)을 Y형 배수관 연결관(140)으로 연결하여 중앙벽체 상부 거더(30)의 하부에 일정 길이로 배수관(110)을 설치하고 배수관의 하부에는 배수관 유지관리를 용이하게 하기 위하여 집수통(120)을 설치하고 집수통 하부에 배수관(130)을 연결한다.In order to install a drain pipe in the drain-only case 150, a drain pipe connection body 300 with a rubber packing 310 inserted inside the drain-only case 150 is placed in a hole 315 in the bottom of the drain-only case 150. Insert the drain-only case (150) in the outer direction, insert the rubber packing (311) into the connection body (300) from the outside of the drainage-only case (150), and use the female screw holder (320) to secure the connection body (300) for drainage use only. It is completely adhered to the case 150, connects the main body and the drain pipe 160 with a drain pipe joint 330, and connects the drain pipe 160 to the drainage case 150 installed on both sides of the upper girder 30 of the central wall. A drain pipe 110 is installed at a certain length in the lower part of the central wall upper girder 30 by connecting it with a Y-type drain pipe connector 140, and a water collection tank 120 is installed at the lower part of the drain pipe to facilitate drain pipe maintenance. And connect the drain pipe 130 to the lower part of the water collection tank.

상기 중앙벽체 상부 거더(30) 양쪽에 설치된 배수 전용 케이스(150)에 연결된 배수관(160)을 Y형 연결관(140)으로 연결하여 중앙벽체 상부 거더(30)의 하부에 일정 길이로 배수관(110)을 설치하고 배수관의 하부에는 배수관 유지관리를 용이하게 하기 위하여 집수통(120)을 설치하고 집수통 하부에 배수관(130)을 연결하여 배수 집수정(41)으로 도 4와 같이 2아치터널 상부의 지하수를 중앙벽체의 누수 없이 완벽하게 외부로 배출시키는 중앙벽체 상부 거더 내부에 배수 전용 케이스(150)를 갖는 2아치터널 및 그 시공방법이 제공된다.The drain pipe 160 connected to the drainage case 150 installed on both sides of the central wall upper girder 30 is connected with a Y-shaped connector 140 to form a drain pipe 110 of a certain length at the lower part of the central wall upper girder 30. ) is installed at the bottom of the drain pipe to facilitate maintenance of the drain pipe, and a water collection tank (120) is installed, and a drain pipe (130) is connected to the lower part of the water collection tank to form a drainage water collection well (41) at the upper part of the two-arch tunnel as shown in Figure 4. A two-arch tunnel with a drainage-only case 150 inside the upper girder of the central wall that completely discharges groundwater to the outside without leakage of the central wall and its construction method are provided.

도 9의 (a)는 중앙터널(25) 시공 후 중앙벽체의 시공단계; (b)는 상부 거더(30)에 배수 전용 케이스(150)와 배수관(110)을 설치한 후 상부 거더 하부구체(30a)를 콘크리트 타설·시공단계; (c)는 중앙터널 천단부에 방수시트(91) 설치 및 상부 거더 상부구체(30b)에 콘크리트 타설·시공단계; (d)는 본선터널(10, 20) 굴착·시공 후 중앙터널 지보(92)와 본선터널 지보(93)를 연결 시공단계; (e)는 본선터널의 드레인보드(200), 방수시트(210) 시공단계; (f)는 좌·우측 본선터널(10, 20)의 라이닝콘크리트(11) 타설·시공단계로 중앙벽체 상부 거더(30) 내부에 배수 전용 케이스(150)를 갖는 2아치터널 및 그 시공순서도이다.Figure 9 (a) shows the construction stage of the central wall after construction of the central tunnel 25; (b) is a concrete pouring/construction step of installing the drainage case 150 and the drain pipe 110 on the upper girder 30 and then installing the upper girder lower body 30a; (c) is a step of installing a waterproof sheet (91) at the ceiling of the central tunnel and pouring/constructing concrete on the upper girder body (30b); (d) is the construction stage of connecting the central tunnel support (92) and the main tunnel support (93) after excavating and constructing the main tunnel (10, 20); (e) is the construction stage of the drain board (200) and waterproof sheet (210) of the main tunnel; (f) is a two-arch tunnel with a drainage case 150 inside the upper girder 30 of the central wall in the pouring and construction stage of the lining concrete 11 of the left and right main tunnels 10 and 20, and its construction flow chart. .

도 10의 (a)는 중앙터널(25) 굴착·시공단계; (b)는 중앙터널의 중심부에 중앙벽체기초(45)와 중앙벽체(40) 시공 후에 중앙벽체 상부 거더(30) 내부에 배수 전용 케이스와 배수관을 연결한 후 상부거더 하부구체(30a)를 시공단계; (c)는 상부거더 상부구체(30b)를 시공단계; (d)는 우측 본선터널(20) 굴착·시공단계; (e)는 좌측 본선터널(10) 굴착·시공단계; (f)는 라이닝콘크리트(11) 시공단계로 시공되는 중앙벽체 상부 거더(30) 내부에 배수 전용 케이스(150)를 갖는 2아치터널 및 그 시공순서도이다.Figure 10 (a) shows the central tunnel 25 excavation and construction stage; In (b), after constructing the central wall foundation (45) and central wall (40) in the center of the central tunnel, the drainage case and drain pipe are connected inside the central wall upper girder (30), and then the upper girder lower sphere (30a) is constructed. step; (c) is the construction step of the upper girder upper body (30b); (d) is the excavation and construction stage of the right main tunnel (20); (e) is the excavation and construction stage of the left main tunnel (10); (f) is a two-arch tunnel with a drainage-only case 150 inside the central wall upper girder 30 constructed in the lining concrete 11 construction stage and its construction flow chart.

도 11은 (a)는 중앙터널(25) 굴착·시공단계; (b)는 중앙터널(25) 내에 중앙벽체를 중앙터널(25) 중심부로부터 일정거리 편측으로 이격하여 중앙벽체 기초(45)와 중앙벽체(40) 시공 후에 중앙벽체 상부 거더(30) 내부에 배수 전용 케이스(150)와 배수관(110, 140, 160)을 연결한 후 상부거더 하부구체(30a)를 시공단계; (c)는 상부거더 상부구체(30b)를 시공단계; (d)는 우측 본선터널(20) 굴착·시공단계; (e)는 좌측 본선터널(10) 굴착·시공단계; (f)는 라이닝콘크리트(11) 시공단계로 시공되어 중앙터널(25) 내에 중앙벽체를 중앙터널(25) 중심부로부터 일정거리 편측으로 이격하여 설치함으로서 중앙벽체와 중앙터널(25) 측벽부간 공간이 넓은 구간에 시공기술자의 이동 및 통행, 공사용 자재운반, 공사용 차량의 통행이 편리하도록 하여 작업공간을 확대하여 안전사고 방지 등의 효과를 갖는 중앙벽체 상부 거더(30) 내부에 배수 전용 케이스(150)를 갖는 비대칭 2아치터널 및 그 시공순서도이다.Figure 11 shows (a) the excavation and construction stage of the central tunnel 25; In (b), the central wall within the central tunnel 25 is spaced on one side at a certain distance from the center of the central tunnel 25, and after construction of the central wall foundation 45 and the central wall 40, drainage is placed inside the central wall upper girder 30. After connecting the dedicated case 150 and the drain pipes 110, 140, and 160, the upper girder lower sphere (30a) is constructed; (c) is the construction step of the upper girder upper body (30b); (d) is the excavation and construction stage of the right main tunnel (20); (e) is the excavation and construction stage of the left main tunnel (10); (f) is constructed at the lining concrete (11) construction stage, and the central wall is installed within the central tunnel (25) at a certain distance on one side from the center of the central tunnel (25), so that the space between the central wall and the side walls of the central tunnel (25) is maintained. A drainage case (150) is installed inside the upper girder (30) of the central wall, which has the effect of preventing safety accidents by expanding the work space by making it convenient for the movement and passage of construction engineers, transportation of construction materials, and passage of construction vehicles in a wide section. This is an asymmetric two-arch tunnel with and its construction flow chart.

5; 중앙터널 록볼트 6; 본선터널 록볼트 10: 본선좌측터널
11: 라이닝콘크리트 20: 본선우측터널 25; 중앙터널
30: 중앙벽체 상부거더 30a; 상부거더 하부구체 30b; 상부거더 상부구체
40: 중앙벽체 41; 집수정 45; 중앙벽체 기초
50: 접합부 60, 140: Y형 배수 연결관 61; 유출 배수관
70; 본선터널 바닥 콘크리트 80; 상부거더 횡방향 배수관
90; 종방향 배수 유공관 91; 중앙벽체 상부 방수시트
92; 중앙터널 지보재 93; 본선터널 지보재 94; 숏크리트
100: 시공 이음부 110,130: 배수관 120; 집수통
140; Y형 연결관 150; 배수 전용 케이스 160; 연결관
170, 180; 차단단부 200; 드레인보드 210: 방수시트
300: 배수 전용케이스와 배수관 연결 본체 310, 311: 고무패킹
315; 케이스 타공 320: 연결본체 고정 암나사 홀더
330: 배수관 이음관
5; Central tunnel rock bolt 6; Main line tunnel rock bolt 10: Main line left tunnel
11: Lining concrete 20: Main line right tunnel 25; central tunnel
30: Central wall upper girder 30a; Upper girder lower sphere 30b; Upper girder upper body
40: central wall 41; sump 45; Central wall foundation
50: junction 60, 140: Y-type drain connector 61; runoff drain pipe
70; Main tunnel floor concrete 80; Upper girder lateral drain pipe
90; longitudinal drainage perforated pipe 91; Waterproofing sheet on top of central wall
92; Central tunnel support material 93; Main tunnel Jibojae 94; shotcrete
100: construction joint 110, 130: drain pipe 120; catch basin
140; Y-type connector 150; Drainage only case 160; connector
170, 180; blocking end 200; Drain board 210: Waterproof sheet
300: Drain case and drain pipe connection main body 310, 311: Rubber packing
315; Case perforation 320: Connection body fixing female screw holder
330: Drain pipe fitting

Claims (4)

중앙터널(25)을 형성시킨 후, 중앙터널(25)의 내부에 중앙벽체를 형성시키고 중앙벽체의 좌·우측에 본선터널(10, 20)을 형성시키는 중앙벽체의 상부에 상부 거더(30)를 형성시키는 2아치터널 시공방법에 있어서,
상기 중앙터널(25)의 천단부에 방수시트(91)를 중앙터널(25)과 좌·우측 본선터널(10, 20)의 굴착면과의 접합부(50)까지 방수시트(91)를 연장 설치하는 단계와,
상기 상부 거더(30)의 좌·우측의 내부에 배수 전용 케이스(150)와 배수관(110, 160)과 Y형 배수관 연결관(140)을 삽입·설치하고 상기 상부 거더부(30)에 콘크리트로 타설하여 중앙벽체의 상부거더(30) 상면이 중앙터널(25) 천단부와 접하여 형성되도록 하는 단계와,
상기 상부 거더(30) 내부에 설치된 배수 전용 케이스(150)의 배수유입부(250)(도 6a 참조)를 열어 본선터널용 드레인보드(200)와 방수시트(210)를 케이스(150) 내부 바닥까지 설치한 후에 본선터널 라이닝콘크리트(11)를 형성시키는 단계를 포함하고,
상기 중앙벽체의 상부 거더(30) 내부에 설치되는 배수 전용 케이스(150)는 배수 전용 케이스(150)의 배수유입부(250)(도 6a 참조)에서 양쪽 바깥쪽으로 90°로 꺾어진 지하수 차단 단부(170, 180)와 배수유입부(250)(도 6a 참조)를 갖는 삼각형 단면을 갖는 것을 특징으로 하는 중앙벽체 상부 거더 내부에 배수 전용 케이스(150)를 갖는 2아치터널 시공방법.
After forming the central tunnel 25, a central wall is formed inside the central tunnel 25, and an upper girder 30 is formed on the upper part of the central wall to form main tunnels 10 and 20 on the left and right sides of the central wall. In the two-arch tunnel construction method to form,
The waterproof sheet 91 is installed at the upper end of the central tunnel 25 by extending it to the junction 50 between the central tunnel 25 and the excavated surfaces of the left and right main tunnels 10 and 20. The steps and
Insert and install the drainage case 150, drain pipes 110, 160, and Y-type drain pipe connector 140 inside the left and right sides of the upper girder 30, and fill the upper girder portion 30 with concrete. Casting the upper surface of the upper girder (30) of the central wall to form contact with the ceiling of the central tunnel (25);
Open the drainage inlet 250 (see FIG. 6a) of the drainage case 150 installed inside the upper girder 30 and place the drain board 200 and waterproof sheet 210 for the main line tunnel on the inner floor of the case 150. It includes the step of forming the main tunnel lining concrete (11) after installation,
The drainage-only case 150 installed inside the upper girder 30 of the central wall has groundwater blocking ends bent at 90° outward on both sides from the drainage inlet 250 (see Figure 6a) of the drainage-only case 150 ( A two-arch tunnel construction method having a drainage-only case 150 inside the upper girder of the central wall, characterized by having a triangular cross-section with 170, 180) and a drainage inlet 250 (see FIG. 6a).
삭제delete 청구항 1에 있어서,
상기 배수 전용 케이스(150)에 배수관을 설치하기 위하여 배수 전용 케이스(150) 바닥을 타공(315)한 곳에 배수 전용 케이스(150) 내부에서 고무패킹(310)을 끼운 배수관 연결본체(300)를 배수 전용 케이스(150) 바깥방향으로 삽입하고 배수 전용 케이스(150)의 외부에서 연결본체(300)에 고무패킹(311)을 끼우고 연결본체(300)를 고정시키는 암나사 홀더(320)로 배수 전용 케이스(150)에 완전하게 밀착시켜 배수관 이음관(330)으로 연결본체(300)와 배수관(160)을 연결하고 상기 중앙벽체 상부 거더(30) 양쪽에 설치된 배수 전용 케이스(150)에 연결된 배수관(160)을 Y형 배수관 연결관(140)으로 연결하여 중앙벽체 상부 거더(30)의 하부에 일정 길이로 배수관(110)을 설치하고 배수관의 하부에는 배수관 유지관리를 용이하게 하기 위하여 집수통(120)을 설치하고 집수통 하부에 배수관(130)을 연결하여 집수정(41)까지 연결하는 것을 특징으로 하는 중앙벽체 상부 거더(30) 내부에 배수 전용 케이스(150)를 갖는 2아치터널 시공방법.
In claim 1,
In order to install a drain pipe in the drain-only case 150, a drain pipe connection body 300 with a rubber packing 310 inserted inside the drain-only case 150 is drilled in a hole 315 in the bottom of the drain-only case 150. Insert the dedicated case 150 outward, insert the rubber packing 311 into the connection body 300 from the outside of the drainage case 150, and use the female screw holder 320 to secure the connection body 300 to the drainage only case. The connection body 300 and the drain pipe 160 are completely adhered to (150) and connected to the drain pipe joint 330, and the drain pipe 160 is connected to the drainage case 150 installed on both sides of the central wall upper girder 30. ) is connected to the Y-type drain pipe connector 140 to install a drain pipe 110 of a certain length in the lower part of the central wall upper girder 30, and a sump 120 is installed at the lower part of the drain pipe to facilitate drain pipe maintenance. A two-arch tunnel construction method having a drainage-only case (150) inside the central wall upper girder (30), characterized by installing and connecting a drain pipe (130) to the lower part of the water collection tank and connecting it to the water collection well (41).
청구항 1에 따른 2아치터널 시공방법에 있어서,
상기 중앙터널(25) 내부에 설치되는 중앙벽체를 상기 중앙터널(25) 중심부에서 편측으로 이격 설치하여 중앙벽체와 상기 중앙터널(25) 측벽간 넓은 구간에 시공기술자의 이동 및 통행, 공사용 자재운반, 공사용 차량의 통행이 가능하도록 설치되는 중앙벽체의 상부 거더 내부에 배수 전용 케이스(150)를 갖는 것을 특징으로 하는 2아치터널 시공방법.
In the two-arch tunnel construction method according to claim 1,
The central wall installed inside the central tunnel 25 is installed spaced apart from the center of the central tunnel 25 to one side to allow movement and passage of construction engineers and transportation of construction materials in the wide section between the central wall and the side walls of the central tunnel 25. , A two-arch tunnel construction method characterized by having a drainage-only case 150 inside the upper girder of the central wall installed to allow passage of construction vehicles.
KR1020210134853A 2021-10-12 2021-10-12 A two-arch tunnel having a dedicate drainage case inside the upper girder of the central wall and its construction method KR102593946B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020210134853A KR102593946B1 (en) 2021-10-12 2021-10-12 A two-arch tunnel having a dedicate drainage case inside the upper girder of the central wall and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020210134853A KR102593946B1 (en) 2021-10-12 2021-10-12 A two-arch tunnel having a dedicate drainage case inside the upper girder of the central wall and its construction method

Publications (2)

Publication Number Publication Date
KR20230051904A KR20230051904A (en) 2023-04-19
KR102593946B1 true KR102593946B1 (en) 2023-10-24

Family

ID=86142436

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020210134853A KR102593946B1 (en) 2021-10-12 2021-10-12 A two-arch tunnel having a dedicate drainage case inside the upper girder of the central wall and its construction method

Country Status (1)

Country Link
KR (1) KR102593946B1 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200337975Y1 (en) * 2003-08-29 2004-01-13 금강종합건설 주식회사 Drain pipe structure of two-arch tunnel
JP2006077560A (en) 2004-09-11 2006-03-23 Yutaka Komatsu Drain mechanism of tunnel

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060084203A (en) * 2005-01-19 2006-07-24 주식회사 하이콘엔지니어링 Method for constructing 2-arch tunnel using steel pile support
KR100877452B1 (en) * 2006-04-13 2009-01-07 서동현 Construction method of middle wall of three arch excavation tunnel

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200337975Y1 (en) * 2003-08-29 2004-01-13 금강종합건설 주식회사 Drain pipe structure of two-arch tunnel
JP2006077560A (en) 2004-09-11 2006-03-23 Yutaka Komatsu Drain mechanism of tunnel

Also Published As

Publication number Publication date
KR20230051904A (en) 2023-04-19

Similar Documents

Publication Publication Date Title
CN109611150B (en) Waterproof drainage structure and waterproof drainage method for tunnel
CN110094213B (en) Space combined supporting structure and supporting method for water-rich broken stratum tunnel
JP5982027B1 (en) Water leakage countermeasures for tunnels constructed by the Natom method
KR100936471B1 (en) A circular structure supported by the segment with A drainage structure and method constructing the shield tunnel
KR102126647B1 (en) Waterproof structure of non-excavation type tunnel improved shearing force and stiffness according to combination of h-beam support material and method of constructing thereof
KR101925597B1 (en) Underground continuous wall grouting waterproofing method
KR100877452B1 (en) Construction method of middle wall of three arch excavation tunnel
KR101973565B1 (en) Sheathing method for constructing both sheathing wall and cutoff collar by welding cutoff plate to phc pile with longitudinal plate
CN109736884B (en) Treatment structure for water gushing in underground river close to tunnel and construction method of treatment structure
KR20040097967A (en) Construction method of three arch excavation tunnel
CN106812131B (en) A kind of permanent sheet pile underground structure and its construction method
KR20060084203A (en) Method for constructing 2-arch tunnel using steel pile support
KR101066198B1 (en) Underground construction method of top-down with slurry walls
KR102593946B1 (en) A two-arch tunnel having a dedicate drainage case inside the upper girder of the central wall and its construction method
KR100701630B1 (en) Center Wall of Two Arch Tunnel
KR101807366B1 (en) A Foundation Method Of Continuous and Cut Off wall By Overlap Casing
KR20100042441A (en) Inducing waterproof structure of underground diaphragm wall
CN112012763A (en) Construction method of double-layer primary support multi-arch tunnel structure
CN111778983A (en) Method for constructing foundation pit above existing facility and supporting structure
JP2001012199A (en) Tunnel waterproof structure and its execution method
KR100399804B1 (en) Construction method for 2arch tunnel
CN113174995B (en) Construction method of TRD composite type enclosure comprehensive pipe gallery close to river channel
CN212318012U (en) Lining structure for tunnel and tunnel
CN109519219B (en) Method for water pumping and drainage of water bin arranged on water-rich section in tunnel
KR100786356B1 (en) Tunnel construction method

Legal Events

Date Code Title Description
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant