KR102349462B1 - Construction methods of wide precast concrete composite structure using support plate - Google Patents

Construction methods of wide precast concrete composite structure using support plate Download PDF

Info

Publication number
KR102349462B1
KR102349462B1 KR1020200046929A KR20200046929A KR102349462B1 KR 102349462 B1 KR102349462 B1 KR 102349462B1 KR 1020200046929 A KR1020200046929 A KR 1020200046929A KR 20200046929 A KR20200046929 A KR 20200046929A KR 102349462 B1 KR102349462 B1 KR 102349462B1
Authority
KR
South Korea
Prior art keywords
support plate
unit
slab
concrete
precast concrete
Prior art date
Application number
KR1020200046929A
Other languages
Korean (ko)
Other versions
KR20210128808A (en
Inventor
최상은
박태준
Original Assignee
최상은
박태준
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 최상은, 박태준 filed Critical 최상은
Priority to KR1020200046929A priority Critical patent/KR102349462B1/en
Publication of KR20210128808A publication Critical patent/KR20210128808A/en
Application granted granted Critical
Publication of KR102349462B1 publication Critical patent/KR102349462B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/01Reinforcing elements of metal, e.g. with non-structural coatings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/02Load-carrying floor structures formed substantially of prefabricated units
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/30Columns; Pillars; Struts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/07Reinforcing elements of material other than metal, e.g. of glass, of plastics, or not exclusively made of metal

Abstract

본 발명에 따른 와이드 복합구조 시공방법은 프리캐스트 콘크리트와 현장타설 콘크리트를 함께 사용하여 와이드 단면을 만든다. 이에 따라, 본 발명은 필요에 따라 와이드 단면 폭을 생산몰드 변경없이 증감시킬 수 있고, 층고를 줄일 수 있으며, 슬래브 지지길이 감소로 경제성을 확보할 수 있고, 프리캐스트 콘크리트 대비 현장타설 콘크리트의 비율을 높여 합성 및 공사비 절감효과를 높일 수 있으며, 기존에 프리캐스트 콘크리트에 매립되던 전기, 소방 설비 등을 현장에서 콘크리트를 타설하기 이전에 용이하게 설치할 수 있으며, 운반 및 양중이 용이하다는 장점을 갖는다.The wide composite structure construction method according to the present invention uses precast concrete and cast-in-place concrete together to make a wide cross-section. Accordingly, the present invention can increase or decrease the wide cross-sectional width as needed without changing the production mold, reduce the floor height, secure economic feasibility by reducing the slab support length, and increase the ratio of cast-in-place concrete to precast concrete It is possible to increase the effect of reducing synthesis and construction costs, and it is possible to easily install electricity and fire-fighting equipment that were previously buried in precast concrete before pouring concrete at the site, and has the advantage of being easy to transport and lift.

Figure R1020200046929
Figure R1020200046929

Description

지지판을 이용한 프리캐스트 콘크리트 와이드 복합구조의 시공방법{Construction methods of wide precast concrete composite structure using support plate} Construction methods of wide precast concrete composite structure using support plate

본 발명은 와이드 복합구조의 시공방법에 대한 것으로서, 더욱 구체적으로는 프리캐스트 콘크리트와 현장타설 콘크리트를 함께 사용하여 와이드 단면을 만들고, 이에 따라 생산몰드 변경없이 와이드 단면 폭을 필요에 따라 증감시킬 수 있으며, 층고를 줄일 수 있고, 슬래브 지지길이 감소로 경제성을 확보할 수 있으며, 프리캐스트 콘크리트 대비 현장타설 콘크리트의 비율을 높여 합성 효과 및 공사비 절감 효과를 높일 수 있고, 기존에 프리캐스트 콘크리트에 매립되던 전기, 소방 설비 등을 현장에서 콘크리트를 타설하기 이전에 용이하게 설치할 수 있으며, 운반 및 양중이 용이한 시공방법에 대한 것이다. The present invention relates to a construction method of a wide composite structure, and more specifically, a wide cross-section is made by using precast concrete and cast-in-place concrete together, and accordingly, the width of the wide cross-section can be increased or decreased as needed without changing the production mold. , the floor height can be reduced, economic feasibility can be secured by reducing the slab support length, the ratio of cast-in-place concrete to precast concrete can be increased to increase the synthesis effect and construction cost reduction effect, and electricity that was previously buried in precast concrete can be increased , fire-fighting equipment, etc. can be easily installed before concrete is poured on site, and it is about a construction method that is easy to transport and lift.

일반적으로, 건축물에서 보와 슬래브는 그 길이가 증가할수록 처짐량이 급격하게 증가하고 내력이 감소한다. 그리고, 기둥은 그 길이가 증가할수록 좌굴 하중을 크게 받게 된다. In general, as the length of beams and slabs in buildings increases, the amount of deflection increases rapidly and the bearing capacity decreases. And, as the length of the column increases, the buckling load is greatly increased.

이러한 문제점을 해결하기 위해, 보의 폭을 증가시키고(즉, 보를 와이드 구조로 만들고) 증가된 보의 폭만큼 슬래브의 길이를 줄임으로써 슬래브의 처짐량을 줄이고 내력을 증가시키는 방법이 제안된 바 있다. In order to solve this problem, a method of reducing the amount of deflection of the slab and increasing the bearing capacity by increasing the width of the beam (that is, making the beam a wide structure) and reducing the length of the slab by the increased width of the beam has been proposed.

그러나, 상기 제안된 방법은 와이드 구조의 프리캐스트 콘크리트보(PC 보)를 생산하기 어렵고 하중이 크므로 운반 및 양중이 어렵다는 문제점이 있다. 또한, 상기 제안된 방법은 프리캐스트 콘크리트 사용량이 증가하므로 생산 단가와 공사비가 올라가는 문제점 등이 있다.However, the proposed method has a problem in that it is difficult to produce a wide structure precast concrete beam (PC beam) and transport and lifting is difficult because the load is large. In addition, the proposed method has problems such as an increase in production cost and construction cost because the amount of precast concrete used increases.

프리캐스트 콘크리트 슬래브(PC 슬래브)는 공사 현장까지 운반하기 위해 그 폭이 최대 2.4m 이하이어야 하고 2.4m를 초과하는 PC 슬래브는 운반이 어렵다는 문제점이 있다. In order to transport the precast concrete slab (PC slab) to the construction site, the maximum width must be less than 2.4 m, and the PC slab exceeding 2.4 m has a problem in that it is difficult to transport.

그리고, 층고가 높거나 활하중이 큰 구조물에 사용되는 프리캐스트 콘크리트 기둥(PC 기둥)은 그 운반이 어렵고 조립 및 양중무게가 크므로 분절 시공해야 할 수도 있어서 공기(工期)에 영향을 줄 수도 있다.In addition, precast concrete columns (PC columns) used for structures with high floor heights or large live loads are difficult to transport and have large assembly and lifting weights, so they may need to be segmented, which may affect air quality.

이러한 문제점을 해결하기 위해, 기둥을 2개로 나누어 시공할 경우(즉, 수직으로 분절할 경우) 1개 기둥의 단면적이 감소하여 좌굴 등의 영향으로 내력이 감소하고 2개 기둥의 연결이 어렵다는 문제점이 있다. 이에 따라, 기둥을 수평으로 분절(기둥의 길이를 짧게 하는 것)하는 것이 대부분인데 수평 조인트(연결 부분)에서 철근 연결 및 몰탈 양생이 필요하여 공사기간이 지연된다는 문제점이 있다. In order to solve this problem, when the column is divided into two and constructed (that is, vertically segmented), the cross-sectional area of one column is reduced, resulting in a decrease in the bearing capacity due to buckling, etc., and the problem that the connection of the two columns is difficult. have. Accordingly, most of the columns are horizontally segmented (shortening the length of the column), but there is a problem in that the construction period is delayed because rebar connection and mortar curing are required at the horizontal joint (connection part).

본 발명은 상기 문제점들을 해결하기 위해 제안된 것으로서, 프리캐스트 콘크리트 부재(PC 기둥, PC 보, PC 슬래브 등) 사이에 장비없이 인력으로 쉽게 설치할 수 있는 지지판(박판, 얇은 강판으로 만들어진 거푸집, 데크플레이트(트러스데크 포함), 파형강판, 골형강판, 섬유혼용얇은시멘트판 등)을 설치하고 현장 타설 콘크리트를 타설하여 와이드 복합 구조 단면을 만드는 방법을 제공하는 데 그 목적이 있다. The present invention has been proposed to solve the above problems, and the support plate (thin plate, formwork made of thin steel plate, deck plate) that can be easily installed by manpower without equipment between precast concrete members (PC column, PC beam, PC slab, etc.) (including truss deck), corrugated steel plate, corrugated steel plate, fiber mixed thin cement plate, etc.) and pouring concrete cast on site to provide a method of making a wide composite structure cross section.

구체적으로, 본 발명은 프리캐스트 콘크리트(PC)와 현장타설 콘크리트를 함께 사용하여 와이드 단면을 만들고, 이에 따라 생산 몰드 변경없이 와이드 단면 폭을 필요에 따라 증감시킬 수 있으며, 층고를 줄일 수 있고, 슬래브 지지길이 감소로 경제성을 확보할 수 있으며, 프리캐스트 콘크리트 대비 현장타설 콘크리트의 비율을 높여 합성 효과 및 공사비 절감 효과를 높일 수 있고, 기존에 프리캐스트 콘크리트에 매립되던 전기, 소방 설비 등을 현장에서 콘크리트를 타설하기 이전에 용이하게 설치할 수 있으며, 운반 및 양중이 용이한, 프리캐스트 콘크리트 와이드 복합구조의 시공방법을 제공하는 데 그 목적이 있다. Specifically, the present invention makes a wide cross-section by using precast concrete (PC) and cast-in-place concrete together, so that the width of the wide cross-section can be increased or decreased as necessary without changing the production mold, and the floor height can be reduced, and the slab Economic feasibility can be secured by reducing the support length, and by increasing the ratio of cast-in-place concrete to precast concrete, the effect of synthesis and reduction of construction costs can be increased. The purpose of this is to provide a construction method of a precast concrete wide composite structure that can be easily installed before pouring, and is easy to transport and lift.

본 발명에 따라 복합 와이드 합성 구조를 갖는 슬래브(100)를 시공하는 방법은, (a) 공사 현장에서, PC 슬래브(precast concrete slab, 110)를 소정 간격으로 PC 보(210)에 설치하는 단계; (b) PC 슬래브(110) 사이에 제1 지지판(140)을 설치하는 단계; 및, (c) PC 슬래브(110)와 제1 지지판(140) 위에 현장철근을 설치하고 현장 콘크리트를 타설하는 단계;를 포함할 수 있다. The method of constructing a slab 100 having a composite wide composite structure according to the present invention comprises the steps of (a) installing a PC slab (precast concrete slab, 110) to the PC beam 210 at predetermined intervals at the construction site; (b) installing a first support plate 140 between the PC slabs 110; And, (c) installing on-site reinforcement on the PC slab 110 and the first support plate 140 and pouring on-site concrete; may include.

상기 PC 슬래브(110)는, 일반적인 더블티 슬래브와 달리, 리브 상단에서 외측으로 형성된 플랜지(날개 부분)가 없거나 PC로 짧게 형성한 후 상기 (c) 단계의 콘크리트 현장 타설에 의해 플랜지(날개 부분)이 형성되거나 연장된다.The PC slab 110, unlike a general double tee slab, does not have a flange (wing part) formed outwardly from the top of the rib or is formed short with PC and then a flange (wing part) by the concrete casting in step (c). is formed or extended.

그리고, 본 발명에 따라 복합 와이드 합성 구조를 갖는 보(200)를 시공하는 방법은, (가) 두 개의 단위 PC보(212)를 소정 간격으로 이격되도록 설치하는 단계; (나) 두 개의 단위 PC보(212) 사이에 제2 지지판(240)을 설치하는 단계; 및, (다) 제2 지지판(240) 위에 현장 콘크리트를 타설하는 단계;를 포함할 수 있다. 상기 (가) 단계 또는 (가),(나) 단계는 (a) 단계의 이전에 이루어질 수 있다. 그리고, 상기 (다) 단계의 현장 콘크리트 타설은 (c) 단계의 현장 콘크리트 타설과 함께(동시에) 이루어질 수도 있다. And, the method of constructing the beam 200 having a composite wide composite structure according to the present invention comprises the steps of: (A) installing two unit PC beams 212 to be spaced apart from each other at a predetermined interval; (B) installing a second support plate 240 between the two unit PC beams 212; And, (c) pouring on-site concrete on the second support plate 240; may include. Step (a) or (a), (b) may be performed before step (a). And, the on-site concrete pouring of step (c) may be made together (simultaneously) with the on-site concrete pouring of step (c).

본 발명에 따른 복합 와이드 합성 구조를 갖는 기둥(300)은, 소정 간격으로 이격되도록 수직으로 설치된 두 개의 단위 PC기둥(312); 및, 두 개의 단위 PC기둥(312)을 연결하도록 설치된 두 개의 제3 지지판(340);을 포함할 수 있다. The pillar 300 having a composite wide composite structure according to the present invention includes: two unit PC pillars 312 vertically installed to be spaced apart at a predetermined interval; and two third support plates 340 installed to connect the two unit PC pillars 312 .

단위 PC보(212)는 단위 PC기둥(312)에 설치되며, 두 개의 단위 PC기둥(312)과 두 개의 제3 지지판(340)은 내부공간을 형성하며, 상기 내부공간에는 현장 콘크리트가 타설된다. The unit PC beam 212 is installed on the unit PC column 312, the two unit PC columns 312 and the two third support plates 340 form an inner space, and the site concrete is poured into the inner space. .

상기 PC 슬래브(110)는, 본체(120); 본체(120)의 폭방향 양쪽 단부에서 아래로 형성된 리브(130); 및, 본체(120)의 폭방향 양쪽 단부에 형성된 걸침턱(122);을 포함할 수 있다. 제1 지지판(140)의 단부는 걸침턱(122)에 설치될 수 있다.The PC slab 110, the body 120; Ribs 130 formed downward at both ends of the body 120 in the width direction; And, the cross-section 122 formed on both ends of the width direction of the body 120; may include. An end of the first support plate 140 may be installed on the clasp 122 .

걸침턱(122)에는 물 유도홈(124)이 형성될 수 있다. 물 유도홈(124)은 PC슬래브(110)의 길이방향을 따라 길게 형성되되 제1 지지판(140)으로부터 아래쪽으로 소정 간격으로 이격되는 것이 바람직하다. 이에 따라, 제1 지지판(140) 또는 PC 슬래브(110)를 타고 흘러내린 물, 녹물, 시멘트페이스트 등이 물 유도홈(124)을 통해서 이동될 수 있다.A water guide groove 124 may be formed in the protruding jaw 122 . It is preferable that the water guide groove 124 is formed to be elongated in the longitudinal direction of the PC slab 110 and spaced downward from the first support plate 140 by a predetermined interval. Accordingly, water, rust, cement paste, etc. that have flowed down on the first support plate 140 or the PC slab 110 may be moved through the water guide groove 124 .

이러한 물 유도홈은 단위 PC보(212)에도 형성할 수 있다. 바람직하게, 물 유도홈은 단위 PC보(212)의 상면에 단위 PC보(212)의 길이방향을 따라 연속적으로 형성될 수 있다. PC슬래브(110)의 물 유도홈(124)을 통해 이동한 물, 녹물, 시멘트페이스트 등은 단위 PC보(212)의 물 유도홈을 통해서 기둥으로 이동한 후 지면 등으로 배출될 수 있다. Such a water guide groove can also be formed in the unit PC beam (212). Preferably, the water guide groove may be continuously formed on the upper surface of the unit PC beam 212 in the longitudinal direction of the unit PC beam 212 . Water, rust, cement paste, etc. that have moved through the water guide groove 124 of the PC slab 110 may be discharged to the ground after moving to the column through the water guide groove of the unit PC beam 212 .

단위 PC보(212)의 양쪽 단부에서 두 개의 단위 PC보(212)의 서로 마주보는 면에는 제1 계단턱(214)이 형성되고, 제2 지지판(240)은 제1 계단턱(214)에 설치되며, 이에 따라 상기 (다) 단계에서 단위 PC보(212)의 양쪽 단부는 중앙 부분 보다 현장 콘크리트의 두께가 더 두껍게 형성된다.At both ends of the unit PC beam 212 , a first step 214 is formed on the opposite surfaces of the two unit PC beams 212 , and the second support plate 240 is on the first step 214 . is installed, and accordingly, both ends of the unit PC beam 212 in step (c) are formed to have a thicker thickness of on-site concrete than the central portion.

단위 PC보(212)의 중앙 부분에서 단면의 외측에는 제2 계단턱(217)이 형성되고 단면의 내측에는 제3 계단턱(218)이 형성될 수 있다. 그리고, PC 슬래브(110)는 제2 계단턱(217)에 설치되고 제2 지지판(240)은 제3 계단턱(218)에 설치될 수 있다. 제2,3 계단턱(217)(218)이 연결하여 통하도록 관통공(219)이 단위 PC보(212)의 상단에 형성되고, PC 슬래브(110)의 철근이 관통공(219)을 통하여 맞은편 PC 슬래브(110)에 연결될 수 있다. In the central portion of the unit PC beam 212, a second step 217 may be formed on the outside of the cross-section, and a third step 218 may be formed on the inside of the cross-section. In addition, the PC slab 110 may be installed on the second step 217 , and the second support plate 240 may be installed on the third step 218 . A through hole 219 is formed at the upper end of the unit PC beam 212 so that the second and third step steps 217 and 218 are connected and communicated, and the reinforcing bar of the PC slab 110 is passed through the through hole 219 . It may be connected to the opposite PC slab 110 .

단위 PC기둥(312) 중에서 맞은 편 단위 PC기둥(312)과 마주보는 면에는 홈(322)이 형성되고, 홈(322)의 양쪽 끝단에는 턱(324)이 형성되며, 제3 지지판(340)은 턱(324)에 의해 지지될 수 있다. A groove 322 is formed on the surface facing the opposite unit PC column 312 among the unit PC columns 312, and jaws 324 are formed at both ends of the groove 322, and the third support plate 340. can be supported by jaws 324 .

상기 (b) 단계와 (c) 단계 사이 또는 상기 (나) 단계와 (다) 단계 사이에, 현장 콘크리트가 타설될 부분에 전기설비 및/또는 소방설비 등을 설치할 수 있다.Between steps (b) and (c) or between steps (b) and (c), electrical equipment and/or fire-fighting equipment, etc. may be installed in the part where on-site concrete is to be poured.

본 발명에 따른 프리캐스트 콘크리트 와이드 복합구조의 시공방법은 프리캐스트 콘크리트 부재(PC 기둥, PC 보, PC 슬래브 등) 사이에 지지판(박판, 얇은 강판으로 만들어진 거푸집, 데크플레이트(트러스데크 포함), 파형강판, 골형강판 등)을 설치하고 현장 타설 콘크리트를 타설하여 와이드 복합 구조 단면을 만들 수 있다. The construction method of the precast concrete wide composite structure according to the present invention is a support plate (thin plate, form made of thin steel plate, etc.) between precast concrete members (PC column, PC beam, PC slab, etc.), deck plate (including truss deck), corrugation Steel plate, corrugated steel plate, etc.) can be installed and cast-in-place concrete can be poured to create a wide composite structure cross section.

이에 따라, 본 발명에 따른 시공 방법은 와이드 단면 폭을 필요에 따라 증감시킬 수 있으며, 층고를 줄일 수 있고, 슬래브 지지길이 감소로 경제성을 확보할 수 있으며, 프리캐스트 콘크리트 대비 현장타설 콘크리트의 비율을 높여 합성 효과 및 공사비 절감 효과를 높일 수 있고, 기존에 프리캐스트 콘크리트에 매립되던 전기선, 수도관, 배수관, 오수관, 환기관 등을 현장에서 콘크리트를 타설하기 이전에 용이하게 설치할 수 있으며, PC부재가 가벼우므로 운반 및 양중이 용이하다는 장점을 갖는다. Accordingly, the construction method according to the present invention can increase or decrease the wide cross-sectional width as needed, reduce the floor height, secure economic feasibility by reducing the slab support length, and increase the ratio of cast-in-place concrete to precast concrete It is possible to increase the synthesis effect and the reduction of construction cost by increasing it, and it is possible to easily install electric cables, water pipes, drain pipes, sewage pipes, ventilation pipes, etc. that were previously buried in precast concrete before pouring concrete on site, and because the PC member is light. It has the advantage of being easy to transport and lift.

도 1은 본 발명에 따라 PC 슬래브 사이에 제1 지지판(트러스 데크)이 설치된 후 현장 콘크리트가 타설된 것을 보여주는 단면도.
도 2a~2b는 각각 PC 슬래브의 변형예를 보여주는 단면도.
도 3은 물 유도홈을 갖는 PC 슬래브와, PC 슬래브에 설치된 제1 지지판(트러스 데크)을 보여주는 단면도.
도 4a는 본 발명에 이용되는 PC보를 보여주는 평면도.
도 4b는 도 4a의 PC보에 제2 지지판이 설치된 것을 보여주는 평면도.
도 5는 도 4a의 PC보가 연속적으로 설치되고 PC슬래브와 제1,2 지지판이 PC보에 설치된 것을 보여주는 평면도.
도 6은 도 5의 정면도.
도 7a는 도 5의 A-A' 단면도.
도 7b는 도 5의 B-B' 단면도.
도 7c는 도 5의 B-B' 단면도의 변형예.
도 7d는 도 5의 B-B' 단면도의 또 다른 변형예.
도 8a는 본 발명에 이용되는 또 다른 PC보를 보여주는 평면도.
도 8b는 도 8a의 PC보에 제2 지지판이 설치된 것을 보여주는 평면도.
도 9는 도 8a의 PC보가 연속적으로 설치되고 PC슬래브와 제1,2 지지판이 PC보에 설치된 것을 보여주는 평면도.
도 10은 도 9의 정면도.
도 11a는 도 9의 C-C' 단면도.
도 11b는 도 9의 D-D' 단면도.
도 11c는 도 9의 E-E' 단면도.
도 11d는 도 9의 E-E' 단면도의 변형예.
도 11e는 도 9의 E-E' 단면도의 또 다른 변형예.
도 12a~12d는 각각 본 발명에 따라 시공된 기둥을 보여주는 평단면도.
1 is a cross-sectional view showing that on-site concrete is poured after a first support plate (truss deck) is installed between PC slabs according to the present invention.
2a to 2b are cross-sectional views each showing a modified example of a PC slab.
3 is a cross-sectional view showing a PC slab having a water guide groove, and a first support plate (truss deck) installed in the PC slab.
Figure 4a is a plan view showing a PC beam used in the present invention.
Figure 4b is a plan view showing that the second support plate is installed on the PC beam of Figure 4a.
Figure 5 is a plan view showing that the PC beam of Figure 4a is installed continuously and the PC slab and the first and second support plates are installed on the PC beam.
Fig. 6 is a front view of Fig. 5;
Fig. 7A is a cross-sectional view taken along line AA' of Fig. 5;
Fig. 7B is a cross-sectional view taken along line BB' of Fig. 5;
FIG. 7C is a modified example of a cross-sectional view taken along line BB′ of FIG. 5 .
FIG. 7D is another modified example of a cross-sectional view taken along line BB′ of FIG. 5 .
Figure 8a is a plan view showing another PC beam used in the present invention.
Figure 8b is a plan view showing that the second support plate is installed on the PC beam of Figure 8a.
9 is a plan view showing that the PC beam of FIG. 8a is continuously installed and the PC slab and the first and second support plates are installed on the PC beam.
Fig. 10 is a front view of Fig. 9;
Fig. 11A is a cross-sectional view taken along line CC' of Fig. 9;
11B is a cross-sectional view DD′ of FIG. 9 ;
11C is a cross-sectional view EE′ of FIG. 9 ;
11D is a modified example of the cross-sectional view EE' of FIG.
11E is another modified example of the cross-sectional view EE' of FIG.
12a to 12d are plan cross-sectional views each showing a column constructed in accordance with the present invention.

이하, 첨부된 도면들을 참조로 본 발명에 대해서 상세히 설명하기로 한다. 이에 앞서, 본 명세서 및 청구범위에 사용된 용어나 단어는 통상적이거나 사전적인 의미로 한정해서 해석되어서는 아니되며, 발명자는 그 자신의 발명을 가장 최선의 방법으로 설명하기 위해 용어의 개념을 적절하게 정의할 수 있다는 원칙에 입각하여 본 발명의 기술적 사상에 부합하는 의미와 개념으로 해석되어야만 한다. 따라서, 본 명세서에 기재된 실시예와 도면에 도시된 구성은 본 발명의 실시예들에 불과할 뿐이고 본 발명의 기술적 사상을 모두 대변하는 것은 아니므로, 본 출원시점에 있어서 이들을 대체할 수 있는 다양한 균등물과 변형예들이 있을 수 있음을 이해하여야 한다. Hereinafter, the present invention will be described in detail with reference to the accompanying drawings. Prior to this, the terms or words used in the present specification and claims should not be construed as being limited to conventional or dictionary meanings, and the inventor should properly understand the concept of the term in order to best describe his invention. Based on the principle that it can be defined, it should be interpreted as meaning and concept consistent with the technical idea of the present invention. Accordingly, the embodiments described in this specification and the configurations shown in the drawings are merely embodiments of the present invention and do not represent all the technical spirit of the present invention, so various equivalents that can be substituted for them at the time of the present application It should be understood that there may be variations and variations.

본 발명은 PC 슬래브, PC 보, PC 기둥 등과 같은 프리캐스트 콘크리트 부재 사이에 지지판(제1,2,3 지지판)을 설치하고 현장 타설 콘크리트를 타설하여 와이드 복합 구조 단면을 만든다. 아래에서는 이를 순차적으로 설명하기로 한다.The present invention installs support plates (first, second, and third support plates) between precast concrete members such as PC slabs, PC beams, PC columns, and the like, and pours cast-in-place concrete to make a wide composite structure cross-section. Hereinafter, these will be sequentially described.

한편, 본 명세서에서 지지판(제1,2,3 지지판)은 박판, 얇은 강판으로 만들어진 거푸집, 데크플레이트(트러스데크 포함), 파형강판, 골형강판, 섬유혼용얇은시멘트판 등을 의미한다. Meanwhile, in the present specification, the support plates (first, second, and third support plates) mean a thin plate, a form made of a thin steel plate, a deck plate (including a truss deck), a corrugated steel plate, a corrugated steel plate, a fiber mixed thin cement plate, and the like.

[PC 슬래브와 제1 지지판 및 현장타설 콘크리트로 이루어지는 슬래브][Slab composed of PC slab, first support plate and cast-in-place concrete]

도 1은 본 발명에 따라 시공된 슬래브를 보여주는 단면도로서, PC 슬래브(precast concrete slab) 사이에 제1 지지판(트러스 데크)이 설치된 후 현장 콘크리트가 타설된 것을 보여준다. 1 is a cross-sectional view showing a slab constructed according to the present invention, showing that the on-site concrete is poured after a first support plate (truss deck) is installed between PC slabs (precast concrete slab).

도면에 나타난 바와 같이, 상기 슬래브(100)는 PC 슬래브(110)와, PC 슬래브(110) 사이에 설치된 제1 지지판(140) 및, PC 슬래브(110)와 제1 지지판(140) 위에 콘크리트가 현장 타설되어 이루어진 콘크리트부(150)를 포함한다.As shown in the drawing, the slab 100 includes a PC slab 110 and a first support plate 140 installed between the PC slab 110, and the PC slab 110 and the first support plate 140 on which concrete is placed. It includes a concrete part 150 that is cast on site.

PC 슬래브(110)는 이웃하는 PC 슬래브(110)와 소정 간격으로 이격되도록 단위 PC보(도 4a~6의 212)에 설치된다. The PC slab 110 is installed in a unit PC beam (212 in FIGS. 4a to 6) so as to be spaced apart from the neighboring PC slab 110 by a predetermined interval.

바람직하게, PC 슬래브(110)는 본체(120)와 리브(130)를 구비한다. 본체(120)는 PC 슬래브(110)의 길이방향(도 1에서 지면(紙面)에 수직인 방향)을 따라 길게 형성된 평판으로서, 본체(120)의 폭 방향 양측 단부에는 걸침턱(122)이 형성되며, 본체(120)의 길이방향을 따라 전단 철근(132)이 설치될 수 있다. 걸침턱(122)에는 제1 지지판(140)의 끝단이 설치된다. 전단 철근(132)으로는 래티스 철근 등이 사용될 수 있는데, 그 상부에 타설되는 현장 콘크리트와 PC 슬래브(110)를 일체화시키고 전단 응력에 저항하는 역할을 한다. Preferably, the PC slab 110 includes a body 120 and ribs 130 . The body 120 is a flat plate elongated along the longitudinal direction (direction perpendicular to the ground in FIG. 1) of the PC slab 110, and cross-sections 122 are formed at both ends of the body 120 in the width direction. And, along the longitudinal direction of the body 120, the shear reinforcement 132 may be installed. The end of the first support plate 140 is installed on the cradle 122 . As the shear reinforcing bar 132, lattice reinforcing bars, etc. may be used, and serves to integrate the on-site concrete and the PC slab 110 poured thereon and resist shear stress.

PC 슬래브(110)는, 일반적인 더블티 슬래브와 달리, 리브(130) 상단에서 외측으로 형성된 플랜지(날개 부분)가 없거나 PC로 짧게 형성된다. 그리고, 제1 지지판(140)의 위에 타설된 현장 콘크리트에 의해 PC 슬래브(110) 양측의 플랜지(날개 부분)가 형성되거나 연장된다. The PC slab 110, unlike a general double tee slab, does not have a flange (wing portion) formed outwardly from the top of the rib 130 or is formed short of PC. Then, flanges (wing portions) on both sides of the PC slab 110 are formed or extended by the on-site concrete poured on the first support plate 140 .

이에 따라, 리브(130)는 본체(120)의 하중을 지지하도록 본체(120)의 양측 단부의 아래에서 PC 슬래브의 길이방향을 따라 연속적으로 형성될 수 있다. 바람직하게, 리브(130)의 바깥쪽 측면은 본체(120)의 폭방향 끝단과 실질적으로 동일 평면상에 위치하는 것이 바람직하다. 그리고, 리브(130)의 하부에는 프리텐션을 인가하기 위한 철근(134)이 설치될 수 있다. Accordingly, the rib 130 may be continuously formed along the longitudinal direction of the PC slab under both ends of the main body 120 to support the load of the main body 120 . Preferably, the outer side of the rib 130 is preferably positioned on the same plane as the width direction end of the body 120 . In addition, a reinforcing bar 134 for applying a pretension may be installed under the rib 130 .

제1 지지판(140)은 현장 타설된 콘크리트의 거푸집 역할과, 타설된 콘크리트의 하중을 지지하는 역할을 한다. 그리고, 현장 타설 콘크리트가 양생 완료된 후에는 제거되지 않고 현장 타설된 콘크리트 및 PC 슬래브(110)와 함께 마감하중과 활하중 등에 저항하는 역할을 한다. The first support plate 140 serves as a formwork of the concrete cast on site, and supports the load of the cast concrete. And, after the cast-in-place concrete is cured, it is not removed and serves to resist the finishing load and live load together with the cast-in-place concrete and the PC slab 110 .

도 1에는 트러스 데크가 제1 지지판(140)으로 사용되었지만 박판, 얇은 강판으로 만들어진 거푸집, 데크플레이트, 파형강판, 골형강판, 섬유혼용얇은시멘트판 등이 제1 지지판으로 사용될 수도 있다. Although the truss deck is used as the first support plate 140 in FIG. 1 , a thin plate, a formwork made of a thin steel plate, a deck plate, a corrugated steel plate, a corrugated steel plate, a fiber mixed thin cement plate, etc. may be used as the first support plate.

위와 같이, PC 슬래브(110)가 소정 간격으로 이격되도록 PC보(210)에 설치되고, 리브(130)의 바깥쪽 측면이 본체(120)의 폭방향 끝단과 실질적으로 동일 평면상에 위치하며, PC 슬래브(110) 사이에 제1 지지판(140)이 설치되고, PC 슬래브(110)와 제1 지지판(140) 위에 현장 콘크리트가 타설된다. 그리고, 제1 지지판(140)의 폭을 필요에 따라 증감할 수 있으므로 와이드 구조의 폭을 조절할 수 있다. As described above, the PC slab 110 is installed on the PC beam 210 so as to be spaced apart by a predetermined interval, and the outer side of the rib 130 is located on the same plane as the width direction end of the body 120, A first support plate 140 is installed between the PC slab 110 , and on-site concrete is poured on the PC slab 110 and the first support plate 140 . And, since the width of the first support plate 140 can be increased or decreased as necessary, the width of the wide structure can be adjusted.

아울러, PC 슬래브(110)와 제1 지지판(140)이 단위 PC보(212)에 설치 완료된 후, 현장 콘크리트가 타설될 부분에 전기설비 및/또는 소방설비 등, 예를 들어 전기선, 수도관, 배수관, 오수관, 환기관 등 중에서 적어도 어느 하나를 현장 콘크리트 타설 이전에 설치할 수 있다. 슬래브가 PC 슬래브'만'으로 이루어지는 경우에는 전기선 등의 설비 공사를 공사 현장에서 하기가 어려웠으나, 본 발명에 따른 시공방법에서는 이러한 설비공사가 쉽고 단순해진다. In addition, after the PC slab 110 and the first support plate 140 are installed on the unit PC beam 212, electrical equipment and/or fire-fighting equipment, etc., for example, an electric wire, a water pipe, a drain pipe, are placed on the part where on-site concrete is to be poured. , at least one of a sewage pipe, a ventilation pipe, etc. may be installed prior to on-site concrete pouring. When the slab is made of 'only PC slab', it is difficult to perform facility work such as electric wires at the construction site, but in the construction method according to the present invention, such facility work becomes easy and simple.

한편, 도 2a에 나타난 바와 같이, 리브(130)는 그 바깥쪽 측면의 상부가 수직면으로 이루어질 수도 있고, 도 2b에 나타난 바와 같이 바깥쪽 측면이 수직면으로 이루어질 수도 있다. Meanwhile, as shown in FIG. 2A , the upper portion of the outer side of the rib 130 may be formed as a vertical surface, and as shown in FIG. 2B , the outer side of the rib 130 may be formed as a vertical surface.

기존의 더블티 PC슬래브는 차량 운반을 고려할 경우 그 최대 폭이 2.4m였다. 이에 비해, 본 발명에 따른 PC 슬래브(110)의 폭이 2.2m이고 제1 지지판(140)의 폭을 3~4m라고 하면 5~6m까지 증가된 폭을 갖는 더블티 슬래브를 만들 수 있다. 이 때 PC 슬래브(110)는 더블티 슬래브의 몸체를 이루는 부분으로서 프리텐션이 인가될 수 있고, 제1 지지판(140)과 그 상부의 콘크리트부(150)는 더블티 슬래브의 날개 부분을 이룬다. The maximum width of the existing double tee PC slab was 2.4m when transporting vehicles was considered. In contrast, if the width of the PC slab 110 according to the present invention is 2.2 m and the width of the first support plate 140 is 3 to 4 m, a double tee slab having an increased width to 5 to 6 m can be made. At this time, the PC slab 110 is a portion constituting the body of the double tee slab, and pretension may be applied, and the first support plate 140 and the upper concrete portion 150 form the wing portion of the double tee slab.

한편, 도 3에 나타난 바와 같이, 걸침턱(122)에는 물 유도홈(124)이 형성될 수 있다. 물 유도홈(124)은 PC 슬래브(110)의 길이방향을 따라 연속적으로 형성될 수 있는데, 제1 지지판(140)으로부터 아래쪽으로 소정간격으로 이격되도록 형성된다. 제1 지지판(140)이 현장에 설치된 후 비 또는 눈이 내리면 철근의 녹물이 PC 슬래브(110)와 PC 보(210)의 측면과 아랫면을 오염시킬 수 있는데, 물 유도홈(124)은 이러한 녹물을 유도하여 배수하므로 오염과 얼룩을 방지할 수 있다.Meanwhile, as shown in FIG. 3 , a water guide groove 124 may be formed in the protrusion 122 . The water guide groove 124 may be continuously formed along the longitudinal direction of the PC slab 110 , and is formed to be spaced downward from the first support plate 140 at a predetermined interval. When it rains or snows after the first support plate 140 is installed on the site, rust of the reinforcing bars may contaminate the side and lower surfaces of the PC slab 110 and the PC beam 210, and the water guide groove 124 is such rust. It induces drainage to prevent contamination and staining.

[PC 보와 제2 지지판 및 현장타설 콘크리트로 이루어지는 보][Beam composed of PC beam, second support plate and cast-in-place concrete]

도 4a는 본 발명에 이용되는 PC보를 보여주는 평면도이고, 도 4b는 상기 PC보에 제2 지지판이 설치된 것을 보여주는 평면도이며, 도 5는 PC보가 연속적으로 설치되고 PC슬래브와 제1,2 지지판이 PC보에 설치된 것을 보여주는 평면도이다. 도 4b와 도 5에서 붉은 점선은 제1 계단턱(214)에 설치된 제2 지지판(240)을 나타내고, 하늘색 점선은 단위 PC보(212)의 상단에 설치된 제2 지지판(240)을 나타내며, 보라색 선은 PC 슬래브(110)를 나타내고, 파란색 선은 제1 지지판(140)을 나타낸다.Figure 4a is a plan view showing the PC beam used in the present invention, Figure 4b is a plan view showing that the second support plate is installed on the PC beam, Figure 5 is the PC beam is installed continuously, the PC slab and the first and second support plates are PC It is a plan view showing what is installed on the beam. In FIGS. 4B and 5 , the red dotted line indicates the second support plate 240 installed on the first stairway 214 , and the light blue dotted line indicates the second support plate 240 installed on the upper end of the unit PC beam 212 , purple The line represents the PC slab 110 , and the blue line represents the first support plate 140 .

상기 보(200)는 PC보(210)와 현장타설 콘크리트를 포함하여 이루어진다. PC보(210)는 두 개의 단위 PC보(212)를 포함하고, 두 개의 단위 PC보(212)는 소정 간격으로 이격되도록 서로 평행하게 설치된다. 각각의 단위 PC보(212)는 후술하는 단위 PC기둥(도 12a의 312)에 설치될 수 있다. 그리고, 도면에는 도시되지 않았지만, 단위 PC보(212)의 내부에는 철근 등이 배근된다. The beam 200 includes a PC beam 210 and cast-in-place concrete. The PC beam 210 includes two unit PC beams 212 , and the two unit PC beams 212 are installed in parallel to each other so as to be spaced apart from each other by a predetermined interval. Each unit PC beam 212 may be installed on a unit PC column (312 in FIG. 12A) to be described later. And, although not shown in the drawings, reinforcing bars and the like are provided inside the unit PC beam 212 .

도 7a~7b에 나타난 바와 같이, 단위 PC보(212)는 직사각형 단면을 갖되, 그 양쪽 단부에는 제1 계단턱(214)이 형성된다. 그리고, 두 개의 단위 PC보(212)는 제1 계단턱(214)이 서로 마주보도록 설치된다. 7a to 7b, the unit PC beam 212 has a rectangular cross-section, and a first step 214 is formed at both ends thereof. In addition, the two unit PC beams 212 are installed so that the first step sill 214 faces each other.

제2 지지판(240)은 그 양쪽 단부가 두 개의 단위 PC보(212)에 걸쳐지도록 설치된다. 구체적으로, 단위 PC보(212)의 양쪽 단부에서는 제2 지지판(240)의 양쪽 단부가 제1 계단턱(214)에 걸쳐지도록 설치되고 상기 양쪽 단부를 제외한 나머지 부분에서는 제2 지지판(240)의 양쪽 단부가 단위 PC보(212)의 상단에 걸쳐지도록 설치된다. 그리고, 제2 지지판(240)의 위에는 현장 콘크리트가 타설된다. 따라서, 현장 타설된 콘크리트의 두께는 보의 양쪽 단부가 보의 나머지 부분 보다 더 두껍다. 이러한 구성은 보의 양쪽 단부의 하부에 작용하는 압축 응력에 더 효과적으로 저항할 수 있으므로 유리하다. The second support plate 240 is installed so that both ends thereof span the two unit PC beams 212 . Specifically, at both ends of the unit PC beam 212, both ends of the second support plate 240 are installed so as to span the first stair step 214, and in the remaining portions except for the both ends of the second support plate 240 Both ends are installed so as to span the upper end of the unit PC beam (212). And, on-site concrete is poured on the second support plate 240 . Therefore, the thickness of cast-in-place concrete is thicker at both ends of the beam than the rest of the beam. This configuration is advantageous as it can more effectively resist the compressive stress acting on the underside of both ends of the beam.

상기 현장 콘크리트 타설은 슬래브(100) 위에 이루어지는 현장 타설과 함께 이루어지거나 별개로 이루어질 수 있다.The on-site concrete pouring may be made together with the on-site pouring made on the slab 100 or may be made separately.

두 개의 단위 PC보(212) 사이의 간격은 필요에 따라 증감될 수 있다. 따라서, 제2 지지판(240)의 폭을 조절하면 와이드 단면 구조의 폭을 조절할 수 있다. The interval between the two unit PC beams 212 may be increased or decreased as needed. Accordingly, if the width of the second support plate 240 is adjusted, the width of the wide cross-sectional structure may be adjusted.

단위 PC보(212)의 단면 바깥쪽의 상단에는 PC 슬래브(110)가 설치된다. 도 5~6에는 단위 PC보(212)의 중앙과 양쪽 단부에 각각 PC 슬래브(110)가 설치된 것으로 도시되어 있으나 PC 슬래브(110)의 설치 위치와 개수는 필요에 따라 증감될 수 있다. 제1 지지판(140)은 그 양쪽 단부가 PC 슬래브(110)의 단부에 걸쳐지도록 설치된다. A PC slab 110 is installed at the upper end of the outer section of the unit PC beam 212 . Although it is shown that the PC slab 110 is installed at the center and both ends of the unit PC beam 212 in FIGS. 5 to 6 , respectively, the installation location and number of the PC slab 110 may be increased or decreased as needed. The first support plate 140 is installed so that both ends thereof span the ends of the PC slab 110 .

기존의 와이드 PC보는 그 폭이 넓으므로 생산이 어렵고 중량이 과대하여 운반 및 양중에 어려움이 많았다. 그리고, 기존에는 PC보의 폭을 변경하기 위해서는 공장에서 철판 거푸집을 조정해야 하므로 공사비가 상승하고 생산성이 저하되는 문제가 있었다. 이에 비해, 본 발명에 따른 보(200)는 상대적으로 가볍고 작으며 대칭적인 구조를 갖는 2개의 단위 PC보(212)를 공장에서 현장까지 운반한 후 현장에서 양중 및 조립하고 그 사이에 제2 지지판(240)을 설치한 다음, 현장타설 콘크리트를 통해 일체화된 와이드 단면의 보(200)를 제조할 수 있다. 그리고, 두 단위 PC보(212) 사이에 제2 지지판(240)이 설치되므로 제2 지지판(240)의 폭을 조절하면 보(200)의 폭을 자유롭게 변경할 수 있다. Existing wide PC beams were difficult to produce because of their wide width, and there were many difficulties in transporting and lifting due to excessive weight. And, in order to change the width of the PC beam in the past, there was a problem that the construction cost increased and productivity was lowered because the iron plate form had to be adjusted in the factory. In contrast, the beam 200 according to the present invention is relatively light and small, and after transporting two unit PC beams 212 having a symmetrical structure from the factory to the site, lifting and assembling at the site, and a second support plate between them After installing the 240, it is possible to manufacture a beam 200 of a wide cross-section integrated through the cast-in-place concrete. And, since the second support plate 240 is installed between the two unit PC beams 212 , the width of the beam 200 can be freely changed by adjusting the width of the second support plate 240 .

도 7c는 제2 지지판(240)이 PC 블록(precast concrete block)으로 이루어진 것을 보여주고, 도 7d는 PC 블록이 걸림턱(244)을 갖는 경우를 보여준다. 제2 지지판(240)의 아랫면이 단위 PC보(212)의 아랫면과 일치하면 보의 단부에서 하중 지지력이 그 만큼 커지므로 유리하다. Figure 7c shows that the second support plate 240 is made of a PC block (precast concrete block), Figure 7d shows a case in which the PC block has a stopping protrusion 244 . When the lower surface of the second support plate 240 coincides with the lower surface of the unit PC beam 212, it is advantageous because the load-bearing force at the end of the beam increases by that much.

한편, 상술한 물 유도홈은 단위 PC보(212)에도 형성될 수 있다. 구체적으로, 물 유도홈은 단위 PC보(212)의 상면에 단위 PC보(212)의 길이방향을 따라 연속적으로 형성될 수 있는데, 더욱 바람직하게는 PC슬래브(110)의 물 유도홈(124)으로부터 배출된 녹물 등이 단위 PC보(212)로 떨어지는 부분에 물 유도홈이 형성될 수 있다. 이에 따라, PC슬래브(110)의 물 유도홈(124)을 통해 이동한 물, 녹물, 시멘트페이스트 등은 단위 PC보(212)의 물 유도홈을 통해서 기둥으로 이동한 후 지면 등으로 배출될 수 있다. On the other hand, the above-described water guide groove may also be formed in the unit PC beam (212). Specifically, the water guide groove may be formed continuously along the longitudinal direction of the unit PC beam 212 on the upper surface of the unit PC beam 212, more preferably the water guide groove 124 of the PC slab 110. A water guide groove may be formed in a portion where rust, etc. discharged from the unit PC beam 212 falls. Accordingly, water, rust, cement paste, etc. that have moved through the water guide groove 124 of the PC slab 110 can be discharged to the ground after moving to the column through the water guide groove of the unit PC beam 212. have.

도 8a는 본 발명에 이용되는 또 다른 PC보를 보여주는 평면도이고, 도 8b는 상기 PC보에 제2 지지판이 설치된 것을 보여주는 평면도이며, 도 9는 상기 PC보가 연속적으로 설치되고 PC슬래브와 제1,2 지지판이 PC보에 설치된 것을 보여주는 평면도이다. 도 8b와 도 9~10에서 붉은 점선은 제1,3 계단턱(214)(218)에 설치된 제2 지지판(240)을 나타내고, 하늘색 점선은 단위 PC보(212)의 상단에 설치된 제2 지지판(240)을 나타내며, 보라색 선은 PC 슬래브(110)를 나타내고, 파란색 선은 제1 지지판(140)을 나타낸다.Figure 8a is a plan view showing another PC beam used in the present invention, Figure 8b is a plan view showing that the second support plate is installed on the PC beam, Figure 9 is the PC beam is installed continuously and PC slab and first and second It is a plan view showing that the support plate is installed on the PC beam. In FIGS. 8B and 9 to 10 , the red dotted line indicates the second support plate 240 installed on the first and third step sills 214 and 218 , and the light blue dotted line indicates the second support plate installed on the upper end of the unit PC beam 212 . 240 , the purple line indicates the PC slab 110 , and the blue line indicates the first support plate 140 .

상기 보(200)는 PC보(210)와 현장타설 콘크리트를 포함하여 이루어진다. PC보(210)는 두 개의 단위 PC보(212)로 이루어지고, 두 개의 단위 PC보(212)는 소정 간격으로 이격되도록 서로 평행하게 설치된다. 각각의 단위 PC보(212)는 후술하는 단위 PC기둥(312)에 설치될 수 있다. 그리고, 도면에는 도시되지 않았지만, 단위 PC보(212)의 내부에는 철근 등이 설치된다. The beam 200 includes a PC beam 210 and cast-in-place concrete. The PC beam 210 is composed of two unit PC beams 212 , and the two unit PC beams 212 are installed in parallel to each other so as to be spaced apart from each other by a predetermined interval. Each unit PC beam 212 may be installed on a unit PC column 312 to be described later. And, although not shown in the drawings, reinforcing bars and the like are installed inside the unit PC beam 212 .

도 11a~11c에 나타난 바와 같이, 단위 PC보(212)는 직사각형 단면을 갖되, 그 양쪽 단부에는 제1 계단턱(214)이 형성되고 중앙 부분에는 제2,3 계단턱(217)(218)이 형성된다. 두 개의 단위 PC보(212)는 제1 계단턱(214)이 서로 마주보도록 설치되고, 그 양쪽 단부에는 단면 감소부(215)가 형성될 수 있다. 11a to 11c, the unit PC beam 212 has a rectangular cross section, the first step 214 is formed at both ends thereof, and the second and third step steps 217 and 218 are formed in the central part. this is formed The two unit PC beams 212 are installed so that the first step sill 214 faces each other, and cross-sectional reduction portions 215 may be formed at both ends thereof.

제2 지지판(240)은 그 양쪽 단부가 두 개의 단위 PC보(212)에 걸쳐지도록 설치된다. 구체적으로, 단위 PC보(212)의 양쪽 단부에서는 제2 지지판(240)의 양쪽 단부가 제1 계단턱(214)에 걸쳐지도록 설치되고, 단위 PC보(212)의 중앙 부분에서는 제2 지지판(240)의 양쪽 단부가 제3 계단턱(218)에 걸쳐지도록 설치되며, 상기 양쪽 단부와 중앙 부분을 제외한 나머지 부분에서는 제2 지지판(240)의 양쪽 단부가 단위 PC보(212)의 상단에 걸쳐지도록 설치된다. 그리고, 제2 지지판(240)과 단위 PC보(212)의 위에는 현장 콘크리트가 타설된다. 따라서, 현장 타설된 콘크리트의 두께는 보(200)의 양쪽 단부와 중앙 부분이 보의 나머지 부분 보다 더 두껍다. 이러한 구성은 보의 양쪽 단부의 하부와 보의 중앙 부분에 작용하는 응력에 더 효과적으로 저항할 수 있으므로 유리하다. The second support plate 240 is installed so that both ends thereof span the two unit PC beams 212 . Specifically, at both ends of the unit PC beam 212, both ends of the second support plate 240 are installed to span the first step 214, and in the central part of the unit PC beam 212, the second support plate ( Both ends of the 240) are installed so as to span the third stair step 218, and in the remaining portions except for the both ends and the central portion, both ends of the second support plate 240 span the upper end of the unit PC beam 212. installed so as to And, on-site concrete is poured on the second support plate 240 and the unit PC beam 212. Therefore, the thickness of the cast-in-place concrete is thicker at both ends and the central portion of the beam 200 than the rest of the beam. This configuration is advantageous as it can more effectively resist the stress acting on the lower portion of both ends of the beam and the central portion of the beam.

단위 PC보(212)의 중앙 부분의 상단에는 관통공(219)이 형성될 수 있다. 바람직하게, 관통공(219)은 제2,3 계단턱(217)(218)을 관통하여 연결하도록 형성된다. PC 슬래브(110)의 철근(도면에 미도시)은 관통공(219)을 통하여 반대편 PC 슬래브(110)와 서로 연결되고 이에 따라 하중이 전달될 수 있다. A through hole 219 may be formed at the upper end of the central portion of the unit PC beam 212 . Preferably, the through hole 219 is formed to penetrate through the second and third step steps 217 and 218 . Reinforcing bars (not shown in the drawing) of the PC slab 110 are connected to the opposite PC slab 110 through the through-hole 219, and thus a load may be transmitted.

도 11d는 제2 지지판(240)이 PC 블록(precast concrete block)으로 이루어진 것을 보여주고, 도 11e는 PC 블록이 걸림턱(244)을 갖는 경우를 보여준다. 제2 지지판(240)의 아랫면이 단위 PC보(212)의 아랫면과 일치하면 보의 단부에서는 하중 지지력이 그 만큼 커지므로 유리하다. Figure 11d shows that the second support plate 240 is made of a PC block (precast concrete block), Figure 11e shows a case in which the PC block has a stopping protrusion 244 . When the lower surface of the second support plate 240 coincides with the lower surface of the unit PC beam 212, it is advantageous because the load-bearing force increases by that much at the end of the beam.

한편, 단위 PC보(212)와 제2 지지판(240)이 설치 완료된 후, 현장 콘크리트가 타설될 부분에 전기설비 및/또는 소방설비 등을 설치할 수 있다. 보가 PC보'만'으로 이루어지는 경우에는 전기선 등의 설비 공사를 하기가 어려웠으나, 본 발명에 따른 시공방법에서는 이러한 설비공사가 쉽고 단순해진다. On the other hand, after the unit PC beam 212 and the second support plate 240 are installed, electrical equipment and/or firefighting equipment may be installed in the part where on-site concrete is to be poured. When the beam consists of 'only PC beams', it is difficult to construct facilities such as electric wires, but in the construction method according to the present invention, such facility work becomes easy and simple.

[PC 기둥과 제3 지지판 및 현장타설 콘크리트로 이루어지는 기둥][Pillar composed of PC column, third support plate, and cast-in-place concrete]

도 12a~12c는 각각 본 발명에 따라 시공된 기둥을 보여주는 평단면도이다. 12a to 12c are plan cross-sectional views each showing a column constructed according to the present invention.

도면에 나타난 바와 같이, 상기 기둥(300)은 두 개의 단위 PC(precast concrete) 기둥(312)과, 두 개의 단위 PC기둥(312)을 연결하도록 설치된 두 개의 제3 지지판(340) 및, 두 개의 단위 PC기둥(312)과 두 개의 제3 지지판(340)에 의해 둘러싸인 공간에 타설된 콘크리트(도면에 미도시)를 포함한다. 그리고, 도면에는 도시되지 않았지만 철근 등이 기둥에 포함될 수 있다. As shown in the drawing, the pillar 300 is two unit PC (precast concrete) pillars 312 and two third support plates 340 installed to connect the two unit PC pillars 312, and two It includes concrete (not shown in the drawing) poured into the space surrounded by the unit PC column 312 and the two third support plates 340 . In addition, although not shown in the drawings, reinforcing bars and the like may be included in the column.

단위 PC기둥(312)은 소정 간격으로 이격되도록 수직으로 설치된다. 바람직하게, 단위 PC기둥(312) 중에서 맞은편 단위 PC기둥(312)과 서로 마주보는 면에는 홈(322)이 형성된다. 상기 홈(322)은 단위 PC기둥(312)의 길이방향을 따라 연속적으로 길게 연장된다. 그리고, 홈(322)의 양측 끝단에는 턱(324)이 형성되며, 이 턱(324)은 현장에서 콘크리트가 타설될 때 제3 지지판(340)을 지지한다. 이에 따라, 단위 PC기둥(312)의 폭 보다 제3 지지판(340) 사이의 폭이 좁고, 현장 타설 콘크리트와 제3 지지판(340)에 의해 형성되는 RC 기둥 부분의 폭도 단위 PC기둥(312)의 폭 보다 좁다. The unit PC pillars 312 are vertically installed so as to be spaced apart at a predetermined interval. Preferably, a groove 322 is formed on the opposite side of the unit PC column 312 and the opposite side of the unit PC column 312 . The groove 322 is continuously extended along the longitudinal direction of the unit PC column 312 . And, at both ends of the groove 322, jaws 324 are formed, and the jaws 324 support the third support plate 340 when concrete is poured in the field. Accordingly, the width between the third support plate 340 is narrower than the width of the unit PC column 312, and the width of the RC column portion formed by the cast-in-place concrete and the third support plate 340 is also the width of the unit PC column 312. narrower than the width

도 12d는 기둥의 변형예를 보여주는 평단면도이다. 상기 기둥(300)은 홈(322)이 단위 PC 기둥(312)의 모서리에 형성되었다는 점을 제외하면 상기 기둥과 동일하다. 12D is a plan sectional view showing a modified example of the column. The pillar 300 is the same as the pillar except that the groove 322 is formed in the corner of the unit PC pillar 312 .

한편, 단위 PC기둥(312)과 제3 지지판(340)이 설치 완료된 후, 현장 콘크리트가 타설될 부분에 전기선, 수도관, 배수관, 오수관, 환기관 등 중에서 적어도 어느 하나를 설치할 수 있다. 기둥이 PC기둥'만'으로 이루어지는 경우에는 전기선 등의 설비 공사를 하기가 어려웠으나, 본 발명에 따른 시공방법에서는 이러한 설비공사가 쉽고 단순해진다. On the other hand, after the installation of the unit PC column 312 and the third support plate 340 is completed, at least one of an electric wire, a water pipe, a drain pipe, a sewage pipe, a ventilation pipe, etc. can be installed in the part where the on-site concrete is to be poured. When the pillar is made of 'only PC pillars', it is difficult to construct facilities such as electric wires, but in the construction method according to the present invention, such facility work becomes easy and simple.

100 : 복합 와이드 합성 구조를 갖는 슬래브
110 : PC 슬래브 120 : PC 슬래브의 본체
122 : 걸침턱 124 : 물 유도홈
130 : PC 슬래브의 리브 132 : 전단 철근
134 : 철근 140 : 제1 지지판
150 : 현장타설 콘크리트부
200 : 복합 와이드 합성 구조를 갖는 보
210 : PC 보 212 : 단위 PC보
214 : 제1 계단턱 215 : 단면 감소부
217 : 제2 계단턱 218 : 제3 계단턱
219 : 관통공 240 : 제2 지지판
242 : 거푸집 244 : 걸림턱
300 : 복합 와이드 합성 구조를 갖는 기둥
312 : 단위 PC 기둥 322 : 홈
324 : 턱 340 : 제3 지지판
100: slab with composite wide composite structure
110: PC slab 120: PC slab body
122: guiding jaw 124: water guide groove
130: rib of PC slab 132: shear reinforcement
134: reinforcing bar 140: first support plate
150: cast-in-place concrete part
200: Beam with composite wide composite structure
210: PC beam 212: unit PC beam
214: first stair step 215: reduced section
217: second stairway 218: third stairway
219: through hole 240: second support plate
242: formwork 244: jamming jaw
300: a column with a composite wide composite structure
312: unit pc pillar 322: groove
324: jaw 340: third support plate

Claims (10)

(a) 공사 현장에서, PC 슬래브(precast concrete slab, 110)를 소정 간격으로 PC 보(210)에 설치하는 단계;
(b) PC 슬래브(110) 사이에 제1 지지판(140)을 설치하는 단계; 및,
(c) PC 슬래브(110)와 제1 지지판(140) 위에 현장 철근을 배근하고 콘크리트를 타설하는 단계;를 포함하고,
PC 슬래브(110)는,
본체(120);
본체(120)의 폭방향 양쪽 단부에서 아래로 형성된 리브(130); 및,
본체(120)의 폭방향 양쪽 단부에 형성된 걸침턱(122);을 포함하고,
제1 지지판(140)의 단부는 걸침턱(122)에 설치되며,
PC 슬래브(110)는 리브(130)의 상단에서 외측으로 형성된 날개 부분을 갖지 않고, 상기 (c) 단계에서 제1 지지판(140) 위에 타설된 콘크리트에 의해 본체(120)의 폭방향 양측의 날개 부분이 형성되며,
PC보(210)는 두 개의 단위 PC보(212)로 이루어지고,
상기 (a) 단계의 이전에,
(a1) 두 개의 단위 PC보(212)를 소정 간격으로 이격되도록 설치하는 단계; 및,
(a2) 두 개의 단위 PC보(212) 사이에 제2 지지판(240)을 설치하는 단계;를 포함하고,
상기 (c) 단계는 제2 지지판(240)과 PC보(210) 위에 현장 콘크리트를 타설하는 것을 포함하며,
단위 PC보(212)의 양쪽 단부에서 두 개의 단위 PC보(212)의 서로 마주보는 면에는 제1 계단턱(214)이 형성되고, 제2 지지판(240)은 제1 계단턱(214)에 설치되며, 이에 따라 단위 PC보(212)의 양쪽 단부는 중앙 부분 보다 현장에서 타설된 콘크리트의 두께가 더 두꺼운 것을 특징으로 하는, 지지판을 이용한 프리캐스트 콘크리트 와이드 복합구조의 시공방법.
(a) at the construction site, installing a PC slab (precast concrete slab, 110) to the PC beam 210 at predetermined intervals;
(b) installing a first support plate 140 between the PC slabs 110; and,
(c) reinforcing on-site reinforcing bars on the PC slab 110 and the first support plate 140 and pouring concrete; including,
PC slab 110,
body 120;
Ribs 130 formed downward at both ends of the body 120 in the width direction; and,
Including;
The end of the first support plate 140 is installed on the protrusion 122,
The PC slab 110 does not have a wing portion formed outward from the upper end of the rib 130, and the wings on both sides of the width direction of the main body 120 by the concrete poured on the first support plate 140 in step (c). part is formed
PC beam 210 consists of two unit PC beams 212,
Before step (a),
(a1) installing two unit PC beams 212 to be spaced apart at a predetermined interval; and,
(a2) installing the second support plate 240 between the two unit PC beams 212;
The step (c) includes pouring on-site concrete on the second support plate 240 and the PC beam 210,
At both ends of the unit PC beam 212 , a first step 214 is formed on the opposite surfaces of the two unit PC beams 212 , and the second support plate 240 is on the first step 214 . Installation method of precast concrete wide composite structure using a support plate, characterized in that both ends of the unit PC beam 212 have a thicker thickness of concrete poured on site than the central part.
삭제delete 제1항에 있어서,
걸침턱(122)에는 물 유도홈(124)이 형성되고, 물 유도홈(124)은 PC슬래브(110)의 길이방향을 따라 길게 형성되되 제1 지지판(140)으로부터 아래쪽으로 소정 간격으로 이격되고,
제1 지지판(140) 또는 PC 슬래브(110)를 타고 흘러내린 물이 물 유도홈(124)을 통해서 이동되는 것을 특징으로 하는, 지지판을 이용한 프리캐스트 콘크리트 와이드 복합구조의 시공방법.
According to claim 1,
A water guide groove 124 is formed in the crossing sill 122, and the water guide groove 124 is formed long along the longitudinal direction of the PC slab 110 and is spaced downward from the first support plate 140 at a predetermined interval. ,
A method of constructing a precast concrete wide composite structure using a support plate, characterized in that the water flowing down on the first support plate 140 or the PC slab 110 is moved through the water guide groove 124 .
삭제delete 삭제delete 삭제delete 제1항에 있어서,
단위 PC보(212)의 중앙 부분에서 단면의 외측에는 제2 계단턱(217)이 형성되고 단면의 내측에는 제3 계단턱(218)이 형성되며,
PC 슬래브(110)는 제2 계단턱(217)에 설치되고 제2 지지판(240)은 제3 계단턱(218)에 설치되며,
제2,3 계단턱(217)(218)이 연결하여 통하도록 관통공(219)이 단위 PC보(212)의 상단에 형성되고, PC 슬래브(110)의 철근이 관통공(219)을 통하여 맞은편 PC 슬래브(110)에 연결되는 것을 특징으로 하는, 지지판을 이용한 프리캐스트 콘크리트 와이드 복합구조의 시공방법.
According to claim 1,
In the central part of the unit PC beam 212, a second step 217 is formed on the outside of the cross-section, and a third step 218 is formed on the inside of the cross-section,
The PC slab 110 is installed on the second step 217 and the second support plate 240 is installed on the third step 218 ,
A through hole 219 is formed at the upper end of the unit PC beam 212 so that the second and third step steps 217 and 218 are connected and communicated, and the reinforcing bar of the PC slab 110 is passed through the through hole 219 . A method of constructing a precast concrete wide composite structure using a support plate, characterized in that it is connected to the opposite PC slab (110).
제1항에 있어서,
PC보(210)는 기둥(300)에 설치되고,
기둥(300)은,
소정 간격으로 이격되도록 수직으로 설치된 두 개의 단위 PC기둥(312); 및
두 개의 단위 PC기둥(312)을 연결하도록 설치된 두 개의 제3 지지판(340);을 포함하고,
단위 PC보(212)는 단위 PC기둥(312)에 설치되며,
두 개의 단위 PC기둥(312)과 두 개의 제3 지지판(340)은 내부공간을 형성하며, 상기 내부공간에는 현장 콘크리트가 타설되는 것을 특징으로 하는, 지지판을 이용한 프리캐스트 콘크리트 와이드 복합구조의 시공방법.
According to claim 1,
PC beam 210 is installed on the pillar 300,
The pillar 300 is
Two unit PC pillars 312 vertically installed to be spaced apart at a predetermined interval; and
Includes; two third support plates 340 installed to connect the two unit PC pillars 312;
The unit PC beam 212 is installed on the unit PC column 312,
The two unit PC pillars 312 and the two third support plates 340 form an inner space, and the site concrete is poured into the inner space. A method of constructing a precast concrete wide composite structure using a support plate, characterized in that .
제8항에 있어서,
단위 PC기둥(312) 중에서 맞은 편 단위 PC기둥과 마주보는 면에는 홈(322)이 형성되고, 홈(322)의 양쪽 끝단에는 턱(324)이 형성되며, 제3 지지판(340)은 턱(324)에 의해 지지되는 것을 특징으로 하는, 지지판을 이용한 프리캐스트 콘크리트 와이드 복합구조의 시공방법.
9. The method of claim 8,
A groove 322 is formed on the side facing the opposite unit PC column among the unit PC columns 312, and jaws 324 are formed at both ends of the groove 322, and the third support plate 340 is a jaw ( 324), characterized in that supported by, the construction method of the precast concrete wide composite structure using a support plate.
제9항에 있어서,
상기 (b) 단계와 (c) 단계 사이에, 현장 콘크리트가 타설될 부분에 전기선, 수도관, 배수관, 환기관 중에서 적어도 어느 하나를 설치하는 것을 특징으로 하는, 지지판을 이용한 프리캐스트 콘크리트 와이드 복합구조의 시공방법.
10. The method of claim 9,
Between the steps (b) and (c), the construction of a precast concrete wide composite structure using a support plate, characterized in that at least one of an electric wire, a water pipe, a drain pipe, and a ventilation pipe is installed in the part where the on-site concrete is to be poured Way.
KR1020200046929A 2020-04-17 2020-04-17 Construction methods of wide precast concrete composite structure using support plate KR102349462B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020200046929A KR102349462B1 (en) 2020-04-17 2020-04-17 Construction methods of wide precast concrete composite structure using support plate

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020200046929A KR102349462B1 (en) 2020-04-17 2020-04-17 Construction methods of wide precast concrete composite structure using support plate

Publications (2)

Publication Number Publication Date
KR20210128808A KR20210128808A (en) 2021-10-27
KR102349462B1 true KR102349462B1 (en) 2022-01-10

Family

ID=78286950

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020200046929A KR102349462B1 (en) 2020-04-17 2020-04-17 Construction methods of wide precast concrete composite structure using support plate

Country Status (1)

Country Link
KR (1) KR102349462B1 (en)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101032104B1 (en) * 2011-03-14 2011-05-02 현대산업개발 주식회사 Double tee slab, parking concrete framework of building using the double-tee slabs and methode there of
JP2011219929A (en) * 2010-04-05 2011-11-04 Shimizu Corp Earthquake resisting party wall and method for constructing the same
KR101576215B1 (en) * 2014-06-12 2015-12-11 신우콘크리트산업 주식회사 Prefabricated precast concrete girder for building construction
KR102080594B1 (en) * 2018-04-17 2020-02-24 염경수 Couple girder

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05340015A (en) * 1992-06-08 1993-12-21 Supankuriito Corp:Kk Concrete floor structure
KR100544368B1 (en) * 2004-01-16 2006-01-23 삼성물산 주식회사 Precast transfer girder and method for constructing a structure by using of it

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011219929A (en) * 2010-04-05 2011-11-04 Shimizu Corp Earthquake resisting party wall and method for constructing the same
KR101032104B1 (en) * 2011-03-14 2011-05-02 현대산업개발 주식회사 Double tee slab, parking concrete framework of building using the double-tee slabs and methode there of
KR101576215B1 (en) * 2014-06-12 2015-12-11 신우콘크리트산업 주식회사 Prefabricated precast concrete girder for building construction
KR102080594B1 (en) * 2018-04-17 2020-02-24 염경수 Couple girder

Also Published As

Publication number Publication date
KR20210128808A (en) 2021-10-27

Similar Documents

Publication Publication Date Title
US9797138B2 (en) Constructive system and method of construction thereof
WO2007011127A1 (en) Precast stairway system, unit structure thereof, and method of constructing stairway system using the same
KR101101204B1 (en) Cantilever of slab for steel box bridge using steel supporter and the method thereof
CN111411687A (en) Novel assembly system
CN207812741U (en) Pre-manufactured steel structure overlapped shear wall
KR20160039855A (en) Construction methods of precast concrete slab having its connection part being concealed by coupled ribs and, precast concrete slab used therefor
KR20120019152A (en) Prestressed precast concrete composite beam and manufacture methode for there of and construction methode for there of
KR101395114B1 (en) Precast panel with corrugated steel web psc girder slab structure
CN108316150B (en) Construction system and construction method for main tower and steel anchor beam of cable-stayed bridge
CN104032855B (en) Assembled cross mixing coupled wall and construction method thereof
KR102349462B1 (en) Construction methods of wide precast concrete composite structure using support plate
KR100639153B1 (en) Slab Structure using Precast Concrete Slab Panel with Lateral Load Resistancy
KR101036177B1 (en) Method for constructing building using PRC integrating method
KR100340115B1 (en) T-shape PC slab dap end and method for constructing structure using the same
KR101527752B1 (en) Construction method of prestressed composite girder bridge
KR20090075484A (en) Preflex composite girder bridge coupled width composite girder and method thereof
CN106032705A (en) Integrated casting molding construction method of reinforced concrete floor system
CN213710154U (en) Steel rib concrete prefabricated staircase
CN109137757A (en) A kind of anti-buckling structure of large span box girder with corrugated steel webs and construction method
KR100791991B1 (en) Temporary bridge consruction method using composite slab girder
KR102267643B1 (en) Inverse Tee PSC Girder Prefabricated With Top Saddle PC blocks And Slab Construction Method Using Thereof
CN104047380B (en) Assembled girder steel seam T-shaped mixing coupled wall and construction method thereof
KR20030063962A (en) Improved T-shape PC Slab and Method for Constructing Structure Using the Same
CN105908705A (en) Prefabricated pretensioned prestressed underground continuous wall and construction method thereof
KR101004221B1 (en) One Way Waffle Slab System Continued by Post-tensioning and Post-tensioning method of the same

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant