KR102316011B1 - Construction method of sheathing temporary facility - Google Patents

Construction method of sheathing temporary facility Download PDF

Info

Publication number
KR102316011B1
KR102316011B1 KR1020190063409A KR20190063409A KR102316011B1 KR 102316011 B1 KR102316011 B1 KR 102316011B1 KR 1020190063409 A KR1020190063409 A KR 1020190063409A KR 20190063409 A KR20190063409 A KR 20190063409A KR 102316011 B1 KR102316011 B1 KR 102316011B1
Authority
KR
South Korea
Prior art keywords
installing
ground
pile
retaining wall
flange
Prior art date
Application number
KR1020190063409A
Other languages
Korean (ko)
Other versions
KR20200137297A (en
Inventor
김재승
Original Assignee
김재승
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김재승 filed Critical 김재승
Priority to KR1020190063409A priority Critical patent/KR102316011B1/en
Publication of KR20200137297A publication Critical patent/KR20200137297A/en
Application granted granted Critical
Publication of KR102316011B1 publication Critical patent/KR102316011B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2220/00Temporary installations or constructions
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2450/00Gaskets
    • E02D2450/10Membranes
    • E02D2450/105Membranes impermeable
    • E02D2450/106Membranes impermeable for liquids
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/40Miscellaneous comprising stabilising elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

본 발명은 흙막이 가시설의 시공방법에 관한 것이다. 본 발명의 일실시 예에 따른 흙막이 가시설의 시공방법은 (a) 경계선의 안쪽으로 터파기가 이루어진 지반의 외곽에 상기 경계선을 따라 횡단면이 직사각형인 제1 플랜지 및 상기 제1 플랜지보다 폭이 좁게 형성되어 횡단면이 정사각형인 제2 플랜지가 연결부를 통해 일체로 연결되어 구성된 측면말뚝의 하단부를 근입하여 등 간격으로 배열하는 단계; (b) 상기 제1,2 플랜지 사이에 형성된 홈부를 통해 측면말뚝 사이에 직사각형의 토류판을 적층 설치하여 흙막이벽체를 형성하는 단계; (c) 상기 측면말뚝의 내벽에 길이방향을 따라 보걸이를 설치하고, 각각의 상기 보걸이의 상부에 단면이 H형으로 구성된 지보공띠장을 수평방향으로 고정설치하는 단계; (d) 각각의 상기 지보공띠장에 버팀보를 설치하여 흙막이벽체의 기립상태를 보강하고, 상기 지반의 각 코너부분은 각각의 지보공띠장에 사보강재를 설치하여 보강하는 단계; 및 (e) 상기 흙막이벽체의 외측 지반에 차수공법을 통해 약액을 주입하여 그라우팅을 하는 단계를 포함한다.The present invention relates to a method of constructing a temporary retaining facility. The construction method of the temporary retaining facility according to an embodiment of the present invention is (a) a first flange having a rectangular cross section along the boundary line on the outskirts of the ground excavated inside the boundary line, and the width is narrower than the first flange. A second flange having a square cross section is integrally connected through a connecting portion and arranged at equal intervals by piercing the lower end of the side pile; (b) forming a retaining wall by laminating a rectangular earth plate between side piles through a groove formed between the first and second flanges; (c) installing a beam hanger along the longitudinal direction on the inner wall of the side pile, and fixing and installing a jibogong wale having an H-shaped cross section on each of the beam hangers in the horizontal direction; (d) reinforcing the standing state of the retaining wall by installing braces in each of the jibogong bands, and reinforcing each corner portion of the ground by installing a saber steel on each jibogong band; and (e) grouting by injecting a chemical solution into the ground outside of the retaining wall through a water blocking method.

Figure R1020190063409
Figure R1020190063409

Description

흙막이 가시설의 시공방법{CONSTRUCTION METHOD OF SHEATHING TEMPORARY FACILITY}Construction method of temporary retaining facility {CONSTRUCTION METHOD OF SHEATHING TEMPORARY FACILITY}

본 발명은 흙막이 가시설의 시공방법에 관한 것이다. 더욱 상세하게는 지반을 굴착할 때 주위지반의 침하나 붕괴를 방지하는 흙막이 가시설을 시공하기 위한 시공방법에 관한 것이다.The present invention relates to a method of constructing a temporary retaining facility. More particularly, it relates to a construction method for constructing a temporary retaining facility that prevents subsidence or collapse of the surrounding ground when excavating the ground.

예컨대, 흙막이 가시설은 지반을 굴착할 때 주위의 지반이 침하나 붕괴하는 것을 방지할 목적으로 만드는 일종의 시설물로서, 토압 등에 저항하는 흙막이벽체와 이를 지탱하는 지보공을 포함하고 있다.For example, a temporary retaining facility is a kind of facility made for the purpose of preventing subsidence or collapse of the surrounding ground when excavating the ground.

이러한 흙막이 가시설은 지보공법으로 앵커를 이용하는 앵커공법 또는 H-파일이나 강관을 이용한 버팀보 공법을 적용하고 있다.For these temporary retaining facilities, the anchor method using an anchor or the H-pillar or steel pipe is applied as the support method.

상기 버팀보 공법은 흙막이벽체 사이에 버팀보를 설치하여 버팀보의 양단이 토압에 저항하게 되는 시공방법이다. 이러한 버팀보 공법에 따르면 버팀보는 압축력을 받게 된다. 따라서 버팀보가 충분한 압축 강성을 갖지 못하는 경우에는 압축파괴나 좌굴파괴가 발생할 수 있다.The beotimbo construction method is a construction method in which both ends of the beotimbo are installed between retaining walls to resist earth pressure. According to this bracing method, the bracing is subjected to compressive force. Therefore, compression failure or buckling failure may occur if the brace does not have sufficient compressive rigidity.

한편, 흙막이벽체를 시공하기 위한 종래기술에 따른 대표적인 시공방법은 현장 타설 콘크리트말뚝(CIP)이나 피에이치씨(PHC) 파일을 사용하여 흙막이벽체를 시공하는 것이다.On the other hand, a typical construction method according to the prior art for constructing a retaining wall is to construct a retaining wall using a cast-in-place concrete pile (CIP) or a PHC (PHC) pile.

즉 현장 타설 콘크리트말뚝(CIP)은 오거장비를 이용해 지반을 천공하여 H-파일을 일정 간격으로 인접대지경계선이나 도로경계선을 따라서 근입 설치하고 그 사이에는 같은 방법으로 천공하여 콘크리트말뚝(CIP)을 설치한 후 철근망을 조립하여 삽입하고, 차수 공법을 통해 시멘트 모르타르 또는 콘크리트를 현장 타설하여 측면말뚝을 만들어 흙막이벽체를 시공하는 방법이다.In other words, for cast-in-place concrete piles (CIP), the ground is drilled using auger equipment, and H-piles are installed at regular intervals along the adjacent land boundary line or road boundary line. It is a method to construct a retaining wall by assembling and inserting a reinforcing bar network, then pouring cement mortar or concrete on-site through the water-reinforcement method to make side piles.

또한, 상기 피에이치씨(PHC) 파일을 이용한 흙막이벽체의 시공은 피에이치씨(PHC) 파일을 인접대지경계선이나 도로경계선에 연속해서 설치하여 흙막이벽체를 만들고, 상기 흙막이벽체에 브라켓과 지보공띠장 등을 용접 고정한 후 차수 공법을 통해 그라우팅을 하는 방법으로 시공하고 있다.In addition, in the construction of a retaining wall using the PHC pile, the PHC file is continuously installed on the adjacent land boundary line or road boundary line to make a retaining wall, and a bracket and a support band are welded to the retaining wall. After fixing it, it is constructed by grouting through the water-order method.

그러나 종래기술에 따른 현장 타설 콘크리트말뚝(CIP)이나 피에이치씨(PHC) 파일을 이용한 흙막이벽체는 횡단면이 원형인 콘크리트말뚝(CIP)이나 피에이치씨(PHC) 파일의 직경으로 인하여 확보할 수 있는 대지면적이 줄어들게 되어 결과적으로 주택이나 건물을 신축할 수 있는 건축면적이 줄어드는 문제점이 있다.However, the retaining wall using cast-in-place concrete piles (CIP) or PHC (PHC) piles according to the prior art has a circular cross section of concrete piles (CIP) or PHC (PHC) piles due to the diameter of the land area that can be secured As a result, there is a problem in that the building area that can be constructed for a house or building is reduced.

대한민국 공개특허공보 제10-2017-0005991호Republic of Korea Patent Publication No. 10-2017-0005991

본 발명의 목적은 주택이나 건물의 신축시 경계선으로부터 대지면적을 좀 더 용이하게 확보 가능할 수 있도록 한 흙막이 가시설의 시공방법을 제공하는 데 있다.An object of the present invention is to provide a method of constructing a temporary retaining facility so that it is possible to more easily secure a site area from a boundary line when a house or a building is constructed.

상기 과제를 해결하기 위하여,In order to solve the above problem,

본 발명의 일실시 예에 따른 흙막이 가시설의 시공방법은 (a) 경계선의 안쪽으로 터파기가 이루어진 지반의 외곽을 따라 횡단면이 직사각형인 제1 플랜지 및 상기 제1 플랜지보다 폭이 좁게 형성되어 횡단면이 정사각형인 제2 플랜지가 연결부를 통해 일체로 연결되어 구성된 측면말뚝의 하단부를 근입하여 등 간격으로 배열하는 단계;The construction method of the temporary retaining facility according to an embodiment of the present invention is (a) a first flange having a rectangular cross-section along the perimeter of the ground excavated inside the boundary line, and a width narrower than the first flange, so that the cross-section is square The second flange is integrally connected through the connecting portion and arranged at equal intervals by rooting the lower end of the side piles;

(b) 상기 제1,2 플랜지 사이에 형성된 홈부를 통해 측면말뚝 사이에 직사각형의 토류판(Timber)을 적층 설치하여 흙막이벽체를 형성하는 단계;(b) forming a retaining wall by laminating a rectangular earth plate (Timber) between the side piles through the groove formed between the first and second flanges;

(c) 상기 측면말뚝의 내벽에 길이방향을 따라 보걸이를 설치하고, 각각의 상기 보걸이의 상부에 단면이 H형으로 구성된 지보공띠장(Wale)을 수평방향으로 고정설치하는 단계;(c) installing a beam hanger along the longitudinal direction on the inner wall of the side pile, and fixing and installing a wale with an H-shaped cross section on the upper portion of each of the beam hangers in the horizontal direction;

(d) 각각의 상기 지보공띠장에 버팀보(Strut)를 설치하여 흙막이벽체의 기립상태를 보강하고, 상기 지반의 각 코너부분은 각각의 지보공띠장에 사보강재(Corner Strut)를 설치하여 보강하는 단계; 및(d) reinforcing the standing state of the retaining wall by installing struts in each of the support beams, and each corner part of the ground is reinforced by installing a corner strut in each of the support beams; and

(e) 상기 흙막이벽체의 외측 지반에 차수공법을 통해 약액을 주입하여 그라우팅을 하는 단계;(e) grouting by injecting a chemical solution to the ground outside of the retaining wall through a water blocking method;

를 포함할 수 있다.may include.

또한, 본 발명의 일실시 예에 따른 흙막이 가시설의 시공방법에 있어서, 상기 측면말뚝은 연결부와 만나는 제1,2 플랜지의 내면이 경사면으로 형성되어 홈부가 사다리꼴의 형태를 갖도록 형성될 수 있다.In addition, in the construction method of the temporary retaining facility according to an embodiment of the present invention, the side pile may be formed so that the inner surface of the first and second flanges meeting the connection part is formed as an inclined surface so that the groove part has a trapezoidal shape.

또한, 본 발명의 일실시 예에 따른 흙막이 가시설의 시공방법에 있어서, 상기 측면말뚝은 제2 플랜지가 경계선을 향해 배치될 수 있다.In addition, in the construction method of the temporary retaining facility according to an embodiment of the present invention, the side pile may be disposed toward the second flange boundary line.

또한, 본 발명의 일실시 예에 따른 흙막이 가시설의 시공방법에 있어서, 상기 측면말뚝은 흙막이벽체의 해체시 철거하여 재사용 가능하도록 지반에 근입되는 하단부에 측면말뚝의 외형과 대응하는 형상의 필링시트(Peeling sheet)를 씌운 후에 상단부가 대지경계선보다 돌출되도록 상기 지반에 기립 설치될 수 있다.In addition, in the construction method of the temporary retaining facility according to an embodiment of the present invention, the side pile is a peeling sheet of a shape corresponding to the external shape of the side pile at the lower end protruding into the ground so that it can be removed and reused when the retaining wall is dismantled ( Peeling sheet) may be installed standing up on the ground so that the upper end protrudes from the site boundary line after covering.

또한, 본 발명의 일실시 예에 따른 흙막이 가시설의 시공방법에 있어서, 상기 (d) 단계는 사보강재와 버팀보의 말단에 스크루잭(Screw Jack)을 설치하여 시공하되, 상기 사보강재는 스크루잭에 앵글잭(Angle Jack)을 설치하여 상기 앵글잭을 통해 지보공띠장에 설치될 수 있다.In addition, in the construction method of the temporary retaining facility according to an embodiment of the present invention, the step (d) is constructed by installing a screw jack at the end of the saber steel and the brace, but the saber steel is on the screw jack. By installing an angle jack, it can be installed in a jibogong belt through the angle jack.

또한, 본 발명의 일실시 예에 따른 흙막이 가시설의 시공방법에 있어서, 상기 지반의 중심부에 H-파일로 구성된 중간말뚝(Post Pile)의 하단부를 근입하여 기립 설치하고, 상기 중간말뚝에 피스 브래킷(Piece Bracket)을 설치하여 상기 피스 브래킷의 상부에 H-빔(H-Beam)으로 구성된 수평보강재를 설치하는 단계;In addition, in the construction method of the temporary retaining facility according to an embodiment of the present invention, the lower end of the intermediate pile (Post Pile) composed of an H-pile is erected and installed in the center of the ground, and the piece bracket ( Installing a piece bracket) to install a horizontal reinforcement composed of an H-beam (H-Beam) on the upper portion of the piece bracket;

를 더 포함할 수 있다.may further include.

또한, 본 발명의 일실시 예에 따른 흙막이 가시설의 시공방법에 있어서, 상기 중간말뚝의 표면에 수팽창성지수제를 통해 방수층을 형성하여 방수처리할 수 있다.In addition, in the construction method of the temporary retaining facility according to an embodiment of the present invention, it is possible to perform waterproofing treatment by forming a waterproofing layer on the surface of the intermediate pile through a water expansible water agent.

또한, 본 발명의 일실시 예에 따른 흙막이 가시설의 시공방법에 있어서, 상기 (e) 단계는 SGR(Space Grouting Rocket System) 공법을 통해 진행될 수 있다.In addition, in the method of constructing a temporary retaining facility according to an embodiment of the present invention, the step (e) may be performed through a Space Grouting Rocket System (SGR) method.

이러한 해결 수단은 첨부된 도면에 의거한 다음의 발명을 실시하기 위한 구체적인 내용으로부터 더욱 명백해질 것이다.These solutions will become more apparent from the detailed description for carrying out the following invention based on the accompanying drawings.

이에 앞서, 본 명세서 및 청구범위에 사용된 용어나 단어는 통상적이고 사전적인 의미로 해석되어서는 아니 되며, 발명자가 그 자신의 발명을 가장 최선의 방법으로 설명하기 위해 용어의 개념을 적절하게 정의할 수 있다는 원칙에 입각하여 본 발명의 기술적 사상에 부합되는 의미와 개념으로 해석되어야만 한다.Prior to this, the terms or words used in the present specification and claims should not be construed in their ordinary and dictionary meanings, and the inventor may properly define the concept of the term in order to best describe his invention. It should be interpreted as meaning and concept consistent with the technical idea of the present invention based on the principle that it is possible.

본 발명의 일실시 예에 따르면, 종래기술의 횡단면이 원형인 측면말뚝보다 더욱 경계선에 가깝게 측면말뚝을 설치하는 방법으로 흙막이 가시설을 시공 가능함으로써, 대지면적을 좀 더 용이하게 확보할 수 있어 결과적으로, 건축면적을 상대적으로 크게 확보할 수 있는 효과가 있다. 따라서 대지면적이 적은 땅에 유익하게 활용 가능하다.According to an embodiment of the present invention, it is possible to construct a temporary retaining facility by a method of installing side piles closer to the boundary line than the side piles having a circular cross section of the prior art, so that it is possible to more easily secure a site area, as a result , it has the effect of securing a relatively large building area. Therefore, it can be used advantageously in land with a small land area.

또한, 본 발명의 일실시 예에 따르면, 종래기술의 H-파일로 구성된 측면말뚝보다 작용 응력이 우수하여 단면력이 향상된 측면말뚝을 통해 흙막이벽체를 구성함으로써, 흙막이 가시설의 신뢰성을 효과적으로 향상시킬 수 있다.In addition, according to an embodiment of the present invention, by composing the retaining wall through the side piles with improved cross-sectional force due to superior working stress than the side piles made of H-piles of the prior art, the reliability of the temporary retaining facilities can be effectively improved. .

도 1은 본 발명의 일실시 예에 따른 흙막이 가시설의 시공방법을 나타내 보인 평면도.
도 2는 본 발명의 일실시 예에 따른 흙막이 가시설의 시공방법을 나타내 보인 단면도.
도 3은 본 발명의 일실시 예에 따른 측면말뚝과 필링시트를 분리하여 나타내 보인 사시도.
도 4는 본 발명의 일실시 예에 따른 흙막이벽체를 일부 확대하여 나타내 보인 사시도.
1 is a plan view showing a construction method of a temporary retaining facility according to an embodiment of the present invention.
Figure 2 is a cross-sectional view showing a construction method of a temporary retaining facility according to an embodiment of the present invention.
Figure 3 is a perspective view showing the side piles and the peeling sheet separated according to an embodiment of the present invention.
4 is a perspective view showing a partially enlarged retaining wall according to an embodiment of the present invention.

본 발명의 특이한 관점, 특정한 기술적 특징들은 첨부된 도면들과 연관되는 이하의 구체적인 내용과 일실시 예로부터 더욱 명백해 질 것이다. 본 명세서에서 각 도면의 구성요소들에 참조 부호를 부가함에 있어, 동일한 구성요소들에 대해서는 비록 다른 도면상에 표시되더라도 가능한 동일한 부호를 가지도록 하고 있음에 유의해야 한다. 또한, 본 발명의 일실시 예를 설명함에 있어, 관련된 공지 구성 또는 기능에 대한 구체적인 설명이 본 발명의 요지를 흐릴 수 있다고 판단되는 경우에는 그 상세한 설명은 생략한다.The specific aspects and specific technical features of the present invention will become more apparent from the following detailed description and embodiments in conjunction with the accompanying drawings. In the present specification, in adding reference numerals to the components of each drawing, it should be noted that the same components are given the same reference numerals as possible even if they are indicated on different drawings. In addition, in describing an embodiment of the present invention, if it is determined that a detailed description of a related well-known configuration or function may obscure the gist of the present invention, the detailed description thereof will be omitted.

또한, 본 발명의 구성요소를 설명하는 데 있어서, 제1, 제2, A, B, (a), (b) 등의 용어를 사용할 수 있다. 이러한 용어는 그 구성요소를 다른 구성 요소와 구별하기 위한 것일 뿐, 그 용어에 의해 해당 구성요소의 본질이나 차례 또는 순서 등이 한정되지 않는다. 어떤 구성요소가 다른 구성요소에 "연결", "결합" 또는 "접속"된다고 기재된 경우, 그 구성요소는 그 다른 구성요소에 직접적으로 연결되거나 또는 접속될 수 있지만, 각 구성요소 사이에 또 다른 구성요소가 "연결", "결합" 또는 "접속"될 수도 있다고 이해되어야 할 것이다.In addition, in describing the components of the present invention, terms such as first, second, A, B, (a), (b), etc. may be used. These terms are only for distinguishing the elements from other elements, and the essence, order, or order of the elements are not limited by the terms. When a component is described as being “connected”, “coupled” or “connected” to another component, the component may be directly connected to or connected to the other component, but another component may exist between each component. It should be understood that elements may be “connected,” “coupled,” or “connected.”

이하, 본 발명의 일실시 예를 첨부된 도면에 의거하여 구체적으로 설명하면 다음과 같다.Hereinafter, an embodiment of the present invention will be described in detail based on the accompanying drawings.

도 1 내지 4에서 보듯이, 본 발명의 일실시 예에 따른 흙막이 가시설의 시공방법은 먼저, 경계선(1)의 안쪽으로 터파기가 이루어진 지반(2)의 외곽에 상기 경계선(1)을 따라 측면말뚝(10)의 하단부(10a)를 근입하여 등 간격으로 배열하는 단계를 실시하게 된다. 상기 경계선(1)이란 인접대지경계선과 도로경계선을 포함하는 개념으로 해석되어야 한다.As shown in Figures 1 to 4, the construction method of the temporary retaining facility according to an embodiment of the present invention is first, along the boundary line (1) on the outside of the ground (2) excavated to the inside of the boundary line (1) side piles The step of arranging the lower end portion 10a of (10) at equal intervals is performed. The boundary line 1 should be interpreted as a concept including an adjacent land boundary line and a road boundary line.

여기서 상기 측면말뚝(10)은 흙막이 가시설 시공현장에서 통상적으로 사용하는 H-파일(H-Pile)과 유사한 형상이나 구조적으로 이를 개선한 구성으로서, 횡단면이 직사각형인 제1 플랜지(11) 및 상기 제1 플랜지(11)보다 폭이 좁게 형성되어 횡단면이 정사각형인 제2 플랜지(12)가 연결부(13)를 통해 일체로 연결되어 구성된다.Here, the side pile 10 has a shape similar to an H-Pile commonly used at the construction site for temporary retaining facilities, but a structurally improved configuration thereof, and a first flange 11 and the first flange 11 having a rectangular cross-section. The width of the first flange 11 is narrower than the second flange 12 having a square cross section is integrally connected through the connecting portion 13 is configured.

또한, 상기 측면말뚝(10)은 연결부(13)와 만나는 제1,2 플랜지(11)(12)의 내면이 경사면으로 형성되어 상기 제1,2 플랜지(11)(12) 사이에 형성되는 홈부(14)가 사다리꼴의 형태를 갖도록 형성될 수 있으며, 상기 제2 플랜지(12)가 경계선(1)을 향해 배치되는 방법으로 시공하게 된다.In addition, in the side pile 10, the inner surfaces of the first and second flanges 11 and 12 meeting the connection part 13 are formed as inclined surfaces, and a groove portion formed between the first and second flanges 11 and 12 is formed. (14) may be formed to have a trapezoidal shape, and the second flange 12 is constructed in such a way that it is disposed toward the boundary line (1).

예컨대, 상기 측면말뚝(10)은 다음과 같은 설계재원으로 실시될 수 있다.For example, the side pile 10 may be implemented with the following design resources.

Figure 112019055368483-pat00001
Figure 112019055368483-pat00001

또한, 상기 설계재원에 따른 측면말뚝(10)의 작용 응력은 다음과 같다.In addition, the working stress of the side pile 10 according to the design resource is as follows.

Figure 112019055368483-pat00002
Figure 112019055368483-pat00002

이러한 측면말뚝(10)의 최대모멘트와 최대전단력은 다음과 같다.The maximum moment and maximum shear force of these side piles 10 are as follows.

Figure 112019055368483-pat00003
Figure 112019055368483-pat00003

따라서 본 발명의 일실시 예에 따른 측면말뚝(10)은 구조개선을 통해 작용 응력, 즉 휨 응력, 압축 응력 및 전단 응력이 우수하여 단면력이 향상됨으로써, 이를 통해 구성되는 흙막이벽체(3) 및 이를 포함하는 흙막이 가시설의 신뢰성을 효과적으로 향상시킬 수 있다.Therefore, the side pile 10 according to an embodiment of the present invention is excellent in working stress, that is, bending stress, compressive stress and shear stress through structural improvement, so that the cross-sectional force is improved, and thus the retaining wall 3 and the It is possible to effectively improve the reliability of the temporary retaining facility including the

여기서 상기 흙막이벽체(3)를 해체하게 되면, 측면말뚝(10)은 철거하여 타현장에서 재사용하게 되는데, 상기 측면말뚝(10)을 지반(2)에서 쉽게 뽑아서 철거할 수 있도록 상기 지반(2)에 근입되는 하단부(10a)에 은박지로 실시되는 필링시트(10b)를 부착하거나 비닐 등의 합성수지로 모양을 만들어 상기 하단부(10a)에 씌운 후에 중장비를 통한 철거가 용이하도록 상단부(10c)가 대지경계선(4)보다 돌출되도록 기립 설치하게 된다.Here, when the retaining wall 3 is dismantled, the side piles 10 are removed and reused at other sites. After attaching a peeling sheet 10b made of silver foil to the lower end 10a, which is inserted into the (4) It is installed upright so that it protrudes from it.

예컨대, 도 3에서 보듯이, 본 발명의 일실시 예에 따른 필링시트(10b)는 측면말뚝(10)의 외형과 대응하는 형상으로 형성되어 상기 측면말뚝(10)의 하단부(10a)에 씌워서 사용하게 되며, 상기 하단부(10a)를 지반(2)에 근입시 함께 상기 지반(2)에 매립된다.For example, as shown in FIG. 3 , the peeling sheet 10b according to an embodiment of the present invention is formed in a shape corresponding to the external shape of the side pile 10 and is used by covering the lower end 10a of the side pile 10 . and is buried in the ground (2) together when the lower end (10a) is approached to the ground (2).

즉 상기 지반(2)에 측면말뚝(10)의 하단부(10a)를 근입시 필링시트(10b)가 함께 매립됨으로써, 중장비를 통한 상기 측면말뚝(10)의 철거시 필링시트(10b)는 지반(2)에 남고 상기 하단부(10a)는 인발되기 때문에 측면말뚝(10)을 쉽게 철거할 수 있게 되는 것이다.That is, when the lower end 10a of the side pile 10 is embedded in the ground 2, the peeling sheet 10b is buried together, and when the side pile 10 is removed through heavy equipment, the peeling sheet 10b is the ground ( 2) and the lower end portion (10a) is pulled out, so that the side piles (10) can be easily removed.

또한, 상기 필링시트(10b)는 내면에 윤활제를 도포하여 측면말뚝(10)의 철거시 하단부(10a)와의 미끄럼현상을 유발하여 상기 측면말뚝(10)을 용이하게 인발토록 할 수도 있다.In addition, the peeling sheet 10b may be easily drawn out by applying a lubricant to the inner surface of the side pile 10 to cause a sliding phenomenon with the lower end 10a when the side pile 10 is removed.

따라서 본 발명의 일실시 예에 따르면, 필링시트(10b)의 제공을 통해 측면말뚝(10)을 시공현장에서 쉽게 철거하여 타현장에서 재사용할 수 있게 됨으로써, 시공편리성을 효과적으로 향상시킬 수 있게 된다.Therefore, according to an embodiment of the present invention, by providing the peeling sheet 10b, the side pile 10 can be easily removed from the construction site and reused at other sites, thereby effectively improving the construction convenience. .

한편, 본 발명의 일실시 예에 따른 흙막이 가시설의 시공방법은 측면말뚝(10)의 시공이 완료되면, 도 4에서 보듯이, 제1,2 플랜지(11)(12) 사이에 형성된 홈부(14)를 통해 측면말뚝(10) 사이에 흙막이널 또는 흙막이판 등으로 지칭되는 직사각형의 토류판(20)을 적층 설치하여 흙막이벽체(3)를 형성하는 단계를 실시하게 된다.On the other hand, in the construction method of the temporary retaining facility according to an embodiment of the present invention, when the construction of the side pile 10 is completed, as shown in FIG. 4 , the groove portion 14 formed between the first and second flanges 11 and 12 . ), the step of forming the retaining wall 3 is carried out by stacking and installing a rectangular earth plate 20 referred to as a retaining board or a retaining plate between the side piles 10 .

여기서 상기 흙막이벽체(3)를 시공하기 전이나 직후에는 지반(2)의 중심부에 H-파일로 구성된 복수의 중간말뚝(60)을 기립 설치하게 되는데, 측면말뚝(10)과 마찬가지로 상기 중간말뚝(60)의 하단부를 지반(2)에 근입하여 기립 설치하게 된다.Here, before or immediately after construction of the retaining wall 3, a plurality of intermediate piles 60 composed of H-piles are erected in the center of the ground 2, and, like the side piles 10, the intermediate piles ( 60) and the lower end of the ground (2) is to be installed standing up.

또한, 상기 중간말뚝(60)은 예컨대, 실란트형지수제인 하이퍼 실러(Hyper Sealer)로 실시 가능한 수팽창성지수제를 지반(2)에 근입되는 하단부의 표면에 도포하여 방수층(60a)을 형성함으로써, 방수처리한 상태에서 시공이 이루어질 수 있다.In addition, the intermediate pile 60 is, for example, by applying a water-expandable water-expandable water agent that can be implemented with a sealant-type water-repellent agent, Hyper Sealer, to the surface of the lower end that is embedded in the ground 2 to form a waterproofing layer 60a, Construction can be done in a waterproofed state.

이러한 흙막이벽체(3)와 중간말뚝(60)의 설치가 완료되면, 측면말뚝(10)의 내벽에 길이방향을 따라 보걸이(30)를 배열 설치하고, 각각의 상기 보걸이(30)의 상부에 단면이 H형으로 구성된 지보공띠장(40)을 수평방향으로 용접하여 고정설치하는 단계를 실시하게 된다.When the installation of the retaining wall 3 and the intermediate pile 60 is completed, the beam hangers 30 are arranged along the longitudinal direction on the inner wall of the side pile 10, and the upper part of each of the beam hangers 30 is completed. A step of fixing and installing the jibogong belt length 40 having an H-shaped cross-section is performed by welding in the horizontal direction.

또한, 각각의 상기 지보공띠장(40)에 버팀보(50)를 설치하여 토압 등에 저항하는 흙막이벽체(3)를 지지토록 함으로써, 상기 흙막이벽체(3)의 기립상태를 보강하게 된다. 상기 버팀보(50)는 어느 하나의 일단에 스크루잭(52)을 설치하여 길이를 조절하면서 시공을 진행하게 된다.In addition, by installing the braces 50 in each of the support beams 40 to support the retaining wall 3 that resists earth pressure, etc., the standing state of the retaining wall 3 is reinforced. The beotimbo 50 is installed at one end of the screw jack 52 to adjust the length while the construction proceeds.

이에 부가하여 중간말뚝(60)에 피스 브래킷(62)을 설치하고, 상기 피스 브래킷(62)의 상부에 H-빔으로 구성된 수평보강재(61)를 설치하여 흙막이벽체(3)를 보강하는 단계를 실시하게 된다.In addition to this, the step of reinforcing the retaining wall 3 by installing the piece bracket 62 on the intermediate pile 60, and installing the horizontal reinforcement 61 composed of H-beams on the upper part of the piece bracket 62 will be carried out

여기서 지반(2)의 각 코너부분은 사보강재(51)를 통해 보강하게 되는데, 상기 사보강재(51)의 양단을 각각의 지보공띠장(40)에 설치함으로써, 토압 등에 저항하는 흙막이벽체(3)를 지지하게 된다.Here, each corner part of the ground (2) is reinforced through the yarn reinforcement material (51), and by installing both ends of the yarn reinforcement material (51) in each support ball belt (40), a retaining wall (3) to resist earth pressure, etc. will support

상기 사보강재(51)는 버팀보(50)와 동일하게 어느 하나의 일단에 스크루잭(52)을 설치하여 길이를 조절하되, 사선방향으로 설치되는 만큼, 각도 역시 조절할 수 있도록 상기 스크루잭(52)에 각도조절이 가능한 앵글잭(53)을 설치한 상태에서 시공하게 된다.The screw reinforcing material 51 adjusts the length by installing a screw jack 52 at one end in the same way as the brace 50, but the screw jack 52 so that the angle can be adjusted as much as it is installed in an oblique direction. It will be constructed in a state in which the angle jack (53) capable of angle adjustment is installed.

이러한 흙막이벽체(3)의 보강시공이 완료되면, 마지막으로 상기 흙막이벽체(3)의 외측 지반에 차수공법을 통해 약액을 주입하여 그라우팅을 하는 단계를 실시하게 된다.When the reinforcement construction of the retaining wall 3 is completed, finally, the step of grouting by injecting a chemical solution through the water blocking method into the ground outside the retaining wall 3 is performed.

예컨대, 상기 차수공법은 널리 알려진 공법의 하나인 SGR(Space Grouting Rocket System) 공법을 이용하게 되는데, 즉 주입관 말단에 로켓이 설치된 이중관을 이용하여 약액을 주입하여 그라우팅을 하게 된다.For example, the water blocking method uses the SGR (Space Grouting Rocket System) method, which is one of the widely known methods, that is, grouting is performed by injecting a chemical solution using a double tube in which a rocket is installed at the end of the injection tube.

따라서 본 발명의 일실시 예에 따르면, 경계선(1)으로부터 확보할 수 있는 대지면적을 종래기술에 따른 흙막이 가시설 시공방법보다 상대적으로 좀 더 확보 가능함으로써, 예컨대 주택이나 건물을 신축하기 위한 대지면적이 적은 땅에 유익하게 활용 가능하다.Therefore, according to an embodiment of the present invention, the land area that can be secured from the boundary line 1 can be secured relatively more than the temporary retaining facility construction method according to the prior art, so that, for example, the site area for constructing a house or building is It can be used advantageously on small land.

이상 본 발명을 일실시 예를 통하여 상세히 설명하였으나, 이는 본 발명을 구체적으로 설명하기 위한 것으로, 본 발명에 따른 흙막이 가시설의 시공방법은 이에 한정되지 않는다. 그리고 이상에서 기재된 "포함하다", "구성하다", 또는 "가지다", 등의 용어는 특별히 반대되는 기재가 없는 한 해당 구성요소가 내재될 수 있음을 의미하는 것이므로, 다른 구성요소를 제외하는 것이 아니라 다른 구성요소를 더 포함할 수 있는 것으로 해석되어야 하며, 기술적이거나 과학적인 용어를 포함한 모든 용어들은, 다르게 정의되지 않는 한, 본 발명이 속하는 기술 분야에서 통상의 지식을 가진 자에 의해 일반적으로 이해되는 것과 동일한 의미를 가진다.Although the present invention has been described in detail through one embodiment, this is for describing the present invention in detail, and the construction method of the temporary retaining facility according to the present invention is not limited thereto. And, terms such as "include", "comprise", or "have" described above mean that the component may be embedded unless otherwise stated, so excluding other components is It should be construed as being able to further include other components rather than other components, and all terms including technical or scientific terms are generally understood by those of ordinary skill in the art to which the present invention belongs, unless otherwise defined. has the same meaning as being

또한, 이상의 설명은 본 발명의 기술 사상을 예시적으로 설명한 것에 불과한 것으로서, 본 발명이 속하는 기술 분야에서 통상의 지식을 가진 자라면 본 발명의 본질적인 특성에서 벗어나지 않는 범위에서 다양한 수정 및 변형 가능하다. 따라서, 본 발명에 개시된 일실시 예들은 본 발명의 기술 사상을 한정하기 위한 것이 아니라 설명하기 위한 것이고, 이러한 일실시 예에 의하여 본 발명의 기술 사상의 범위가 한정되는 것은 아니다. 본 발명의 보호 범위는 아래의 청구범위에 의하여 해석되어야 하며, 그와 동등한 범위 내에 있는 모든 기술 사상은 본 발명의 권리범위에 포함되는 것으로 해석되어야 할 것이다.In addition, the above description is merely illustrative of the technical idea of the present invention, and various modifications and variations are possible by those skilled in the art to which the present invention pertains without departing from the essential characteristics of the present invention. Accordingly, one embodiment disclosed in the present invention is not intended to limit the technical spirit of the present invention, but to explain, and the scope of the technical spirit of the present invention is not limited by this one embodiment. The protection scope of the present invention should be construed by the following claims, and all technical ideas within the equivalent range should be construed as being included in the scope of the present invention.

1: 경계선 2: 지반
3: 흙막이벽체 4: 대지경계선
10: 측면말뚝 10a: 측면말뚝의 하단부
10b: 필링시트 10c: 측면말뚝의 상단부
11: 제1 플랜지 12: 제2 플랜지
13: 연결부 14: 홈부
20: 토류판 30: 보걸이
40: 지보공띠장 50: 버팀보
51: 사보강재 52: 스크루잭
53: 앵글잭 60: 중간말뚝
60a: 방수층 61: 수평보강재
62: 피스 브래킷
1: Boundary 2: Ground
3: retaining wall 4: site boundary
10: side pile 10a: the lower end of the side pile
10b: peeling sheet 10c: upper part of the side pile
11: first flange 12: second flange
13: connection part 14: groove part
20: earth plate 30: beam hanger
40: Jibo ball belt 50: Beotimbo
51: reinforcing steel 52: screw jack
53: angle jack 60: middle stake
60a: waterproof layer 61: horizontal reinforcement
62: piece bracket

Claims (7)

경계선(1)의 안쪽으로 터파기가 이루어진 지반(2)의 외곽에 상기 경계선(1)을 따라 횡단면이 직사각형인 제1 플랜지(11) 및 상기 제1 플랜지(11)보다 폭이 좁게 형성되어 횡단면이 정사각형인 제2 플랜지(12)가 연결부(13)를 통해 일체로 연결되어 구성된 측면말뚝(10)의 하단부(10a)를 근입하여 등 간격으로 배열하는 단계;
상기 제1,2 플랜지(11,12) 사이에 형성된 홈부(14)를 통해 측면말뚝(10) 사이에 직사각형의 토류판(20)을 적층 설치하여 흙막이벽체(3)를 형성하는 단계;
상기 측면말뚝(10)의 내벽에 길이방향을 따라 보걸이(30)를 설치하고, 각각의 상기 보걸이(30)의 상부에 단면이 H형으로 구성된 지보공띠장(40)을 수평방향으로 고정설치하는 단계;
상기 지반(2)의 중심부에 H-파일로 구성된 중간말뚝(60)의 하단부(10a)를 근입하여 기립 설치하고, 상기 중간말뚝(60)의 표면에 수팽창성지수제를 통해 방수층(60a)을 형성하여 방수처리하며, 상기 중간말뚝(60)에 피스 브래킷(62)을 설치하여 상기 피스 브래킷(62)의 상부에 H-빔으로 구성된 수평보강재(61)를 설치하는 단계;
상기 지보공띠장(40)에 버팀보(50)를 설치하여 흙막이벽체(3)의 기립상태를 보강하고, 상기 지반(2)의 각 코너부분은 각각의 지보공띠장(40)에 사보강재(51)를 설치하되, 사보강재(51)와 버팀보(50)의 말단에 스크루잭(52)을 설치하여 시공하되, 상기 사보강재(51)는 스크루잭(52)에 앵글잭(53)을 설치하여 상기 앵글잭(53)을 통해 지보공띠장(40)에 설치하여 보강하는 단계; 및
상기 흙막이벽체(3)의 외측 지반(2)에 차수공법을 통해 약액을 주입하여 그라우팅을 하는 단계를 포함하여 구성되며,
상기 측면말뚝(10)은 연결부(13)와 만나는 제1,2 플랜지(11,12)의 내면이 경사면으로 형성되어 홈부(14)가 사다리꼴의 형태로 제2 플랜지(12)가 경계선(1)을 향해 배치되며, 흙막이벽체(3)의 해체시 철거하여 재사용 가능하도록 지반(2)에 근입되는 하단부(10a)에 측면말뚝(10)의 외형과 대응하는 형상의 필링시트(10b)를 씌운 후에 상단부(10c)가 대지경계선(4)보다 돌출되도록 상기 지반(2)에 기립 설치되는 것을 특징으로 하는 흙막이 가시설의 시공방법.
The cross-section is formed narrower than the first flange 11 and the first flange 11 having a rectangular cross-section along the boundary line 1 on the outside of the ground 2 excavated inside the boundary line 1, so that the cross-section is A step of arranging the lower end (10a) of the square second flange (12) integrally connected through the connecting portion (13) to the lower end (10a) of the side pile (10) at equal intervals;
forming a retaining wall 3 by stacking and installing a rectangular earth plate 20 between the side piles 10 through the groove portion 14 formed between the first and second flanges 11 and 12;
A beam hanger 30 is installed on the inner wall of the side pile 10 in the longitudinal direction, and a jibogong band 40 having an H-shaped cross section is fixed and installed on the upper portion of each of the beam hangers 30 in the horizontal direction. to do;
In the center of the ground (2), the lower end (10a) of the intermediate pile (60) composed of an H-pile is erected and installed, and the waterproof layer (60a) is applied to the surface of the intermediate pile (60) through a water expansibility agent. forming and waterproofing, and installing a piece bracket 62 on the intermediate pile 60 to install a horizontal reinforcement 61 composed of an H-beam on the piece bracket 62;
Reinforcement of the standing state of the retaining wall 3 by installing a brace 50 on the jibogong girders 40, and each corner part of the ground 2 is each jibogong girders 40 with a saber steel material 51. However, the construction is performed by installing a screw jack 52 at the ends of the saber reinforcement 51 and the brace 50, and the saber reinforcement 51 is installed by installing an angle jack 53 on the screw jack 52 to provide the angle Reinforcing by installing to the jibogong belt 40 through the jack (53); and
It is configured including the step of grouting by injecting a chemical solution through the water blocking method into the outer ground (2) of the retaining wall (3),
In the side pile 10, the inner surfaces of the first and second flanges 11 and 12 that meet the connecting portion 13 are formed as inclined surfaces, so that the groove portion 14 is in the form of a trapezoid, and the second flange 12 is a boundary line (1). After covering the lower end 10a of the lower end 10a that is inserted into the ground 2 so that it can be removed and reused when the retaining wall 3 is dismantled, the peeling sheet 10b of a shape corresponding to the external shape of the side pile 10 is covered. The construction method of the temporary retaining facility, characterized in that the upper end (10c) is installed upright on the ground (2) so that it protrudes from the site boundary line (4).
삭제delete 삭제delete 삭제delete 삭제delete 삭제delete 삭제delete
KR1020190063409A 2019-05-29 2019-05-29 Construction method of sheathing temporary facility KR102316011B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020190063409A KR102316011B1 (en) 2019-05-29 2019-05-29 Construction method of sheathing temporary facility

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020190063409A KR102316011B1 (en) 2019-05-29 2019-05-29 Construction method of sheathing temporary facility

Publications (2)

Publication Number Publication Date
KR20200137297A KR20200137297A (en) 2020-12-09
KR102316011B1 true KR102316011B1 (en) 2021-10-21

Family

ID=73786721

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020190063409A KR102316011B1 (en) 2019-05-29 2019-05-29 Construction method of sheathing temporary facility

Country Status (1)

Country Link
KR (1) KR102316011B1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102655594B1 (en) * 2023-09-15 2024-04-08 보천토건(주) Safety temparary facilities structure

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015175226A (en) * 2014-03-18 2015-10-05 ジェコス株式会社 Strut device and earth-retaining timbering

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR950001661Y1 (en) * 1992-03-19 1995-03-11 손우준 Steel pile structure for foundation engineering
KR100648409B1 (en) * 2002-07-27 2006-11-24 김정민 A method of construction for temporary retaining wall
KR100646178B1 (en) * 2004-02-23 2006-11-14 곽찬열 temporary facilities using steel pipe
KR100641697B1 (en) * 2004-11-15 2006-11-03 정연창 Frame to draw out beam and manufacting device thereof
KR101061516B1 (en) * 2008-12-01 2011-09-02 유진지오 주식회사 Temporary wall structure using arched steel pile
KR101549938B1 (en) * 2014-02-07 2015-09-03 (주)나우기술 Concrete timbering and installation structure
KR20170005991A (en) 2015-07-07 2017-01-17 김형민 soil retaining wall using PHC pile and its construction method

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015175226A (en) * 2014-03-18 2015-10-05 ジェコス株式会社 Strut device and earth-retaining timbering

Also Published As

Publication number Publication date
KR20200137297A (en) 2020-12-09

Similar Documents

Publication Publication Date Title
KR102071225B1 (en) Construction method of sheathing temporary facility using steel sheet pile
KR100633796B1 (en) Connecting structure of mid supporting beam for temporary soil sheathing work
KR100855098B1 (en) Strut structure as temporary system using a vertical truss at the end and the method thereof
KR102197103B1 (en) One-sided Camber-type Composite File for Retaining Wall and Method for manufacturing this same and Method for constructing Retaining Wall using this same
KR100831332B1 (en) Underground retaining wall for public works and method for constructing the same
JP2007205161A (en) Retaining wall and its construction method
KR20140013497A (en) Method for constructing block type reinforced retaining wall in cut site
JP2016528406A (en) Beam connection structure of temporary retaining works for earth retaining
KR102316011B1 (en) Construction method of sheathing temporary facility
KR101296857B1 (en) Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same
KR102362257B1 (en) Top-down construction method
JP4780781B2 (en) Seismic reinforcement method for existing concrete pier
JP2007297861A (en) Joint part structure of bridge pier with pile
KR20110052360A (en) Downward construction method of underground structure that enables continuous basement wall using non-wale and diaphragm action of concrete slab
KR20100001516A (en) Joint structure for connecting slant supporter and square steel strut for temporary soil sheathing work
KR101835828B1 (en) Complex Steel Pipe Structure for Underground Wall and the Construction Method Using the Same
KR102482690B1 (en) Bridge foundation construction method using formwork integrated PC panels
KR100640244B1 (en) Method for constructing underground slabs and walls using erection piles without preliminary wall-attached supports
CN113404060A (en) Rigid rib wall type pile wall foundation pit supporting structure and construction method
KR101958768B1 (en) Structure for Constructing the Lagging Board using Strut Beam having Reinforcement Bar
KR200308716Y1 (en) Prestressed scaffolding method
JPH0559728A (en) Sheathing work above underground structure
KR102400508B1 (en) Construction method of retaining wall installation structure
KR101520771B1 (en) H-pile composited with v-shape steel plate and reinforced concrete for open cut construction
RU2581853C1 (en) Method for construction of pile foundation

Legal Events

Date Code Title Description
E902 Notification of reason for refusal
AMND Amendment
E601 Decision to refuse application
X091 Application refused [patent]
AMND Amendment
X701 Decision to grant (after re-examination)
GRNT Written decision to grant