KR102283153B1 - Form for repairing sleeper on concrete bed - Google Patents

Form for repairing sleeper on concrete bed Download PDF

Info

Publication number
KR102283153B1
KR102283153B1 KR1020210046588A KR20210046588A KR102283153B1 KR 102283153 B1 KR102283153 B1 KR 102283153B1 KR 1020210046588 A KR1020210046588 A KR 1020210046588A KR 20210046588 A KR20210046588 A KR 20210046588A KR 102283153 B1 KR102283153 B1 KR 102283153B1
Authority
KR
South Korea
Prior art keywords
formwork
sleeper
concrete ballast
concrete
height
Prior art date
Application number
KR1020210046588A
Other languages
Korean (ko)
Inventor
천완길
Original Assignee
주식회사 케이알티씨
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 케이알티씨 filed Critical 주식회사 케이알티씨
Priority to KR1020210046588A priority Critical patent/KR102283153B1/en
Application granted granted Critical
Publication of KR102283153B1 publication Critical patent/KR102283153B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B29/00Laying, rebuilding, or taking-up tracks; Tools or machines therefor
    • E01B29/005Making of concrete parts of the track in situ
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B1/00Ballastway; Other means for supporting the sleepers or the track; Drainage of the ballastway
    • E01B1/002Ballastless track, e.g. concrete slab trackway, or with asphalt layers
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B29/00Laying, rebuilding, or taking-up tracks; Tools or machines therefor
    • E01B29/04Lifting or levelling of tracks
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2203/00Devices for working the railway-superstructure
    • E01B2203/10Track-lifting or-lining devices or methods
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B2204/00Characteristics of the track and its foundations
    • E01B2204/06Height or lateral adjustment means or positioning means for slabs, sleepers or rails

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Machines For Laying And Maintaining Railways (AREA)

Abstract

The present invention relates to a sleeper formwork for repair of a concrete bed and aims to provide a sleeper formwork for production of a new sleeper by pouring and curing mortar on the concrete bed, which allows the new sleeper to be freely adjusted in height in response to site conditions. To this end, the sleeper formwork for repair of a concrete bed comprises: a lower formwork fixedly installed on the concrete bed to form a wall extending along the periphery of a chipping part just above the chipping part formed in a recessed structure on the concrete bed; an upper formwork assembled to the lower formwork to form an upper surface of a sleeper and to form a space for shaping the sleeper together with the lower formwork while covering an open top of the lower formwork, and having the sleeper adjusted in height by moving up and down while being coupled to the lower formwork; and a position adjusting mechanism connecting the lower formwork and the upper formwork, and moving the upper formwork up and down while working by a worker's operation, to adjust the height of the upper formwork.

Description

콘크리트 도상 보수용 침목 거푸집{Form for repairing sleeper on concrete bed}Form for repairing sleeper on concrete bed}

본 발명은 콘크리트 도상에 몰탈을 직접 타설하고 양생하여 콘크리트 도상에 신설침목을 구성하는 거푸집에 관한 것으로, 더욱 상세하게는 콘크리트 도상의 침하로 인해 침목의 높이 조절이 요구되는 경우 그리고 콘크리트 도상에 설치된 침목의 노후화로 인해 침목의 재시공이 요구되는 경우, 콘크리트 도상에 거푸집을 설치하고 몰탈을 타설하여 콘크리트 도상과 일체화된 침목을 현장에서 구성할 수 있도록 한 콘크리트 도상 보수용 침목 거푸집에 관한 것이다.The present invention relates to a formwork for constructing a new sleeper on a concrete ballast by directly pouring and curing mortar on the concrete ballast, and more particularly, when the height of the sleeper is required due to subsidence of the concrete ballast and a sleeper installed on the concrete ballast When re-construction of the sleeper is required due to the deterioration of the concrete ballast, it relates to a sleeper formwork for repairing concrete ballast, in which a formwork is installed on the concrete ballast and mortar is poured so that a sleeper integrated with the concrete ballast can be constructed on site.

일반적으로 철도 궤도는 침목, 도상, 레일체결장치 및 레일을 포함하며, 견고한 노반 위에 도상을 일정한 두께로 설치하고, 그 위에 침목을 일정 간격으로 부설하며, 부설된 침목 위에 레일을 평행하게 체결한 것을 말한다.In general, railroad tracks include sleepers, ballasts, rail fastening devices, and rails, in which the ballast is installed at a certain thickness on a solid roadbed, sleepers are laid on it at regular intervals, and rails are fastened in parallel on the laid sleepers. say

이러한 철도 궤도는 자갈도상궤도와 콘크리트 도상궤도로 구분할 수 있다.These railroad tracks can be divided into gravel ballast tracks and concrete ballast tracks.

상기 자갈도상궤도는 건설비용이 상대적으로 저렴하고, 궤도 비틀림 시 복구가 비교적 쉽다는 장점이 있지만, 선형유지를 위하여 주기적인 유지보수가 필요하다는 단점이 있다.The gravel ballast has the advantages of relatively low construction cost and relatively easy recovery when the track is twisted, but has the disadvantage that periodic maintenance is required for linear maintenance.

상기 콘크리트 도상궤도는 자갈도상궤도 보다 궤도 틀림이 덜하고, 궤도 및 도상의 손상 및 마모가 적으며, 지속적인 유지보수가 덜 요구되는 장점이 있으며, 이러한 장점으로 인하여 콘크리트 도상궤도가 자갈도상궤도 보다 많이 건설되고 있다.The concrete ballast has the advantages of less track error than the gravel ballast, less damage and wear of the track and ballast, and less continuous maintenance. is being built

한편, 콘크리트 도상궤도의 보수는 선로유지관리지침의 궤도정비기준에 따라 선형(궤간, 면맞춤, 줄마춤, 수평, 캔트 등)을 정정하게 되며, 콘트리드 도상 하부의 노반 침하가 발생된 경우 실시되는 면맞춤 보수작업은 침목과 레일 사이에 조절패드를 삽입하는 방식으로 실시되고 있으나, 조절패드를 이용한 면맞춤 보수작업은 56㎜까지만 보수가 가능하여 제한적으로 실시될 수밖에 없고, 콘크리트 도상에서의 침목교체는 시간이 많이 필요하게 되어 열차운행에 지장을 초래하게 되는 문제점이 있다.On the other hand, the repair of the concrete ballast is to correct the alignment (gauge, mating, lined, horizontal, cant, etc.) according to the track maintenance standards of the track maintenance guidelines. The mating repair work is carried out by inserting the adjusting pad between the sleeper and the rail, but the mating repair work using the adjusting pad can only be performed limitedly as it can only be repaired up to 56 mm, and the sleeper on the concrete roadway is limited. There is a problem in that the replacement takes a lot of time and causes trouble in train operation.

한편, 특허문헌1에는 노반 침하가 발생된 콘크리트 도상에 합성수지층을 형성하고, 형성된 합성수지층 위에 레일 고정 플레이트를 설치하여 레일을 지지하도록 한 침하 노반 콘크리트궤도 복구 시스템이 개시되어 있다.On the other hand, Patent Document 1 discloses a subsidence concrete track restoration system in which a synthetic resin layer is formed on a concrete roadway on which subsidence has occurred, and a rail fixing plate is installed on the formed synthetic resin layer to support the rail.

상기 침하 노반 콘크리트궤도 복구 시스템은 합성수지층을 형성하기 위한 거푸집이 콘크리트 도상과 레일 고정 플레이트의 사이에 형성된 공간을 둘러싸도록 설치하고, 합성수지가 레일 고정 플레이트의 저면까지 차오르도록 거푸집에 타설한 후 양생시킴으로써 레일 고정 플레이트를 지지하는 합성수지층을 레일 고정 플레이트의 하부에 형성하도록 이루어져 있다.The subsidence roadbed concrete track recovery system is installed so that the form for forming the synthetic resin layer surrounds the space formed between the concrete ballast and the rail fixing plate, and the synthetic resin is poured into the form so that it fills up to the bottom of the rail fixing plate and then cured By doing so, a synthetic resin layer supporting the rail fixing plate is formed under the rail fixing plate.

이러한 특허문헌1은 레일 고정 플레이트가 합성수지층의 높이만큼 높아진 위치에서 레일을 지지하게 되므로 노반 침하로 인해 낮아진 콘크리트 도상의 높이를 보완하게 된다.In Patent Document 1, since the rail fixing plate supports the rail at a position as high as the height of the synthetic resin layer, the height of the concrete ballast lowered due to subsidence of the roadbed is supplemented.

그러나, 특허문헌1은 합성수지층의 높이가 레일에 매달린 레일 고정 플레이트에 의해 결정되므로 정밀한 보수작업이 어려운 문제점이 있다.However, Patent Document 1 has a problem in that precise repair work is difficult because the height of the synthetic resin layer is determined by the rail fixing plate suspended from the rail.

즉, 특허문헌1은 레일체결장치와 레일 고정 플레이트를 조립한 상태에서 레일 고정 플레이트의 하부에 거푸집을 설치한 후, 레일 고정 플레이트의 저면까지 합성수지를 타설하게 되므로, 결국 합성수지층의 높이는 지반 침하로 인해 낮아진 콘크리트 도상의 높이를 측량하여 결정되는 것이 아닌 레일에 매달린 레일 고정 플레이트의 높이에 의해 결정되므로 정밀한 보수작업이 불가능하다.That is, in Patent Document 1, after installing a formwork under the rail fixing plate in a state where the rail fastening device and the rail fixing plate are assembled, the synthetic resin is poured up to the bottom of the rail fixing plate. Precise repair work is impossible because it is determined by the height of the rail fixing plate hanging from the rail, not by measuring the height of the concrete ballast lowered due to it.

등록특허공보 제10-2199351호(2021.01.06.공고)Registered Patent Publication No. 10-2199351 (2021.01.06. Announcement)

본 발명은 상기와 같은 문제점을 고려하여 이루어진 것으로, 본 발명의 목적은 몰탈을 콘크리트 도상에 타설하고 양생하여 신설침목을 형성하도록 이루어지되, 신설침목의 높이를 현장 여건에 대응하여 자유롭게 조절할 수 있도록 한 콘크리트 도상 보수용 침목 거푸집을 제공함에 있다.The present invention has been made in consideration of the above problems, and an object of the present invention is to form a new sleeper by pouring and curing mortar on a concrete ballast, and to allow the height of the new sleeper to be freely adjusted in response to site conditions. To provide a sleeper formwork for concrete ballast repair.

본 발명의 다른 목적은 노반 침하로 인해 실시되는 면맞춤 보수작업의 작업시간을 줄여 열차운행에 지장이 없도록 한 콘크리트 도상 보수용 침목 거푸집을 제공함에 있다.Another object of the present invention is to provide a sleeper formwork for concrete ballast repair, which reduces the working time of mating repair work performed due to subsidence of the roadbed so that there is no hindrance to train operation.

본 발명의 또 다른 목적은 조절패드의 삽입을 통한 보수작업이 불가능할 정도로 심한 노반 침하가 발생된 구간에서도 대규모 교체 공사 없이 보수가 가능한 콘크리트 도상 보수용 침목 거푸집을 제공함에 있다.Another object of the present invention is to provide a sleeper form for concrete ballast repair that can be repaired without large-scale replacement work even in a section in which subsidence of the roadbed has been so severe that repair work through insertion of a control pad is impossible.

상기한 바와 같은 목적을 달성하고 종래의 결점을 제거하기 위한 과제를 수행하는 본 발명은 콘크리트 도상에 함몰된 구조로 형성된 치핑부의 바로 위에서 치핑부의 둘레를 따라 연장되는 벽을 형성하도록 콘크리트 도상에 고정되게 설치되는 하부 형틀; 상기 하부 형틀의 개방된 상부를 덮어주면서 침목의 상면을 형성하도록 하부 형틀에 조립되어 하부 형틀과 함께 침목의 성형을 위한 공간을 형성하도록 이루어지되, 하부 형틀에 결합된 채로 상하로 이동하면서 침목의 높이가 조절되게 하는 상부 형틀; 및 상기 하부 형틀과 상부 형틀을 연결하며, 작업자의 조작에 의해 작동하면서 상부 형틀을 상하로 이동시켜 상부 형틀의 높이를 조절하는 위치조절기구;로 구성된 것을 특징으로 하는 콘크리트 도상 보수용 침목 거푸집을 제공한다.The present invention, which achieves the above object and performs the task for eliminating the conventional defects, is fixed on the concrete ballast to form a wall extending along the circumference of the chipping part just above the chipping part formed as a recessed structure on the concrete ballast. lower formwork to be installed; It is assembled to the lower formwork to form the upper surface of the sleeper while covering the open upper part of the lower formwork to form a space for forming the sleeper together with the lower formwork. an upper form that allows the adjustment; and a position adjusting mechanism connecting the lower formwork and the upper formwork, and controlling the height of the upper formwork by moving the upper formwork up and down while operating by the operator's operation; do.

한편 상기 콘크리트 도상 보수용 침목 거푸집에 있어서, 상기 위치조절기구는, 상부 형틀의 선단부 좌우 양측 그리고 후단부 좌우 양측에서 수평방향으로 돌출되게 형성된 지지 브라켓; 수직한 자세로 상기 지지 브라켓을 관통하도록 설치되고, 하단부가 하부 형틀 또는 콘크리트 도상에 닿으며, 상기 지지 브라켓에 나사 결합되거나 하나 이상의 너트를 매개로 지지 브라켓에 결속되는 높이 조절 볼트;로 구성될 수 있다.Meanwhile, in the sleeper formwork for concrete ballast repair, the position adjusting mechanism includes: support brackets formed to protrude in the horizontal direction from both left and right sides of the front end and left and right sides of the rear end of the upper formwork; A height adjustment bolt installed to pass through the support bracket in a vertical posture, the lower end touching the lower formwork or the concrete ballast, screwed to the support bracket or bound to the support bracket via one or more nuts; Can be composed of there is.

한편 상기 콘크리트 도상 보수용 침목 거푸집에 있어서, 상기 지지 브라켓은 높이 조절 볼트가 관통하도록 형성된 구멍의 일부가 외측 방향으로 개방되도록 일부분이 절개되게 형성되고, 상기 하부 형틀에는 높이 조절 볼트의 하단부가 관통하면서 높이 조절 볼트를 정위치에서 지지하는 다수의 보조 브라켓이 수평 방향으로 돌출되게 형성될 수 있다.On the other hand, in the sleeper formwork for concrete ballast repair, the support bracket is formed in such a way that a part of the hole formed through which the height adjustment bolt passes is opened outwardly, and the lower end of the height adjustment bolt penetrates through the lower formwork. A plurality of auxiliary brackets for supporting the height adjustment bolt in place may be formed to protrude in the horizontal direction.

한편 상기 콘크리트 도상 보수용 침목 거푸집에 있어서, 상기 상부 형틀의 상면에는 각각의 덮개에 의해 개폐되는 3개의 주입구가 형성되며, 이중 가운데 위치한 제1주입구는 양측의 제1,2주입구를 향해 길게 연장되게 형성되고, 나머지 제2주입구 및 제3주입구는 제1주입구와 직교하는 방향으로 길게 연장되게 형성될 수 있다.On the other hand, in the sleeper formwork for concrete ballast repair, three inlets opened and closed by respective covers are formed on the upper surface of the upper formwork, and the first inlet located in the middle is extended toward the first and second inlets on both sides. The remaining second inlet and the third inlet may be formed to extend long in a direction orthogonal to the first inlet.

한편 상기 콘크리트 도상 보수용 침목 거푸집에 있어서, 상기 치핑부의 바닥에 하단부가 고정되고, 상단부가 상부 형틀의 안쪽에 위치하도록 치핑부에 설치되어 침목 성형을 위해 타설되는 몰탈에 매립되면서 콘크리트 도상과 침목의 결속력을 높이는 다수의 보강철근이 더 포함될 수 있다.On the other hand, in the sleeper formwork for concrete ballast repair, the lower end is fixed to the bottom of the chipping portion, and the upper end is installed in the chipping portion so that it is located inside the upper formwork and embedded in the mortar to be poured for sleeper molding. A plurality of reinforcing bars to increase the binding force may be further included.

한편 상기 콘크리트 도상 보수용 침목 거푸집에 있어서, 상기 상부 형틀에 설치되어 상부 형틀과 신설침목의 분리를 돕는 하나 이상의 이형유도볼트를 더 포함하되, 상기 이형유도볼트는 수직한 자세로 상부 형틀을 관통한 채로 상부 형틀에 나사결합되어 회전에 의해 상하로 이동하는 볼트축을 포함하는 것으로 구성될 수 있다.On the other hand, in the sleeper formwork for concrete ballast repair, it further comprises one or more release induction bolts installed on the upper formwork to help separate the upper formwork from the new sleeper, wherein the release inducing bolts penetrate the upper formwork in a vertical posture. It may be configured to include a bolt shaft that is screwed to the upper formwork and moves up and down by rotation.

한편 상기 콘크리트 도상 보수용 침목 거푸집에 있어서, 상기 하부 형틀은 4개의 형강재가 사각의 평면구조를 형성하도록 서로 연결된 것으로 이루어지되, 어느 한 형강재는 양 끝단이 인접한 다른 두 형강재와 분리 가능한 구조로 조립되어 해당 형강재의 분리를 통해 상부 형틀이 하부 형틀의 측면부로 빠져나오는 공간을 형성하도록 이루어질 수 있다.On the other hand, in the sleeper formwork for concrete ballast repair, the lower formwork consists of four section steels connected to each other to form a square planar structure, and one section steel is assembled in a structure that is separable from the other two section steel members having both ends adjacent to it. It can be made to form a space through which the upper formwork exits to the side part of the lower formwork through the separation of the corresponding section steel.

상기와 같은 특징을 갖는 본 발명에 의하면, 상부 형틀의 높낮이 조절을 통해 침목의 높이를 다양하고 정확하게 형성할 수 있게 되므로, 정밀한 보수작업이 가능하게 된다.According to the present invention having the above characteristics, it is possible to form the height of the sleeper variously and accurately by adjusting the height of the upper frame, so that precise maintenance work is possible.

또한, 레일의 면맞춤 보수작업을 위해 요구되는 높이의 침목을 현장에서 콘크리트 도상에 일체형의 구조로 형성하게 되므로, 작업의 편의성을 향상시킬 수 있고 우수한 강도를 갖는 침목을 콘크리트 도상에 형성할 수 있다.In addition, since the sleeper of the required height for the rail mating repair work is formed in an integrated structure on the concrete ballast at the site, the convenience of work can be improved and a sleeper with excellent strength can be formed on the concrete ballast. .

또한, 신속한 보수작업이 가능하여 열차운행에 지장을 주지 않고 보수작업이 가능하다.In addition, quick repair work is possible, so repair work is possible without interfering with train operation.

또한, 조절패드를 이용한 보수작업이 불가능한 구간에서 대규모 교체 공사 없이 보수작업이 가능하므로 보수비용을 절감할 수 있다.In addition, since repair work is possible without large-scale replacement work in a section where repair work using the control pad is impossible, repair costs can be reduced.

도 1 은 본 발명의 바람직한 실시예에 따른 거푸집의 사시도,
도 2 는 본 발명의 바람직한 실시예에 따른 거푸집의 분해 사시도,
도 3 은 본 발명에 따른 하부 형틀이 치핑부의 상부에 배치된 상태를 보인 사시도,
도 4 는 본 발명에 따른 위치조절기구의 사시도,
도 5 는 본 발명에 따른 보강철근이 치핑부의 내부에 설치된 상태를 보인 사시도,
도 6 은 본 발명에 따른 거푸집을 이용하여 콘크리트 도상에 신설침목을 형성하고 레일을 지지하는 과정을 간략히 보인 예시도,
도 7 은 본 발명에 따른 상부 형틀이 하부 형틀로부터 분리되는 상태를 보인 예시도,
도 8 은 본 발명에 따른 거푸집에 의해 콘크리트 도상에 형성된 신설침목의 사시도.
1 is a perspective view of a formwork according to a preferred embodiment of the present invention;
2 is an exploded perspective view of a formwork according to a preferred embodiment of the present invention;
3 is a perspective view showing a state in which the lower formwork according to the present invention is disposed on the top of the chipping part;
4 is a perspective view of a positioning mechanism according to the present invention;
5 is a perspective view showing a state in which the reinforcing bar according to the present invention is installed inside the chipping part;
6 is an exemplary view briefly showing a process of forming a new sleeper on a concrete roadway and supporting a rail using a formwork according to the present invention;
7 is an exemplary view showing a state in which the upper form according to the present invention is separated from the lower form;
8 is a perspective view of a new sleeper formed on a concrete ballast by a formwork according to the present invention;

이하, 본 발명의 바람직한 실시예를 첨부된 도면과 연계하여 상세히 설명하면 다음과 같다. 본 발명을 설명함에 있어서, 관련된 공지기능 혹은 구성에 대한 구체적인 설명이 본 발명의 요지를 불필요하게 흐릴 수 있다고 판단되는 경우 그 상세한 설명은 생략한다.Hereinafter, preferred embodiments of the present invention will be described in detail in conjunction with the accompanying drawings. In describing the present invention, if it is determined that a detailed description of a related known function or configuration may unnecessarily obscure the gist of the present invention, the detailed description thereof will be omitted.

도 1은 본 발명의 바람직한 실시예에 따른 거푸집의 사시도를, 도 2는 본 발명의 바람직한 실시예에 따른 거푸집의 분해 사시도를, 도 3은 본 발명에 따른 하부 형틀이 치핑부의 상부에 배치된 상태를 보인 사시도를, 도 4는 본 발명에 따른 위치조절기구의 사시도를, 도 5는 본 발명에 따른 보강철근이 치핑부의 내부에 설치된 상태를 보인 사시도를 도시하고 있다.1 is a perspective view of a formwork according to a preferred embodiment of the present invention, FIG. 2 is an exploded perspective view of a formwork according to a preferred embodiment of the present invention, and FIG. 3 is a state in which the lower formwork according to the present invention is disposed above the chipping part 4 is a perspective view of the positioning mechanism according to the present invention, Figure 5 is a perspective view showing a state in which the reinforcing bar according to the present invention is installed inside the chipping unit.

본 발명의 바람직한 실시예에 따른 콘크리트 도상 보수용 침목 거푸집은 하부 형틀(100)과 상부 형틀(200) 및 위치조절기구(300)로 구성되며, 노반 침하가 발생된 콘크리트 도상에서 레일을 지지하기 위한 신설침목을 콘크리트 도상에 직접 성형하는데 사용될 수 있다.The sleeper formwork for concrete ballast repair according to a preferred embodiment of the present invention is composed of a lower formwork 100, an upper formwork 200, and a position adjustment mechanism 300, and is used to support rails on a concrete ballast on which subsidence has occurred. It can be used to form new sleepers directly on the concrete ballast.

상기 하부 형틀(100)은 침목의 아래쪽 부분을 성형하기 위한 공간을 형성하면서 상부 형틀(200)을 지지하는 것으로, 4개의 형강재(101,102,103,104)가 사각의 평면구조를 형성하도록 서로 결합된 것으로 구성된다.The lower formwork 100 supports the upper formwork 200 while forming a space for forming the lower part of the sleeper, and four section steels 101, 102, 103, and 104 are combined with each other to form a rectangular planar structure. .

이와 같이 4개의 형강재(101,102,103,104)로 이루어진 하부 형틀(100)은 콘크리트 도상에 함몰된 구조로 가공된 치핑부(30)의 바로 위에 위치하도록 콘크리트 도상에 설치되며, 치핑부(30)의 둘레를 따라 연장되는 벽을 형성하도록 이루어진다.As described above, the lower formwork 100 made of the four section steel materials 101, 102, 103, and 104 is installed on the concrete ballast so as to be located directly above the chipping part 30 processed into a recessed structure on the concrete ballast, and the circumference of the chipping part 30 is installed on the concrete ballast. formed to form a wall extending along it.

한편, 상기 치핑부(30)는 침목과 침목의 사이에서 콘크리트 도상의 일부를 절개 및 제거하여 대략 40㎜의 깊이를 갖는 사각형의 홈을 형성한 것으로 구성될 수 있다.Meanwhile, the chipping unit 30 may be configured to form a rectangular groove having a depth of about 40 mm by cutting and removing a part of the concrete ballast between the sleeper and the sleeper.

한편, 하부 형틀(100)을 구성하는 형강재(101,102,103,104)는 ㄱ자 형상의 단면을 갖는 앵글로 구성될 수 있으며, 앵글의 한쪽 측면은 콘크리트 도상에 밀착된 채로 앵커볼트에 의해 콘크리트 도상에 고정되고, 다른 한쪽 측면은 치핑부(30)의 벽과 연속된 구조의 벽을 형성하면서 몰탈이 타설되는 공간을 형성하도록 구성된다.On the other hand, the section steel (101, 102, 103, 104) constituting the lower formwork 100 may be composed of an angle having a L-shaped cross section, and one side of the angle is fixed to the concrete ballast by anchor bolts while being in close contact with the concrete ballast, The other side is configured to form a space in which mortar is poured while forming a wall of a continuous structure with the wall of the chipping part 30 .

또한, 하부 형틀(100)을 형성하는 4개의 형강재(101,102,103,104) 중, 하나는 분리 가능한 구조로 인접한 두 형강재(102,103)와 결합되어 하부 형틀(100)의 한쪽 부분을 선택적으로 개방하도록 구성될 수 있다.In addition, one of the four section steels 101, 102, 103, and 104 forming the lower formwork 100 is combined with two adjacent sections 102 and 103 in a separable structure to selectively open one part of the lower formwork 100. can

보다 구체적으로, 하부 형틀(100)을 형성하는 4개의 형강재(101,102,103,104) 중, 개방측에 위치하는 형강재(101)의 양끝단에는 수평방향으로 연장되면서 해당 형강재(101)의 외측 방향으로 돌출되는 고정볼트(105)가 설치되고, 개방측에 인접한 두 형강재(102,103)의 일측 단부에는 상기 고정볼트(105)가 삽입되는 슬릿(106)이 형성되며, 고정볼트(105)는 슬릿(106)에 삽입된 채로 너트(107)와 체결됨으로써 슬릿(106)이 형성된 형강재(102,103)에 분리 가능한 구조로 고정된다.More specifically, among the four section steels 101, 102, 103, and 104 forming the lower formwork 100, both ends of the section steel 101 positioned on the open side are extended in the horizontal direction to the outside of the corresponding section material 101. A fixing bolt 105 that protrudes is installed, and a slit 106 into which the fixing bolt 105 is inserted is formed at one end of the two section steels 102 and 103 adjacent to the open side, and the fixing bolt 105 is a slit ( By being fastened with the nut 107 while being inserted into the 106, the slit 106 is fixed to the formed steel sections 102 and 103 in a separable structure.

따라서, 개방측 형강재(101)에 형성된 고정볼트(105)가 인접한 두 형강재(102,103)의 슬릿(106)에 삽입되도록 개방측 형강재(101)를 배치하고, 슬릿(106)을 통해 돌출된 고정볼트(105)의 단부에 너트(107)를 체결함으로써, 개방측 형강재(101)와 그에 인접한 두 형강재(102,103)를 분리 가능한 구조로 결속시키게 된다.Accordingly, the open-side section member 101 is disposed so that the fixing bolt 105 formed on the open-side section member 101 is inserted into the slit 106 of the two adjacent section steel members 102 and 103, and protrudes through the slit 106. By fastening the nut 107 to the end of the fixed bolt 105, the open-side section steel 101 and the two adjacent section steel members 102 and 103 are bound in a separable structure.

한편, 상기 고정볼트(105)는 형강재(101)의 양측에 각각 하나의 볼트를 설치한 것으로 구성되거나, 수평한 자세로 연장되면서 양끝단이 형강재(101)의 양측으로 돌출될 수 있을 정도로 충분히 긴 하나의 전산볼트로 구성될 수도 있다.On the other hand, the fixing bolt 105 is constituted by installing one bolt on both sides of the section steel 101, or extending in a horizontal posture so that both ends can protrude to both sides of the section steel 101 It may consist of one long enough computational bolt.

상기 상부 형틀(200)은 하부 형틀(100)의 개방된 상부를 덮어주면서 침목의 상면을 형성하도록 하부 형틀(100)의 상단부에 조립되어 하부 형틀(100)과 함께 침목의 성형을 위한 공간을 형성하는 것으로, 하부 형틀(100)의 안쪽으로 삽입되어 하부 형틀(100)과 결합되며 침목의 측면을 형성하는 측면 성형부(210)와, 상기 측면 성형부(210)를 구성하는 부재들의 상단부를 서로 연결하되 성형하고자 하는 침목의 상부 형상에 대응하는 형상을 구현하면서 측면 성형부(210)를 구성하는 부재들을 서로 연결하는 덮개부(220)로 구성된다.The upper formwork 200 is assembled to the upper end of the lower formwork 100 so as to form an upper surface of the sleeper while covering the open upper part of the lower formwork 100 to form a space for molding the sleeper together with the lower formwork 100 . In this way, the side molded part 210 inserted into the lower mold 100 and coupled to the lower mold 100 to form the side of the sleeper, and the upper ends of the members constituting the side molded part 210 are mutually It is composed of a cover part 220 that connects the members constituting the side molding part 210 to each other while implementing a shape corresponding to the upper shape of the sleeper to be formed.

이때, 상기 측면 성형부(210)는 수직하거나 수직에 근접한 자세로 기울어지거나 굽어진 형상을 갖는 4개의 판재가 사각의 평면구조를 형성하도록 결합된 것으로 구성될 수 있다.At this time, the side forming part 210 may be configured by combining four plates having a shape inclined or bent in a vertical or near-vertical posture to form a rectangular planar structure.

이때 각 판재의 기울기나 형상은 성형하고자 하는 침목의 측면 구조에 따라 자유롭게 결정될 수 있다.At this time, the slope or shape of each plate can be freely determined according to the side structure of the sleeper to be formed.

상기 덮개부(220)는 측면 성형부(210)의 상부에 일체형의 구조로 형성되어 침목의 상면이 요구되는 형태로 성형되게 하는 것으로, 양끝단에 돌출부가 형성되고, 두 돌출부의 사이에 상대적으로 낮은 높이의 안착부가 형성된 침목을 성형하도록 구성된다.The cover part 220 is formed in an integral structure on the upper part of the side molding part 210 so that the upper surface of the sleeper is molded into a required shape. It is configured to form a sleeper having a low height seating portion.

이를 위하여 상기 덮개부(220)는 침목의 일측 돌출부를 성형하도록 상부 방향으로 볼록하게 굽어진 형상을 갖는 제1성형부(221)와, 타측 돌출부를 성형하도록 상부 방향으로 볼록하게 굽어진 형상을 갖는 제2성형부(222)와, 제1성형부(221)와 제2성형부(222)의 사이에서 상대적으로 낮은 높이로 형성되어 안착부를 성형하는 제3성형부(223)로 구성된다.To this end, the cover part 220 includes a first molding part 221 having a shape convexly curved upward to shape one side protrusion of the sleeper, and a first molding part 221 having a shape convexly curved upward to shape the other side projection part of the sleeper. It is composed of a second molding part 222 and a third molding part 223 formed at a relatively low height between the first molding part 221 and the second molding part 222 and forming a seating part.

이와 같이 구성된 상부 형틀(200)에 있어서, 몰탈의 원활한 주입을 위해 3개의 주입구(231,232,233)가 상부 형틀(200)에 분산되게 형성된다.In the upper formwork 200 configured as described above, three injection holes 231,232 and 233 are formed to be dispersed in the upper formwork 200 for smooth injection of mortar.

보다 구체적으로, 상기 주입구(231,232,233)는 제1성형부(221)와 제2성형부(222) 및 제3성형부(223)에 각각 형성되며, 이때 제3성형부(223)에 형성되는 제3주입구(233)는 나머지 두 주입구(231,232)를 향하여 길게 연장된 장방형의 형상으로 제3성형부(223)의 일부를 개방하도록 형성되고, 제1성형부(221)에 형성되는 제1주입구(231)와 제2성형부(222)에 형성되는 제2주입구(232)는 제3주입구(233)와 직교하는 방향으로 길게 연장된 장방형의 형상으로 제1성형부(221)와 제2성형부(222)의 일부를 각각 개방하도록 형성된다.More specifically, the injection holes 231,232 and 233 are respectively formed in the first molding part 221 , the second molding part 222 , and the third molding part 223 , and in this case, the first molding part 223 formed in the third molding part 223 . The third inlet 233 is formed to open a part of the third forming part 223 in a rectangular shape extending long toward the other two inlet ports 231,232, and the first inlet formed in the first forming part 221 ( 231) and the second inlet 232 formed in the second forming part 222 has a rectangular shape elongated in a direction orthogonal to the third inlet 233, the first forming part 221 and the second forming part A portion of the 222 is formed to open, respectively.

이와 같은 제1주입구(231)와 제2주입구(232) 및 제3주입구(233)에는 덮개(234,235,236)가 각각 설치되며, 덮개(234,235,236)의 설치와 분해를 통해 각각의 주입구(231,232,233)를 독립적으로 개폐하도록 이루어진다.The first inlet 231, the second inlet 232, and the third inlet 233 are provided with covers 234,235,236, respectively, and through the installation and disassembly of the covers 234,235,236, the respective inlets 231,232,233 are independently separated. made to open and close.

또한, 상기 상부 형틀(200)에는 몰탈의 양생 후 상부 형틀(200)을 신설침목으로부터 원활하게 분리시킬 수 있게 하는 이형유도볼트(240)가 더 설치될 수 있다.In addition, the upper formwork 200 may be further installed with a release induction bolt 240 that enables the upper formwork 200 to be smoothly separated from the new sleeper after curing of the mortar.

상기 이형유도볼트(240)는 다수개가 상부 형틀(200)에 분산되게 설치될 수 있으며, 본 발명의 비람직한 실시예에 따른 상부 형틀(200)에는 4개의 이형유도볼트(240)가 분산되게 설치된다.A plurality of the release induction bolts 240 may be installed to be dispersed in the upper formwork 200, and the four release induction bolts 240 are dispersed in the upper formwork 200 according to an undesirable embodiment of the present invention. is installed

한편, 각각의 이형유도볼트(240)는, 수직한 자세로 상부 형틀(200)을 관통하되 상부 형틀(200)에 나사결합되어 회전방향에 따라 상승하거나 하강하는 볼트축(241)을 포함하는 것으로 구성된다.On the other hand, each release induction bolt 240 passes through the upper formwork 200 in a vertical posture, but is screwed to the upper formwork 200 to include a bolt shaft 241 that ascends or descends according to the rotational direction. is composed

이와 같은 이형유도볼트(240)는 몰탈의 양생에 의한 신설침목의 성형이 완료된 후, 작업자의 조작에 의해 회전하면서 하강하게 되고, 이때 볼트축(241)의 하단이 신설침목의 상면에 닿으면서 상부 형틀(200)을 들어 올리는 작용을 하게 되므로, 상부 형틀(200)과 신설침목을 용이하게 분리시킬 수 있다.After the molding of the new sleeper by curing of the mortar is completed, the release induction bolt 240 is lowered while rotating by the operator's operation. At this time, the lower end of the bolt shaft 241 touches the upper surface of the new sleeper and the upper part Since it acts to lift the formwork 200, the upper formwork 200 and the new sleeper can be easily separated.

상기와 같이 구성된 상부 형틀(200)은 하부 형틀(100)에 결합된 채로 위치조절기구(300)에 의해 상하로 이동하면서 다양한 높이의 신설침목을 성형하도록 구성된다.The upper formwork 200 configured as described above is configured to form new sleepers of various heights while being coupled to the lower formwork 100 and moving up and down by the positioning mechanism 300 .

상기 위치조절기구(300)는 하부 형틀(100)과 상부 형틀(200)을 연결하며, 작업자의 조작에 의해 작동하면서 상부 형틀(200)을 상하로 이동시켜 상부 형틀(200)의 높이를 조절하는 것으로, 다수의 지지 브라켓(310)과, 다수의 높이 조절 볼트(320)로 구성된다.The position adjusting mechanism 300 connects the lower formwork 100 and the upper formwork 200, and moves the upper formwork 200 up and down while operating by the operator's operation to adjust the height of the upper formwork 200 As such, it is composed of a plurality of support brackets 310 and a plurality of height adjustment bolts 320 .

상기 다수의 지지 브라켓(310)은 상부 형틀(200)의 선단부 좌우 양측 그리고 후단부 좌우 양측에서 수평방향으로 돌출되게 형성된다. 즉 본 발명의 바람직한 실시예에 따른 상부 형틀(200)에는 4개의 지지 브라켓(310)이 구비된다.The plurality of support brackets 310 are formed to protrude in the horizontal direction from both left and right sides of the front end and left and right sides of the rear end of the upper frame 200 . That is, the upper formwork 200 according to the preferred embodiment of the present invention is provided with four support brackets 310 .

한편, 지지 브라켓(310)과 하부 형틀(100)의 간섭으로 인해 지지 브라켓(310)의 설치가 용이하지 않을 경우, 수직한 자세의 연장부(미도시됨)를 매개로 지지 브라켓(310)을 상부 형틀(200)에 설치하여 지지 브라켓(310)의 위치를 상부로 이동시킬 수도 있다.On the other hand, when the installation of the support bracket 310 is not easy due to the interference between the support bracket 310 and the lower formwork 100, the support bracket 310 is installed via an extension part (not shown) in a vertical posture. It may be installed on the upper frame 200 to move the position of the support bracket 310 upward.

상기 높이 조절 볼트(320)는 작업자의 조작에 의해 회전하면서 지지 브라켓(310)을 상하로 이동시키는 것으로, 각각의 지지 브라켓(310)에 하나의 높이 조절 볼트(320)가 설치된다.The height adjustment bolt 320 moves the support bracket 310 up and down while rotating by the operator's operation, and one height adjustment bolt 320 is installed in each support bracket 310 .

한편, 각각의 높이 조절 볼트(320)는 수직한 자세로써 지지 브라켓(310)의 상부로부터 지지 브라켓(310)을 관통하여 하단부가 하부 형틀(100) 또는 콘크리트 도상에 닿도록 이루어지되, 지지 브라켓(310)에 나사 결합되거나 하나 이상의 너트(330)를 매개로 지지 브라켓(310)에 결속되도록 구성된다.On the other hand, each height adjustment bolt 320 penetrates the support bracket 310 from the upper part of the support bracket 310 in a vertical posture so that the lower end part touches the lower formwork 100 or the concrete ballast, the support bracket ( It is configured to be screwed to 310 or bound to the support bracket 310 via one or more nuts 330 .

한편, 도 1, 2, 4에는 지지 브라켓(310)의 상부와 하부에 각각 위치하도록 배치된 두 개의 너트(330)에 의해 높이 조절 볼트(320)가 지지 브라켓(310)에 결속되며, 두 너트(330)를 조이거나 풀어주면서 높이 조절 볼트(320)가 지지 브라켓(310)에 결속되는 위치를 조절하여 상부 형틀(200)의 높이를 조절하도록 한 구조가 도시되어 있다.On the other hand, in FIGS. 1, 2, and 4, the height adjustment bolt 320 is bound to the support bracket 310 by two nuts 330 arranged to be respectively positioned on the upper and lower portions of the support bracket 310, and the two nuts A structure is shown to adjust the height of the upper frame 200 by adjusting the position at which the height adjustment bolt 320 is bound to the support bracket 310 while tightening or loosening the 330 .

이와 같은 위치조절기구(300)에 있어서, 높이 조절 볼트(320)가 관통하도록 지지 브라켓(310)에 형성된 구멍(311)의 일부분이 외측 방향으로 개방된 구조를 갖도록 하기 위한 절개부(312)가 지지 브라켓(310)의 외측 단부에 형성되고, 이와 더불어 높이 조절 볼트(320)의 하단부가 관통하면서 높이 조절 볼트(320)를 정위치에서 지지하는 다수의 보조 브라켓(340)이 하부 형틀(100)에 더 설치될 수 있다.In such a position adjusting mechanism 300, a cutout 312 for allowing a portion of the hole 311 formed in the support bracket 310 to pass through the height adjustment bolt 320 has a structure that is opened outward. A plurality of auxiliary brackets 340 formed at the outer end of the support bracket 310 and supporting the height adjustment bolt 320 in place while the lower end of the height adjustment bolt 320 penetrates through the lower formwork 100 can be further installed in

한편, 상기 절개부(312)와 보조 브라켓(340)에 의하면, 높이 조절 볼트(320)를 지지 브라켓(310)에 설치함에 있어서 지지 브라켓(310)의 측면부에서 높이 조절 볼트(320)를 밀어 넣는 방식으로 설치할 수 있으므로, 다양한 작업환경에 대응하여 높이 조절 볼트(320)의 설치와 분해 작업을 용이하게 실시할 수 있고, 보조 브라켓(340)을 이용하여 높이 조절 볼트(320)의 하단부를 정위치에서 잡아주게 되므로 높이 조절 볼트(320)의 올바른 자세 유지를 통해 높이 조절의 정밀도를 향상시킬 수 있게 된다.On the other hand, according to the cutout 312 and the auxiliary bracket 340 , when the height adjustment bolt 320 is installed in the support bracket 310 , the height adjustment bolt 320 is pushed in from the side portion of the support bracket 310 . Since it can be installed in this way, the installation and disassembly of the height adjustment bolt 320 can be easily performed in response to various working environments, and the lower end of the height adjustment bolt 320 is positioned in place by using the auxiliary bracket 340 . It is possible to improve the precision of height adjustment by maintaining the correct posture of the height adjustment bolt 320 because it is held in the .

상기와 같이 구성된 본 발명에 따른 콘크리트 도상 보수용 침목 거푸집에 있어서, 콘크리트 도상과 신설침목의 결속력을 높이는 보강철근(400)이 더 포함될 수 있다.In the sleeper formwork for concrete ballast repair according to the present invention configured as described above, the reinforcing reinforcing bar 400 for increasing the bonding force between the concrete ballast and the new sleeper may be further included.

상기 보강철근(400)은 치핑부(30)의 바닥과 신설침목을 연결하여 신설침목이 보다 견고한 구조로 콘크리트 도상에 고정되게 하는 것으로, 다수의 보강철근(400)이 치핑부(30)의 내부에 설치되되, 일부 보강철근(400)은 하단부가 치핑부(30)의 바닥에 고정되어 기립되고, 나머지 보강철근(400)은 기립된 보강철근(400)의 상단부를 서로 연결하도록 설치된다.The reinforcing bar 400 connects the floor of the chipping part 30 and the new sleeper so that the new sleeper is fixed to the concrete ballast with a more robust structure. Doedoe, some reinforcing bars 400 have their lower ends fixed to the bottom of the chipping part 30 to stand up, and the remaining reinforcing bars 400 are installed to connect the upper ends of the erected reinforcing bars 400 to each other.

한편, 도 2의 도면부호 240은 몰탈을 타설하는 과정에서 거푸집 내부의 공기가 원활하게 배출될 수 있도록 하는 공기배출구로서, 다수개가 상부 형틀(220)에 분산되게 형성된다.On the other hand, reference numeral 240 in FIG. 2 is an air outlet that allows the air inside the mold to be smoothly discharged in the process of pouring the mortar, and a plurality of them are formed to be dispersed in the upper mold 220 .

도 6은 본 발명에 따른 거푸집을 이용하여 콘크리트 도상에 신설침목을 형성하고 레일을 지지하는 과정을 간략히 보인 예시도를, 도 7은 본 발명에 따른 상부 형틀이 하부 형틀로부터 분리되는 상태를 보인 예시도를, 도 8은 본 발명에 따른 거푸집에 의해 콘크리트 도상에 형성된 신설침목의 사시도를 도시하고 있다.6 is an exemplary view briefly showing a process of forming a new sleeper on a concrete roadway and supporting a rail using a formwork according to the present invention, and FIG. 7 is an example showing a state in which the upper formwork according to the present invention is separated from the lower formwork 8 is a perspective view of a new sleeper formed on a concrete ballast by a formwork according to the present invention.

이하에서는 노반의 침하로 인해 높이가 낮아진 콘크리트 도상(10)에 침목을 새로 형성하여 레일(20)의 면맞춤 보수작업을 실시하는 과정을 설명하도록 한다. 물론 신설침목의 형성은 본 발명에 따른 거푸집을 이용하는 것으로 한다.Hereinafter, a process of performing mating repair work of the rail 20 by forming a new sleeper on the concrete ballast 10 whose height has been lowered due to subsidence of the roadbed will be described. Of course, the new sleeper is formed by using the formwork according to the present invention.

먼저, 측량작업을 통해 노반 침하가 발생된 구간을 확인하고, 신설침목이 형성될 위치와 높이를 결정한다.First, check the section where subsidence has occurred through surveying, and determine the location and height where the new sleeper will be formed.

신설침목이 형성될 위치에 치핑부(30)를 형성한다. 신설침목은 기존 침목과 침목의 사이에 새로 형성되어 레일을 지지하게 되므로, 기존 침목과 침목의 사이에 치핑부(30)를 형성하게 된다.A chipping portion 30 is formed at a position where the new sleeper is to be formed. Since the new sleeper is newly formed between the existing sleeper and the sleeper to support the rail, the chipping portion 30 is formed between the existing sleeper and the sleeper.

상기 치핑부(30)는 사각형의 평면구조를 가지며 대략 40㎜의 깊이를 갖는 홈을 콘크리트 도상(10)의 컷팅과 파쇄작업을 통해 가공함으로써 형성될 수 있다.The chipping part 30 may be formed by machining a groove having a rectangular planar structure and a depth of about 40 mm through cutting and crushing of the concrete ballast 10 .

한편, 콘크리트 도상(10)에 치핑부(30)를 형성하기에 앞서 콘크리트 도상의 컷팅작업 공간을 확보하기 위하여 작업지점을 기준으로 전후 일정 구간의 레일 체결구(40)를 해체하고, 조절패드(50)를 이용하여 레일(20)을 높인 상태에서 치핑작업을 실시하는 것이 바람직하다.On the other hand, before forming the chipping part 30 on the concrete ballast 10, in order to secure a cutting work space on the concrete ballast, the rail fasteners 40 in a predetermined section before and after the work point are dismantled, and the control pad ( 50), it is preferable to carry out the chipping operation in a state in which the rail 20 is raised.

상기와 같은 과정을 통해 치핑부(30)를 형성하고 난 후, 치핑부(30)의 바닥에 보강철근(400)의 설치를 위한 다수의 구멍을 천공하고, 천공된 구멍에 보강철근(400)의 하단부를 삽입하여 고정하되, 보강철근(400)이 기립된 상태를 유지하면서 상단부가 상부 형틀(200)의 안쪽에 위치할 수 있도록 보강철근(400)을 치핑부(30)에 고정하게 된다.After the chipping part 30 is formed through the above process, a plurality of holes for installation of the reinforcing bar 400 are drilled in the bottom of the chipping part 30, and the reinforcing bar 400 is drilled in the drilled hole. Insert and fix the lower end of the, but the reinforcing bar 400 is fixed to the chipping portion 30 so that the upper end can be located inside the upper formwork 200 while maintaining the upright state.

한편, 보강철근(400)을 구멍에 고정하기 위해 케미컬앙카가 사용될 수 있다.On the other hand, a chemical anchor may be used to fix the reinforcing bar 400 to the hole.

한편, 기립되게 설치된 보강철근(400)의 상단부는 또 다른 보강철근(400)에 의해 서로 연결되어 다수의 보강철근(400)이 치핑부(30)의 내부에 격자형의 보강구조를 형성하게 된다.On the other hand, the upper end of the reinforcing rebar 400 installed to stand up is connected to each other by another reinforcing bar 400 , so that a plurality of reinforcing reinforcing bars 400 form a grid-type reinforcing structure inside the chipping part 30 . .

상기 보강철근(400)의 설치가 완료된 후, 치핑부(30)의 내면에 접착력 강화를 위한 콘크리트 접착제를 바르고, 본 발명에 따른 거푸집을 치핑부(30) 위에 설치한다.After the installation of the reinforcing bar 400 is completed, a concrete adhesive for strengthening adhesion is applied to the inner surface of the chipping unit 30 , and the formwork according to the present invention is installed on the chipping unit 30 .

상기 거푸집을 치핑부(30) 위에 설치함에 있어서, 레일면고의 측량 결과에 따라 결정된 신설침목의 높이에 따라 거푸집의 높이를 조절하게 된다.When the formwork is installed on the chipping part 30, the height of the formwork is adjusted according to the height of the new sleeper determined according to the measurement result of the height of the rail.

한편, 거푸집은 성형 가능한 침목의 높이에 따라 여러 종류로 구분하여 준비해둘 수 있으며, A타입 거푸집은 0~40㎜, B타입 거푸집은 40~80㎜, C타입 거푸집은 80~120㎜, D타입 거푸집은 120~160㎜와 같은 방식으로 여러 종류의 거푸집을 준비하고, 결정된 신설침목의 높이에 따라 적절한 타입의 거푸집을 선택하여 사용하게 된다.On the other hand, the formwork can be prepared by dividing it into several types according to the height of the sleeper that can be molded. For the formwork, various types of formwork are prepared in the same way as 120~160mm, and an appropriate type of formwork is selected and used according to the determined height of the new sleeper.

상기 거푸집의 설치는 하부 형틀(100)을 콘트리트 도상(10)에 고정시키고, 상부 형틀(200)을 하부 형틀(100)에 조립하되, 위치조절기구(300)를 이용하여 상부 형틀(200)의 높이를 신설침목의 높이에 맞추어 조절하게 된다.The installation of the formwork is performed by fixing the lower formwork 100 to the concrete ballast 10, and assembling the upper formwork 200 to the lower formwork 100, but using the positioning mechanism 300 to the upper formwork 200. The height is adjusted according to the height of the new sleeper.

한편, 상기 하부 형틀(100)은 앵커볼트에 의해 콘크리트 도상(10)에 고정될 수 있으며, 상기 위치조절기구(300)는 높이 조절 볼트(320)가 지지 브라켓(310)에 고정되는 위치를 높이 조절 볼트(320)의 회전 또는 너트(330)의 회전을 통해 조절함으로써 이루어질 수 있다.On the other hand, the lower formwork 100 may be fixed to the concrete ballast 10 by anchor bolts, and the position adjusting mechanism 300 increases the height at which the height adjustment bolt 320 is fixed to the support bracket 310 . This may be accomplished by adjusting the adjustment bolt 320 through rotation of the nut 330 or rotation of the nut 330 .

상기 위치조절기구(300)를 이용하여 상부 형틀(200)의 높이를 조절함에 있어서, 상부 형틀(200)에 분산되게 설치된 다수의 높이 조절 볼트(320)를 서로 다른 높이로 조작하여 상부 형틀(200)의 기울기를 콘크리트 도상의 기울기에 대응하여 추가적으로 조절할 수도 있다.In adjusting the height of the upper formwork 200 using the position adjusting mechanism 300, a plurality of height adjustment bolts 320 dispersedly installed in the upper formwork 200 are operated to different heights to adjust the height of the upper formwork 200. ) can be additionally adjusted in response to the inclination of the concrete ballast.

상기와 같은 과정을 통해 하부 형틀(100)과 상부 형틀(200)의 설치가 완료되면, 상부 형틀(200)에 형성된 제1,2,3주입구(231,232,233)를 통해 초속경 몰탈을 주입하고, 몰탈의 주입이 완료되면, 제1,2,3주입구(231,232,233)에 덮개(234,235,236)를 설치하여 폐쇄하게 된다.When the installation of the lower formwork 100 and the upper formwork 200 is completed through the process as described above, the first, second, and third inlets 231,232,233 formed in the upper formwork 200 are injected with super-velocity mortar, and the mortar is injected. Upon completion of the injection, the covers 234, 235, and 236 are installed in the first, second, and third inlets 231,232, 233 to close them.

한편, 거푸집에 타설된 몰탈의 양생되면 거푸집을 해체하고, 거푸집의 해체로 인해 노출되는 신설침목의 표면을 정리하는 작업을 실시하게 된다.On the other hand, when the mortar poured into the formwork is cured, the formwork is dismantled and the surface of the new sleeper exposed due to the dismantling of the formwork is arranged.

상기 거푸집의 해체는 상부 형틀(200)을 들어 올려 하부 형틀(100)로부터 분리시키는 방식으로 실시될 수 있지만, 운행선상에서 이루어지는 작업의 특성상 거푸집의 상부에 레일(20)이 위치하는 관계로 상부 형틀(200)을 들어올리기 위한 공간확보가 어려울 수 있다.The dismantling of the form can be carried out by lifting the upper form 200 and separating it from the lower form 100, but due to the nature of the work performed on the operating line, the rail 20 is located on the upper part of the form. It may be difficult to secure space for lifting the 200.

이러한 경우, 하부 형틀(100)의 일부를 구성하되 분리 가능한 구조로 다른 형강재(102,103)와 결합된 개방측 형강재(101)를 분리하여 하부 형틀(100)의 한쪽 측면을 개방하고, 개방된 측면 방향으로 상부 형틀(200)을 이동시키는 방식으로 상부 형틀(200)을 하부 형틀(100)로부터 분리시킬 수도 있다.In this case, one side of the lower formwork 100 is opened, and one side of the lower formwork 100 is opened by separating the open side steel material 101 combined with the other section steel materials 102 and 103 in a separable structure but constituting a part of the lower formwork 100 . The upper formwork 200 may be separated from the lower formwork 100 by moving the upper formwork 200 in the lateral direction.

상기와 같이 거푸집을 해체하는 과정에서 상부 형틀(200)이 신설침목(500)으로부터 잘 분리되지 않을 경우, 이형유도볼트(240)가 이용될 수 있다.When the upper formwork 200 is not well separated from the new sleeper 500 in the process of dismantling the form as described above, the release guide bolt 240 may be used.

즉, 이형유도볼트(240)가 하강하는 방향으로 이형유도볼트(240)를 회전시키게 되면, 하단부가 신설침목(500)에 닿은 이형유도볼트(240)는 하강하지 못하고, 이형유도볼트(240)가 나사결합된 상부 형틀(200)이 상부로 들어 올려지므로, 상부 형틀(200)을 신설침목(500)으로부터 보다 용이하게 분리시킬 수 있다.That is, when the release inducing bolt 240 is rotated in the direction in which the release induction bolt 240 descends, the release induction bolt 240 whose lower end is in contact with the new sleeper 500 does not descend, and the release induction bolt 240 Since the upper formwork 200 to which the is screwed is lifted upward, the upper formwork 200 can be more easily separated from the new sleeper 500 .

거푸집의 해체와 신설침목의 표면정리작업이 완료되면, 새로운 레일 체결구(51)를 신설침목(500)에 고정하기 위한 매립전이 설치되는 구멍을 신설침목(500)에 가공하고, 신설침목(500)에 가공된 구멍에 매립전을 삽입한 뒤 케미컬앙카로 고정하며, 레일(20)과 결합되는 레일 체결구(51)를 매립전을 이용하여 신설침목(500)에 고정하게 된다.When the dismantling of the formwork and the surface preparation of the new sleeper are completed, a hole for installing the burial pole for fixing the new rail fastener 51 to the new sleeper 500 is machined in the new sleeper 500, and the new sleeper 500 is ), and then fixed with a chemical anchor, and the rail fastener 51 coupled to the rail 20 is fixed to the new sleeper 500 using the embedding.

상술한 바와 같이, 본 발명에 따른 콘크리트 도상 보수용 침목 거푸집은 현장에서 콘크리트 도상에 몰탈을 타설하고 양생시켜 콘크리트 도상과 일체화된 침목을 구성할 수 있도록 하되, 신설침목의 높이를 현장 여건에 맞추어 다양하게 조절할 수 있으므로, 불규칙한 노반 침하에 상관없이 정밀한 보수작업이 가능하고, 신속한 보수작업이 가능하며, 과도한 노반 침하가 발생된 구간에서도 보수작업이 가능하게 하는 매우 유용한 발명이다.As described above, in the sleeper formwork for concrete ballast repair according to the present invention, mortar is poured and cured on the concrete ballast to form a sleeper integrated with the concrete ballast. It is a very useful invention that enables precise repair work regardless of irregular subsidence, rapid repair work, and repair work even in a section where excessive subsidence subsidence occurs.

본 발명은 상술한 특정의 바람직한 실시 예에 한정되지 아니하며, 청구범위에서 청구하는 본 발명의 요지를 벗어남이 없이 당해 발명이 속하는 기술분야에서 통상의 지식을 가진 자라면 누구든지 다양한 변형실시가 가능한 것은 물론이고, 그와 같은 변경은 청구범위 기재의 범위 내에 있게 된다.The present invention is not limited to the specific preferred embodiments described above, and without departing from the gist of the present invention claimed in the claims, anyone with ordinary skill in the art to which the invention pertains can implement various modifications Of course, such modifications are intended to be within the scope of the claims.

<도면의 주요 부분에 대한 부호의 설명>
10: 콘크리트 도상 20 : 레일
30: 치핑부 100: 하부 형틀
101,102,103,104: 형강재 200: 상부 형틀
231: 제1주입구 232: 제2주입구
233: 제3주입구 234,235,236: 덮개
240: 이형유도볼트 241: 볼트축
300: 위치조절기구 310: 지지 브라켓
311: 구멍 320: 높이 조절 볼트
330: 너트 340: 보조 브라켓
400: 보강철근
<Explanation of symbols for main parts of the drawing>
10: concrete road 20: rail
30: chipping part 100: lower mold
101,102,103,104: section steel 200: upper formwork
231: first inlet 232: second inlet
233: third inlet 234,235,236: cover
240: deformed induction bolt 241: bolt shaft
300: positioning mechanism 310: support bracket
311: hole 320: height adjustment bolt
330: nut 340: auxiliary bracket
400: rebar

Claims (7)

콘크리트 도상에 함몰된 구조로 형성된 치핑부(30)의 바로 위에서 치핑부(30)의 둘레를 따라 연장되는 벽을 형성하도록 콘크리트 도상에 고정되게 설치되는 하부 형틀(100);
상기 하부 형틀(100)의 개방된 상부를 덮어주면서 침목의 상면을 형성하도록 하부 형틀(100)에 조립되어 하부 형틀(100)과 함께 침목의 성형을 위한 공간을 형성하도록 이루어지되, 하부 형틀(100)에 결합된 채로 상하로 이동하면서 침목의 높이가 조절되게 하는 상부 형틀(200); 및
상기 하부 형틀(100)과 상부 형틀(200)을 연결하며, 작업자의 조작에 의해 작동하면서 상부 형틀(200)을 상하로 이동시켜 상부 형틀(200)의 높이를 조절하는 위치조절기구(300);로 구성되며,
상기 위치조절기구(300)는,
상부 형틀(200)의 선단부 좌우 양측 그리고 후단부 좌우 양측에서 수평방향으로 돌출되게 형성된 지지 브라켓(310);
수직한 자세로 상기 지지 브라켓(310)을 관통하도록 설치되고, 하단부가 하부 형틀(100) 또는 콘크리트 도상에 닿으며, 상기 지지 브라켓(310)에 나사 결합되거나 하나 이상의 너트(330)를 매개로 지지 브라켓(310)에 결속되는 높이 조절 볼트(320);로 구성된 것을 특징으로 하는 콘크리트 도상 보수용 침목 거푸집.
a lower formwork 100 that is fixedly installed on the concrete ballast to form a wall extending along the periphery of the chipping part 30 just above the chipping part 30 formed in a recessed structure on the concrete ballast;
It is assembled to the lower formwork 100 so as to form the upper surface of the sleeper while covering the open upper part of the lower formwork 100 to form a space for molding the sleeper together with the lower formwork 100, the lower formwork 100 ) while moving up and down while being coupled to the upper frame 200 to adjust the height of the sleeper; and
a position adjusting mechanism that connects the lower formwork 100 and the upper formwork 200, and controls the height of the upper formwork 200 by moving the upper formwork 200 up and down while operating by the operator's operation (300); is composed of
The position adjustment mechanism 300,
Support brackets 310 formed to protrude in the horizontal direction from both left and right sides of the front end and left and right sides of the rear end of the upper frame 200;
It is installed to penetrate the support bracket 310 in a vertical posture, the lower end touches the lower formwork 100 or the concrete ballast, and is screwed to the support bracket 310 or supported through one or more nuts 330 . A sleeper formwork for concrete ballast repair, characterized in that it comprises; a height adjustment bolt (320) bound to the bracket (310).
삭제delete 청구항 1에 있어서,
상기 지지 브라켓(310)은 높이 조절 볼트(320)가 관통하도록 형성된 구멍(311)의 일부가 외측 방향으로 개방되도록 일부분이 절개되게 형성되고,
상기 하부 형틀(100)에는 높이 조절 볼트(320)의 하단부가 관통하면서 높이 조절 볼트(320)를 정위치에서 지지하는 다수의 보조 브라켓(340)이 수평 방향으로 돌출되게 형성된 것을 특징으로 하는 콘크리트 도상 보수용 침목 거푸집.
The method according to claim 1,
The support bracket 310 is formed in such a way that a portion of the hole 311 formed through the height adjustment bolt 320 is opened in an outward direction,
Concrete ballast, characterized in that a plurality of auxiliary brackets 340 for supporting the height adjustment bolt 320 in a fixed position while passing through the lower end of the height adjustment bolt 320 are formed in the lower formwork 100 to protrude in the horizontal direction Repair sleeper formwork.
삭제delete 청구항 1에 있어서,
상기 치핑부(30)의 바닥에 하단부가 고정되고, 상단부가 상부 형틀(200)의 안쪽에 위치하도록 치핑부(30)에 설치되어 침목 성형을 위해 타설되는 몰탈에 매립되면서 콘크리트 도상과 침목의 결속력을 높이는 다수의 보강철근(400)을 더 포함하는 것을 특징으로 하는 콘크리트 도상 보수용 침목 거푸집.
The method according to claim 1,
The lower end is fixed to the bottom of the chipping unit 30 , and the upper end is installed in the chipping unit 30 so that it is located inside the upper mold 200 , and is embedded in the mortar poured for forming the sleeper, and the bonding force between the concrete ballast and the sleeper Concrete ballast repair sleeper formwork, characterized in that it further comprises a plurality of reinforcing bars 400 to increase the.
청구항 1에 있어서,
상기 상부 형틀(200)에 설치되어 상부 형틀(200)과 신설침목의 분리를 돕는 하나 이상의 이형유도볼트(240)를 더 포함하되,
상기 이형유도볼트(240)는 수직한 자세로 상부 형틀(200)을 관통한 채로 상부 형틀(200)에 나사결합되어 회전에 의해 상하로 이동하는 볼트축(241)을 포함하는 것을 특징으로 하는 콘크리트 도상 보수용 침목 거푸집.
The method according to claim 1,
It further includes one or more release induction bolts 240 installed on the upper formwork 200 to help separate the upper formwork 200 from the new sleeper,
The release inducing bolt 240 is screwed to the upper formwork 200 while penetrating the upper formwork 200 in a vertical posture and includes a bolt shaft 241 that moves up and down by rotation Concrete Sleeper formwork for ballast repair.
청구항 1에 있어서,
상기 하부 형틀(100)은 4개의 형강재(101,102,103,104)가 사각의 평면구조를 형성하도록 서로 연결된 것으로 이루어지되, 어느 한 형강재(101,102,103,104)는 양 끝단이 인접한 다른 두 형강재(101,102,103,104)와 분리 가능한 구조로 조립되어 해당 형강재(101,102,103,104)의 분리를 통해 상부 형틀(200)이 하부 형틀(100)의 측면부로 빠져나오는 공간을 형성하도록 이루어진 것을 특징으로 하는 콘크리트 도상 보수용 침목 거푸집.
The method according to claim 1,
The lower formwork 100 consists of four section steel members 101, 102, 103, and 104 connected to each other to form a rectangular planar structure. The sleeper formwork for concrete ballast repair, characterized in that it is assembled into a structure and formed to form a space through which the upper formwork 200 exits to the side part of the lower formwork through separation of the corresponding section members (101,102,103,104).
KR1020210046588A 2021-04-09 2021-04-09 Form for repairing sleeper on concrete bed KR102283153B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020210046588A KR102283153B1 (en) 2021-04-09 2021-04-09 Form for repairing sleeper on concrete bed

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020210046588A KR102283153B1 (en) 2021-04-09 2021-04-09 Form for repairing sleeper on concrete bed

Publications (1)

Publication Number Publication Date
KR102283153B1 true KR102283153B1 (en) 2021-07-29

Family

ID=77127542

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020210046588A KR102283153B1 (en) 2021-04-09 2021-04-09 Form for repairing sleeper on concrete bed

Country Status (1)

Country Link
KR (1) KR102283153B1 (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200288352Y1 (en) * 2002-06-05 2002-09-11 궤도공영 주식회사 a support for a mold to construct a concrete roadbed in railroad
KR20170109358A (en) * 2016-03-21 2017-09-29 (주)엘더스티앤엘 concrete ballast turnout construction method
KR102199351B1 (en) 2020-06-10 2021-01-06 김광문 Recovery systmes for concret tracks on sank road-bed and construction method thereof

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200288352Y1 (en) * 2002-06-05 2002-09-11 궤도공영 주식회사 a support for a mold to construct a concrete roadbed in railroad
KR20170109358A (en) * 2016-03-21 2017-09-29 (주)엘더스티앤엘 concrete ballast turnout construction method
KR102199351B1 (en) 2020-06-10 2021-01-06 김광문 Recovery systmes for concret tracks on sank road-bed and construction method thereof

Similar Documents

Publication Publication Date Title
US7381008B2 (en) Disk plate concrete dowel system
EP1700954A2 (en) Prefabricated modular member, permanent railway for tramways and subways including said member, and process for laying the same
KR102273901B1 (en) Method for repairing sleeper on concrete bed
US6237856B1 (en) Method for installing a steady rail track
KR20040030113A (en) Method for the continuous laying of a rail on a rigid track, in addition to an alignment device and a rigid track
CN106758879B (en) A method of for runing the correction of high-speed railway bridge ballastless track structure
EP1123443A1 (en) Method for manufacturing a ground slab field and a ground slab field
KR100757958B1 (en) Insert reclamation apparatus for construction of linear induction motor panel in linear induction motor
JP2018112009A (en) Vertical member installation structure, vertical member installation method, and precast vertical member
KR100454405B1 (en) Method for changing steel bridge of supporting rail into concreat bridge
KR100556219B1 (en) A method for changing plate-girder bridge of railway bridge into slab bridge by using temporary construction bents.
JP4934779B2 (en) Boarding / exit structure and boarding / exiting method
KR20060091615A (en) Railroad crane and method for carrying out replacement of an upper structure of a railway bridge utilizing the same
KR20190034815A (en) Railroad bridge construction method for keeping preexistence railroad track and rail service
SE434862B (en) SETTING UP TO ARRANGEMENT FOR PLAN CROSSING PLATFOR AT A TRANSFER TRANSFER TO RAILWAY SAVINGS
KR102283153B1 (en) Form for repairing sleeper on concrete bed
KR101405468B1 (en) Method for manufacturing concrete block for railway track and method for laying railway track using concrete block manufactured by the same method
KR102501040B1 (en) Method For Constructing Embedded Rail Track
KR102212757B1 (en) Concrete track construction method that can be used suitably for a rapid improvement of ballast track, and concrete slab support device and railway building device for the same
JP2009161961A (en) Gutter and method of constructing gutter
JP2019078065A (en) Laying method of cantilever-type retaining wall
WO2003014479A1 (en) Prefabricated unit for refurbishment or construction of platforms
KR100729842B1 (en) Repair work of railroad bridge and that structure
JP2022081909A (en) Concrete sleeper installation device
CN1198016C (en) Road surface for quick transportation