KR102247344B1 - Method for constructing vertical structure in vertical tunnel using top down method - Google Patents

Method for constructing vertical structure in vertical tunnel using top down method Download PDF

Info

Publication number
KR102247344B1
KR102247344B1 KR1020200079222A KR20200079222A KR102247344B1 KR 102247344 B1 KR102247344 B1 KR 102247344B1 KR 1020200079222 A KR1020200079222 A KR 1020200079222A KR 20200079222 A KR20200079222 A KR 20200079222A KR 102247344 B1 KR102247344 B1 KR 102247344B1
Authority
KR
South Korea
Prior art keywords
vertical sphere
vertical
precast concrete
construction method
ground
Prior art date
Application number
KR1020200079222A
Other languages
Korean (ko)
Inventor
고엄식
Original Assignee
주식회사 네오시티
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 네오시티 filed Critical 주식회사 네오시티
Priority to KR1020200079222A priority Critical patent/KR102247344B1/en
Priority to KR1020200189716A priority patent/KR102368269B1/en
Application granted granted Critical
Publication of KR102247344B1 publication Critical patent/KR102247344B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/04Lining shafts; Linings therefor with brick, concrete, stone, or similar building materials
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor
    • E02D29/121Manhole shafts; Other inspection or access chambers; Accessories therefor characterised by the connection between shaft elements, e.g. of rings forming said shaft
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • E21D11/083Methods or devices for joining adjacent concrete segments
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D5/00Lining shafts; Linings therefor
    • E21D5/12Accessories for making shaft linings, e.g. suspended cradles, shutterings

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Mechanical Engineering (AREA)
  • Architecture (AREA)
  • Environmental & Geological Engineering (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention relates to a method for constructing a vertical structure using a top-down method, which is able to be constructed by lowering a vertical wall from on the ground toward a lower side of a vertical hole at the same time as excavating the vertical hole. In accordance with the present invention, the method for constructing the vertical structure using the top-down method comprises: a first step to install a temporary structure (100) on the ground; a second step to bury support structures at regular intervals along an inner edge of the temporary structure a third step to install a lowering inducing member (300) on an upper side of the temporary structure; a fourth step to placing the vertical wall (B) on the lowering inducing member at the same time as excavating the vertical hole to a certain depth in the temporary structure; a fifth step to remove an upper end of the support structures exposed to an upper side as much as a certain depth; a sixth step in which the lowering inducing member lowers the vertical wall into the vertical hole for a certain depth; and a seventh step to repeat the fourth to the sixth steps until the vertical wall reaches the target depth.

Description

하향식 공법을 이용한 수직구 구조물의 시공방법{Method for constructing vertical structure in vertical tunnel using top down method}Method for constructing vertical structure in vertical tunnel using top down method}

본 발명은 수직구의 굴착과 동시에 수직구 벽체를 지상에서 수직구 하부로 하강시키면서 시공이 이루어지는 하향식 공법을 이용한 수직구 구조물의 시공방법에 관한 것이다.The present invention relates to a construction method of a vertical sphere structure using a top-down method in which construction is performed while the vertical sphere wall is lowered from the ground to the bottom of the vertical sphere at the same time as the vertical sphere is excavated.

일반적으로 수직구는 터널을 굴착하기 위하여 지상으로부터 지하 터널까지 수직으로 연결해 주는 일종의 수직터널로서, 터널 공사시에는 각종 장비 및 건설 자재들을 지상으로부터 운반 및 이동시키고 터널 굴착시 발생한 토사와 암반을 지상으로 배출하는 통로 역할을 하며, 터널이 완성된 후에는 관리자의 이동통로 및 통신구나 전력구의 각종 케이블을 지하 터널로부터 지상으로 연결시켜 주고 각종 배관을 연결시켜 주는 역할을 한다.In general, a vertical hole is a type of vertical tunnel that connects vertically from the ground to an underground tunnel in order to excavate a tunnel. During tunnel construction, various equipment and construction materials are transported and moved from the ground, and the soil and rock generated during tunnel excavation are discharged to the ground. After the tunnel is completed, it connects the mobile passage of the manager and various cables of communication or power outlets from the underground tunnel to the ground and connects various pipes.

이러한 수직구는 터파기 후 외곽부에 가설 흙막이벽을 설치하고, 가설 흙막이벽에 걸리는 하중을 버팀대로 지탱하면서 지하 맨 하부쪽에서부터 상부측으로 구축해 올라가는 전통적인 공법을 통해 구조물을 시공하게 되나, 수시로 드나드는 공사차량의 정차로 인해 교통체증을 유발하고 인근 주변에 피해를 주기 때문에 대도시와 같이 건물이 부지경계선 가까이 근접하게 위치되어 있는 경우에 상기 공법을 적용하는데 많은 문제점이 있고, 가설흙막이 벽 설치시에 함께 설치되는 버팀대는 구조물 공사로 인한 공정의 복잡성과 작업의 위험성과 폐기물의 발생 등 여러 가지 문제점들이 발생하기 때문에 최근에는 토지 이용효율을 높이면서 공기가 빠르고 경제적이며, 구조적으로 안전한 하향식 공법(Top-Down Method)이 각광을 받고 있다.These vertical spheres are constructed through the traditional method of installing temporary dirt walls on the outer periphery after digging, and building up from the bottom of the basement to the upper side while supporting the load on the temporary dirt walls with a brace. There are many problems in applying the above construction method when the building is located close to the site boundary line, such as in a large city, because it causes traffic congestion due to vehicle stopping and damages the surrounding area. The brace is a top-down method that has a fast, economical, and structurally safe construction process while increasing land use efficiency and increasing land use efficiency because various problems such as the complexity of the process due to the construction of the structure, the risk of work, and the generation of waste occur. ) Is in the limelight.

하향식 공법을 이용한 수직구 구조물의 시공방법으로는 특허 제1859367호를 통해 개시된 "하향식 공법을 이용한 수직구 구조물의 시공방법"이 알려져 있다.As a construction method of a vertical sphere structure using a top-down construction method, a "construction method of a vertical sphere structure using a top-down construction method" disclosed through Patent No. 1885367 is known.

상기한 종래의 하향식 공법을 이용한 수직구 구조물의 시공방법은 지상에 가설구조물을 설치하고, 가설구조물에 가설대를 설치한 다음 가설구조물의 내부에서 수직구를 굴착함과 동시에 상기 가설대를 통해 제1수직구 벽체를 성형한다. 그리고 제1수직구 벽체를 수직구 내부로 일정 깊이 하강시키고 상기 제1수직구 벽체의 상단에 제2수직구 벽체를 성형한다. 그리고 상기 제2수직구 벽체를 제1수직구와 함께 동반 하강시키는 방법으로 수직구 구조물을 시공하도록 되어 있다.In the above-described conventional top-down construction method, a temporary structure is installed on the ground, a temporary structure is installed on the temporary structure, and a vertical sphere is excavated from the inside of the temporary structure. 1 Mold the vertical sphere wall. Then, the first vertical sphere wall is lowered to a certain depth into the vertical sphere, and a second vertical sphere wall is formed on the upper end of the first vertical sphere wall. In addition, the vertical sphere structure is constructed by lowering the wall of the second vertical sphere together with the first vertical sphere.

그러나 이와 같은 종래의 하향식 공법을 이용한 수직구 구조물의 시공방법에 따르면, 수직구의 지반이 연약할 경우, 하강하는 수직구 벽체들이 수평상태를 이루지 못하고 일측으로 기울어지는 문제가 발생된다.However, according to the conventional construction method of the vertical sphere structure using the top-down construction method, when the ground of the vertical sphere is soft, the descending vertical sphere walls do not achieve a horizontal state and are inclined to one side.

이 경우, 기울어진 수직구 벽체를 수평상태로 위치조정을 해야 하므로 공기가 지연되고 안전사고가 발생하는 등 여러가지 문제가 발생한다.In this case, since it is necessary to adjust the position of the inclined vertical sphere wall in a horizontal state, various problems arise, such as delays in air and safety accidents.

뿐만 아니라, 수직구 벽체가 기울어지면서 수직구 벽면과 충돌하여 균열이 발생되는 경우가 종종 발생되는데, 이 경우 완성되는 수직구 구조물의 내구성에 심각한 악영향을 미치는 것은 물론 균열된 부분으로 수직구 벽체 내부로 지하수가 유입되므로 대책마련이 매우 시급한 실정이다.In addition, when the vertical sphere wall is inclined and collides with the vertical sphere wall, cracks often occur.In this case, the durability of the completed vertical sphere structure is severely adversely affected, as well as the cracked part inside the vertical sphere wall. As groundwater flows in, it is very urgent to prepare a countermeasure.

본 발명은 상기한 문제점들을 해결하기 위해 안출된 것으로서, 하강하는 수직구 벽체들이 일측으로 기울어지지 않고 수평상태를 유지하면서 안정적으로 하강되는 하향식 공법을 이용한 수직구 구조물의 시공방법을 제공하는데 그 목적이 있다.The present invention has been conceived to solve the above problems, and provides a method of constructing a vertical sphere structure using a top-down method in which the descending vertical sphere walls are not inclined to one side and are stably descended while maintaining a horizontal state. have.

상기 목적을 달성하기 위해, 본 발명의 하향식 공법을 이용한 수직구 구조물의 시공방법은 지상에 가설구조물이 설치되는 제1단계와, 상기 가설구조물의 내측 가장자리를 따라 일정간격으로 지지구조물이 매설되는 제2단계와, 상기 가설구조물의 상부에 설치되는 유압잭과 상기 지지구조물의 상단에 지지되는 슈와, 상기 유압잭과 슈를 슈직으로 연결하는 잭로드와 상기 슈의 하부에 설치된 승강부재를 구비한 하강유도부재가 설치되는 제3단계와, 상기 가설구조물의 내부에서 수직구가 일정 깊이로 굴착됨과 동시에 상기 하강유도부재에 수직구 벽체가 거치되는 제4단계와, 일정 깊이만큼 상부로 노출된 지지구조물의 상단이 제거되는 제5단계와, 상기 하강유도부재가 상기 수직구 벽체를 수직구 내부로 일정 깊이 하강시키는 제6단계와, 상기 수직구 벽체가 목표 깊이에 도달할 때까지 상기 제4단계 내지 제6단계가 반복되는 제7단계를 포함한다.In order to achieve the above object, the construction method of the vertical sphere structure using the top-down construction method of the present invention includes a first step in which a temporary structure is installed on the ground, and a support structure is buried at regular intervals along the inner edge of the temporary structure. Step 2, a hydraulic jack installed on the upper part of the temporary structure, a shoe supported on the upper end of the support structure, a jack rod connecting the hydraulic jack and the shoe by a shoe, and a descending guide provided with an elevating member installed at the lower part of the shoe. The third step in which the member is installed, the fourth step in which the vertical sphere is excavated to a certain depth inside the temporary structure, and the vertical ball wall is mounted on the descending guide member, and the support structure exposed to the top by a certain depth. A fifth step in which the upper end is removed, a sixth step in which the descending induction member lowers the vertical sphere wall to a certain depth into the vertical sphere, and the fourth to fourth steps until the vertical sphere wall reaches a target depth. It includes a seventh step in which step six is repeated.

또한, 상기 지지구조물은 지상에서 암반지반까지 형성시킨 굴착공에 콘크리트를 현장 타설하여 성형한 콘크리트 파일일 수 있다.In addition, the support structure may be a concrete pile formed by casting concrete on-site in an excavation hole formed from the ground to the rocky ground.

이 경우, 상기 제5단계는 상부로 노출된 콘크리트 파일의 상단이 커터기를 통해 절단되는 단계와 상부로 노출된 콘크리트 파일의 상단이 제거될 때 마다 해당 하강유도부재의 승강부재가 하강되면서 콘크리트 파일의 절단상면에 지지되는 단계가 각 콘크리트 파일별로 순차적으로 이루어지고, 상기 제6단계는 하강된 모든 승강부재가 상승되는 단계를 포함하는 것이 바람직하다.In this case, the fifth step is a step in which the upper end of the concrete pile exposed to the top is cut through a cutter machine, and each time the upper end of the concrete pile exposed to the upper end is removed, the lifting member of the corresponding lowering guide member descends, It is preferable that the step of being supported on the cut top surface is sequentially performed for each concrete pile, and the sixth step includes the step of raising all the lowered lifting members.

또한, 상기 지지구조물은 지상에서 암반지반까지 형성시킨 굴착공에 삽입되는 프리캐스트 콘크리트 세그먼트 적층 조립체일 수도 있다.In addition, the support structure may be a precast concrete segment laminated assembly inserted into an excavation hole formed from the ground to the rocky ground.

이 경우, 상기 제3단계에서 하강유도부재의 승강부재는 1단 하강된 상태로 프리캐스트 콘크리트 세그먼트 적층 조립체의 상단에 지지되며, 상기 제5단계가 승강부재가 1단 상승하는 단계와 상부로 노출된 프리캐스트 콘크리트 세그먼트가 프리캐스트 콘크리트 세그먼트 적층 조립체로부터 분리되어 제거되는 단계와 상기 프리캐스트 콘크리트 세그먼트가 제거된 프리캐스트 콘크리트 세그먼트 적층 조립체의 분리상면에 승강부재가 2단 하강되면서 지지되는 단계가 각 프리캐스트 콘크리트 세그먼트 적층 조립체 별로 순차적으로 이루어지며, 상기 제6단계가 2단 하강된 모든 승강부재가 1단으로 수축되는 단계를 포함한다.In this case, in the third step, the lifting member of the descending guide member is supported on the top of the precast concrete segment stacking assembly in a state that is lowered by one step, and the fifth step is the step of raising the lifting member by one step and exposing it to the top. The step of separating and removing the precast concrete segment from the precast concrete segment stacking assembly and the step of supporting the lifting member by descending two steps on the separating upper surface of the precast concrete segment stacking assembly from which the precast concrete segment has been removed are each precast. It is made sequentially for each cast concrete segment laminated assembly, and the sixth step includes a step in which all the lifting members lowered in two stages are contracted to one stage.

한편, 상기 프리캐스트 콘크리트 세그먼트들은 핀 결합을 통해 착탈가능하게 조립되며, 상기 프리캐스트 콘크리트 세그먼트들의 상단과 하단에는 각각 핀 끼움공이 형성된 결합돌기가 수직구의 내측 방향으로 돌출형성될 수 있다.On the other hand, the precast concrete segments are detachably assembled through pin coupling, and coupling protrusions having pin fitting holes respectively formed at upper and lower ends of the precast concrete segments may protrude in the inner direction of the vertical sphere.

이 경우, 상기 프리캐스트 콘크리트 세그먼트들의 하단에는 수직구의 내측 방향으로 슬라이딩 홈부가 형성되고 상단에는 상기 슬라이딩 홈부에 대응되는 슬라이딩 돌출부가 형성되는 것이 바람직하다.In this case, it is preferable that a sliding groove portion is formed at the lower end of the precast concrete segments in the inward direction of the vertical sphere, and a sliding protrusion corresponding to the sliding groove portion is formed at the upper end of the precast concrete segments.

한편, 상기 승강부재는 유압실린더일 수 있다.Meanwhile, the elevating member may be a hydraulic cylinder.

또한, 상기 지지구조물의 상단에는 모든 승강부재들이 동일수평선에 위치하도록 높이를 조절시켜 주는 높이조절블록이 더 구비될 수도 있다.In addition, a height adjustment block may be further provided at the upper end of the support structure to adjust the height so that all the lifting members are located on the same horizontal line.

한편, 상기 제3단계에서 하강유도부재의 승강부재는 1단 하강된 상태로 프리캐스트 콘크리트 세그먼트 적층 조립체의 상단에 고정되며, 상기 제5단계는 승강부재가 1단 상승하면서 고정된 프리캐스트 콘크리트 세그먼트를 인양하는 단계와 인양된 프리캐스트 콘크리트 세그먼트가 승강부재로부터 분리되어 제거되는 단계와 상기 프리캐스트 콘크리트 세그먼트가 제거된 프리캐스트 콘크리트 세그먼트 적층 조립체의 분리상면에 승강부재가 2단 하강되면서 지지되는 단계가 각 프리캐스트 콘크리트 세그먼트 적층 조립체 별로 순차적으로 이루어지며, 상기 제6단계는 2단 하강된 모든 승강부재가 1단으로 수축되는 단계를 포함할 수도 있다.On the other hand, in the third step, the lifting member of the descending guide member is fixed to the top of the precast concrete segment stacking assembly in a state of being lowered one step, and the fifth step is the precast concrete segment fixed while the lifting member rises one step. The step of lifting the lifted precast concrete segment and removing the lifted precast concrete segment from the lifting member, and the step of supporting the lifting member while descending two steps on the separating upper surface of the precast concrete segment stacking assembly from which the precast concrete segment was removed. It is made sequentially for each precast concrete segment stacking assembly, and the sixth step may include a step in which all the lifting members lowered in two stages are contracted to one stage.

이 경우, 상기 승강부재의 하단에는 제1핀부재가 수직으로 구비되고, 상기 프리캐스트 콘크리트 세그먼트들의 상단에는 상기 제1핀부재가 삽입되는 수직핀홀이 형성되며, 상기 프리캐스트 콘크리트 세그먼트들의 측방에는 상기 수직핀홀과 연통되는 수평핀홀이 형성되고, 상기 수평핀홀에는 상기 제1핀부재에 끼워져 결합됨과 함께 상기 수평핀홀 외부로 단부가 노출되는 제2핀부재가 삽입되며, 상기 제2핀부재의 노출 단부는 상기 제2핀부재의 유동을 막아주는 Ÿ‡지가 끼워져 결합될 수 있다.In this case, a first pin member is vertically provided at the lower end of the elevating member, a vertical pin hole into which the first pin member is inserted is formed at the upper end of the precast concrete segments, and the side of the precast concrete segments A horizontal pinhole communicating with the vertical pinhole is formed, and a second pin member is inserted into the horizontal pinhole and coupled to the first pin member and the end is exposed outside the horizontal pinhole, and the exposed end of the second pin member May be coupled by inserting a paper sheet that prevents the flow of the second pin member.

아울러, 상기 프리캐스트 콘크리트 세그먼트들의 하단에는 돌부가 형성되고 상단에는 상기 돌부에 대응되는 홈부가 형성되는 것이 바람직하다.In addition, it is preferable that a protrusion is formed at a lower end of the precast concrete segments and a groove corresponding to the protrusion is formed at an upper end.

한편, 상기 프리캐스트 콘크리트 세그먼트들 중 최하단에 위치되는 프리캐스트 콘크리트 세그먼트의 하단은 하부로 수렴하는 첨예부로 이루어지는 것이 바람직하다.On the other hand, it is preferable that the lower end of the precast concrete segment located at the lower end of the precast concrete segments is made of a sharpened portion that converges downward.

상기와 같이 구성된 본 발명은 수직구 벽체가 매설된 지지구조물를 통해 항상 수평상태로 지지되고 있기 때문에 목표 깊이까지 일측으로 기울어지지 않고 수평상태를 안정적으로 유지하면서 하강할 수 있는 효과가 있다.In the present invention configured as described above, since the vertical sphere wall is always supported in a horizontal state through a buried support structure, it is not inclined to one side to the target depth and can descend while stably maintaining the horizontal state.

도 1 및 도 2는 본 발명의 일실시예에 따른 하향식 공법을 이용한 수직구 구조물의 시공방법 순서대로 나타내는 단면도.
도 3은 도 2의 평면도.
도 4는 본 발명의 일실시예에 따른 하향식 공법을 이용한 수직구 구조물의 시공방법 순서대로 나타내는 단면도로서, 가설구조물에 하강유도부재가 설치된 상태를 나타내는 도면.
도 5 내지 도 7은 발명의 일실시예에 따른 하향식 공법을 이용한 수직구 구조물의 시공방법 순서대로 나타내는 단면도.
도 8은 본 발명의 다른 실시예에 따른 하향식 공법을 이용한 수직구 구조물의 시공방법을 나타내는 단면도.
도 9은 도 8의 프리캐스트 콘크리트 세그먼트의 분해사시도.
도 10 및 도 11은 본 발명의 다른 실시예에 따른 하향식 공법을 이용한 수직구 구조물의 시공방법을 순서대로 나타내는 단면도.
도 12는 본 발명의 또 다른 실시예에 따른 프리캐스트 콘크리트 세그먼트의 분해사시도.
도 13 및 도 14는 본 발명의 또 다른 실시예에 따른 하향식 공법을 이용한 수직구 구조물의 시공방법을 순서대로 나타내는 단면도.
1 and 2 are cross-sectional views sequentially showing a construction method of a vertical sphere structure using a top-down construction method according to an embodiment of the present invention.
Figure 3 is a plan view of Figure 2;
Figure 4 is a cross-sectional view showing the order of the construction method of the vertical sphere structure using a top-down construction method according to an embodiment of the present invention, a view showing a state in which a descending guide member is installed in a temporary structure.
5 to 7 are cross-sectional views showing in sequence a construction method of a vertical sphere structure using a top-down construction method according to an embodiment of the present invention.
8 is a cross-sectional view showing a construction method of a vertical ball structure using a top-down method according to another embodiment of the present invention.
Figure 9 is an exploded perspective view of the precast concrete segment of Figure 8;
10 and 11 are cross-sectional views sequentially showing a construction method of a vertical ball structure using a top-down construction method according to another embodiment of the present invention.
12 is an exploded perspective view of a precast concrete segment according to another embodiment of the present invention.
13 and 14 are cross-sectional views sequentially showing a construction method of a vertical ball structure using a top-down construction method according to another embodiment of the present invention.

본 발명의 특징 및 이점들은 첨부도면에 의거한 다음의 바람직한 실시예에 대한 상세한 설명으로 더욱 명백해질 것이다. 이에 앞서, 본 명세서 및 청구범위에 사용된 용어나 단어는 발명자가 그 자신의 발명을 가장 최선의 방법으로 설명하기 위해 용어의 개념을 적절하게 정의할 수 있다는 원칙에 입각하여 본 발명의 기술적 사상에 부합하는 의미와 개념으로 해석되어야만 한다.Features and advantages of the present invention will become more apparent from the detailed description of the following preferred embodiments based on the accompanying drawings. Prior to this, terms or words used in the present specification and claims are based on the principle that the inventor can appropriately define the concept of the term in order to describe his or her invention in the best way. It must be interpreted as a corresponding meaning and concept.

이하, 본 발명의 일 실시예를 도면을 참조하여 상세히 설명함에 있어, 동일한 구성에 대해서는 동일한 부호를 사용하며, 명료성을 위하여 가능한 중복되지 않게 상이한 부분만을 주로 설명한다.Hereinafter, in describing an embodiment of the present invention in detail with reference to the drawings, the same reference numerals are used for the same configuration, and only different parts will be mainly described so as not to overlap as possible for clarity.

본 발명에 따른 하향식 공법을 이용한 수직구 구조물의 시공방법은 지상에 가설구조물이 설치되는 제1단계와, 상기 가설구조물의 내측 가장자리를 따라 일정간격으로 지지구조물을 매설하는 제2단계와, 상기 가설구조물의 상부에 하강유도부재가 설치되는 제3단계와, 상기 가설구조물의 내부에서 수직구가 일정 깊이로 굴착됨과 동시에 상기 하강유도부재에 수직구 벽체가 거치되는 제4단계와, 일정 깊이만큼 상부로 노출된 지지구조물의 상단이 제거되는 제5단계와, 상기 하강유도부재가 상기 수직구 벽체를 수직구 내부로 일정 깊이 하강시키는 제6단계와 상기 수직구 벽체가 목표 깊이에 도달할 때까지 상기 제4단계 내지 제6단계가 반복되는 제7단계를 포함한다.The construction method of the vertical sphere structure using the top-down construction method according to the present invention includes a first step of installing a temporary structure on the ground, a second step of burying a support structure at regular intervals along the inner edge of the temporary structure, and the temporary structure. The third step in which the descending guide member is installed on the upper part of the structure, the fourth step in which the vertical sphere is excavated to a certain depth inside the temporary structure and the vertical sphere wall is mounted on the descending guide member, and the upper part by a certain depth. The fifth step of removing the upper end of the support structure exposed by the lowering member, the sixth step of lowering the vertical sphere wall by a predetermined depth into the vertical sphere, and the vertical sphere until the wall reaches a target depth. It includes a seventh step in which steps 4 to 6 are repeated.

도 1에 도시된 바와 같이, 수직구 구조물을 시공할 지상에 가설구조물(100)을 설치한다.As shown in Fig. 1, a temporary structure 100 is installed on the ground on which the vertical sphere structure is to be constructed.

상기 가설구조물(100)은 지상에서 이루어지는 일련의 작업들이 원활하게 수행되도록 견고한 바닥면을 제공한다.The temporary structure 100 provides a solid bottom surface to smoothly perform a series of operations on the ground.

상기 가설구조물(100)은 굴착될 수직구를 따라 링 형상으로 이루어지며 굴착할 수직구보다 큰 내경을 가진다. 상기 가설구조물(100)은 현장타설 콘크리트 구조물 또는 프리캐스트 콘크리트 세그먼트(210)를 조립체일 수 있다.The temporary structure 100 is formed in a ring shape along the vertical sphere to be excavated and has an inner diameter larger than the vertical sphere to be excavated. The temporary structure 100 may be an assembly of a cast-in-place concrete structure or a precast concrete segment 210.

도 2 및 도 3에 도시된 바와 같이, 가설구조물(100)의 설치가 완료되면, 상기 가설구조물(100)의 내측 가장자리를 따라 일정간격으로 지지구조물이 매설된다.2 and 3, when the installation of the temporary structure 100 is completed, the support structure is buried at regular intervals along the inner edge of the temporary structure 100.

이 경우, 상기 지지구조물들은 견고한 지지력을 발휘할 수 있도록 지상에서 암반지반(A)까지 굴착공을 형성시키고 상기 굴착공에 콘크리트를 현장 타설하여 성형한 콘크리트 파일(200a)일 수 있다.In this case, the support structures may be a concrete pile 200a formed by forming an excavation hole from the ground to the rock ground A so as to exert a solid support and placing concrete in the excavation hole on-site.

도 4에 도시된 바와 같이, 상기 콘크리트 파일(200a)의 매설이 완료되면, 가설구조물(100)의 상부에 하강유도부재(300)가 설치된다.As shown in FIG. 4, when the concrete pile 200a is completely buried, the descending guide member 300 is installed on the upper part of the temporary structure 100.

상기 하강유도부재(300)는 가설구조물(100)의 상부에 설치되는 유압잭(310)과, 상기 콘크리트 파일(200a)의 상단에 지지되는 슈(320)와, 상기 유압잭(310)과 슈(320)를 슈(320)직으로 연결하는 잭로드(330)와, 상기 슈(320)의 하부에 설치된 승강부재(340)를 구비한다.The descending guide member 300 includes a hydraulic jack 310 installed on the upper part of the temporary structure 100, a shoe 320 supported on an upper end of the concrete pile 200a, and the hydraulic jack 310 and shoe 320 ) And a jack rod 330 directly connecting the shoe 320, and an elevating member 340 installed under the shoe 320.

상기 승강부재(340)는 큰 구동력을 발휘할 수 있으면서 설치가 용이하고 정밀한 제어가 가능한 유압실린더가 바람직하다.The elevating member 340 is preferably a hydraulic cylinder capable of exerting a large driving force and easy installation and precise control.

도 5a에 도시된 바와 같이, 가설구조물(100)의 상부에 하강유도부재(300)의 설치가 완료되면, 가설구조물(100)의 내부로 포크레인과 같은 장비를 투입시켜 수직구를 일정깊이로 굴착함과 동시에 슈(320)의 상부에 수직구 벽체(B)를 거치시킨다.As shown in Figure 5a, when the installation of the descending guide member 300 on the upper part of the temporary structure 100 is completed, equipment such as a fork lane is inserted into the temporary structure 100 to excavate the vertical sphere to a certain depth. At the same time, the vertical sphere wall (B) is mounted on the upper portion of the shoe (320).

이 경우, 상시 수직구 벽체(B)는 프리캐스트 콘크리트 구조물일 수도 있고 상기 슈(320)의 상부에서 현장 타설 콘크리트 구조물일 수도 있다. 상기 잭로드(330)는 수직구 벽체(B) 사이를 통과하여 연결된다.In this case, the permanent vertical sphere wall (B) may be a precast concrete structure or may be a concrete structure cast in place from the top of the shoe (320). The jack rod 330 is connected through the vertical sphere walls (B).

이와 같이, 수직구의 굴착이 진행되는 동안 수직구 벽체(B)가 준비되므로 공기를 크게 단축시킬 수 있게 된다. In this way, since the vertical sphere wall (B) is prepared during the excavation of the vertical sphere, the air can be greatly shortened.

아울러, 상기 슈(320)는 암반지반(A)까지 매설된 콘크리트 파일(200a)에 의해 수평상태로 안정되게 지지되므로 슈(320)의 상부에 거치된 수직구 벽체(B) 역시 높은 하중에도 불구하고 일측으로 기울어지지 않고 수평상태를 안정적으로 유지하게 된다.In addition, since the shoe 320 is stably supported in a horizontal state by the concrete pile 200a buried up to the rock ground (A), the vertical sphere wall (B) mounted on the upper portion of the shoe (320) is also a high load. It does not tilt to one side and maintains the horizontal state stably.

도시하지는 않았으나, 매설된 콘크리트 파일(200a)들의 상단 높이가 일정하지 않을 경우에 상기 슈(320)가 일측으로 기울어지면서 수직구 벽체(B)를 수평상태로 지지할 수 없게 되므로 상기 콘크리트 파일(200a)의 상단에는 모든 승강부재(340)들이 동일수평선에 위치하도록 높이를 조절시켜 주는 높이조절블록이 더 구비될 수도 있다.Although not shown, when the height of the top of the buried concrete piles 200a is not constant, the shoe 320 is inclined to one side and the vertical ball wall B cannot be supported in a horizontal state, so the concrete pile 200a A height adjustment block for adjusting the height so that all the lifting members 340 are located on the same horizontal line may be further provided at the top of the ).

한편, 상기 수직구를 일정 깊이 굴착하게 되면 승강부재(340)를 지지하고 있는 콘크리트 파일(200a)의 상부가 일정 높이로 노출된다.On the other hand, when the vertical sphere is excavated to a certain depth, the upper part of the concrete pile 200a supporting the elevating member 340 is exposed to a certain height.

도 5b에 도시된 바와 같이, 수직구의 굴착과 수직구 벽체(B)의 거치가 완료되면, 일정 깊이만큼 상부로 노출된 콘크리트 파일(200a)의 상단을 제거한다.As shown in FIG. 5B, when the excavation of the vertical sphere and the mounting of the vertical sphere wall (B) are completed, the upper end of the concrete pile 200a exposed upward by a predetermined depth is removed.

즉, 상부로 노출된 콘크리트 파일(200a)의 상단을 커터기를 이용하여 절단한 다음, 절단된 콘크리트 파일(200a)의 상단을 수직구측으로 잡아 당겨 콘크리트 파일(200a)로부터 제거하는 것이다.That is, the upper end of the concrete pile 200a exposed to the top is cut using a cutter, and then the upper end of the cut concrete pile 200a is pulled toward the vertical sphere to be removed from the concrete pile 200a.

이러한 절단 작업은 각 콘크리트 파일(200a)마다 순차적으로 이루어지게 되는데 상부로 노출된 콘크리트 파일(200a)의 상단이 제거될 때 마다 해당 하강유도부재(300)의 승강부재(340)를 하강시켜 콘크리트 파일(200a)의 절단상면에 지지되도록 함으로써 수직구 벽체(B)의 지지가 변함없이 안정적으로 이루어지도록 한다.This cutting operation is performed sequentially for each concrete pile 200a. Whenever the upper end of the concrete pile 200a exposed to the top is removed, the lifting member 340 of the corresponding descending guide member 300 is lowered to lower the concrete pile. By being supported on the cut top surface of (200a), the support of the vertical sphere wall (B) is unchanged and stable.

도 5c 및 5d에 도시된 바와 같이, 이러한 방법으로 모든 콘크리트 파일(200a)의 상단이 제거되면, 하강유도부재(300)를 이용하여 수직구 벽체(B)를 일정 깊이로 하강시킨다.As shown in FIGS. 5C and 5D, when the upper ends of all the concrete piles 200a are removed in this way, the vertical sphere wall B is lowered to a predetermined depth using the descending guide member 300.

즉, 하강된 모든 승강부재(340)를 동시에 상승시키게 되면, 수직구 벽체(B)의 자중에 의해 상기 수직구 벽체(B)가 자연스럽게 수직구 내부로 일정 깊이 하강하게 되는 것이다.That is, when all the lowered lifting members 340 are simultaneously raised, the vertical sphere wall (B) naturally descends into the vertical sphere by a certain depth due to the weight of the vertical sphere wall (B).

이때, 승강부재(340)의 하단을 절단상면에 고정시켜 놓으면 승강부재(340)가 슈(320)를 잡아당기는 작용을 하게 되므로 보다 용이하게 수직구 벽체(B)가 하강하게 된다.At this time, if the lower end of the elevating member 340 is fixed to the cut upper surface, the elevating member 340 acts to pull the shoe 320 so that the vertical sphere wall (B) descends more easily.

도 6에 도시된 바와 같이, 상기와 같은 방법으로 상기 수직구 벽체(B)가 목표 깊이에 도달할 때까지, 수직구를 일정 깊이로 굴착하고 하강유도부재(300)에 수직구 벽체(B)를 거치시킨 다음, 일정 깊이만큼 상부로 노출된 콘크리트 파일(200a)의 상단을 제거하고, 상기 수직구 벽체(B)를 수직구 내부로 일정 깊이 하강시키는 과정을 반복한다.As shown in Fig. 6, the vertical sphere wall (B) is excavated to a predetermined depth until the vertical sphere wall (B) reaches the target depth in the same manner as described above, and the vertical sphere wall (B) is placed on the descending guide member (300). After mounting, the upper end of the concrete pile 200a exposed to the top by a predetermined depth is removed, and the process of lowering the vertical sphere wall (B) into the vertical sphere by a predetermined depth is repeated.

이후, 슈(320)와 승강부재(340)를 철거하고 수직구의 바닥에 콘크리트를 타설하여 바닥면(C)을 시공한 다음, 지상에 설치된 하강유도부재(300)와 가설구조물(100)을 철거하고 수직구와 수직구 벽체에 콘크리트를 타설하여 틈새(D)를 메우면, 도 7에 도시된 바와 같이 수직구 구조물의 시공이 완료된다.Thereafter, the shoe 320 and the elevating member 340 are removed, concrete is poured into the bottom of the vertical sphere to construct the floor surface (C), and then the descending guide member 300 and the temporary structure 100 installed on the ground are demolished. Then, when concrete is poured into the vertical sphere and the vertical sphere wall to fill the gap (D), the construction of the vertical sphere structure is completed as shown in FIG. 7.

이와 같이, 본 발명은 수직구 벽체(B)가 매설된 콘크리트 파일(200a)을 통해 수평상태로 지지되므로 목표 깊이까지 수직구 벽체(B)들이 일측으로 기울어지지 않고 수평상태를 유지하면서 안정적으로 하강하게 된다.As described above, the present invention is supported in a horizontal state through the concrete pile 200a in which the vertical sphere wall (B) is embedded, so that the vertical sphere wall (B) is stably descended while maintaining the horizontal state without inclining to one side to the target depth. It is done.

도 8 및 도 9에 도시된 바와 같이, 본 발명의 다른 실시예로서, 상기 지지구조물들은 지상에서 암반지반(A)까지 형성시킨 굴착공에 삽입되는 프리캐스트 콘크리트 세그먼트 적층 조립체(200b)일 수도 있다.8 and 9, as another embodiment of the present invention, the support structures may be a precast concrete segment lamination assembly 200b inserted into an excavation hole formed from the ground to the rock ground (A). .

이 경우, 상기 프리캐스트 콘크리트 세그먼트(210)들의 상단과 하단에 각각 핀 끼움공(212)이 형성된 결합돌기(211)가 수직구의 내측 방향으로 돌출 형성되면, 상부의 프리캐스트 콘크리트 세그먼트(210)의 하단에 형성된 핀 끼움공(212)과 하부의 프리캐스트 콘크리트 세그먼트(210)의 상단에 형성된 핀 끼움공(212)에 핀(220)을 끼우고 핀(220)이 빠지지 않도록 핀(200)의 하부에 Ÿ‡지(230)를 삽입하여 상기 프리캐스트 콘크리트 세그먼트(210)들을 매우 용이하게 결합시킬 수 있다.In this case, when the coupling protrusions 211 having pin fitting holes 212 formed at the upper and lower ends of the precast concrete segments 210, respectively, are formed to protrude in the inner direction of the vertical sphere, the upper precast concrete segment 210 The pin 220 is inserted into the pin fitting hole 212 formed at the bottom and the pin fitting hole 212 formed at the upper end of the precast concrete segment 210 at the lower portion of the pin 200 so that the pin 220 does not come off. The precast concrete segments 210 can be joined very easily by inserting the paper 230 into the wall.

아울러, 상기 프리캐스트 콘크리트 세그먼트(210)들의 하단에는 수직구의 내측 방향으로 슬라이딩 홈부(240)가 형성되고 상단에는 상기 슬라이딩 홈부(240)에 대응되는 슬라이딩 돌출부(250)가 형성되는 것이 바람직하다.In addition, it is preferable that a sliding groove part 240 is formed at the lower end of the precast concrete segments 210 in the inner direction of the vertical sphere, and a sliding protrusion 250 corresponding to the sliding groove part 240 is formed at the upper end.

이 경우, 핀(220)을 핀 끼움공(212)으로부터 분리한 후 상부의 프리캐스트 콘크리트 세그먼트(210)를 쉽게 프리캐스트 콘크리트 세그먼트 적층 조립체(200b)로부터 제거할 수 있다.In this case, after separating the pin 220 from the pin fitting hole 212, the upper precast concrete segment 210 can be easily removed from the precast concrete segment stacking assembly 200b.

도 10에 도시된 바와 같이, 상기 지지구조물이 프리캐스트 콘크리트 세그먼트 적층 조립체(200b)인 경우에 있어서, 하강유도부재(300)가 설치될 때 상기 승강부재(340)는 1단 하강된 상태로 프리캐스트 콘크리트 세그먼트 적층 조립체(200b)의 상단에 지지된다.As shown in FIG. 10, in the case where the support structure is a precast concrete segment stacking assembly 200b, when the descending induction member 300 is installed, the elevating member 340 is freely lowered by one stage. It is supported on the top of the cast concrete segment laminate assembly 200b.

그리고, 일정 깊이만큼 상부로 노출된 콘크리트 세그먼트 적층 조립체(200b)의 상단을 제거할 경우, 도 11a에 도시된 바와 같이, 승강부재(340)를 1단 상승시킨 다음, 상부로 노출된 프리캐스트 콘크리트 세그먼트(210)를 프리캐스트 콘크리트 세그먼트 적층 조립체(200b)로부터 분리하여 제거한다.And, when removing the upper end of the concrete segment laminate assembly (200b) exposed to the top by a certain depth, as shown in Figure 11a, the lifting member 340 is raised one step, and then the precast concrete exposed to the top The segment 210 is separated and removed from the precast concrete segment laminate assembly 200b.

도 11b에 도시된 바와 같이, 이러한 프리캐스트 콘크리트 세그먼트(210)의 제거작업은 각 프리캐스트 콘크리트 세그먼트 적층 조립체(200b) 별로 순차적으로 이루어지는데, 상부로 노출된 프리캐스트 콘크리트 세그먼트(210)가 제거될 때마다. 1단 상승한 승강부재(340)를 2단 하강시켜 프리캐스트 콘크리트 세그먼트 적층 조립체(200b)의 분리상면에 지지되도록 함으로써 수직구 벽체(B)의 지지가 변함없이 안정적으로 이루어지도록 한다.As shown in FIG. 11B, the removal operation of the precast concrete segment 210 is sequentially performed for each precast concrete segment stacking assembly 200b, and the precast concrete segment 210 exposed to the top is removed. Whenever. By lowering the elevating member 340 that has risen by one step by two steps so as to be supported on the separated upper surface of the precast concrete segment stacking assembly 200b, the support of the vertical sphere wall (B) is unchanged and stably supported.

도 11c에 도시된 바와 같이, 이러한 방법으로 상부로 노출된 모든 프리캐스트 콘크리트 세그먼트(210)들이 제거되면, 하강유도부재(300)를 이용하여 수직구 벽체(B)를 일정 깊이로 하강시킨다.As shown in FIG. 11C, when all the precast concrete segments 210 exposed to the top are removed in this way, the vertical sphere wall B is lowered to a predetermined depth using the descending guide member 300.

즉, 도 11d에 도시된 바와 같이, 2단 하강된 모든 승강부재(340)를 동시에 1단으로 수축시키면 수직구 벽체(B)의 자중에 의해 상기 수직구 벽체(B)가 자연스럽게 수직구 내부로 일정 깊이 하강하게 되는 것이다.That is, as shown in FIG. 11D, when all the lifting members 340 lowered by two stages are simultaneously contracted to one stage, the vertical sphere wall (B) naturally moves into the vertical sphere by the weight of the vertical sphere wall (B). It descends a certain depth.

이때, 승강부재(340)의 하단을 분리상면에 고정시켜 놓으면 승강부재(340)가 슈(320)를 잡아당기는 작용을 하게 되므로 보다 용이하게 수직구 벽체(B)가 하강하게 된다.At this time, if the lower end of the lifting member 340 is fixed to the separate upper surface, the lifting member 340 acts to pull the shoe 320, so that the vertical sphere wall (B) descends more easily.

상기와 같은 방법으로 상기 수직구 벽체(B)가 목표 깊이에 도달할 때까지, 수직구를 일정 깊이로 굴착하고 하강유도부재(300)에 수직구 벽체(B)가 거치한 다음, 일정 깊이만큼 상부로 노출된 프리캐스트 콘크리트 세그먼트(210)를 제거하고, 상기 수직구 벽체(B)를 수직구 내부로 일정 깊이 하강시키는 과정을 반복하면 도 8에 도시된 바와 같이 수직구 구조물의 시공은 완료된다.In the same manner as described above, until the vertical sphere wall (B) reaches the target depth, the vertical sphere is excavated to a certain depth, and the vertical sphere wall (B) is mounted on the descending guide member 300, and then the vertical sphere wall (B) is mounted by a certain depth. When the precast concrete segment 210 exposed to the top is removed and the process of lowering the vertical sphere wall (B) to a certain depth inside the vertical sphere is repeated, the construction of the vertical sphere structure is completed as shown in FIG. 8. .

도 12에 도시된 바와 같이, 본 발명의 또 다른 실시예로서, 상기 지지구조물들이 지상에서 암반지반(A)까지 형성시킨 굴착공에 삽입되는 프리캐스트 콘크리트 세그먼트 적층 조립체(200c)인 경우에 있어서, 상기 승강부재(340)의 하단에는 제1핀부재(341)가 수직으로 구비되고, 상기 프리캐스트 콘크리트 세그먼트(260)들은 상단에는 상기 제1핀부재(341)가 삽입되는 수직핀홀(261)이 형성되고, 측방에는 상기 수직핀홀(261)과 연통되는 수평핀홀(262)이 형성될 수 있다.As shown in FIG. 12, as another embodiment of the present invention, in the case of the precast concrete segment stacking assembly 200c inserted into the excavation hole formed from the ground to the rock ground (A), the support structures, A first pin member 341 is vertically provided at the lower end of the elevating member 340, and the precast concrete segments 260 have a vertical pin hole 261 into which the first pin member 341 is inserted at the upper end. It is formed, and a horizontal pinhole 262 communicating with the vertical pinhole 261 may be formed in the side.

이 경우, 상기 수평핀홀(262)에는 상기 제1핀부재(341)에 끼워져 결합되고, 상기 수평핀홀(262)에는 제2핀부재(270)가 삽입된다. 상기 제2핀부재(270)의 단부는 수평핀홀(262)의 외부로 노출되며, 상기 제2핀부재(270)의 노출 단부에는 Ÿ‡지(280)가 끼워져 상기 제2핀부재(270)의 유동을 막아준다.In this case, the horizontal pinhole 262 is fitted and coupled to the first pin member 341, and the second pin member 270 is inserted into the horizontal pinhole 262. The end of the second pin member 270 is exposed to the outside of the horizontal pin hole 262, and a Ÿ‡ paper 280 is inserted into the exposed end of the second pin member 270 so that the second pin member 270 Prevents the flow of

아울러, 상기 프리캐스트 콘크리트 세그먼트(260)들의 하단에는 돌부(264)가 형성되고 상단에는 상기 돌부(264)에 대응되는 홈부(263)가 형성되어 상부의 프리캐스트 콘크리트 세그먼트(260)와 하부의 프리캐스트 콘크리트 세그먼트(260)들이 일정한 위치에서 안정적으로 결합되도록 할 수 있다.In addition, a protrusion 264 is formed at the lower end of the precast concrete segments 260 and a groove 263 corresponding to the protrusion 264 is formed at the upper end of the precast concrete segment 260 and the precast concrete segment 260 at the lower part. Cast concrete segments 260 may be stably coupled at a certain position.

한편, 상기 프리캐스트 콘크리트 세그먼트(260)들 중 최하단에 위치되는 프리캐스트 콘크리트 세그먼트(260a)의 하단은 하부로 수렴하는 첨예부(265)를 가지는 것이 바람직하다.On the other hand, it is preferable that the lower end of the precast concrete segment 260a located at the lowermost end of the precast concrete segments 260 has a sharpened portion 265 that converges downward.

이 경우, 상기 첨예부(265)는 상부에 적층되는 프리캐스트 콘크리트 세그먼트(260)들의 하중에 의해 굴착공의 바닥면에 깊게 박히면서 굴착공 내부에서 프리캐스트 콘크리트 세그먼트 적층 조립체(200c)가 안정적인 자세로 매설될 수 있도록 돕는다.In this case, the sharpening part 265 is deeply embedded in the bottom surface of the excavation hole by the load of the precast concrete segments 260 stacked thereon, and the precast concrete segment stacking assembly 200c is stable inside the excavation hole. Helps to be buried.

도 13에 도시된 바와 같이, 상기와 같이 프리캐스트 콘크리트 세그먼트(260)가 구성된 경우, 하강유도부재(300)가 설치될 때 상기 승강부재(340)는 1단 하강된 상태로 프리캐스트 콘크리트 세그먼트 적층 조립체(200c)의 상단에 고정된다.As shown in Figure 13, when the precast concrete segment 260 is configured as described above, when the descending induction member 300 is installed, the elevating member 340 is stacked in a state in which the precast concrete segment is lowered by one stage. It is fixed to the top of the assembly (200c).

그리고, 일정 깊이만큼 상부로 노출된 콘크리트 세그먼트 적층 조립체(200c)의 상단을 제거할 경우, 도 14a에 도시된 바와 같이, 승강부재(340)를 1단 상승시키면 승강부재(340)를 따라 최상단의 프리캐스트 콘크리트 세그먼트(260)가 인양되며, 인양된 최상단의 프리캐스트 콘크리트 세그먼트(260)를 승강부재(340)로부터 분리하여 제거한다.And, when removing the upper end of the concrete segment stacking assembly (200c) exposed to the top by a certain depth, as shown in Figure 14a, if the lifting member 340 is raised one step, the uppermost end along the lifting member 340 The precast concrete segment 260 is lifted, and the lifted top precast concrete segment 260 is separated from the lifting member 340 and removed.

이와 같이, 본 실시예에서는 승강부재(340)가 프리캐스트 콘크리트 세그먼트(260)를 인양하는 방식으로 제거하므로 프리캐스트 콘크리트 세그먼트(260)를 제거하는데 별도의 장비가 요구되지 않으며 제거작업이 매우 쉽고 빠르게 진행된다.As described above, in this embodiment, since the lifting member 340 is removed by lifting the precast concrete segment 260, no separate equipment is required to remove the precast concrete segment 260, and the removal operation is very easy and fast. It goes on.

도 14b에 도시된 바와 같이, 이러한 프리캐스트 콘크리트 세그먼트(260)의 제거작업은 각 프리캐스트 콘크리트 세그먼트 적층 조립체(200c) 별로 순차적으로 이루어지는데, 상부로 노출된 프리캐스트 콘크리트 세그먼트(260)가 제거될 때마다. 1단 상승한 승강부재(340)를 2단 하강시켜 프리캐스트 콘크리트 세그먼트(260)에 고정시킴으로써 수직구 벽체(B)의 지지가 변함없이 안정적으로 이루어지도록 한다.As shown in FIG. 14B, the removal operation of the precast concrete segment 260 is sequentially performed for each precast concrete segment stacking assembly 200c, and the precast concrete segment 260 exposed to the top is removed. Whenever. By lowering the elevating member 340, which has risen by one stage, to the precast concrete segment 260 by lowering it by two stages, the support of the vertical sphere wall (B) is unchanged and stably made.

도 14c에 도시된 바와 같이, 이러한 방법으로 상부로 노출된 모든 프리캐스트 콘크리트 세그먼트(260)들이 제거되면, 하강유도부재(300)를 이용하여 수직구 벽체(B)를 일정 깊이로 하강시킨다.As shown in FIG. 14C, when all the precast concrete segments 260 exposed to the top are removed in this way, the vertical sphere wall B is lowered to a predetermined depth using the descending guide member 300.

즉, 도 14d에 도시된 바와 같이, 2단 하강된 모든 승강부재(340)를 동시에 1단으로 수축시키면 수직구 벽체(B)의 자중에 의해 상기 수직구 벽체(B)가 자연스럽게 수직구 내부로 일정 깊이 하강하게 되는 것이다.That is, as shown in Fig. 14D, when all the lifting members 340 lowered by two stages are simultaneously contracted to one stage, the vertical sphere wall (B) naturally moves into the vertical sphere by the weight of the vertical sphere wall (B). It descends a certain depth.

상기와 같은 방법으로 상기 수직구 벽체(B)가 목표 깊이에 도달할 때까지, 수직구를 일정 깊이로 굴착하고 하강유도부재(300)에 수직구 벽체(B)가 거치한 다음, 일정 깊이만큼 상부로 노출된 프리캐스트 콘크리트 세그먼트(260)를 제거하고, 상기 수직구 벽체(B)를 수직구 내부로 일정 깊이 하강시키는 과정을 반복하면 도 8에 도시된 바와 같이 수직구 구조물의 시공은 완료된다.In the same manner as described above, until the vertical sphere wall (B) reaches the target depth, the vertical sphere is excavated to a certain depth, and the vertical sphere wall (B) is mounted on the descending guide member 300, and then the vertical sphere wall (B) is mounted by a certain depth. If the precast concrete segment 260 exposed to the top is removed and the process of lowering the vertical sphere wall (B) to a certain depth inside the vertical sphere is repeated, the construction of the vertical sphere structure is completed as shown in FIG. 8. .

이와 같이, 상기 지지구조물이 프리캐스트 콘크리트 세그먼트 적층 조립체(200b,200c)일 경우, 전술한 콘크리트 파일(200a)에 비하여 재활용이 가능하고 제거가 신속하고 용이해지는 이점이 있다.As such, the support structure is a precast concrete segment laminate assembly (200b, 200c). In this case, compared to the above-described concrete pile (200a), there is an advantage that recycling is possible and removal is quick and easy.

이와 같이, 도면을 참조하여 본 발명의 바람직한 실시예에 대해 상술하였으나 본 발명은 전술한 실시예에 한정되지 않으며, 본 발명이 속하는 기술분야에서 통상의 지식을 가진자가 본 발명의 사상을 벗어나지 않고 변형 가능하며, 이러한 변형은 본 발명의 권리범위에 속할 것이다.As described above, preferred embodiments of the present invention have been described above with reference to the drawings, but the present invention is not limited to the above-described embodiments, and those of ordinary skill in the art to which the present invention pertains are modified without departing from the spirit of the present invention. It is possible, and such modifications will fall within the scope of the present invention.

100...가설구조물 200a...콘크리트 파일
200b,200c...프리캐스트 콘크리트 세그먼트 적층 조립체
210,260...프리캐스트 콘크리트 세그먼트
211...결합돌기 212...핀 끼움공
220...핀 240...슬라이딩 홈부
250...슬라이딩 돌출부 261...수직핀홀
262...수평핀홀 263...홈부
264...돌부 265...첨예부
270...제2핀부재 280...Ÿ‡지
300...하강유도부재 310...유압잭
320...슈 330...잭로드
340...승강부재 341...제1핀부재
A...암반지반 B...수직구 벽체
100...Temporary structure 200a...Concrete pile
200b,200c... Precast Concrete Segment Lamination Assembly
210,260... precast concrete segments
211...Joining protrusion 212...Pin inserting hole
220...pin 240...sliding groove
250...Sliding protrusion 261...Vertical pinhole
262...Horizontal pinhole 263...groove
264... protrusion 265... sharpening
270...second pin member 280...Ÿ‡paper
300...down induction member 310...hydraulic jack
320...Shoe 330...Jack Rod
340...elevating member 341...first pin member
A...rock ground B...vertical sphere wall

Claims (13)

지상에 가설구조물이 설치되는 제1단계;
상기 가설구조물의 내측 가장자리를 따라 일정간격으로 지상에서 암반지반까지 형성시킨 굴착공에 콘크리트를 현장 타설하여 성형한 콘크리트 파일로 구성된 지지구조물이 매설되는 제2단계;
상기 가설구조물의 상부에 설치되는 유압잭과, 상기 지지구조물의 상단에 지지되는 슈와, 상기 유압잭과 슈를 연결하는 잭로드와, 상기 슈의 하부에 설치된 승강부재를 구비한 하강유도부재가 설치되는 제3단계;
상기 가설구조물의 내부에서 수직구가 일정 깊이로 굴착됨과 동시에 상기 하강유도부재에 수직구 벽체가 거치되는 제4단계;
일정 깊이만큼 상부로 노출된 지지구조물의 상단이 제거되는 제5단계;
상기 하강유도부재가 상기 수직구 벽체를 수직구 내부로 일정 깊이 하강시키는 제6단계; 및
상기 수직구 벽체가 목표 깊이에 도달할 때까지 상기 제4단계 내지 제6단계가 반복되는 제7단계를 포함하는 하향식 공법을 이용한 수직구 구조물의 시공방법.
The first step of installing a temporary structure on the ground;
A second step of burying a supporting structure composed of a concrete pile formed by placing concrete in an excavation hole formed from the ground to the rocky ground at regular intervals along the inner edge of the temporary structure;
A descending guide member having a hydraulic jack installed on the upper part of the temporary structure, a shoe supported on the upper end of the support structure, a jack rod connecting the hydraulic jack and the shoe, and an elevating member installed under the shoe is installed. The third step;
A fourth step in which a vertical sphere wall is mounted on the descending guide member while the vertical sphere is excavated to a predetermined depth within the temporary structure;
A fifth step of removing the upper end of the support structure exposed to the top by a predetermined depth;
A sixth step of lowering, by the descending induction member, the vertical sphere wall to a predetermined depth into the vertical sphere; And
Construction method of a vertical sphere structure using a top-down construction method comprising a seventh step in which the fourth to sixth steps are repeated until the vertical sphere wall reaches a target depth.
삭제delete 제1항에 있어서,
상기 제5단계는 상부로 노출된 콘크리트 파일의 상단이 커터기를 통해 절단되는 단계와, 상부로 노출된 콘크리트 파일의 상단이 제거될 때 마다 해당 하강유도부재의 승강부재가 하강되면서 콘크리트 파일의 절단상면에 지지되는 단계가 각 콘크리트 파일별로 순차적으로 이루어지고;
상기 제6단계는 하강된 모든 승강부재가 상승되는 단계를 포함하는 하향식 공법을 이용한 수직구 구조물의 시공방법.
The method of claim 1,
The fifth step is a step in which the upper end of the concrete pile exposed to the top is cut through a cutter machine, and each time the upper end of the concrete pile exposed to the top is removed, the lifting member of the corresponding lowering guide member descends to the cut top surface of the concrete pile. Steps supported on are sequentially performed for each concrete pile;
The sixth step is a method of constructing a vertical ball structure using a top-down method including the step of raising all the lowered lifting members.
삭제delete 삭제delete 삭제delete 삭제delete 제1항에 있어서,
상기 승강부재는 유압실린더인 것을 특징으로 하는 하향식 공법을 이용한 수직구 구조물의 시공방법.
The method of claim 1,
The elevating member is a construction method of a vertical sphere structure using a top-down method, characterized in that the hydraulic cylinder.
제1항에 있어서,
상기 지지구조물의 상단에는 모든 승강부재들이 동일수평선에 위치하도록 높이를 조절시켜 주는 높이조절블록이 더 구비되는 하향식 공법을 이용한 수직구 구조물의 시공방법.
The method of claim 1,
Construction method of a vertical ball structure using a top-down construction method further provided with a height adjustment block for adjusting the height so that all the lifting members are located on the same horizontal line at the upper end of the support structure.
삭제delete 삭제delete 삭제delete 삭제delete
KR1020200079222A 2020-06-29 2020-06-29 Method for constructing vertical structure in vertical tunnel using top down method KR102247344B1 (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
KR1020200079222A KR102247344B1 (en) 2020-06-29 2020-06-29 Method for constructing vertical structure in vertical tunnel using top down method
KR1020200189716A KR102368269B1 (en) 2020-06-29 2020-12-31 Method for constructing vertical structure in vertical tunnel using top down method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020200079222A KR102247344B1 (en) 2020-06-29 2020-06-29 Method for constructing vertical structure in vertical tunnel using top down method

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR1020200189716A Division KR102368269B1 (en) 2020-06-29 2020-12-31 Method for constructing vertical structure in vertical tunnel using top down method

Publications (1)

Publication Number Publication Date
KR102247344B1 true KR102247344B1 (en) 2021-05-03

Family

ID=75910892

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020200079222A KR102247344B1 (en) 2020-06-29 2020-06-29 Method for constructing vertical structure in vertical tunnel using top down method

Country Status (1)

Country Link
KR (1) KR102247344B1 (en)

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012117209A (en) * 2010-11-29 2012-06-21 Kenji Machisuji Caisson method and equipment for caisson method
KR101859367B1 (en) * 2017-03-31 2018-06-28 고엄식 Method for constructing vertical structure in vertical tunnel using top down method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012117209A (en) * 2010-11-29 2012-06-21 Kenji Machisuji Caisson method and equipment for caisson method
KR101859367B1 (en) * 2017-03-31 2018-06-28 고엄식 Method for constructing vertical structure in vertical tunnel using top down method

Similar Documents

Publication Publication Date Title
KR101859367B1 (en) Method for constructing vertical structure in vertical tunnel using top down method
US20220098817A1 (en) Method for constructing structure
CN106013053B (en) A kind of steel sheet pile construction method for supporting for being used to build underground garage open caisson
JP2684155B2 (en) Excavation method used for construction of underground structures
KR102368269B1 (en) Method for constructing vertical structure in vertical tunnel using top down method
CN109025349B (en) Method for correcting inclination of brick-concrete structure building and adding underground layer
US10246313B2 (en) Precast concrete pit
KR102247344B1 (en) Method for constructing vertical structure in vertical tunnel using top down method
CN114164860A (en) Sinking frame foundation, ground prefabrication equipment thereof and sinking device
US6948885B2 (en) Method for constructing foundation
KR102428358B1 (en) Method for constructing vertical structure in vertical tunnel using top down method
CN111877321A (en) Cast-in-place pile applied to underground reinforced concrete structure and construction method thereof
KR102079190B1 (en) weight down type perpendicular hole hive-cut press in mehthod of construction
CN214832836U (en) Caisson type underground garage construction equipment
CN211058437U (en) Intelligent electric pole inclination prevention device
JP2018197463A (en) Co-settlement preventing structure and settling method of caisson
KR102102593B1 (en) constructing level tunnel connecting part of vertical structure and apparatus thereof
CN105926582A (en) Prefabricated hollow component underground tunneling construction combined body, continuous wall and construction method
CN210658420U (en) Prefabricated foundation implantation box suitable for sandy soil installation
CN218757568U (en) Transverse pipeline left groove and then closed open caisson
JP4484100B2 (en) Installation method of steel pipe sheet pile assembly for well formation
CN217651789U (en) Sliding pin type old pile pulling device
AU2003206504B2 (en) Method of construction
JP4755361B2 (en) Vertical shaft construction method
KR20230169492A (en) Method for demolishing an underground structure

Legal Events

Date Code Title Description
GRNT Written decision to grant