KR101984238B1 - Construction method of slide steel structure for connection of culverts for prevention of urban flooding - Google Patents
Construction method of slide steel structure for connection of culverts for prevention of urban flooding Download PDFInfo
- Publication number
- KR101984238B1 KR101984238B1 KR1020180075147A KR20180075147A KR101984238B1 KR 101984238 B1 KR101984238 B1 KR 101984238B1 KR 1020180075147 A KR1020180075147 A KR 1020180075147A KR 20180075147 A KR20180075147 A KR 20180075147A KR 101984238 B1 KR101984238 B1 KR 101984238B1
- Authority
- KR
- South Korea
- Prior art keywords
- culvert
- steel structure
- prevention
- flooding
- main
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F3/00—Sewer pipe-line systems
- E03F3/04—Pipes or fittings specially adapted to sewers
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F3/00—Sewer pipe-line systems
- E03F3/06—Methods of, or installations for, laying sewer pipes
Landscapes
- Health & Medical Sciences (AREA)
- Life Sciences & Earth Sciences (AREA)
- Engineering & Computer Science (AREA)
- Hydrology & Water Resources (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- Sewage (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
본 발명은 도시침수 예방용 암거의 시공에 관한 것으로서, 더욱 상세하게는 도시침수 예방용 PC 암거 시공시 지장물 때문에 연결하지 못하고 일정한 간격을 두고 PC 암거를 계속하여 시공할 때, 이격된 두개의 PC 암거를 단시간에 간단하게 연결할 수 있는 도시침수 예방용 암거연결용 슬라이드 철골 구조물의 시공방법에 관한 것이다.More particularly, the present invention relates to the construction of a culvert for urban flooding prevention, and more particularly, to a culvert for urban flooding prevention, And more particularly, to a method of constructing a slide steel structure for connection to a culvert for prevention of flooding in a city, which can be easily connected to a culvert in a short time.
장마철과 같이 많은 비가 내리는 경우, 기존의 우수관으로 빗물이 배수되지 못하여 도시 침수가 발생하는 것을 예방하기 위해 근래에는 대형의 도시침수 예방용 암거를 지하에 매설하고 있다. 도시침수 예방용 암거로는 프리캐스트 콘크리트(PC:precast concrete) 암거가 많이 사용되고 있다.In case of heavy rains such as the rainy season, in order to prevent rainwater from being drained by the existing gutters and to prevent urban flooding, a large urban flood prevention culvert has been buried underground. Precast concrete (PC) culvert is widely used as a culvert for urban flooding prevention.
그런데, 도시의 경우에는 지하에 수도관, 가스관, 전선 등 많은 지장물이 매립되어 있다.However, in the case of cities, many obstacles such as water pipes, gas pipes and electric wires are buried underground.
따라서, 도시침수 예방용 암거를 시공하다보면 지장물을 만나게 된다. 도시침수 예방용 암거는 직선으로 연결하여야 하므로 다른 지장물을 제거하거나 설치 위치를 변경하여 도시침수 예방용 암거의 설치에 방해가 되지 않도록 할 필요가 있다.Therefore, when we construct culvert for city flood prevention, we encounter obstacle water. Since the culvert for urban flood prevention should be connected by a straight line, it is necessary to remove other obstacles or change the installation position so as not to interfere with the installation of the culvert for prevention of flooding in the city.
그러나, 지장물을 제거하거나 이동하는데 많은 시간이 걸릴 수 있으므로, 도시침수 예방용 암거를 설치할 때는 지장물이 있는 부분을 나두고, 다음 도시침수 예방용 암거를 설치한다. However, since it may take a long time to remove or move the obstacles, when installing the culvert for urban flooding prevention, it is necessary to leave the part where the obstacle is present and install the culvert for the flooding prevention of the next city.
그 후, 지장물이 제거되거나 이동되면, 떨어져 있는 2개의 암거를 현장 콘크리트 타설 작업을 하여 연결하게 된다. Thereafter, when the obstacle is removed or moved, the two separated culverts are connected by the on-site concrete pouring work.
그러나, 이와 같은 현장 콘크리트 타설작업은 철근을 설치하고, 그 둘레에 거푸집을 설치한 후, 콘크리트를 타설한 뒤, 일정 기간 양생을 할 필요가 있다. 따라서, 현장 콘크리트 타설작업은 대략 20일 정도가 소요되므로, 도시침수 예방용 암거의 설치에 많은 시간이 걸린다는 문제점이 있다.However, it is necessary to install reinforcing bars, place a mold around the reinforcing bars, pour concrete, and cure for a certain period of time. Therefore, since it takes about 20 days to put the concrete in place, there is a problem that it takes much time to install the culvert for prevention of flooding in the city.
이와 같이 설치공사가 오래 걸리면, 차량의 운행이나 보행자의 보행에 방해가 되므로 많은 민원이 제기된다는 문제점이 있다.If the installation work takes a long time in this way, there is a problem that many complaints are caused because it interferes with the operation of the vehicle or the walking of the pedestrian.
또한, 현장 콘크리트 타설은 공정이 복잡하여 품질이 저하될 우려가 있으며, 많은 공사기간이 소요되므로 공사비용이 높다는 문제점도 있다.In addition, the installation of the on-site concrete has a problem that the quality is lowered due to the complexity of the process, and the construction cost is high due to the long construction period.
본 발명은 상기와 같은 문제점을 감안하여 안출된 것으로서, 지장물 제거를 위해 이격되어 설치된 2개의 도시침수 예방용 암거를 간단하고 신속하게 연결할 수 있는 도시침수 예방용 암거 연결용 슬라이드 철골 구조물의 시공방법을 제공하는 것을 목적으로 한다.The present invention has been made in view of the above problems, and it is an object of the present invention to provide a method of constructing a slide steel structure for culvert connection for prevention of flooding in an urban area, And to provide the above objects.
상기와 같은 목적을 달성하기 위해, 본 발명의 일 실시예에 의한 도시침수 예방용 암거 연결용 슬라이드 철골 구조물의 시공방법은,According to an aspect of the present invention, there is provided a method of constructing a slide steel structure for culvert connection for prevention of flooding of a city,
일정 거리 이격된 제1도시침수 예방용 암거와 제2도시침수 예방용 암거 사이의 거리를 측정하는 단계;Measuring a distance between a first city flooding prevention cage and a second city flooding prevention cage which are spaced apart from each other by a predetermined distance;
상기 제1도시침수 예방용 암거와 상기 제2도시침수 예방용 암거 사이의 거리보다 짧은 길이를 갖는 도시침수 예방용 암거 연결용 철골 구조물을 준비하는 단계;Preparing a culvert-connecting steel structure for prevention of flooding of a city having a length shorter than a distance between the first city flooding prevention culvert and the second city flooding prevention culvert;
상기 제1도시침수 예방용 암거와 상기 제2도시침수 예방용 암거 사이에 상기 도시침수 예방용 암거 연결용 철골 구조물을 위치시키는 단계;Placing the steel structure for culvert connection for prevention of urban flooding prevention between the first city flooding prevention culvert and the second city flooding prevention culvert;
상기 도시침수 예방용 암거 연결용 철골 구조물의 메인 철골 구조물의 메인 플랜지의 복수의 관통공을 상기 제1도시침수 예방용 암거의 일단에 마련된 복수의 앵커 볼트에 삽입하여 상기 메인 플랜지를 상기 제1도시침수 예방용 암거의 일단에 접촉시키는 단계;A plurality of through holes of a main flange of a main steel structure of a culvert-connecting steel structure for city flooding prevention are inserted into a plurality of anchor bolts provided at one end of the first city flooding prevention culvert, Contacting one end of the culvert for prevention of flooding;
상기 제1도시침수 예방용 암거의 복수의 앵커 볼트에 복수의 너트를 체결하여 상기 메인 철골 구조물을 상기 제1도시침수 예방용 암거에 고정하는 단계;Fixing the main steel structure to the first urban flooding prevention culler by fastening a plurality of nuts to a plurality of anchor bolts of the first urban flooding prevention culvert;
상기 메인 철골 구조물의 일단에 슬라이딩 가능하게 마련된 연장 철골 구조물을 이동시켜, 상기 연장 철골 구조물의 연장 플랜지의 복수의 관통공을 상기 제2도시침수 예방용 암거의 일단에 마련된 복수의 앵커 볼트에 삽입하여 상기 연장 플랜지를 상기 제2도시침수 예방용 암거의 일단에 접촉시키는 단계; 및A plurality of through holes of an extension flange of the extended steel structure are inserted into a plurality of anchor bolts provided at one end of the second urban flooding prevention culvert to move an extended steel structure slidably provided at one end of the main steel structure, Contacting the extending flange to one end of the second city flooding prevention culvert; And
상기 제2도시침수 예방용 암거의 복수의 앵커 볼트에 복수의 너트를 체결하여 상기 연장 철골 구조물을 상기 제2도시침수 예방용 암거에 고정하는 단계;를 포함하는 것을 특징으로 한다. And fixing the extended steel structure to the second urban flooding prevention culler by fastening a plurality of nuts to a plurality of anchor bolts of the second urban flooding prevention culvert.
이때, 상기 메인 철골 구조물은, 상기 제1도시침수 예방용 암거의 단면에 대응하는 단면을 갖는 메인 몸체를 포함하며, 상기 메인 플랜지는 상기 메인 몸체의 일단에 마련될 수 있다. At this time, the main frame structure may include a main body having a cross section corresponding to a cross section of the first city flooding prevention culvert, and the main flange may be provided at one end of the main body.
또한, 상기 연장 철골 구조물은, 상기 메인 철골 구조물의 메인 몸체에 대응하는 단면을 갖는 슬라이딩 몸체를 포함하며, 상기 연장 플랜지는 상기 슬라이딩 몸체의 일단에 마련될 수 있다. The extended steel structure may include a sliding body having a cross section corresponding to a main body of the main steel structure, and the extending flange may be provided at one end of the sliding body.
또한, 상기 도시침수 예방용 암거 연결용 철골 구조물은 상기 메인 철골 구조물의 일단과 상기 연장 철골 구조물의 연장 플랜지 사이에 설치되며, 상기 메인 철골 구조물에 대해 상기 연장 철골 구조물을 이동시키는 복수의 연장 길이 조절부재;를 더 포함할 수 있다. Further, the culvert-connecting steel structure for preventing flooding may be installed between one end of the main steel structure and the extended flange of the extended steel structure, and a plurality of elongated length adjustments for moving the extended steel structure to the main steel structure Member; < / RTI >
또한, 상기 연장 철골 구조물은 상기 메인 철골 구조물의 일단과 상기 연장 철골 구조물의 연장 플랜지 사이에 설치되는 복수의 잭을 이용하여 이동시킬 수 있다.In addition, the extended steel structure may be moved using a plurality of jacks provided between one end of the main steel structure and the extended flange of the extended steel structure.
상기와 같은 구조를 갖는 본 발명의 일 실시예에 의한 도시침수 예방용 암거 연결용 슬라이드 철골 구조물의 시공방법에 의하면, 지장물을 제거하기 위해 일정 거리 이격되어 설치된 2개의 도시침수 예방용 암거를 연결할 때, 2개의 도시침수 예방용 암거 사이의 공간에 대략 대응하는 메인 철골 구조물을 설치하고, 메인 철골 구조물에 대해 일정 길이 연장 가능한 연장 철골 구조물을 이용하여 메인 철골 구조물과 도시침수 예방용 암거 사이의 간격을 맞출 수 있으므로 정밀한 시공이 가능하다는 이점이 있다.According to the construction method of the slide steel structure for culvert connection for preventing flooding of the city according to the embodiment of the present invention having the above-described structure, two urban flood prevention culverts , The main steel frame structure corresponding to the space between the two culverts for flooding prevention is installed and the distance between the main steel frame structure and the culvert for prevention of urban flooding prevention So that it is possible to perform precise construction.
또한, 본 발명의 일 실시예에 의한 도시침수 예방용 암거 연결용 슬라이드 철골 구조물의 시공방법을 이용하여 2개의 도시침수 예방용 암거를 연결하면, 종래 기술과 같이 현장 콘크리트 타설이 필요 없으므로, 2개의 도시침수 예방용 암거를 연결하는 작업이 하루에 완료될 수 있다.In addition, if two culvert culverts for flooding prevention are connected to each other by using the construction method of a slide steel structure for culvert connection for preventing flooding of an urban area according to an embodiment of the present invention, Connecting the culvert for urban flooding prevention can be completed in one day.
따라서, 본 발명의 일 실시예에 의한 도시침수 예방용 암거 연결용 철골 구조물의 시공방법에 의하면, 공사기간이 단축되므로, 공사기간의 장기화로 발생하는 민원과 교통지체를 최단기간에 해소할 수 있으며, 공사기간이 짧아지므로 시공비용도 절감할 수 있다는 이점이 있다.Therefore, according to the method of constructing a steel structure for culvert connection for urban flooding prevention according to an embodiment of the present invention, the construction period is shortened, so that complaints and traffic delays caused by prolonged construction period can be eliminated in the shortest period of time , The construction period is shortened, and the construction cost can be reduced.
도 1은 본 발명의 일 실시예에 의한 도시침수 예방용 암거 연결용 슬라이드 철골 구조물을 나타내는 사시도;
도 2는 도 1의 도시침수 예방용 암거 연결용 슬라이드 철골 구조물을 선Ⅰ-Ⅰ을 따라 절단한 단면도;
도 3은 도 1의 도시침수 예방용 암거 연결용 슬라이드 철골 구조물을 선Ⅱ-Ⅱ을 따라 절단한 단면도;
도 4a 내지 도 4d는 본 발명의 일 실시예에 의한 도시침수 예방용 암거 연결용 슬라이드 철골 구조물의 시공방법을 설명하기 위한 도면;
도 5는 본 발명의 다른 실시예에 의한 도시침수 예방용 암거 연결용 슬라이드 철골 구조물을 나타내는 사시도;
도 6은 본 발명의 다른 실시예에 의한 도시침수 예방용 암거 연결용 슬라이드 철골 구조물을 나타내는 평면도;
도 7은 본 발명의 다른 실시예에 의한 도시침수 예방용 암거 연결용 슬라이드 철골 구조물을 나타내는 평면도;이다.1 is a perspective view illustrating a slide steel structure for culvert connection for prevention of flooding in an urban area according to an embodiment of the present invention;
Fig. 2 is a sectional view of the slide steel structure for culvert connection for prevention of flooding in Fig. 1 taken along line I-I;
3 is a cross-sectional view of the slide steel structure for culvert connection for prevention of flooding in Fig. 1 taken along line II-II;
FIGS. 4A to 4D are views for explaining a method of constructing a slide steel structure for culvert connection for prevention of flooding in the city according to an embodiment of the present invention; FIGS.
5 is a perspective view illustrating a slide steel structure for culvert connection for prevention of flooding in the city according to another embodiment of the present invention;
6 is a plan view showing a slide steel structure for culvert connection for prevention of flooding of a city according to another embodiment of the present invention;
FIG. 7 is a plan view of a slide steel structure for culvert connection for prevention of flooding of an urban according to another embodiment of the present invention; FIG.
이하, 첨부된 도면을 참조하여 본 발명에 의한 도시침수 예방용 암거 연결용 슬라이드 철골 구조물의 시공방법의 실시예들에 대해 상세하게 설명한다.DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, embodiments of a method of constructing a slide steel structure for culvert connection for prevention of flooding of an urban area according to the present invention will be described in detail with reference to the accompanying drawings.
이하에서 설명되는 실시 예는 본 발명의 이해를 돕기 위하여 예시적으로 나타낸 것이며, 본 발명은 여기서 설명되는 실시 예들과 다르게 다양하게 변형되어 실시될 수 있음이 이해되어야 할 것이다. 다만, 이하에서 본 발명을 설명함에 있어서, 관련된 공지 기능 혹은 구성요소에 대한 구체적인 설명이 본 발명의 요지를 불필요하게 흐릴 수 있다고 판단되는 경우 그 상세한 설명 및 구체적인 도시를 생략한다. 또한, 첨부된 도면은 발명의 이해를 돕기 위하여 실제 축척대로 도시된 것이 아니라 일부 구성요소의 치수가 과장되게 도시될 수 있다.It is to be understood that the embodiments described below are provided for illustrative purposes only, and that the present invention may be embodied with various modifications and alterations of the embodiments described herein. In the following description, well-known functions or components are not described in detail to avoid obscuring the subject matter of the present invention. In addition, the attached drawings are not drawn to scale in order to facilitate understanding of the invention, but the dimensions of some of the components may be exaggerated.
본 발명은 도시침수 예방용 암거를 설치하는 공사를 진행하는 동안, 방해되는 지장물을 제거하기 위해 2개의 도시침수 예방용 암거를 일정 거리 이격된 상태로 설치하는 경우, 지장물을 제거한 후, 일정 거리 이격된 2개의 도시침수 예방용 암거를 연결하기 위해 그 사이에 설치되는 도시침수 예방용 암거 연결용 슬라이드 철골 구조물을 시공하는 방법에 관한 것이다.In the case of installing two culvert culverts for flooding prevention at a certain distance in order to remove obstruction obstacles while constructing a culvert for urban flooding prevention, The present invention relates to a method of constructing a slide steel structure for connection to a culvert for preventing inundation in an urban area, which is installed therebetween in order to connect two urban flood prevention culverts.
도 1은 본 발명의 일 실시예에 의한 도시침수 예방용 암거 연결용 슬라이드 철골 구조물을 나타내는 사시도이다. 도 2는 도 1의 도시침수 예방용 암거 연결용 슬라이드 철골 구조물을 선Ⅰ-Ⅰ을 따라 절단한 단면도이고, 도 3은 도 1의 도시침수 예방용 암거 연결용 슬라이드 철골 구조물을 선Ⅱ-Ⅱ을 따라 절단한 단면도이다. FIG. 1 is a perspective view showing a slide steel structure for culvert connection for prevention of flooding in the city according to an embodiment of the present invention. Fig. 2 is a sectional view of a slide steel structure for culvert connection for prevention of submergence in Fig. 1, taken along line I-I; Fig. 3 is a cross- Fig.
도 1 내지 도 3을 참조하면, 본 발명의 일 실시예에 의한 도시침수 예방용 암거 연결용 슬라이드 철골 구조물(1)은 메인 철골 구조물(10)과 연장 철골 구조물(20)을 포함할 수 있다. 1 to 3, a
메인 철골 구조물(10)은 일정 거리 이격된 2개의 도시침수 예방용 암거(PC1, PC2, 도 4 참조) 중 한 개의 암거(PC1), 예를 들면, 제1도시침수 예방용 암거(PC1)의 일단에 연결된다. 메인 철골 구조물(10)은 2개의 도시침수 예방용 암거(PC1, PC2) 사이에 쉽게 설치할 수 있도록, 메인 철골 구조물(10)의 길이는 이격된 2개의 암거 사이(PC1, PC2)의 거리(D)(도 4 참조)보다 짧게 형성된다. The main
메인 철골 구조물(10)은 도시침수 예방용 암거(PC1)의 단면에 대응하는 단면을 갖는 메인 몸체(11)와, 메인 몸체(11)의 일단에 마련되며 제1도시침수 예방용 암거(PC1)의 일단에 결합되는 메인 플랜지(13)를 포함할 수 있다.The
메인 몸체(11)는 제1도시침수 예방용 암거(PC1)의 단면에 대응하는 단면을 가지며, 내부(16)가 빈 중공 형태로 형성된다. 예를 들면, 제1도시침수 예방용 암거(PC1)가 직사각형의 단면을 갖는 프리캐스팅 콘크리트(Preecast concrete) 암거인 경우에, 메인 몸체(11)는 직사각형의 단면을 갖는 채널 형태로 형성된다. The
이때, 메인 몸체(11)의 내부 단면은 상기 제1도시침수 예방용 암거(PC1)의 내부 단면과 거의 동일한 형상과 면적을 갖도록 형성된다. At this time, an inner end surface of the
메인 몸체(11)는 강도를 유지하고 경량화를 위해 샌드위치 패널(100)로 형성될 수 있다.The
샌드위치 패널(100)은 2장의 철판(101,102)과 그 사이에 설치되어 철판(101,102)의 강도를 보강하는 복수의 보강부재(103)로 구성될 수 있다. The
예를 들면, 샌드위치 패널(100)은 제1철판(101), 제2철판(102), 복수의 보강 부재(103), 및 충진제(104)로 구성될 수 있다. For example, the
제1철판(101)과 제2철판(102)은 상면과 하면이 방수 표면 처리가 된 철판을 사용할 수 있다.The
제1철판(101)과 제2철판(102) 사이에는 복수의 보강부재(103)가 설치된다. 복수의 보강부재(103) 중 일부는 제1 및 제2철판(101,102)의 둘레를 따라 설치된다. 외부로 노출되는 보강부재(103)에는 충진제(104)를 주입하는 주입구(미도시)가 마련된다. 충진제(104)로는 우레탄 발포제, 에폭시 우레탄 등이 사용될 수 있다.A plurality of reinforcing
제1철판(101)과 제2철판(102) 사이에는 제1철판(101)의 일 측변에 평행하게 일정한 간격으로 복수의 보강 부재(103)가 설치된다. 보강 부재(103)는 띠 형상의 철판을 사용할 수도 있으나, ㄷ자 형강, ㄱ자 형강, 사각 파이프, H빔 등을 사용할 수 있다. 본 실시예에서는 강도와 중량을 고려하여 복수의 보강 부재(103)로 ㄷ자 형강을 사용하고 있다. A plurality of reinforcing
도 3에 도시된 바와 같이, 본 실시예에 의한 샌드위치 패널(100)은 제1철판(101)과 제2철판(102) 사이에 복수의 ㄷ자 형강(103)이 일정 간격으로 설치되어 제1철판(101)과 제2철판(102)의 강도를 보강하므로, 메인 철골 구조물(10)이 지하에 매설되었을 때, 외부에서 가해지는 압력을 견딜 수 있는 충분한 강도를 확보할 수 있다.3, in the
또한, 복수의 보강 부재(103)는 제1철판(101)과 제2철판(102)의 강도를 보강하면서, 내부로 충진되는 충진제(104)가 이동하는 경로를 형성하도록 설치될 수 있다. 이를 위해, 복수의 보강 부재(103)는 지그 재그 형태로 설치될 수 있다. 예를 들면, 보강 부재(103)의 일단은 일측의 보강 부재(103)에 접촉하도록 설치되고, 타단은 타측의 보강 부재(103)와 일정 간격 떨어지도록 설치될 수 있다. The plurality of reinforcing
이와 같이 본 발명의 일 실시예에 의한 메인 철골 구조물(10)은 강도가 보강되고, 중량이 가벼운 샌드위치 패널(100)을 사용하여 제작하므로, 중량이 가벼워서 현장에서 콘크리트 타설을 하여 2개의 도시침수 예방용 암거를 연결하는 것보다 설치가 용이하다. 또한, 샌드위치 패널(100)을 형성하는 제1철판(101)과 제2철판(102)의 표면이 방수 표면 처리가 되어 있으므로 메인 철골 구조물(10)이 지하에 매설되어 우수를 이송할 때 녹이 스는 것을 최소화할 수 있다. As described above, since the
그러나, 다른 예로서, 도시하지는 않았지만, 메인 철골 구조물(10)은 샌드위치 패널(100)로 형성하지 않고, 한 장의 두꺼운 철판을 사용하여 형성할 수 있다. However, as another example, although not shown, the
메인 플랜지(13)는 메인 철골 구조물(11)을 제1도시침수 예방용 암거(PC1)에 연결하기 위한 것으로서, 메인 몸체(11)의 일단에 메인 몸체(11)에 대해 외측으로 수직하게 연장되며, 대략 직사각형 형상으로 형성된다. 즉, 메인 플랜지(13)는 메인 몸체(11)의 일단을 감싸는 속이 빈 직사각형 테두리로 형성된다. The
메인 플랜지(13)에는 복수의 관통공(14)이 마련된다. 복수의 관통공(14)은 도시침수 예방용 암거(PC1, PC2)에 설치된 복수의 앵커 볼트(55)에 대응하는 개수로 마련될 수 있다. 따라서, 메인 플랜지(13)의 복수의 관통공(14)을 제1도시침수 예방용 암거(PC1)의 일단에 마련된 복수의 앵커 볼트(55)에 삽입하고, 너트(50)를 채우면 메인 철골 구조물(10)을 제1도시침수 예방용 암거(PC1)에 고정할 수 있다.A plurality of through holes (14) are provided in the main flange (13). The plurality of through
연장 철골 구조물(20)은 메인 철골 구조물(10)과 제2도시침수 예방용 암거(PC2) 사이의 간격을 메울 수 있도록 길이를 조절할 수 있도록 형성된다. 이를 위해, 연장 철골 구조물(20)은 메인 철골 구조물(10)의 일단에 메인 철골 구조물(10)의 내면을 따라 슬라이딩 가능하게 마련되며, 2개의 도시침수 예방용 암거(PC1, PC2) 중 나머지 암거(PC2), 예를 들면, 제2도시침수 예방용 암거(PC2)의 일단에 연결된다. The extended
연장 철골 구조물(20)은 메인 철골 구조물(10)의 메인 몸체(11)에 대응하는 단면을 갖는 슬라이딩 몸체(21)와, 슬라이딩 몸체(21)의 일단에 마련되며 제2도시침수 예방용 암거(PC2)의 일단에 결합되는 연장 플랜지(23)를 포함할 수 있다.The extended
슬라이딩 몸체(21)는 메인 몸체(11)의 내부에 삽입되어 메인 몸체(11)의 내면을 따라 슬라이딩할 수 있도록 형성된다. 즉, 슬라이딩 몸체(21)의 외면이 메인 몸체(11)의 내면과 접촉하면서, 메인 몸체(11)에 대해 미끄럼 이동을 할 수 있도록 형성된다. 따라서, 도 1 및 도 3에 도시된 바와 같이 메인 몸체(11)가 직사각형 단면을 갖는 중공의 파이프 형상으로 형성된 경우에, 슬라이딩 몸체(21)도 직사각형 단면을 갖는 중공의 파이프 형상으로 형성된다. 즉, 슬라이딩 몸체(21)의 내부에도 메인 몸체(11)의 내부 공간(16)에 대응하는 빈 공간(26)이 형성된다.The sliding
연장 철골 구조물(20)의 길이는 메인 철골 구조물(10)의 길이보다 짧으므로, 슬라이딩 몸체(21)는 철판으로 성형할 수 있다. 일반적으로, 연장 철골 구조물(20)은 2개의 도시침수 예방용 암거(PC1, PC2) 사이에 설치되는 도시침수 예방용 암거 연결용 슬라이드 철골 구조물(1)의 길이를 조절하는 기능을 하므로 메인 철골 구조물(10) 길이의 20% 정도의 길이를 갖도록 형성할 수 있다. 메인 철골 구조물(10)을 좀 더 정밀하게 제작하는 경우에는 연장 철골 구조물(20)의 길이는 메인 철골 구조물(10) 길이의 10% 이하로 할 수도 있다.Since the length of the extended
그러나, 다른 예로서, 연장 철골 구조물(20)의 강도를 높일 수 있도록 연장 철골 구조물(20)의 슬라이딩 몸체(21)도 상술한 메인 철골 구조물(10)의 메인 몸체(11)와 동일하게 샌드위치 패널(100)로 형성할 수 있다. However, as another example, in order to increase the strength of the extended
연장 플랜지(23)는 연장 철골 구조물(20)을 제2도시침수 예방용 암거(PC2)에 연결하기 위한 것으로서, 슬라이딩 몸체(21)의 일단에 슬라이딩 몸체(21)에 대해 외측으로 수직하게 연장되며, 대략 직사각형 형상으로 형성된다. 즉, 연장 플랜지(23)는 슬라이딩 몸체(21)의 일단을 감싸는 속이 빈 직사각형 테두리로 형성된다. The
연장 플랜지(23)에는 복수의 관통공(24)이 마련된다. 복수의 관통공(24)은 제2도시침수 예방용 암거(PC2)에 설치된 복수의 앵커 볼트(55)에 대응하는 개수로 마련될 수 있다. 따라서, 연장 플랜지(23)의 복수의 관통공(24)을 제2도시침수 예방용 암거(PC2)의 일단에 마련된 복수의 앵커 볼트(55)에 삽입하고, 너트(50)를 채우면 연장 철골 구조물(20)을 제2도시침수 예방용 암거(PC2)에 고정할 수 있다.The
또한, 연장 철골 구조물(20)의 이동을 용이하게 하기 위해 메인 철골 구조물(10)과 연장 철골 구조물(20) 사이에는 복수의 연장 길이 조절부재(30)가 설치될 수 있다. Further, a plurality of extension
복수의 연장 길이 조절부재(30)는 메인 철골 구조물(10)의 메인 몸체(11)의 일단, 즉 메인 플랜지(13)가 설치되지 않은 메인 몸체(11)의 일단과 연장 철골 구조물(20)의 연장 플랜지(23) 사이에 메인 철골 구조물(10)에 대해 연장 철골 구조물(20)을 이동시킬 수 있도록 설치된다. A plurality of extension
복수의 연장 길이 조절부재(30)는 사각 파이프 형상의 슬라이딩 몸체(21)의 각 측면에 한 개씩 4개가 설치될 수 있다. 슬라이딩 몸체(21)의 4개의 측면에 각각 한 개씩의 연장 길이 조절부재(30)를 설치하면, 연장 길이 조절부재(30)를 작동시켜 연장 철골 구조물(20)을 메인 철골 구조물(10)로부터 쉽게 연장시킬 수 있다. The plurality of extension-
다른 예로서, 도시침수 예방용 암거 연결용 슬라이드 철골 구조물(1)을 지하에 매설할 때, 바닥에 위치하는 슬라이딩 몸체(21)의 하면에는 연장 길이 조절부재(30)를 설치하지 않을 수도 있다. 즉, 슬라이딩 몸체(21)의 상면과 양 측면에만 연장 길이 조절부재(30)를 설치할 수 있다. As another example, when the
복수의 연장길이 조절부재(30) 각각은 잭 볼트(31), 메인 몸체(11)의 일단에 마련된 너트부재(32), 연장 철골 구조물(20)의 연장 플랜지(23)에 마련된 홀딩부재(34)를 포함할 수 있다.Each of the plurality of extension
잭 볼트(31)의 일단에는 홀딩부재(34)의 홈(34a)에 삽입되어 회전하는 헤드부(31a)가 마련되며, 헤드부(31a)의 일측에는 잭 볼트(31)를 돌릴 수 있든 돌림부(33)가 마련되며, 돌림부(33)에서 잭 볼트(31)의 타단까지는 숫나사가 형성된다. 돌림부(33)는 스패너로 돌릴 수 있도록 6각 몸체로 형성될 수 있다.One end of the
너트부재(32)는 메인 몸체(11)의 일단에 고정되며, 중앙에는 잭 볼트(31)의 숫나사가 체결되는 암나사가 형성된다. 너트부재(32)의 하부로 메인 몸체(11)에는 잭 볼트(31)가 삽입될 수 있는 공간이 마련되어 있다. The
홀딩부재(34)는 연장 철골 구조물(20)의 연장 플랜지(23)에 고정되며, 중앙에는 잭 볼트(31)의 헤드부(31a)의 선단에 대응하는 홈(34a)이 형성된다. 예를 들어, 잭 볼트(31)의 헤드부(31a)의 선단이 돔 형상으로 형성되면, 홀딩부재(34)의 홈(34a)은 잭 볼트(31)의 헤드부(31a)의 선단을 수용할 수 있는 반구의 홈으로 형성될 수 있다. The holding
따라서, 잭 볼트(31)의 숫나사를 메인 철골 구조물(10)의 일단에 마련된 너트부재(32)에 체결하고, 잭 볼트(31)의 헤드부(31a)를 연장 철골 구조물(20)의 연장 플랜지(23)에 마련된 홀딩부재(34)에 삽입하면 연장 길이 조절부재(30)가 도시침수 예방용 암거 연결용 슬라이드 철골 구조물(1)에 설치된다. 이와 같이 잭 볼트(31)의 숫나사가 형성된 일단부는 메인 철골 구조물(10)의 너트부재(32)에 체결하고, 잭 볼트(31)의 헤드부(31a)는 연장 철골 구조물(20)의 홀딩부재(34)에 삽입하면, 잭 볼트(31)가 양단 지지된 상태이므로 잭 볼트(31)를 안정적으로 돌릴 수 있다.The male screw of the
이 상태에서, 잭 볼트(31)의 돌림부(33)를 잭 볼트(31)가 너트부재(32)에서 빠지는 방향으로 돌리면, 잭 볼트(31)가 메인 철골 구조물(10)의 너트부재(32)에 대해 멀어지는 방향으로 직선 이동하므로, 연장 철골 구조물(20)이 메인 철골 구조물(10)에서 빠지게 된다. In this state, when the projecting
따라서, 메인 철골 구조물(10)을 제1도시침수 예방용 암거(PC1)에 고정한 상태에서, 복수의 연장 길이 조절부재(30)를 회전시키면, 연장 철골 구조물(20)이 이동하게 된다. 연장 철골 구조물(20)이 이동하여, 연장 철골 구조물(20)의 일단이 제2도시침수 예방용 암거(PC2)의 일단에 접촉되면, 제1도시침수 예방용 암거(PC1)와 제2도시침수 예방용 암거(PC2) 사이를 본 발명의 일 실시예에 의한 도시침수 예방용 암거 연결용 슬라이드 철골 구조물(1)로 연결할 수 있다. Therefore, when the plurality of extension-
이하, 도 4a 내지 도 4d를 참조하여 본 발명의 일 실시예에 의한 도시침수 예방용 암거 연결용 슬라이드 철골 구조물의 시공방법에 대해 상세하게 설명한다.Hereinafter, a method of constructing a slide steel structure for culvert connection for prevention of flooding of an urban area according to an embodiment of the present invention will be described in detail with reference to FIGS. 4A to 4D.
도 4a 내지 도 4d는 본 발명의 일 실시예에 의한 도시침수 예방용 암거 연결용 슬라이드 철골 구조물의 시공방법을 설명하기 위한 도면이다.4A to 4D are views for explaining a method of constructing a slide steel structure for culvert connection for prevention of flooding of an urban area according to an embodiment of the present invention.
먼저, 작업자는 도 4a에 도시된 바와 같이 서로 이격되어 설치된 2개의 도시침수 예방용 암거, 즉 제1도시침수 예방용 암거(PC1)와 제2도시침수 예방용 암거(PC2) 사이의 거리(D)를 측정한다. 이 경우, 제1도시침수 예방용 암거(PC1)와 제2도시침수 예방용 암거(PC2)는 그 사이에 있는 지장물(미도시)때문에 이격되어 설치되어 있다.First, as shown in FIG. 4A, the operator sets the distance D between the two urban flood prevention culverts, that is, the first urban flood prevention culvert PC1 and the second urban flood prevention culvert PC2, ). In this case, the first urban water immersion prevention culvert PC1 and the second urban water immersion prevention culvert PC2 are spaced apart from each other due to obstacles (not shown) therebetween.
이어서, 2개의 도시침수 예방용 암거(PC1, PC2) 사이를 채울 수 있는 길이를 갖는 본 발명의 일 실시예에 의한 도시침수 예방용 암거 연결용 슬라이드 철골 구조물(1)을 준비한다. Next, a
이때, 본 발명에 의한 도시침수 예방용 암거 연결용 철골 구조물(1)은 현장에서 제작되는 것이 아니라, 별도의 공장에서 제작된다. 따라서, 현장에서 방해가 되는 지장물을 제거하는 동안 별도의 공장에서 도시침수 예방용 암거 연결용 철골 구조물(1)을 제작할 수 있으므로 공사기간을 단축할 수 있다. At this time, the steel structure for culvert connection (1) for flooding prevention of floods according to the present invention is not manufactured on site, but is manufactured in a separate factory. Therefore, it is possible to construct a steel structure (1) for culvert connection for prevention of flooding of a city in a separate factory while removing disturbing obstacles in the field, thereby shortening the construction period.
도시침수 예방용 암거 연결용 슬라이드 철골 구조물(1)은 연장 철골 구조물(20)이 메인 철골 구조물(10)에 완전히 삽입되어 있는 상태에서의 전체 길이(L)는 2개의 도시침수 예방용 암거(PC1, PC2) 사이의 거리(D)보다 작고, 연장 철골 구조물(20)을 메인 철골 구조물(10)에서 충분히 뺀 상태에서의 전체 길이는 2개의 도시침수 예방용 암거(PC1, PC2) 사이의 거리(D)보다 큰 것을 사용한다. 이때, 연장 철골 구조물(20)이 메인 철골 구조물(10)에 삽입된 상태에서 도시침수 예방용 암거 연결용 철골 구조물(1)의 길이(L)는 제1도시침수 예방용 암거(PC1)의 앵커 볼트(55)와 제2도시침수 예방용 암거(PC2)의 앵커 볼트(55) 사이의 거리(D1)보다 작게 제작할 필요가 있다.The total length L of the
연장 철골 구조물(20)이 메인 철골 구조물(10)에 완전히 삽입되어 있는 상태에서, 도시침수 예방용 암거 연결용 슬라이드 철골 구조물(1)을 2개의 도시침수 예방용 암거(PC1, PC2) 사이에 위치시킨다. With the
그후, 메인 철골 구조물(10)의 메인 플랜지(13)의 복수의 관통공(14)이 제1도시침수 예방용 암거(PC1)의 일단에 마련된 복수의 앵커 볼트(55)에 삽입되고, 메인 플랜지(13)가 제1도시침수 예방용 암거(PC1)의 일단에 접촉하도록 도시침수 예방용 암거 연결용 슬라이드 철골 구조물(1)을 위치시킨다. Then a plurality of through
이 상태에서, 도 4b에 도시된 바와 같이, 복수의 앵커 볼트(55) 각각에 너트(50)를 체결하여 메인 철골 구조물(10)을 제1도시침수 예방용 암거(PC1)의 일단에 고정한다.4B, the
이어서, 작업자는 복수의 연장 길이 조절부재(30)를 동작시켜 연장 철골 구조물(20)을 메인 철골 구조물(10)에서 제2도시침수 예방용 암거(PC2) 쪽으로 이동시킨다. 구체적으로, 연장 길이 조절부재(30)의 잭 볼트(31)의 돌림부(33)를 공구를 이용하여 돌리면, 연장 철골 구조물(20)이 메인 철골 구조물(10)에 대해 슬라이딩 이동을 하여 제2도시침수 예방용 암거(PC2)의 일단 쪽으로 이동한다. Subsequently, the operator operates a plurality of extension
그러면, 연장 철골 구조물(20)의 연장 플랜지(23)에 마련된 복수의 관통공(24)에 제2도시침수 예방용 암거(PC2)의 일단에 마련된 복수의 앵커 볼트(55)가 삽입된다. 이 상태에서 복수의 연장 길이 조절부재(30)의 잭 볼트(31)를 계속 돌려, 도 4c에 도시된 바와 같이, 연장 철골 구조물(20)의 연장 플랜지(23)가 제2도시침수 예방용 암거(PC2)의 일단에 접촉하도록 한다. A plurality of
그후, 연장 철골 구조물(20)의 연장 플랜지(23)의 복수의 관통공(24)을 통해 돌출된 제2도시침수 예방용 암거(PC2)의 복수의 앵커 볼트(55) 각각에 너트(50)를 체결한다. 그러면, 도 4d에 도시된 바와 같이, 연장 철골 구조물(20)이 제2도시침수 예방용 암거(PC2)의 일단에 고정된다.A
그 후, 필요한 경우, 메인 철골 구조물(10)과 연장 철골 구조물(20)의 연결부에 실링작업을 수행하여, 메인 철골 구조물(10)과 연장 철골 구조물(20) 사이의 틈새로 물이 새는 것을 차단할 수 있다.Thereafter, a sealing operation is performed on the connection between the
이상에서는 연장 철골 구조물(20)을 메인 철골 구조물(10)과 연장 철골 구조물(20) 사이에 설치된 복수의 연장 길이 조절부재(30)를 사용하여 이동시키는 구조에 대해 설명하였으나, 연장 철골 구조물(20)을 이동시키는 방법이 이에 한정되는 것은 아니다.Although the extended
다른 실시예로서, 메인 철골 구조물(10)과 연장 철골 구조물(20)에 연장 철골 구조물(20)을 이동시키기 위한 복수의 연장 길이 조절부재(30)를 설치하지 않을 수 있다.As another embodiment, it is not necessary to provide a plurality of elongated
도 5에는 메인 철골 구조물(10)과 연장 철골 구조물(20) 사이에 복수의 연장 길이 조절부재가 설치되지 않은 도시침수 예방용 암거 연결용 슬라이드 철골 구조물(1')의 일 예가 도시되어 있다. FIG. 5 shows an example of a slide steel structure for culvert connection 1 'for prevention of flooding in the city, in which a plurality of extension length adjusting members are not provided between the
이와 같이, 도시침수 예방용 암거 연결용 슬라이드 철골 구조물(1')에 복수의 연장 길이 조절부재(30)가 설치되지 않은 경우에는 무거운 것을 들어올리는 일반적인 기구인 잭(jack)을 이용하여 연장 철골 구조물(20)을 이동시킬 수 있다.When a plurality of extension
예를 들면, 메인 철골 구조물(10)의 일단과 연장 철골 구조물(20)의 연장 플랜지(23) 사이에 복수의 잭(미도시)을 설치하고, 복수의 잭을 작동시키면 연장 철골 구조물(20)을 메인 철골 구조물(10)에 대해 슬라이딩 이동시킬 수 있다. For example, a plurality of jacks (not shown) may be provided between one end of the
이상에서는 2개의 도시침수 예방용 암거(PC1, PC2)가 일자형으로 배치된 경우에 사용되는 일자형 도시침수 예방용 암거 연결용 슬라이드 철골 구조물(1)에 대해 설명하였으나, 도시침수 예방용 암거(PC1, PC2)가 반드시 일자로 배치되는 것은 아니다. In the above description, the
2개의 도시침수 예방용 암거가 일정 각도를 이루도록 배치된 경우에는 꺽임형 도시침수 예방용 암거 연결용 슬라이드 철골 구조물을 사용하여 2개의 도시침수 예방용 암거를 연결할 수 있다.If two culverts for flooding prevention are arranged at an angle, two culvert culverts can be connected by using a slide steel structure for culvert-type flood prevention culvert.
도 6에는 꺽임형 도시침수 예방용 암거 연결용 슬라이드 철골 구조물의 일 예가 도시되어 있다.FIG. 6 shows an example of a slide steel structure for culvert connection for preventing flooding of the city.
도 6을 참조하면, 꺽임형 도시침수 예방용 암거 연결용 슬라이드 철골 구조물(2)은 2개의 도시침수 예방용 암거 중 한 개(제1도시침수 예방용 암거)에 연결되는 메인 철골 구조물(210)과 2개의 도시침수 예방용 암거 중 나머지 한 개(제2도시침수 예방용 암거)에 연결되는 연장 철골 구조물(220)을 포함할 수 있다.Referring to FIG. 6, the
메인 철골 구조물(210)은 도시침수 예방용 암거의 단면에 대응하는 단면을 갖는 메인 몸체(211)와, 메인 몸체(211)의 일단에 마련되며 제1도시침수 예방용 암거의 일단에 결합되는 메인 플랜지(213)를 포함할 수 있다.The
도 6에 도시된 꺽임형 도시침수 예방용 암거 연결용 슬라이드 철골 구조물(2)의 메인 철골 구조물(210)은 메인 몸체(211)가 일정 각도로 설치된 2개의 도시침수 예방용 암거를 연결할 수 있도록 일정 각도로 꺽인 것 외에는 상술한 일자형 도시침수 예방용 암거 연결용 슬라이드 철골 구조물(1)의 메인 철골 구조물(10)과 동일하므로 상세한 설명은 생략한다. The
연장 철골 구조물(220)은 메인 철골 구조물(210)과 도시침수 예방용 암거 사이의 간격을 메울 수 있도록 길이를 조절할 수 있도록 형성된다. 이를 위해, 연장 철골 구조물(220)은 메인 철골 구조물(210)의 일단에 메인 철골 구조물(210)의 내면을 따라 슬라이딩 가능하게 마련되며, 제2도시침수 예방용 암거의 일단에 연결된다. The extended
연장 철골 구조물(220)은 메인 철골 구조물(210)의 메인 몸체(211)에 대응하는 단면을 갖는 슬라이딩 몸체(221)와, 슬라이딩 몸체(221)의 일단에 마련되며 제2도시침수 예방용 암거에 결합되는 연장 플랜지(223)를 포함할 수 있다. The extended
도 6에 도시된 꺽임형 도시침수 예방용 암거 연결용 슬라이드 철골 구조물(2)의 연장 철골 구조물(220)은 상술한 일자형 도시침수 예방용 암거 연결용 슬라이드 철골 구조물(1)의 연장 철골 구조물(20)과 동일하므로 상세한 설명은 생략한다.The extended
도 6에 도시된 바와 같은 꺽임형 도시침수 예방용 암거 연결용 철골 구조물을 시공하는 방법은 상술한 일자형 도시침수 예방용 암거 연결용 철골 구조물의 시공방법과 유사하므로 상세한 설명은 생략한다. The method for constructing the steel structure for culvert connection for prevention of flooding of the downward city as shown in FIG. 6 is similar to the construction method of the steel structure for culvert connection for preventing flooding of the straight-type city described above, and a detailed description thereof will be omitted.
다른 실시예로서, 도시하지는 않았지만, 꺽임형 도시침수 예방용 암거 연결용 슬라이드 철골 구조물(2)의 메인 철골 구조물(210)의 메인 플랜지(213)가 형성된 일단에 메인 플랜지(213)를 마련하지 않고 제2의 연장 철골 구조물을 설치할 수도 있다. 이와 같이 꺽임형 도시침수 예방용 암거 연결용 슬라이드 철골 구조물(2)의 양단에 연장 철골 구조물(220)을 각각 설치하면, 일정 각도로 배치된 2개의 도시침수 예방용 암거를 연결하는 작업이 더욱 쉽다는 이점이 있다.The
또한, 도시침수 예방용 암거를 시공하는 중에 2개 이상의 도시침수 예방용 암거를 연결할 필요가 있는 경우도 있다. In addition, it is sometimes necessary to connect two or more flood prevention culverts during the construction of the city culvert prevention culvert.
도 7에는 3개의 도시침수 예방용 암거가 서로 일정 거리 이격되어 배치되어 그 사이의 공간이 대략 T자형인 경우에 사용될 수 있는 본 발명의 일 실시예에 의한 T자형 도시침수 예방용 암거 연결용 슬라이드 철골 구조물(3)의 일 예가 도시되어 있다. 7 shows a T-shaped urban immersion prevention cowl connection slide according to an embodiment of the present invention, which can be used when three urban flood prevention culverts are spaced apart from each other by a certain distance and a space therebetween is substantially T- An example of the
도 7을 참조하면, 본 발명의 일 실시예에 의한 T자형 도시침수 예방용 암거 연결용 슬라이드 철골 구조물(3)은 T자 형상의 메인 철골 구조물(310)과 3개의 연장 철골 구조물(320,330,340)을 포함할 수 있다.Referring to FIG. 7, a
메인 철골 구조물(310)은 T자형으로 형성되며 도시침수 예방용 암거의 단면에 대응하는 단면을 갖는 메인 몸체(314)로 형성된다. T자형의 메인 몸체(314)에는 3개의 단부(311,312,313)가 마련되며 3개의 도시침수 예방용 암거의 일단에 결합되는 3개의 연장 철골 구조물(320,330,340)이 설치된다. The
도 7에 도시된 T자형 도시침수 예방용 암거 연결용 슬라이드 철골 구조물(3)의 메인 철골 구조물(310)은 메인 몸체(314)가 서로 이격된 3개의 도시침수 예방용 암거를 연결할 수 있도록 T자형으로 형성된 것 외에는 상술한 일자형 도시침수 예방용 암거 연결용 슬라이드 철골 구조물(1)의 메인 철골 구조물(10)의 메인 몸체(11)와 동일하게 형성할 수 있으므로 상세한 설명은 생략한다. The
3개의 연장 철골 구조물(320,330,340)은 메인 철골 구조물(310)과 3개의 도시침수 예방용 암거 사이의 간격을 메울 수 있도록 길이를 조절할 수 있도록 형성된다. 이를 위해, 3개의 연장 철골 구조물(320,330,340)은 메인 철골 구조물(310)의 3개의 단부(311,312,313)에 메인 철골 구조물(310)의 각 단부(311,312,313)의 내면을 따라 슬라이딩 가능하게 마련되며, 3개의 제2도시침수 예방용 암거의 일단에 연결된다. Three
3개의 연장 철골 구조물(320,330,340) 각각은 메인 철골 구조물(310)의 메인 몸체(314)에 대응하는 단면을 갖는 슬라이딩 몸체(321,331,341)와, 슬라이딩 몸체(321,331,341)의 일단에 마련되며 도시침수 예방용 암거에 결합되는 연장 플랜지(323,333,343)를 포함할 수 있다. Each of the three
도 7에 도시된 T자형 도시침수 예방용 암거 연결용 슬라이드 철골 구조물(3)의 연장 철골 구조물(320,330,340)은 상술한 일자형 도시침수 예방용 암거 연결용 슬라이드 철골 구조물(1)의 연장 철골 구조물(20)과 동일하므로 상세한 설명은 생략한다.The extended
도 7에 도시된 바와 같은 T자형 도시침수 예방용 암거 연결용 철골 구조물(3)을 시공하는 방법은 일자형에서 돌출된 단부(313)에 설치된 연장 철골 구조물(340)을 먼저 대응하는 도시침수 예방용 암거에 연결하고, 그후에 일자형으로 배치된 2개의 단부(311,312)에 설치된 2개의 연장 철골 구조물(320,330)을 각각 대응하는 2개의 도시침수 예방용 암거에 연결할 수 있다. 3개의 연장 철골 구조물(320,330,340)을 도시침수 예방용 암거에 연결하는 방법은 상술한 일자형 도시침수 예방용 암거 연결용 철골 구조물(1)의 시공방법과 유사하므로 상세한 설명은 생략한다.As shown in FIG. 7, the method for constructing the T-shaped waterproofing culvert-connecting
도 7에서는 3개의 도시침수 예방용 암거가 대략 T자형 공간을 형성하도록 이격된 경우에 사용할 수 있는 T자형 도시침수 예방용 암거 연결용 슬라이드 철골 구조물(3)에 대해 설명하였으나, 3개의 도시침수 예방용 암거의 배치가 이에 한정되는 것은 아니다. 3개의 도시침수 예방용 암거가 다양하게 이격되어 배치된 경우에도, 3개의 도시침수 예방용 암거 사이의 공간에 대응하도록 메인 철골 구조물을 형성하고, 메인 철골 구조물의 3개의 단부 각각에 연장 철골 구조물을 슬라이딩 가능하게 설치하면, 3개의 도시침수 예방용 암거를 쉽게 연결할 수 있다.In FIG. 7, a description has been given of the
예를 들어, 3개의 도시침수 예방용 암거가 중간에 대략 Y자형의 공간을 형성하도록 서로 이격된 경우에는 메인 철골 구조물을 Y자형으로 형성하고, 메인 철골 구조물의 3개의 단부에 슬라이딩 가능한 3개의 연장 철골 구조물을 설치하여 3개의 도시침수 예방용 암거를 연결할 수 있다.For example, in the case where three city waterproofing culverts are spaced from each other to form a substantially Y-shaped space in the middle, the main steel structure is formed into a Y-shape, and three elongate slides Steel structures can be installed to connect three culvert culverts.
이상에서 설명한 바와 같이 본 발명의 일 실시예에 의한 도시침수 예방용 암거 연결용 슬라이드 철골 구조물의 시공방법에 의하면, 지장물을 제거하기 위해 2개 또는 3개의 도시침수 예방용 암거를 일정 거리 이격된 상태로 설치하는 경우, 지장물을 제거한 후, 2개 또는 3개의 도시침수 예방용 암거 사이의 공간에 대략 대응하는 메인 철골 구조물을 설치하고, 메인 철골 구조물에 대해 일정 길이 연장 가능한 연장 철골 구조물을 이용하여 메인 철골 구조물과 도시침수 예방용 암거 사이의 간격을 맞출 수 있다.As described above, according to the method of constructing a slide steel structure for culvert connection for preventing flooding in the city according to an embodiment of the present invention, in order to remove the obstacle, two or three flood prevention culverts It is necessary to install a corresponding main steel structure in a space between two or three flood prevention culverts and to use an extended steel structure which can be extended by a predetermined length to the main steel structure So that the gap between the main steel structure and the culvert for urban flooding prevention can be matched.
따라서, 본 발명의 일 실시예에 의한 도시침수 예방용 암거 연결용 슬라이드 철골 구조물의 시공방법에 의하면, 종래 기술과 같이 현장 콘크리트 타설이 필요 없으므로, 당일에 공사를 완료할 수 있다.Therefore, according to the construction method of the slide steel structure for culvert connection for preventing the flooding of the city according to the embodiment of the present invention, since the installation of the on-site concrete is not necessary as in the prior art, the construction can be completed on the same day.
예를 들면, 종래기술과 같이 현장 콘크리트 타설을 할 경우에는 지장물 제거 후 대략 20일 정도의 시간이 필요하나, 본 발명의 일 실시예에 의한 도시침수 예방용 암거 연결용 슬라이드 철골 구조물의 시공방법에 의하면, 지장물 제거 후 하루면 공사를 완료할 수 있다는 이점이 있다. For example, in the case where the concrete pouring is performed as in the conventional art, it takes about 20 days after the removal of the obstacle. However, according to one embodiment of the present invention, According to this, there is an advantage that the work can be completed one day after removing the obstacle.
따라서, 공사기간의 장기화로 발생하는 민원과 교통지체를 최단기간에 해소할 수 있으며, 공사기간이 짧아지므로 시공비용도 절감할 수 있다는 이점이 있다.Therefore, it is possible to eliminate complaints and traffic delays caused by prolonged construction period in the shortest period, and the construction period is shortened, so that the construction cost can be reduced.
상기에서 본 발명은 예시적인 방법으로 설명되었다. 여기서 사용된 용어들은 설명을 위한 것이며, 한정의 의미로 이해되어서는 안 될 것이다. 상기 내용에 따라 본 발명의 다양한 수정 및 변형이 가능하다. 따라서 따로 부가 언급하지 않는 한 본 발명은 청구범위의 범주 내에서 자유로이 실시될 수 있을 것이다.The invention has been described above in an illustrative manner. The terms used herein are for the purpose of description and should not be construed as limiting. Various modifications and variations of the present invention are possible in light of the above teachings. Therefore, unless otherwise indicated, the present invention may be practiced freely within the scope of the claims.
1,2,3; 도시침수 예방용 암거 연결용 철골 구조물
10; 메인 철골 구조물 11; 메인 몸체
13; 메인 플랜지 20; 연장 철골 구조물
21; 슬라이딩 몸체 23; 연장 플랜지
30; 연장 길이 조절부재 31; 잭 볼트
32; 너트부재 33; 돌림부
34; 홀딩부재 50; 너트
55; 앵커 볼트 100; 샌드위치 패널
101,102; 철판 103; 보강부재
210; 메인 철골 구조물 220; 연장 철골 구조물
310; 메인 철골 구조물 314; 메인 몸체
320,330,340; 연장 철골 구조물1,2,3; Metal constructions for ventilation ...
10; A
13; A
21; A sliding
30; An extension
32;
34; A holding
55;
101, 102;
210; A
310; A
320,330,340; Extensible steel constructions
Claims (5)
상기 제1도시침수 예방용 암거와 상기 제2도시침수 예방용 암거 사이의 거리보다 짧은 길이를 갖는 도시침수 예방용 암거 연결용 철골 구조물을 준비하는 단계;
상기 제1도시침수 예방용 암거와 상기 제2도시침수 예방용 암거 사이에 상기 도시침수 예방용 암거 연결용 철골 구조물을 위치시키는 단계;
상기 도시침수 예방용 암거 연결용 철골 구조물의 메인 철골 구조물의 메인 플랜지의 복수의 관통공을 상기 제1도시침수 예방용 암거의 일단에 마련된 복수의 앵커 볼트에 삽입하여 상기 메인 플랜지를 상기 제1도시침수 예방용 암거의 일단에 접촉시키는 단계;
상기 제1도시침수 예방용 암거의 복수의 앵커 볼트에 복수의 너트를 체결하여 상기 메인 철골 구조물을 상기 제1도시침수 예방용 암거에 고정하는 단계;
상기 메인 철골 구조물의 일단에 슬라이딩 가능하게 마련된 연장 철골 구조물을 이동시켜, 상기 연장 철골 구조물의 연장 플랜지의 복수의 관통공을 상기 제2도시침수 예방용 암거의 일단에 마련된 복수의 앵커 볼트에 삽입하여 상기 연장 플랜지를 상기 제2도시침수 예방용 암거의 일단에 접촉시키는 단계; 및
상기 제2도시침수 예방용 암거의 복수의 앵커 볼트에 복수의 너트를 체결하여 상기 연장 철골 구조물을 상기 제2도시침수 예방용 암거에 고정하는 단계;를 포함하며,
상기 도시침수 예방용 암거 연결용 철골 구조물은, 상기 메인 철골 구조물의 일단과 상기 연장 철골 구조물의 연장 플랜지 사이에 설치되며, 상기 메인 철골 구조물에 대해 상기 연장 철골 구조물을 이동시키는 복수의 연장 길이 조절부재를 포함하며,
상기 복수의 연장 길이 조절부재 각각은,
상기 메인 철골 구조물의 일단에 설치된 너트부재;
상기 연장 철골 구조물의 연장 플랜지에 설치된 홀딩부재;
일단은 상기 홀딩부재에 회전 가능하게 삽입되며, 타단은 상기 너트부재에 체결되어 상기 메인 철골 구조물의 내부로 삽입되는 잭 볼트; 및
상기 잭 볼트에 마련된 돌림부;를 포함하며,
상기 복수의 연장 길이 조절부재의 돌림부를 돌려 상기 연장 철골 구조물을 이동시킴으로써 상기 연장 플랜지가 상기 제2도시침수 예방용 암거의 일단에 접촉되도록 하는 것을 특징으로 하는 도시침수 예방용 암거 연결용 슬라이드 철골 구조물의 시공방법.Measuring a distance between a first city flooding prevention cage and a second city flooding prevention cage which are spaced apart from each other by a predetermined distance;
Preparing a culvert-connecting steel structure for prevention of flooding of a city having a length shorter than a distance between the first city flooding prevention culvert and the second city flooding prevention culvert;
Placing the steel structure for culvert connection for prevention of urban flooding prevention between the first city flooding prevention culvert and the second city flooding prevention culvert;
A plurality of through holes of a main flange of a main steel structure of a culvert-connecting steel structure for city flooding prevention are inserted into a plurality of anchor bolts provided at one end of the first city flooding prevention culvert, Contacting one end of the culvert for prevention of flooding;
Fixing the main steel structure to the first urban flooding prevention culler by fastening a plurality of nuts to a plurality of anchor bolts of the first urban flooding prevention culvert;
A plurality of through holes of an extension flange of the extended steel structure are inserted into a plurality of anchor bolts provided at one end of the second urban flooding prevention culvert to move an extended steel structure slidably provided at one end of the main steel structure, Contacting the extending flange to one end of the second city flooding prevention culvert; And
And fixing the extended steel structure to the second urban flooding prevention culler by fastening a plurality of nuts to a plurality of anchor bolts of the second urban flooding prevention culvert,
The culvert-connecting steel structure for preventing flooding of the city is provided between one end of the main steel structure and an extending flange of the extended steel structure and includes a plurality of elongated length adjusting members for moving the extended steel structure to the main steel structure, / RTI >
Wherein each of the plurality of extension length adjusting members comprises:
A nut member installed at one end of the main steel structure;
A holding member installed on an extension flange of the extended steel structure;
A jack bolt whose one end is rotatably inserted into the holding member and the other end is inserted into the main steel structure by being fastened to the nut member; And
And a projecting portion provided on the jack bolt,
Wherein the extending flange is brought into contact with one end of the second urban flooding prevention culvert by rotating the projecting portion of the plurality of extension length adjusting members to move the extended steel structure, .
상기 메인 철골 구조물은,
상기 제1도시침수 예방용 암거의 단면에 대응하는 단면을 갖는 메인 몸체를 포함하며,
상기 메인 플랜지는 상기 메인 몸체의 일단에 마련되는 것을 특징으로 하는 도시침수 예방용 암거 연결용 슬라이드 철골 구조물의 시공방법.The method according to claim 1,
The main steel structure includes:
And a main body having a cross section corresponding to a cross section of the first city flooding prevention culvert,
Wherein the main flange is provided at one end of the main body, and the main flange is provided at one end of the main body.
상기 연장 철골 구조물은,
상기 메인 철골 구조물의 메인 몸체에 대응하는 단면을 갖는 슬라이딩 몸체를 포함하며,
상기 연장 플랜지는 상기 슬라이딩 몸체의 일단에 마련되는 것을 특징으로 하는 도시침수 예방용 암거 연결용 슬라이드 철골 구조물의 시공방법.3. The method of claim 2,
The extended steel structure,
And a sliding body having a section corresponding to the main body of the main steel structure,
Wherein the extension flange is provided at one end of the sliding body. ≪ RTI ID = 0.0 > 18. < / RTI >
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020180075147A KR101984238B1 (en) | 2018-06-29 | 2018-06-29 | Construction method of slide steel structure for connection of culverts for prevention of urban flooding |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020180075147A KR101984238B1 (en) | 2018-06-29 | 2018-06-29 | Construction method of slide steel structure for connection of culverts for prevention of urban flooding |
Publications (1)
Publication Number | Publication Date |
---|---|
KR101984238B1 true KR101984238B1 (en) | 2019-05-30 |
Family
ID=66675779
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020180075147A KR101984238B1 (en) | 2018-06-29 | 2018-06-29 | Construction method of slide steel structure for connection of culverts for prevention of urban flooding |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR101984238B1 (en) |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2849690B2 (en) * | 1990-08-21 | 1999-01-20 | 清水建設株式会社 | Underground piping construction method and device |
KR19990011579U (en) * | 1997-08-30 | 1999-03-25 | 윤정희 | Tube telescopic connector |
KR20140003512U (en) * | 2012-12-03 | 2014-06-11 | 현대중공업 주식회사 | Dummy for pipeline distance connection |
-
2018
- 2018-06-29 KR KR1020180075147A patent/KR101984238B1/en active IP Right Grant
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2849690B2 (en) * | 1990-08-21 | 1999-01-20 | 清水建設株式会社 | Underground piping construction method and device |
KR19990011579U (en) * | 1997-08-30 | 1999-03-25 | 윤정희 | Tube telescopic connector |
KR20140003512U (en) * | 2012-12-03 | 2014-06-11 | 현대중공업 주식회사 | Dummy for pipeline distance connection |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP6533842B2 (en) | Joints used as final connections in submerged tunnels | |
KR101506782B1 (en) | In-Site Molding Apparatus for manufacturing In-site Concrete Culverts with assembled Partial Precast Concrete | |
KR100743369B1 (en) | Precast culvert assembly for both culvert and utility-pipe conduit | |
KR100994805B1 (en) | Multipurpose reservoir apparatus | |
KR101588593B1 (en) | Temporary bridge construction method | |
KR102028899B1 (en) | Underground parking lot partition structure of PC method for maximizing cost saving | |
CN104652364A (en) | Construction method of vertical water-sealing structure for water conservancy project | |
CN103821180A (en) | Double-water stop structure for concrete expansion joint and manufacturing and construction method for double-water stop structure | |
KR101559751B1 (en) | This does not require a retaining wall erected formwork | |
CN215630170U (en) | Advanced sealing structure of basement outer wall post-cast strip | |
KR101984238B1 (en) | Construction method of slide steel structure for connection of culverts for prevention of urban flooding | |
KR101984237B1 (en) | Slide steel structure for connection of culverts for prevention of urban flooding | |
KR20080114297A (en) | Arch bridge and method of constructing the bridge in brook | |
KR101526461B1 (en) | Functional precast concrete culvert | |
CN209854577U (en) | Assembled thin-wall box-shaped channel | |
KR100805622B1 (en) | Mold device for manufacturing multi-divided segments of sectional manhole | |
KR101886661B1 (en) | Steel Aqueduct and Construction Methods thereof | |
KR101272898B1 (en) | Reinforced water conduit and manufacturing apparatus | |
KR100934980B1 (en) | Precast concrete forms for the capconcrete of caisson and the construction method using the same | |
KR101524272B1 (en) | A repairing assembled structure precast-manhole and constructing method it | |
KR100891617B1 (en) | The steel box for the concrete filling type closed conduit construction | |
KR100805555B1 (en) | Sectional manhole using multi-divided segments | |
KR200384474Y1 (en) | Prefabricated Precast Concrete Culvert | |
CN104727276A (en) | Manufacturing method for concrete expansion joint dual waterstop structure | |
KR102494159B1 (en) | Pipe protection block structure, And the method for building the structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GRNT | Written decision to grant |