KR101922324B1 - Ceiling lift up construction method - Google Patents

Ceiling lift up construction method Download PDF

Info

Publication number
KR101922324B1
KR101922324B1 KR1020170005636A KR20170005636A KR101922324B1 KR 101922324 B1 KR101922324 B1 KR 101922324B1 KR 1020170005636 A KR1020170005636 A KR 1020170005636A KR 20170005636 A KR20170005636 A KR 20170005636A KR 101922324 B1 KR101922324 B1 KR 101922324B1
Authority
KR
South Korea
Prior art keywords
lifting
jack
frame
lifting frame
shaped steel
Prior art date
Application number
KR1020170005636A
Other languages
Korean (ko)
Other versions
KR20180083229A (en
Inventor
고석진
이성두
김영찬
Original Assignee
삼성물산 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 삼성물산 주식회사 filed Critical 삼성물산 주식회사
Priority to KR1020170005636A priority Critical patent/KR101922324B1/en
Publication of KR20180083229A publication Critical patent/KR20180083229A/en
Application granted granted Critical
Publication of KR101922324B1 publication Critical patent/KR101922324B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/22Scaffolds essentially supported by building constructions, e.g. adjustable in height supported by roofs or ceilings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • E04G3/30Mobile scaffolds; Scaffolds with mobile platforms suspended by flexible supporting elements, e.g. cables
    • E04G3/32Hoisting devices; Safety devices
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/16Struts or stiffening rods, e.g. diagonal rods

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Working Measures On Existing Buildindgs (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

본 발명은 비계 공사의 제거에 따른 공사비가 절감되고, 모듈화 공법으로서 공기가 단축되고, 기존 건물의 개보수 공사에 따른 천정고 변경시도 기존 천정을 재활용 할 수 있도록 한 천정 리프트 업 시공 방법을 제공한다.
본 발명의 일 실시 형태에 따른 천정 리프트 업 시공 방법은, 상부층 슬래브에 천공위치 기준점 작업을 수행한 후, 천공장비를 사용하여 기준점마다 상부층 슬래브에 타공을 실시하는 단계와; 타공의 위치마다 잭받침용 가설프레임을 설치한 후, 리프팅 잭을 잭받침용 가설프레임에 설치해 놓고 리프팅 잭의 구동 제어를 위해 유압파워팩을 상부층 슬래브에 배치하는 단계와; 하부층 슬래브에 리프팅 프레임을 설치한 후, 리프팅 와이어를 타공을 통해 삽입시킨 후 일단을 리프팅 잭에 연결하고 타단을 리프팅 프레임에 연결하는 단계와; 리프팅 잭을 구동시켜 리프팅 프레임의 인상 높이를 제어해 가면서 천정을 보수 시공하는 것을 특징으로 한다.
The present invention provides a ceiling lift-up construction method in which construction cost due to removal of scaffolding is reduced, air is shortened as a modular construction method, and existing ceilings are attempted to be changed due to renovation work of existing buildings.
A ceiling lift-up construction method according to an embodiment of the present invention includes: performing perforation position reference point work on an upper layer slab and then puncturing the upper layer slab at each reference point using a perforation equipment; Placing a lifting jack on a jack base supporting frame for each jack position, disposing a hydraulic power pack on a top layer slab for driving control of the lifting jack; Inserting the lifting wire through the hole and connecting one end to the lifting jack and the other end to the lifting frame after installing the lifting frame on the lower layer slab; The lifting jack is driven to control the lifting height of the lifting frame, and the ceiling is repaired and constructed.

Description

천정 리프트 업 시공 방법{Ceiling lift up construction method}{Ceiling lift up construction method}

본 발명은 천정 리프트 업 시공 방법에 관한 것으로, 특히 비계 공사의 제거에 따른 공사비가 절감되고, 모듈화 공법으로서 공기가 단축되고, 기존 건물의 개보수 공사에 따른 천정고 변경시에도 기존 천정을 재활용하여 천정 시공이 이루어질 수 있도록 한 천정 리프트 업 시공 방법에 관한 것이다.The present invention relates to a ceiling lift-up construction method, and more particularly, it relates to a method of constructing a ceiling lift-up construction method, in which a construction cost is reduced by eliminating a scaffold construction, air is shortened as a modular construction method, To a ceiling lift-up construction method.

기존의 천정 공사는 천정하부에 비계를 설치하여 공사하므로 많은 가설작업이 요구되며 더불어 안전사고 발생 가능성이 높았다. 즉, 천정 내 팬 필터 유닛(Fan Filter Unit), M/B 철거 및 재설치를 위해 비계를 이용하는 방법을 사용되었으나, 이 경우 비계 설치 및 해체 그리고 장시간 고소 공중 작업으로 추락위험이 상존하고, 천정 레벨이 달라 수시로 비계높이 조정 작업이 필요하며, 작업자의 투입이 많아져 공사비용을 상승시킨다.Existing ceiling construction is constructed by installing a scaffold at the bottom of the ceiling, so many construction works are required and the possibility of safety accidents is high. That is, a fan filter unit (Fan Filter Unit), a method of using a scaffold for demolishing and reinstalling the M / B, was used. In this case, there is a risk of falling due to scaffold installation and disassembly and long- Different scaffold height adjustment work is needed from time to time, and worker's input is increased, which increases construction cost.

따라서 지상 작업으로 추락위험 감소시켜 안전성을 확보하고 공사비용을 절감시킬 수 있는 방안이 요구된다.Therefore, it is required to reduce the risk of falling by ground work to secure safety and reduce construction cost.

본 발명의 배경이 되는 기술로는 한국 공개특허 공개번호 특2002-0021662호로서, '실내 리프팅장치'가 제안되어 있다. 이는 I형 빔을 사용하여 호이스트를 장착하기 위한 붐을 형성하고, 상기 붐은 일측 단부에 회전축을 결합하여 공장구조물의 천정프레임에 고정시키며, 붐의 단부에는 공장구조물의 천정프레임에 고정되는 원형레일에 의해 지지되도록 한 구조로 리프팅장치를 구성하여 회전축을 중심으로 한 붐의 회전운동과 붐에서 이루어지는 호이스트의 직선운동 조합에 의해 공간내에서 물건의 이송,운반 적재가 이루어지도록 한 구성을 갖는다. 따라서 공장이나 작업장등 천장이 낮아 대용량 크레인등의 설치가 곤란한 공간에서의 작업하물의 리프팅, 운반등에 적용될 수 있다.As a background of the present invention, Korean Unexamined Patent Publication No. 2002-0021662, an 'indoor lifting device' has been proposed. The boom is fixed to a ceiling frame of a factory structure by coupling a rotary shaft to one end of the boom. The end of the boom is fixed to a ceiling frame of a factory structure, So that the lifting device is constructed so that the object is transported and transported in the space by the combination of the rotational motion of the boom about the rotational axis and the linear motion of the hoist in the boom. Therefore, it can be applied to lifting and transportation of working load in a space where installation of a large-capacity crane or the like is difficult due to a low ceiling such as a factory or workplace.

그러나 전자의 배경기술은 바닥에서 리프트 프레임을 상승시키면서 천정 공사를 진행할 수 없고, 기존 건물의 개보수 공사에 따른 천정고 변경시 기존 천정을 재활용 할 수 없는 문제가 있다.However, the background technology of the electron can not proceed with the ceiling construction while lifting the lift frame from the floor, and there is a problem that the ceiling can not be recycled when the ceiling is changed due to the renovation work of the existing building.

한국 공개특허 공개번호 특2002-0021662호Korean Unexamined Patent Publication No. 2002-0021662

본 발명은 비계 공사의 제거에 따른 공사비가 절감되고, 모듈화 공법으로서 공기가 단축되고, 기존 건물의 개보수 공사에 따른 천정고 변경시도 기존 천정을 재활용 할 수 있도록 한 천정 리프트 업 시공 방법을 제공함에 그 목적이 있다.The present invention provides a ceiling lift-up construction method in which the construction cost due to removal of scaffolding is reduced, air is shortened as a modular construction method, and existing ceilings are attempted to be changed due to renovation work on existing buildings. .

본 발명의 일 실시 형태에 따른 천정 리프트 업 시공 방법은, 상부층 슬래브에 천공위치 기준점 작업을 수행한 후, 천공장비를 사용하여 기준점마다 상부층 슬래브에 타공을 실시하는 단계와; 타공의 위치마다 잭받침용 가설프레임을 설치한 후, 리프팅 잭을 잭받침용 가설프레임에 설치해 놓고 리프팅 잭의 구동 제어를 위해 유압파워팩을 상부층 슬래브에 배치하는 단계와; 하부층 슬래브에 리프팅 프레임을 설치한 후, 리프팅 와이어를 타공을 통해 삽입시킨 후 일단을 리프팅 잭에 연결하고 타단을 리프팅 프레임에 연결하는 단계와; 리프팅 잭을 구동시켜 리프팅 프레임의 인상 높이를 제어해 가면서 천정을 보수 시공하는 것을 특징으로 한다.A ceiling lift-up construction method according to an embodiment of the present invention includes: performing perforation position reference point work on an upper layer slab and then puncturing the upper layer slab at each reference point using a perforation equipment; Placing a lifting jack on a jack base supporting frame for each jack position, disposing a hydraulic power pack on a top layer slab for driving control of the lifting jack; Inserting the lifting wire through the hole and connecting one end to the lifting jack and the other end to the lifting frame after installing the lifting frame on the lower layer slab; The lifting jack is driven to control the lifting height of the lifting frame, and the ceiling is repaired and constructed.

본 발명의 다른 실시 형태에 따른 천정 리프트 업 시공 방법은, 상부층 슬래브에 천공위치 기준점 작업을 수행한 후, 천공장비를 사용하여 기준점마다 상부층 슬래브에 타공을 실시하는 단계와; 타공의 위치마다 잭받침용 가설프레임을 설치한 후, 리프팅 잭을 잭받침용 가설프레임에 설치해 놓고 리프팅 잭의 구동 제어를 위해 유압파워팩을 상부층 슬래브에 배치하는 단계와; 하부층 슬래브에 리프팅 프레임을 설치한 후, 리프팅 와이어를 타공을 통해 삽입시킨 후 일단을 리프팅 잭에 연결하고 타단을 리프팅 프레임에 연결하는 단계와; 리프팅 프레임에 올려진 시스템 실링을 재배열한 후 리프팅 잭을 다시 구동시켜 리프팅 프레임을 재시공 위치까지 인상시켜 놓고, 달대를 연결한 후 리프팅 잭을 다시 구동시켜 리프팅 프레임을 하강시키고 기둥 사이 실링을 수행하는 단계;를 포함하여 천정을 신축 시공하는 것을 특징으로 한다.A ceiling lift up construction method according to another embodiment of the present invention includes: performing perforation position reference point work on an upper layer slab, then puncturing the upper layer slab at each reference point using a perforating machine; Placing a lifting jack on a jack base supporting frame for each jack position, disposing a hydraulic power pack on a top layer slab for driving control of the lifting jack; Inserting the lifting wire through the hole and connecting one end to the lifting jack and the other end to the lifting frame after installing the lifting frame on the lower layer slab; The lifting frame is moved back to the retracted position by driving the lifting jack again after re-arranging the system sealing mounted on the lifting frame, then driving the lifting jack again to lower the lifting frame and performing the inter-column sealing And a ceiling is built up and expanded.

또한, 리프팅 프레임은, 동일 평면상에 종방향과 횡방향으로 배열되어 상호 접합되어 있는 H형 강재와; 리프팅 프레임의 균형된 인상을 위해 H형 강재에 접합되어 있는 다수개의 인상용 고리와; H형 강재의 상면에 종방향으로 배열된 것과 직각 방향으로 위치되어 일정 간격마다 배열되어 설치된 사각파이프와; 상기 사각파이프의 상면에 안착된 구조용 합판과; 상기 구조용 합판의 상면에 안착되어 사각파이프측에 고정된 방진고무패드와; 상기 H형 강재의 하면에 리프팅 프레임의 이동을 위해 다수 설치된 회전 바퀴를 포함하여 구성된 것을 특징으로 한다.Further, the lifting frame comprises: an H-shaped steel material which is arranged on the same plane in longitudinal and transverse directions and bonded to each other; A plurality of lifting rings joined to the H-shaped steel for balanced lifting of the lifting frame; A square pipe arranged in the longitudinal direction on the upper surface of the H-shaped steel material and disposed in a direction perpendicular to the H-shaped steel material and arranged at regular intervals; A structural plywood placed on the upper surface of the square pipe; A vibration proof rubber pad seated on the upper surface of the structural plywood and fixed to the square pipe side; And a plurality of rotating wheels provided on the lower surface of the H-shaped steel for moving the lifting frame.

또한, 잭받침용 가설프레임은 나란한 한 쌍의 H 빔, 한 쌍의 H 빔의 하부 양단에 접합되어 있는 하부 연결판, 한 쌍의 H 빔의 상부 양단에 접합되어 있는 상부 연결판을 포함하여 구성된 것을 특징으로 한다.The hypothetical frame for jack support comprises a pair of H beams arranged in parallel, a lower coupling plate joined to both lower ends of the pair of H beams, and an upper coupling plate joined to both ends of the pair of H beams .

본 발명의 천정 리프트 업 시공 방법에 따르면, 상부층에서 리프팅 잭을 구동시켜 리프팅 잭과 와이어를 매개로 연결된 하부층에 위치한 리프트 프레임을 상승시키면서 천정 공사를 진행할 수 있기 때문에 종래와 같이 비계를 사용할 필요가 없어져 비계 공사의 제거에 따른 공사비가 절감된다.According to the ceiling lift-up method of the present invention, since the lifting jack is driven in the upper layer and the lift frame located on the lower layer connected with the lifting jack via the wire is raised, ceiling work can be performed, The cost of construction due to removal of scaffold construction is reduced.

또한, 모듈화 공법으로서 종래와 같이 비계를 조립 및 해체할 필요가 없어져 공기가 단축되고, 기존 건물의 개보수 공사에 따른 천정고 변경시에도 기존 천정을 재활용 할 수 있는 장점을 갖는다.In addition, as a modularization method, there is no need to assemble and disassemble a scaffold as in the prior art, and air is shortened, and the existing ceiling can be recycled even when changing the ceiling according to the renovation work of existing buildings.

본 명세서에서 첨부되는 다음의 도면들은 본 발명의 바람직한 실시 예를 예시하는 것이며, 발명의 상세한 설명과 함께 본 발명의 기술사상을 더욱 이해시키는 역할을 하는 것이므로, 본 발명은 첨부한 도면에 기재된 사항에만 한정되어서 해석되어서는 아니 된다.
도 1은 본 발명에 따른 천정 리프트 업 시공 방법을 구현하기 위한 개략적인 시스템 구성도.
도 2 내지 도 19는 본 발명의 일 실시예에 따른 리모델링시 천정 리프트 업 시공 순서도.
도 20a는 본 발명에 적용되는 잭받침용 가설프레임의 사시도.
도 20b 및 도 20c는 본 발명에 적용되는 잭받침용 가설프레임의 서로 다른 위치에서 본 설치상태도.
도 21a는 본 발명에 적용되는 리프팅 프레임의 일부 구성도.
도 21b는 본 발명에 적용되는 리프팅 프레임의 인상용 고리 부분의 구성도.
도 21c는 도 21b의 일측면도.
도 22 내지 도 26은 본 발명의 다른 실시예에 따른 신축시 천정 리프트 업 시공 순서도.
BRIEF DESCRIPTION OF THE DRAWINGS The accompanying drawings, which are incorporated in and constitute a part of the specification, illustrate exemplary embodiments of the invention and, together with the description, serve to explain the principles of the invention, Shall not be construed as limiting.
1 is a schematic system configuration diagram for implementing a ceiling lift-up method according to the present invention;
FIGS. 2 to 19 are views showing a ceiling lift-up construction procedure in remodeling according to an embodiment of the present invention. FIG.
FIG. 20A is a perspective view of a jack-fixing frame for jack support according to the present invention; FIG.
Fig. 20B and Fig. 20C are views of the installation position of the jack-supporting temporary frame for use in the present invention, viewed from different positions. Fig.
21A is a partial structural view of a lifting frame according to the present invention.
Fig. 21B is a configuration diagram of a lifting ring portion of a lifting frame according to the present invention; Fig.
Figure 21c is a side view of Figure 21b.
FIG. 22 to FIG. 26 are flowcharts of a ceiling lift-up construction in a new construction according to another embodiment of the present invention. FIG.

아래에서 본 발명은 첨부된 도면에 제시된 실시 예를 참조하여 상세하게 설명이 되지만 제시된 실시 예는 본 발명의 명확한 이해를 위한 예시적인 것으로 본 발명은 이에 제한되지 않는다.DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described in detail below with reference to the embodiments shown in the accompanying drawings, but the present invention is not limited thereto.

본 발명에 따른 천정 리프트 업 시공 방법을 위한 시스템의 구성을 도 1을 참조하여 설명한다. The configuration of a system for a ceiling lift-up method according to the present invention will be described with reference to Fig.

도 1과 같이 천정 공사를 위해 상부층 슬래브(12)에 리프팅 잭(18)이 가설프레임(16)에 지지되어 설치된다. 리프팅 잭(18)은 리프팅 프레임(100)의 안전한 인상을 위해 4개소에 설치되어 있으나 그 이상으로 설치될 수도 있다. 리프팅 잭(18)은 유압으로 구동되는 알려진 구조로서, 중공 피스톤 실린더를 사용하고 상,하부측에 와이어를 반복적으로 클램핑하는 클램프가 설치되어 있는 구성을 갖고 있다.As shown in FIG. 1, a lifting jack 18 is mounted on the upper frame slab 12 for ceiling work while being supported by a temporary frame 16. The lifting jacks 18 are installed at four locations for safe lifting of the lifting frame 100, but they may be installed at more than one lifting jack. The lifting jack 18 is a known structure driven by hydraulic pressure, and has a structure in which a hollow piston cylinder is used and clamps are provided on upper and lower sides for repeatedly clamping the wire.

하부층 슬래브(13)에는 리프팅 잭(18)과 리프팅 와이어(22)를 매개로 연결되는 리프팅 프레임(100)이 설치된다. 이때 리프팅 와이어(22)는 상부층 슬래브(12)에 천공된 위치를 통하여 삽입된 후 리프팅 프레임(100)에 연결된다. 따라서 리프팅 프레임(100)은 리프팅 잭(18)의 구동으로 리프팅 와이어(22)를 매개로 상승할 수 있고, 상승 위치에 따라 천정 공사 작업을 수행할 수 있다. 리프팅 프레임(100)은 구조적 안전성과 이동성 및 방진을 갖기 위한 구성을 갖는 것으로 하기에서 후술한다.The lower layer slab 13 is provided with a lifting frame 100 which is connected to the lifting jack 18 via a lifting wire 22. At this time, the lifting wire 22 is inserted through the perforated position in the upper layer slab 12 and then connected to the lifting frame 100. Therefore, the lifting frame 100 can be lifted via the lifting wire 22 by driving the lifting jack 18, and the ceiling construction work can be performed according to the lifted position. The lifting frame 100 has a structure for providing structural safety, mobility and dustproofness, which will be described later.

이같이 구성된 천정 리프트 업 시공 시스템을 이용한 천정공사를 리모델링 경우와 신축 경우를 나누어 하기에서 설명한다.The ceiling construction using the ceiling lift-up construction system constructed as above is divided into a remodeling case and a stretching case.

<천정의 리모델링 공사시><Ceiling remodeling work>

천정의 리모델링 공사를 시행하는 경우에 천정 리프트 업 시공 방법을 설명한다.Describe ceiling lift-up construction method when ceiling remodeling work is carried out.

먼저, 상부층에서 천공위치 기준점작업과 슬래브타공이 이루어진다.First, the piercing position reference point work and slab piercing are done in the upper layer.

도 2와 같이 상부층 슬래브(12)에 천공위치가 되는 기준점(P) 작업을 수행한 후, 도 3과 같이 천공장비(14)를 사용하여 기준점(P)마다 상부층 슬래브(12)에 타공(12a)을 실시한다. 타공(12a)은 후술할 리프팅 프레임(100)을 인상하기 위한 인상 지점수와 동일하게 구비된다. 타공(12a)의 직경은 리프팅 와이어(22)를 충분히 통과시킬 수 있으면 족하다. 본 실시 예에서 타공(12a)은 상부층 슬래브(12)의 4개소에 형성하였으나 그 이상이 될 수도 있다. 리프팅 와이어(22)는 강연선으로 제작된 것이 바람직하다.3, the upper slab 12 is provided with perforations 12a (see FIG. 3) for every reference point P by using the perforating equipment 14 as shown in FIG. 3, ). The perforation 12a is provided to be the same as the number of pulling-up points for pulling up the lifting frame 100 to be described later. The diameter of the perforation 12a is sufficient to allow the lifting wire 22 to pass sufficiently. In this embodiment, the perforations 12a are formed at four places of the upper layer slab 12, but they may be more. The lifting wire 22 is preferably made of stranded wire.

그 다음, 잭받침용 가설프레임(16), 리프팅 잭(18) 및 유압파워팩(20)의 설치가 이루어진다.Then, the installation of the jack base supporting frame 16, the lifting jack 18 and the hydraulic power pack 20 is carried out.

이는 도 4와 같이 타공(12a)의 위치마다 잭받침용 가설프레임(16)을 설치한 후, 도 5와 같이 리프팅 잭(18)을 잭받침용 가설프레임(16) 위에 설치해 놓고 리프팅 잭(18)의 구동 제어를 위해 유압파워팩(20)을 상부층 슬래브(12)에 배치한다. 유압파워팩(20)은 리프팅 잭(18)의 구동에 필요한 압유를 공급하는 펌프 및 제어패널을 갖는다. 따라서 리프팅 잭(18)은 유압파워팩(20)과 유압라인 및 전기적 신호제어선을 통해 연결된다.5, the lifting jack 18 is mounted on the jack receiving supporting frame 16, and the lifting jack 18 (see FIG. 5) The hydraulic power pack 20 is disposed on the upper-layer slab 12 for drive control of the upper slab 12. [ The hydraulic power pack (20) has a pump and a control panel for supplying the pressurized oil necessary for driving the lifting jack (18). The lifting jack 18 is thus connected to the hydraulic power pack 20 via hydraulic lines and electrical signal control lines.

잭받침용 가설프레임(16)은 도 20a 내지 도 20c와 같이 나란한 한 쌍의 H 빔(161,161), 한 쌍의 H 빔(161,161)의 하부 양단에 접합되어 있는 하부 연결판(162,162), 한 쌍의 H 빔(161,161)의 상부 양단에 접합되어 있는 상부 연결판(163,163)을 포함하여 구성된다. 잭받침용 가설프레임(16)은 하부 연결판(162,162)에 설치되는 앵커볼트(165)를 통해 상부층 슬래브(12)에 고정 설치된다. 이때 한 쌍의 H 빔(161,161)의 간격은 리프팅 와이어(22)를 충분히 삽통시킬 수 있도록 한다.The jack supporting pedestal frame 16 includes a pair of H beams 161 and 161 arranged side by side as shown in Figs. 20A to 20C, lower connecting plates 162 and 162 bonded to both ends of a lower portion of a pair of H beams 161 and 161, And upper connection plates 163 and 163 bonded to both ends of the upper portions of the H beams 161 and 161 of the first and second H beams 161 and 161, respectively. The jack-supporting hypothetical frame 16 is fixed to the upper-layer slab 12 through anchor bolts 165 installed on the lower connecting plates 162 and 162. The spacing of the pair of H beams 161,161 allows the lifting wire 22 to be inserted sufficiently.

그 다음, 도 6과 같이 하부층 슬래브(13)에 리프팅 프레임(100)을 설치한 후, 리프팅 와이어(22)를 타공(12a)을 통해 삽입시킨 후 일단을 리프팅 잭(18)에 연결하고 타단을 리프팅 프레임(100)에 연결한다.6, after the lifting frame 100 is installed on the lower layer slab 13, the lifting wire 22 is inserted through the hole 12a, one end is connected to the lifting jack 18, To the lifting frame (100).

도 21a 내지 도 21c와 같이 리프팅 프레임(100)은 동일 평면상에 종방향과 횡방향으로 배열되어 상호 접합되어 있는 H형 강재(101)와, 리프팅 프레임(100)의 균형된 인상을 위해 H형 강재(101)에 접합되어 있는 다수개의 인상용 고리(102)와, H형 강재(101)의 상면에 종방향으로 배열된 것과 직각 방향으로 위치되어 일정 간격마다 배열되어 설치된 사각파이프(103)와, 사각파이프(103)의 상면에 안착된 구조용 합판(104)과, 상기 구조용 합판(104)의 상면에 안착되어 사각파이프(103)측에 고정된 방진고무패드(105)와, H형 강재(101)의 하면에 리프팅 프레임(100)의 이동을 위해 다수 설치된 회전 바퀴(106)를 포함하여 구성된다. 여기서, 구조용 합판(104)과 방진고무패드(105)는 사각파이프(103)에 나사결합되는 스크류나사(107)에 의해 고정된다.As shown in FIGS. 21A to 21C, the lifting frame 100 includes an H-shaped steel material 101 which is arranged on the same plane in the longitudinal direction and the transverse direction and bonded to each other, A plurality of pulling rings 102 joined to the steel material 101, a rectangular pipe 103 arranged longitudinally on the upper surface of the H-shaped steel material 101 and arranged in a direction perpendicular to the H- An anti-vibration rubber pad 105 which is seated on the upper surface of the structural plywood 104 and fixed to the side of the square pipe 103, And a plurality of rotating wheels 106 installed on the lower surface of the lifting frame 100 for moving the lifting frame 100. Here, the structural plywood 104 and the anti-vibration rubber pad 105 are fixed by a screw 107 screwed to the square pipe 103.

그 다음, 도 7과 같이 리프팅 잭(18)을 구동시켜 낮은 층고부까지 리프팅 프레임(100)을 인상시켜 놓고, 도 1의 낮은 층고부 달대(121) 및 도 9에서 단차판을 해체하는 작업을 실시한다. 낮은 층고부 달대(121)는 2차 달대로서 각파이프에서 몰드 바 즉 실링을 지지한다.Then, the lifting jack 18 is driven to pull up the lifting frame 100 to the lower tier and the operation of dismounting the lower tier tier 121 of Fig. 1 and the step plate of Fig. 9 Conduct. The low-rise tall lantern 121 supports the mold bar or seal in each pipe as a secondary lantern.

그 다음, 도 10과 같이 리프팅 잭(18)을 다시 구동시켜 높은 층고부까지 리프팅 프레임(100)을 재인상시켜 놓고, 도 1에 도시된 높은 층고부 달대(123)를 도 11과 같이 해체하는 작업을 실시한다. 높은 층고부 달대(123)는 1차 달대로서 슬래브에서 각파이프를 지지한다.Then, the lifting jack 18 is driven again as shown in Fig. 10 to re-raise the lifting frame 100 to the higher and higher tiers, and the high-tier lifter 123 shown in Fig. 1 is dismantled as shown in Fig. 11 Perform work. The high-rise high-rise lane 123 supports each pipe in the slab as the primary lunar stage.

그 다음, 도 12와 같이 리프팅 잭(18)을 다시 구동시켜 리프팅 프레임(100)을 하강시켜 놓은 후, 도 13과 같이 기둥 사이 실링 철거와 도 14와 같이 시스템 실링을 재배열하는 작업을 실시한다. 여기서 시스템 실링은 천정에 시공되는 부설물로서 팬 필터 유닛, 천정 마감재 등을 의미한다.Then, the lifting jack 18 is driven again to lower the lifting frame 100 as shown in FIG. 12, and thereafter, work for lifting and lowering the sealing between the pillars and the system as shown in FIG. 14 is performed . Here, the system sealing refers to a fan filter unit, a ceiling finishing material, or the like, which is laid on the ceiling.

그 다음, 도 15와 같이 재시공 위치까지 리프팅 잭(18)을 다시 구동시켜 리프팅 프레임(100)을 재시공 위치까지 인상시켜 놓고, 도 16과 같이 달대를 연결한 후 도 17과 같이 리프팅 잭(18)을 다시 구동시켜 리프팅 프레임(100)을 하강시킨다. 이후 도 18과 같이 기둥 사이 실링을 수행하여 도 19와 같이 작업을 마치게 된다.15, the lifting jack 18 is driven again to raise the lifting frame 100 to the retry position. After the lifting jack 18 is connected to the lifting jack 18 as shown in FIG. 16, The lifting frame 100 is lowered. Thereafter, as shown in FIG. 18, the column-to-column sealing is performed to complete the operation as shown in FIG.

여기서, 리프팅 프레임(100)에는 구조용 합판(104)과 방진고무패드(105)가 설치되어 있어 실링의 재배열 작업시 소음이 발생되지 않는다. 또한 회전 바퀴(106)의 설치로 인해 리프팅 프레임(100)의 전체 중량의 영향을 받지 않고 이웃한 작업 위치로 리프팅 프레임(100)을 용이하게 이동시킬 수 있다.Here, since the structural plywood 104 and the anti-vibration rubber pad 105 are installed in the lifting frame 100, no noise is generated during the re-arrangement of the sealing. Also, the lifting frame 100 can be easily moved to a neighboring working position without being affected by the entire weight of the lifting frame 100 by installing the rotary wheel 106.

<천정의 신축 공사시><New construction of ceiling>

한편, 천정의 신축 공사를 시행하는 경우에 천정 리프트 업 시공 방법을 설명한다.On the other hand, the ceiling lift-up construction method is explained when the ceiling is newly constructed.

먼저, 상부층 슬래브(12)의 시공시 기준점마다 타공(12a)을 형성하여 둔다. 여기서 타공(12a)은 도시안된 원통관(슬리브)을 미리 매립하여 두고 상부층 슬래브(12)의 콘크리트 타설시 형성된다. 이후 잭받침용 가설프레임(16), 리프팅 잭(18) 및 유압파워팩(20)의 설치가 순차적으로 이루어진다.First, a perforation 12a is formed for each reference point at the time of construction of the upper slab 12. Here, the perforation 12a is formed when the unillustrated tube (sleeve) is previously embedded and the concrete of the upper layer slab 12 is poured. Thereafter, the installation of the jack base supporting frame 16, the lifting jack 18 and the hydraulic power pack 20 are sequentially performed.

이는 리모델링 시공과 동일한 방법으로써 상세한 설명은 생략한다.This is the same method as the remodeling construction and the detailed description is omitted.

이후, 도 22와 같이 리프팅 프레임(100)에 올려진 시스템 실링을 재배열한 후, 도 23과 같이 리프팅 잭(18)을 다시 구동시켜 리프팅 프레임(100)을 재시공 위치까지 인상시켜 놓는다. 여기서 시스템 실링은 천정에 시공되는 부설물로서 팬 필터 유닛, 천정 마감재 등을 의미한다.Thereafter, as shown in FIG. 22, the lifting frame 100 is lifted up to the retreat position by rearranging the lifting frame 100 and lifting the lifting jack 18 again as shown in FIG. Here, the system sealing refers to a fan filter unit, a ceiling finishing material, or the like, which is laid on the ceiling.

그 다음, 도 24와 같이 통상의 달대를 시스템 실링과 연결한 후 리프팅 잭(18)을 다시 구동시켜 도 25와 같이 리프팅 프레임(100)을 하강시킨다. 이후 도 26과 같이 기둥 사이의 실링을 수행하는 작업을 갖는다.Then, as shown in FIG. 24, the lifting frame 100 is lowered as shown in FIG. 25 by driving the lifting jack 18 again after connecting the normal month to the system sealing. Thereafter, as shown in Fig. 26, there is performed an operation of performing sealing between the columns.

이같이 천정의 신축 공사시에는 상대적으로 리모델링 시공과 달리 작업이 단축되어 실링 작업 시간을 더욱 단축시킬 수 있다.In this way, the ceiling construction can be shortened in comparison with the remodeling construction, thereby shortening the sealing work time.

이와 같이 본 공법에 따르면, 비계 공사를 사용하지 않으므로 공사비가 절감되고, 모듈화 공법으로서 공기가 단축되고, 기존건물 개보수 공사에 따른 천정고 변경시 기존 천정을 재활용 할 수 있는 장점을 갖는다.As described above, according to the present method, since the scaffold construction is not used, the construction cost is reduced, the air is shortened as a modularization method, and the existing ceiling can be recycled when the ceiling is changed according to the existing building renovation work.

지금까지 본 발명은 제시된 실시 예를 참조하여 상세하게 설명이 되었지만 이 분야에서 통상의 지식을 가진 자는 제시된 실시 예를 참조하여 본 발명의 기술적 사상을 벗어나지 않는 범위에서 다양한 변형 및 수정 발명을 만들 수 있을 것이다. 본 발명은 이와 같은 변형 및 수정 발명에 의하여 제한되지 않으며 다만 아래에 첨부된 청구범위에 의하여 제한된다. While the present invention has been particularly shown and described with reference to exemplary embodiments thereof, it is evident that many alternatives, modifications and variations will be apparent to those skilled in the art in light of the above teachings. will be. The invention is not limited by these variations and modifications, but is limited only by the claims appended hereto.

16: 잭받침용 가설프레임
18: 리프팅 잭
22: 리프팅 와이어
100: 리프팅 프레임
16: Hybrid frame for jack base
18: Lifting jack
22: lifting wire
100: Lifting frame

Claims (4)

(a) 상부층 슬래브(12)에 천공위치 기준점 작업을 수행한 후, 천공장비(14)를 사용하여 기준점마다 상부층 슬래브(12)에 타공(12a)을 실시하는 단계와;
(b) 타공(12a)의 위치마다 잭받침용 가설프레임(16)을 설치한 후, 리프팅 잭(18)을 잭받침용 가설프레임(16)에 설치해 놓고 리프팅 잭(18)의 구동 제어를 위해 유압파워팩(20)을 상부층 슬래브(12)에 배치하는 단계와;
(c) 하부층 슬래브(13)에 리프팅 프레임(100)을 설치한 후, 리프팅 와이어(22)를 타공(12a)을 통해 삽입시킨 후 일단을 리프팅 잭(18)에 연결하고 타단을 리프팅 프레임(100)에 연결하는 단계와;
(d) 리프팅 잭(18)을 구동시켜 리프팅 프레임(100)의 인상 높이를 제어해 가면서 천정을 보수 시공하되;
리프팅 프레임(100)은, 동일 평면상에 종방향과 횡방향으로 배열되어 상호 접합되어 있는 H형 강재(101)와; 리프팅 프레임(100)의 균형된 인상을 위해 H형 강재(101)에 접합되어 있는 다수개의 인상용 고리(102)와; H형 강재(101)의 상면에 종방향으로 배열된 것과 직각 방향으로 위치되어 일정 간격마다 배열되어 설치된 사각파이프(103)와; 사각파이프(103)의 상면에 안착된 구조용 합판(104)과; 상기 구조용 합판(104)의 상면에 안착되어 사각파이프(103)측에 고정된 방진고무패드(105)와; 상기 H형 강재(101)의 하면에 리프팅 프레임(100)의 이동을 위해 다수 설치된 회전 바퀴(106);를 포함하여 구성된 것을 특징으로 하는 천정 리프트 업 시공 방법.
(a) performing a perforation position reference point operation on the upper layer slab 12, and then performing a perforation 12a on the upper layer slab 12 at each reference point using the perforation equipment 14;
(b) After installing the jack-supporting hypothetical frame 16 at each position of the perforation 12a, the lifting jack 18 is installed in the jack-supporting temporary frame 16, and for the drive control of the lifting jack 18 Placing the hydraulic power pack (20) in the upper layer slab (12);
(c) After the lifting frame 100 is installed on the lower layer slab 13, the lifting wire 22 is inserted through the hole 12a, one end is connected to the lifting jack 18 and the other end is connected to the lifting frame 100 );
(d) repairing the ceiling while driving the lifting jack (18) to control the lifting height of the lifting frame (100);
The lifting frame (100) comprises: an H-shaped steel material (101) arranged on the same plane in longitudinal and transverse directions and bonded to each other; A plurality of lifting rings (102) joined to the H-shaped steel (101) for balanced lifting of the lifting frame (100); A square pipe 103 arranged longitudinally on the upper surface of the H-shaped steel material 101 and arranged in a direction perpendicular to the H-shaped steel material 101 and arranged at regular intervals; A structural plywood (104) seated on the upper surface of the square pipe (103); An anti-vibration rubber pad 105 mounted on the upper surface of the structural plywood 104 and fixed to the side of the square pipe 103; And a plurality of rotating wheels (106) installed on the lower surface of the H-shaped steel material (101) for moving the lifting frame (100).
(a) 상부층 슬래브(12)의 시공시 기준점마다 타공(12a)을 형성하여 두는 단계와;
(b) 타공(12a)의 위치마다 잭받침용 가설프레임(16)을 설치한 후, 리프팅 잭(18)을 잭받침용 가설프레임(16)에 설치해 놓고 리프팅 잭(18)의 구동 제어를 위해 유압파워팩(20)을 상부층 슬래브(12)에 배치하는 단계와;
(c) 하부층 슬래브(13)에 리프팅 프레임(100)을 설치한 후, 리프팅 와이어(22)를 타공(12a)을 통해 삽입시킨 후 일단을 리프팅 잭(18)에 연결하고 타단을 리프팅 프레임(100)에 연결하는 단계와;
(d) 리프팅 프레임(100)에 올려진 시스템 실링을 재배열한 후 리프팅 잭(18)을 다시 구동시켜 리프팅 프레임(100)을 재시공 위치까지 인상시켜 놓고, 달대를 연결한 후 리프팅 잭(18)을 다시 구동시켜 리프팅 프레임(100)을 하강시키고 기둥 사이 실링을 수행하는 단계;를 포함하여 천정을 신축 시공하되,
리프팅 프레임(100)은, 동일 평면상에 종방향과 횡방향으로 배열되어 상호 접합되어 있는 H형 강재(101)와; 리프팅 프레임(100)의 균형된 인상을 위해 H형 강재(101)에 접합되어 있는 다수개의 인상용 고리(102)와; H형 강재(101)의 상면에 종방향으로 배열된 것과 직각 방향으로 위치되어 일정 간격마다 배열되어 설치된 사각파이프(103)와; 사각파이프(103)의 상면에 안착된 구조용 합판(104)과; 상기 구조용 합판(104)의 상면에 안착되어 사각파이프(103)측에 고정된 방진고무패드(105)와; 상기 H형 강재(101)의 하면에 리프팅 프레임(100)의 이동을 위해 다수 설치된 회전 바퀴(106);를 포함하여 구성된 것을 특징으로 하는 천정 리프트 업 시공 방법.
(a) forming a perforation (12a) for each reference point at the time of construction of the upper slab (12);
(b) After installing the jack-supporting hypothetical frame 16 at each position of the perforation 12a, the lifting jack 18 is installed in the jack-supporting temporary frame 16, and for the drive control of the lifting jack 18 Placing the hydraulic power pack (20) in the upper layer slab (12);
(c) After the lifting frame 100 is installed on the lower layer slab 13, the lifting wire 22 is inserted through the hole 12a, one end is connected to the lifting jack 18 and the other end is connected to the lifting frame 100 );
(d) After lifting the system seal on the lifting frame 100, the lifting jack 18 is driven again to raise the lifting frame 100 to the retracted position. After lifting the lifting frame 100, And lowering the lifting frame 100 and performing ceiling sealing between the pillars,
The lifting frame (100) comprises: an H-shaped steel material (101) arranged on the same plane in longitudinal and transverse directions and bonded to each other; A plurality of lifting rings (102) joined to the H-shaped steel (101) for balanced lifting of the lifting frame (100); A square pipe 103 arranged longitudinally on the upper surface of the H-shaped steel material 101 and arranged in a direction perpendicular to the H-shaped steel material 101 and arranged at regular intervals; A structural plywood (104) seated on the upper surface of the square pipe (103); An anti-vibration rubber pad 105 mounted on the upper surface of the structural plywood 104 and fixed to the side of the square pipe 103; And a plurality of rotating wheels (106) installed on the lower surface of the H-shaped steel material (101) for moving the lifting frame (100).
삭제delete 제 1항 또는 제 2항에 있어서,
잭받침용 가설프레임(16)은 나란한 한 쌍의 H 빔(161,161), 한 쌍의 H 빔(161,161)의 하부 양단에 접합되어 있는 하부 연결판(162,162), 한 쌍의 H 빔(161,161)의 상부 양단에 접합되어 있는 상부 연결판(163,163)을 포함하여 구성된 것을 특징으로 하는 천정 리프트 업 시공 방법.
3. The method according to claim 1 or 2,
The jack supporting pedestal frame 16 includes a pair of H beams 161 and 161, lower connecting plates 162 and 162 bonded to both ends of a pair of H beams 161 and 161, a pair of H beams 161 and 161 And upper connection plates (163, 163) joined to both ends of the upper portion.
KR1020170005636A 2017-01-12 2017-01-12 Ceiling lift up construction method KR101922324B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020170005636A KR101922324B1 (en) 2017-01-12 2017-01-12 Ceiling lift up construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020170005636A KR101922324B1 (en) 2017-01-12 2017-01-12 Ceiling lift up construction method

Publications (2)

Publication Number Publication Date
KR20180083229A KR20180083229A (en) 2018-07-20
KR101922324B1 true KR101922324B1 (en) 2018-11-26

Family

ID=63103603

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020170005636A KR101922324B1 (en) 2017-01-12 2017-01-12 Ceiling lift up construction method

Country Status (1)

Country Link
KR (1) KR101922324B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2020028965A1 (en) * 2018-08-10 2020-02-13 Kirschner Junior Paulo Movable platform assembly for a housing unit, movable platform assembly arrangement for a housing unit, housing unit and group of housing units
CN111287441A (en) * 2020-02-18 2020-06-16 中国建筑第八工程局有限公司 Suspended anti-shaking construction platform and construction method thereof
KR20210056621A (en) 2019-11-11 2021-05-20 박배승 Apparatus for drilling on the ceil
KR20220146056A (en) 2021-04-23 2022-11-01 장동익 Lifting apparatus using hydraulic cylinder

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101977909B1 (en) * 2018-09-11 2019-05-21 주식회사 경신산기 Gondola for working at indoor
KR102242485B1 (en) * 2019-04-24 2021-04-20 삼성물산 주식회사 Method for vertical transportation of a heavy module using of a module lifting system inculding of a strand jack

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008038414A (en) * 2006-08-03 2008-02-21 Hitachi Plant Technologies Ltd Construction method for boiler cage section floor

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4921649A (en) * 1987-09-21 1990-05-01 Greeson Logan C Method for pouring concrete slabs
JP2003008414A (en) * 2001-06-21 2003-01-10 Seiko Epson Corp Clock edge detection circuit
KR20020021662A (en) 2002-02-15 2002-03-21 이규석 Lifting Device at Work Room
KR100944458B1 (en) * 2007-09-28 2010-03-03 삼성중공업 주식회사 Apparatus preventing separation of cage for construction
KR101250482B1 (en) * 2010-06-14 2013-04-03 (주)엠씨에스에스티기술사사무소 Underground slab construction method using wire rope and curing pannel flame

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008038414A (en) * 2006-08-03 2008-02-21 Hitachi Plant Technologies Ltd Construction method for boiler cage section floor

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2020028965A1 (en) * 2018-08-10 2020-02-13 Kirschner Junior Paulo Movable platform assembly for a housing unit, movable platform assembly arrangement for a housing unit, housing unit and group of housing units
KR20210056621A (en) 2019-11-11 2021-05-20 박배승 Apparatus for drilling on the ceil
CN111287441A (en) * 2020-02-18 2020-06-16 中国建筑第八工程局有限公司 Suspended anti-shaking construction platform and construction method thereof
KR20220146056A (en) 2021-04-23 2022-11-01 장동익 Lifting apparatus using hydraulic cylinder

Also Published As

Publication number Publication date
KR20180083229A (en) 2018-07-20

Similar Documents

Publication Publication Date Title
KR101922324B1 (en) Ceiling lift up construction method
JP4563413B2 (en) Bridge girder construction method
CN108868193B (en) Construction method for reversely dismantling steel structure building
KR102063433B1 (en) vertical refloat method of the integrated module for plumbing fixture
JP6503716B2 (en) Demolition system and demolition method
US20130263549A1 (en) Safety screen system for steel erection work
JP5390553B2 (en) Pile press-fitting device
JP2010242308A (en) Method for demolishing high-rise building of concrete slab structure, and concrete slab demolition equipment
JP6508958B2 (en) Demolition system and demolition method
JP6712501B2 (en) High-rise building demolition system and demolition method
JP2017031681A (en) Scaffold for chimney demolition, and chimney demolition method
JP6059176B2 (en) Mobile lifting scaffold for assembling temporary elevated jetty
JPH08270232A (en) Demolishing method for steel structural building
JP2018003559A (en) Column-beam frame repairing method and repaired column-beam frame
JP6508959B2 (en) Demolition system and demolition method
JP6391134B2 (en) Dismantling method and dismantling system
JP2017040072A (en) Chimney demolition scaffold
JP5356091B2 (en) Crane girder exchanging method and crane girder exchanging apparatus
CN104372948A (en) Elevator shaft formwork lifting frame
JP6061339B2 (en) Structure reconstruction method and structure reconstruction system
KR100293687B1 (en) Concrete delivery device and its installation method
US11946217B1 (en) Top plate jacking device and jacking construction method configured for V-shaped columns
JP5437876B2 (en) Method of dismantling and removing support members in the construction process of RC RC ramen structure viaduct
JPH10184037A (en) Construction method of water-containing type gas holder
JP3834325B2 (en) Building demolition method

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant