KR101722574B1 - Riser pipe installation apparatus and construction method thereof - Google Patents
Riser pipe installation apparatus and construction method thereof Download PDFInfo
- Publication number
- KR101722574B1 KR101722574B1 KR1020150089310A KR20150089310A KR101722574B1 KR 101722574 B1 KR101722574 B1 KR 101722574B1 KR 1020150089310 A KR1020150089310 A KR 1020150089310A KR 20150089310 A KR20150089310 A KR 20150089310A KR 101722574 B1 KR101722574 B1 KR 101722574B1
- Authority
- KR
- South Korea
- Prior art keywords
- pipe
- frame
- piping
- lifting
- lift
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F17/00—Vertical ducts; Channels, e.g. for drainage
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
- E04G21/163—Jacks specially adapted for working-up building elements
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Sewage (AREA)
Abstract
In the granular piping installation apparatus (A) of a building according to the present invention, the piping 100 is installed in an upright state, and the piping 100 is connected through a piping hole 2 formed in the upper floor slab 1 And a fixing frame 420 for fixing the pipe 100 moved to the upper level by the lift-up device 410. The lift-up device 410 includes a lift-
According to the present invention, it is possible to easily construct the granular piping in the field by using the granular piping installation device. In addition, it minimizes site work and shortens construction period.
In addition, it is possible to prevent a safety accident at the site and to minimize the input of construction manpower by performing piping installation work by using a granular piping installation device.
Description
The present invention relates to a granular piping installation apparatus for installing a granular piping of a plant and an architectural structure and a granular piping installation method using the granular piping installation apparatus. More particularly, the present invention relates to a granular piping installation apparatus The present invention relates to a granular piping installation apparatus and a granular piping installation method using the granular piping installation apparatus, which can simplify the field work and shorten the air by lifting the granular pipeline successively.
Generally, the granulation piping such as the air-conditioning piping and the water supply piping of the plant and the factory is installed by a method in which the piping is installed after a supporting stand for supporting the piping is installed.
When installing granular piping on multiple floors, first install piping for each floor, then install piping hole (2) on bottom slab (1), install piping through piping hole (2) And the piping is completed by connecting with the piping.
That is, a method has been adopted in which piping construction is started in each of a plurality of layers, and an interlayer connecting pipe is connected to a piping installed in each layer.
In this case, there is a problem that the process time is long and the working efficiency is lowered because the supporter is provided and the interlayer connection pipe is to be connected while each pipeline is installed afterwards.
An object of the present invention is to provide a method for constructing a plurality of building granular piping, in which piping holes (2) are firstly installed in a plurality of slabs (1), and the granular piping installation device (A) And to provide a granular piping construction method using the same.
It is another object of the present invention to provide a granular piping installation apparatus and a construction method which can shorten a construction period by minimizing field work.
It is still another object of the present invention to provide a granular piping installation apparatus and a construction method that can prevent safety accidents on site by minimizing installation work by using a granular piping installation apparatus, .
In order to solve the above problems, the present invention provides a granular piping installation apparatus (A) for a building, comprising a piping (100) installed in an upright state, a piping hole (2) formed in an upper floor slab A lift up
The lift-up
A
The
The lift adjusting
The
The moving
The layer
The upper
A lift-up device (410) includes a support frame (411) installed in an upright position, a lower end of the pipe (100) A moving
The
A second step S200 of lifting the moving
The
The upper end of the
It is preferable that the first step (S100) to the sixth step (S600) are repeated to complete the installation of a plurality of layers.
According to the present invention, the granular piping installation apparatus and the granular piping installation method using the granular piping installation apparatus can be used to continuously construct the granular piping in the field.
According to the present invention, it is possible to minimize the field work and shorten the construction period.
According to the present invention, it is possible to prevent a safety accident at the site and to minimize the input of construction manpower by performing pipeline installation work by using the granular pipeline installation apparatus.
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a perspective view of a granular piping installation using a granular piping installation apparatus according to an embodiment of the present invention; FIG.
2 is a perspective view of a lift-up device according to an embodiment of the present invention;
3 is a perspective view of a fixed frame according to an embodiment of the present invention;
4 is a perspective view of a mobile frame according to an embodiment of the present invention;
FIG. 5 is a perspective view of a floor pipe fixing frame according to an embodiment of the present invention. FIG.
FIG. 6 is a perspective view of a pipe lifting device and a reinforcing frame according to an embodiment of the present invention; FIG.
7 is a perspective view of a lift control device coupled to a support frame in accordance with one embodiment of the present invention.
8 is a sectional view of a first step construction method according to an embodiment of the present invention;
9 is a sectional view of a second step construction method according to an embodiment of the present invention.
10 is a sectional view of a fourth step construction method according to an embodiment of the present invention;
11 is a cross-sectional view of steps 5 and 6 according to an embodiment of the present invention.
12 is a cross-sectional view of a sixth step according to an embodiment of the present invention;
The present invention will now be described more fully hereinafter with reference to the accompanying drawings, in which exemplary embodiments of the invention are shown. And redundant explanations thereof will be omitted.
It is also to be understood that the terms first, second, etc. used hereinafter are merely reference numerals for distinguishing between identical or corresponding components, and the same or corresponding components are defined by terms such as first, second, no.
In addition, the term " coupled " is used not only in the case of direct physical contact between the respective constituent elements in the contact relation between the constituent elements, but also means that other constituent elements are interposed between the constituent elements, Use them as a concept to cover each contact.
Hereinafter, a granular pipe installation apparatus and a granular pipe installation method using the granular pipe installation apparatus according to an embodiment of the present invention will be described in detail with reference to the accompanying drawings.
The granular piping installation apparatus A according to the present invention mounts the
In this case, the
In addition, since the construction is carried out with a small number of workers, safety accidents can be minimized.
The lift-up
In this case, since the lift-up device is constituted only by the combination of the moving frame, the supporting frame and the floor
Further, since one or a plurality of pipes can be stacked at the same time, the plurality of granular pipes can be lifted at the same time.
The
In this case, since the pipe lifting device for lifting the pipe and the lifting device for lifting the moving frame lifts the pipe, the pulley-type device driven by the chain is used. Therefore, Can be performed.
In addition, since the pipe lifting device and the lift adjusting device are small in size, it is easy to install and disassemble the movable frame.
The
In this case, since the pipe lifting device can move in the left-right direction by being coupled to the reinforcing frame, it is possible to stably mount a plurality of granular pipes in the moving frame.
In addition, the piping lifting device is divided into a lifting device support and a lifting pulley, so that the lifting device can be easily installed and disassembled.
The
In this case, since the lift adjusting device is structured to be coupled to the connecting
Further, since the mobile frame is lifted up by driving the chain with a human force, no separate power unit is required, and the construction can be completed only by the human force.
The upper
The fixed frame temporarily fixes the piping (100) moved to the upper portion to provide a lower work space where the next process can be smoothly prepared. At the same time, the fixed frame functions as a first piping (100) lifted and a second piping It is used as a welding workshop.
In this case, since the upper layer
The moving
In this case, since the moving frame is constituted by the connecting
In addition, since the
Since the
The layer
In this case, since the length and position of the
Further, the piping lifted by the moving frame can be stably supported.
The upper layer
In this case, since the upper
Further, since the piping lifted to the upper layer is supported by the upper-layer
The method of installing the granulation piping of the building using the lift-up
The
The granulation piping can be installed in a plurality of layers by repeating the first step S100 to the sixth step S600.
In this case, it is possible to construct the granular piping, which is independently or plurally connected, from the lower layer to the upper layer. This improves the operating speed of the existing granular piping construction method, which must be installed and fixed individually in a plurality of layers.
In addition, since the work is performed only in the lower layer portion, the safety of the worker is improved, and the entire process can be shortened because different layers can be performed in all layers other than the work layer.
In addition, since all processes are performed by manpower, no separate power equipment and large equipment are required, and uniform construction is possible.
It will be apparent to those skilled in the art that various modifications and variations can be made in the present invention without departing from the spirit or scope of the invention as defined in the appended claims. It is to be understood that both the technical idea and the technical spirit of the invention are included in the scope of the present invention.
A: Granite piping installation 1: Upper floor slab
2: piping hole 100: piping
410: lift-up device 411: support frame
412: Moving
412b:
413: the floor
414: Pipe lifting device 415: Lift control device
416: reinforcing frame 420: fixed frame
421: upper layer supporting frame 422: upper layer pipe fixing frame
422a: upper layer
422c: upper layer piping support
Claims (12)
A lift-up device 410 for lifting the pipe 100 to an upper level through a pipe hole 2 formed in an upper-stage bottom slab 1, the pipe 100 being installed in an upright state; And
And a fixing frame 420 for fixing the pipe 100 moved to the upper layer by the lift-up device 410
The lift-up device 410
An upright support frame 411;
A movable frame 412 which is fixed to the lower end of the pipe 100 and which is coupled to the pair of support frames 411 and is moved up and down along the longitudinal direction of the support frame 411;
A floor pipe fixing frame 413 for restraining an upper portion of the pipe 100 mounted on the moving frame 412;
A pipe lifting device 414 lifting the upper end of the pipe 100 so that the pipe 100 can be placed upright on the moving frame 412;
And a lift adjusting device (415) lifting the moving frame (412) so that the moving frame (412) can be moved up and down along the longitudinal direction of the supporting frame (411)
The pipe lifting device 414,
A reinforcing frame 416 to which both ends are coupled to the pair of support frames 411;
A lifting device support 414a formed in a structure to be fitted to the reinforcing frame 416 so as to be movable laterally on the reinforcing frame 416;
And a lifting sheave 414c coupled to the lifting device support 414a and lifting the upper portion of the pipe 100,
The fixed frame 420
An upper pipe fixing frame 422 for fixing the pipe 100 moved to the upper level by the lift-up device 410; And
And an upper support frame 421 supporting the upper pipe fixing frame 422 so that the upper pipe fixing frame 422 can be spaced apart from the upper floor slab 1 at a predetermined interval To be installed in the piping system.
The lift adjusting device 415
A body portion 415a for receiving the pulley;
An upper ring portion 415b formed on the body portion 415a and connected to the support frame connection portion 411a by a ring;
And a chain 415c having one end coupled to the moving frame 412 and the other end exposed to the outside of the body 415a around the pulley,
And the height of the moving frame (412) changes according to driving of the chain (415c).
The moving frame 412
A connection portion 412a fitted to the support frame 411;
A bottom plate 412b coupled with the connection portion 412a; And
A pipe fixing part 412c protruding from the upper surface of the bottom plate 412b to prevent the pipe 100 from being detached when the pipe 100 is lifted;
And wherein the plurality of piping devices are connected to each other.
The layer pipe fixing frame 413 includes:
A pipe support frame 413b provided along the longitudinal direction of the bottom plate 412b;
A pipe fixing arm 413c coupled to the pipe support frame 413b and formed at a position corresponding to the pipe fixing portion 412c;
And wherein the plurality of piping devices are connected to each other.
The upper layer pipe fixing frame 422
An upper vertical plate 422a coupled to the pair of upper support frames 421;
A pair of upper horizontal plate (422b) coupled to the upper vertical plate (422a) to form the upper pipe fixing frame (422) having a lattice shape; And
And an upper pipe support part (422c) coupled to an inner side of the pair of upper side horizontal plates (422b) to support the pipe (100).
The lift-up device 410
An upright support frame 411;
A movable frame 412 which is fixed to the lower end of the pipe 100 and which is coupled to the pair of support frames 411 and is moved up and down along the longitudinal direction of the support frame 411; And
And a floor pipe fixing frame 413 for restraining a part of the pipe 100 which is fixed to the moving frame 412,
The fixed frame 420
An upper pipe fixing frame 422 for fixing the pipe 100 moved to the upper level by the lift-up device 410; And
And an upper supporting frame 421 supporting the upper pipe fixing frame 422 such that the upper pipe fixing frame 422 can be spaced apart from the upper floor slab 1 at a predetermined interval,
A first step S100 of erecting and mounting the first pipe 100a in the moving frame 412 and restraining a part of the first pipe 100a in the layer pipe fixing frame 413;
A second step S200 of lifting the moving frame 412 upward to move a part of the first pipe 100a to an upper layer through a pipe hole 2 formed in the upper floor slab 1; And
A third step S300 of restricting the first pipe 100a using the upper pipe fixing frame 422 and moving the moving frame 412 downward from the first pipe 100a by separating the moving pipe 412 from the first pipe 100a; And a step of installing the granular piping of the building.
The second pipe 100b can be erected upright on the lower part of the first pipe 100a and the second pipe 100b can be mounted on the floor pipe fixing frame 413, (S400) of restricting a part of the image (S400);
The upper end of the second pipe 100b pushes up the lower end of the first pipe 100a so that the contact portion between the second pipe 100b and the first pipe 100a is lifted up by lifting the moving frame 412 upward, A fifth step (S500) of causing the upper pipe fixing frame (422) to be positioned between the pipe hole (2) and the upper pipe fixing frame (422); And
A sixth step (S600) of welding the contact portion;
Wherein the method comprises the steps of:
Wherein the first step (S100) to the sixth step (S600) are repeatedly performed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020150089310A KR101722574B1 (en) | 2015-06-23 | 2015-06-23 | Riser pipe installation apparatus and construction method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020150089310A KR101722574B1 (en) | 2015-06-23 | 2015-06-23 | Riser pipe installation apparatus and construction method thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20170000277A KR20170000277A (en) | 2017-01-02 |
KR101722574B1 true KR101722574B1 (en) | 2017-04-11 |
Family
ID=57810610
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020150089310A KR101722574B1 (en) | 2015-06-23 | 2015-06-23 | Riser pipe installation apparatus and construction method thereof |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR101722574B1 (en) |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003294170A (en) * | 2002-03-29 | 2003-10-15 | Sanki Eng Co Ltd | Vertical pipe connection method for multistory building |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR970006525B1 (en) * | 1994-12-26 | 1997-04-29 | 이훈주 | Lifter |
JP3658118B2 (en) * | 1996-11-27 | 2005-06-08 | 高砂熱学工業株式会社 | Temporary fixing device for dredging construction and construction method for dredging |
KR20150058911A (en) * | 2013-11-21 | 2015-05-29 | 박정윤 | Transportation device of pipe |
-
2015
- 2015-06-23 KR KR1020150089310A patent/KR101722574B1/en active IP Right Grant
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003294170A (en) * | 2002-03-29 | 2003-10-15 | Sanki Eng Co Ltd | Vertical pipe connection method for multistory building |
Also Published As
Publication number | Publication date |
---|---|
KR20170000277A (en) | 2017-01-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101899515B1 (en) | Module rack mounting structure of semiconductor fab utility | |
JP4858822B2 (en) | Building steel construction method | |
KR101922324B1 (en) | Ceiling lift up construction method | |
KR20090012570A (en) | Multi-horizontal structure member forming method | |
JP2011153421A (en) | Module structure, plant, and method for constructing the plant using the module structure | |
KR102063433B1 (en) | vertical refloat method of the integrated module for plumbing fixture | |
JP2011038381A (en) | Reconstruction method for existing building | |
KR101722574B1 (en) | Riser pipe installation apparatus and construction method thereof | |
JP2016089601A (en) | Apparatus for installing suspended scaffold and curing net used in painting work of communications steel tower | |
KR20170038368A (en) | Rolling method of girder using the rolling apparatus | |
JP5940404B2 (en) | Construction method of beam members | |
KR102080275B1 (en) | Methods and systems of installing mechanical and electrical modular assembly units in buildings | |
JP2019055875A (en) | Lifting workbench and construction method using the same | |
JP6059176B2 (en) | Mobile lifting scaffold for assembling temporary elevated jetty | |
JP6391134B2 (en) | Dismantling method and dismantling system | |
KR102242485B1 (en) | Method for vertical transportation of a heavy module using of a module lifting system inculding of a strand jack | |
JP3073155B2 (en) | How to set product groups for construction buildings | |
JP6061339B2 (en) | Structure reconstruction method and structure reconstruction system | |
JP5948828B2 (en) | Lifting device used for assembling cargo lift for building demolition work, cargo lift for building demolition work, and assembling method thereof | |
KR20090129574A (en) | Climbing scaffolding and method thereof | |
WO2012132161A1 (en) | Module structure, and module construction method | |
CN114934657B (en) | Integral lifting construction method for main stage suspension structure of theater | |
KR102052680B1 (en) | Construction method of standing module for building | |
JP4191584B2 (en) | Multilayer building structure construction apparatus and construction method | |
KR102125809B1 (en) | Construction Method of Pipe Rack Structure Using Segmente Module |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
N231 | Notification of change of applicant | ||
E902 | Notification of reason for refusal | ||
AMND | Amendment | ||
N231 | Notification of change of applicant | ||
E601 | Decision to refuse application | ||
AMND | Amendment | ||
X701 | Decision to grant (after re-examination) | ||
GRNT | Written decision to grant |