KR101501453B1 - anchor and drainage system and it's construction method for tunnel - Google Patents

anchor and drainage system and it's construction method for tunnel Download PDF

Info

Publication number
KR101501453B1
KR101501453B1 KR20140032986A KR20140032986A KR101501453B1 KR 101501453 B1 KR101501453 B1 KR 101501453B1 KR 20140032986 A KR20140032986 A KR 20140032986A KR 20140032986 A KR20140032986 A KR 20140032986A KR 101501453 B1 KR101501453 B1 KR 101501453B1
Authority
KR
South Korea
Prior art keywords
pipe
tunnel
segment
wedge
fixedly installed
Prior art date
Application number
KR20140032986A
Other languages
Korean (ko)
Inventor
신종호
김두래
박길춘
Original Assignee
건국대학교 산학협력단
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 건국대학교 산학협력단 filed Critical 건국대학교 산학협력단
Priority to KR20140032986A priority Critical patent/KR101501453B1/en
Application granted granted Critical
Publication of KR101501453B1 publication Critical patent/KR101501453B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • E21D21/0026Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection characterised by constructional features of the bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • E21D21/0093Accessories
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Soil Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The present invention provides an anchor and drainage system for a tunnel and a construction method thereof capable of reducing a pressure load applied to tunnel lining and performing a function of a girder at the same time by guiding and draining ground water flowing near the tunnel lining. To achieve the purpose above, the anchor and drainage system for a tunnel according to the present invention comprises: an anchorage having a constant diameter and length and consisting of a perforated drainpipe where a hole is formed on the side surface thereof; a drainage unit consisting of a hollow filter inserted into a predetermined position in the perforated drainpipe; an expanded pressurizing segment fixated and installed on an inner circumferential surface by surrounding a wedge; a drainage connection cap screwed to an outer circumferential surface of a front end portion of the perforated drainpipe; a bearing plate fixated and installed in the perforated drainpipe including the drainage connection cap; and a tunnel fixing unit arranged outside the bearing plate, consisting of a nut fastened to a front end portion of the wedge.

Description

터널용 앵커 겸용 배수시스템 및 이의 시공방법{anchor and drainage system and it's construction method for tunnel}BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an anchor and drainage system for a tunnel,

본 발명은 터널용 앵커 겸용 배수시스템 및 이의 시공방법에 관한 것으로, 특히 유공배수관과 앵커기능을 동시에 만족하는 섬유강화플라스틱으로 이루어진 터널용 앵커 겸용 배수시스템 및 이의 시공방법에 관한 것이다. The present invention relates to a drainage system for a tunnel and an installation method thereof, and more particularly, to a drainage system for a tunnel anchor and a method of constructing the drainage system, which is made of a fiber reinforced plastic that simultaneously satisfies both the hole drainage pipe and the anchor function.

일반적으로 터널에 작용하는 하중은 상재한 지반에 의한 하중과, 주변 지하수에 의한 수압이다.  Generally, the load acting on the tunnel is the load due to the ground and the water pressure due to the surrounding groundwater.

이러한 하중들은 보통의 지반상태에서는 배수 터널의 형식으로 수압을 저감시키고, 터널 라이닝과 지반보강재를 통해 하중을 구조적으로 분담한다. These loads reduce the hydraulic pressure in the form of a drainage tunnel in the normal ground condition, and share the load structurally through the tunnel lining and the ground reinforcement.

하지만, 파쇄대와 같이 국부적으로 터널 라이닝에 높은 수압을 가중시키는 지반에서는 터널 라이닝이 구조적으로 취약하기 때문에 추가적인 조치가 필요하다.However, additional grounding is required for localized tunnel lining, such as fracture, because the tunnel lining is structurally weak.

여기서, 상기한 터널 수압을 저감시키기 위한 방법으로는 배수공(Weep hole)을 설치하여 지하수의 유도배수를 통하여 라이닝에 가해지는 수압하중을 해소시키는 것이 있다. Here, as a method for reducing the hydraulic pressure of the tunnel, there is a method of providing a weep hole to relieve the hydrostatic load applied to the lining through the induction drainage of the groundwater.

또한, 가해지는 하중을 버티기 위한 터널의 일반적인 지보재로는 앵커볼트(록볼트), 숏크리트와 강지보재 등이 있다. In addition, anchor bolts (rock bolts), shotcrete and steel supports are general supports for tunnels to resist the applied load.

이러한 지보재들은 지보압을 통해 내공변위를 억제함으로써 터널의 안정성을 유지시킨다.These supports maintain the stability of the tunnel by suppressing the internal displacement through the support pressure.

상기한 바와 같이 배수공과 앵커는 통상 독립적인 구조물로 각각 설치되며, 만일 배수공과 앵커가 하나의 구조물로 설계되어 설치되더라도 그 구조는 매우 복잡한 실정이다. As described above, the drainage hole and the anchor are usually installed as independent structures, respectively. Even if the drainage hole and the anchor are designed as a single structure, the structure is very complicated.

또한, 일반적인 앵커의 경우는 PC강재로 설치되기 때문에 지하수 및 해수의 영향으로 인하여 PC강재의 부식이 발생되므로 이에 대비하기 위해 추가적인 방청 처리가 필요하다.In addition, since general anchors are installed with PC steel, corrosion of PC steels occurs due to the influence of ground water and seawater.

여기서, 종래에서는 배수공과 지보재의 직접적인 결합을 시도한 예는 찾아볼 수 없다.Here, in the past, no attempt has been made to attempt direct coupling between a drain hole and a support material.

즉, 터널의 지반보강을 위해서는 앵커를 설치하고, 배수를 위해서는 배수공을 별도로 설치하는 것이 대부분이었다. In other words, anchor was installed to reinforce the ground of the tunnel, and drainage was installed separately for drainage.

아울러, 재료적인 측면에서도 종래의 앵커에서 사용되는 인장재로는 PC강재(PC steel strand, PC steel bar, PC 강 복합 strand 등)가 주로 쓰인다.In addition, as a tensile material used in conventional anchors, PC steels (PC steel strand, PC steel bar, PC steel composite strand, etc.) are mainly used in terms of materials.

이러한 종래의 PC강재와 같은 소재는 부식되기 쉬운 터널 지반 환경으로 인해 영구식 앵커의 적용에 있어 무리가 있어서, 앵커 부식을 방지하기 위한 내부식성 처리 방법 및 절차가 복잡하다.Such a conventional PC steel material is complicated in the corrosion resistant treatment method and procedure for preventing anchor corrosion because of the difficulty in applying the permanent anchor due to the ground environment of the tunnel where corrosion is likely to occur.

또한, 일반적인 배수관의 경우에는 PVC, PE 재질로 구성되기 때문에, 강도적인 측면에서 취약한 점을 확인할 수 있다.In addition, since general drain pipes are made of PVC and PE materials, they are weak in terms of strength.

등록실용신안공보 20-0352267(2004.05.25.)Registration Utility Model Bulletin 20-0352267 (May 25, 2004) 등록특허공보 10-0638548(2006.10.19.)Patent Document 1: Japanese Patent Application Laid-Open No. 10-0638548 (Oct. 19, 2006) 등록특허공보 10-0823980(2008.04.15.)Patent Registration No. 10-0823980 (Apr. 15, 2008)

이에, 본 발명은 상기한 바와 같은 제문제점을 해결하기 위해 안출된 것으로, 터널 라이닝 주변에 흐르는 지하수를 유도배수시킴으로써, 터널 라이닝에 작용하는 수압 하중을 감소시킴과 동시에 지보재로서의 기능도 함께 수행하도록 한 터널용 앵커 겸용 배수시스템 및 이의 시공방법을 제공하는데 그 목적이 있다.SUMMARY OF THE INVENTION Accordingly, the present invention has been made in order to solve the above-mentioned problems, and it is an object of the present invention to provide a tunnel lining structure, in which groundwater flowing around a tunnel lining is guided and drained to reduce a hydraulic pressure load acting on the tunnel lining, And an object of the present invention is to provide a drainage system for anchor for a tunnel and a construction method thereof.

상기한 목적을 달성하기 위한 본 발명에 따른 터널용 앵커 겸용 배수시스템은 일정한 직경 및 길이를 가지며, 측면에 구멍이 형성된 유공관으로 구성되는 정착부와; 상기 유공관의 소정의 위치에 삽입되는 중공필터로 구성되는 배수부와; 상기 유공관의 선단부 내주면에 웨지를 감싼 상태로 고정 설치되는 확장형 가압세그먼트와; 상기 유공관 선단부 외주면에 나사 결합되는 배수연결캡과; 상기 배수연결캡을 포함한 유공관에 고정 설치되는 지압판과; 상기 지압판의 외측에 배치됨과 동시에 웨지의 선단부에 체결되는 너트로 구성되는 터널고정부로 구성됨을 특징으로 한다.According to an aspect of the present invention, there is provided an anchor and drainage system for a tunnel, comprising: a fusing unit having a predetermined diameter and a length, A drain portion formed of a hollow filter inserted at a predetermined position of the oil pipe; An expandable pressing segment fixedly installed on an inner circumferential surface of a distal end of the porous tube in a state of wrapping a wedge; A drain connection cap screwed to an outer circumferential surface of the distal end of the tube; A piercing plate fixedly installed on a pipe including the drain connection cap; And a nut secured to the tip of the wedge and disposed on the outer side of the platen.

상기 유공관은 섬유강화플라스틱으로 구성된다.The foraminous pipe is made of fiber-reinforced plastic.

상기 유공관의 소정의 위치에 패커가 고정설치된다.And a packer is fixedly installed at a predetermined position of the pipe.

상기 확장형 가압세그먼트는 전체적으로 3-4개의 금속편이 조립되어 가압세그먼트가 형성되고, 상기 가압세그먼트의 내주면에는 일측단에서 타측단에 걸쳐 내경이 좁아지도록 테이퍼가 형성되고, 상기 가압세그먼트의 외주면에는 일정한 깊이를 갖는 요홈이 형성되고, 상기 요홈에 고무링이 끼워진다.Wherein a taper is formed in the inner peripheral surface of the pressing segment so as to narrow the inner diameter from the one end to the other end, and the outer peripheral surface of the pressing segment has a constant depth And a rubber ring is fitted in the groove.

상기 웨지는 절두원추형상으로 이루어지는 절두원추부와, 상기 절두원추부의 타단으로부터 일직선상으로 동일 직경으로 연장 형성됨과 동시에 단부에 나사산이 형성된 고정봉으로 구성된다.The wedge includes a stepped two-stepped portion formed of a truncated conical shape, and a fixed rod extending in the same diameter straight line from the other end of the stepped two-stepped portion and having threads at the end thereof.

상기 배수연결캡에 배수관이 나사결합된다.A drain pipe is screwed into the drain connection cap.

상기 지압판과 유공관 단부 사이에 변형방지용 원형캡이 고정 설치된다.And a circular cap for preventing deformation is fixedly installed between the end plate and the end of the pipe.

상기 변형방지용 원형캡과 유공관 단부 사이에 수팽창 고무지수재가 고정 설치된다.And an expansion rubber index material is fixedly installed between the deformation preventing circular cap and the end of the pipe.

또한, 상기한 목적을 달성하기 위한 본 발명에 따른 터널용 앵커 겸용 배수시스템 시공방법은 터널용 앵커 겸용 배수시스템을 시공하는 방법으로서, 터널 내부에 콘크리트를 타설 및 양생시켜 1차 라이닝을 시공하는 단계(S Ⅰ); 상기 1차 라이닝의 소정의 위치를 일정한 직경 및 깊이로 천공하여 천공홀을 형성하는 단계(S Ⅱ); 상기 천공홀에 일정한 직경 및 길이를 갖는 유공관을 삽입하는 단계(S Ⅲ); 상기 유공관 내에 일정한 직경 및 길이를 갖는 그라우팅튜브를 삽입하고, 상기 그라우팅튜브를 통해 그라우트재를 주입하여 천공홀의 일정부분을 그라우팅하는 단계(S Ⅳ); 상기 1차 라이닝에 방수막을 설치하고, 상기 유공관의 하단에 콘크리트 유입방지용 씰을 설치하는 단계(S Ⅴ); 상기 방수막에 콘크리트를 타설 및 양생시켜 2차 라이닝을 시공하는 단계(S Ⅵ); 상기 콘크리트 유입방지용 씰을 제거하고, 상기 유공관의 선단부에 배수연결캡을 설치하는 단계(S Ⅶ); 상기 유공관 선단부 내주면에 웨지를 감싼 상태로 확장형 가압세그먼트를 삽입 설치하는 단계(S Ⅷ); 상기 확장형 가압세그먼트를 포함한 유공관에 수팽창 고무지수재를 설치하고, 상기 수팽창 고무지수재에 변형방지용 원형캡을 설치하는 단계(S Ⅸ); 상기 변형방지용 원형캡의 외측에 지압판을 설치하고, 고정나사로 터널 2차 라이닝에 고정하는 단계(S Ⅹ); 상기 확장형 가압세그먼트의 웨지에 너트를 삽입함과 동시에 회전시켜 확장형 가압세그먼트를 유공관에 인장력을 가하는 단계(S ⅩⅠ)로 이루어짐을 특징으로 한다.In order to accomplish the above object, there is also provided a method of constructing a drainage system for an anchor for a tunnel according to the present invention, comprising the steps of placing a concrete in a tunnel and curing the same to construct a primary lining (S I); Drilling a predetermined position of the primary lining to a predetermined diameter and depth to form a perforation hole (SII); Inserting a perforation hole having a predetermined diameter and length into the perforation hole (SIII); Inserting a grouting tube having a predetermined diameter and a predetermined length into the pipe tube, grouting a certain portion of the perforation hole by injecting grout material through the grouting tube (SIV); Providing a waterproof membrane on the primary lining and installing a seal for preventing concrete inflow at the bottom of the pipe (S V); Placing (S VI) a secondary lining by placing and curing concrete on the waterproof membrane; Removing the concrete inflow preventing seal and installing a drain connection cap at a front end of the pipe (S VII); (S VIII) of inserting the expandable pressing segment in a state of wrapping the wedge on the inner circumferential surface of the end portion of the pipe; Providing a water expansion rubber exponent material in a pipe including the expandable pressure segment, and installing a circular cap for preventing deformation of the water expansion rubber exponent (SIX); (SX) of installing a pressure plate on the outside of the deformation preventing circular cap and securing it to the tunnel secondary lining with a fixing screw; And a step (SXI) of inserting a nut into the wedge of the expandable pressurizing segment and simultaneously rotating the nut to apply a tensile force to the expandable pressurizing segment to the pipe.

상기 터널용 앵커 겸용 배수시스템은 일정한 직경 및 길이를 가지며, 측면에 구멍이 형성된 유공관으로 구성되는 정착부와; 상기 유공관의 소정의 위치에 삽입되는 중공필터로 구성되는 배수부와; 상기 유공관의 선단부 내주면에 웨지를 감싼 상태로 고정 설치되는 확장형 가압세그먼트와; 상기 유공관 선단부 외주면에 나사 결합되는 배수연결캡과; 상기 배수연결캡을 포함한 유공관에 고정 설치되는 지압판과; 상기 지압판의 외측에 배치됨과 동시에 웨지의 선단부에 체결되는 너트로 구성되는 터널고정부로 구성된다.The anchor and drainage system for a tunnel includes: a fusing unit having a predetermined diameter and a length, the fusing unit having a hole formed in a side surface thereof; A drain portion formed of a hollow filter inserted at a predetermined position of the oil pipe; An expandable pressing segment fixedly installed on an inner circumferential surface of a distal end of the porous tube in a state of wrapping a wedge; A drain connection cap screwed to an outer circumferential surface of the distal end of the tube; A piercing plate fixedly installed on a pipe including the drain connection cap; And a nut secured to the tip of the wedge and disposed on the outside of the platen.

상기 유공관은 섬유강화플라스틱으로 구성된다.The foraminous pipe is made of fiber-reinforced plastic.

상기 유공관의 소정의 위치에 패커가 고정설치된다.And a packer is fixedly installed at a predetermined position of the pipe.

상기 확장형 가압세그먼트는 전체적으로 3-4개의 금속편이 조립되어 가압세그먼트가 형성되고, 상기 가압세그먼트의 내주면에는 일측단에서 타측단에 걸쳐 내경이 좁아지도록 테이퍼가 형성되고, 상기 가압세그먼트의 외주면에는 일정한 깊이를 갖는 요홈이 형성되고, 상기 요홈에 고무링이 끼워진다.Wherein a taper is formed in the inner peripheral surface of the pressing segment so as to narrow the inner diameter from the one end to the other end, and the outer peripheral surface of the pressing segment has a constant depth And a rubber ring is fitted in the groove.

상기 웨지는 절두원추형상으로 이루어지는 절두원추부와 상기 절두원추부의 타단으로부터 일직선상으로 동일 직경으로 연장 형성됨과 동시에 단부에 나사산이 형성된 고정봉으로 구성된다.The wedge includes a stepped two-stepped portion formed of a frusto-conical shape and a fixed rod extending in the same diameter straightly from the other end of the stepped two-stepped portion and having threads at the end thereof.

상기 배수연결캡에 배수관이 나사결합된다.A drain pipe is screwed into the drain connection cap.

상기 지압판과 유공관 단부 사이에 변형방지용 원형캡이 고정 설치된다.And a circular cap for preventing deformation is fixedly installed between the end plate and the end of the pipe.

상기 변형방지용 원형캡과 유공관 단부 사이에 수팽창 고무지수재가 고정 설치된다.And an expansion rubber index material is fixedly installed between the deformation preventing circular cap and the end of the pipe.

이상에서 설명한 바와 같이, 본 발명에 따른 터널용 앵커 겸용 배수시스템 및 이의 시공방법은 다음과 같은 효과가 있다.INDUSTRIAL APPLICABILITY As described above, the drainage system for the tunnel anchor and the construction method thereof according to the present invention have the following effects.

첫째, 본 발명은 터널 라이닝 주변에 흐르는 지하수를 유공관을 통해 유도배수시킴으로써, 터널 라이닝에 작용하는 수압 하중을 감소시킴과 동시에 지보재로서의 기능도 함께하는 효과가 있다.First, according to the present invention, groundwater flowing in the vicinity of a tunnel lining is guided and drained through a pipe, thereby reducing hydraulic load acting on the tunnel lining and also functioning as a support.

둘째, 본 발명은 유공관을 섬유강화플라스틱 재질로 구성됨으로써, 내부식성을 가져 시공절차와 장기적인 관리차원에서 시간적, 경제적인 이점이 있다.Second, since the pipe is made of a fiber-reinforced plastic material, it has corrosion resistance and is advantageous in terms of time and economy in terms of construction procedures and long-term management.

셋째, 본 발명은 앵커 겸용 배수관인 유공관을 터널에 고정시킴으로써 터널의 내공변위를 줄이기 위해 지보재에 작용하는 인장력을 터널 라이닝에 전달하며, 터널 내부의 배수관과의 연결을 통해 외부의 유입수를 처리함으로써, 터널의 사용성에 영향을 주지 않는 이점이 있다. Third, the present invention relates to an anchor pipe which is anchored to a tunnel by fixing a toe pipe, which is a drain pipe serving as an anchor, to the tunnel lining in order to reduce the internal displacement of the tunnel, and the external influent water is treated through connection with a drain pipe in the tunnel, There is an advantage that the usability of the tunnel is not affected.

도 1은 본 발명에 따른 터널용 앵커 겸용 배수시스템의 기본개념을 도시한 개념도,
도 2는 본 발명에 따른 터널용 앵커 겸용 배수시스템을 도시한 개략도,
도 3은 본 발명에 따른 터널용 앵커 겸용 배수시스템을 도시한 단면도,
도 4는 본 발명에 따른 터널용 앵커 겸용 배수시스템의 정착부를 도시한 사시도,
도 5는 도 4의 A-A선 단면도,
도 6은 본 발명에 따른 터널용 앵커 겸용 배수시스템의 배수부를 도시한 사시도,
도 7은 도 6의 B-B선 단면도,
도 8은 본 발명에 따른 터널용 앵커 겸용 배수시스템의 터널 고정부를 도시한 단면도,
도 9는 도 8의 C-C선 단면도,
도 10은 도 8의 D-D선 단면도,
도 11은 본 발명에 따른 터널용 앵커 겸용 배수시스템의 터널 고정부의 확장형 가압세그먼트를 도시한 예시도,
도 12a 내지 도 12h은 본 발명에 따른 터널용 앵커 겸용 배수시스템을 시공하는 과정을 도시한 공정도,
도 13a 내지 도 13e는 본 발명에 따른 터널용 앵커 겸용 배수시스템의 시공 중 터널 고정부 시공과정을 도시한 공정도.
1 is a conceptual diagram showing a basic concept of a drainage system for anchor for a tunnel according to the present invention,
FIG. 2 is a schematic view showing a drainage system serving as an anchor for a tunnel according to the present invention,
3 is a cross-sectional view showing a drainage system serving as an anchor for a tunnel according to the present invention,
4 is a perspective view illustrating a fixing unit of a drainage system for anchor for a tunnel according to the present invention,
5 is a sectional view taken along the line AA in Fig. 4,
FIG. 6 is a perspective view showing a drainage section of a drainage system for anchor for a tunnel according to the present invention,
Fig. 7 is a sectional view taken along line BB of Fig. 6,
8 is a sectional view showing a tunnel fixing portion of a drainage system for anchor for a tunnel according to the present invention,
Fig. 9 is a cross-sectional view taken along line CC of Fig. 8,
10 is a cross-sectional view taken along line DD of Fig. 8,
11 is an exemplary view showing an expandable press segment of a tunnel fixing portion of a drainage system for anchor for a tunnel according to the present invention,
12A to 12H are process drawings showing a process of constructing a drainage system for anchor for a tunnel according to the present invention,
FIGS. 13A to 13E are process drawings showing a tunnel installation process during installation of a drainage system for anchor for a tunnel according to the present invention. FIG.

이하, 본 발명을 첨부한 예시도면을 참조하여 상세히 설명한다.Hereinafter, the present invention will be described in detail with reference to the accompanying drawings.

도 1은 본 발명에 따른 터널용 앵커 겸용 배수시스템의 기본개념을 도시한 개념도이고, 도 2는 본 발명에 따른 터널용 앵커 겸용 배수시스템을 도시한 개략도이며, 도 3은 본 발명에 따른 터널용 앵커 겸용 배수시스템을 도시한 단면도이다.FIG. 1 is a conceptual diagram showing a basic concept of a drainage system for anchor for a tunnel according to the present invention, FIG. 2 is a schematic view showing a drainage system for anchor for a tunnel according to the present invention, Sectional view showing a combined anchor drainage system.

이들 도면에 도시된 바와 같이, 본 발명에 따른 터널용 앵커 겸용 배수시스템(S)은 일정한 직경 및 길이를 가지며, 측면에 구멍(112)이 형성된 유공관(110)으로 구성되는 정착부(100)와; 상기 유공관(110)의 소정의 위치에 삽입되는 중공필터(210)로 구성되는 배수부(200)와; 상기 유공관(110)의 선단부 내주면에 웨지(310)를 감싼 상태로 고정 설치되는 확장형 가압세그먼트(320)와; 상기 유공관(110) 선단부 외주면에 나사 결합되는 배수연결캡(340)과; 상기 배수연결캡(340)을 포함한 유공관(110)에 고정 설치되는 지압판(350)과; 상기 지압판(350)의 외측에 배치됨과 동시에 웨지(310)의 선단부에 체결되는 너트(370)로 구성되는 터널고정부(300)로 구성된다.As shown in these figures, the drainage system S for a tunnel anchor according to the present invention includes a fusing unit 100 having a constant diameter and a length and having a hole 112 formed in a side surface thereof, ; A drain 200 formed of a hollow filter 210 inserted at a predetermined position of the hole 110; An expandable pressing segment 320 fixedly installed on the inner circumferential surface of the distal end of the porous tube 110 while surrounding the wedge 310; A drain connection cap 340 screwed to an outer circumferential surface of the distal end of the porous tube 110; A platen 350 fixedly installed on the pipe 110 including the drain connection cap 340; And a nut 370 disposed on the outer side of the platen 350 and fastened to the distal end of the wedge 310.

즉, 본 발명에 따른 터널용 앵커 겸용 배수시스템(S)은 도 1 내지 도 3에 도시된 바와 같이, 유공관(110)으로 배수기능과 앵커기능을 동시에 만족하는 구조물로, 그라우팅을 통해 지반과 지보재 구조물을 일체화시키는 정착부(100)와, 상기 정착부(100)의 하단에 위치되며, 인장력을 전달하고, 집중 누수구간에서 유도배수 기능을 하는 배수부(200)와, 상기 배수부(200)의 하단에 위치되며, 일반적인 앵커구조와 유사하며 터널 내부에 고정되어 내압을 터널 라이닝(L)에 작용하는 터널고정부(300)가 유기적으로 결합되어 이루어진 것이다.That is, as shown in FIGS. 1 to 3, the drainage system S for a tunnel anchor according to the present invention is a structure that simultaneously satisfies a drainage function and an anchor function with a pipe structure 110, A drainage unit 200 disposed at a lower end of the fixing unit 100 and delivering a tensile force and performing an induction drainage function in a concentrated leak section, Which is similar to a general anchor structure and is fixed to the inside of the tunnel and is connected to the tunnel fixing part 300 which is operated in the tunnel lining L with the internal pressure.

여기서, 상기 정착부(100)는 도 4 및 도 5에 도시된 바와 같이, 일정한 직경 및 길이를 가지며, 측면에 구멍(112)이 형성된 섬유강화플라스틱 유공관(110)으로 구성되고, 상기 유공관(110)의 소정의 위치에 패커(160)가 고정설치된 구조이다.4 and 5, the fusing unit 100 includes a fiber-reinforced plastic pipe 110 having a predetermined diameter and length and having a hole 112 formed in a side thereof. The fusing pipe 110 And the packer 160 is fixed at a predetermined position of the packer 160.

또한, 상기 유공관(110)의 정착은 기존의 패커식 가압그라우팅을 사용하는 대신에 유공관(110)의 구멍(112)을 통해 그라우트재(130)가 유공관(110)의 외부로 분출되어 유공관(100)을 지반에 정착시킨다.The grout material 130 may be discharged to the outside of the pipe 110 through the hole 112 of the pipe 110 so that the pipe 100 may be fixed to the pipe 100. [ ) On the ground.

상기 정착부(100)의 길이와 유공관(110)의 구멍(112) 개수는 요구되는 정착강도에 맞춰서 조정할 수 있다.The length of the fusing unit 100 and the number of holes 112 of the tube 110 can be adjusted according to the required fixing strength.

또한, 상기 배수부(200)는 도 6 및 도 7에 도시된 바와 같이, 유공관(110)의 소정의 위치에 삽입되는 중공필터(210)로 구성된다.6 and 7, the drainage unit 200 includes a hollow filter 210 to be inserted into a predetermined position of the oil filter pipe 110. As shown in FIG.

즉, 상기 배수부(200)는 터널(T) 지반의 배수 및 인장력을 전달하는 부분으로서, 섬유강화플라스틱으로 제조된 유공관(110)으로 설계하여 배수기능을 수행하는 중심부분이다.That is, the drainage unit 200 is a center portion for draining drainage and tensile force of the tunnel T, designed as a pipe 110 made of fiber-reinforced plastic and performing a drainage function.

여기서, 상기 유공관(110)의 구멍(112)은 일정한 간격마다 위치하여 주변 지반에 흐르는 지하수를 유입시키는 기능을 하며, 상기 유공관(110) 내부에 삽입된 중공필터(210)는 외부 토사의 유입을 막아서 유공관(110)의 구멍(112)이 막히는 것을 방지하여 원할한 지하수 유입을 가능하게 한다.The holes 112 of the holes 110 are positioned at predetermined intervals to introduce groundwater flowing in the surrounding ground. The hollow filter 210 inserted into the holes 110 can be used to introduce external soil Thereby preventing the hole 112 of the pipe 110 from being clogged to enable the groundwater to flow smoothly.

특히, 상기 배수부(200)의 길이 및 유공관(110)의 구멍(112)의 개수는 파쇄대(집중누수구간)의 위치와 저감이 요구되는 수압의 크기에 맞춰서 조절할 수 있음을 밝혀둔다.Particularly, it is found that the length of the drainage part 200 and the number of the holes 112 of the pipe tube 110 can be adjusted according to the position of the fracture zone (concentrated leaking section) and the magnitude of the water pressure required to be reduced.

그리고, 상기 터널고정부(300)는 도 8 내지 도 10에 도시된 바와 같이, 유공관(110)의 선단부 내주면에 웨지(310)를 감싼 상태로 고정 설치되는 확장형 가압세그먼트(320)와; 상기 유공관(110)의 선단부 외주면에 나사 결합되는 배수연결캡(340)과; 상기 배수연결캡(340)을 포함한 유공관(110)에 고정 설치되는 지압판(350)과; 상기 지압판(350)의 외측에 배치됨과 동시에 웨지(310)의 선단부에 체결되는 너트(370)로 구성된다.As shown in FIGS. 8 to 10, the tunnel fixing part 300 includes an expandable pressing segment 320 fixedly installed on the inner circumferential surface of the end portion of the pipe 110, while the wedge 310 is being worn. A drain connection cap 340 screwed to the outer circumferential surface of the distal end of the porous tube 110; A platen 350 fixedly installed on the pipe 110 including the drain connection cap 340; And a nut 370 disposed on the outer side of the pressure plate 350 and fastened to the distal end of the wedge 310.

즉, 상기 터널고정부(300)는 유공관(110)을 터널(T) 라이닝(L)에 고정하기 위한 장치로, 터널(T)의 내공변위를 줄이기 위해 지보재에 작용하는 인장력을 터널(T)의 라이닝(L)에 전달하며, 터널(T) 내부의 유공관(110)과의 연결을 통해 외부로 유입수를 처리함으로써 터널(T)의 사용성에 영향을 주지 않는다.That is, the tunnel fixing unit 300 is a device for fixing the tubular pipe 110 to the tunnel lining L. In order to reduce the internal displacement of the tunnel T, a tensile force acting on the support is called a tunnel T, And does not affect the usability of the tunnel T by treating the inflow water through the connection with the pipe 110 inside the tunnel T. [

여기서, 상기 터널고정부(300)는 웨지(310), 확장형 가압세그먼트(320), 배수연결캡(340), 지압판(350) 및 너트(370)로 구성된다.The tunnel fixing portion 300 includes a wedge 310, an expandable pressing segment 320, a drain connection cap 340, a support plate 350, and a nut 370.

여기서, 상기 웨지(310)는 도 11에 도시된 바와 같이, 절두원추형상으로 이루어지는 절두원추부(312)와 상기 절두원추부(312)의 타단으로부터 일직선상으로 동일 직경으로 연장 형성됨과 동시에 단부에 나사산(314)이 형성된 고정봉(316)으로 구성된다.11, the wedge 310 is formed to extend in a straight line from the other end of the two-step circular weights 312, which are formed in a frusto-conical shape, with the same diameter, and at the same time, And a fixing rod 316 having a thread 314 formed therein.

즉, 상기 웨지(310)는 절두원추부(312)와 나사형 고정봉(316)으로 구성되어, 터널(T) 내측에서 와셔(390)를 이용하여 나사산(314)을 당겨주면 유공관(110) 내측의 절두원추부(312)가 확장형 가압세그먼트(320)에 인장력과 그립력을 가하는 장치이다.That is, the wedge 310 is composed of a two-round weave portion 312 and a threaded fixing rod 316. When the threaded portion 314 is pulled by using the washer 390 inside the tunnel T, And the inner half step portion 312 applies a tensile force and a gripping force to the expandable pressing segment 320.

또한, 상기 확장형 가압세그먼트(320)는 도 11에 도시된 바와 같이, 전체적으로 3-4개의 금속편(322)이 조립되어 가압세그먼트(324)가 형성되고, 상기 가압세그먼트(324)의 내주면에는 일측단에서 타측단에 걸쳐 내경이 좁아지도록 테이퍼(326)가 형성되고, 상기 가압세그먼트(324)의 외주면에는 일정한 깊이를 갖는 요홈(328)이 형성되고, 상기 요홈(328)에 고무링(330)이 끼워진 구조이다.11, three or four metal pieces 322 are assembled as a whole to form a pressing segment 324, and the inner peripheral surface of the pressing segment 324 is provided with one side end A groove 328 having a predetermined depth is formed on the outer peripheral surface of the pressing segment 324 and a rubber ring 330 is attached to the groove 328 It is an embedded structure.

여기서, 상기한 확장형 가압세그먼트(320)는 그 내부의 웨지(310)의 이동에 의해 확장되어 유공관(110) 내부에서 유공관(110)을 고정지지하며 유공관(110)에 인장력을 전단 및 유지시키는 장치이다.The expandable pressurizing segment 320 is extended by the movement of the wedge 310 therein to fix and support the pipe 110 in the pipe 110 and to apply a tensile force to the pipe 110. [ to be.

그리고, 상기 배수연결캡(340)은 터널(T) 외측에서 들어온 유입수를 처리하기 위해 터널(T) 내부의 배수관(380)과 연결되는 장치이다.The drain connection cap 340 is connected to the drain pipe 380 inside the tunnel T to process inflow water from outside the tunnel T. [

또한, 상기 지압판(350)은 본 발명에 따른 터널용 앵커 겸용 배수시스템의 긴장력을 터널 라이닝에 전달하여 내공변위를 방지한다.In addition, the above-mentioned pressure plate 350 transmits the tension force of the drainage system for anchor for a tunnel according to the present invention to the tunnel lining to prevent the internal displacement.

그리고, 상기 지압판(350)에는 고정나사(360)가 결합되어 상기 고정나사(360)에 의해 지압판(350)을 터널(T)의 라이닝(L)에 부착시킨다.A fixing screw 360 is coupled to the pressure plate 350 and the pressure plate 350 is attached to the lining L of the tunnel T by the fixing screw 360.

또한, 상기 너트(370)는 웨지(310)의 나사(314)에 결합되어 상기 너트(370)의 회전에 의해 웨지(310)를 인장하여 상기 웨지(310)를 감싸는 확장형 가압세그먼트(320)를 유공관(110) 내측으로 밀착시키며, 유공관(110)을 인장시키는 기능을 한다.The nut 370 is coupled to a screw 314 of the wedge 310 to tension the wedge 310 by rotation of the nut 370 to provide an expandable pressurizing segment 320 that wraps the wedge 310 Tightly in contact with the inside of the tube 110 and tension the tube 110.

한편, 상기 지압판(350)과 유공관(110) 단부 사이에 변형방지용 원형캡(400)이 고정 설치된다.Meanwhile, a deformation preventing circular cap 400 is fixedly installed between the end plate of the pipe plate 350 and the end of the pipe 110.

즉, 상기 변형방지용 원형캡(400)은 확장형 가압세그먼트(320)에 의해 가해지는 압력으로 인한 유공관(110)의 손상을 방지하는 장치로, 상기 유공관(110)의 단부에 나사 결합된다.In other words, the deformation preventing circular cap 400 is screwed to the end of the pipe tube 110 to prevent damage to the pipe tube 110 due to the pressure applied by the expandable pressure segment 320.

상기 변형방지용 원형캡(400) 및 확장형 가압세그먼트(320)에 의해 유공관(110)의 손상을 방지하며, 인장력을 가할 수 있도록 한다.By preventing the deformation preventing circular cap 400 and the expandable pressing segment 320 from being damaged, the pipe 110 can be prevented from being damaged and a tensile force can be applied.

또한, 상기 변형방지용 원형캡(400)과 유공관(110) 단부 사이에 수팽창 고무지수재(410)가 고정 설치된다.Further, a water expansion rubber exponent material 410 is fixedly installed between the deformation preventing circular cap 400 and the end of the pipe tube 110.

이와 같은 수팽창 고무지수재(410)는 유공관(110) 내부를 흐르는 유체가 지압판(350)의 외측으로 누수되는 것을 방지토록 한다.The water expansive rubber exponent material 410 prevents the fluid flowing inside the pipe 110 from leaking to the outside of the pressure plate 350.

이하, 상기한 바와 같은 구성으로 이루어진 본 발명에 따른 터널용 앵커 겸용 배수시스템의 시공에 대해 설명한다. Hereinafter, the construction of the drainage system for anchor for a tunnel according to the present invention constructed as described above will be described.

도 12a 내지 도 12h은 본 발명에 따른 터널용 앵커 겸용 배수시스템을 시공하는 과정을 도시한 공정도이며, 도 13a 내지 도 13e는 본 발명에 따른 터널용 앵커 겸용 배수시스템의 시공 중 터널 고정부 시공과정을 도시한 공정도이다.12A to 12H are process charts showing a process of constructing an anchor and drainage system for a tunnel according to the present invention. FIGS. 13A to 13E are views showing a tunnel construction process Fig.

이들 도면에 도시된 바와 같이, 본 발명에 따른 터널용 앵커 겸용 배수시스템 시공방법은 일정한 직경 및 길이를 가지며, 측면에 구멍(112)이 형성된 유공관(110)으로 구성되는 정착부(100)와; 상기 유공관(110)의 소정의 위치에 삽입되는 중공필터(210)로 구성되는 배수부(200)와; 상기 유공관(110)의 선단부 내주면에 웨지(310)를 감싼 상태로 고정 설치되는 확장형 가압세그먼트(320)와; 상기 유공관(110) 선단부 외주면에 나사 결합되는 배수연결캡(340)과; 상기 배수연결캡(340)을 포함한 유공관(110)에 고정 설치되는 지압판(350)과; 상기 지압판(350)의 외측에 배치됨과 동시에 웨지(310)의 선단부에 체결되는 너트(370)로 구성되는 터널고정부(300)로 구성된 터널용 앵커 겸용 배수시스템(S)을 시공하는 방법으로, 터널(T) 내부에 콘크리트를 타설 및 양생시켜 1차 라이닝(L1)을 시공하는 단계(S Ⅰ); 상기 1차 라이닝(L1)의 소정의 위치를 일정한 직경 및 깊이로 천공하여 천공홀(H)을 형성하는 단계(S Ⅱ); 상기 천공홀(H)에 일정한 직경 및 길이를 갖는 유공관(110)을 삽입하는 단계(S Ⅲ); 상기 유공관(110) 내에 일정한 직경 및 길이를 갖는 그라우팅튜브(120)를 삽입하고, 상기 그라우팅튜브(120)를 통해 그라우트재(130)를 주입하여 천공홀(H)의 일정부분을 그라우팅하는 단계(S Ⅳ); 상기 1차 라이닝(L1)에 방수막(140)을 설치하고, 상기 유공관(110)의 하단에 콘크리트 유입방지용 씰(150)을 설치하는 단계(S Ⅴ); 상기 방수막(140)에 콘크리트를 타설 및 양생시켜 2차 라이닝(L2)을 시공하는 단계(S Ⅵ); 상기 콘크리트 유입방지용 씰(150)을 제거하고, 상기 유공관(110)의 선단부에 배수연결캡(340)을 설치하는 단계(S Ⅶ); 상기 유공관(110) 선단부 내주면에 웨지(310)를 감싼 상태로 확장형 가압세그먼트(320)를 삽입 설치하는 단계(S Ⅷ); 상기 확장형 가압세그먼트(320)를 포함한 유공관(110)에 수팽창 고무지수재(410)을 설치하고, 상기 수팽창 고무지수재(410)에 변형방지용 원형캡을 설치하는 단계(S Ⅸ); 상기 변형방지용 원형캡(400)의 외측에 지압판(350)을 설치하고, 고정나사(360)로 터널 2차 라이닝(L2)에 고정하는 단계(S Ⅹ); 상기 확장형 가압세그먼트(320)의 웨지(310)에 너트(370)를 삽입함과 동시에 회전시켜 확장형 가압세그먼트(320)를 유공관(110)에 밀착시키는 단계(S ⅩⅠ)로 이루어진다.As shown in these drawings, the method for constructing a drainage system for anchor for a tunnel according to the present invention includes a fusing unit 100 having a constant diameter and a length and having a hole 110 formed in a side surface thereof; A drain 200 formed of a hollow filter 210 inserted at a predetermined position of the hole 110; An expandable pressing segment 320 fixedly installed on the inner circumferential surface of the distal end of the porous tube 110 while surrounding the wedge 310; A drain connection cap 340 screwed to an outer circumferential surface of the distal end of the porous tube 110; A platen 350 fixedly installed on the pipe 110 including the drain connection cap 340; And a tunnel fixing part 300 composed of a nut 370 which is disposed on the outer side of the supporting plate 350 and is fastened to the front end of the wedge 310. In this way, A step (S I) of placing a primary lining (L1) by pouring and curing concrete inside a tunnel (T); Drilling a predetermined position of the primary lining (L1) to a predetermined diameter and depth to form a perforation hole (SII); Inserting a perforation hole (H) having a predetermined diameter and length into the perforation hole (S III); A step of inserting a grouting tube 120 having a predetermined diameter and a predetermined length into the hole 110 and injecting grout material 130 through the grouting tube 120 to grout a predetermined portion of the hole H S IV); Providing a waterproofing membrane (140) on the primary lining (L1) and installing a sealant (150) on the bottom of the pipe (110) to prevent concrete inflow (S V); Placing (S VI) a secondary lining (L2) by placing and curing concrete in the waterproof membrane (140); Removing the concrete inflow preventing seal 150 and installing a drain connection cap 340 at the tip of the pipe 110; (S VIII) of inserting the expandable pressing segment 320 with the wedge 310 wrapped around the inner circumferential surface of the leading end of the pipe 110; The step (SIX) of providing a water expanding rubber exponent material (410) in the pipe (110) including the expandable pressure segment (320) and installing a deformation preventing circular cap on the water expanding rubber exponent material (410); A step SX of installing a pressure plate 350 on the outer side of the deformation preventing circular cap 400 and fixing the pressure plate 350 to the tunnel secondary lining L2 with the fixing screw 360; A nut 370 is inserted into the wedge 310 of the expandable pressurizing segment 320 and is simultaneously rotated to bring the expandable pressurizing segment 320 into close contact with the pipe 110.

즉, 본 발명에 따른 터널용 앵커 겸용 배수시스템 시공방법은 도 12a 내지 도 12h에 도시된 바와 같이, 1차 라이닝(L1) 시공단계(S Ⅰ), 천공홀(H) 형성단계(S Ⅱ), 유공관(110) 삽입단계(S Ⅲ), 그라우팅 단계(S Ⅳ), 콘크리트 유입방지용 씰(150) 설치단계(S Ⅴ), 2차 라이닝(L2) 시공단계(S Ⅵ), 배수연결캡(340) 설치단계(S Ⅶ), 확장형 가압세그먼트(320) 삽입 설치단계(S Ⅷ), 변형방지용 원형캡(400) 설치단계(S Ⅸ), 지압판(350) 고정단계(S Ⅹ); 유공관(110) 밀착단계(S ⅩⅠ)를 순차적으로 시행하여 터널용 앵커 겸용 배수시스템(S)을 터널(T) 내에 시공함을 특징으로 한다.That is, as shown in FIGS. 12A to 12H, a method of constructing a drainage system for anchor for a tunnel according to the present invention includes a first lining (L1) construction step (SII), a hole forming step (SII) (S Ⅲ), the grouting step (S Ⅳ), the installation step (S Ⅴ) of the seal for preventing inflow of concrete (150), the construction step (S Ⅵ) of the second lining (S VII), installing the expansion type pressure segment 320 (S VIII), installing the deformation preventing circular cap 400 (S IX), fixing the pressure plate 350 (S X); And a step (S XI) of adhesion of the tunnel pipe (110) is sequentially carried out to construct a drainage system (S) serving as an anchor for a tunnel in the tunnel (T).

여기서, 상기 1차 라이닝(L1) 시공단계(S Ⅰ)는 도 12a에 도시된 바와 같이, 터널(T) 내부에 콘크리트를 타설 및 양생시켜 일정한 두께를 갖는 터널 1차 라이닝(L1)을 시공한다.As shown in FIG. 12A, the primary lining (L1) construction step S I is performed by placing and curing concrete in the tunnel T to construct a tunnel primary lining L1 having a constant thickness .

이어서, 상기 천공홀(H) 형성단계(S Ⅱ)는 도 12b에 도시된 바와 같이, 터널 1차 라이닝(L1)의 소정의 위치를 일정한 직경 및 깊이로 상향으로 천공하여 천공홀(H)을 형성한다.12 (b), the predetermined position of the tunnel primary lining L1 is punctured upward to a predetermined diameter and depth to form the perforation hole H, .

이어서, 상기 유공관(110) 삽입단계(S Ⅲ)는 도 12c에 도시된 바와 같이, 천공홀(H)에 일정한 직경 및 길이를 갖는 유공관(110)을 패커가 끼워진 상태로 삽입한다.Next, as shown in FIG. 12C, the perforated pipe 110 is inserted into the perforated hole H with a predetermined diameter and length inserted into the perforated pipe 110 (S III).

이어서, 상기 그라우팅 단계(S Ⅳ)는 도 12d에 도시된 바와 같이, 유공관(110) 내에 일정한 직경 및 길이를 갖는 그라우팅튜브(120)를 삽입하고, 상기 그라우팅튜브(120)를 통해 시멘트밀크 또는 우레탄 등의 그라우트재(130)를 주입하여 천공홀(H)의 상단부 일정부분을 그라우팅 처리한다.12D, the grouting step S IV is performed by inserting a grouting tube 120 having a predetermined diameter and length into the pipe tube 110 and supplying the grouting tube 120 with cement milk or urethane Grouting material 130 is injected to grout a predetermined portion of the upper end of the perforation hole H. [

이어서, 상기 콘크리트 유입방지용 씰(150) 설치단계(S Ⅴ)는 도 12e에 도시된 바와 같이, 1차 라이닝(L1)에 방수막(140)을 설치하고, 상기 유공관(110)의 하단에 콘크리트 타설시 콘크리트의 유입을 방지하기 위한 콘크리트 유입방지용 씰(150)을 설치한다.12E, the waterproofing membrane 140 is installed on the primary lining L1, and the waterproofing membrane 140 is installed on the lower end of the pipe 110. [ A seal 150 for preventing the inflow of concrete is installed at the time of pouring.

이어서, 상기 2차 라이닝(L2) 시공단계(S Ⅵ)는 도 12f에 도시된 바와 같이, 방수막(140)에 콘크리트를 타설 및 양생시켜 일정한 두께를 갖는 터널 2차 라이닝(L2)을 시공한다.Next, as shown in FIG. 12F, the secondary lining (L2) construction step S VI is performed by placing and curing concrete in the waterproofing membrane 140 to construct a tunnel secondary lining L2 having a constant thickness .

이어서, 상기 배수연결캡(340) 설치단계(S Ⅶ)는 도 12g 및 도 13a에 도시된 바와 같이, 콘크리트 유입방지용 씰(150)을 제거하고, 상기 유공관(110)의 선단부에 배수연결캡(340)을 설치한다.12G and 13A, the drainage connection cap 340 is installed in the drainage connection cap 340. The concrete drainage prevention seal 150 is removed and the drainage connection cap (not shown) is attached to the front end of the drainage connection cap 340 340 are installed.

이어서, 상기 확장형 가압세그먼트(320) 삽입 설치단계(S Ⅷ)는 도 13b에 도시된 바와 같이, 유공관(110) 선단부 내주면에 웨지(310)를 감싼 상태로 확장형 가압세그먼트(320)를 삽입 설치한다.Next, as shown in FIG. 13B, the expandable pressing segment 320 is inserted into the inner circumferential surface of the leading end of the pipe 110 while the wedge 310 is wrapped around the enlarged pressing segment 320 (S VIII) .

이어서, 상기 변형방지용 원형캡(400) 설치단계(S Ⅸ)는 도 13c에 도시된 바와 같이, 확장형 가압세그먼트(320)를 포함한 유공관(110)에 수팽창 고무지수재(410)를 설치하고, 상기 수팽창 고무지수재(410)를 포함한 상태에서 유공관(110)에 변형방지용 원형캡(400)을 나사 결합한다. 13C, the waterproof rubber exponential material 410 is installed in the pipe 110 including the expandable pressure segment 320, The deformation preventing circular cap 400 is screwed to the pipe 110 in a state including the water expansive rubber exponent material 410.

이어서, 상기 지압판(350) 고정단계(S Ⅹ)는 도 13d에 도시된 바와 같이, 변형방지용 원형캡(400)의 외측에 지압판(350)을 설치하고, 고정나사(360)로 터널 2차 라이닝(L2)에 고정한다.13D, the pressure plate 350 is installed on the outer side of the deformation preventing circular cap 400 and the fixing screw 360 is used to fix the tunnel secondary lining 400. [ (L2).

이어서, 상기 유공관(110) 밀착단계(S ⅩⅠ)는 도 13e에 도시된 바와 같이, 확장형 가압세그먼트(320)의 웨지(310)에 너트(370)를 삽입함과 동시에 회전시켜 확장형 가압세그먼트(320)를 유공관(110)에 밀착시킨다.13E, the nut 370 is inserted into the wedge 310 of the expandable pressing segment 320 and simultaneously rotated to insert the expandable pressing segment 320 (FIG. ) Is brought into close contact with the porous tube 110.

이어서, 상기 배수연결캡(340)의 하부에 배수관(380)을 나사 결합하여, 상기 터널(T) 외측에서 발생된 유입수를 배수관(380)을 통해 터널 하부로 배수시킨다.A drain pipe 380 is screwed to a lower portion of the drain connection cap 340 to drain the inflow water generated outside the tunnel T to the lower portion of the tunnel through the drain pipe 380.

상기한 바와 같은 구성 및 단계로 이루어진 본 발명에 따른 터널용 앵커 겸용 배수시스템 및 이의 시공방법은 터널(T) 라이닝(L) 주변에 흐르는 지하수를 유공관(110)을 통해 유도배수시킴으로써, 터널(T) 라이닝(L)에 작용하는 수압 하중을 감소시킴과 동시에 지보재로서의 기능도 함께하는 작용효과가 있다.According to the drainage system and method for constructing an anchor for tunnel according to the present invention constructed as described above, groundwater flowing around a tunnel (T) lining L is guided and drained through a pipe 110, ) There is an operation effect of reducing the hydrostatic load acting on the lining (L) and also functioning as a support material.

또한, 본 발명은 앵커 겸용 배수관인 유공관(110)을 터널(T)에 고정시킴으로써 터널(T)의 내공변위를 줄이기 위해 지보재에 작용하는 인장력을 터널(T) 라이닝(L)에 전달하며, 터널(T) 내부의 배수관(380)과의 연결을 통해 외부의 유입수를 처리함으로써, 터널(T)의 사용성에 영향을 주지 않는 작용효과가 있다.The present invention also relates to a method of controlling a tunnel (T) lining (L) by transmitting a tensile force acting on a support material (T) to reduce the internal displacement of the tunnel (T) There is an effect that the usability of the tunnel T is not affected by treating the influent water from the outside via the connection with the drain pipe 380 inside the tank T. [

이상의 설명은 나틈 터널(NATM TUNNEL)을 대상으로 하여 설명하였으나, 그 이외의 쉴드 터널(TBM TUNNEL)에도 용이하게 변형하여 실시할 수 있음을 밝혀두는 바이다.
Although the above description has been made on the NATM TUNNEL, it is to be understood that the present invention can be easily modified to other shield tunnels (TBM tunnels).

본 발명의 명세서에 기재한 바람직한 실시예는 예시적인 것으로서 한정적인 것은 아니며, 본 발명의 범위는 첨부된 특허청구범위에 의해서 나타나 있고, 그들 특허청구범위의 의미중에 들어가는 모든 변형예는 본 발명에 포함되는 것이다.The preferred embodiments described in the specification of the present invention are intended to be illustrative, not limiting, and the scope of the present invention is indicated by the appended claims, and all modifications that come within the meaning of the claims are included in the present invention. .

100: 정착부 110: 유공관
112: 구멍 120: 그라우팅튜브
130: 그라우트재 140: 방수막
150: 콘크리트 유입방지용 씰 160: 패커
200: 배수부 210: 중공필터
300: 터널고정부 310: 웨지
312: 절두원추부 314: 나사산
316: 고정봉 320: 확장형 가압세그먼트
322: 금속편 324: 가압세그먼트
326: 테이퍼 328: 요홈
330: 고무링 340: 배수연결캡
350: 지압판 360: 고정나사
370: 너트 380: 배수관
400: 변형방지용 원형캡 410: 수팽창 고무지수재
H: 천공홀 L: 라이닝
L1: 1차 라이닝 L2: 2차 라이닝
S: 터널용 앵커 겸용 배수시스템 T: 터널
100: fusing unit 110:
112: hole 120: grouting tube
130: Grout material 140: Waterproof membrane
150: Seal to prevent concrete inflow 160: Packer
200: drainage part 210: hollow filter
300: Tunnel fixing part 310: Wedge
312: Section Two-headed portion 314: Threaded
316: stator rods 320: expandable pressure segment
322: metal piece 324: pressure segment
326: Taper 328: Groove
330: rubber ring 340: drain connection cap
350: Pliers 360: Fixing screws
370: Nut 380: Drain pipe
400: Deformation preventing circular cap 410: Water expansion rubber index material
H: Perforated hole L: Lining
L1: primary lining L2: secondary lining
S: Drain system combined with anchor for tunnel T: Tunnel

Claims (17)

일정한 직경 및 길이를 가지며, 측면에 구멍이 형성된 유공관으로 구성되는 정착부와; 상기 유공관의 소정의 위치에 삽입되는 중공필터로 구성되는 배수부와; 상기 유공관의 선단부 내주면에 웨지를 감싼 상태로 고정 설치되는 확장형 가압세그먼트와; 상기 유공관 선단부 외주면에 나사 결합되는 배수연결캡과; 상기 배수연결캡을 포함한 유공관에 고정 설치되는 지압판과; 상기 지압판의 외측에 배치됨과 동시에 웨지의 선단부에 체결되는 너트로 구성되는 터널고정부로 구성됨을 특징으로 하는 터널용 앵커 겸용 배수시스템.A fusing unit having a constant diameter and a length, the fusing unit comprising a porous tube having a hole formed in a side surface thereof; A drain portion formed of a hollow filter inserted at a predetermined position of the oil pipe; An expandable pressing segment fixedly installed on an inner circumferential surface of a distal end of the porous tube in a state of wrapping a wedge; A drain connection cap screwed to an outer circumferential surface of the distal end of the tube; A piercing plate fixedly installed on a pipe including the drain connection cap; And a tunnel fixing portion which is composed of a nut disposed on the outside of the platen and fastened to a front end portion of the wedge. 제1항에 있어서,
상기 유공관은 섬유강화플라스틱으로 구성됨을 특징으로 하는 터널용 앵커 겸용 배수시스템.
The method according to claim 1,
Wherein the tubular pipe is made of a fiber reinforced plastic.
제1항 또는 제2항에 있어서,
상기 유공관의 소정의 위치에 패커가 고정설치됨을 특징으로 하는 터널용 앵커 겸용 배수시스템.
3. The method according to claim 1 or 2,
And a packer is fixedly installed at a predetermined position of the pipe tube.
제1항에 있어서,
상기 확장형 가압세그먼트는 3-4개의 금속편이 조립되어 가압세그먼트가 형성되고, 상기 가압세그먼트의 내주면에는 일측단에서 타측단에 걸쳐 내경이 좁아지도록 테이퍼가 형성되고, 상기 가압세그먼트의 외주면에는 일정한 깊이를 갖는 요홈이 형성되고, 상기 요홈에 고무링이 끼워짐을 특징으로 하는 터널용 앵커 겸용 배수시스템.
The method according to claim 1,
The expandable pressurizing segment is formed with three to four metal pieces to form a pressurizing segment. A taper is formed on the inner circumferential surface of the pressurizing segment so as to narrow the inner diameter from one end to the other end of the pressurizing segment. And a rubber ring is inserted in the groove.
제1항에 있어서,
상기 웨지는 절두원추형상으로 이루어지는 절두원추부와, 상기 절두원추부의 타단으로부터 일직선상으로 동일 직경으로 연장 형성됨과 동시에 단부에 나사산이 형성된 고정봉으로 구성됨을 특징으로 하는 터널용 앵커 겸용 배수시스템.
The method according to claim 1,
Wherein the wedge comprises a stepped two-stepped portion made up of a truncated conical shape and a fixed rod extending in the same diameter straight line from the other end of the stepped two-stepped portion and having threads formed at the end thereof.
제1항에 있어서,
상기 배수연결캡에 배수관이 나사결합됨을 특징으로 하는 터널용 앵커 겸용 배수시스템.
The method according to claim 1,
And a drain pipe is screwed to the drain connection cap.
제1항에 있어서,
상기 지압판과 유공관 단부 사이에 변형방지용 원형캡이 고정 설치됨을 특징으로 하는 터널용 앵커 겸용 배수시스템.
The method according to claim 1,
And an anti-deformation circular cap is fixedly installed between the piping plate and the end of the pipe.
제7항에 있어서,
상기 변형방지용 원형캡과 유공관 단부 사이에 수팽창 고무지수재가 고정 설치됨을 특징으로 하는 터널용 앵커 겸용 배수시스템.
8. The method of claim 7,
Wherein an expansion rubber index material is fixedly installed between the deformation preventing circular cap and the end of the pipe.
터널용 앵커 겸용 배수시스템을 시공하는 방법으로서,
터널 내부에 콘크리트를 타설 및 양생시켜 1차 라이닝을 시공하는 단계(S Ⅰ);
상기 1차 라이닝의 소정의 위치를 일정한 직경 및 깊이로 천공하여 천공홀을 형성하는 단계(S Ⅱ);
상기 천공홀에 일정한 직경 및 길이를 갖는 유공관을 삽입하는 단계(S Ⅲ);
상기 유공관 내에 일정한 직경 및 길이를 갖는 그라우팅튜브를 삽입하고, 상기 그라우팅튜브를 통해 그라우트재를 주입하여 천공홀의 일정부분을 그라우팅하는 단계(S Ⅳ);
상기 1차 라이닝에 방수막을 설치하고, 상기 유공관의 하단에 콘크리트 유입방지용 씰을 설치하는 단계(S Ⅴ);
상기 방수막에 콘크리트를 타설 및 양생시켜 2차 라이닝을 시공하는 단계(S Ⅵ);
상기 콘크리트 유입방지용 씰을 제거하고, 상기 유공관의 선단부에 배수연결캡을 설치하는 단계(S Ⅶ);
상기 유공관 선단부 내주면에 웨지를 감싼 상태로 확장형 가압세그먼트를 삽입 설치하는 단계(S Ⅷ);
상기 확장형 가압세그먼트를 포함한 유공관에 수팽창 고무지수재를 설치하고, 상기 수팽창 고무지수재에 변형방지용 원형캡을 설치하는 단계(S Ⅸ);
상기 변형방지용 원형캡의 외측에 지압판을 설치하고, 고정나사로 터널 2차 라이닝에 고정하는 단계(S Ⅹ);
상기 확장형 가압세그먼트의 웨지에 너트를 삽입함과 동시에 회전시켜 확장형 가압세그먼트를 유공관에 인장력을 가하는 단계(S ⅩⅠ)로 이루어짐을 특징으로 하는 터널용 앵커 겸용 배수시스템 시공방법.
1. A method of constructing an anchor double drainage system for a tunnel,
A step (S I) of constructing a primary lining by pouring and curing concrete inside the tunnel;
Drilling a predetermined position of the primary lining to a predetermined diameter and depth to form a perforation hole (SII);
Inserting a perforation hole having a predetermined diameter and length into the perforation hole (SIII);
Inserting a grouting tube having a predetermined diameter and a predetermined length into the pipe tube, grouting a certain portion of the perforation hole by injecting grout material through the grouting tube (SIV);
Providing a waterproof membrane on the primary lining and installing a seal for preventing concrete inflow at the bottom of the pipe (S V);
Placing (S VI) a secondary lining by placing and curing concrete on the waterproof membrane;
Removing the concrete inflow preventing seal and installing a drain connection cap at a front end of the pipe (S VII);
(S VIII) of inserting the expandable pressing segment in a state of wrapping the wedge on the inner circumferential surface of the end portion of the pipe;
Providing a water expansion rubber exponent material in a pipe including the expandable pressure segment, and installing a circular cap for preventing deformation of the water expansion rubber exponent (SIX);
(SX) of installing a pressure plate on the outside of the deformation preventing circular cap and securing it to the tunnel secondary lining with a fixing screw;
And a step (SXI) of inserting a nut into the wedge of the expandable pressurizing segment and simultaneously rotating the nut to apply a tensile force to the expandable pressurizing segment to the pipe.
제9항에 있어서,
상기 터널용 앵커 겸용 배수시스템은 일정한 직경 및 길이를 가지며, 측면에 구멍이 형성된 유공관으로 구성되는 정착부와; 상기 유공관의 소정의 위치에 삽입되는 중공필터로 구성되는 배수부와; 상기 유공관의 선단부 내주면에 웨지를 감싼 상태로 고정 설치되는 확장형 가압세그먼트와; 상기 유공관 선단부 외주면에 나사 결합되는 배수연결캡과; 상기 배수연결캡을 포함한 유공관에 고정 설치되는 지압판과; 상기 지압판의 외측에 배치됨과 동시에 웨지의 선단부에 체결되는 너트로 구성되는 터널고정부로 구성됨을 특징으로 하는 터널용 앵커 겸용 배수시스템 시공방법.
10. The method of claim 9,
The anchor and drainage system for a tunnel includes: a fusing unit having a predetermined diameter and a length, the fusing unit having a hole formed in a side surface thereof; A drain portion formed of a hollow filter inserted at a predetermined position of the oil pipe; An expandable pressing segment fixedly installed on an inner circumferential surface of a distal end of the porous tube in a state of wrapping a wedge; A drain connection cap screwed to an outer circumferential surface of the distal end of the tube; A piercing plate fixedly installed on a pipe including the drain connection cap; And a tunnel fixing portion formed of a nut disposed outside the pressure plate and fastened to a front end portion of the wedge.
제10항에 있어서,
상기 유공관은 섬유강화플라스틱으로 구성됨을 특징으로 하는 터널용 앵커 겸용 배수시스템 시공방법.
11. The method of claim 10,
Wherein the piercing pipe is made of a fiber reinforced plastic.
제10항 또는 제11항에 있어서,
상기 유공관의 소정의 위치에 패커가 고정설치됨을 특징으로 하는 터널용 앵커 겸용 배수시스템 시공방법.
The method according to claim 10 or 11,
And a packer is fixedly installed at a predetermined position of the pipe tube.
제10항에 있어서,
상기 확장형 가압세그먼트는 3-4개의 금속편이 조립되어 가압세그먼트가 형성되고, 상기 가압세그먼트의 내주면에는 일측단에서 타측단에 걸쳐 내경이 좁아지도록 테이퍼가 형성되고, 상기 가압세그먼트의 외주면에는 일정한 깊이를 갖는 요홈이 형성되고, 상기 요홈에 고무링이 끼워짐을 특징으로 하는 터널용 앵커 겸용 배수시스템 시공방법.
11. The method of claim 10,
The expandable pressurizing segment is formed with three to four metal pieces to form a pressurizing segment. A taper is formed on the inner circumferential surface of the pressurizing segment so as to narrow the inner diameter from one end to the other end of the pressurizing segment. And a rubber ring is inserted into the groove. The method of claim 1, wherein the rubber ring is inserted into the groove.
제10항에 있어서,
상기 웨지는 절두원추형상으로 이루어지는 절두원추부와 상기 절두원추부의 타단으로부터 일직선상으로 동일 직경으로 연장 형성됨과 동시에 단부에 나사산이 형성된 고정봉으로 구성됨을 특징으로 하는 터널용 앵커 겸용 배수시스템 시공방법.
11. The method of claim 10,
Wherein the wedge comprises a stepped two-stepped portion made of a frusto-conical shape and a fixed rod extending in the same diameter in a straight line from the other end of the stepped two-stepped portion and having threads formed at the end thereof. .
제10항에 있어서,
상기 배수연결캡에 배수관이 나사결합됨을 특징으로 하는 터널용 앵커 겸용 배수시스템 시공방법.
11. The method of claim 10,
And a drain pipe is screwed to the drain connection cap.
제9항에 있어서,
상기 지압판과 유공관 단부 사이에 변형방지용 원형캡이 고정 설치됨을 특징으로 하는 터널용 앵커 겸용 배수시스템 시공방법.
10. The method of claim 9,
And a circular cap for preventing deformation is fixedly installed between the piping plate and the end of the pipe.
제16항에 있어서,
상기 변형방지용 원형캡과 유공관 단부 사이에 수팽창 고무지수재가 고정 설치됨을 특징으로 하는 터널용 앵커 겸용 배수시스템 시공방법.
17. The method of claim 16,
And a water expansion rubber exponent material is fixedly installed between the deformation preventing circular cap and the end of the porous pipe.
KR20140032986A 2014-03-20 2014-03-20 anchor and drainage system and it's construction method for tunnel KR101501453B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR20140032986A KR101501453B1 (en) 2014-03-20 2014-03-20 anchor and drainage system and it's construction method for tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR20140032986A KR101501453B1 (en) 2014-03-20 2014-03-20 anchor and drainage system and it's construction method for tunnel

Publications (1)

Publication Number Publication Date
KR101501453B1 true KR101501453B1 (en) 2015-03-12

Family

ID=53027197

Family Applications (1)

Application Number Title Priority Date Filing Date
KR20140032986A KR101501453B1 (en) 2014-03-20 2014-03-20 anchor and drainage system and it's construction method for tunnel

Country Status (1)

Country Link
KR (1) KR101501453B1 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101541005B1 (en) 2015-01-29 2015-08-03 현주건설(주) Packing type drainpipe, drain apparatus for tunnel and constructing methode thereof
KR101782517B1 (en) 2016-10-26 2017-09-29 한국건설기술연구원 Construction method for girder of pillar type underground structure
NO20170512A1 (en) * 2016-04-05 2017-10-06 Jon Aarbakk Drainage of water from a fuse bolt
CN107489438A (en) * 2016-11-29 2017-12-19 建国大学校产业学校协力团 Utilize the earth anchor dual-purpose drainpipe and its method to set up of steel pipe expansion
CN112879050A (en) * 2021-02-10 2021-06-01 中国电建集团成都勘测设计研究院有限公司 Waterproof structure of drainage type tunnel primary support system and construction method thereof
KR20220145186A (en) * 2021-04-21 2022-10-28 건국대학교 산학협력단 Apparatus for reducing water pressure on tunnel and installation method thereof
CN117587809A (en) * 2024-01-15 2024-02-23 中国矿业大学(北京) Anchor assembly suitable for shallow water-rich environment and anchor construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200352267Y1 (en) * 2004-02-12 2004-06-10 (주)피에스테크 Slope-reinforcing structure for soil nailing having function of drainage
KR100638548B1 (en) * 2005-06-27 2006-10-27 최용기 Drain combination pressurization grouting equipment and this was used upward type using slope and ground reinforcement method of construction
JP2007070952A (en) * 2005-09-09 2007-03-22 Kfc Ltd Lock bolt working method and attachment
KR100865579B1 (en) * 2007-03-30 2008-10-28 한국지질자원연구원 Assembling-type drain device for hydraulic pressure reducing

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200352267Y1 (en) * 2004-02-12 2004-06-10 (주)피에스테크 Slope-reinforcing structure for soil nailing having function of drainage
KR100638548B1 (en) * 2005-06-27 2006-10-27 최용기 Drain combination pressurization grouting equipment and this was used upward type using slope and ground reinforcement method of construction
JP2007070952A (en) * 2005-09-09 2007-03-22 Kfc Ltd Lock bolt working method and attachment
KR100865579B1 (en) * 2007-03-30 2008-10-28 한국지질자원연구원 Assembling-type drain device for hydraulic pressure reducing

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101541005B1 (en) 2015-01-29 2015-08-03 현주건설(주) Packing type drainpipe, drain apparatus for tunnel and constructing methode thereof
NO20170512A1 (en) * 2016-04-05 2017-10-06 Jon Aarbakk Drainage of water from a fuse bolt
KR101782517B1 (en) 2016-10-26 2017-09-29 한국건설기술연구원 Construction method for girder of pillar type underground structure
CN107489438A (en) * 2016-11-29 2017-12-19 建国大学校产业学校协力团 Utilize the earth anchor dual-purpose drainpipe and its method to set up of steel pipe expansion
KR20180060825A (en) * 2016-11-29 2018-06-07 건국대학교 산학협력단 Drain pipe suitable for anchor using expanding steel pipe and method of installation of the same
KR101934104B1 (en) * 2016-11-29 2019-03-25 건국대학교 산학협력단 Drain pipe suitable for anchor using expanding steel pipe and method of installation of the same
CN112879050A (en) * 2021-02-10 2021-06-01 中国电建集团成都勘测设计研究院有限公司 Waterproof structure of drainage type tunnel primary support system and construction method thereof
KR20220145186A (en) * 2021-04-21 2022-10-28 건국대학교 산학협력단 Apparatus for reducing water pressure on tunnel and installation method thereof
KR102591430B1 (en) * 2021-04-21 2023-10-19 건국대학교 산학협력단 Apparatus for reducing water pressure on tunnel and installation method thereof
CN117587809A (en) * 2024-01-15 2024-02-23 中国矿业大学(北京) Anchor assembly suitable for shallow water-rich environment and anchor construction method
CN117587809B (en) * 2024-01-15 2024-03-15 中国矿业大学(北京) Anchor assembly suitable for shallow water-rich environment and anchor construction method

Similar Documents

Publication Publication Date Title
KR101501453B1 (en) anchor and drainage system and it's construction method for tunnel
CN104775428B (en) Compound-type pre-stvessed anchor cable structure and construction method thereof
CN106193030B (en) A kind of prestressing force grouted anchor bar and construction method with hangnail head
CN104790393B (en) Double-anchoring-section prestress anchor cable structure and constructing method thereof
RU2651681C2 (en) Rock anchor bolt
CN204703160U (en) Two anchoring section prestressed anchor Cable Structure
CN107060774B (en) A kind of anti-tunnel portal wall damage device and construction method
CN103410161B (en) Oblique control slip casting steel anchor tube framework and construction method thereof
KR101353882B1 (en) Method of reinforcement and construction of pillar of neighboring tunnel
CN204703159U (en) Prefabricated anchor head pressure anchor wire structure
CN104790394A (en) Pressure anchor cable structure with prefabricated anchor head and construction method of pressure anchor cable structure
KR101605028B1 (en) Structure of Permanent Anchor
CN203717001U (en) Flexible prestressed grouting anchor rope
CN107119682A (en) A kind of soil nail wall and its construction method
CN110984173B (en) Underground support anchoring equipment for building construction and construction method thereof
JP4696556B2 (en) Natural ground reinforcement earth construction method and natural ground reinforcement soil structure
KR20090132033A (en) The support material for a tunnel and tunnel support structure
CN108360561A (en) The Basement reconstruction of raft foundation constructs
CN206737950U (en) A kind of stainless steel floral tube structure of tunnel arch foot draining
CN217438921U (en) Anchor rod and isolation pile combined reinforcing structure for protecting excavation of side tunnel of foundation pit
CN108755677B (en) Prefabricated inner anchor head anchor rope structure for controlling grouting for multiple times
CN206581314U (en) Screw head muscle body posttension pile foundation
CN109958460A (en) The multi-functional anchoring waterproof construction of one kind and its anchoring process
CN115928704A (en) Segmented opening-closing type grouting pipe and grouting reinforcement method
CN215949527U (en) Hole sealing, grouting and water plugging reinforcing device for anchor cable holes in roadway water sprinkling area

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20180305

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20190305

Year of fee payment: 5