KR101431623B1 - Mehod for constructing underground wall in extension of undergound parking lot - Google Patents

Mehod for constructing underground wall in extension of undergound parking lot Download PDF

Info

Publication number
KR101431623B1
KR101431623B1 KR1020130029112A KR20130029112A KR101431623B1 KR 101431623 B1 KR101431623 B1 KR 101431623B1 KR 1020130029112 A KR1020130029112 A KR 1020130029112A KR 20130029112 A KR20130029112 A KR 20130029112A KR 101431623 B1 KR101431623 B1 KR 101431623B1
Authority
KR
South Korea
Prior art keywords
wall
steel pipe
work space
underground
building
Prior art date
Application number
KR1020130029112A
Other languages
Korean (ko)
Inventor
김정윤
Original Assignee
주식회사 엔티에스건설
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 엔티에스건설 filed Critical 주식회사 엔티에스건설
Priority to KR1020130029112A priority Critical patent/KR101431623B1/en
Application granted granted Critical
Publication of KR101431623B1 publication Critical patent/KR101431623B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/04Prefabricated parts, e.g. composite sheet piles made of steel
    • E02D5/06Fitted piles or other elements specially adapted for closing gaps between two sheet piles or between two walls of sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/28Prefabricated piles made of steel or other metals
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/0021Mortar

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Composite Materials (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The present invention relates to a construction method for the construction of walls by extending a basement of a building and, more specifically, to a method for constructing a underground wall for extending a underground parking lot, comprising: a first workspace drilling step of ensuring a primary work space; a steel pipe press fitting step of press-fitting an upper steel pipe and a lower steel pipe; an iron plate installing step of forming incision grooves respectively, pressing an iron plate on both sides, and welding the steel plate and the steel pipe; a second workspace drilling step of forming a secondary workspace; a steel pipe cutting step of cutting out the upper steel pipe and the lower steel pipe; an H beam installing step of using multiple H beams to support vertical connection; and a wall finishing step of running and finishing formation of the wall and the finishing mortar.

Description

지하주차장 증축을 위한 지하 벽체 시공공법{Mehod for constructing underground wall in extension of undergound parking lot}[0001] The present invention relates to a method of constructing an underground parking lot,

본 발명은 건축물의 지하를 연장하여 벽체를 시공하기 위한 시공공법에 관한 것으로, 더욱 상세하게는 건축물 리모델링시 지하주차장을 증축하기 위해 그 지하 벽체를 연장 시공하되, 기존 건축물을 그대로 둔 상태에서 견고한 지지력을 유지한 생태에서의 시공이 가능하게 함으로써, 안정성을 확보한 상태에서 신속하면서도 정교하게 연장 가능하게 하기 위한 지하주차장 증축을 위한 지하 벽체 시공공법에 관한 것이다.
The present invention relates to a construction method for constructing a wall by extending the underground structure of a building. More particularly, the present invention relates to a construction method for constructing a wall by extending an underground wall, The present invention relates to an underground wall construction method for enlarging an underground parking lot in order to enable quick and precise extension of a building in a stable state by making it possible to construct an underground parking lot.

일반적으로 시공한 지 20년 이상 오래된 고층 건축물(아파트) 등의 경우 건설당시 주차장의 필요성이나 건축법상의 여건으로 인하여 지하 주차장 시설이 완비되어 있지 않았다.In the case of high-rise buildings (apartments) that were built more than 20 years ago, the underground parking facilities were not fully equipped due to the necessity of parking at the time of construction and the conditions of building law.

한편, 상기와 같이 오래된 건축물의 경우 상당한 노후가 진행되어 있는 상태로 재건축을 필요로 하고 있으나, 건축상의 난해함과 상당한 비용이 투입되어야 한다는 단점으로 인해 재건축이 지연되고 있는 실정이며, 이러한 현상으로 거주자로 하여금 생활 환경의 낙후와 위험을 그대로 감수하고 있는 실정이다.On the other hand, in the case of the above-mentioned old buildings, the reconstruction is required in a state of considerable aging, but the reconstruction is delayed due to the inconvenience of the architectural difficulty and considerable cost. It is the situation that it is taking the risk of the backwardness and the risk of the living environment.

이에, 근자에 들어 기존의 아파트를 보수보강 및 증축 등을 이용한 리모델링 공사가 활성화되고 있으며, 상기와 같은 리모델링 공사 중 현재 생활수준이 향상함에 따라 자동차의 보유가 증가하여 지상공간의 조경 및 보행에 따른 안전 등 생활환경의 개선을 위해 지하주차장이 절실히 필요하였다.Accordingly, the remodeling work using the existing apartments for repair and reinforcement is being activated in the recent years, and as the living standard is improved during the remodeling work as described above, the number of vehicles is increased, In order to improve the living environment such as safety, an underground parking lot was desperately needed.

이에, 지하 주차장 증축에 따른 다양한 시도가 행해져 왔다. 그 하나의 예로서 특허출원공개 제10-2004-0092200호와 같이 콘크리트 패널을 이용한 방법이 제안된바 있다.Therefore, various attempts have been made to increase the underground parking lots. As an example of such a method, a method using a concrete panel has been proposed as disclosed in Japanese Patent Application Laid-Open No. 10-2004-0092200.

그러나 상기와 같은 콘크리트 패널을 이용한 시공방법은 시공상의 번거로움과 기존 건축물과의 연결관계가 이루어지지 않아 추후 안전상의 문제와 시공단가의 상승을 가져오는 문제점이 있었다.
However, the construction method using the concrete panel as described above has a problem in that it is inconvenient for the construction and the connection relation with the existing building is not made, which leads to a safety problem and an increase in the construction cost.

대한민국공개특허공보 제10-2004-0092200호.Korean Patent Publication No. 10-2004-0092200.

본 발명은 상기와 같은 제반 문제점을 해결하기 위해 창안된 것으로, 토류벽 시공에 따른 작업 공간의 안정된 확보와 H빔을 이용한 견고한 지지와 강관 및 철판을 이용한 보강시공이 가능하게 함으로써, 시공상의 편리함과 건축물의 안정성의 확보가 가능하게 하고, 특히 시공단가의 절감을 가져오게 하기 위한 지하주차장 증축을 위한 지하 벽체 시공공법을 제공함에 본 발명의 목적이 있다.
SUMMARY OF THE INVENTION The present invention has been made to solve the above problems and it is an object of the present invention to provide a method and a system for securing a stable working space according to the construction of a toll wall and a rigid support using H beams and a reinforcement construction using steel pipes and steel plates, The present invention has been made in view of the above problems, and it is an object of the present invention to provide an underground wall construction method for enlarging an underground parking lot to reduce the construction cost.

상기 목적을 달성하기 위한 구체적인 수단으로는, 건축물 리모델링 공사시 지하주차장 증축을 위해 기존 건축물의 수평보 저면으로 지하 벽체를 연결 시공하는 벽체 시공공법에 있어서,
기존 건축물의 외벽 일측에서 그 외벽의 내측 및 외측을 연결하는 네 모서리에 H빔을 지면에 설치하여 작업구역을 설정하는 한편, 그 작업구역을 굴착하여 가면서 H빔에 지지되는 토류판을 이용한 토류벽을 시공 및 마주보는 토류벽은 턴버클바로 연결 지지하여 1차 작업공간을 확보하는 제1 작업공간 굴착단계;
1차 작업공간의 상부에서 수평보의 저면으로부터 이격되는 위치에 상부강관을 압입하되, 수평보와 상부강관의 이격공간에는 수평보의 저면과 상부강관의 상부면을 지지하는 H빔블록을 더 설치하며, 1차 작업공간의 하부에서 외벽의 길이방향으로 1차 작업공간의 바닥면에 해당하게 하부강관을 압입하는 강관 압입단계;
압입된 상,하부강관의 내부 토사를 제거한 후, 상부강관의 저면과 하부강관의 상부면에 건축물의 벽체 외측으로 치우치는 한편 서로 대항되는 형태로 절개홈을 각각 형성하되, 상,하 대항되는 절개홈을 따라 양측으로 철판을 압입하고, 강관과 철판을 용접 결합하는 철판 설치단계;
건축물의 내부에서 압입된 하부강관의 저면까지 굴착을 수행하여 상기 1차 작업공간과 연결되도록 2차 작업공간을 형성하는 제2 작업공간 굴착단계;
상기 2차 작업공간내에서 상기 압입된 철판과 수직을 이루도록 상부강관 및 하부강관을 절개하는 강관 절단단계;
기존 건축물의 하부에서 상단이 수평보 저면에 지지되고 하단이 1차 작업공간 및 2차 작업공간의 저면에 지지되도록 자키가 형성되어 길이조절이 가능한 다수의 H빔을 이용하여 수직 연결 지지하는 H빔 설치단계; 및
상기 H빔이 설치된 상태에서 그 H빔이 묻히도록 제1,2 작업공간의 바닥면으로부터 건축물의 수평보 저면에 이르게 벽돌을 조적하여 벽체를 형성 및 마감몰탈을 수행하여 완성하는 벽체 완성단계;를 포함하여 수행함으로 달성할 수 있는 것이다.
As a concrete means for accomplishing the above object, there is a wall construction method in which an underground wall is connected to a horizontal bottom surface of an existing building to enlarge an underground parking lot when remodeling a building,
The H beam is installed on the ground at four corners connecting the inside and outside of the outside wall of the existing building from the outside wall of the existing building to construct a working area. And a first workspace excavating step of securing a primary work space by supporting a turning wall of the opposing toe wall;
An H beam block supporting the bottom surface of the horizontal beam and the upper surface of the upper steel pipe is further installed in the space between the horizontal beam and the upper steel pipe at a position spaced from the bottom surface of the horizontal beam at the upper part of the primary work space A step of press-fitting a lower steel pipe corresponding to a bottom surface of the primary work space in a longitudinal direction of the outer wall at a lower portion of the primary work space;
After the inner soil of the press-fitted upper and lower steel pipes is removed, the bottom surface of the upper steel pipe and the upper surface of the lower steel pipe are biased toward the outside of the wall of the building, A steel plate mounting step of press-fitting the steel plate to both sides along the steel plate and welding the steel plate and the steel plate together;
A second work space excavating step of excavating from the inside of the building to the bottom surface of the lower steel pipe pressurized to form a secondary work space to be connected to the primary work space;
A steel pipe cutting step of cutting the upper steel pipe and the lower steel pipe so as to be perpendicular to the press-fitted steel plate in the secondary work space;
The upper end of the H-beam is supported on the horizontal bottom surface of the existing structure and the lower end is supported on the bottom of the primary working space and the secondary working space by using a plurality of H- Installation phase; And
And a wall finishing step of finishing the wall by forming walls and finishing mortar by assembling the bricks from the bottom surface of the first and second work spaces to the horizontal bottom surface of the building so that the H beams are embedded in the H beams, And can be achieved.

삭제delete

삭제delete

삭제delete

삭제delete

삭제delete

삭제delete

이상과 같이 본 발명 지하주차장 증축을 위한 지하 벽체 시공공법은, 토류벽 시공에 따른 작업 공간확보와 H빔을 이용한 기존 건축물의 안정된 지지력 확보와 강관 및 철판을 이용한 보강시공이 가능하여, 시공상 매우 편리하면서도 증축된 건축물의 안정성이 확보된 상태로의 시공이 가능하고, 특히 증축에 따른 시공비용이 절감되어 건축물 리모델링에 따른 투자비용의 절감을 가져오는 등 리모델링 활성화를 가져오는 효과를 얻을 수 있는 것이다.
As described above, the underground wall construction method for the extension of the underground parking lot according to the present invention can secure the work space according to the construction of the toll wall, secure the stable bearing capacity of the existing structure using the H beam, and reinforce the construction using the steel pipe and the steel plate, The construction can be performed in a state in which the stability of the enlarged building is ensured. In particular, the construction cost due to the enlargement can be reduced, thereby reducing the investment cost due to the remodeling of the building.

도 1은 본 발명 지하주차장 증축을 위한 지하 벽체 시공공법의 공정 단계를 나타낸 간략도.
도 2는 본 발명 지하주차장 증축을 위한 지하 벽체 시공공법의 작업공간 굴착단계를 나타낸 평면도.
도 3은 본 발명 지하주차장 증축을 위한 지하 벽체 시공공법의 작업공간 굴착단계를 나타낸 정 단면도.
도 4는 본 발명 지하주차장 증축을 위한 지하 벽체 시공공법의 강관 압입단계를 나타낸 정 단면도.
도 5는 본 발명 지하주차장 증축을 위한 지하 벽체 시공공법의 철판 설치단계를 나타낸 측 단면도.
도 6은 본 발명 지하주차장 증축을 위한 지하 벽체 시공공법의 철판 설치단계를 나타낸 정 단면도.
도 7은 본 발명 지하주차장 증축을 위한 지하 벽체 시공공법의 제2 작업공간 굴착단계를 나타낸 측 단면도.
도 8은 본 발명 지하주차장 증축을 위한 지하 벽체 시공공법의 강관 절단단계를 나타낸 측 단면도.
도 9는 본 발명 지하주차장 증축을 위한 지하 벽체 시공공법의 H빔 설치단계를 나타낸 측 단면도.
도 10은 지하주차장 증축을 위한 지하 벽체 시공공법의 H빔 설치단계를 나타낸 정 단면도.
도 11은 본 발명 지하주차장 증축을 위한 지하 벽체 시공공법의 벽체 완성단계를 나타낸 측 단면도.
BRIEF DESCRIPTION OF THE DRAWINGS FIG. 1 is a schematic view showing a process step of an underground wall construction method for enlarging an underground parking lot according to the present invention. FIG.
2 is a plan view showing a work space excavation step of an underground wall construction method for enlarging an underground parking lot of the present invention.
3 is a front sectional view showing a work space excavation step of an underground wall construction method for enlarging an underground parking lot according to the present invention.
4 is a front sectional view showing the step of pressurizing a steel pipe in the method of constructing an underground wall for the expansion of an underground parking lot according to the present invention.
5 is a side cross-sectional view showing a step of installing an iron plate in an underground wall construction method for enlarging an underground parking lot according to the present invention.
6 is a front sectional view showing a step of installing an iron plate in an underground wall construction method for enlarging an underground parking lot according to the present invention.
FIG. 7 is a side cross-sectional view showing a second work space excavation step of an underground wall construction method for enlarging an underground parking lot of the present invention. FIG.
8 is a side sectional view showing a step of cutting a steel pipe in an underground wall construction method for enlarging an underground parking lot of the present invention.
9 is a side sectional view showing an H beam installation step of an underground wall construction method for enlarging an underground parking lot of the present invention.
10 is a front sectional view showing an H beam installation step of an underground wall construction method for an underground parking lot extension.
11 is a side cross-sectional view showing a wall finishing step of an underground wall construction method for enlarging an underground parking lot of the present invention.

본 명세서 및 청구범위에 사용된 용어나 단어는 통상적이거나 사전적인 의미로 한정해서 해석되어서는 아니 되며, 발명자는 그 자신의 발명을 가장 최선의 방법으로 설명하기 위해 용어의 개념을 적절하게 정의할 수 있다는 원칙에 입각하여 본 발명의 기술적 사상에 부합하는 의미와 개념으로 해석되어야만 한다.The terms and words used in the present specification and claims should not be construed as limited to ordinary or dictionary terms and the inventor may appropriately define the concept of the term in order to best describe its invention It should be construed as meaning and concept consistent with the technical idea of the present invention.

따라서, 본 명세서에 기재된 실시예와 도면에 도시된 구성은 본 발명의 가장 바람직한 일 실시예에 불과할 뿐이고, 본 발명의 기술적 사상을 모두 대변하는 것은 아니므로, 본 출원시점에 있어서 이들을 대체할 수 있는 다양한 균등물과 변형예들이 있을 수 있음을 이해하여야 한다.
Therefore, the embodiments described in the present specification and the configurations shown in the drawings are merely the most preferred embodiments of the present invention, and not all of the technical ideas of the present invention are described. Therefore, It should be understood that various equivalents and modifications may be present.

이하, 본 발명의 바람직한 실시예를 첨부된 도면을 참고하여 상세히 설명한다.Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 1은 본 발명 지하주차장 증축을 위한 지하 벽체 시공공법의 공정 단계를 나타낸 간략도 이다.1 is a schematic view showing a process step of an underground wall construction method for enlarging an underground parking lot of the present invention.

도 1의 도시와 같이 본 발명 지하주차장 증축을 위한 지하 벽체 시공방법은, 1차 작업공간 굴착단계(S100)와, 강관 압입단계(S200)와, 철판 설치단계(S300)와, 2차 작업공간 굴착단계(S400)와, 강관 절단단계(S500)와, H빔 설치단계(S600)와, 벽체 완성단계(S700)를 수행하여 된다.As shown in FIG. 1, the method for constructing an underground wall for enlarging an underground parking lot according to the present invention includes a primary work space excavation step S100, a steel pipe press-in step S200, a steel plate installation step S300, The excavation step S400, the steel pipe cutting step S500, the H beam installing step S600, and the wall finishing step S700.

여기서, 상기 작업공간 굴착단계(S100)는, Here, the work space excavation step (SlOO)

도 2는 본 발명 지하주차장 증축을 위한 지하 벽체 시공공법의 작업공간 굴착단계를 나타낸 평면도이고, 도 3은 본 발명 지하주차장 증축을 위한 지하 벽체 시공공법의 작업공간 굴착단계를 나타낸 정 단면도이다.FIG. 2 is a plan view showing a work space excavation step of an underground wall construction method for enlarging an underground parking lot according to the present invention, and FIG. 3 is a front sectional view showing a work space excavation step of an underground wall construction method for enlarging an underground parking lot according to the present invention.

도 2의 도시와 같이 기존 건축물(10)의 외벽(20) 길이방향 일측에는 제1 작업공간(100)이 확보된다.As shown in FIG. 2, a first work space 100 is secured to one side of a longitudinal direction of an outer wall 20 of an existing building 10.

이때, 제1 작업공간(100)을 확보하기 위해서는 외벽의 내측 및 외측을 연결하는 네 모서리에 수직으로 H빔(110)을 지면에 박아 작업구역(101)을 설정하면 되는 것으로, 이때 설정되는 작업구역(101)은 약 2×2m에 해당하는 구역이 설정되게 함이 적합하다.In this case, in order to secure the first work space 100, the work area 101 is set by vertically inserting the H beams 110 on the ground at four corners connecting the inside and the outside of the outside wall. Zone 101 is suitably set to have a zone of about 2 x 2 m.

이후, 도 3의 도시와 같이 그 작업구역(101)을 굴착하되, 기존 건축물(10)의 수평보(30) 하부로 굴착을 수행하면 되는 것으로, 굴착을 수행하는 동시에 H빔에는 토류판(121)이 순차적으로 설치되어 토류벽(120)을 이루는 것이며, 이에, 그 토류벽(120)의 사이에는 공간 형태의 2×2m에 해당하는 제1 작업공간(100)이 확보되는 것이다.3, excavation is performed to the lower part of the horizontal beam 30 of the existing building 10 by excavating the work area 101. Excavation is performed while the H beam is irradiated with the current plate 121, And the first working space 100 corresponding to a space of 2 x 2 m is secured between the toothed walls 120. [

한편, 필요에 따라 상기와 같이 시공된 토류벽(120)의 토압에 의한 붕괴를 막기 위해 제1 작업공간(100) 내의 건축물 내측과 외측의 마주보는 토류벽(120)을 서로 연결 지지하는 턴버클바(130)를 더 시공할 수 있다.In order to prevent the earth wall 120 from being collapsed due to the earth pressure, the turnbuckle bar 130, which connects and supports the opposing earth walls 120 on the inside and the outside of the building in the first work space 100, ) Can be further constructed.

이때, 상기 턴버클바(130)는, 통상의 턴버클과 같이 너트체를 조임시 양측으로 지지봉이 전개될 수 있는 형태면 가능한 것으로, 여기서 설치되는 턴버클바(130)는 내,외측의 마주보는 H빔(110)을 지지하거나 마주보는 토류판(121)을 지지하되, 제1 작업공간(100) 내에서 작업의 간섭을 받지 않는 범위에서 설치함이 바람직하다.At this time, the turnbuckle bar 130 can be formed in such a manner that the support bar can be deployed on both sides when the nut body is tightened like a normal turnbuckle. The turnbuckle bar 130 installed here is a bar- It is preferable to support the turntable 121 supporting the turntable 110 or the turntable 121 facing the turntable 121 within a range that does not interfere with the operation in the first work space 100.

이후, 강관 압입단계(S200)를 수행하되,Thereafter, the steel pipe press-fitting step (S200) is performed,

도 4는 본 발명 지하주차장 증축을 위한 지하 벽체 시공공법의 강관 압입단계를 나타낸 정 단면도이다.4 is a front sectional view showing a step of pressurizing a steel pipe in an underground wall construction method for enlarging an underground parking lot according to the present invention.

도 4의 도시와 같이 제1 작업공간(100)에서는 외벽(20)의 길이방향으로 기존 건축물(10)의 수평보(30) 저면과 제1 작업공간(100)의 바닥면에 해당하게 상부강관(200) 및 하부강관(300)을 각각 압입 시공한다.4, in the first work space 100, the bottom surface of the horizontal beam 30 of the existing building 10 and the bottom surface of the first work space 100 are arranged in the longitudinal direction of the outer wall 20, (200) and the lower steel pipe (300).

이때, 상,하부강관(200)(300)의 압입 방법으로는, 본 발명 출원인에 의해 제안된 특허출원등록 제10-1070678호에서와 같이 유압실린더 및 유압잭을 이용하여 선도관및 강관을 압입하는 방식을 적용할 수 있는 것으로, 일 예로 하부강관(300)의 압입상태를 살펴보면,As a method of pressing the upper and lower steel pipes 200 and 300, as shown in Patent Application No. 10-1070678 proposed by the applicant of the present invention, a leading pipe and a steel pipe are press-fitted using a hydraulic cylinder and a hydraulic jack For example, when the press-fitting state of the lower steel pipe 300 is examined,

먼저, 작업공간 내에서 외벽(20)의 길이방향 일측 토류벽(120)에는 유압실린더(40)가 설치되고 그 유압실린더(40)의 추진력에 의해 선도관(41)이 먼저 압입된다.First, a hydraulic cylinder 40 is installed in the toothed wall 120 on one side in the longitudinal direction of the outer wall 20 in the work space, and the leading pipe 41 is first press-fitted by the driving force of the hydraulic cylinder 40.

이후, 유압실린더(40)가 후퇴한 상태에서 압입된 선도관(41)의 후미에는 그 내측으로 하부강관(300)이 내입되는 한편, 유압잭(42)에 의해 연결된다. Thereafter, the lower steel pipe 300 is inserted into the rear end of the leading pipe 41, which is press-fitted while the hydraulic cylinder 40 is retracted, and is connected by the hydraulic jack 42.

이후, 유압실린더(40)의 추진력에 의해 하부강관(300)을 압입시키면 되는 것으로, 이에 그 하부강관(300)과 연결된 선도관(41)도 함께 1차 압입되는 것이고, 이후 유압잭(42)에 의해 선도관(41)을 2차로 더 압입시키게 된다.Thereafter, the lower pipe 300 is pressed by the driving force of the hydraulic cylinder 40, so that the leading pipe 41 connected to the lower pipe 300 is also firstly press-fitted together. Then, the hydraulic jack 42 The guide pipe 41 is further press-fitted into the second pipe.

이후, 상기와 같이 압입된 하부강관(300)의 후미에는 또 다른 하부강관(300)이 연속하여 용접 연결되는 것이고, 각각의 하부강관(300)을 연결시마다 전기한 바와 같이 1차 압입과 2차 압입을 연속 수행하면 된다.Thereafter, another lower steel pipe 300 is continuously welded and connected to the rear of the lower steel pipe 300. When each of the lower steel pipes 300 is connected, the first and second press- The press-fitting can be continuously performed.

여기서, 상기와 같이 상,하부강관(200)(300)을 시공하기 위해서는 그 상,하부강관(200)(300)이 압입되는 측의 토류벽(120)은 제거함이 바람직하다.In order to construct the upper and lower steel pipes 200 and 300 as described above, it is preferable to remove the toe wall 120 on the side where the upper and lower steel pipes 200 and 300 are inserted.

한편, 강관 압입단계(S200)에서, 압입되는 상부강관(200)은, 기존 건축물(10)의 수평보(30)의 저면으로부터 이격되는 위치에 압입함이 바람직한 것으로, 이는, 상부강관(200) 압입 과정에서 수평보(30)가 파손되는 것을 방지하기 위한 것이며, 그 이격공간에는 수평보(30) 저면과 상부강관(200)의 상부면을 지지하는 H빔블록(250)을 설치함으로 수평보(30)를 지지할 수 있다.In the steel pipe press-in step S200, the press-fitted upper steel pipe 200 is preferably press-fitted into a position spaced apart from the bottom surface of the horizontal beam 30 of the existing building 10, The H beam block 250 supporting the bottom surface of the horizontal beam 30 and the upper surface of the upper steel pipe 200 is installed in the spacing space to prevent the horizontal beam 30 from being damaged during the press- (30).

이후, 철판 설치단계(S300)를 수행하되,Thereafter, the steel plate installation step S300 is performed,

도 5는 본 발명 지하주차장 증축을 위한 지하 벽체 시공공법의 철판 설치단계를 나타낸 측 단면도이고, 도 6은 본 발명 지하주차장 증축을 위한 지하 벽체 시공공법의 철판 설치단계를 나타낸 정 단면도이다.FIG. 5 is a side sectional view showing a step of installing an iron plate in an underground wall construction method for enlarging an underground parking lot according to the present invention, and FIG. 6 is a front sectional view showing a step of installing an iron plate in an underground wall construction method for enlarging an underground parking lot according to the present invention.

철판 설치단계(S300)는, 압입된 상부강관(200)과 하부강관(300)을 철판(350)을 이용하여 서로 연결하는 것으로, 이때, 철판(350) 설치방법으로는, 본 발명 출원인에 의해 제안된 특허출원등록 제10-1069705호에서와 같이 유압잭을 이용한 철판 압입 방식을 적용할 수 있다.In the steel plate installing step S300, the press-fitted upper steel pipe 200 and the lower steel pipe 300 are connected to each other by using the steel plate 350. At this time, as a method of installing the steel plate 350, It is possible to apply a steel plate indentation method using a hydraulic jack as in the proposed patent application No. 10-1069705.

먼저, 도 5의 도시와 같이 압입된 상,하부강관(200)(300)의 내부 토사를 제거한 후, 상부강관(200)과 하부강관(300)을 절개하여 절개홈(210)(310)을 각각 형성하면 된다.5, the inner soil of the upper and lower steel pipes 200 and 300 is removed and then the upper and lower steel pipes 200 and 300 are cut to form the cutout grooves 210 and 310 Respectively.

이때, 절개홈(210)(310) 형성시에는 상,하부강관(200)(300)의 중심을 기준으로 하여 기존 건축물(10)의 외측을 향하게 치우치도록 형성함이 바람직하며, 상부강관(200)에는 그 저면 일측에 절개홈(210)을 형성하면 되는 것이고, 하부강관(300)에는 그 상부면 일측에 절개홈(310)을 설치하면 되는 것이며, 상기 절개홈(210)(310)은 서로 대항되는 형태를 이루게 된다.At the time of forming the cutouts 210 and 310, the upper and lower steel pipes 200 and 300 are preferably formed so as to be offset toward the outside of the existing building 10 with respect to the center of the upper and lower steel pipes 200 and 300, The incision grooves 210 and 310 may be formed on one side of the upper surface of the lower steel pipe 300 and the incision grooves 310 may be formed on the upper surface of the lower steel pipe 300, They form a form against each other.

이후, 도 6의 도시와 같이 그 일측 철판(350) 설치에 따른 실시예에 따라 상기 대항되는 절개홈(210)(310)에는 상,하부강관(200)(300)을 연결하는 철판(350)이 압입되는 것으로, 그 절개홈(210)(310)에 철판(350)이 내입된 상태에서 유압잭(52)을 이용하여 철판(350)을 압입 추진시키면 되는 것이고, 추진되어 발생한 후측에는 또 다른 철판(350)을 용접 연결 및 유압잭(52)을 이용하여 연속하여 압입하면 되는 것이고, 압입된 철판(350)은 그 외측에서 상,하부강관(200)(300)과 용접 연결하면 된다.6, an iron plate 350 for connecting the upper and lower steel pipes 200 and 300 is formed in the corresponding cut-off groove 210 and 310 according to the embodiment of the one-side iron plate 350, The steel plate 350 is pressed by using the hydraulic jack 52 in a state in which the steel plate 350 is inserted into the cutout grooves 210 and 310. After the steel plate 350 is propelled, The press-fitted steel plate 350 may be welded to the upper and lower steel pipes 200 and 300 from the outside thereof.

이후, 제2 작업공간 굴착단계(S400)을 수행하되,Thereafter, a second workspace excavation step (S400) is performed,

도 7은 본 발명 지하주차장 증축을 위한 지하 벽체 시공공법의 제2 작업공간 굴착단계를 나타낸 측 단면도이다.7 is a side cross-sectional view illustrating a second work space excavation step of an underground wall construction method for enlarging an underground parking lot of the present invention.

도 7의 도시와 같이 기존 건축물(10)의 내측에서 지면 굴착을 수행하여 제2 작업공간(400)을 형성하기 위한 것으로, 상기와 같이 굴착 형성된 제2 작업공간(400)은 상기 제1 작업공간 굴착단계(S100)에서 형성된 제1 작업공간(100)과 연결되게 함이 바람직한 것이며, 이때 연결부의 토류벽(120)은 제거함이 바람직하다.As shown in FIG. 7, the second work space 400 is excavated from the inside of the existing building 10 to form the second work space 400. The second work space 400, which is excavated as described above, It is preferable to connect the first work space 100 formed in the excavation step S100 and the toe wall 120 of the connection part is preferably removed.

이후, 강관 절단단계(S500)을 수행하되,Thereafter, the steel pipe cutting step S500 is performed,

도 8은 본 발명 지하주차장 증축을 위한 지하 벽체 시공공법의 강관 절단단계를 나타낸 측 단면도이다.8 is a side cross-sectional view showing a step of cutting a steel pipe in an underground wall construction method for enlarging an underground parking lot of the present invention.

도 8의 도시와 같이 2차 작업공간(400) 내에서 상부강관(200) 및 하부강관(300)의 일부 절단을 수행하면 되는 것으로, 각각의 상,하부강관(200)(300)의 절단 범위는 상기 철판(350)의 상,하단부로부터 그 철판(350)을 수직으로 하여 기존 건축물(10)의 외측에 해당하는 부분은 남겨두고 기존 건축물(10)의 내측에 해당하는 부분을 절개하여 제거하면 되는 것이다.Cutting of the upper steel pipe 200 and the lower steel pipe 300 is performed in the secondary work space 400 as shown in FIG. 8, so that the cutting range of each of the upper and lower steel pipes 200 and 300 The portion corresponding to the inner side of the existing building 10 is cut off and removed from the upper and lower ends of the steel plate 350 with the steel plate 350 vertically and leaving a portion corresponding to the outside of the existing building 10 .

여기서, 상,하부강관(200)(300)을 절단 제거하는 과정에서 수평보(30)와 상부강관(200) 사이에 설치된 H빔블록(250)은 제거함이 바람직하다.It is preferable that the H beam block 250 installed between the horizontal beam 30 and the upper steel pipe 200 is removed in the process of cutting and removing the upper and lower steel pipes 200 and 300.

한편, 강관 절단단계(S500)에서 상기 제1 작업공간(100)과 제2 작업공간(400)의 바닥면에 지반 보강작업(S500a)을 추가로 더 수행할 수 있는 것인데, 여기서 지반 보강작업(S500a)은 지반의 보강과 기존 건축물(10)의 지지력을 확보하기 위한 것으로, 그 보강방법으로는 H빔이나 콘크리트재의 보강파일(70)이나 콘크리트 파일을 이용한 보강이나 시멘트 그라우팅(80)을 이용한 보강방법을 적용할 수 있다.In the steel pipe cutting step S500, the ground reinforcement work S500a may be further performed on the bottom surfaces of the first work space 100 and the second work space 400. Here, S500a) is used to reinforce the ground and to secure the supporting force of the existing building 10. The reinforcement method includes reinforcing pile 70 of H beam or concrete material or reinforcement using concrete pile or reinforcement using cement grouting 80 Method can be applied.

이후, H빔 설치단계(S600)를 수행하되,Thereafter, an H beam installation step (S600) is performed,

도 9는 본 발명 지하주차장 증축을 위한 지하 벽체 시공공법의 H빔 설치단계를 나타낸 측 단면도이고, 도 10은 지하주차장 증축을 위한 지하 벽체 시공공법의 H빔 설치단계를 나타낸 정 단면도이다.FIG. 9 is a side sectional view showing an H beam installation step of an underground wall construction method for enlarging an underground parking lot of the present invention, and FIG. 10 is a front sectional view showing an H beam installation step of an underground wall construction method for enlarging an underground parking lot.

도 9 및 도 10의 도시와 같이 H빔(600)을 이용하여 기존 건축물(10)의 하중으로부터 견고히 지지할 수 있는 것으로, 이때 사용되는 H빔(600)은 통상의 중간부에 길이조절용 자키(610)가 형성된 것을 사용함이 바람직하며, 그 설치되는 H빔(600)은, 1차 작업공간(100)과 2차 작업공간(400)에서 수평보(30)의 저면으로 일정간격을 두고 설치된다.9 and 10, the H beam 600 can be firmly supported from the load of the existing building 10. The H beam 600 used at this time is provided with a length adjusting jockey The H beams 600 are installed at regular intervals on the bottom surface of the horizontal beam 30 in the primary work space 100 and the secondary work space 400 .

즉, H빔(600)을 설치시에는 그 상단이 수평보(30)의 저면에 지지되고, 그 하단이 제1 작업공간(100) 및 제2 작업공간(400)의 바닥면에 지지되도록 설치하면 된다.That is, when the H beam 600 is installed, the upper end of the H beam 600 is supported on the bottom surface of the horizontal beam 30, and the lower end of the H beam 600 is supported on the bottom surface of the first work space 100 and the second work space 400 .

이후, 벽체 완성단계(S700)를 수행하되,Thereafter, the wall completion step S700 is performed,

도 11은 본 발명 지하주차장 증축을 위한 지하 벽체 시공공법의 벽체 완성단계를 나타낸 측 단면도이다.11 is a side cross-sectional view showing a wall finishing step of an underground wall construction method for enlarging an underground parking lot according to the present invention.

도 11의 도시와 같이 벽체(700)을 완성하기 위한 것으로, 벽체(700)를 완성하기 위해서는 조적용 벽돌(710)을 이용하여 조적 방식을 적용하여 이루게 되는 것이다.11, the wall 700 is completed. In order to complete the wall 700, a masonry system is applied by using the masonry bricks 710.

즉, 벽돌(710)을 이용하여 벽체(700)를 형성하되, 제1,2 작업공간의 바닥면으로부터 기존 건축물(10)의 수평보(30) 저면에 이르게 벽돌(710)을 조적하여 형성하면 되는 것이며, 이때, 상기 H빔 설치단계(S600)에서 설치된 H빔(600)은 제거하지 않은 상태에서 벽돌(710)에 묻히도록 하면 되는 것으로, 이는 철근 콘크리트 방식이 아닌 벽돌 조적방식을 적용하더라도 H빔(600)에 의해 충분한 건축물 지지력을 확보할 수 있는 것이다.That is, the brick 710 is used to form the wall 700. When the brick 710 is formed by joining the brick 710 to the bottom surface of the horizontal beam 30 of the existing building 10 from the bottom surface of the first and second work spaces The H beam 600 installed in the H beam installation step S600 may be buried in the brick 710 without being removed. This is because, even if a brick masonry method is applied instead of a reinforced concrete method, The beam 600 can secure a sufficient building supporting force.

또한, 상기와 같이 조적을 수행시 조적되는 벽돌(710)의 일측은 철판(350)과 밀착되게 수행함이 바람직한 것으로, 이때, 철판(350)은 방수 기능을 수행할 수 있는 것이다.In addition, it is preferable that one side of the brick 710 to be assembled when performing the assembly is closely attached to the steel plate 350, and the steel plate 350 can perform a waterproof function.

이후, 상기와 같이 조적 형성된 벽체(700)의 노출된 표면에는 시멘트를 이용한 마감몰탈(720)을 수행함으로 완성된 벽체를 이룰 수 있는 것이다.Thereafter, a finished mortar 720 made of cement is formed on the exposed surface of the wall 700 formed as described above, thereby completing the wall.

한편, 상기와 같이 벽체(700)를 시공하는 과정에서 그 벽체(700)의 하단에 새로운 수평보(730)을 더 형성할 수 있는 것으로, 수평보(730) 형성시에는 상기 벽체(700) 시공시에 앞서 조적방식에 의해 시공하되, 벽체(700)보다 두꺼운 두께로 시공함이 바람직하다.A new horizontal beam 730 may be further formed at the lower end of the wall 700 in the process of constructing the wall 700. When the horizontal beam 730 is formed, It is preferable that the wall 700 is formed to have a thickness greater than that of the wall 700.

이상과 같이 상기에서 설명한 본 발명 벽체 연장 시공공법은, 그 실시예로써, 건축물을 이루는 다수의 벽체면 중 그 일면을 기준으로 설명한 것으로, 타 면을 시공시에는 동일한 공법을 적용할 수 있는 것이다. As described above, the wall extension method of the present invention described above is based on one side of a plurality of wall surfaces constituting a building, and the same method can be applied to the other side when constructing the other side.

또한, 상기와 같이 벽체를 연장 시공시 다수의 지하층을 구성시에는 상기와 같은 공정을 연속 시공하면 되는 것이데, 이때, 상기 지반 보강작업은 최 하단에 해당하는 제1,2 작업공간(100)(400)에서 수행함이 바람직하다.When a plurality of basement layers are formed during the extension of the wall, the above-mentioned processes may be continuously performed. In this case, the ground reinforcement work may be performed in the first and second work spaces 100, (400).

한편, 상기와 같은 일련의 시공단계를 통해 지하 벽체를 완성 시공 후, 작업공간 굴착단계(S100)에서 형성된 제1 작업공간(100)의 외측에 해당하는 부분은 되메움하는 한편, 완성된 벽체(700)의 내측에 해당하는 지반은 굴착하여 지하공간을 이룸은 자명한 사실이다.After completing the construction of the underground wall through the series of construction steps as described above, the portion corresponding to the outside of the first work space 100 formed in the work space excavation step (S100) is backfilled, while the completed wall 700) is excavated to form an underground space.

이상에서와 같이 본 발명 지하주차장 증축을 위한 지하 벽체 시공공법은, 토류벽 시공에 따른 공간확보와 H빔을 이용한 건축물 지지력 확보와 강관 및 철판을 이용한 보강 및 방수시공이 가능하여 시공상의 편리함과 건축물의 안정성의 확보된 상태의 시공이 가능한 것이다.
As described above, the underground wall construction method for enlarging the underground parking lot according to the present invention can secure the space according to the construction of the toothed wall, securing the supporting force of the building using the H beam, and reinforcing and waterproofing construction using steel pipes and steel plates, It is possible to construct a state in which stability is ensured.

10 : 기존 건축물 20 : 외벽
30 : 수평보
100 : 작업공간 101 : 작업구역
110 : H빔 120 : 토류벽
121 : 토류판 130 : 턴버클바
200,300 : 상,하부강관 210,310 : 절개홈
250 : H빔블록 350 : 철판
600 : H빔 700 : 벽체
710 : 벽돌 720 : 마감몰탈
10: existing building 20: outer wall
30: Horizontal beam
100: Workspace 101: Workspace
110: H beam 120:
121: turntable 130: turnbuckle bar
200, 300: upper and lower steel pipes 210, 310:
250: H beam block 350: Steel plate
600: H beam 700: Wall
710: Brick 720: Finishing mortar

Claims (5)

건축물 리모델링 공사시 지하주차장 증축을 위해 기존 건축물의 수평보 저면으로 지하 벽체를 연결 시공하는 벽체 시공공법에 있어서,
기존 건축물의 외벽 일측에서 그 외벽의 내측 및 외측을 연결하는 네 모서리에 H빔을 지면에 설치하여 작업구역을 설정하는 한편, 그 작업구역을 굴착하여 가면서 H빔에 지지되는 토류판을 이용한 토류벽을 시공 및 마주보는 토류벽은 턴버클바로 연결 지지하여 1차 작업공간을 확보하는 제1 작업공간 굴착단계(S100);
1차 작업공간의 상부에서 수평보의 저면으로부터 이격되는 위치에 상부강관을 압입하되, 수평보와 상부강관의 이격공간에는 수평보의 저면과 상부강관의 상부면을 지지하는 H빔블록을 더 설치하며, 1차 작업공간의 하부에서 외벽의 길이방향으로 1차 작업공간의 바닥면에 해당하게 하부강관을 압입하는 강관 압입단계(S200);
압입된 상,하부강관의 내부 토사를 제거한 후, 상부강관의 저면과 하부강관의 상부면에 건축물의 벽체 외측으로 치우치는 한편 서로 대항되는 형태로 절개홈을 각각 형성하되, 상,하 대항되는 절개홈을 따라 양측으로 철판을 압입하고, 강관과 철판을 용접 결합하는 철판 설치단계(S300);
건축물의 내부에서 압입된 하부강관의 저면까지 굴착을 수행하여 상기 1차 작업공간과 연결되도록 2차 작업공간을 형성하는 제2 작업공간 굴착단계(S400);
상기 2차 작업공간내에서 상기 압입된 철판과 수직을 이루도록 상부강관 및 하부강관을 절개하는 강관 절단단계(S500);
기존 건축물의 하부에서 상단이 수평보 저면에 지지되고 하단이 1차 작업공간 및 2차 작업공간의 저면에 지지되도록 자키가 형성되어 길이조절이 가능한 다수의 H빔을 이용하여 수직 연결 지지하는 H빔 설치단계(S600); 및
상기 H빔이 설치된 상태에서 그 H빔이 묻히도록 제1,2 작업공간의 바닥면으로부터 건축물의 수평보 저면에 이르게 벽돌을 조적하여 벽체를 형성 및 마감몰탈을 수행하여 완성하는 벽체 완성단계(S700);를 포함하여 수행함을 특징으로 하는 지하주차장 증축을 위한 지하 벽체 시공공법.
In the wall construction method in which an underground wall is connected to a horizontal bottom surface of an existing building in order to enlarge an underground parking lot at the remodeling work of a building,
The H beam is installed on the ground at four corners connecting the inside and outside of the outside wall of the existing building from the outside wall of the existing building to construct a working area. And a first workspace excavation step (S100) for securing a primary work space by supporting a turning wall of the opposing toe wall,
An H beam block supporting the bottom surface of the horizontal beam and the upper surface of the upper steel pipe is further installed in the space between the horizontal beam and the upper steel pipe at a position spaced from the bottom surface of the horizontal beam at the upper part of the primary work space A step S200 of pressurizing the lower steel pipe corresponding to the bottom surface of the primary work space in the longitudinal direction of the outer wall at the lower part of the primary work space;
After the inner soil of the press-fitted upper and lower steel pipes is removed, the bottom surface of the upper steel pipe and the upper surface of the lower steel pipe are biased toward the outside of the wall of the building, (S300) for press-fitting the steel plate to both sides along the steel plate and welding the steel plate and the steel plate together;
A second work space excavation step (S400) of performing excavation from the inside of the building to the bottom surface of the lower steel pipe pressurized to form a secondary work space to be connected to the primary work space;
A steel pipe cutting step (S500) of cutting the upper steel pipe and the lower steel pipe perpendicularly to the press-fitted steel plate in the secondary work space;
The upper end of the H-beam is supported on the horizontal bottom surface of the existing structure and the lower end is supported on the bottom of the primary working space and the secondary working space by using a plurality of H- Installation step S600; And
A wall finishing step (S700) for finishing a wall by forming bricks and finishing mortar by joining the bricks to the horizontal bottom surface of the building from the bottom surface of the first and second work spaces so that the H beams are embedded in the H beams, ); ≪ / RTI > a method of constructing an underground wall structure for the extension of an underground parking lot.
삭제delete 삭제delete 제 1항에 있어서,
상기 강관 절단단계(S500)에서,
제1 작업공간과 제2 작업공간의 바닥면에 지반 보강작업(S500a)을 더 수행함을 특징으로 하는 지하주차장 증축을 위한 지하 벽체 시공공법.
The method according to claim 1,
In the steel pipe cutting step S500,
And a ground reinforcement operation (S500a) is further performed on the bottom surfaces of the first work space and the second work space.
제 1항에 있어서,
벽체 완성단계(S700)에서,
벽체의 하단에 수평보를 더 형성하여 수행함을 특징으로 하는 지하주차장 증축을 위한 지하 벽체 시공공법.
The method according to claim 1,
In the wall completion step S700,
And a horizontal beam is further formed at the lower end of the wall.
KR1020130029112A 2013-03-19 2013-03-19 Mehod for constructing underground wall in extension of undergound parking lot KR101431623B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020130029112A KR101431623B1 (en) 2013-03-19 2013-03-19 Mehod for constructing underground wall in extension of undergound parking lot

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020130029112A KR101431623B1 (en) 2013-03-19 2013-03-19 Mehod for constructing underground wall in extension of undergound parking lot

Publications (1)

Publication Number Publication Date
KR101431623B1 true KR101431623B1 (en) 2014-08-21

Family

ID=51750769

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020130029112A KR101431623B1 (en) 2013-03-19 2013-03-19 Mehod for constructing underground wall in extension of undergound parking lot

Country Status (1)

Country Link
KR (1) KR101431623B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104532867A (en) * 2014-12-25 2015-04-22 张继红 Composite-cavity steel pipe continuous wall and waterstop effect detection method thereof
CN105586975A (en) * 2016-02-29 2016-05-18 济南轨道交通集团有限公司 Integrated construction method for overlapping prefabricated guard post and structural wall
CN115977124A (en) * 2023-02-01 2023-04-18 甘肃省水利水电勘测设计研究院有限责任公司 Automatic dismantlement formula underwater supporting device based on hydrodynamic force

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008013926A (en) * 2006-07-03 2008-01-24 Takenaka Komuten Co Ltd Existing building foundation reinforcing method
KR101022382B1 (en) * 2010-08-16 2011-03-22 (주)정토지오텍 Precast horizontality tubular roof and tunnel construction method using the same
KR101069702B1 (en) * 2009-06-22 2011-10-04 주식회사 엔티에스이앤씨 Method for installing waterproofing steel plate and soil-drop preventing plate in construction of undergound tunnel

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2008013926A (en) * 2006-07-03 2008-01-24 Takenaka Komuten Co Ltd Existing building foundation reinforcing method
KR101069702B1 (en) * 2009-06-22 2011-10-04 주식회사 엔티에스이앤씨 Method for installing waterproofing steel plate and soil-drop preventing plate in construction of undergound tunnel
KR101022382B1 (en) * 2010-08-16 2011-03-22 (주)정토지오텍 Precast horizontality tubular roof and tunnel construction method using the same

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104532867A (en) * 2014-12-25 2015-04-22 张继红 Composite-cavity steel pipe continuous wall and waterstop effect detection method thereof
CN105586975A (en) * 2016-02-29 2016-05-18 济南轨道交通集团有限公司 Integrated construction method for overlapping prefabricated guard post and structural wall
CN105586975B (en) * 2016-02-29 2017-12-19 济南轨道交通集团有限公司 The integrated structure and construction method that prefabricated fender post is superimposed with structural wall
CN115977124A (en) * 2023-02-01 2023-04-18 甘肃省水利水电勘测设计研究院有限责任公司 Automatic dismantlement formula underwater supporting device based on hydrodynamic force
CN115977124B (en) * 2023-02-01 2023-09-01 甘肃省水利水电勘测设计研究院有限责任公司 Automatic dismantlement formula is strutting arrangement under water based on hydrodynamic force

Similar Documents

Publication Publication Date Title
KR101069705B1 (en) Method for installing waterproofing steel plate in construction of undergound tunnel
KR102071225B1 (en) Construction method of sheathing temporary facility using steel sheet pile
KR100855098B1 (en) Strut structure as temporary system using a vertical truss at the end and the method thereof
WO2011114507A1 (en) Method of constructing underground structure to be newly built
KR101040066B1 (en) Method of constructing non-excavation type tunnel
JP2012107479A (en) Method for constructing underground and aboveground structure
KR20070075506A (en) Construction method of underground structure using concrete filled pipe roof and concrete wall
KR100313720B1 (en) Composite Underground Structure Construction Method
KR101431623B1 (en) Mehod for constructing underground wall in extension of undergound parking lot
JP2016528406A (en) Beam connection structure of temporary retaining works for earth retaining
KR20070076553A (en) Construction method of underground structure using concrete filled pipe roof and concrete wall
KR101431621B1 (en) Mehod for constructing underground wall in extension of undergound parking lot
KR101069702B1 (en) Method for installing waterproofing steel plate and soil-drop preventing plate in construction of undergound tunnel
KR101387954B1 (en) Mehod for constructing underground wall in extension of undergound parking lot
JP2004263467A (en) Reconstruction method using existing underground skeleton
JP2001349065A (en) Underground base isolating construction method for existing building
KR20020007521A (en) method for underground construction of building by using permanent structural member as strut for support retaining wall
KR20200091114A (en) Construction method of underground tunnel forming structure
KR101372334B1 (en) Mehod for constructing underground wall in extension of undergound parking lot
KR101128955B1 (en) The Construction Method of Pressing Underground Structure
JPH11310928A (en) Vibration isolation reinforcing method for existing structure
KR100767953B1 (en) Separating method of Monowall with spandrel girders
KR101217488B1 (en) Extension structure of pile foundation
JP2010084460A (en) Construction method for underground structure
KR20210098162A (en) Under ground structure using column steel pipe wall and construction method thereof

Legal Events

Date Code Title Description
A201 Request for examination
N231 Notification of change of applicant
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20170811

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20190211

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20190812

Year of fee payment: 6