KR101372261B1 - Box form structure for culvert construction - Google Patents

Box form structure for culvert construction Download PDF

Info

Publication number
KR101372261B1
KR101372261B1 KR1020130007257A KR20130007257A KR101372261B1 KR 101372261 B1 KR101372261 B1 KR 101372261B1 KR 1020130007257 A KR1020130007257 A KR 1020130007257A KR 20130007257 A KR20130007257 A KR 20130007257A KR 101372261 B1 KR101372261 B1 KR 101372261B1
Authority
KR
South Korea
Prior art keywords
formwork
fixing member
culvert
coupled
concrete
Prior art date
Application number
KR1020130007257A
Other languages
Korean (ko)
Inventor
한우람
성원석
이창범
Original Assignee
현대알루미늄(주)
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 현대알루미늄(주) filed Critical 현대알루미늄(주)
Priority to KR1020130007257A priority Critical patent/KR101372261B1/en
Application granted granted Critical
Publication of KR101372261B1 publication Critical patent/KR101372261B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01FADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
    • E01F5/00Draining the sub-base, i.e. subgrade or ground-work, e.g. embankment of roads or of the ballastway of railways or draining-off road surface or ballastway drainage by trenches, culverts, or conduits or other specially adapted means
    • E01F5/005Culverts ; Head-structures for culverts, or for drainage-conduit outlets in slopes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0258Retaining or protecting walls characterised by constructional features
    • E02D29/0275Retaining or protecting walls characterised by constructional features cast in situ
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/34Horizontally-travelling moulds for making walls blockwise or section-wise
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • E21D11/083Methods or devices for joining adjacent concrete segments

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Mechanical Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • Sewage (AREA)

Abstract

The present invention relates to a box form structure for constructing a culvert which is provided not only to construct a concrete culvert continuously as well as sturdily enough to bear distributed load, the box form structure comprising: outer form materials which are disposed on the right and left sides of a concrete culvert respectively before construction and which maintain a fixed interval therebetween to construct outer wall units of the concrete culvert; inner form materials which are positioned in between the outer form materials and spaced with a fixed interval apart from the outer form materials and which are installed to construct inner wall units of the concrete culvert; a form material-operating unit which has the inner form materials connected thereto in between the outer form materials, and which moves along a rail to construct the next concrete culvert after finishing the construction of the concrete culvert by being provided to separate the inner form materials of the inner wall units of the constructed concrete culvert from the inner wall units.

Description

암거 시공용 박스 폼 구조{box form structure for culvert construction}Box form structure for culvert construction

본 발명은 토목용 콘크리트 암거 시공에 관한 것으로서, 좀 더 구체적으로는 암거 시공용 박스 폼을 이용하여 분포하중을 충분히 지탱하도록 콘크리트 암거를 견고하게 시공할 뿐만 아니라 상기의 콘크리트 암거를 연속적으로 시공하도록 하는 암거 시공용 박스 폼 구조에 관한 것이다.
The present invention relates to the construction of civil concrete culverts, and more specifically, to construct the concrete culverts not only firmly but also to construct the concrete culverts continuously to sufficiently support the distribution load using the culvert box construction form. It relates to the box form structure for culvert construction.

일반적으로 토목 공사에서 적용되는 암거는, 대단위 택지 지구나 밀집 주택의 각종 빗물처리구나 하수구 및, 농공업용수의 수로는 물론 인도 및 차도 등의 통행로, 지하차도 또는, 전기통신구 및 지하 공동구, 저유조, 항만(부두), 플랜트, 하천, 댐 등 다양하게 사용되고 있다. The culverts generally applied in civil engineering work include rainwater treatment or sewerage in large residential districts and dense houses, waterways of agricultural and industrial waterways, passageways such as sidewalks and roadways, underground roadways, telecommunications zones, underground community areas, and oil tanks. It is used in various ways such as port, pier, plant, river and dam.

종래에는 철근 콘크리트로 제작된 강성벽체 형태의 구조물인 바닥판과 측판 및 상부판 등을 각각 제작하여 이를 현장에서 조립 작업 즉, 암거를 시공하고자 하는 위치의 지면에 바닥판을 깔고 나서 상기 바닥판의 양측면에 측판을 각각 결합한 다음 상기 각 측판의 상부에 상부판을 얹혀 놓은 상태에서 상기 상부판을 각 측판에 결합하는 상기 각 구조물 간의 조립 공정을 통해 암거를 시공한다. Conventionally, a bottom plate, a side plate, and a top plate, which are rigid wall-shaped structures made of reinforced concrete, are manufactured, respectively, and then assembled at the site, that is, the floor plate is laid on the ground at the position where the culvert is to be installed. The side plates are coupled to both sides, and the culvert is constructed through an assembly process between the respective structures for coupling the top plate to each side plate while the top plate is placed on the top of each side plate.

그러나, 이러한 종래의 암거 시공은 미리 제작된 구조물을 가져다가 현장에서 조립함에 따라 암거 시공에 따른 공기를 단축할 수 있으나, 재료의 비경제성 및 중량성을 갖는다는 재료의 특성상 구조물의 자중에 의한 많은 공학적 단점 즉, 성토층의 하중이 클수록 매설 암거의 크기도 비례하여 커져야 하기 때문에 경제적인 측면이나 시공 및, 제작적인 측면에서 많은 단점이 있었다. However, such a conventional culvert construction can take the prefabricated structure and shorten the air according to the culvert construction by assembling in the field, but due to the characteristics of the material that has the material economy and weight, Engineering disadvantages, namely, the greater the load of the fill layer, the larger the size of the buried culvert has to be proportionately larger, so there are many disadvantages in terms of economics, construction and production.

또한, 상기 구조물 간의 조립으로 시공된 암거는 성토 하중 및 교통 하중에 의한 분포하중(수평하중, 수직하중 등)을 충분히 지탱하지 못하는 문제가 있으며, 연약 지반 상에 시공된 암거는 연약 지반에서의 지반 침하 현상으로 인해 상기 구조물 간 연결부에서의 응력집중과 침하에 의해 상대 변위에 따른 추가 하중 및 암거 기초의 부동침하 등으로 인하여 암거가 파손되는 문제가 있었다. In addition, the culverts constructed by assembling between the structures have a problem that they do not sufficiently support the distribution loads (horizontal loads, vertical loads, etc.) due to the fill load and traffic load, and the culverts constructed on the soft ground are grounds on the soft ground. Due to the settlement phenomenon, there is a problem that the culvert is damaged due to the additional load and the immersion of the culvert foundation due to the stress concentration and settlement in the connection between the structures.

본 발명은 상기한 바와 같은 종래 기술에서의 문제점 해결하기 위하여 제안된 것으로서, 콘크리트 암거를 시공하기 위한 암거 시공용 박스 폼을 구비함으로써, 상기 암거 시공용 박스 폼에 의해 분포하중을 충분히 지탱할 수 있는 견고한 구조의 콘크리트 암거 시공이 용이하게 이루어질 뿐만 아니라 상기 암거 시공용 박스 폼의 용이한 설치 및 시공된 콘크리트 암거로부터 암거 시공용 박스 폼을 용이하게 분리하여 다음 공정으로의 이동가능함에 따라 상기 콘크리트 암거를 연속적으로 시공가능하도록 하는데 그 목적이 있다.
The present invention has been proposed to solve the problems in the prior art as described above, by having a culvert construction box form for constructing concrete culverts, a solid that can sufficiently support the distribution load by the culvert construction box form In addition to the easy construction of concrete culverts in the structure, easy installation of the culvert construction box form and easy separation of the culvert construction box form from the constructed concrete culverts, the concrete culvert can be continuously The purpose is to make it possible to construct.

상기한 바와 같은 목적을 달성하기 위한 본 발명은, 콘크리트 암거를 연속적으로 시공하기 위한 암거 시공용 박스 폼에 있어서, 상기 콘크리트 암거의 외측벽부를 시공하기 위해 시공 전 콘크리트 암거의 좌, 우측에 각각 설치되어 일정한 간격을 유지하는 외측거푸집부재; 상기 각 외측거푸집부재와 일정 간격으로 이격되도록 상기 각 외측거푸지부재 사이에 위치되어 상기 콘크리트 암거의 내측벽부를 시공하기 위해 설치되는 내측거푸집부재; 상기 각 외측거푸집부재 사이에는 상기 내측거푸집부재가 결합됨과 함께 시공된 콘크리트 암거의 내측벽부로부터 내측거푸집부재를 분리하도록 구비되어 콘크리트 암거 시공 완료 후 다음 콘크리트 암거의 시공을 위해 레일을 따라 이동하는 거푸집부재작동장치부;가 구비되되, 상기의 거푸집부재작동장치부는, 상기 내측거푸집부재가 결합되는 복수 개의 거푸집고정부재와, 상기 거푸집고정부재의 내측에 설치되어 거푸집고정부재를 지지 고정하는 프레임부와, 상기 각 거푸집고정부재와 프레임부 사이에 결합되어 콘크리트 암거의 내측벽부를 시공 및 콘크리트 암거의 내측벽부로부터 내측거푸집부재를 분리하도록 상기 거푸집고정부재를 왕복 이동시키도록 하는 복수 개의 유압실린더와, 상기 각 거푸집고정부재와 프레임부 사이에 결합 설치되어 상기 각 거푸집고정부재를 지지하도록 복수 개의 브레이징과, 상기 프레임부의 하부에 회전가능하게 결합되어 레일을 따라 거푸집부재작동장치부를 이동시키는 복수 개의 바퀴로 구성됨을 특징으로 하는 암거 시공용 박스 폼 구조가 제공된다.
The present invention for achieving the object as described above, in the culvert construction box form for continuously constructing concrete culverts, respectively installed on the left and right of the concrete culverts before construction to construct the outer wall portion of the concrete culvert Outer formwork member to maintain a constant interval; An inner formwork member disposed between the outer formwork members so as to be spaced apart from the outer formwork members at predetermined intervals and installed to construct an inner wall portion of the concrete culvert; The inner formwork member is coupled between each outer formwork member and provided to separate the inner formwork member from the inner wall portion of the constructed concrete culvert, and the formwork moves along the rail for the construction of the next concrete culvert after completion of the concrete culvert construction. And a member operating device unit, wherein the form member operating device unit includes a plurality of formwork fixing members to which the inner formwork members are coupled, and a frame portion installed inside the formwork fixing member to support and fix the formwork fixing member. A plurality of hydraulic cylinders coupled between each of the die fixing members and the frame portion to construct the inner wall of the concrete culvert and to reciprocate the form fixing member to separate the inner form member from the inner wall of the concrete culvert; It is installed coupled between each die fixing member and the frame portion The ergonomic box form structure is characterized by consisting of a plurality of brazing to support each of the formwork fixing members, and a plurality of wheels rotatably coupled to the lower portion of the frame portion to move the formwork member operating unit along the rail Is provided.

상기에서 설명한 바와 같이 이루어진 본 발명에 따르면, 외측거푸집부재와, 내측거푸집부재 및, 거푸집고정부재와 프레임부와 유압실린더 및 브레이징과 바퀴로 구성된 거푸집부재작동장치부가 구비된 암거 시공용 박스 폼으로 콘크리트 암거를 시공함으로써, 상기 암거 시공용 박스 폼에 의해 콘크리트 암거를 보다 용이하면서도 견고한 구조의 콘크리트 암거를 시공할 수 있을 뿐만 아니라 상기 견고한 구조의 콘크리트 암거는 성토 하중 및 교통 하중에 의한 분포하중(수평하중, 수직하중 등)을 충분히 지탱함은 물론 콘크리트 암거와 콘크리트 암거 간의 연결부에서의 응력집중과 침하에 의한 상태 변위에 따른 추가 하중 및 부동침하를 지탱함에 따라 상기 시공된 콘트리트 암거가 손상이나 파손되는 것을 방지하는 효과가 있다. According to the present invention made as described above, the concrete in the culvert construction box form with the outer formwork member, the inner formwork member, the formwork fixing member, the frame portion, the hydraulic cylinder and the formwork member operating device portion consisting of brazing and wheels By constructing the culvert, the concrete culvert can be easily and rigidly constructed by the culvert construction box form, and the concrete culvert of the rigid structure is distributed load due to the fill load and traffic load (horizontal load). Not only fully supporting the vertical loads, but also supporting the loads and floating settlements caused by stress concentrations and settlements caused by settlements at the connection between concrete culverts and concrete culverts. It is effective to prevent.

또한, 암거 시공용 박스 폼의 설치가 매우 용이하여 콘크리트 암거를 보다 바른 시간에 용이하고 신속하면서도 안전하게 시공할 수 있을 뿐만 아니라 상기 콘크리트 암거의 시공에 따른 작업 인력이나 시간 등을 절감함에 따라 상기 콘크리트 암거의 시공에 따른 작업 효율성 향상 및, 시공 비용 절감은 물론 콘크리트 암거의 시공 기간을 단축할 수 있는 효과도 있다. In addition, the installation of the culvert box form is very easy, so that the concrete culvert can be installed easily, quickly and safely at the right time, and the concrete culvert according to saving work manpower or time according to the construction of the concrete culvert Work efficiency is improved and construction cost is reduced, and the construction period of concrete culvert can be shortened.

그리고, 시공된 콘크리트 암거로부터 암거 시공용 박스 폼을 간편하고 용이하면서도 빠르게 분리 즉, 해체함에 따라 상기 암거 시공용 박스 폼의 해체작업에 따른 작업 효율성이 향상될 뿐만 아니라 상기 암거 시공용 박스 폼을 다음 공정으로 이동가능하여 상기 콘크리트 암거를 연속적으로 시공가능한 효과도 있다. In addition, the culvert construction box form from the constructed concrete culvert can be easily, easily and quickly separated, that is, dismantling, as well as the work efficiency according to the dismantling operation of the culvert construction box form, as well as following the culvert construction box form. There is also an effect that can be moved to the process to be able to continuously construct the concrete culvert.

한편, 암거 시공용 박스 폼의 외측거푸집부재 및 내측거푸집부재의 구조 변경 및 설계 변경이 용이하여 다양한 형태의 구조물 시공이 가능할 뿐만 아니라 상기 암거 시공용 박스 폼을 여러 번 사용할 수 있음에 따라 장기적인 사용이 가능함은 물론 재료의 손실 및 시공 비용을 절감할 수 있는 효과도 있다.
On the other hand, it is easy to change the structure and design of the outer formwork member and the inner formwork member of the culvert box form not only possible to construct a variety of structures, but also to use the culvert box form for a long time use Not only is it possible, but it also has the effect of reducing material loss and construction costs.

도 1은 본 발명 암거 시공용 박스 폼 구조를 나타낸 구조도.
도 2는 본 발명 암거 시공용 박스 폼이 설치된 상태를 나타낸 정면도.
도 3은 본 발명 암거 시공용 박스 폼을 평면에서 본 상태의 평면도.
도 4는 본 발명 암거 시공용 박스 폼에서 내측거푸집부재가 결합된 거푸집부재작동장치부를 측면에서 나타낸 측면도.
도 5 내지 도 8은 본 발명 콘크리트 암거 시공 및 콘크리트 암거로부터 박스 폼을 분리하는 상태를 순차적으로 도시한 시공 상태도.
1 is a structural diagram showing the structure of the present invention culvert box form.
Figure 2 is a front view showing a state of the present invention installed culvert box form.
Figure 3 is a plan view of the present invention culvert construction box form viewed from the plane.
Figure 4 is a side view showing the formwork member operating unit coupled to the inner formwork member in the present invention culvert box form.
5 to 8 is a construction state sequentially showing a state of separating the box form from the concrete culvert construction and concrete culvert of the present invention.

이하, 본 발명에 따른 암거 시공용 박스 폼 구조는 첨부된 도 1 내지 도 8을 참조하여 보다 구체적으로 설명하면 다음과 같다. Hereinafter, the culvert construction box form structure according to the present invention will be described in more detail with reference to FIGS. 1 to 8 as follows.

본 발명은, 대단위 택지 지구나 밀집 주택의 각종 빗물처리구나 하수구 및, 농공업용수의 수로는 물론 인도 및 차도 등의 통행로, 지하차도 또는, 전기통신구 및 지하 공동구, 저유조, 항만(부두), 플랜트, 하천, 댐 등 다양하게 사용되는 콘크리트 암거를 견고하게 시공함은 물론 상기의 콘크리트 암거를 연속적으로 시공하기 위한 암거 시공용 박스 폼이 구비되어 있다. The present invention provides a variety of rainwater treatment and sewerage in large residential land districts and dense houses, passages such as sidewalks and driveways, underground roadways or telecommunications, underground troughs, oil tanks, ports (piers), The culvert construction box box for the continuous construction of the concrete culvert as well as the concrete culvert used in various plants, rivers, dams, etc. are installed.

상기 암거 시공용 박스 폼은 도 1 내지 도 4에서와 같이, 상기 콘크리트 암거의 외측벽부를 시공하기 위해 시공 전 콘크리트 암거의 좌, 우측에는 일정한 간격으로 이격된 상태를 유지하는 외측거푸집부재(10)가 각각 설치되어 있다. The culvert construction box form, as shown in Figures 1 to 4, the outer formwork member 10 for maintaining the spaced apart at regular intervals on the left and right sides of the concrete culvert before construction to construct the outer wall portion of the concrete culvert Each is installed.

상기 각 외측거푸집부재(10) 사이에는 상기 각 외측거푸집부재(10)와 일정 간격으로 이격되도록 위치되어 상기 콘크리트 암거의 내측벽부를 시공하기 위한 내측거푸집부재(20)가 설치되어 있다. The inner formwork member 20 is installed between the outer formwork members 10 to be spaced apart from the outer formwork members 10 at regular intervals to construct the inner wall portion of the concrete culvert.

상기 각 외측거푸집부재(10) 사이에는 상기 내측거푸집부재(20)가 결합됨과 함께 시공된 콘크리트 암거의 내측벽부로부터 내측거푸집부재(20)를 분리하도록 함은 물론 상기 콘크리트 암거 시공 완료 후 다음 콘크리트 암거의 시공을 위해 레일(40)을 따라 이동하도록 하는 거푸집부재작동장치부(30)가 구비되어 있다. The inner formwork member 20 is coupled between each of the outer formwork members 10, and the inner formwork member 20 is separated from the inner wall portion of the concrete culvert that is constructed, as well as the next concrete after completion of the concrete culvert construction. Formwork member operating unit 30 is provided to move along the rail 40 for the construction of the culvert.

상기 각 외측거푸집부재(10)의 외측면에는 외측거푸집부재(10)에서 작업자가 작업 및 이동할 수 있도록 적어도 하나 이상의 안전발판부(110)가 각각 설치되어 있고, 상기 각 외측거푸집부재(10)에는 상기 외측거푸집부재(10)가 쓰러지거나 넘어지지 않도록 지면으로부터 외측거푸집부재(10)를 지지 고정하도록 하는 복수 개의 외측지지바(120)가 각각 결합되어 있다. At least one safety scaffold 110 is provided on an outer surface of each of the outer mold members 10 to allow an operator to work and move on the outer mold member 10, and each of the outer mold members 10 is provided on the outer surface of the outer mold member 10. A plurality of outer support bars 120 are coupled to each other to support the outer formwork member 10 from the ground so that the outer formwork member 10 does not fall or fall.

상기 각 외측거푸집부재(10) 사이에는 상기 각 외측거푸집부재(10)를 서로 연결함은 물론 각 외측거푸집부재(10) 간의 간격을 일정하게 유지하는 복수 개의 제1간격유지부재(131)가 결합되어 있고, 상기 각 외측거푸집부재(10)과 상기 내측거푸집부재(20)의 측부 사이에는 각 외측거푸집부재(10)와 내측거푸집부재(20)를 서로 연결함은 물론 상기 각 외측거푸집부재(10)와 내측거푸집부재(20) 간의 간격을 일정하게 유지하는 복수 개의 제2간격유지부재(132)가 결합되어 있다. A plurality of first interval maintaining members 131 are coupled between the outer formwork members 10 to connect the outer formwork members 10 to each other, as well as to maintain a constant distance between the outer formwork members 10. The outer formwork member 10 and the inner formwork member 20 are connected to each other between the outer formwork member 10 and the inner formwork member 20, as well as the respective outer formwork members 10. ) And a plurality of second interval maintaining members 132 for maintaining a constant gap between the inner mold member 20 and the inner mold member 20.

상기 내측거푸집부재(20)의 양측 하부에는 상기 콘크리트 암거의 내측벽부 하부를 시공 및 시공된 후 암거의 내측벽부 하부로부터 분리되도록 일정 각도만큼 회동가능한 저부거푸집(210)이 설치되어 있고, 상기 내측거푸집부재(20)와 상기 저부거푸집(210)은 경첩(211)에 의해 연결 결합되어 있으며, 상기 저부거푸집(210)과 후술할 거푸집부재작동장치부(30)의 프레임부(320)의 하부 사이에는 프레임부(320)를 중심으로 하여 상기 저부거푸집(210)을 회동시키기 위한 복수 개의 실린더(220)가 결합되어 있고, 상기의 실린더(220)는 유압실린더, 공압실린더 등을 사용한다. Both side lower portions of the inner formwork member 20 are provided with a lower formwork 210 which can be rotated by an angle to be separated from the inner wall portion of the culvert after the inner wall portion of the concrete culvert is constructed and constructed. The inner formwork member 20 and the bottom formwork 210 are connected and coupled by a hinge 211, and the lower formwork 210 and the lower portion of the frame portion 320 of the formwork member operating device 30 to be described later. A plurality of cylinders 220 for pivoting the bottom die 210 around the frame part 320 are coupled therebetween, and the cylinder 220 uses a hydraulic cylinder, a pneumatic cylinder, or the like.

즉, 상기 각 실린더(220)는 저부거푸집(210)에 의해 콘크리트 암거의 내측벽부 하부를 시공하도록 저부거푸집(210)를 지지할 뿐만 아니라 상기 콘크리트 암거의 시공이 완료되어 상기 콘크리트 암거의 내측벽부 하부로부터 저부거푸집(210)을 분리할 때에는 프레임부(320) 측에 결합된 각 실린더(220)의 일단을 분리하여 상기 분리된 각 실린더(220)의 일단을 거푸집고정부재(310) 즉, 후술할 거푸집고정부재(310)의 좌, 우측 고정부재(311,312)에 각각 결합하여 상기 각 실린더(220)의 작동에 따라 경첩(211)을 중심으로 하여 저부거푸집(210)이 회동되면서 상기 콘크리트 암거의 내측벽부 하부로부터 저부거푸집(210)을 원활하게 분리하도록 한다. That is, each of the cylinders 220 not only supports the bottom formwork 210 so as to construct the lower portion of the inner wall portion of the concrete culvert by the bottom formwork 210, and the construction of the concrete culvert is completed to the inner wall of the concrete culvert When the bottom formwork 210 is separated from the lower part, one end of each cylinder 220 coupled to the frame part 320 is separated to form one end of each of the separated cylinders 220. The concrete culvert while being coupled to the left and right fixing members 311 and 312 of the form fixing member 310, which will be described later, by rotating the bottom formwork 210 around the hinge 211 according to the operation of the respective cylinders 220. Smoothly separating the bottom formwork 210 from the lower inner wall portion.

상기 내측거푸집부재(20)의 상부면 중앙부에는 상기 내측거푸집부재(20)과 분리되도록 하는 중앙거푸집(230)이 이동가능하게 설치되고, 후술할 거푸집부재작동장치부(30)의 거푸집고정부재(310) 구성 중 하나인 상부 고정부재(313)의 중앙부에는 상기 중앙거푸집(230)의 저면에 단부가 결합되어 상기의 중앙거푸집(230)을 상하방향으로 이동시키도록 하는 고정볼트(240)가 체결되어 있다. The central formwork 230 to be separated from the inner formwork member 20 is movable on the central portion of the upper surface of the inner formwork member 20, and the formwork fixing member of the formwork member operating device 30 to be described later ( 310 is fixed to the central portion of the upper fixing member 313, the fixing bolt 240 to the end is coupled to the bottom of the central formwork 230 to move the central formwork 230 in the vertical direction It is.

상기 내측거푸집부재(20)의 상부 전면은 상기 내측거푸집부재(20)의 전방으로 돌출 형성되어 있고, 후술할 거푸집부재작동장치부(30)의 거푸집고정부재(310) 상부 전면 즉, 거푸집고정부재(310)의 각 구성 중 하나인 상부 고정부재(313)의 전면에는 상기 전면으로 돌출된 내측거푸집부재(20)를 지지하는 지지고정부재(317)가 설치되어 있으며, 상기 전방으로 돌출 형성된 내측거푸집부재(20)의 상부 전면에는 작업자가 작업 및 이동가능한 전면작업부(350)가 구비되어 있다. The upper front surface of the inner formwork member 20 is formed to protrude toward the front of the inner formwork member 20, that is, the form fixing member 310 upper front of the formwork member operating unit 30 to be described later, that is, the formwork fixing member On the front of the upper fixing member 313, which is one of the respective components of the 310, a support fixing member 317 for supporting the inner formwork member 20 protruding to the front is provided, the inner formwork protruding forward The upper front surface of the member 20 is provided with a front working portion 350 that can be moved and operated by the operator.

상기의 거푸집부재작동장치부(30)는 외면에 내측거푸집부재(20)가 결합되는 복수 개의 거푸집고정부재(310)가 설치되어 있고, 상기 거푸집고정부재(310)의 내측에는 상기 거푸집고정부재(310)를 지지 고정하도록 하는 프레임부(320)가 설치되어 있다. The formwork member operating device 30 has a plurality of formwork fixing members 310, the inner formwork member 20 is coupled to the outer surface is installed, the formwork fixing member 310 inside the formwork fixing member (310) The frame part 320 which supports and fixes 310 is provided.

상기 거푸집고정부재(310)와 상기 프레임부(320) 사이에는 상기 거푸집고정부재(310)와 프레임부(320) 사이의 간격을 일정하게 유지함은 물론 상기 거푸집고정부재(310)와 프레임부(320)를 고정 결합 또는 착탈가능하게 결합하도록 하는 복수 개의 결합부재(340)가 설치되어 있다. The gap between the form fixing member 310 and the frame part 320 maintains a constant distance between the form fixing member 310 and the frame part 320 as well as the form fixing member 310 and the frame part 320. ) Is provided with a plurality of coupling members 340 to be fixedly coupled or detachably coupled.

상기 각 거푸집고정부재(310)와 상기 프레임부(320) 사이에는 콘크리트 암거의 내측벽부를 시공 및 콘크리트 암거의 내측벽부로부터 상기 내측거푸집부재(20)를 분리하도록 상기 거푸집고정부재(20)를 왕복 이동시키도록 하는 복수 개의 유압실린더(330)가 결합되어 있고, 상기 프레임부(320)의 하부에는 레일(40)을 따라 거푸집부재작동장치부(30)를 이동시키는 복수 개의 바퀴(328)가 회전가능하게 결합되어 있다. Between the formwork fixing members 310 and the frame portion 320, the inner wall portion of the concrete culvert is constructed and the formwork fixing member 20 is separated to separate the inner formwork member 20 from the inner wall portion of the concrete culvert. A plurality of hydraulic cylinders 330 for reciprocating are coupled, and a plurality of wheels 328 for moving the formwork member operating unit 30 along the rail 40 are provided below the frame part 320. It is rotatably coupled.

상기 각 거푸집고정부재(310)와 상기 프레임부(320) 사이에는 상기 프레임부(320)에 각 거푸집고정부재(310)를 지지하도록 하는 복수 개의 브레이징이 결합 설치되어 있다. Between the die fixing members 310 and the frame portion 320, a plurality of brazing for supporting each of the die fixing members 310 in the frame portion 320 is coupled.

상기의 각 브레이징은 도 2에서와 같이, 후술할 각 거푸집고정부재(310)의 상부 고정부재(313)와 후술할 프레임부(320)의 세로프레임(323) 간의 간격을 일정하게 유지함은 물론 상기 프레임부(320)의 세로프레임(323)으로부터 상부 고정부재(313)를 지지하는 복수 개의 상부 브레이징(360)과, 후술할 각 거푸집고정부재(310)의 좌, 우측 고정부재(311,312)와 후술할 프레임부(320)의 좌, 우측 가로프레임(321,322) 간의 간격을 일정하게 유지함은 물론 상기 프레임부(320)의 좌, 우측 가로프레임(321,322)으로부터 좌, 우측 고정부재(311,312)를 각각 지지하는 복수 개의 측부 브레이징(370)으로 구성되어 있다. Each of the brazing is as shown in Figure 2, as well as maintaining a constant distance between the upper fixing member 313 of each die fixing member 310 to be described later and the vertical frame 323 of the frame portion 320 to be described later A plurality of upper brazing 360 for supporting the upper fixing member 313 from the vertical frame 323 of the frame part 320, and the left and right fixing members 311 and 312 of each form fixing member 310 to be described later and The interval between the left and right horizontal frames 321 and 322 of the frame unit 320 is kept constant, and the left and right fixing members 311 and 312 are supported from the left and right horizontal frames 321 and 322 of the frame unit 320, respectively. It is composed of a plurality of side brazing (370).

상기 각 상부 브레이징(360)과 상기 각 측부 브레이징(370)은 콘크리트 암거를 시공할 때에는 상기 프레임부(320)의 세로프레임(323)과 거푸집고정부재(310)의 상부 고정부재(313) 그리고, 상기 프레임부(320)의 좌, 우측 가로프레임(321,322)과 상기 거푸집고정부재(310)의 좌, 우측 고정부재(311,312)에 서로 연결 결합되고, 상기 콘크리트 암거의 시공이 완료되면 상기 각 상부 브레이징(360)의 일단은 상부 고정부재(313)에서 분리하고, 상기 각 측부 브레이징(370)은 거푸집고정부재(310)와 프레임부(320)에서 완전 분리하여 상기 유압실린더(330)의 작동에 따라 거푸집고정부재(310)가 콘크리트 암거의 내측벽부로부터 분리가능하도록 한다. Each of the upper brazing 360 and each side brazing 370 is a vertical frame 323 of the frame part 320 and the upper fixing member 313 of the form fixing member 310 when constructing concrete culvert, The left and right horizontal frames 321 and 322 of the frame part 320 and the left and right fixing members 311 and 312 of the form fixing member 310 are connected to each other, and the upper brazing is completed when the construction of the concrete culvert is completed. One end of the 360 is separated from the upper fixing member 313, and each side brazing 370 is completely separated from the form fixing member 310 and the frame portion 320 in accordance with the operation of the hydraulic cylinder 330 The formwork fixing member 310 is detachable from the inner wall portion of the concrete culvert.

상기 거푸집부재작동장치부(30)의 거푸집고정부재(310)는 도 2 내지 도 4에서와 같이, 상기 거푸집고정부재(310)의 양측부에 위치하여 내측거푸집부재(20)가 각각 결합되는 중공 형상의 좌, 우측 고정부재(311,313)가 각각 설치되어 있고, 상기 거푸집고정부재(310)의 상부 측인 상기 좌, 우측 고정부재(311,312)의 상부 사이에는 내측거푸집부재(20)가 결합되는 중공형상의 상부 고정부재(313)가 설치되어 있으며, 상기 좌측 고정부재(311)의 상단과 상기 상부 고정부재(313)의 일단 사이에는 상기 좌측 고정부재(311)의 상단에 일단이 결합됨과 함께 상기 상부 고정부재(313)의 일단에 타단이 이동가능하게 삽입 설치되어 상기 좌측 고정부재(311)와 상부 고정부재(313)가 이동가능하도록 상기 좌측 고정부재(311)와 상기 상부 고정부재(313)를 연결하도록 하는 제1연결부재(314)가 설치되어 있고, 상기 우측 고정부재(313)의 상단과 상기 상부 고정부재(313)의 타단 사이에는 상기 우측 고정부재(312)의 상단에 일단이 결합됨과 함께 상기 상부 고정부재(313)의 타단에 타단이 이동가능하게 삽입 설치되어 상기 우측 고정부재(312)와 상부 고정부재(313)가 이동가능하도록 상기 우측 고정부재(312)와 상기 상부 고정부재(313)를 연결하도록 하는 제2연결부재(315)가 설치되어 있다. The form fixing member 310 of the form member operating device unit 30 is located on both sides of the form fixing member 310, as shown in Figure 2 to 4, the inner formwork member 20 is coupled to each hollow The left and right fixing members 311 and 313 of the shape are respectively provided, and a hollow shape in which the inner mold member 20 is coupled between the upper portions of the left and right fixing members 311 and 312 which are the upper sides of the mold fixing member 310. An upper fixing member 313 is installed, and one end is coupled to the upper end of the left fixing member 311 between the upper end of the left fixing member 311 and one end of the upper fixing member 313 and the upper The other end is inserted into one end of the fixing member 313 so as to be movable to move the left fixing member 311 and the upper fixing member 313 so that the left fixing member 311 and the upper fixing member 313 are movable. First connecting member 314 to connect It is installed, and one end is coupled to the upper end of the right fixing member 312 between the upper end of the right fixing member 313 and the other end of the upper fixing member 313 and at the other end of the upper fixing member 313 A second connection member which connects the right fixing member 312 and the upper fixing member 313 such that the other end is inserted and movable so that the right fixing member 312 and the upper fixing member 313 are movable; 315 is installed.

상기 상부 고정부재(313)의 중앙부에는 도 1과 도 2에서와 같이 상기 중앙거푸집(230)을 상하방향으로 이동시키도록 하는 고정볼트(240)가 회전가능하게 결합되어 있다. A fixing bolt 240 is rotatably coupled to the central portion of the upper fixing member 313 to move the central formwork 230 in the vertical direction as shown in FIGS. 1 and 2.

상기 상부 고정부재(313)의 양단으로부터 상기 제1,2연결부재(314,315)가 탈거되는 것을 방지하기 위하여, 상기 상부 고정부재(313)의 양단면에 각각 슬라이딩공을 형성하고, 상기 제1,2연결부재(314,315)에는 슬라이딩공과 일치하는 가이드공을 각각 형성하며, 상기 상부 고정부재(313)의 이동에 따라 상부 고정부재(313) 내로 제1,2연결부재(314,315)의 단부가 삽탈되도록 상기 일치하는 각 공 내에서 이동가능한 힌지를 삽입 결합되어 있다. In order to prevent the first and second connection members 314 and 315 from being detached from both ends of the upper fixing member 313, sliding holes are formed on both end surfaces of the upper fixing member 313, respectively. Two connecting members 314 and 315 are formed with guide holes corresponding to the sliding holes, respectively, and end portions of the first and second connecting members 314 and 315 are inserted into the upper fixing member 313 according to the movement of the upper fixing member 313. The movable hinge is inserted into and engaged in each matching ball.

상기 거푸집부재작동장치부(30)의 프레임부(320)는 도 2 내지 도 4에서와 같이, 저면에 레일(40)을 따라 이동하도록 회전하는 바퀴(328) 또는 상기 레일(40)의 상면에 안착 고정되는 지지고정부(327)가 결합됨은 물론 상단은 거푸집고정부재(310)의 상부 고정부재(313)에 결합되어 상기 거푸집고정부재(310)를 지지 고정하도록 하는 복수 개의 좌, 우측 가로프레임(321,322)가 각각 설치되어 있고, 상기 좌측 가로프레임(321)과 상기 우측 가로프레임(322) 사이에는 상기 좌측 가로프레임(321)과 우측 가로프레임(322)을 연결 결합하는 복수 개의 세로프레임(323)이 세로방향으로 결합 설치되어 있으며, 상기 각 좌측 가로프레임(321) 및 상기 각 우측 가로프레임(322)에는 상기 각 좌측 가로프레임(321) 간을 서로 연결함은 물론 상기 각 우측 가로프레임(322) 간을 서로 연결하여 상기 각각의 좌측 가로프레임(321) 및 우측 가로프레임(322)을 각각 지지 고정하는 복수 개의 고정프레임(324)이 각각 결합 설치되어 있다. Frame portion 320 of the formwork member operating device 30 is on the wheel 328 or the upper surface of the rail 40 to rotate to move along the rail 40 on the bottom as shown in Figures 2 to 4 A plurality of left and right horizontal frames for supporting and fixing the form fixing member 310 are coupled to the upper fixing member 313 of the form fixing member 310 as well as the support fixing portion 327 to be seated and fixed ( 321 and 322 are respectively provided, and a plurality of vertical frames 323 are connected between the left horizontal frame 321 and the right horizontal frame 322 to connect the left horizontal frame 321 and the right horizontal frame 322. The vertically coupled is installed, and each of the left horizontal frame 321 and the right horizontal frame 322 is connected to each of the left horizontal frame 321, as well as the right horizontal frame 322 each. Connect the liver to each other Each of the plurality of the fixed frame 324 fixed to the support respectively the left horizontal frame 321 and a right horizontal frame 322 are coupled respectively.

상기 프레임부(320)의 각 세로 프레임(323) 상면에는 작업자가 작업하기 위해 작업자가 밟는 적어도 하나 이상의 작업발판(325)이 설치되어 있다. On the upper surface of each vertical frame 323 of the frame part 320 is provided at least one or more working scaffold 325 to be stepped by the worker to work.

상기 각 거푸집고정부재(310)의 좌, 우측 가로프레임(321,322) 중 전면 측 즉, 상기 거푸집부재작동장치부(30)의 전면 측에 위치하는 좌, 우측 가로프레임(321,322)에는 거푸집부재작동장치부(30)의 이동을 제한하도록 레일(40)에 고정 설치되는 클램프(326)가 각각 설치되어 있으며, 상기 각 좌, 우측 가로프레임(321,322) 중 어느 하나의 좌, 우측 가로프레임(321,322) 저면에는 레일(40)의 상면에 안착 고정됨은 물론 상기 레일(40)로부터 분리되는 지지고정부(327)가 상하 방향으로 이동가능하게 각각 결합되어 있다. Formwork member operating device in the left, right horizontal frame (321, 322) located on the front side of the left, right horizontal frame (321, 322) of each of the formwork fixing members 310, that is, the front side of the formwork member operating device (30). Clamps 326 fixed to the rail 40 are installed to limit the movement of the unit 30, respectively, and the bottom of any one of the left and right horizontal frames 321 and 322, respectively. The seat fixing is fixed to the upper surface of the rail 40 as well as the support fixing portion 327 is separated from the rail 40 is coupled to each other so as to move in the vertical direction.

상기 거푸집고정부재(310)의 좌측 고정부재(311)와 상기 제1연결부재(314) 사이 및, 상기 우측 고정부재(312)와 상기 제2연결부재(315) 사이에는 상기 좌, 우측 고정부재(311,312)와 제1,2연결부재(314,315)를 서로 연결 지지하도록 하는 복수 개의 연결지지바(380)가 결합 설치되어 있고, 상기 거푸집고정부재(310)의 좌, 우측 고정부재(311,312)와 상기 상부 고정부재(313) 사이에는 상기 좌, 우측 고정부재(311,312)와 상부 고정부재(313)를 서로 연결 지지하도록 하는 복수 개의 고정지지바(316)가 결합 설치되어 있으며, 상기 프레임부(320)에는 상기 좌, 우측 가로프레임(321,322)과 세로 프레임(323)을 연결 지지함은 물론 상기 각 좌측 가로프레임(321)과 상기 각 우측 가로프레임(322) 간을 연결 지지하도록 하는 복수 개의 프레임 지지바(329)가 설치되어 있다. The left and right fixing members between the left fixing member 311 and the first connecting member 314 of the form fixing member 310 and between the right fixing member 312 and the second connecting member 315. A plurality of connection support bars 380 are installed to connect and support the 311 and 312 and the first and second connection members 314 and 315, and the left and right fixing members 311 and 312 of the form fixing member 310 are coupled to each other. A plurality of fixing support bars 316 are coupled and installed between the upper fixing members 313 to support the left and right fixing members 311 and 312 and the upper fixing member 313 to each other. ) Supports a plurality of frames to connect and support the left and right horizontal frames 321 and 322 and the vertical frame 323 as well as to connect and support the left and right horizontal frames 321 and the right horizontal frames 322. The bar 329 is provided.

상기 프레임부(320)의 각 프레임 즉, 좌, 우측 가로프레임(321,322)과 세로프레임(323) 및 고정프레임(324)은 하나의 단위체로 형성하거나 또는, 길이 조절이 가능하도록 복수 개가 서로 연결 결합되도록 구성할 수 있는데, 이는 거푸집부재작동장치부(30)의 사용목적이나 효과 및 제작여건, 구매자의 요구사항에 따라 다양한 구조의 프레임부(320)를 구비하기 위함이다. Each frame of the frame part 320, that is, the left and right horizontal frames 321 and 322, the vertical frame 323, and the fixed frame 324 are formed as a single unit or a plurality of pieces are connected to each other so as to be adjustable in length. It can be configured to be, which is to provide a frame portion 320 of various structures according to the purpose of use or effect and manufacturing conditions of the formwork member operating device unit 30, the buyer's requirements.

이와 같이 구성된 본 발명은, 콘크리트 암거를 시공하고자 하는 지면을 일정 깊이로 파고 나서 상기 파여 진 지면의 바닥면에 콘크리트를 타설하여 상기 콘크리트 암거의 바닥면으로 시공한다. According to the present invention configured as described above, the ground to be constructed with concrete culvert is dug to a certain depth, and then concrete is placed on the bottom surface of the dug ground to construct the bottom surface of the concrete culvert.

그런 다음, 상기 콘크리트 암거의 바닥면에 레일(40)을 깔아 설치한 다음 상기 파여 진 지면의 양측 부에 상기 콘크리트 암거의 외측벽부를 시공하기 위한 외측거푸집부재(10)를 각각 세워 설치하고 나서, 상기 콘크리트 암거의 내측벽부를 시공하기 위한 내측거푸집부재(20)가 결합된 거푸집부재작동장치부(30)를 양 외측거푸집부재(10) 사이에 설치한다. Then, the rail 40 is laid on the bottom surface of the concrete culvert, and then the outer formwork members 10 for constructing the outer wall portions of the concrete culvert are installed on both sides of the dug ground, respectively, and then the Forming member operating device portion 30, which is coupled to the inner formwork member 20 for constructing the inner wall portion of the concrete culvert is installed between both outer formwork members (10).

이때, 상기 내측거푸집부재(20)가 결합된 거푸집부재작동장치부(30)는 현장의 외부에서 제작하여 차량을 이용하여 콘크리트 암거 시공 장소로 이송한 후 크레인으로 파여 진 지면의 바닥에 설치되도록 내려놓으며, 상기 내려지는 거푸집부재작동장치부(30)의 프레임부(320) 구성 중 좌, 우측 가로프레임(321,322)의 하부에 결합된 바퀴(328)가 레일(40)의 상면에 이동가능하게 안착되도록 설치한다. At this time, the formwork member operating unit 30 coupled to the inner formwork member 20 is manufactured to be installed on the outside of the site and transported to the concrete culvert construction site using a vehicle, and then lowered to be installed on the ground of the ground dug by a crane. The wheel 328 coupled to the lower left and right horizontal frames 321 and 322 of the frame member 320 of the formwork member operating device 30 to be lowered is movably seated on the upper surface of the rail 40. Install.

그리고 나서, 상기 좌, 우측 가로프레임(321,322) 중 어느 좌, 우측 가로프레임(321,322)의 하부에 결합된 지지고정부(327)를 레일(40)의 상면에 안착 고정함과 동시에 상기 거푸집고정부재(310)의 좌, 우측 가로프레임(321,322) 중 전면 측에 위치하는 좌, 우측 가로프레임(321,322)에 각각 설치된 클램프(326)를 레일(40)에 고정 설치함에 따라 상기 거푸집부재작동장치부(30)는 레일(40)에서 이동되지 않는 상태로 고정된다. Then, the support fixing part 327 coupled to the lower portion of the left and right horizontal frame (321,322) of the left and right horizontal frame (321,322) to the upper surface of the rail 40 and at the same time the form fixing member ( The form member operating device unit 30 is fixed by installing the clamps 326 installed on the left and right horizontal frames 321 and 322 respectively located at the front side of the left and right horizontal frames 321 and 322 of the 310, respectively. ) Is fixed in a state that does not move in the rail (40).

이 상태에서, 상기 양 외측거푸집부재(10)와 상기 내측거푸집부재(20) 사이의 전, 후면을 전, 후면 거푸집부재(미도시)를 설치하는데, 상기 콘크리트 암거를 처음 시공할 때에는 상기 전, 후면 거푸집부재를 설치하나, 이미 시공된 콘크리트 암거에 연이어지도록 연속적으로 콘크리트 암거를 시공할 때에는 후면 거푸집부재를 설치하지 않을 수 있다. In this state, the front and rear between the outer formwork member 10 and the inner formwork member 20, the rear formwork member (not shown) is installed, when the first construction of the concrete culvert, The rear formwork member may be installed, but the rear formwork member may not be installed when the concrete culvert is constructed continuously so as to be connected to the concrete culvert already constructed.

상기와 같이, 상기 양 외측거푸집부재(10)와 내측거푸집부재(20) 및 전, 후면 거푸집부재의 설치가 완료되면, 상기 양 외측거푸집부재(10)와 내측거푸집부재(20) 사이에 콘크리트를 타설하고, 상기 타설된 콘크리트는 일정 시간 동안 양생과정을 거치면서 굳어지면 상기 전, 후면 거푸집부재를 분리한다. As described above, when the installation of both the outer formwork member 10 and the inner formwork member 20 and the front, rear formwork member is completed, the concrete between the two outer formwork member 10 and the inner formwork member 20. After pouring, the poured concrete is hardened through a curing process for a predetermined time to separate the front and rear formwork members.

그리고, 시공 완료된 콘크리트 암거의 내측벽부로부터 내측거푸집부재(20)를 떼어내어 분리한 후 상기 거푸집부재작동장치부(30)를 이동 즉, 레일(40)을 따라 이미 시공된 콘크리트 암거의 전방 측에 내측거푸집부재(20)가 결합된 거푸집부재작동장치부(30)를 이동시킨다. Then, the inner formwork member 20 is removed and separated from the inner wall portion of the completed concrete culvert, and then the form member operating device 30 is moved, that is, the front side of the concrete culvert already constructed along the rail 40. Move the mold member operating device portion 30 to which the inner mold member 20 is coupled.

그런 다음, 상기와 같은 방법으로 이미 시공된 콘크리트 암거의 전방에 양 외측거푸집부재(10)와 내측거푸지부재(20)를 위치시키고 나서 상기 이미 시공된 콘크리트 암거의 전면에 연이어지게 연결되도록 콘크리트를 타설하여 다음 콘크리트 암거를 시공함에 따라 상기 콘크리트 암거의 시공이 연속적으로 이루어지게 된다. Then, by placing the outer formwork member 10 and the inner formwork member 20 in front of the concrete culvert already constructed by the above method, the concrete is connected so as to be connected to the front of the concrete culvert already constructed. As the next concrete culvert is constructed by pouring, the construction of the concrete culvert is made continuously.

여기서, 상기 시공된 콘크리트 암거의 내측벽부로부터 내측거푸집부재(20)를 분리 및 다음 콘크리트 암거를 시공하기 위해 거푸집부재작동장치부(30)를 이동시키는 과정을 설명하면, 도 5에서와 같이 양 외측거푸집부재(10)와 내측거푸집부재(20)에 의해 콘크리트 암거가 시공되면, 상기 거푸집부재작동장치부(30)의 내측거푸집부재(20) 중앙부에 설치된 중앙거푸집(230)을 도면상에서와 같이 하방 측으로 이동시킨다. Here, the process of moving the formwork member operating unit 30 to separate the inner formwork member 20 from the inner wall portion of the constructed concrete culvert and to construct the next concrete culvert, as shown in Figure 5 When the concrete culvert is constructed by the outer formwork member 10 and the inner formwork member 20, the central formwork 230 installed at the center of the inner formwork member 20 of the formwork member operating device 30 is as shown in the drawing. Move to the lower side.

즉, 상기 중앙거푸집(230)의 하방 측인 상기 거푸집부재작동장치부(30)의 거푸집고정부재(310) 구성 중 상부 고정부재(313)에 체결된 고정볼트(240)를 회전시키면 상기 고정볼트(240)의 회전에 따라 중앙거푸집(230)은 도 6에서와 같이 상기 내측거푸집부재(20)의 하방 측으로 이동한다. That is, when the fixing bolt 240 is fastened to the upper fixing member 313 of the form fixing member 310 of the form member operating device portion 30, which is the lower side of the central formwork 230, the fixing bolt ( In accordance with the rotation of 240, the central die 230 moves to the lower side of the inner die member 20 as shown in FIG.

상기 고정볼트(240)는 작업자가 거푸집부재작동장치부(30)의 프레임부(320) 구성 중 세로프레임(323)에 결합 설치된 작업발판(325) 위에 올라가서 수작업으로 회전시키거나 또는, 상기 고정볼트(240)에 별도의 제어부를 연결하여 제어부에서 보내지는 신호에 따라 자동으로 회전시킬 수 있다. The fixing bolt 240 is rotated by a worker by manually climbing on the work step 325 installed in the vertical frame 323 of the frame part 320 of the form member operating device unit 30, or the fixing bolt A separate control unit may be connected to the 240 to automatically rotate according to a signal sent from the control unit.

상기 중앙거푸집(230)이 하방 측으로 이동하면, 상기 내측거푸집부재(20)의 양측 하부에 각각 설치된 저부거푸집(210)을 내측 방향으로 회동시켜 콘크리트 암거의 내측벽부 하부로부터 저부거푸집(210)을 떼어내어 분리한다. When the central formwork 230 moves downward, the bottom formwork 210 installed on both lower sides of the inner formwork member 20 is rotated inward to move the bottom formwork 210 from the lower portion of the inner wall of the concrete culvert. Remove and remove.

즉, 상기의 저부거푸집(210)은 콘크리트 암거가 시공될 때에는 실린더(220)에 의해 지지 고정되었다가 상기 콘크리트 암거의 시공이 완료되어 암거의 내측벽부로부터 분리하고자 할 때에는 프레임부(320)의 좌, 우측 가로프레임(321,322) 하부에 결합된 실린더(220)의 일단을 분리한 후 상기 실린더(220)의 일단을 거푸집고정부재(310)의 좌, 우측 고정부재(311,312)에 결합 고정한 다음 상기 실린더(220)를 작동시키면 저부거푸집(210)은 경첩(211)을 중심으로 하여 내측방향으로 회동되어 접혀지면서 콘크리트 암거의 내측벽부 하부로부터 분리된다. That is, the bottom formwork 210 is supported and fixed by the cylinder 220 when the concrete culvert is constructed, but when the construction of the concrete culvert is completed and is to be separated from the inner wall part of the culvert, After separating one end of the cylinder 220 coupled to the lower left and right horizontal frame (321,322) and then fixed to one end of the cylinder 220 to the left and right fixing members (311,312) of the die fixing member (310) When the cylinder 220 is operated, the bottom formwork 210 is rotated inward with respect to the hinge 211 and folded, and is separated from the lower portion of the inner wall of the concrete culvert.

그런 다음, 상기 거푸집고정부재(310)의 상부 고정부재(313)과 상기 프레임부(320)의 세로프레임(323) 중 상부 측에 위치하는 세로프레임(323) 사이에 설치된 각 상부 브레이징(360)을 분리하여 제거함과 함께 상기 거푸집고정부재(310)의 좌, 우측 고정부재(311,312)과 상기 프레임부(320)의 좌, 우측 가로프레임(321,322) 사이에 설치된 각 측부 브레이징(370)을 분리하여 제거한다. Then, each upper brazing 360 installed between the upper fixing member 313 of the form fixing member 310 and the vertical frame 323 located on the upper side of the vertical frame 323 of the frame part 320. While removing and removing each side brazing 370 installed between the left and right fixing members 311 and 312 of the form fixing member 310 and the left and right horizontal frames 321 and 322 of the frame part 320. Remove

이때, 상기 각 상부 브레이징(360)과 각 측부 브레이징(370)을 상기 거푸집고정부재(310) 및 프레임부(320)에서 완전히 분리하여 제거하거나 또는, 상기 프레임부(320)에는 고정되고 상기 거푸집고정부재(310)에서만 분리할 수 있는데, 이는 작업 목적이나 효과 및 작업 효율성에 따라 작업자가 선택할 수 있다. At this time, each of the upper brazing 360 and each side brazing 370 is completely separated from the form fixing member 310 and the frame portion 320 or removed, or fixed to the frame portion 320 and the form fixing Only the member 310 can be removed, which can be selected by the operator according to the purpose or effect of the work and the work efficiency.

상기 각 브레이징(360,370)이 분리되어 제거되면, 상기 거푸집고정부재(310)와 상기 프레임부(320) 사이 즉, 상기 거푸집고정부재(310)의 좌, 우측 고정부재(311,312)와 상기 프레임부(320)의 좌, 우측 가로프레임(321,322) 사이에 각각 설치된 복수 개의 유압실린더(330)를 동시에 작동시킴에 따라 도 7에서와 같이 상기의 거푸집고정부재(310) 전체가 하방 측으로 이동하므로 인해, 상기 거푸집고정부재(310)의 상부 고정부재(313) 측에 결합된 내측거푸집부재(20)는 상기 콘크리트 암거의 내측벽부 상부면으로부터 분리된다. When the brazing 360 and 370 are separated and removed, the left and right fixing members 311 and 312 and the frame portion between the form fixing member 310 and the frame portion 320, that is, the form fixing member 310, are removed. By simultaneously operating the plurality of hydraulic cylinders 330 respectively installed between the left and right horizontal frames 321 and 322 of the 320, as shown in FIG. 7, the entire formwork fixing member 310 moves downward, The inner formwork member 20 coupled to the upper fixing member 313 side of the formwork fixing member 310 is separated from the upper surface of the inner wall portion of the concrete culvert.

그리고, 콘크리트 암거의 내측벽부 상부면으로부터 내측거푸집부재(20)가 분리되면, 상기의 각 유압실린더(330)를 상기와 반대방향으로 작동 즉, 상기 각 유압실린더(330)의 축이 삽입되도록 작동시키게 되면, 상기 각 유압실린더(330)에 의해 상기 거푸집고정부재(310)의 좌, 우측 고정부재(311,312)가 각각 내측방향으로 이동하므로 인해, 상기 좌, 우측 고정부재(311,312) 측에 결합된 내측거푸집부재(20)는 도 8에서와 같이 상기 콘크리트 암거의 내측벽부 좌, 우측면으로부터 각각 분리된다. Then, when the inner formwork member 20 is separated from the upper surface of the inner wall portion of the concrete culvert, the hydraulic cylinders 330 operate in the opposite direction to the above, that is, the shafts of the hydraulic cylinders 330 are inserted. When operated, the left and right fixing members 311 and 312 of the form fixing member 310 are moved inward by the hydraulic cylinders 330, respectively, so that the left and right fixing members 311 and 312 are coupled to the left and right fixing members 311 and 312. The inner formwork member 20 is separated from the left and right sides of the inner wall portion of the concrete culvert as shown in FIG.

즉, 상기 좌, 우측 고정부재(311,312)의 상단과 상기 상부 고정부재(313)의 양단 사이에 제1,2연결부재(314,315)의 각 타단이 삽입된 상태로 이동 가능하게 결합되어 있으므로, 상기 각 유압실린더(330)의 작동에 따라 상기 거푸지부재작동장치부(30)의 내측방향으로 상기의 좌, 우측 고정부재(311,312)가 각각 이동하게 된다. That is, since the other ends of the first and second connection members 314 and 315 are movably coupled between upper ends of the left and right fixing members 311 and 312 and both ends of the upper fixing member 313, As the hydraulic cylinders 330 operate, the left and right fixing members 311 and 312 move inwardly of the form member operating device unit 30, respectively.

이때, 상기 제1연결부재(314)의 타단은 좌측 고정부재(311) 내로 삽입된 상태에서 이동됨과 동시에 상기 제2연결부재(315)의 타단은 우측 고정부재(312) 내로 삽입된 상태에서 이동될 뿐만 아니라, 상기 중앙거푸집(230)이 하방 측을 이동하여 형성된 공간으로 상기 상부 고정부재(313)의 양측에 위치하는 내측거푸집부재(20)가 이동하면서 서로 맞닿게 되므로, 상기 거푸집고정부재(310)의 좌, 우측 고정부재(311,313) 측에 결합된 내측거푸집부재(20)는 상기 콘크리트 암거의 내측벽부 좌, 우측면으로부터 각각 분리된다. At this time, the other end of the first connection member 314 is moved in the state inserted into the left fixing member 311 and the other end of the second connection member 315 is moved in the state inserted into the right fixing member 312 In addition, since the inner formwork member 20 located on both sides of the upper fixing member 313 moves into a space formed by moving the lower side of the central formwork 230, the formwork fixing member ( The inner formwork members 20 coupled to the left and right fixing members 311 and 313 of the 310 are separated from the left and right sides of the inner wall portion of the concrete culvert, respectively.

그러므로, 상기 거푸집고정부재(310)에 결합된 내측거푸집부재(20)는 상기 콘크리트 암거의 내측벽부 상부면과 좌, 우측면에서 분리됨에 따라 상기 콘크리트 암거의 시공이 완료됨은 물론 상기 콘크리트 암거에서 암거 시공용 박스 폼이 분리된다. Therefore, the inner mold member 20 coupled to the mold fixing member 310 is separated from the upper and left and right sides of the inner wall portion of the concrete culvert, the construction of the concrete culvert is completed as well as the culvert in the concrete culvert The construction box foam is separated.

그런 다음, 상기 거푸집부재작동장치부(30)의 프레임부(320) 중 좌, 우측 가로프레임(321,322)에서 어느 하나의 좌, 우측 가로프레임(321,322) 저면에 결합된 지지고정부(327)를 상방으로 이동시켜 레일(40)로부터 분리함과 함께 상기 거푸집부재작동장치부(30)의 전방 측의 레일(40) 상면에 고정 설치된 클램프(326)를 상기 레일(40)로부터 클램핑상태를 해제하고 나서 상기 내측거푸집부재(20)가 결합된 거푸집부재작동장치부(30)를 시공된 콘크리트 암거의 외부로 밀어 탈거시킨다. Then, the support fixing part 327 coupled to the bottom of any one of the left and right horizontal frames 321 and 322 in the left and right horizontal frames 321 and 322 of the frame part 320 of the form member operating device unit 30 is upward. The clamp 326 fixed to the upper surface of the rail 40 on the front side of the form member operating device part 30 and then released from the rail 40 to release the clamping state from the rail 40. The formwork member operating device 30 to which the inner formwork member 20 is coupled is removed by pushing out of the constructed concrete culvert.

즉, 상기 프레임부(320)의 좌, 우측 가로프레임(321,322) 중 다른 좌, 우측 가로프레임(321,322) 저면에 결합된 바퀴(328)가 레일(40)의 상면에 회전가능하게 안착되어 있으므로, 상기 거푸집부재작동장치부(30)를 밀게 되면 상기 레일(40) 위를 바퀴(328)가 회전하면서 시공된 콘크리트 암거의 내부에서 상기 거푸집부재작동장치부(30)가 빠져나오게 된다. That is, since the wheels 328 coupled to the bottom of the other left and right horizontal frames 321 and 322 of the left and right horizontal frames 321 and 322 of the frame part 320 are rotatably seated on the upper surface of the rail 40, When the die member operating device 30 is pushed, the die member operating device 30 is released from the inside of the concrete culvert that is constructed while the wheel 328 rotates on the rail 40.

상기 시공된 콘크리트 암거와 연이어지도록 다음 콘크리트 암거를 연속적으로 시공하고자 할 때에는 상기 시공된 콘크리트 암거로부터 빠져나온 거푸집부재작동장치부(30)를 시공된 콘크리트 암거의 전방 측에 위치시키고 나서 상기에서 설명한 방법의 역순으로 각 장치들을 작동시켜 원상태로 복원시킨다. In order to continuously construct the next concrete culvert so as to be connected with the constructed concrete culvert, the method described above after placing the formwork member operating device 30 escaped from the constructed concrete culvert on the front side of the constructed concrete culvert Operate each unit in reverse order to restore it to its original state.

즉, 상기 각 유압실린더(330)를 작동시켜 상기 거푸집고정부재(310)의 좌, 우측 고정부재(311,312)와 상부 고정부재(313) 및, 중앙거푸집(230)과, 저부거푸집(210)을 원래 위치로 이동시킴과 함께 상기 각 상부 브레이징(360)과 측부 브레이징(370)을 연결 설치하는 등 상기의 각 장치들을 원상태로 복원시킨다. That is, the hydraulic cylinders 330 are operated to operate the left and right fixing members 311 and 312 and the upper fixing member 313 and the central mold 230 and the lower mold 210 of the mold fixing member 310. Each of the above devices is restored to its original state, such as connecting the upper brazing 360 and the side brazing 370 together with the original position.

그런 다음, 상기 내측거푸집부재(20)가 결합된 거푸집부재작동장치부(30)의 양 측방에 외측거푸집부재(10)를 각각 설치하고 나서 상기에서와 같은 방식으로 콘크리트를 타설 및 일정 시간 동안 양생시켜 상기 시공된 콘크리트 암거에 연결되도록 다음 콘크리트 암거를 연속적으로 시공한다.
Then, the outer formwork member 10 is installed on both sides of the formwork member operating device 30 to which the inner formwork member 20 is coupled, and then the concrete is poured and cured for a predetermined time in the same manner as described above. The next concrete culvert is continuously constructed so as to be connected to the constructed concrete culvert.

이와 같이, 본 발명에 따른 암거 시공용 박스 폼 구조는 예시된 도면을 참조하여 설명하였으나, 본 명세서에 기재된 실시예와 도면에 의해 본 발명은 한정되지 않으며 그 발명의 기술범위 내에서 당업자에 의해 다양한 변형이 이루어질 수 있으므로 본 발명의 기술적 사상이나 전망으로부터 개별적으로 이해되어져서는 안 되는 것이다. As described above, the culvert box structure for construction according to the present invention has been described with reference to the illustrated drawings, but the present invention is not limited by the embodiments and drawings described herein, and various modifications are made by those skilled in the art within the technical scope of the present invention. Modifications may be made and should not be understood individually from the technical spirit or prospect of the present invention.

10: 외측거푸집부재 20: 내측거푸집부재
30:거푸집부재작동장치부 40: 레일
110: 안전발판부 120: 외측지지바
131,132: 제1,2간격유지부재 210: 저부거푸집
211: 경첩 220: 실린더
230: 중앙거푸집 240: 고정볼트
310: 거푸집고정부재 311,312: 좌, 우측 고정부재
313: 상부 고정부재 314,315: 제1,2연결부재
316: 고정지지바 317: 지지고정부재
320: 프레임부 321,322: 좌, 우측 가로프레임
323: 세로프레임 324: 고정프레임
325: 작업발판 326: 클램프
327: 지지고정부 328: 바퀴
329: 프레임지지바 330: 유압실린더
340: 결합부재 350: 전면작업부
360: 상부 브레이징 370: 측부 브레이징
380: 연결지지바
10: outer die member 20: inner die member
30: die member operating unit 40: rail
110: safety footrest 120: outer support bar
131, 132: first and second interval holding member 210: bottom die
211: hinge 220: cylinder
230: center die 240: fixing bolt
310: formwork fixing member 311,312: left, right fixing member
313: upper fixing member 314, 315: first, second connecting member
316: fixed support bar 317: support fixing member
320: frame portion 321, 322: left and right horizontal frame
323: vertical frame 324: fixed frame
325: working step 326: clamp
327: Suspended Government 328: Wheels
329: frame support bar 330: hydraulic cylinder
340: coupling member 350: front working part
360: upper brazing 370: side brazing
380: connecting support bar

Claims (9)

콘크리트 암거를 연속적으로 시공하기 위한 암거 시공용 박스 폼에 있어서,
상기 콘크리트 암거의 외측벽부를 시공하기 위해 시공 전 콘크리트 암거의 좌, 우측에 각각 설치되어 일정한 간격을 유지하는 외측거푸집부재;
상기 각 외측거푸집부재와 일정 간격으로 이격되도록 상기 각 외측거푸지부재 사이에 위치되어 상기 콘크리트 암거의 내측벽부를 시공하기 위해 설치되는 내측거푸집부재;
상기 각 외측거푸집부재 사이에는 상기 내측거푸집부재가 결합됨과 함께 시공된 콘크리트 암거의 내측벽부로부터 내측거푸집부재를 분리하도록 구비되어 콘크리트 암거 시공 완료 후 다음 콘크리트 암거의 시공을 위해 레일을 따라 이동하는 거푸집부재작동장치부;가 구비되되,
상기의 거푸집부재작동장치부는, 상기 내측거푸집부재가 결합되는 복수 개의 거푸집고정부재와, 상기 거푸집고정부재의 내측에 설치되어 거푸집고정부재를 지지 고정하는 프레임부와, 상기 각 거푸집고정부재와 프레임부 사이에 결합되어 콘크리트 암거의 내측벽부를 시공 및 콘크리트 암거의 내측벽부로부터 내측거푸집부재를 분리하도록 상기 거푸집고정부재를 왕복 이동시키도록 하는 복수 개의 유압실린더와, 상기 각 거푸집고정부재와 프레임부 사이에 결합 설치되어 상기 각 거푸집고정부재를 지지하도록 복수 개의 브레이징과, 상기 프레임부의 하부에 회전가능하게 결합되어 레일을 따라 거푸집부재작동장치부를 이동시키는 복수 개의 바퀴로 구성됨을 특징으로 하는 암거 시공용 박스 폼 구조.
In the culvert construction box form for continuously constructing concrete culverts,
An outer formwork member installed at left and right sides of the concrete culvert before construction to maintain an outer wall portion of the concrete culvert;
An inner formwork member disposed between the outer formwork members so as to be spaced apart from the outer formwork members at predetermined intervals and installed to construct an inner wall portion of the concrete culvert;
The inner formwork member is coupled between each outer formwork member and provided to separate the inner formwork member from the inner wall portion of the constructed concrete culvert, and the formwork moves along the rail for the construction of the next concrete culvert after completion of the concrete culvert construction. Member operating device; is provided,
The formwork member operating device unit, a plurality of formwork fixing member to which the inner formwork member is coupled, a frame portion installed inside the formwork fixing member to support and fix the formwork fixing member, each of the formwork fixing member and the frame portion A plurality of hydraulic cylinders coupled between the plurality of hydraulic cylinders for constructing the inner wall portion of the concrete culvert and reciprocating the formwork fixing member to separate the inner formwork member from the inner wall portion of the concrete culvert; Cultivating construction box comprising a plurality of brazing and coupled to the lower portion of the frame portion rotatably coupled to support the respective die fixing member and a plurality of wheels to move the formwork member operating unit along the rail Foam structure.
제 1 항에 있어서,
각 외측거푸집부재의 외측면에는 작업자가 이동할 수 있도록 적어도 하나 이상의 안전발판부가 각각 설치됨을 특징으로 하는 암거 시공용 박스 폼 구조.
The method of claim 1,
Crimper construction box foam structure, characterized in that at least one or more safety scaffolding portion is installed on the outer surface of each outer formwork member so that the operator can move.
제 1 항에 있어서,
내측거푸집부재의 양측 하부에는 경첩에 의해 회동가능한 저부거푸집이 설치되고, 상기 각 저부거푸집과 프레임부의 하부 사이에는 상기 저부거푸집을 회동시키도록 하는 복수 개의 실린더가 결합되어, 상기 각 실린더는 저부거푸집을 지지함은 물론 상기 저부거푸집을 콘크리트 암거의 내측벽부 하부로부터 분리할 때에는 상기 프레임부 측에 결합된 실린더의 일단을 분리하여 거푸집고정부재에 고정 결합함을 특징으로 하는 암거 시공용 박스 폼 구조.
The method of claim 1,
Bottom dies rotatable by hinges are installed on both lower portions of the inner die member, and a plurality of cylinders are coupled between the bottom dies and the lower portion of the frame part to rotate the bottom dies, and each cylinder forms a bottom die. When releasing the bottom formwork from the bottom of the inner wall portion of the concrete culvert as well as supporting the box form structure for culvert construction, characterized in that the one end of the cylinder coupled to the frame portion is separated and fixed to the form fixing member.
제 1 항에 있어서,
거푸집고정부재는, 양측부에 위치하는 내측거푸집부재가 각각 결합되는 중공형상의 좌, 우측 고정부재와,
상기 좌, 우측 고정부재의 상부 사이에 설치되어 상부 측에 위치하는 내측거푸집부재가 결합되는 중공형상의 상부 고정부재와,
상기 좌측 고정부재의 상단에 일단이 결합됨과 함께 타단은 상기 상부 고정부재의 일단에 이동가능하게 삽입 설치되어 상기 좌측 고정부재가 이동가능하도록 상기 좌측 고정부재와 상기 상부 고정부재를 연결하는 제1연결부재와,
상기 우측 고정부재의 상단에 일단이 결합됨과 함께 타단은 상기 상부 고정부재의 타단에 이동가능하게 삽입 설치되어 상기 우측 고정부재가 이동가능하도록 상기 우측 고정부재와 상기 상부 고정부재를 연결하는 제2연결부재로 구성됨을 특징으로 하는 암거 시공용 박스 폼 구조.
The method of claim 1,
The formwork fixing member includes a hollow left and right fixing member to which the inner formwork members positioned at both side portions are respectively coupled;
A hollow upper fixing member installed between the left and right fixing members and coupled to an inner mold member positioned at an upper side thereof;
The first connection is coupled to the upper end of the left fixing member and the other end is inserted into the one end of the upper fixing member so as to be movable to connect the left fixing member and the upper fixing member so that the left fixing member is movable. Absence,
A second connection is connected to the upper end of the right fixing member and the other end is inserted into the other end of the upper fixing member so as to be movable to connect the right fixing member and the upper fixing member to move the right fixing member. Culvert construction box foam structure, characterized in that composed of members.
제 4 항에 있어서,
좌측 고정부재와 제1연결부재 사이 및, 우측 고정부재와 제2연결부재 사이에는 상기 좌, 우측 고정부재와 제1,2연결부재를 서로 연결 지지하도록 하는 복수 개의 연결지지바가 결합 설치되고, 상기 좌, 우측 고정부재와 상부 고정부재 사이에는 상기 좌, 우측 고정부재와 상부 고정부재를 서로 연결 지지하도록 하는 복수 개의 고정지지바가 결합 설치됨을 특징으로 하는 암거 시공용 박스 폼 구조.
5. The method of claim 4,
A plurality of connection support bars are coupled between the left fixing member and the first connecting member and between the right fixing member and the second connecting member to connect and support the left and right fixing members and the first and second connecting members. The culvert construction box form structure, characterized in that the left and right fixing member and the upper fixing member is coupled between the plurality of fixing support bars for supporting the left and right fixing member and the upper fixing member to each other.
제 1 항 또는 제 4 항에 있어서,
내측거푸집부재의 상부면 중앙부에는 상기 내측거푸집부재과 분리되는 중앙거푸집이 설치되고, 거푸집고정부재의 상부 고정부재 중앙부에는 중앙거푸집의 저면에 단부가 결합되어 상기의 중앙거푸집을 상하방향으로 이동시키도록 하는 고정볼트가 체결됨을 특징으로 하는 암거 시공용 박스 폼 구조.
The method according to claim 1 or 4,
A central formwork separate from the inner formwork member is installed at the center of the upper surface of the inner formwork member, and an end is coupled to the bottom of the central formwork at the center of the upper fixing member of the formwork fixing member to move the central formwork in the vertical direction. Culvert construction box foam structure, characterized in that the fixing bolt is fastened.
제 1 항에 있어서,
프레임부는, 저면에 레일을 따라 이동하도록 회전하는 바퀴가 결합됨은 물론 상단은 거푸집고정부재의 상부 고정부재에 결합되어 상기 거푸집고정부재를 지지 고정하는 복수 개의 좌, 우측 가로프레임과,
상기 좌측 가로프레임과 상기 우측 가로프레임 사이에 세로방향으로 설치되어 상기 좌측 가로프레임과 우측 가로프레임을 연결 결합하는 복수 개의 세로프레임과,
상기 각 좌측 가로프레임 및 상기 각 우측 가로프레임을 연결하도록 설치되어 상기 각 좌, 우측 가로프레임을 각각 지지 고정하는 복수 개의 고정프레임으로 구성됨을 특징으로 하는 암거 시공용 박스 폼 구조.
The method of claim 1,
The frame part is coupled to the wheel to rotate to move along the rail on the bottom, as well as a plurality of left and right horizontal frames coupled to the upper fixing member of the form fixing member to support and fix the form fixing member,
A plurality of vertical frames installed vertically between the left horizontal frame and the right horizontal frame to connect and couple the left horizontal frame and the right horizontal frame;
The culvert construction box form structure, characterized in that composed of a plurality of fixed frames are installed to connect each of the left horizontal frame and each of the right horizontal frame to support and fix the left and right horizontal frames respectively.
제 7 항에 있어서,
좌, 우측 가로프레임 중 전면 측에 위치하는 좌, 우측 가로프레임에는 거푸집부재작동장치부의 이동을 제한하도록 레일에 고정 설치되는 클램프가 각각 설치되고, 상기 좌, 우측 가로프레임의 어느 하나의 좌, 우측 가로프레임 저면에는 레일의 상면에 안착 고정되는 지지고정부가 각각 결합됨을 특징으로 하는 암거 시공용 박스 폼 구조.
The method of claim 7, wherein
The left and right horizontal frames positioned on the front side of the left and right horizontal frames are respectively provided with clamps fixed to the rails to limit the movement of the formwork member operating unit, and any one of the left and right horizontal frames is provided. The culvert construction box foam structure, characterized in that the bottom of the horizontal frame is coupled to each of the support fixing parts that are fixed to the upper surface of the rail.
제 1 항에 있어서,
내측거푸집부재의 상부 전면은 상기 내측거푸집부재의 전방으로 돌출 형성되고, 거푸집고정부재의 상부 전면에는 상기 전면으로 돌출된 내측거푸집부재의 상부를 지지하는 지지고정부재가 설치되며, 상기 전방으로 돌출 형성된 내측거푸집부재의 상부 전면에는 전면작업부가 구비됨을 특징으로 하는 암거 시공용 박스 폼 구조.
The method of claim 1,
The upper front surface of the inner formwork member is formed to protrude forward of the inner formwork member, the upper front surface of the formwork fixing member is provided with a support fixing member for supporting the upper portion of the inner formwork member projecting to the front, protruding forward The culvert construction box foam structure, characterized in that the front working portion is provided on the upper front of the inner formwork member.
KR1020130007257A 2013-01-23 2013-01-23 Box form structure for culvert construction KR101372261B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020130007257A KR101372261B1 (en) 2013-01-23 2013-01-23 Box form structure for culvert construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020130007257A KR101372261B1 (en) 2013-01-23 2013-01-23 Box form structure for culvert construction

Publications (1)

Publication Number Publication Date
KR101372261B1 true KR101372261B1 (en) 2014-03-10

Family

ID=50648105

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020130007257A KR101372261B1 (en) 2013-01-23 2013-01-23 Box form structure for culvert construction

Country Status (1)

Country Link
KR (1) KR101372261B1 (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106760486A (en) * 2017-03-17 2017-05-31 中铁隧道集团有限公司 Exterior wall mould and its erection method in foundation ditch
CN108867420A (en) * 2018-09-18 2018-11-23 甘肃恒捷路桥养护科技有限公司 All-hydraulic automatically walk culvert abutment body trolley and construction technology process
CN109339098A (en) * 2018-11-08 2019-02-15 北京场道市政工程集团有限公司 A kind of underground pipe gallery removable support template
CN109538250A (en) * 2019-01-28 2019-03-29 中南大学 Device and method for branch at the beginning of tunnel with mould gunite concrete rapid construction
CN110042771A (en) * 2019-05-12 2019-07-23 中国水利水电第五工程局有限公司 A kind of moveable modularization box culvert rapid construction device
KR102060692B1 (en) 2019-06-25 2019-12-30 허연희 Construction method using road soundproof wall concrete retaining wall construction device
CN111088761A (en) * 2019-12-31 2020-05-01 广东冠粤路桥有限公司 Sliding type template system for cast-in-situ box culvert
CN111809536A (en) * 2020-08-07 2020-10-23 中铁五局集团建筑工程有限责任公司 Integrally-moving box culvert template and construction method thereof
CN112012115A (en) * 2020-08-28 2020-12-01 浙江省围海建设集团股份有限公司 Box culvert walking type internal mold, construction device and construction method
CN112458936A (en) * 2020-11-30 2021-03-09 中铁十六局集团地铁工程有限公司 Construction method for integrally translating box culvert full-hall support
CN112663405A (en) * 2020-11-30 2021-04-16 中国十七冶集团有限公司 Railway underpass box culvert jacking track reinforcing method
KR20210112609A (en) * 2020-03-05 2021-09-15 신성식 gangform device for subway construction and method for constructing the same
CN115467258A (en) * 2022-09-28 2022-12-13 河南省沿太行高速公路有限公司 High efficiency culvert construction bearing structure

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200237675Y1 (en) 2001-04-24 2001-10-12 주식회사 한국종합기술개발공사 Structure of movable sheeting
KR20020005537A (en) * 2001-11-12 2002-01-17 주식회사 신보성종합건설 Movable Steel Form for Constructing Culvert and Continuous Constructing Method of Culvert Using the Same
KR20110055796A (en) * 2009-11-20 2011-05-26 고엄식 A passage fabric used to multi slip form and methode there of
KR101130923B1 (en) 2009-08-01 2012-03-28 동우건설(주) the mold with self-propelled type trolley for construction of continuous structure and the construction method of continuous structure therewith

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200237675Y1 (en) 2001-04-24 2001-10-12 주식회사 한국종합기술개발공사 Structure of movable sheeting
KR20020005537A (en) * 2001-11-12 2002-01-17 주식회사 신보성종합건설 Movable Steel Form for Constructing Culvert and Continuous Constructing Method of Culvert Using the Same
KR101130923B1 (en) 2009-08-01 2012-03-28 동우건설(주) the mold with self-propelled type trolley for construction of continuous structure and the construction method of continuous structure therewith
KR20110055796A (en) * 2009-11-20 2011-05-26 고엄식 A passage fabric used to multi slip form and methode there of

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106760486A (en) * 2017-03-17 2017-05-31 中铁隧道集团有限公司 Exterior wall mould and its erection method in foundation ditch
CN108867420A (en) * 2018-09-18 2018-11-23 甘肃恒捷路桥养护科技有限公司 All-hydraulic automatically walk culvert abutment body trolley and construction technology process
CN109339098A (en) * 2018-11-08 2019-02-15 北京场道市政工程集团有限公司 A kind of underground pipe gallery removable support template
CN109339098B (en) * 2018-11-08 2023-09-22 北京场道市政工程集团有限公司 Portable support template of utility tunnel
CN109538250A (en) * 2019-01-28 2019-03-29 中南大学 Device and method for branch at the beginning of tunnel with mould gunite concrete rapid construction
CN109538250B (en) * 2019-01-28 2023-09-15 中南大学 Device and method for quick construction of tunnel primary support with mould sprayed concrete
CN110042771A (en) * 2019-05-12 2019-07-23 中国水利水电第五工程局有限公司 A kind of moveable modularization box culvert rapid construction device
KR102060692B1 (en) 2019-06-25 2019-12-30 허연희 Construction method using road soundproof wall concrete retaining wall construction device
CN111088761A (en) * 2019-12-31 2020-05-01 广东冠粤路桥有限公司 Sliding type template system for cast-in-situ box culvert
KR102384951B1 (en) * 2020-03-05 2022-04-07 신성식 gangform device for subway construction and method for constructing the same
KR20210112609A (en) * 2020-03-05 2021-09-15 신성식 gangform device for subway construction and method for constructing the same
CN111809536A (en) * 2020-08-07 2020-10-23 中铁五局集团建筑工程有限责任公司 Integrally-moving box culvert template and construction method thereof
CN112012115A (en) * 2020-08-28 2020-12-01 浙江省围海建设集团股份有限公司 Box culvert walking type internal mold, construction device and construction method
CN112663405A (en) * 2020-11-30 2021-04-16 中国十七冶集团有限公司 Railway underpass box culvert jacking track reinforcing method
CN112458936A (en) * 2020-11-30 2021-03-09 中铁十六局集团地铁工程有限公司 Construction method for integrally translating box culvert full-hall support
CN115467258A (en) * 2022-09-28 2022-12-13 河南省沿太行高速公路有限公司 High efficiency culvert construction bearing structure
CN115467258B (en) * 2022-09-28 2024-01-26 河南省沿太行高速公路有限公司 High efficiency culvert construction bearing structure

Similar Documents

Publication Publication Date Title
KR101372261B1 (en) Box form structure for culvert construction
CN106854873B (en) Engineering method of prefabricated spliced open caisson type parking garage and parking garage
CN108505805B (en) Large cast-in-situ water pool with expansion reinforcing belt for crack control and construction method thereof
CN106049530B (en) City integrated piping lane and construction method
CN104631512A (en) Post-cast strip beam and slab construction method adopting formwork hanging method
CN104632251A (en) Integrally cast type mould plate trolley and construction method of concrete pouring of underground passage
CN109577342B (en) Swift supporting device of circular pit construction
CN104533460A (en) Construction method for concrete pouring of support-changing type formwork trolley and underground channel
CN104060781A (en) Cast-in-situ cranked slab stair without seams at stair sections and construction method
CN107516866A (en) A kind of Prefabricated cable duct
CN206844275U (en) Mutual buckle type precast concrete cover ditch and its suspender
CN109371910B (en) Ground-cushion height-filling protection and construction method
CN208563380U (en) A kind of self-propelled pipe gallery plate device
CN107558483B (en) A kind of construction method of building foundation that installing wallboard
CN107794945B (en) Movable assembly type template mounting and dismounting operation system and construction method thereof
CN209854577U (en) Assembled thin-wall box-shaped channel
KR101150829B1 (en) The mold with self-propelled type trolley for construction of retaining wall
CN209353364U (en) A kind of assembled case change basis
CN215210384U (en) Slip form concrete pouring device for drainage ditch
CN104929154B (en) Covered back-digging subway station totally-enclosed post one-time-concreting molding construction technique
CN110847065A (en) Prefabricated assembled box channel and construction method
CN203905331U (en) Cast-in-place plate-type staircase with seamless steps
CN107023061B (en) Assembled plastic municipal drainage inspection well and construction method
KR100928566B1 (en) Roof assembly and constructing method thereof
CN111119204B (en) Construction method of concrete arch framework revetment

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20170303

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20180202

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20190329

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20200128

Year of fee payment: 7