KR101268681B1 - Construction method of shore protection using soil-bag having geotextile - Google Patents
Construction method of shore protection using soil-bag having geotextile Download PDFInfo
- Publication number
- KR101268681B1 KR101268681B1 KR1020130033961A KR20130033961A KR101268681B1 KR 101268681 B1 KR101268681 B1 KR 101268681B1 KR 1020130033961 A KR1020130033961 A KR 1020130033961A KR 20130033961 A KR20130033961 A KR 20130033961A KR 101268681 B1 KR101268681 B1 KR 101268681B1
- Authority
- KR
- South Korea
- Prior art keywords
- stage
- geotextile
- bag
- soil
- filling material
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B3/00—Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
- E02B3/04—Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
- E02B3/12—Revetment of banks, dams, watercourses, or the like, e.g. the sea-floor
- E02B3/122—Flexible prefabricated covering elements, e.g. mats, strips
- E02B3/127—Flexible prefabricated covering elements, e.g. mats, strips bags filled at the side
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B3/00—Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
- E02B3/04—Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
- E02B3/10—Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like
- E02B3/106—Temporary dykes
- E02B3/108—Temporary dykes with a filling, e.g. filled by water or sand
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Revetment (AREA)
Abstract
Description
본 발명은 호안 축조 공법에 관한 것으로, 더욱 상세하게는 육상에서 토목섬유 안에 채움재를 채워 방파제 형태의 흙주머니를 제작하고, 이 흙주머니를 시공 현장으로 운반한 후 수중에 적치하는 방법을 통해 호안을 축조할 수 있는 다단 토목섬유를 이용한 흙주머니 호안 축조 공법에 관한 것이다.
The present invention relates to a revetment construction method, and more particularly, to fill the filling material in the geosynthetic fiber in the land to make a breakwater-type soil bag, and to transport the soil bag to the construction site and to carry out the revetment in water The present invention relates to a soil bag revetment construction method using multi-stage geosynthetic fibers.
종래에는 항만의 호안 및 방조제를 설치하기 위해 예를 들어 사석을 투하하여 기본 제방을 형성한 후 그 표면에 바다측에는 바윗돌 크기의 피복석을, 호안이 조성되는 매립지 측에는 매트와 잔자갈 또는 토사를 이용하여 호안 또는 방조제를 축조하였다.Conventionally, in order to install harbor revetment and seawalls, for example, sandstone is dropped to form a basic embankment. Or a scavenger was constructed.
상기와 같이 호안 축조시 수중의 바닥에 위치하는 제방 사석은 바위와 같이 직경이 큰 돌을 사용함으로서 호안 및 저수측의 물이 바다측으로 이동이 되면서 사석과 사석 사이에는 큰홀이 형성되어 벤츄리와 같은 작용을 함으로 유속이 빠르게 진행되는 문제점이 있다. 이 경우 유속을 차단하지 않으면 방조제 내측에 조성되는 호안을 매립시 투기되는 준설토가 유실될 뿐만 아니라 필터사석을 설치하기 위해 직경이 작은 사석을 투기할 경유 유실되는 양이 많아 골재의 낭비와 필터사석을 설치하는 공사기간이 길어져 공사비용이 증대되는 문제점과 축조된 호안이 세굴되어 방조제가 유실되는 문제점이 있었다.As described above, the embankment seats located on the bottom of the water during the revetment of the revetment are made of large diameters, such as rocks, so that the water in the revetment and the reservoir is moved to the sea side, and a large hole is formed between the relics. By doing so, there is a problem that the flow rate proceeds quickly. In this case, if the flow velocity is not blocked, the dredged soil that is dumped when the revetment is made inside the embankment is lost, and the amount of diesel oil that is dumped through the small-diameter sand to install the filter sand is largely lost. There was a problem of increasing the construction cost due to the long construction period, and a problem of loss of the dike due to scrubbing of the constructed revetment.
즉, 종래에는 호안 제방을 형성하기 위해 바지선에 또는 덤프트럭으로 사석을 적재하여 해상 위치까지 이동한 후 지정된 위치에 굴삭기 등을 이용하여 설계규격 및 구배로 수중 또는 수상에 투하하는 방법으로 시공하여 왔으나, 사석이 투하중에 유속에 의해 정 위치에 투하되지 못할 뿐만 아니라 유실되는 문제점이 있었다.In other words, in order to form a bank embankment, the sandstone was loaded on a barge or a dump truck to move to the offshore location, and then it was constructed by dropping underwater or in the water by design specifications and a gradient using an excavator at a designated location. In addition, there was a problem that the dead stone was not dropped in place due to the flow rate during the dropping, as well as lost.
그리고, 사석의 구입 비용이 고가이고, 다량의 사석이 사용됨에 따라 공사비용이 커지는 문제점도 있고, 석산의 채석을 통해서 사석을 공급함에 따라 환경이 파괴되는 문제점도 있다.In addition, there is a problem in that the purchase cost of the sandstone is expensive, and the construction cost increases as a large amount of the sandstone is used, and the environment is destroyed by supplying the sandstone through the quarrying of the stone.
아울러, 사석의 투하, 바다측의 피복석 투하, 매립지측의 매트(잔자갈, 토사)의 시공 등 여러방식의 작업을 필요로 하므로 시공성이 떨어지는 문제점도 있다.In addition, there is a problem in that the workability is inferior because it requires various types of work such as dropping of sandstones, coating stones on the sea side, and construction of mats (cobbles, earth and sand) on the landfill side.
또한, 매립지측에 있는 토사 등의 유실됨에 따라 부지의 안정성이 약하고 부지의 침하도 유발되며, 해양이 오염되는 문제점이 있다.In addition, due to the loss of the earth and sand on the landfill side, the stability of the site is weak, causing settlement of the site, there is a problem that the ocean is polluted.
이러한 문제점을 해결하기 위한 것으로 특허문헌 1이 있다.There is a patent document 1 to solve such a problem.
특허문헌1은 튜브구조체, 보조구조물, 보강구조물을 쌓아 방파제를 시공하는 것으로, 사석 등의 투기 적층으로 발생하는 문제점을 해결할 수는 있지만, 시공 현장의 수중에서 튜브구조체의 내부에 준설토를 주입하는 등 해상에서 제작이 이루어지기 때문에 파랑 등으로 인하여 작업이 어렵고 오랜 시간이 걸리는 문제점이 있고, 또한, 튜브구조체와 다른 보조구조물을 사용함에 따라 작업이 번거롭고 튜브구조체와 보조구조물 간의 결속력이 약하여 견실한 호안 구조물을 시공하지 못하는 문제점이 있다.
Patent Literature 1 stacks a tube structure, an auxiliary structure, and a reinforcement structure to construct a breakwater, and can solve problems caused by dumping of sandstones, etc., but injects dredged soil into the inside of the tube structure in the construction site. Because the production is made at sea, the work is difficult and takes a long time due to the blue, etc. Also, as the tube structure and other auxiliary structures are used, the work is cumbersome and the solid bond between the tube structure and the auxiliary structures is weak, which makes it a robust shore structure. There is a problem that can not be constructed.
본 발명은 전술한 바와 같은 문제점을 해결하기 위한 것으로, 육상에서 토목섬유 안에 채움재를 채워 방파제 형태의 흙주머니를 제작하고, 이 흙주머니를 시공 현장으로 운반한 후 수중에 적치하는 방법을 통해 호안을 축조함으로써 자갈과 토사가 유실되는 것을 방지하고 공기 단축과 용이한 높이 조정 등의 시공성을 향상할 수 있는 다단 토목섬유를 이용한 흙주머니 호안 축조 공법을 제공하려는데 그 목적이 있다.
The present invention is to solve the problems as described above, by filling the filling material in the geosynthetic fiber in the land to make a breakwater-type soil bag, and transport the soil bag to the construction site after the retreat through the method of placing it in water The purpose of the present invention is to provide a soil bag revetment construction method using multi-stage geosynthetic fibers that can prevent the loss of gravel and soil and improve the construction properties such as shortening the air and easy height adjustment.
본 발명에 의한 다단 토목섬유를 이용한 흙주머니 호안 축조 공법은, 육상에서 흙과 모래와 준설토를 포함하는 채움재 중 하나 이상이 채워지되, 상기 채움재가 토목섬유를 통해 2단 이상으로 격리되도록 채워진 흙주머니를 제작하되, 상기 토목섬유는 가장 아랫단의 제1토목섬유, 상기 제1토목섬유의 둘레부에 일측이 연쇄적으로 연결되는 다단의 토목섬유로 구성되는 제1단계와; 상기 제1단계를 통해 제작된 흙주머니를 해상으로 운반한 후 수중에 적치하여 시공하는 제2단계를 포함하고, 상기 제1단계는, 2단 이상의 채움이 가능하도록 구성된 토목섬유를 깔아 설치하되 채움재를 일정 높이로 채움 가능하도록 제1단 지지틀 안에 토목섬유의 가장 아랫단인 제1단 토목섬유를 깔아 설치하고, 상기 제1단 토목섬유 안에 제1단 채움재를 채운 후 상기 제1단 토목섬유의 둘레부를 올려 상기 제1단 채움재를 감싸 밀봉하여 제1단 호안백을 제작하는 제1-1단계, 상기 제1-1단계를 통해 제작된 제1단 호안백 위에 제2단 지지틀을 세우고 상기 제2지지틀 안에 제2단 채움재를 채운 후 상기 제1단 토목섬유의 둘레부에 연결된 제2단 토목섬유를 올려 상기 제2단 채움재를 감싸 밀봉하여 제2단 호안백을 제작하는 제1-2단계를 포함하여 이루어지는 것을 특징으로 한다.
In the soil bag revetment construction method using the multi-stage geosynthetic fiber according to the present invention, one or more of the filling material including soil, sand and dredged soil is filled in the land, the soil bag filled so that the filling material is isolated in two or more steps through the geosynthetic fiber Wherein, the geosynthetic fiber is the first step of the first geosynthetic fiber, the first step consisting of a multi-stage geosynthetic fiber which is connected to one side in the circumference of the first geosynthetic fiber; The first step includes a second step of carrying the soil bag produced by the first step to the sea and then loaded and installed in water, wherein the first step is to install the geotextiles configured to be filled in two or more stages, but the filling material And install the first stage geotextiles, which is the bottom end of the geosynthetic fibers, in the first stage support frame to fill the first stage support frame, and fill the first stage fill material in the first stage geotextiles of the first stage geotextiles. Raising the circumference to surround the first stage filling material to seal the first stage to produce the first stage revetment bag, the second stage support frame on the first stage revetment bag produced through the first-first step After filling the second stage filling material in the second support frame, the second stage geotextiles connected to the periphery of the first stage geotextiles are raised, and the second stage filling material is wrapped and sealed to manufacture the second stage revetment bag. Comprising two steps It characterized.
본 발명에 의한 다단 토목섬유를 이용한 흙주머니 호안 축조 공법에 의하면, 육상에서 토목섬유(호안 구조물의 높이에 맞도록 미리 봉재 등으로 구성)에 채움재(흙, 모래, 준설토 등)를 채워 밀봉한 흙주머니를 제작한 후, 제작된 흙주머니를 운반하여 수중에 적치하는 단일 작업을 통해 시공이 가능하므로 즉, 육상 작업(흙주머니 제작)과 해상 작업(흙주머니 적치)으로 구분되어 해상의 기상 조건 등의 제약을 받지 않고 신속한 시공이 가능하다.According to the soil bag revetment construction method using the multi-stage geosynthetic fiber according to the present invention, the soil filled with the filling material (soil, sand, dredged soil, etc.) in the land civil engineering fibers (consisting of the bar material, etc. in advance to match the height of the revetment structure) After the pouch is manufactured, it can be constructed by carrying out a single bag that is carried in the bag and carried it in water. That is, it is divided into land work (making bag) and sea work (bag of bag). Rapid construction is possible without being restricted.
특히, 아래 단의 토목섬유가 위단의 바닥부를 형성하여 즉 토목섬유가 아랫단과 위단에 공유하면서 일체화되어 채움재를 채우고 아래 단의 토목섬유를 덮어 밀봉하는 작업의 반복을 통해 원하는 높이(단)의 호안 구조물을 제작 시공할 수 있으며, 따라서, 수중 작업에 따른 불편함과 어려움을 해결할 수 있으므로 공기를 단축하고 공사비용을 절감할 수 있다.In particular, the geotechnical fibers of the lower stage form the bottom of the upper stage, that is, the geotextiles are integrated while sharing the lower and upper stages, filling the filling material, and covering and sealing the geotextiles of the lower stage. The structure can be manufactured and constructed, and therefore, inconveniences and difficulties due to underwater work can be solved, thereby shortening the air and reducing the construction cost.
그리고, 가격이 저렴한 흙을 이용하여 시공비용을 절감할 수 있고, 흙의 구입을 위한 환경파괴를 일으키지 않아 환경파괴로 인한 민원을 피할 수 있으며 수급이 원활하여 시공성이 향상된다.In addition, it is possible to reduce the construction cost by using low-cost soil, avoid the complaints caused by environmental destruction because it does not cause environmental destruction for the purchase of soil, and the supply and demand is smoothly improved construction.
아울러, 흙을 다단으로 채워 마감하는 단일 작업만을 통해 호안 시설물의 시공이 가능하여 공기를 단축하고 단일 종류의 장비만을 이용하여도 시공이 가능하므로 역시 시공성이 향상된다.In addition, construction of the revetment facility is possible through only a single operation of filling the soil with multiple stages, thereby shortening the air and using only a single type of equipment.
또한, 흙이 토목섬유 안에서 밖으로 누출되지 않게 되어 부지의 안정성을 확보할 수 있고 해양오염을 방지할 수 있다.
In addition, the soil does not leak out in the geosynthetic fiber can ensure the stability of the site and can prevent marine pollution.
도 1은 본 발명의 실시예에 의한 다단 토목섬유를 이용한 흙주머니 호안 축조 공법에 의한 흙주머니의 단면도.
도 2는 본 발명의 실시예에 의한 다단 토목섬유를 이용한 흙주머니 호안 축조 공법에 적용된 토목섬유의 단면도.
도 3은 본 발명의 실시예에 의한 다단 토목섬유를 이용한 흙주머니 호안 축조 공법에 적용된 흙주머니 제작 공정도.
도 4는 본 발명의 실시예에 의한 다단 토목섬유를 이용한 흙주머니 호안 축조 공법에 사석층과 피복층이 적용된 예시도.1 is a cross-sectional view of the soil bag by the soil bag revetment construction method using a multi-stage geosynthetic fiber according to an embodiment of the present invention.
Figure 2 is a cross-sectional view of the geosynthetic fiber applied to the soil bag revetment construction method using a multi-stage geosynthetic fiber according to an embodiment of the present invention.
Figure 3 is a soil bag manufacturing process applied to the soil bag revetment construction method using a multi-stage geosynthetic fiber according to an embodiment of the present invention.
Figure 4 is an exemplary diagram applied to the sand stone layer and the coating layer in the soil bag revetment construction method using a multi-stage geosynthetic fiber according to an embodiment of the present invention.
<실시예 1>≪ Example 1 >
본 발명에 따른 다단 토목섬유를 이용한 흙주머니 호안 축조 공법은 다음과 같다.Soil bag revetment construction method using multi-stage geosynthetic fiber according to the present invention is as follows.
1. 흙주머니 제작.1. Make a clay bag.
본 발명은 토목섬유 안에 채움재가 채워진 흙주머니를 수중에 설치하는 것으로 이루어지며, 도 1에서 보이는 것처럼, 흙주머니(10)는 2단 이상(이하에서는 3단을 예로 들어 설명함) 즉 제1단 내지 제3단 호안백(11,12,13)으로 구성된다. 흙주머니(10)의 제1 내지 제3호안백(11,12,13)은 각각의 채움재가 서로 격리되도록 채워지며 단 토목섬유는 하나로 구성된다.The present invention consists of installing the soil bag filled with the filling material in the geosynthetic fiber in water, as shown in Figure 1, the
이와 같은 구성의 흙주머니(10)는 상부로 갈수록 단면적이 좁아지는 형태로서 둘레부가 계단형 단면인 것이 바람직하다.The
도 2는 토목섬유(20)는 제1단 토목섬유(21), 제1단 토목섬유(21)의 둘레부에 연결되는 제2단 토목섬유(22), 제2단 토목섬유(22)의 둘레부에 연결되는 제3단 토목섬유(23)로 구성된다.2 is a
토목섬유(20)의 재질은 토목분야에서 사용되는 것과 동일한 재질(부직포 등)이며, 제1단 내지 제3단 호안백(11,12,13)을 일체로 구성하도록 제1단 내지 제3단 토목섬유(21,22,23)는 다음과 같이 연결 구성된다.The material of the
제1단 토목섬유(21)의 둘레부에는 제2단 토목섬유(22)가, 제2단 토목섬유(22)의 둘레부에는 제3단 토목섬유(23)가 연결된다.The
이때, 제2단 토목섬유(22)의 일측은 제1단 토목섬유(21)의 단부로부터 안쪽으로 이격된 곳에 재봉 등으로 연결되어 제1단 토목섬유(21)에는 제1단 채움재를 덮을 수 있는 덮음부(21a)가 구성된다.At this time, one side of the second stage
이와 마찬가지로 제2단 토목섬유(22)의 자유단부에도 덮음부(22a)가 구성되도록 제3단 토목섬유(23)가 연결된다.Similarly, the
제3단 토목섬유(23)는 자유단부가 서로 겹쳐지면서 제3단 채움재(13a)를 덮어 밀봉하도록 구성된다.The
제1단과 제2단 토목섬유(21,22)의 덮음부(21a,22a)는 채움재의 분실 등을 막기 위하여 겹이음을 통해 밀봉된다.Covering portions (21a, 22a) of the first and second stage geosynthetic fibers (21, 22) is sealed through the lap joint to prevent the loss of the filler material.
이와 같이 구성된 토목섬유(20)를 이용한 흙주머니의 제작 공정은 다음과 같다.The manufacturing process of the soil bag using the
완성된 흙주머니(10)를 운반 및 적치할 수 있도록 크레인 등의 장비를 사용할 것이며, 상기 크레인으로 흙주머니(10)를 운반할 수 있도록 인양로프 등을 육상의 지면에 깔아 설치한다.Equipment such as a crane will be used to carry and stow the finished
1. 제1단 호안백(11) 제작.1. Manufacture of the first stage Hoan bags (11).
도 3에서처럼, 제1단 토목섬유(21)의 둘레부에 제1단 지지틀(30)을 세워 설치한다. 제1단 지지틀(30)의 높이는 제1단 호안백(11)의 높이 이상인 것이 바람직하다.As shown in Figure 3, the first
제1단 토목섬유(21) 위, 제1단 지지틀(30) 안에 제1단 채움재(11a)를 채운다.The
제1단 토목섬유(21)의 덮음부(21a)를 제1단 채움재(11a) 위로 덮어 밀봉하되, 제1단 채움재(11a)가 외부로 누출되지 않도록 덮음부(21a)를 겹이음한 후 재봉 등으로 고정한다.
After covering the covering
2. 제2단 호안백 제작.2. Manufacture of the second stage lanyard.
제1단 호안백(11)은 제2단 호안백(12)의 바닥부를 조성하며, 제2단 지지틀(40)을 세워 설치하고, 제2단 채움재(12a)를 채운 후 덮음부(22a)를 덮어 겹이음으로 밀봉(재봉, 고정핀 등)함으로써 제2단 호안백(12)을 제작한다.
The first-
3. 제3단 호안백 제작.3. Manufacture 3rd tidal tiger bag.
제2단 호안백(12)은 제3단 호안백(13)의 바닥부를 조성하며, 제3단 지지틀(50)을 세워 설치하고, 제3단 채움재(13a)를 채운 후 제3단 토목섬유(23)를 덮어 밀봉함으로써 제3단 호안백(13)을 제작한다.The second-
이상의 공정을 통해 3단의 높이로 이루어진 흙주머니(10)를 완성하며, 인양벨트로 흙주머니(10)를 묶어 고정하여 인양을 준비한다.
Through the above process to complete the soil bag (10) consisting of three heights, by fixing the soil bag (10) with a lifting belt to prepare the salvage.
이렇게 제작된 흙주머니(10)를 바지선 등의 선박에 싣고 해상으로 운반한 후 수중에 적치하여 시공한다.
The soil bag (10) thus prepared is loaded on a ship such as a barge and transported to the sea, and then loaded and placed in water.
한편, 본 발명은 도 4에서처럼, 흙주머니(10)를 수중에 적치한 후 흙주머니(10)의 일측에 사석과 피복석(소파블록 등)을 일정 두께로 포설 및 설치하여 사석층(60)과 피복층(70)을 형성함으로써 보강할 수 있다.
On the other hand, the present invention, as shown in Figure 4, after placing the soil bag (10) in the water and then installed and installed a sandstone and coated stone (sofa block, etc.) in a predetermined thickness on one side of the soil bag (10) It can be reinforced by forming the
10 : 흙주머니, 11,12,13 : 제1단 내지 제3호안백
20 : 토목섬유, 21,22,23 : 제1단 내지 제3단 토목섬유
21a,22a : 덮음부, 30,40,50 : 제1단 내지 제3단 지지틀
60 : 사석층, 70 : 피복층 10: soil bag, 11, 12, 13: 1st to 3rd bag
20: geosynthetic fiber, 21, 22, 23: first to third stage geotextile
21a, 22a: covering portion, 30, 40, 50: first to third stage support frame
60: sandstone layer, 70: coating layer
Claims (4)
상기 제1단계를 통해 제작된 흙주머니를 해상으로 운반한 후 수중에 적치하여 시공하는 제2단계를 포함하고,
상기 제1단계는,
2단 이상의 채움이 가능하도록 구성된 토목섬유를 깔아 설치하되 채움재를 일정 높이로 채움 가능하도록 제1단 지지틀 안에 토목섬유의 가장 아랫단인 제1단 토목섬유를 깔아 설치하고, 상기 제1단 토목섬유 안에 제1단 채움재를 채운 후 상기 제1단 토목섬유의 둘레부를 올려 상기 제1단 채움재를 감싸 밀봉하여 제1단 호안백을 제작하는 제1-1단계,
상기 제1-1단계를 통해 제작된 제1단 호안백 위에 윗단용 지지틀을 세우고 상기 윗단용 지지틀 안에 채움재를 채운 후 상기 제1단 토목섬유의 둘레부에 연결된 윗단 토목섬유를 올려 상기 채움재를 감싸 밀봉하여 윗단 호안백을 제작하는 제1-2단계를 포함하되, 상기 윗단 호안백을 반복하여 3단 이상의 호안백을 형성하는 것을 특징으로 하는 다단 토목섬유를 이용한 흙주머니 호안 축조 공법.
One or more of the filling material including soil, sand and dredged soil is filled in the land, and the filling material is manufactured so that the filling material is segregated into two or more stages through the geotextile, wherein the geotextile is the first stage geotextile of the lowest stage. A first step consisting of multiple stages of geotextiles, one side of which is serially connected to the circumference of the first stage geotextiles;
And carrying the earth bag produced by the first step to the sea and then the second step of loading and laying in water,
In the first step,
Install the geosynthetic fiber configured to be filled in two or more stages, but install the first stage geosynthetic fiber, which is the bottom end of the geosynthetic fiber, in the first stage support frame to fill the filling material at a predetermined height, and the first stage geotextile Step 1-1, after filling the first stage filling material to raise the circumference of the first stage geosynthetic fiber to surround the first stage filling material and to seal the first stage filling material;
The upper end support frame is placed on the first end revetment bag manufactured through the first step 1-1, and the filling material is filled in the upper end support frame, and then the upper end geotextile connected to the circumference of the first end geotextile is raised to the filling material. A method of constructing a soil pocket using a multi-stage geosynthetic fiber, comprising: 1-2 steps of enveloping and enclosing the upper end revetment bag;
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020130033961A KR101268681B1 (en) | 2013-03-28 | 2013-03-28 | Construction method of shore protection using soil-bag having geotextile |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020130033961A KR101268681B1 (en) | 2013-03-28 | 2013-03-28 | Construction method of shore protection using soil-bag having geotextile |
Publications (1)
Publication Number | Publication Date |
---|---|
KR101268681B1 true KR101268681B1 (en) | 2013-05-29 |
Family
ID=48667066
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020130033961A KR101268681B1 (en) | 2013-03-28 | 2013-03-28 | Construction method of shore protection using soil-bag having geotextile |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR101268681B1 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113047315A (en) * | 2021-03-31 | 2021-06-29 | 上海交通大学 | Anti-skid waterproof woven geotextile bag suitable for expansive soil slope and construction method |
US11916508B1 (en) | 2017-03-13 | 2024-02-27 | Aquaenergy Llc | Underground pumped hydro storage |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004143702A (en) | 2002-10-22 | 2004-05-20 | Shohei Senda | Wall surface construction method using bagged soil, and wall surface structure using the bagged soil |
WO2009060228A1 (en) | 2007-11-09 | 2009-05-14 | Maelgwyn Mineral Services Limited | A method and device for dewatering and, drying a wet mineral concentrate |
KR101230275B1 (en) | 2010-06-28 | 2013-02-07 | 주식회사 젠트로 | Geotextile Tube Structure |
-
2013
- 2013-03-28 KR KR1020130033961A patent/KR101268681B1/en active IP Right Grant
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004143702A (en) | 2002-10-22 | 2004-05-20 | Shohei Senda | Wall surface construction method using bagged soil, and wall surface structure using the bagged soil |
WO2009060228A1 (en) | 2007-11-09 | 2009-05-14 | Maelgwyn Mineral Services Limited | A method and device for dewatering and, drying a wet mineral concentrate |
KR101230275B1 (en) | 2010-06-28 | 2013-02-07 | 주식회사 젠트로 | Geotextile Tube Structure |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US11916508B1 (en) | 2017-03-13 | 2024-02-27 | Aquaenergy Llc | Underground pumped hydro storage |
CN113047315A (en) * | 2021-03-31 | 2021-06-29 | 上海交通大学 | Anti-skid waterproof woven geotextile bag suitable for expansive soil slope and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104164851B (en) | The construction method of the ecological flexible mud-rock flow blocking dam of gabion arch | |
CN202706042U (en) | Improved rapid-construction causeway | |
RU2432431C2 (en) | Long-length device for marine and river hydraulic facilities and method of its manufacturing | |
CN203668885U (en) | Novel hydraulic reclamation mould bag | |
CN104164853B (en) | Ecological navigation channel revetment barricade and the method thereof of gabion box dress ecology bag and junked tire | |
KR20110120627A (en) | Method of construction for scour prevension and reinforcement of bridge pier, and structure of the same | |
KR101666626B1 (en) | Shore bank using frame and geotextile, and method for constructing this same | |
KR20160027646A (en) | Bank and method for the same using the geotextiles tube law for preventing coastal erosion | |
CN108999142A (en) | The construction method of dome rectangular light-duty caisson and pile foundation combined type deep water breakwater | |
KR101268681B1 (en) | Construction method of shore protection using soil-bag having geotextile | |
CN103397646B (en) | Technique for fast filling constructed wetland in shore area | |
AU2019203298A1 (en) | A method and system for underwater scour prevention | |
Heibaum | Coastal scour stabilisation using granular filter in geosynthetic nonwoven containers | |
KR101268235B1 (en) | Shore protection using soil-bag | |
CN201495521U (en) | Hinged large earth bags for river emergency and flood prevention | |
JP5868352B2 (en) | How to lay a road on the slope | |
KR20110046209A (en) | Method Of Construction For Scour Prevension And Reinforcement Of Bridge Pier, And Structure Of The Same | |
US10787781B2 (en) | Marine and river protection system and method of supporting coastal structures | |
KR100791264B1 (en) | Method for constructing pack filter in a tide embankment, shore protection works | |
CN105804003B (en) | A kind of width shoulder formula breakwater and its transportation installation method | |
KR20160128560A (en) | Reinforced earth retaining wall with blocks of structure frame and wire mesh | |
KR20020024136A (en) | Erosion control structures of coastal area and the construction methodology of erosion control structure and embankment by this structure | |
JP2009287364A (en) | Reinforcing soil wall and construction method | |
KR102231145B1 (en) | Crane and Structure Construction Method Using the Crane | |
JP2007051514A (en) | Long-sandbag drain reinforcing method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
A302 | Request for accelerated examination | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20160510 Year of fee payment: 4 |
|
FPAY | Annual fee payment |
Payment date: 20190508 Year of fee payment: 7 |