CN105804003B - A kind of width shoulder formula breakwater and its transportation installation method - Google Patents

A kind of width shoulder formula breakwater and its transportation installation method Download PDF

Info

Publication number
CN105804003B
CN105804003B CN201610167772.3A CN201610167772A CN105804003B CN 105804003 B CN105804003 B CN 105804003B CN 201610167772 A CN201610167772 A CN 201610167772A CN 105804003 B CN105804003 B CN 105804003B
Authority
CN
China
Prior art keywords
layer
dike
outer slope
breakwater
shoulder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201610167772.3A
Other languages
Chinese (zh)
Other versions
CN105804003A (en
Inventor
刘洪山
曹剑林
谢光华
黄远明
张联玖
王振红
郑玉河
张克浩
徐杰
王定武
卢普伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Fourth Harbor Engineering Co Ltd
Original Assignee
CCCC Fourth Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Fourth Harbor Engineering Co Ltd filed Critical CCCC Fourth Harbor Engineering Co Ltd
Priority to CN201610167772.3A priority Critical patent/CN105804003B/en
Publication of CN105804003A publication Critical patent/CN105804003A/en
Application granted granted Critical
Publication of CN105804003B publication Critical patent/CN105804003B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/18Making embankments, e.g. dikes, dams
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/11Hard structures, e.g. dams, dykes or breakwaters

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Revetment (AREA)

Abstract

A kind of wide shoulder formula breakwater of present invention offer and its transportation installation method, the width shoulder formula breakwater include:The sloping breakwater of trapezium structure, the sloping breakwater are respectively arranged with dike central layer, outer slope layer and wide shoulder layer outward by interior, and the outer slope layer is laid on the outer slope of the dike central layer, and the width shoulder layer is set to the side of the outer slope layer far from dike central layer;Two slabstones, inverted filter and rear packing layer are additionally provided on the inner slope of the dike central layer, two slabstone is set between the dike central layer and inverted filter, and the inverted filter is set between two slabstone and rear packing layer.The wide shoulder formula breakwater that the present invention is collectively formed by the wide shoulder layer formed by super boulder and more grain size block bank of stone bodies, its transportation installation method takes rational construction technology and a variety of heavy duty equipments realize precision-fit, can smoothly and be accurately performed construction, and construction speed is very fast, and the wind wave action of construction time is smaller to the influence for completing levee body section.

Description

A kind of width shoulder formula breakwater and its transportation installation method
Technical field
The present invention relates to a kind of breakwater more particularly to a kind of wide shoulder formula breakwater, and are related to the anti-wave of width shoulder formula The transportation installation method of dike.
Background technology
Sloping breakwater is the most common structural shape of harbour mole engineering.Wide shoulder sloping breakwater refer to Border on the sea the slightly above design high-water of side setting one and the platform with one fixed width, under certain wave action, permission dike Body section deforms, and gradually adapts to local Wave power condition and forms the novel inclined similar to S type dynamic equilibrium sections Formula breakwater.
For the artificial armour sloping breakwater of conventional concrete, it, which has, does not need the artificial mask block of concrete Body makes full use of building stones, cost to be substantially reduced and damages the advantages such as lighter under especially big wave action, and design concept embodies The Advanced Ideas such as resource makes full use of, construction machinery generalization and can repairing utilizes, are worthy to be popularized and answer in the breakwater of deep-sea Gear wave type formula.
But for stormy waves large area, to ensure breakwater, outer slope deformation is in control range under the wave action, deformation Line of slope is no more than dynamic equilibrium slope line, and armour stone weight is required sufficiently large, and sometimes up to 10t or more, this is for entirety Structure and transportation installation method are proposed prodigious challenge;In addition, larger stormy waves can make the completion of levee body section in construction At influence, construction precision is substantially reduced.
Invention content
The technical problem to be solved by the present invention is to need to provide a kind of firm wide shoulder formula breakwater reasonable for structure, and Accurately transportation installation method for realizing the width shoulder formula breakwater is provided.
In this regard, the present invention provides a kind of wide shoulder formula breakwater, including:The sloping breakwater of trapezium structure, the sloping breakwater by It is inside respectively arranged with dike central layer, outer slope layer and wide shoulder layer outward, the outer slope layer is laid on the outer slope of the dike central layer, institute It states wide shoulder layer and is set to the side of the outer slope layer far from dike central layer;Be additionally provided on the inner slope of the dike central layer two slabstones, Inverted filter and rear packing layer, two slabstone are set between the dike central layer and inverted filter, and the inverted filter is set to institute It states between two slabstones and rear packing layer.
Further improvement of the present invention is that the depth-width ratio gradient of the sloping breakwater is 1:1.5~1:2.
Further improvement of the present invention is that the thickness of two slabstone is 0.4~0.8m, and the thickness of the inverted filter is The depth-width ratio gradient of 0.7~0.9m, two slabstone and inverted filter is 1:1.5~1:2.Wherein, the thickness of two slabstone The thickness of preferably 0.5m or so, the inverted filter are 0.8m or so.
Further improvement of the present invention is that the dike central layer includes the dike that weight is made of the block stone of 1~1000kg The outer slope depth-width ratio gradient of the heart, the dike heart is 1:1.5~1:2, the inner slope depth-width ratio gradient of the dike central layer is 1:1.5~1: 2。
Further improvement of the present invention is, the outer slope layer includes the first outer slope layer and the second outer slope layer, described first The block stone that outer slope layer laying depth is 1.5~2.0m, weight is 300~1000kg is on the outer slope of the dike central layer;Described The two block stones that outer slope layer laying depth is 1.5~5.0m, weight is 1~5t in the described first outer separate dike central layer of slope layer one Side.
Further improvement of the present invention is that the depth-width ratio gradient of the first outer slope layer is 1:1.5~1:2, described Two outer slope layers use stair-stepping block of stone.
Further improvement of the present invention is, the wide shoulder layer is laid with super boulder that weight is 5~10t described the On two outer slope layers, there are the wide shoulders of 10m or more at the top of the width shoulder layer.
The present invention also provides a kind of transportation installation methods of wide shoulder formula breakwater, for realizing wide shoulder as described above The transport of formula breakwater and mounting process, and include the following steps:
Step S1, moving rock material;
Step S2 pushes away bull-dozer by mountain and push away filling out operation to interim dike and dike central layer;
Step S3, the block stone of dike heart material, outer slope layer, two slabstones and inverted filter is increased by excavator and loop wheel machine, Leveling and reason slope;
Step S4, the super boulder that the width shoulder layer in its working range is carried out using backacter are tentatively got rid of It throws, then remaining region is mended by long-armed backacter and is thrown;
The smart throwing of super boulder progress of step S5, loop wheel machine cooperation iron chains ring and Automated shackle to the wide shoulder layer, and In the construction of super boulder to when being only left last two layers, the building stones platform surface layer that the super boulder constructed is constituted is flattened, is led to It crosses backacter and is moved to the outermost of building stones platform and carry out the last placement for two layers surpassing boulder;
Step S6 is refuted using body is opened to the sloping breakwater outermost protection-apron progress jackstone;
Wherein, the outermost protection-apron of the sloping breakwater is the position that water is most deep on the outside of sloping breakwater;According to the interim dike The gear wave dike that the plan-position of wave direction and embankment is set up.
Further improvement of the present invention is, before construction, first carries out underwater dumped rockfill situation survey with loop wheel machine cooperation hanging basket Amount;Entire underwater dumped rockfill region is divided into the grid of 2.0m × 2.0m according to the amount of capacity of jackstone bucket, from sloping breakwater Arrange then seat in the plane, adjacent seat in the plane interval 20m use method of polar coordinates to carry out jackstone positioning in outer slope safe distance;By hanging The height of the height difference and underwater block stone between the elevation, underwater block stone and hanging basket of current hanging basket is measured on basket using survey dipsey lead Journey, and GPS positioning device is installed on loop wheel machine, accurately measure current position coordinates;After measuring underwater information, calculate corresponding The amount of stone thrown is mended needed for position, then the required information for mending jackstone material is depicted as table, the required packet for mending jackstone material It includes:Angle, distance and building stones quantity, and then jackstone task is completed by the cooperation of GPS positioning device.
Further improvement of the present invention is, the outer slope layer for placing wide shoulder layer is extended 3~4m more outward;Outermost The sequence of construction of block stone is carried out for ecto-entad, and ecto-entad is carried out first to place the bottom and outermost block of stone, then successively Next to putting block stone inwardly;After the completion of the block stone of the bottom is placed, then place block stone, position inward since outermost Block stone positioned at upper layer is pressed on the link position between two blocks of block stones of lower layer.
Compared with prior art, the beneficial effects of the present invention are:By the wide shoulder layer that is formed by super boulder and more The wide shoulder formula breakwater that grain size block bank of stone body collectively forms, transportation installation method take rational construction technology and a variety of Heavy duty equipment realizes precision-fit, smoothly and can be accurately performed construction, and construction speed is very fast, construction time Wind wave action is smaller to the influence for completing levee body section.
Description of the drawings
Fig. 1 is the cross section structure schematic diagram of an embodiment of the present invention;
Fig. 2 is the workflow schematic diagram of another embodiment of the invention;
Fig. 3 is the construction schematic diagram on the first outer slope stratification slope of another embodiment of the invention;
Fig. 4 is that the first outer slope layer of another embodiment of the invention hangs the construction schematic diagram of throwing;
Fig. 5 is half section of the second outer slope layer of another embodiment of the invention and the block stone of the first outer slope layer is got rid of below The construction schematic diagram of throwing;
Fig. 6 is that the body of opening of another embodiment of the invention refutes the construction schematic diagram for carrying out outermost protection-apron position jackstone;
Fig. 7 is that the second outer slope layer of another embodiment of the invention gets rid of the construction schematic diagram of throwing;
Fig. 8 is the construction schematic diagram of the wide shoulder layer of another embodiment of the invention.
Specific implementation mode
Below in conjunction with the accompanying drawings, the preferably embodiment of the present invention is described in further detail:
Embodiment 1:
As shown in Figure 1, this example provides a kind of wide shoulder formula breakwater, including:The sloping breakwater of trapezium structure, the sloping breakwater It is respectively arranged with dike central layer 1, outer slope layer and wide shoulder layer 4 outward by interior, the outer slope layer is laid on the outer slope of the dike central layer 1 On, the wide shoulder layer 4 is set to the side of the outer slope layer far from dike central layer 1;It is additionally provided on the inner slope of the dike central layer 1 Two slabstones 5, inverted filter 6 and rear packing layer 7, two slabstone 5 are set between the dike central layer 1 and inverted filter 6, it is described fall Filtering layer 6 is set between two slabstone 5 and rear packing layer 7.
The depth-width ratio gradient of sloping breakwater described in this example is 1:1.5~1:2.The thickness of two slabstone 5 is 0.4~0.8m, The thickness of the inverted filter 6 is 0.7~0.9m, and the depth-width ratio gradient of two slabstone 5 and inverted filter 6 is 1:1.5~1:2; Wherein, the thickness of two slabstone 5 is preferably 0.5m or so, and the thickness of the inverted filter 6 is 0.8m or so.The dike central layer 1 Including the dike heart that weight is made of the block stone of 1~1000kg, the outer slope depth-width ratio gradient of the dike heart is 1:1.5~1:2, institute The inner slope depth-width ratio gradient for stating dike central layer 1 is 1:1.5~1:2.
As shown in Figure 1, outer slope layer described in this example includes 2 and second outer slope layer 3 of the first outer slope layer, the first outer slope layer 2 The block stone that laying depth is 1.5~2.0m, weight is 300~1000kg is on the outer slope of the dike central layer 1;The second outer slope The block stone that 3 laying depth of layer are 1.5~5.0m, weight is 1~5t is in the described first 2 side far from dike central layer 1 of outer slope layer;Institute The depth-width ratio gradient for stating the first outer slope layer 2 is 1:1.5~1:2, the second outer slope layer 3 uses stair-stepping block of stone;The width Shoulder layer 4 is laid with super boulder that weight is 5~10t on the described second outer slope layer 3, the top of the wide shoulder layer 4 there are The wide shoulder of 10m or more, the wide shoulder of preferably reserved 15m.
Since the shoulder of the wide shoulder layer 4 of wide shoulder formula breakwater is arranged more than design high-water, convenient for being set with land It is standby that propelling method is taken gradually to be filled to off-lying sea, in most cases can throwing only be carried out with dump truck and bull-dozer etc., it is less Using loop wheel machine, therefore, construction speed is very fast, and the wind wave action of construction time is smaller on completing the influence of levee body section.
The width shoulder formula breakwater is the sloping breakwater of trapezoidal structure, determines the size in its section in turn according to the depth of water, Wide shoulder formula breakwater as shown in Figure 1, it is assumed that the depth of water in sea bed face is 12m, then the section of the wide shoulder formula breakwater can It is designed as being greater than or equal to 58m;At this point it is possible to which it is 2.3m left that a cross-sectional width, which is arranged, close to the side of sea bed in dike central layer 1 Right slope surface, and the dike central layer 1 is the flat of 5m or so extending cross-sectional width toward slope layer outer than first more than 2 on sea bed direction Platform enables to the structure of outer slope layer and stress more solid and reliable in this way;It is arranged close to the side of sea bed in the first outer slope layer 2 One cross-sectional width is the slope surface of 3.8m or so, and the first outer slope layer 2 is toward slope outer than second layer more than 3 on sea bed direction Extend the platform that cross-sectional width is 5m or so, likewise, setting is it is also possible that the structure and stress of outer slope layer are more steady in this way Gu reliable;The slope surface that one cross-sectional width is 7.5m or so is set close to the side of sea bed in the second outer slope layer 3, and described the Two outer slopes layers 3 toward extending the platform that cross-sectional width is 9~13.5m or so than wide shoulder layer more than 4 on sea bed direction, likewise, Setting enables to the structure of wide shoulder layer 4 and stress more solid and reliable in this way;It is set close to the side of sea bed in wide shoulder layer 4 The slope surface that a cross-sectional width is 13.5m or so is set, the shoulder cross-sectional width of the wide shoulder layer 4 is preferably 15m, the width shoulder It is provided with the slope surface that cross-sectional width is 6m or so between the shoulder of platform layer 4 and the top of the second outer slope layer 3.It is worth mentioning It is that the setting of the data such as the above thickness, the gradient and cross-sectional width is not independent from each other, there is phases between them Mutual relation, being not to say that can be obtained by simply testing or changing, and build the wide anti-wave of shoulder formula come in this way Dike effect is especially good, and sound construction is reliable, convenient for construction.
Embodiment 2:
As shown in Fig. 2, this example also provides a kind of transportation installation method of wide shoulder formula breakwater, for realizing such as embodiment The transport of wide shoulder formula breakwater described in 1 and mounting process, and include the following steps:
Step S1, moving rock material;
Step S2 pushes away bull-dozer by mountain and push away filling out operation to interim dike and dike central layer 1;
Step S3 adds the block stone of dike heart material, outer slope layer, two slabstones 5 and inverted filter 6 by excavator and loop wheel machine High, leveling and reason slope;
Step S4, the super boulder that the wide shoulder layer 4 in its working range is carried out using backacter are carried out tentatively Throwing is got rid of, then remaining region is mended by long-armed backacter and is thrown;
The smart throwing of super boulder progress of step S5, loop wheel machine cooperation iron chains ring and Automated shackle to the wide shoulder layer 4, and In the construction of super boulder to when being only left last two layers, the building stones platform surface layer that the super boulder constructed is constituted is flattened, is led to It crosses backacter and is moved to the outermost of building stones platform and carry out the last placement for two layers surpassing boulder;
Step S6 is refuted using body is opened to the sloping breakwater outermost protection-apron progress jackstone;
Wherein, the outermost protection-apron of the sloping breakwater is the position that water is most deep on the outside of sloping breakwater;According to the interim dike The gear wave dike that the plan-position of wave direction and embankment is set up.
In the step S1, the transport about building stones includes following sub-step:Step S101 by 150t loop wheel machines and goes to keep off The combination of plate dumper is realized, such as carries out the super boulder entruckings of 12~20t by 150t loop wheel machines, goes baffle dumper for substituting number It measures insufficient flat car and carries out super boulder transport;Step S102 is realized by CAT349 backhoes and mine vehicle combination, is such as passed through CAT349 backhoes carry out the entrucking of 12t or less boulders, and the transport of boulder is used for by mine vehicle;Step S103, by grabbing Bucket and mine vehicle combine to realize, the grab bucket conveniently carries out the entrucking of 12t or less boulders, and mine vehicle is used for bulk The transport of stone.The building stones refer to block stone.
In the installation process of block stone, including the following:The first, building stones sieve:It is specified stack region place 1t, The sample of a variety of Stone Standard Values such as 3t, 5t, 7t, 10t is compared to classify into row block stone and be stacked;The second, bull-dozer is pushed away to facing using mountain When dike and dike heart material push away filling out operation;Third, using PC200 excavators to dike heart material, outer slope layer, two slabstones 5 and inverted filter 6 Etc. small particles block stone increased, flattened and managed slope, the dike heart material refers to the block stone of dike central layer 1, i.e. the dike central layer 1 Building stones;4th carries out the super boulder in its working range using backacter tentatively gets rid of throwing, then is dug with 80t grades of long-armed backhoes Pick machine is mended remaining region and is thrown;5th, after backacter has carried out tentatively getting rid of throwing, then using 280t grades of loop wheel machines cooperation iron chains Ring and Automated shackle carry out smart throwing;6th when the construction of super boulder arrives only last two layers remaining, and the surface layer of building stones platform is whole Flat, the outermost that backacter is moved to platform is placed into row block stone;8th use is opened body and is refuted to sloping breakwater outermost protection-apron Carry out jackstone, the outermost protection-apron, that is, most deep position of water, near the position of sea bed.
In the installation process of block stone, the installation method of block stone:According to principle from bottom to top in section sequence of construction It carries out, in the interspersed arrangement construction of the crossover location of the block stone of different size;Subregion piecemeal arrangement carries out plane construction, and in guarantee The covering construction of layer structure must can carry out after the completion of substructure.Specifically sequence of construction is:The first, interim dike pushes away It fills out;The block stone of the dike central layer 1 of 2 1~1000kg, which pushes away, to be filled out;The block stone construction of the first outer slope layer 2 of 3 300~1000kg;The Four, two slabstones 5 and inverted filter 6 are constructed;5th, the block stone construction of the second of 1~5t the outer slope layer 3;6th, the wide shoulder of 5t or more The super boulder construction of layer 4.
This example, according to the construction features and working procedure of wide shoulder formula breakwater, is formed in entire sloped embankment construction Time and Multi-working-surface continuous productive process spatially, effect are very good.As shown in Figures 3 to 8 is exactly a kind of more excellent preferred The construction sequence of construction figure of the transportation installation method of wide shoulder formula breakwater, wherein what Fig. 3 was indicated is made by high-front shovel Industry carries out the slopes block Shi Li of the first outer slope layer 2 of 300~1000kg;What Fig. 4 was indicated is outside carry out 1~5t by loop wheel machine second The block stone of the first outer slope layer 2 of 3 300~1000kg of lower section of slope layer hangs throwing;What Fig. 5 was indicated is that high-front shovel carries out 1~5t The block stone of the first outer slope layer 2 of half section of the second outer slope layer 3 and below 300~1000kg gets rid of throwing;What Fig. 6 was indicated is to pass through It opens body and refutes progress outermost protection-apron position jackstone;What Fig. 7 was indicated is the second outer slope layer 3 that 1~5t is carried out by high-front shovel Block stone gets rid of throwing;Fig. 8 shows be jackstone and Li Po that high-front shovel carries out the wide shoulder layers of 5~10t and 1.9m or less 4;Fig. 3 is extremely In Fig. 8, what thick line outlined is the region of hot work in progress and the region finished of having constructed in current schematic diagram.
This example realizes Multi-working-surface continuous productive process over time and space, and according to on-site actual situations, system considers season The factors such as wind phase Lidar Equation, foundation pit exploitation of stone, mechanical equipment configuration and the reasonable overlap joint of process, entire sloped embankment construction process In in different elevation different locations can create several working faces simultaneously, independently working and taken according to process between each working face It connects to form continuous productive process, mechanical equipment work efficiency can be significantly improved, greatly speed up construction speed.
More specifically in practical operation, in building stones transportational process, the mark of setting mark different colours on transport vehicle Board, by the color of Sign Board on vehicle window can quick sub-material, reduce the time that transport vehicle on the way delays, improve Transportation Efficiency Rate.Large-scale backacter is equipped with wighing instrument, can be clear by the mating display screen of the instrument when backhoe triggers building stones The weight for seeing the block stone of Chu facilitates hand to be accurately controlled block stone specification, better ensures that block stone quality.Use 150t loop wheel machines When carrying out super boulder handling, using carrying out tying up button with choke chain.Pitching automatically for rope chain is can be realized as by controlling suspension hook, It avoids manually carrying out solution rope, accelerates lifting speed.It is assisted in addition, scene is equipped with a PC200, place cleaning and stirs block Stone carries out tying up button.
In the installation process of block stone, before construction, first underwater dumped rockfill situation measurement is carried out with loop wheel machine cooperation hanging basket;Root Entire underwater dumped rockfill region is divided into the grid of 2.0m × 2.0m according to the amount of capacity of jackstone bucket, is pacified on the outer slope from sloping breakwater Arrange then seat in the plane, adjacent seat in the plane interval 20m use method of polar coordinates to carry out jackstone positioning in full distance;By making on hanging basket Measure the elevation of the height difference and underwater block stone between the elevation, underwater block stone and hanging basket of current hanging basket with survey dipsey lead, and GPS positioning device is installed on loop wheel machine, accurately measures current position coordinates;After measuring underwater information, corresponding position institute is calculated The amount of stone of throwing need to be mended, then the required information for mending jackstone material is depicted as table, the required information for mending jackstone material includes:Angle Degree, distance and building stones quantity, and then jackstone task is completed by the cooperation of GPS positioning device.
It is noted that deposit is closing on construction area after the super boulder of the wide shoulder layer 4 goes out to transport to scene, keep away Exempting from secondary transhipment causes cost to increase;Since the thickness of this layer is big, backacter can not once construct in place, need to be divided into inside and outside It constructs from inside to outside for two layers;In order to realize that the construction of outer layer, long-armed backacter need telephone-moving to the top of super boulder Face.In order to reduce crawler belt damage of the excavator caused by the movement of block stone top surface, some discarded automobiles are placed in platform top surface Tire is protected.
It is noted that the super boulder installation of the wide shoulder layer 4 is generally with two backacters It carries out, is responsible for for one super boulder going to working face front porch area, another responsible block stone installation is dug to avoid installation backhoe The extra movement of pick machine.For the super boulder installation of two layers of stone of outermost according to sequence from outside to inside, from low to high, one piece is pushed down one Block, to reinforce the stability of slope surface;In order to increase wave absorbing effect, super boulder does not need the direction of adjustment block stone, adopts when installing It is not smooth drop-over between block stone but uneven to improve voidage with the mode placed at random.
When construction, when stormy waves can directly influence the construction of falling filtrate, this example is according to the flat of wave direction and embankment Face position is taken " segmentation encirclement method ", i.e., releases an interim dike every 200m in inside, longitudinal to release the unrestrained earth embankment of a gear again To ensure that the hydrostatic construction environment of inverted filter, while starting to widen backfill and weathering toward inside from these interim earth embankments Material starts to backfill in island in advance, can alleviate the spoir pressure of foundation pit significantly, accelerate construction speed.
During sloped embankment construction, dike heart material 1~1000kg building stones in face of heading sea are difficult to keep stability, construction speed slow And there are certain security risks.Therefore, two kinds of dimension stones of 1~1000kg and 300~1000kg are taken while being constructed, protection-apron Position 1~1000kg dike cardioliths are replaced using 300~1000kg block stones, carry out outside wave resistance with 300~1000kg blocks stone, significantly Construction efficiency is accelerated, working security is improved.
In order to ensure the safety of breakwater, prevents super boulder to be drawn to seabed by wave, wide shoulder will be placed in construction The platform of 1~5t blocks stone (the second outer slope layer 3) of the super boulder of layer 4 outward more extends 3~4m;In order to increase breakwater Stability, outermost lateral mass stone construction are that ecto-entad is carried out, i.e., first place the bottom, outermost boulder, then successively closely It and puts block stone inwardly;It after the completion of the block stone of the bottom is placed, then is placed since outermost, position is located at the block on upper layer Stone is pressed on the link position between two blocks of block stones of lower layer, and so on.
This example is prevented by the wide shoulder formula that the wide shoulder layer 4 formed by super boulder and more grain size block bank of stone bodies collectively form Wave dike, transportation installation method takes rational construction technology and a variety of heavy duty equipments realize precision-fit, Neng Goushun Profit and be accurately performed construction, and construction speed is very fast, the influence of the wind wave action of construction time to completion levee body section compared with It is small.
This example realizes a kind of wide shoulder sloping breakwater of practicality, uses middle super large-scale block stone and multistage block stone The combined transportation of multimachine tool and mounting technique, as shown in the table, the super large block needed in the construction of the width shoulder formula breakwater Stone and at different levels pieces of stones (1kg~10t) are respectively adopted first, loop wheel machine according to the size of transport block stone in transit and remove baffle certainly It unloads combination;The second, backacter and mine vehicle combination;Third, clamp excavator and mine vehicle combination.Root in the installation of block stone It is carried out respectively according to the characteristics of different mechanical equipments:The first, building stones sieve;The second, mountain, which pushes away bull-dozer and pushes away, fills out;Third, PC200 are anti- Shovel operation;4th, throwing is got rid of in long-armed backhoe;5th, loop wheel machine essence is thrown;6th, slope is managed in long-armed backhoe;7th, which opens body, refutes the operations such as jackstone Form.In addition, the characteristics of according to the multistage block stone of wide shoulder formula breakwater, this example interts peace according to sequence of construction from bottom to top Arrange the crossed construction of different size building stones;Meanwhile in entire sloped embankment construction, according to the construction features of wide shoulder formula breakwater And working procedure, time and Multi-working-surface continuous productive process spatially are formed, effect is very good.
The above content is a further detailed description of the present invention in conjunction with specific preferred embodiments, and it cannot be said that The specific implementation of the present invention is confined to these explanations.For those of ordinary skill in the art to which the present invention belongs, exist Under the premise of not departing from present inventive concept, a number of simple deductions or replacements can also be made, all shall be regarded as belonging to the present invention's Protection domain.

Claims (7)

1. a kind of transportation installation method of width shoulder formula breakwater, which is characterized in that for realizing the fortune of wide shoulder formula breakwater Defeated and mounting process, and include the following steps:
Step S1, moving rock material;
Step S2 pushes away bull-dozer by mountain and push away filling out operation to interim dike and dike central layer;
Step S3 increases the block stone of dike heart material, outer slope layer, two slabstones and inverted filter by excavator and loop wheel machine, is flattened With reason slope;
Step S4, the super boulder progress that the width shoulder layer in its working range is carried out using backacter tentatively get rid of throwing, Remaining region is mended by long-armed backacter again and is thrown;
Step S5, loop wheel machine coordinate iron chains ring and Automated shackle to carry out smart throwing to the super boulder of the wide shoulder layer, and super Boulder construction flattens the building stones platform surface layer that the super boulder constructed is constituted, by anti-to when being only left last two layers The outermost that shovel excavator is moved to building stones platform carries out the last placement for two layers surpassing boulder;
Step S6 is refuted using body is opened to sloping breakwater outermost protection-apron progress jackstone;
Wherein, the outermost protection-apron of the sloping breakwater is the position that water is most deep on the outside of sloping breakwater;The interim dike is according to wave The gear wave dike that direction and the plan-position of embankment are set up;
It is described width shoulder formula breakwater include:The sloping breakwater of trapezium structure, the sloping breakwater are respectively arranged with the dike heart outward by interior Layer, outer slope layer and wide shoulder layer, the outer slope layer are laid on the outer slope of the dike central layer, and the width shoulder layer is set to described Side of the outer slope layer far from dike central layer;Two slabstones, inverted filter and rear packing layer, institute are additionally provided on the inner slope of the dike central layer Two slabstones are stated to be set between the dike central layer and inverted filter, the inverted filter be set to two slabstone and rear packing layer it Between.
2. the transportation installation method of width shoulder formula breakwater according to claim 1, which is characterized in that the sloping breakwater The depth-width ratio gradient is 1:1.5~1:2.
3. the transportation installation method of width shoulder formula breakwater according to claim 1, which is characterized in that two slabstone Thickness is 0.4~0.8m, and the thickness of the inverted filter is 0.7~0.9m, and the depth-width ratio gradient of two slabstone and inverted filter is equal It is 1:1.5~1:2.
4. the transportation installation method of the wide shoulder formula breakwater according to claims 1 to 3 any one, which is characterized in that The dike central layer includes the dike heart that weight is made of the block stone of 1~1000kg, and the outer slope depth-width ratio gradient of the dike heart is 1: 1.5~1:2, the inner slope depth-width ratio gradient of the dike central layer is 1:1.5~1:2.
5. the transportation installation method of the wide shoulder formula breakwater according to claims 1 to 3 any one, which is characterized in that The outer slope layer includes the first outer slope layer and the second outer slope layer, and the first outer slope layer laying depth is 1.5~2.0m, weight is The block stone of 300~1000kg is on the outer slope of the dike central layer;The second outer slope layer laying depth is 1.5~5.0m, weight For 1~5t block stone in the described first outer slope side of the layer far from dike central layer.
6. the transportation installation method of width shoulder formula breakwater according to claim 5, which is characterized in that the first outer slope The depth-width ratio gradient of layer is 1:1.5~1:2, the second outer slope layer uses stair-stepping block of stone.
7. the transportation installation method of width shoulder formula breakwater according to claim 5, which is characterized in that the width shoulder layer The super boulder that laying weight is 5~10t is on the described second outer slope layer, and there are 10m's or more at the top of the width shoulder layer Wide shoulder.
CN201610167772.3A 2016-03-22 2016-03-22 A kind of width shoulder formula breakwater and its transportation installation method Expired - Fee Related CN105804003B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610167772.3A CN105804003B (en) 2016-03-22 2016-03-22 A kind of width shoulder formula breakwater and its transportation installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610167772.3A CN105804003B (en) 2016-03-22 2016-03-22 A kind of width shoulder formula breakwater and its transportation installation method

Publications (2)

Publication Number Publication Date
CN105804003A CN105804003A (en) 2016-07-27
CN105804003B true CN105804003B (en) 2018-08-24

Family

ID=56454651

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610167772.3A Expired - Fee Related CN105804003B (en) 2016-03-22 2016-03-22 A kind of width shoulder formula breakwater and its transportation installation method

Country Status (1)

Country Link
CN (1) CN105804003B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109113020B (en) * 2018-08-28 2020-07-03 中交上海航道局有限公司 Seaport breakwater structure and construction method thereof
CN114718012A (en) * 2022-05-05 2022-07-08 中交第四航务工程勘察设计院有限公司 Composite dyke body ecological sea dike structure on soft soil foundation and construction method thereof

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201738284U (en) * 2010-07-14 2011-02-09 沈迪州 Parapet wall with permeable anti-sliding plate
CN202012067U (en) * 2011-02-16 2011-10-19 谢怀东 Slope-type breakwater structure
JP5519613B2 (en) * 2011-10-24 2014-06-11 株式会社不動テトラ Wave-absorbing structure for long-period wave countermeasures
CN104499459A (en) * 2014-12-22 2015-04-08 中国水利水电第八工程局有限公司 Geotextile tube breakwater
CN205636635U (en) * 2016-03-22 2016-10-12 中交第四航务工程局有限公司 Wide shoulder formula breakwater

Also Published As

Publication number Publication date
CN105804003A (en) 2016-07-27

Similar Documents

Publication Publication Date Title
CN102305075A (en) Vertical shaft construction method under unfavorable geological condition
CN1773022A (en) Fast soft foundation dyke building method and technology
CN109113020B (en) Seaport breakwater structure and construction method thereof
CN109780325A (en) A kind of water factory's water intaking tunnel submarine pipeline installation method
CN105970900A (en) Offshore wind turbine gravity type foundation installation seabed treatment process
CN105568805B (en) A method of it is repaired based on circuit embankment along the river is carried out using container
CN110284547A (en) The construction method of intake pipe
CN102561379A (en) Novel bridge installation foundation and construction method thereof
CN106245652B (en) A kind of construction method of deep foundation pit earthwork digging near a river
CN105804003B (en) A kind of width shoulder formula breakwater and its transportation installation method
KR101169023B1 (en) Method for installing soil nailing and tunnel prevent hole for tidal plant
CN104878779B (en) The anti-silting cover plate of immersed tube tunnel rubble bedding cover type, anti-silting system and construction method
CN110331991A (en) Ultra-shallow earth-covered lower big section tube coupling crosses the river the riverbed preprocess method of jacking construction
CN207919486U (en) A kind of deep water soft soil foundation quay wall structure
CN205636635U (en) Wide shoulder formula breakwater
CN106609506A (en) Method for sea reclamation by using caissons
CN202610677U (en) Auxiliary tool for soft soil earthwork construction
CN104612128B (en) Vacuum preloading reinforcement construction method applicable to underwater silt environment
CN110438857A (en) A kind of Freeway of Mountain Range steel reinforcement cage stalagmite stake and its construction technology
CN109680647A (en) A kind of Construction at ports technique convenient for later maintenance
CN100582382C (en) Process for constructing quickly consolidated temperory horizontal platform by picking clay of lake bottom
KR101268681B1 (en) Construction method of shore protection using soil-bag having geotextile
CN204510181U (en) A kind of phytal zone drilling platform
KR102231145B1 (en) Crane and Structure Construction Method Using the Crane
JP2003171918A (en) Back-fill structure and back-fill construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180824

Termination date: 20210322