CN109680647A - A kind of Construction at ports technique convenient for later maintenance - Google Patents

A kind of Construction at ports technique convenient for later maintenance Download PDF

Info

Publication number
CN109680647A
CN109680647A CN201811568873.7A CN201811568873A CN109680647A CN 109680647 A CN109680647 A CN 109680647A CN 201811568873 A CN201811568873 A CN 201811568873A CN 109680647 A CN109680647 A CN 109680647A
Authority
CN
China
Prior art keywords
construction
caisson
foundation trench
ports
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811568873.7A
Other languages
Chinese (zh)
Inventor
卢璐
杨兆鹏
邓晗
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dalian Jiaotong University
Original Assignee
Dalian Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dalian Jiaotong University filed Critical Dalian Jiaotong University
Priority to CN201811568873.7A priority Critical patent/CN109680647A/en
Publication of CN109680647A publication Critical patent/CN109680647A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • E02B3/068Landing stages for vessels
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/12Back-filling of foundation trenches or ditches
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • E02D23/08Lowering or sinking caissons

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Revetment (AREA)
  • Underground Or Underwater Handling Of Building Materials (AREA)

Abstract

The invention discloses a kind of Construction at ports techniques convenient for later maintenance, include the following steps: step 1, and foundation trench, which excavates, prepares construction;Step 2 excavates foundation trench;Step 3, rubble-mound foundation construction;Step 4, Caisson;Step 5, the backfill of rear rib body and superstructure installation;Wherein in above-mentioned step one, it is determined by the width and depth that calculate and verify to foundation trench, edge at foundation trench excavation carries out the construction of pumping plant, after pumping plant is set up, in the ferry at harbour and the harbour of maintenance carries out that cofferdam is filled and steel sheet pile is set, while making a construction channel;Wherein in above-mentioned step two, channel is laid in foundation trench using rock ballast and other materials and is constructed, and carries out excavation of earthwork using excavator, the present invention, convenient for the later maintenance to harbour, the quality of Construction at ports is effectively increased, can guarantee Construction at ports safety and stability, efficient progress.

Description

A kind of Construction at ports technique convenient for later maintenance
Technical field
The present invention relates to Construction at ports technical field, specially a kind of Construction at ports technique convenient for later maintenance.
Background technique
Harbour is to be located at sea, and river, river, lake, reservoir is littoral, and there is water route through transport equipment and condition to pass in and out for safety of ship It is assembly place and the hinge of land and water transportation with the transportation junction berthed, the distribution centre of industrial and agricultural products and import and export values of foreign trade goods and materials, Vessel berth, handling goods, upper and lower passenger, the place to replenish the provisions, Construction at ports have more operation at sea, completion time of project ratio It is shorter, to Construction at ports quality control bring very big difficulty, it cannot be guaranteed that Construction at ports safety and stability, efficiently into Row, therefore, designing a kind of convenient for the Construction at ports technique of later maintenance is necessary.
Summary of the invention
The purpose of the present invention is to provide a kind of Construction at ports techniques convenient for later maintenance, to solve above-mentioned background technique The problem of middle proposition.
To achieve the above object, the invention provides the following technical scheme:
A kind of Construction at ports technique convenient for later maintenance includes the following steps: step 1, and foundation trench, which excavates, prepares construction; Step 2 excavates foundation trench;Step 3, rubble-mound foundation construction;Step 4, Caisson;Step 5, the backfill of rear rib body and top Structure installation;
Wherein in above-mentioned step one, it is determined by the width and depth that calculate and verify to foundation trench, in foundation trench Edge at excavation carries out the construction of pumping plant, and after pumping plant is set up, in the ferry at harbour and the harbour of maintenance is enclosed Weir is filled and steel sheet pile is set, while making a construction channel;
Wherein in above-mentioned step two, channel is laid in foundation trench using rock ballast and other materials and is constructed, and Excavation of earthwork is carried out using excavator, periodically the absolute altitude of foundation trench and position are measured, timely processing of finding the problem;
Wherein in above-mentioned step three, the throwing of stone is carried out using excavator and the truck cooperation for transporting building stones, Guarantee the smooth of bedding during throwing;
Wherein in above-mentioned step four, caisson handling is refuted into place to side, is transported to the caisson of needs using barge specified Scene is carefully checked component gauge size and bedding top surface etc., is measured to construction site, and according to practical survey The control baseline that parameter grasps caisson placing is measured, the position of caisson placing is positioned using theodolite or total station immediately, Caisson sinking is controlled to bedding face, then carries out caisson backfill;
Wherein in above-mentioned step five, the backfill of rear rib body is carried out after caisson placement is stablized, according to the heavy of caisson Drop amount determines breastwork anticipated settlement and hypsokinesis amount, then carries out the superstructures such as cable duct, gutter, track girder, bollard Installation.
According to the above technical scheme, in the step 2, foundation trench side slope is determined according to the ratio of 1:6 or 1:4, if construction Its bearing capacity of the submarine soil layer in location is relatively high, then should change side slope ratio, reduces and excavates.
According to the above technical scheme, in the step 3, foundation trench deposit, absolute altitude and its ruler are carried out before bedding jackstone Very little inspection then should immediately clear up mud, when finding that foundation ditch back silting amount is greater than the design standard of engineering if bedding The stress ratio foundation load more hour of top surface, construction cannot be below 0.6m, otherwise cannot be less than 1.2m.
According to the above technical scheme, in the step 4, in the sinking watching of caisson, the levelness of caisson is controlled, Ensure horizontal sinking, when caisson sinking is to bedding face, need to check the lateral of caisson, longitudinal direction and torsional angle, controls Deviation processed is within the scope of specification and design requirement.
According to the above technical scheme, in the step 4, when caisson backfills, backfill material should select the block stone of 10kg-100kg Material, and harmful substance is free of in its material, caisson retaining wall is made of reinforcing bar and angle steel, and in caisson partition wall Or exterior wall top surface is installed.
According to the above technical scheme, in the step 5, in one layer of inverted filter of outgoing arrangement of rib body, inverted filter is by two Stone and graded broken stone or graded sand and stone composition, two slabstone thickness are not less than 0.4m, and graded broken stone thickness is not less than 0.3m.
Compared with prior art, the beneficial effects of the present invention are: it is of the invention, by calculating and verify to the width of foundation trench and Depth is determined, and edge at foundation trench excavation carries out the construction of pumping plant, after pumping plant is set up, in the ferry at harbour with And the harbour of maintenance carries out that cofferdam is filled and steel sheet pile is set, while making a construction channel;Using rock ballast and its His material is laid with channel in foundation trench and constructs, and carries out excavation of earthwork using excavator, periodically to the absolute altitude of foundation trench and position It sets and measures, timely processing of finding the problem;The throwing of stone is carried out using excavator and the truck cooperation for transporting building stones, is being thrown Guarantee the smooth of bedding during filling out;Caisson handling is refuted into place to side, the caisson of needs is transported into specified scene using barge, Component gauge size and bedding top surface etc. are carefully checked, construction site is measured, and is joined according to actual measurement Number grasps the control baseline of caisson placing, positions immediately using theodolite or total station to the position of caisson placing, controls Then caisson sinking carries out caisson backfill to bedding face;The backfill that rib body in rear is carried out after caisson placement is stablized, according to caisson Settling amount determine breastwork anticipated settlement and hypsokinesis amount, then carry out cable duct, gutter, track girder, the tops such as bollard The installation of structure;The present invention effectively increases the quality of Construction at ports convenient for the later maintenance to harbour, can guarantee that harbour is applied Work safety and stability, efficient progress.
Detailed description of the invention
Fig. 1 is process flow chart of the invention.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
Referring to Fig. 1, the present invention provides a kind of technical solution:
A kind of Construction at ports technique convenient for later maintenance includes the following steps: step 1, and foundation trench, which excavates, prepares construction; Step 2 excavates foundation trench;Step 3, rubble-mound foundation construction;Step 4, Caisson;Step 5, the backfill of rear rib body and top Structure installation;
Wherein in above-mentioned step one, it is determined by the width and depth that calculate and verify to foundation trench, in foundation trench Edge at excavation carries out the construction of pumping plant, and after pumping plant is set up, in the ferry at harbour and the harbour of maintenance is enclosed Weir is filled and steel sheet pile is set, while making a construction channel;
Wherein in above-mentioned step two, channel is laid in foundation trench using rock ballast and other materials and is constructed, and Excavation of earthwork is carried out using excavator, periodically the absolute altitude of foundation trench and position are measured, timely processing of finding the problem;
Wherein in above-mentioned step three, the throwing of stone is carried out using excavator and the truck cooperation for transporting building stones, Guarantee the smooth of bedding during throwing;
Wherein in above-mentioned step four, caisson handling is refuted into place to side, is transported to the caisson of needs using barge specified Scene is carefully checked component gauge size and bedding top surface etc., is measured to construction site, and according to practical survey The control baseline that parameter grasps caisson placing is measured, the position of caisson placing is positioned using theodolite or total station immediately, Caisson sinking is controlled to bedding face, then carries out caisson backfill;
Wherein in above-mentioned step five, the backfill of rear rib body is carried out after caisson placement is stablized, according to the heavy of caisson Drop amount determines breastwork anticipated settlement and hypsokinesis amount, then carries out the superstructures such as cable duct, gutter, track girder, bollard Installation.
According to the above technical scheme, in step 2, foundation trench side slope is determined according to the ratio of 1:6 or 1:4, if where construction Its bearing capacity of the submarine soil layer on ground is relatively high, then should change side slope ratio, reduces and excavates.
According to the above technical scheme, in step 3, foundation trench deposit, absolute altitude and its size are carried out before bedding jackstone It checks, when finding that foundation ditch back silting amount is greater than the design standard of engineering, then mud should be cleared up immediately, if bedding top surface Stress ratio foundation load more hour, construction cannot be below 0.6m, otherwise 1.2m cannot be less than.
According to the above technical scheme, in step 4, in the sinking watching of caisson, the levelness of caisson is controlled, it is ensured that Level sink, once caisson sinking arrive bedding face when, need to check the lateral of caisson, longitudinal direction and torsional angle, control partially Difference is within the scope of specification and design requirement.
According to the above technical scheme, in step 4, when caisson backfills, backfill material should select the block stone material of 10kg-100kg Matter, and harmful substance is free of in its material, makes caisson retaining wall of reinforcing bar and angle steel, and in caisson partition wall or It installs person's exterior wall top surface.
According to the above technical scheme, in step 5, in one layer of inverted filter of outgoing arrangement of rib body, inverted filter by two slabstones and Graded broken stone or graded sand and stone composition, two slabstone thickness are not less than 0.4m, and graded broken stone thickness is not less than 0.3m.
Based on above-mentioned, it is an advantage of the current invention that it is of the invention, by calculating and verifying width and the depth progress to foundation trench It determines, edge at foundation trench excavation carries out the construction of pumping plant, after pumping plant is set up, in the ferry at harbour and maintenance Harbour carries out that cofferdam is filled and steel sheet pile is set, while making a construction channel;Existed using rock ballast and other materials It is laid with channel in foundation trench to construct, and carries out excavation of earthwork using excavator, periodically the absolute altitude of foundation trench and position are surveyed Amount, timely processing of finding the problem;The throwing of stone is carried out using excavator and the truck cooperation for transporting building stones, in the process of throwing It is middle to guarantee the smooth of bedding;Caisson handling is refuted into place to side, the caisson of needs is transported into specified scene using barge, to member type Number size and bedding top surface etc. are carefully checked, and are measured to construction site, and grasped according to actual measurement parameter it is heavy The control baseline of case installation, immediately positions the position of caisson placing using theodolite or total station, controls caisson sinking To bedding face, caisson backfill is then carried out;The backfill that rib body in rear is carried out after caisson placement is stablized, according to the settling amount of caisson It determines breastwork anticipated settlement and hypsokinesis amount, then carries out the peace of the superstructures such as cable duct, gutter, track girder, bollard Dress;The present invention effectively increases the quality of Construction at ports convenient for the later maintenance to harbour, can guarantee that Construction at ports is steady safely It is fixed, efficient to carry out.
It should be noted that, in this document, relational terms such as first and second and the like are used merely to a reality Body or operation are distinguished with another entity or operation, are deposited without necessarily requiring or implying between these entities or operation In any actual relationship or order or sequence.Moreover, the terms "include", "comprise" or its any other variant are intended to Non-exclusive inclusion, so that the process, method, article or equipment including a series of elements is not only wanted including those Element, but also including other elements that are not explicitly listed, or further include for this process, method, article or equipment Intrinsic element.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with A variety of variations, modification, replacement can be carried out to these embodiments without departing from the principles and spirit of the present invention by understanding And modification, the scope of the present invention is defined by the appended.

Claims (6)

1. a kind of Construction at ports technique convenient for later maintenance includes the following steps: step 1, foundation trench, which excavates, prepares construction;Step Rapid two, excavate foundation trench;Step 3, rubble-mound foundation construction;Step 4, Caisson;Step 5, the backfill of rear rib body and top knot Structure installation;It is characterized by:
It wherein in above-mentioned step one, is determined by the width and depth that calculate and verify to foundation trench, is excavated in foundation trench The edge at place carries out the construction of pumping plant, and after pumping plant is set up, in the ferry at harbour and the harbour of maintenance carries out cofferdam and fills out It builds and steel sheet pile is set, while making a construction channel;
Wherein in above-mentioned step two, channel is laid in foundation trench using rock ballast and other materials and is constructed, and is utilized Excavator carries out excavation of earthwork, periodically measures to the absolute altitude of foundation trench and position, timely processing of finding the problem;
Wherein in above-mentioned step three, the throwing of stone is carried out using excavator and the truck cooperation for transporting building stones, in throwing During guarantee bedding it is smooth;
Wherein in above-mentioned step four, caisson handling is refuted into place to side, the caisson of needs is transported into specified scene using barge, Component gauge size and bedding top surface etc. are carefully checked, construction site is measured, and is joined according to actual measurement Number grasps the control baseline of caisson placing, positions immediately using theodolite or total station to the position of caisson placing, controls Then caisson sinking carries out caisson backfill to bedding face;
Wherein in above-mentioned step five, the backfill of rear rib body is carried out after caisson placement is stablized, according to the settling amount of caisson It determines breastwork anticipated settlement and hypsokinesis amount, then carries out the peace of the superstructures such as cable duct, gutter, track girder, bollard Dress.
2. a kind of Construction at ports technique convenient for later maintenance according to claim 1, it is characterised in that: the step 2 In, foundation trench side slope is determined according to the ratio of 1:6 or 1:4, if its bearing capacity of the submarine soil layer in construction location is relatively high, Side slope ratio should be changed, reduce and excavate.
3. a kind of Construction at ports technique convenient for later maintenance according to claim 1, it is characterised in that: the step 3 In, the inspection of foundation trench deposit, absolute altitude and its size is carried out before bedding jackstone, once discovery foundation ditch back silting amount is greater than engineering Design standard when, then mud should be cleared up immediately, if the stress ratio foundation load more hour of bedding top surface, construction not 0.6m can be lower than, otherwise 1.2m cannot be less than.
4. a kind of Construction at ports technique convenient for later maintenance according to claim 1, it is characterised in that: the step 4 In, in the sinking watching of caisson, control the levelness of caisson, it is ensured that level is sunk, when caisson sinking is to bedding face, It needs to check the lateral of caisson, longitudinal direction and torsional angle, control deviation is within the scope of specification and design requirement.
5. a kind of Construction at ports technique convenient for later maintenance according to claim 1, it is characterised in that: the step 4 In, when caisson backfills, backfill material should select the block stone material matter of 10kg-100kg, and harmful substance is free of in its material, use Reinforcing bar and angle steel make caisson retaining wall, and are installed in caisson partition wall or exterior wall top surface.
6. a kind of Construction at ports technique convenient for later maintenance according to claim 1, it is characterised in that: the step 5 In, in one layer of inverted filter of outgoing arrangement of rib body, inverted filter is made of two slabstones and graded broken stone or graded sand and stone, and two slabstones are thick Degree is not less than 0.4m, and graded broken stone thickness is not less than 0.3m.
CN201811568873.7A 2018-12-21 2018-12-21 A kind of Construction at ports technique convenient for later maintenance Pending CN109680647A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811568873.7A CN109680647A (en) 2018-12-21 2018-12-21 A kind of Construction at ports technique convenient for later maintenance

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811568873.7A CN109680647A (en) 2018-12-21 2018-12-21 A kind of Construction at ports technique convenient for later maintenance

Publications (1)

Publication Number Publication Date
CN109680647A true CN109680647A (en) 2019-04-26

Family

ID=66188628

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811568873.7A Pending CN109680647A (en) 2018-12-21 2018-12-21 A kind of Construction at ports technique convenient for later maintenance

Country Status (1)

Country Link
CN (1) CN109680647A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112854117A (en) * 2021-01-09 2021-05-28 中铁广州工程局集团有限公司 L-shaped wharf construction method
CN113186876A (en) * 2021-03-23 2021-07-30 中船第九设计研究院工程有限公司 Construction method of floating dock anchoring facility

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101130991A (en) * 2006-08-24 2008-02-27 中船第九设计研究院 Caisson cofferdam based on prepacked foundation bed
CN103374900A (en) * 2012-04-13 2013-10-30 中交第三航务工程勘察设计院有限公司 Gravity wharf built on silt foundation and method for constructing gravity wharf
CN105970900A (en) * 2016-06-16 2016-09-28 江苏海上龙源风力发电有限公司 Offshore wind turbine gravity type foundation installation seabed treatment process

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101130991A (en) * 2006-08-24 2008-02-27 中船第九设计研究院 Caisson cofferdam based on prepacked foundation bed
CN103374900A (en) * 2012-04-13 2013-10-30 中交第三航务工程勘察设计院有限公司 Gravity wharf built on silt foundation and method for constructing gravity wharf
CN105970900A (en) * 2016-06-16 2016-09-28 江苏海上龙源风力发电有限公司 Offshore wind turbine gravity type foundation installation seabed treatment process

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
成嶂旻: "港口重力式码头的工程建设", 《中国高新技术企业》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112854117A (en) * 2021-01-09 2021-05-28 中铁广州工程局集团有限公司 L-shaped wharf construction method
CN112854117B (en) * 2021-01-09 2022-06-03 中铁广州工程局集团有限公司 L-shaped wharf construction method
CN113186876A (en) * 2021-03-23 2021-07-30 中船第九设计研究院工程有限公司 Construction method of floating dock anchoring facility

Similar Documents

Publication Publication Date Title
CN106120859B (en) Construction method for river crossing by multi-pipe-section immersed tube
CN102691300B (en) Construction method of foundation pit earthwork
CN102605697A (en) Sand dredger filling construction method of soft soil foundation embankment
CN105672195A (en) Underwater cutter-suction type dredging construction method for urban ecological river
CN102430277B (en) Coarse grid sunk well for physically processing waste water and construction method thereof
CN108505529A (en) A kind of construction method of the bearing platform construction steel cofferdam of Through Steel case arch bridge
CN109680647A (en) A kind of Construction at ports technique convenient for later maintenance
CN102561379A (en) Novel bridge installation foundation and construction method thereof
CN113047215B (en) High stake pier structure of medium plate stake
CN108166507A (en) The construction system and its method of construction of coral reef piping lane foundation pit
CN210288280U (en) Open type cofferdam-free coral sand island reef reclamation system
Clark et al. 41. The Whitby cliff stabilisation and coast protection scheme
CN202263468U (en) Coarse screen open caisson for physical wastewater treatment
Rosa et al. River bank stabilization utilizing rock vanes in puerto rico
Patil et al. Construction and Maintenance of Port Structures
Jurgensen 95% DESIGN REPORT LABRANCHE EAST MARSH CREATION PROJECT (PO-75)
McArthur Geotechnical challenges in reclamation of a soft soil site
Zaťko FOUNDATION OF THE NEW RAILWAY BRIDGE OVER THE NOSICKÁ DAM ON THE RIVER VÁH
Lopes et al. The port of Leixões (Portugal): over 120 years of knowledge
De Leeuw et al. Reclamation on Soft Subsoil by Spraying Thin Layers of Sand: The" IJburg" Project near Amsterdam
Cochrane et al. DUBAI DRY DOCK: DESIGN AND CONSTRUCTION.
Ospina et al. Optimized Design Addresses Site and Constructability Challenges for Container Wharf in Iraq
CN104563077B (en) A kind of phytal zone drilling platform and construction method thereof
CN110258725A (en) Water works water tank fabrication and installation method
IRWIN CHILDS et al. REDCAR ORE TERMINAL.

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190426

RJ01 Rejection of invention patent application after publication