KR101229095B1 - Inner roof system for reactor containment building of nuclear power plant - Google Patents

Inner roof system for reactor containment building of nuclear power plant Download PDF

Info

Publication number
KR101229095B1
KR101229095B1 KR1020100106412A KR20100106412A KR101229095B1 KR 101229095 B1 KR101229095 B1 KR 101229095B1 KR 1020100106412 A KR1020100106412 A KR 1020100106412A KR 20100106412 A KR20100106412 A KR 20100106412A KR 101229095 B1 KR101229095 B1 KR 101229095B1
Authority
KR
South Korea
Prior art keywords
lug
nuclear power
power plant
sump
containment building
Prior art date
Application number
KR1020100106412A
Other languages
Korean (ko)
Other versions
KR20120045090A (en
Inventor
이명호
오보환
최장규
이장복
Original Assignee
주식회사 동아스트
(주)대우건설
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 동아스트, (주)대우건설 filed Critical 주식회사 동아스트
Priority to KR1020100106412A priority Critical patent/KR101229095B1/en
Publication of KR20120045090A publication Critical patent/KR20120045090A/en
Application granted granted Critical
Publication of KR101229095B1 publication Critical patent/KR101229095B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction
    • E04G21/242Safety or protective measures preventing damage to building parts or finishing work during construction for temporarily covering the whole worksite, e.g. building, trench
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction
    • E04G21/28Safety or protective measures preventing damage to building parts or finishing work during construction against unfavourable weather influence
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B7/00Roofs; Roof construction with regard to insulation
    • E04B7/16Roof structures with movable roof parts
    • E04B7/166Roof structures with movable roof parts characterised by a translation movement of the movable roof part, with or without additional movements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B7/00Roofs; Roof construction with regard to insulation
    • E04B7/18Special structures in or on roofs, e.g. dormer windows

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

본 발명은 원자력 발전소의 격납건물 구간용 내부지붕 시스템에 관한 것으로서, 특히 원자력 발전소의 격납건물을 형성하기 위하여 다단으로 결합된 CLP에 설치되는 내부지붕 시스템에 있어서, 상기 CLP의 내측면에서 등간격으로 설치되는 러그와; 상면이 개방된 원통형으로 형성되고, 외측면에 상기 러그와 대향되는 위치에 복수의 케이블 고리가 설치되는 집수통과; 상기 러그와 일단이 연결되고, 타단이 상기 집수통에 연결되어 상기 집수통을 부양시키는 서스펜션 케이블; 및 상기 서스펜션 케이블의 상부에 결합되는 지붕막으로 이루어지는 것을 특징으로 한다.
상기와 같은 본 발명에 따르면 원자력 발전소 시공시 격납건물 CLP의 내측면 상하단에서 등간격으로 서스펜션 케이블의 일단을 설치하고, 각각의 서스펜션 케이블의 타단을 격납건물 CLP의 중심에 집수정이 위치하도록 연결하며, 상기 집수정의 저면에 수중 펌프를 설치후, 서스펜션 케이블의 상면에 지붕막을 설치함으로써 강우시에도 작업이 가능하도록 하여 공기를 단축시킬 수 있다.
The present invention relates to an internal roof system for a containment building section of a nuclear power plant, and more particularly, to an internal roof system installed in CLPs coupled in multiple stages to form a containment building of a nuclear power plant, at equal intervals on an inner surface of the CLP. Lugs installed; A water collecting tube having an upper surface formed in an open cylindrical shape, and having a plurality of cable loops installed at a position opposite to the lug on an outer surface thereof; A suspension cable having one end connected to the lug and the other end connected to the sump to support the sump; And a roof film coupled to the upper portion of the suspension cable.
According to the present invention as described above, one end of the suspension cable is installed at equal intervals at the upper and lower ends of the inner surface of the containment building CLP during the construction of the nuclear power plant, and connects the other end of each suspension cable to the center of the containment building CLP. After installing the submersible pump on the bottom surface of the sump, the roof membrane is installed on the upper surface of the suspension cable so that the air can be shortened in case of rainfall.

Description

원자력 발전소의 격납건물 구간용 내부지붕 시스템{INNER ROOF SYSTEM FOR REACTOR CONTAINMENT BUILDING OF NUCLEAR POWER PLANT}INNER ROOF SYSTEM FOR REACTOR CONTAINMENT BUILDING OF NUCLEAR POWER PLANT}

본 발명은 원자력 발전소의 격납건물 구간용 내부지붕 시스템에 관한 것으로서, 상세하게는 원자력 발전소 시공시 격납건물 CLP의 내측면 상하단에서 등간격으로 서스펜션 케이블의 일단을 설치하고, 각각의 서스펜션 케이블의 타단을 격납건물 CLP의 중심에 집수정이 위치하도록 연결하며, 상기 집수정의 저면에 수중 펌프를 설치후, 서스펜션 케이블의 상면에 지붕막을 설치하도록 하는 원자력 발전소의 격납건물 구간용 내부지붕 시스템에 관한 것이다.The present invention relates to an internal roof system for a containment building section of a nuclear power plant. Specifically, one end of a suspension cable is installed at equal intervals at the upper and lower ends of the inner surface of the containment building CLP during the construction of a nuclear power plant, and the other end of each suspension cable is installed. The present invention relates to an internal roof system for a containment section of a nuclear power plant that connects a sump to a center of a containment CLP, and installs a water pump on a bottom of the sump, and installs a roof membrane on an upper surface of a suspension cable.

세계적으로 에너지 관련 사항은 항상 중요한 이슈로 대두되고 있다. 중국을 위시한 개발도상국 및 모든 산업국가에서 이를 해결하기 위해 꾸준히 노력하고 있다. 특히 지구온난화의 주범으로 지목되는 탄소배출을 줄이기 위해 기존의 화력발전을 대체하는 연구개발을 하고 있으나, 그 중에서도 가능성이 있는 대체 에너지 자원으로는 원자력, 풍력, 태양광/태양열, 지열, 조력, 수소에너지 등을 꼽을 수 있다. 그러나 현재 경제성 및 현실성의 관점에서 원자력에너지 개발이 가장 선두에 있으며, 각 나라마다 원자력발전소의 건설에 박차를 가하고 있는 실정이다.Globally, energy-related issues are always an important issue. Developing countries, including China, and all industrial countries are constantly working to resolve them. In particular, we are conducting research and development to replace existing thermal power plants to reduce carbon emissions, which are considered as the main culprit of global warming. Among them, potential alternative energy sources are nuclear, wind, solar / solar, geothermal, tidal, and hydrogen Energy, etc. However, in terms of economics and practicality, nuclear energy development is at the forefront, and each country is accelerating the construction of nuclear power plants.

세계적으로 원자력발전소 건설을 추진하고 있는 국가를 살펴보면 다음과 같다. 중국의 경우 2020년까지 32기, 2050년까지 150기를 건설할 예정이고, 미국도 2020년까지 10기를 건설할 계획이다. 또한 한국에서 현재 가동중인 원전 20기 이외에 신고리 3, 4호기, 신월성 1, 2호기와, 신울진 1, 2호기가 건설 중이며, 계속해서 신고리 5, 6호기가 건설 준비 중에 있다. 특히 고리 한 지역에서만 향후 기존의 4호기를 포함해 1, 2호기가 건설되는 세계적으로 유래 없는 원자력발전소 타운이 생기게 되는 것이다. 국제원자력기구(IAEA)에서는 앞으로 25년 이내에 300기 정도의 새로운 원자력발전소를 기대한다고 한다.The countries that are promoting the construction of nuclear power plants in the world are as follows. China plans to build 32 units by 2020 and 150 units by 2050, while the United States plans to build 10 units by 2020. In addition to the 20 nuclear power plants currently in operation in Korea, Shingori Units 3 and 4, Shinwolseong Units 1 and 2, and Shin-Uljin Units 1 and 2 are under construction, while Shingori Units 5 and 6 are under construction. In particular, there will be a globally unprecedented nuclear power plant town where Units 1 and 2, including the existing Unit 4, will be built. The International Atomic Energy Agency (IAEA) expects about 300 new nuclear power plants within the next 25 years.

가히 원자력 르네상스가 도래하고 있다고 말할 수 있겠다. 세계에서 가장 많은 원자력발전소를 보유하고 있는 미국에서도 최근 수십 년 동안 원자력발전소 건설을 한 사례가 없는 반면에 한국에서는 계속해서 원전건설을 추진하고 있었다. 더구나 국내의 경우는 미국, 프랑스(Framatome) 및 캐나다(CANDU) 시스템의 다양한 원전이 건설 및 운영되고 있어 세계적으로 주목받고 있는 실정이다.I can say that the nuclear renaissance is coming. In the United States, which has the largest number of nuclear power plants in the world, no nuclear power plants have been built in recent decades, while South Korea has continued to build nuclear power plants. Moreover, in the case of Korea, various nuclear power plants of the US, France, and Canada (CANDU) systems are being constructed and operated.

국내의 원자력발전소는 초기에 고리원전을 시작해 다양한 원전형태의 건설 및 운영 경험으로 인해 많은 기술이 축적되어 있으며, 최근에 이러한 기술이 세계적으로 인정되어 UAE에 한국형 원자력발전소가 진출하게 되는 쾌거를 이룩하게 되었다.Nuclear power plants in Korea started with Kori Nuclear Power Plant in the early stages, and many technologies have been accumulated due to various construction and operation experiences of various types of nuclear power plants. Recently, these technologies have been recognized globally, and the Korean nuclear power plant has entered the UAE. It became.

원자력발전소 건설은 안전을 최우선으로 확보하기 위한 설계 및 운전이 필수적인 과제이다. 체르노빌 및 TMI 사고 이후, 특히 원자로가 들어가는 격납건물(RCB·Reactor Containment Building)의 중요성이 한층 주목받고 있는 상황이다. 원자력발전소의 격납건물은 압력유지 및 방사성물질의 유출을 방지하는 마지막 보루이다. 원전의 격납건물 건설에 있어서 안전성뿐만 아니라 경제성을 고려하지 않을 수 없다. 특히 원전 수출 및 국내 건설에 있어서 가장 중요한 건설 공기 단축 원자력발전소의 구조건전성 및 안전성을 확보하는데 있어서 격납건물의 중요한 목적은 방사성물질의 유출을 방지하는 최후의 보루 역할을 한다는 것이다.Nuclear power plant construction is an essential task to design and operate to ensure safety first. After the Chernobyl and TMI accidents, the importance of the reactor containment building (RCB), especially for nuclear reactors, is drawing more attention. The containment building of a nuclear power plant is the last bulwark to maintain pressure and prevent the release of radioactive material. In the construction of containment of nuclear power plants, not only safety but also economics must be considered. In particular, the most important purpose of the containment building in securing structural integrity and safety of nuclear power plants, which is the most important for nuclear power plant export and domestic construction, is to act as a last resort to prevent the leakage of radioactive materials.

또한 원전의 격납건물 건설에 있어서 고려해야 될 가장 중요한 인자는 안전성과 경제성이다. 이러한 목표를 달성하기 위해, CLP(Containment Liner Plate) 공법이 개발되어 적용되었다. 이 공법은 건설기간 단축, 비용 절감 및 구조건전성을 확보하는 계기가 되었다. 그리고 이러한 공법을 바탕으로 국내건설 뿐만 아니라 원전 수출에 커다란 기여를 하게 되었다.In addition, the most important factors to be considered in the construction of containment of nuclear power plants are safety and economics. To achieve this goal, a CLP (Containment Liner Plate) method was developed and applied. This construction method has helped to shorten the construction period, reduce costs and ensure structural health. Based on this construction method, it contributed not only to domestic construction but also to nuclear power plant exports.

그러나, 최근에 발주되는 원자력 구조물은 촉박한 공기로 발주되고 있는 데, 우리나라 기후가 아열대 기후로 변환되면서, 우천일수가 증가되고, 우천일수 증가가 공기지연의 큰 원인이 되고 있는 문제점이 있다.However, the recently ordered nuclear structure is being ordered by the tight air, there is a problem that the number of rainy days, the increase in the number of rainy days is a major cause of air delay as the climate of Korea is converted to subtropical climate.

본 발명은 상기와 같은 문제점을 해결하기 위한 것으로, 원자력 발전소 시공시 격납건물 CLP의 내측면 상하단에서 등간격으로 서스펜션 케이블의 일단을 설치하고, 각각의 서스펜션 케이블의 타단을 격납건물 CLP의 중심에 집수정이 위치하도록 연결하며, 상기 집수정의 저면에 수중 펌프를 설치후, 서스펜션 케이블의 상면에 지붕막을 설치함으로써 강우시에도 작업이 가능하도록 하여 공기를 단축시킬 수 있도록 하는 원자력 발전소의 격납건물 구간용 내부지붕 시스템을 제공하는데 그 목적이 있다.The present invention is to solve the above problems, the installation of one end of the suspension cable at equal intervals in the upper and lower ends of the inner surface of the containment building CLP during the construction of the nuclear power plant, the other end of each of the suspension cable is housed in the center of the containment building CLP For the containment section of the nuclear power plant which connects the crystal to the location, installs a submersible pump on the bottom of the sump, and installs a roof membrane on the upper surface of the suspension cable so that the operation can be performed even in the rain, so that the air can be shortened. The purpose is to provide an internal roof system.

상기와 같은 목적을 달성하기 위한 본 발명의 특징은,According to an aspect of the present invention,

원자력 발전소의 격납건물을 형성하기 위하여 다단으로 결합된 CLP에 설치되는 내부지붕 시스템에 있어서, 상기 CLP의 내측면에서 등간격으로 설치되는 러그와; 상면이 개방된 원통형으로 형성되고, 외측면에 상기 러그와 대향되는 위치에 복수의 케이블 고리가 설치되는 집수통과; 상기 러그와 일단이 연결되고, 타단이 상기 집수통에 연결되어 상기 집수통을 부양시키는 서스펜션 케이블; 및 상기 서스펜션 케이블의 상부에 결합되는 지붕막으로 이루어지는 것을 특징으로 한다.An internal roof system installed in CLPs coupled in multiple stages to form a containment building of a nuclear power plant, comprising: lugs installed at equal intervals on an inner surface of the CLP; A water collecting tube having an upper surface formed in an open cylindrical shape, and having a plurality of cable loops installed at a position opposite to the lug on an outer surface thereof; A suspension cable having one end connected to the lug and the other end connected to the sump to support the sump; And a roof film coupled to the upper portion of the suspension cable.

여기에서, 상기 러그는 Here, the lug is

상기 러그는, 상기 CLP의 상단에 설치되는 상부 러그와; 상기 상부 러그의 하단에 설치되는 하부 러그로 이루어진다.The lug, the upper lug is installed on the upper end of the CLP; It consists of a lower lug installed on the lower end of the upper lug.

여기에서 또한, 상기 러그는 상기 지붕막의 인양후 재설치시 상기 하부 러그만을 해체하여 상기 하부 러그를 상기 상부 러그 상단에 설치한다.Here, the lug dismantles only the lower lug upon re-installation after lifting of the roof film to install the lower lug on top of the upper lug.

여기에서 또, 상기 집수통은 내부 저면에 수중 모터가 설치되고, 상기 CLP의 측면에 고정된 배수관이 상기 수중 모터와 연결된다.Here, the sump is provided with an underwater motor on an inner bottom thereof, and a drain pipe fixed to the side of the CLP is connected to the underwater motor.

여기에서 또, 상기 서스펜션 케이블은 상기 러그의 상부 러그 및 하부 러그에 각각 체결되어 상기 집수통을 중심으로 경사지게 형성되어 상기 지붕막의 중심부가 하향 경사를 이루도록 설치된다.Here, the suspension cable is fastened to the upper lug and the lower lug of the lug, respectively, and is formed to be inclined around the sump, so that the center of the roof film is inclined downward.

여기에서 또, 상기 지붕막은 빛을 투과하는 막 재질로 8각 형태로 형성되고, 중앙부에 상기 집수통으로 우수를 배수하는 배수홀이 형성되며, 측면으로 자재 투입이 가능하도록 일측에 자재투입구가 형성된다.Here, the roof membrane is formed of an octagonal shape of a membrane material that transmits light, and a drainage hole for draining rainwater through the sump is formed at the center, and a material inlet is formed at one side to allow material input to the side. do.

상기와 같이 구성되는 본 발명인 원자력 발전소의 격납건물 구간용 내부지붕 시스템에 따르면, 원자력 발전소 시공시 격납건물 CLP의 내측면 상하단에서 등간격으로 서스펜션 케이블의 일단을 설치하고, 각각의 서스펜션 케이블의 타단을 격납건물 CLP의 중심에 집수정이 위치하도록 연결하며, 상기 집수정의 저면에 수중 펌프를 설치후, 서스펜션 케이블의 상면에 지붕막을 설치함으로써 강우시에도 작업이 가능하도록 하여 공기를 단축시킬 수 있다.According to the internal roof system for the containment building section of the nuclear power plant of the present invention configured as described above, one end of the suspension cable is installed at equal intervals in the upper and lower ends of the inner surface of the containment building CLP during the construction of the nuclear power plant, and the other end of each suspension cable The catchment is connected to the center of the containment building CLP, and the water pump is installed on the bottom of the catchment, and a roof membrane is installed on the upper surface of the suspension cable, so that the air can be shortened in case of rainfall.

도 1은 본 발명에 따른 원자력 발전소의 격납건물 구간용 내부지붕 시스템의 구성을 나타낸 측단면도이다.
도 2는 본 발명에 따른 원자력 발전소의 격납건물 구간용 내부지붕 시스템의 구성을 나타낸 사시도이다.
도 3은 본 발명에 따른 원자력 발전소의 격납건물 구간용 내부지붕 시스템중 집수정의 구성을 나타낸 사시도이다.
도 4 내지 도 7은 본 발명에 따른 원자력 발전소의 격납건물 구간용 내부지붕 시스템의 설치 과정을 나타낸 설명도이다.
1 is a side cross-sectional view showing the configuration of the internal roof system for the containment building section of the nuclear power plant according to the present invention.
Figure 2 is a perspective view showing the configuration of the internal roof system for the containment building section of the nuclear power plant according to the present invention.
Figure 3 is a perspective view showing the configuration of the sump of the inner roof system for the containment building section of the nuclear power plant according to the present invention.
4 to 7 are explanatory views showing the installation process of the internal roof system for the containment building section of the nuclear power plant according to the present invention.

이하, 본 발명에 따른 원자력 발전소의 격납건물 구간용 내부지붕 시스템의 구성을 첨부된 도면을 참조하여 상세하게 설명하면 다음과 같다.Hereinafter, the configuration of the internal roof system for the containment building section of the nuclear power plant according to the present invention will be described in detail with reference to the accompanying drawings.

하기에서 본 발명을 설명함에 있어, 관련된 공지 기능 또는 구성에 대한 구체적인 설명이 본 발명의 요지를 불필요하게 흐릴 수 있다고 판단되는 경우에는 그 상세한 설명은 생략할 것이다. 그리고 후술되는 용어들은 본 발명에서의 기능을 고려하여 정의된 용어들로서 이는 사용자, 운용자의 의도 또는 관례 등에 따라 달라질 수 있다. 그러므로 그 정의는 본 명세서 전반에 걸친 내용을 토대로 내려져야 할 것이다.In the following description of the present invention, detailed description of known functions and configurations incorporated herein will be omitted when it may make the subject matter of the present invention rather unclear. The following terms are defined in consideration of the functions of the present invention, and may be changed according to the intentions or customs of the user, the operator, and the like. Therefore, the definition should be based on the contents throughout this specification.

도 1은 본 발명에 따른 원자력 발전소의 격납건물 구간용 내부지붕 시스템의 구성을 나타낸 측단면도이고, 도 2는 본 발명에 따른 원자력 발전소의 격납건물 구간용 내부지붕 시스템의 구성을 나타낸 사시도이며, 도 3은 본 발명에 따른 원자력 발전소의 격납건물 구간용 내부지붕 시스템중 집수정의 구성을 나타낸 사시도이다.1 is a side cross-sectional view showing the configuration of the internal roof system for the containment building section of the nuclear power plant according to the present invention, Figure 2 is a perspective view showing the configuration of the internal roof system for the containment building section of the nuclear power plant according to the present invention, 3 is a perspective view showing the configuration of a water collecting well of the internal roof system for the containment building section of the nuclear power plant according to the present invention.

도 1 내지 도 3을 참조하면, 본 발명에 따른 원자력 발전소의 격납건물 구간용 내부지붕 시스템(1)은, 러그(10)와, 집수통(20)과, 서스펜션 케이블(30)과, 지붕막(40)으로 구성된다.1 to 3, the inner roof system 1 for the containment building section of the nuclear power plant according to the present invention includes a lug 10, a sump 20, a suspension cable 30, and a roof membrane. It consists of 40.

먼저, 러그(10)는 CLP(50)의 상단에 설치되는 상부 러그(11)와, 상부 러그(11)의 하단에 설치되는 하부 러그(13)로 구성된다. 여기에서, 본 발명에 따른 원자력 발전소의 격납건물 구간용 내부지붕 시스템(1)은 인양이 가능한 데, 인양시 러그(10)중 하부 러그(13)만을 해체하여 하부 러그(13)를 상부 러그(11)의 상단에 설치한다.
First, the lug 10 is composed of an upper lug 11 installed at the upper end of the CLP 50 and a lower lug 13 installed at the lower end of the upper lug 11. Here, the internal roof system 1 for the containment building section of the nuclear power plant according to the present invention is capable of lifting, by dismantling only the lower lug 13 of the lug 10 when lifting the lower lug 13 to the upper lug ( 11) Install on top.

그리고, 집수통(20)은 도 3에 도시된 바와 같이 상면이 개방된 원통형으로 형성되고, 외측면에 러그(10)와 대향되는 위치에 복수의 케이블 고리(21)가 설치된다. 여기에서, 집수통(20)은 내부 저면에 수중 모터(23)가 설치되고, CLP(50)의 측면에 고정된 배수관(25)이 수중 모터(23)와 연결된다.
And, as shown in Figure 3, the sump 20 is formed in a cylindrical shape with an upper surface open, and a plurality of cable hooks 21 are installed in a position opposite to the lug 10 on the outer surface. Here, the sump 20 is provided with an underwater motor 23 on the inner bottom, and the drain pipe 25 fixed to the side of the CLP 50 is connected to the underwater motor 23.

또한, 서스펜션 케이블(30)은 상부 러그(11) 및 하부 러그(13)와 일단이 각각 연결되고, 각각의 타단이 집수통(20)의 케이블 고리(21)에 연결되어 집수통(20)을 부양시킨다. 여기에서, 서스펜션 케이블(30)은 상부 러그(11) 및 하부 러그(13)에 각각 체결되어 집수통(20)을 중심으로 경사지게 형성되어 하기에서 설명할 지붕막(40)의 중심부가 하향 경사를 이루도록 설치된다.In addition, one end of the suspension cable 30 is connected to the upper lug 11 and the lower lug 13, and the other end thereof is connected to the cable hook 21 of the sump 20 to connect the sump 20. Provide support. Here, the suspension cable 30 is fastened to the upper lug 11 and the lower lug 13 to be inclined about the sump 20, so that the center of the roof film 40 to be described below is inclined downward. It is installed to achieve.

또, 지붕막(40)은 빛을 투과하는 막 재질로 8각 형태로 형성되고, 중앙부에 집수통(20)으로 우수를 배수하는 배수홀(41)이 형성되어 서스펜션 케이블(30)의 상부에 결합되고, 측면으로 자재 투입이 가능하도록 일측에 자재투입구(43)가 형성된다. 이때, 지붕막(40)은 선택에 따라 CLP(50) 상부를 모두 덮는 크기로 형성될 수도 있다.
In addition, the roof membrane 40 is formed of an octagonal shape of a membrane material that transmits light, and a drainage hole 41 for draining rainwater to the sump 20 is formed at the center of the roof membrane 40. Combined, the material input port 43 is formed on one side to enable the material input to the side. In this case, the roof film 40 may be formed to have a size to cover all of the top of the CLP 50 according to the selection.

이하, 본 발명에 따른 원자력 발전소의 격납건물 구간용 내부지붕 시스템의 설치 과정을 첨부된 도면을 참조하여 상세하게 설명하면 다음과 같다.Hereinafter, the installation process of the internal roof system for the containment building section of the nuclear power plant according to the present invention will be described in detail with reference to the accompanying drawings.

도 4 내지 도 7은 본 발명에 따른 원자력 발전소의 격납건물 구간용 내부지붕 시스템의 설치 과정을 나타낸 설명도이다.4 to 7 are explanatory views showing the installation process of the internal roof system for the containment building section of the nuclear power plant according to the present invention.

먼저, 도 4에 도시된 바와 같이 원자력 발전소의 격납건물의 설치에 따라 CLP(50)가 일정 높이로 설치되면, 러그(10)중 상부 러그(11)를 CLP(50)의 상부 설치하고, 러그(10)중 하부 러그(13)를 상부 러그(11)의 하단에 설치한다.First, as shown in FIG. 4, when the CLP 50 is installed at a predetermined height according to the installation of the containment building of the nuclear power plant, the upper lug 11 of the lugs 10 is installed above the CLP 50, and the lug The lower lug 13 of 10 is attached to the lower end of the upper lug 11.

그런 다음, 도 5에 도시된 바와 같이 상부 러그(11)와 하부 러그(13)에 각각 서스펜션 케이블(30)을 연결한다.Then, as shown in FIG. 5, the suspension cable 30 is connected to the upper lugs 11 and the lower lugs 13, respectively.

이러한 상태에서, 도 6에 도시된 바와 같이 수중 모터(23)가 내부에 설치된 집수통(20)을 크레인과 같은 인양 장비(미도시)를 통해 인양한 상태에서 서스펜션 케이블(30)을 케이블 고리(21)에 연결하여 CLP(50) 내부에서 집수통(20)을 부양시킨다.In such a state, as shown in FIG. 6, the suspension cable 30 is connected to the cable loop in a state in which the water collecting tank 20 installed therein is lifted through a lifting equipment (not shown) such as a crane. 21) to support the sump 20 inside the CLP 50.

이어서, 도 7에 도시된 바와 같이 지붕막(40)을 서스펜션 케이블(30)의 상부에 결합시킨다. 이때, 지붕막(40)은 저면에 걸고리(미도시)를 형성하여 서스펜션 케이블(30)과 결합할 수도 있고, 다양한 방식으로 결합될 수 있다.Subsequently, the roof membrane 40 is coupled to the upper portion of the suspension cable 30 as shown in FIG. 7. At this time, the roof film 40 may be coupled to the suspension cable 30 by forming a hook (not shown) on the bottom, or may be coupled in various ways.

그리고, 도 2에 도시된 바와 같이 CLP(50)의 측면에 고정된 배수관(25)을 수중 모터(23)와 연결시켜 설치를 완료한다.And, as shown in Figure 2 is connected to the drainage pipe 25 is fixed to the side of the CLP 50 and the underwater motor 23 to complete the installation.

한편, 본 발명에 따른 원자력 발전소의 격납건물 구간용 내부지붕 시스템(1)은 필요에 따라 해체되어 인양된 후 재설치되는 데, 예를 들어 CLP(50)의 적층 또는 건물의 높이에 따라 해체되어 재설치된다.On the other hand, the inner roof system (1) for the containment building section of the nuclear power plant according to the present invention is dismantled and lifted as necessary, and then reinstalled, for example, dismantled and reinstalled according to the stacking of the CLP (50) or the height of the building. do.

이런 경우 배수관(25)과, 집수통(20)과, 지붕막(40) 및 서스펜션 케이블(30)을 제거한 후, 하부 러그(13)만을 해체한 후 이를 다시 상부 러그(11)의 상부에 설치한다. 이때, 배수관(25)과, 집수통(20)과, 지붕막(40) 및 서스펜션 케이블(30)을 인양 장비로 부양시킨 상태로 작업할 수도 있다.In this case, after removing the drain pipe 25, the sump 20, the roof membrane 40 and the suspension cable 30, only the lower lug 13 is dismantled and installed again on the upper lug 11 again. do. At this time, the drain pipe 25, the sump 20, the roof membrane 40 and the suspension cable 30 may be in a state of supporting the lifting equipment.

그런 다음, 상기와 같은 과정으로 하부 러그(13)와 상부 러그(11)에 각각 서스펜션 케이블(30)을 연결 후 집수통(20)과 서스펜션 케이블(30)을 연결한다.Then, the suspension cable 30 is connected to the lower lug 13 and the upper lug 11 by the above-described process, and then the sump 20 and the suspension cable 30 are connected.

그리고, 지붕막(40)을 서스펜션 케이블(30)의 상부에 결합시킨 후 배수관(25)과 수중 모터(23)를 연결시켜 재설치를 완료한다.Then, the roof membrane 40 is coupled to the upper portion of the suspension cable 30, and then the drain pipe 25 and the underwater motor 23 are connected to complete the reinstallation.

한편, 지붕막(40)이 서스펜션 케이블(30)의 경사에 의해 이의 중심부가 하향 경사를 이루도록 설치되기 때문에 빗물이 배수홀(41)을 통해 집수통(20)으로 집수된 후 수중 모터(23)의 동작으로 인해 배수관(25)으로 배수된다.On the other hand, since the roof membrane 40 is installed so that its center is inclined downward by the inclination of the suspension cable 30, the rainwater is collected into the sump 20 through the drain hole 41 and then the underwater motor 23. Due to the operation of the drain pipe 25 is drained.

그리고, 건설 자재의 투입이 필요한 경우 별도의 인양 장비를 통해 건설 자재를 지붕막(40)의 자재투입구(43)를 통해 투입시킨다.Then, when the input of the construction material is necessary, the construction material is input through the material input hole 43 of the roof membrane 40 through a separate lifting equipment.

본 발명은 다양하게 변형될 수 있고 여러 가지 형태를 취할 수 있으며 상기 발명의 상세한 설명에서는 그에 따른 특별한 실시 예에 대해서만 기술하였다. 하지만 본 발명은 상세한 설명에서 언급되는 특별한 형태로 한정되는 것이 아닌 것으로 이해되어야 하며, 오히려 첨부된 청구범위에 의해 정의되는 본 발명의 정신과 범위 내에 있는 모든 변형물과 균등물 및 대체물을 포함하는 것으로 이해되어야 한다.While the present invention has been particularly shown and described with reference to exemplary embodiments thereof, it is to be understood that the invention is not limited to the disclosed exemplary embodiments. It is to be understood, however, that the invention is not to be limited to the specific forms thereof, which are to be considered as being limited to the specific embodiments, but on the contrary, the intention is to cover all modifications, equivalents, and alternatives falling within the spirit and scope of the invention as defined by the appended claims. .

10 : 러그 20 : 집수통
30 : 서스펜션 케이블 40 : 지붕막
10: lug 20: sump
30: suspension cable 40: roof membrane

Claims (6)

원자력 발전소의 격납건물을 형성하기 위하여 다단으로 결합된 CLP에 설치되는 내부지붕 시스템에 있어서,
상기 CLP의 내측면 상단에 등간격으로 설치되는 상부 러그와, 상기 상부 러그의 하단에 설치되는 하부 러그를 구비하는 러그와;
상면이 개방된 원통형으로 형성되고, 외측면에 상기 러그와 대향되는 위치에 복수의 케이블 고리가 설치되는 집수통과;
상기 러그와 일단이 연결되고, 타단이 상기 집수통에 연결되어 상기 집수통을 부양시키는 서스펜션 케이블; 및
상기 서스펜션 케이블의 상부에 결합되는 지붕막을 포함하며,
상기 러그는,
상기 지붕막의 인양후 재설치시 상기 하부 러그만을 해체하여 상기 하부 러그를 상기 상부 러그 상단에 설치하는 것을 특징으로 하는 원자력 발전소의 격납건물 구간용 내부지붕 시스템.
In the internal roof system installed in the CLP coupled in multiple stages to form a containment building of a nuclear power plant,
A lug having an upper lug installed at equal intervals at an upper end of an inner surface of the CLP, and a lower lug installed at a lower end of the upper lug;
A water collecting tube having an upper surface formed in an open cylindrical shape, and having a plurality of cable loops installed at a position opposite to the lug on an outer surface thereof;
A suspension cable having one end connected to the lug and the other end connected to the sump to support the sump; And
It includes a roof film coupled to the upper portion of the suspension cable,
The lug is
Internal roof system for the containment building section of the nuclear power plant, characterized in that when the lifting and re-installation of the roof membrane to dismantle the lower lug only to install the lower lug on top of the upper lug.
삭제delete 삭제delete 제 1 항에 있어서,
상기 집수통은,
내부 저면에 수중 모터가 설치되고, 상기 CLP의 측면에 고정된 배수관이 상기 수중 모터와 연결되는 것을 특징으로 하는 원자력 발전소의 격납건물 구간용 내부지붕 시스템.
The method of claim 1,
The sump can,
An inner roof system for a containment building section of a nuclear power plant, characterized in that the water motor is installed on the inner bottom, and the drain pipe fixed to the side of the CLP is connected to the underwater motor.
제 1 항에 있어서,
상기 서스펜션 케이블은,
상기 러그의 상부 러그 및 하부 러그에 각각 체결되어 상기 집수통을 중심으로 경사지게 형성되어 상기 지붕막의 중심부가 하향 경사를 이루도록 설치되는 것을 특징으로 하는 원자력 발전소의 격납건물 구간용 내부지붕 시스템.
The method of claim 1,
The suspension cable,
The inner roof system for the containment building section of the nuclear power plant, characterized in that the fastening is respectively formed to the upper lug and the lower lug of the lug to be inclined around the sump, so that the center of the roof film is inclined downward.
제 1 항에 있어서,
상기 지붕막은,
빛을 투과하는 막 재질로 8각 형태로 형성되고, 중앙부에 상기 집수통으로 우수를 배수하는 배수홀이 형성되며, 측면으로 자재 투입이 가능하도록 일측에 자재투입구가 형성되는 것을 특징으로 하는 원자력 발전소의 격납건물 구간용 내부지붕 시스템.
The method of claim 1,
The roof membrane is
A nuclear power plant, which is formed in an octagonal form of a membrane material that transmits light, has a drainage hole for draining rainwater through the sump at a central portion thereof, and a material inlet is formed at one side to allow material input to the side. Roof system for containment sections
KR1020100106412A 2010-10-29 2010-10-29 Inner roof system for reactor containment building of nuclear power plant KR101229095B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020100106412A KR101229095B1 (en) 2010-10-29 2010-10-29 Inner roof system for reactor containment building of nuclear power plant

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020100106412A KR101229095B1 (en) 2010-10-29 2010-10-29 Inner roof system for reactor containment building of nuclear power plant

Publications (2)

Publication Number Publication Date
KR20120045090A KR20120045090A (en) 2012-05-09
KR101229095B1 true KR101229095B1 (en) 2013-02-01

Family

ID=46264608

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020100106412A KR101229095B1 (en) 2010-10-29 2010-10-29 Inner roof system for reactor containment building of nuclear power plant

Country Status (1)

Country Link
KR (1) KR101229095B1 (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07305515A (en) * 1994-05-16 1995-11-21 Fujita Corp All weather type temporary tent in building work
JPH08144534A (en) * 1994-11-22 1996-06-04 Kajima Corp Self-rising openable-closable type temporarily constructed roof for work
JPH09242340A (en) * 1996-03-13 1997-09-16 Fujiki Komuten:Kk All weather temporary roof

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07305515A (en) * 1994-05-16 1995-11-21 Fujita Corp All weather type temporary tent in building work
JPH08144534A (en) * 1994-11-22 1996-06-04 Kajima Corp Self-rising openable-closable type temporarily constructed roof for work
JPH09242340A (en) * 1996-03-13 1997-09-16 Fujiki Komuten:Kk All weather temporary roof

Also Published As

Publication number Publication date
KR20120045090A (en) 2012-05-09

Similar Documents

Publication Publication Date Title
CN203452123U (en) Rainwater collection and treatment system
CN202880996U (en) Modularized dismountable constructed wetland
CN204238243U (en) A kind of city integrated piping lane
KR102116189B1 (en) A Development Device for Renewable Energy Using Rainwater
CN201933821U (en) Prefabricated reinforced concrete assembled and combined type water storage device
KR101229095B1 (en) Inner roof system for reactor containment building of nuclear power plant
KR101221072B1 (en) Opening and closing roof system for all-weather construction in main control room block of nuclear power plant
KR101216595B1 (en) Temporary roof system for reactor containment building of nuclear power plant
CN206396785U (en) The common cabin pattern synthesis piping lane section structure of the rain sewage of easy access
CN203462518U (en) Separating type prefabricated pump station
CN102182225A (en) Automatic foundation ground water collecting system
CN201387731Y (en) Containment sump device
CN217500152U (en) Water patrol access way for connecting beam overhanging type pile foundation
CN203487584U (en) Modularized integration pump station
CN216239414U (en) Ecological environmental protection cast-in-place steel-concrete structure green building of ZK
CN104775481A (en) Reclaimed water self-circulating system for residential quarter with buildings
CN105198073B (en) Integrated effluent disposal system
CN207405663U (en) A kind of self-suspending resets town road manhole lid device
CN209636848U (en) A kind of combined type sea windward electricity bucket foundation
CN202355908U (en) Wastewater treating and recycling device
CN106013213A (en) Offshore wind power pile foundation capable of increasing unit capacity and using method thereof
CN208668588U (en) A kind of integrated prefabricated pumping plant
KR101665240B1 (en) Temporary Anti-rain System for Reactor Building of Nuclear power plant
CN209653198U (en) A kind of nuclear power plant reactor construction of hydropower top cover
CN220989816U (en) Garbage bin percolate dredging grid structure of garbage incineration power plant

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20170116

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20171228

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20190109

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20191220

Year of fee payment: 8