CN204238243U - A kind of city integrated piping lane - Google Patents

A kind of city integrated piping lane Download PDF

Info

Publication number
CN204238243U
CN204238243U CN201420635667.4U CN201420635667U CN204238243U CN 204238243 U CN204238243 U CN 204238243U CN 201420635667 U CN201420635667 U CN 201420635667U CN 204238243 U CN204238243 U CN 204238243U
Authority
CN
China
Prior art keywords
dividing plate
central dividing
main body
trench portion
gallery
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201420635667.4U
Other languages
Chinese (zh)
Inventor
沈晓铃
王泽阳
朱沙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201420635667.4U priority Critical patent/CN204238243U/en
Application granted granted Critical
Publication of CN204238243U publication Critical patent/CN204238243U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sewage (AREA)

Abstract

The utility model relates to a kind of city integrated piping lane, belongs to urban operating mechanism technical field.Comprise gallery main body, gallery body interior is provided with at least one central dividing plate, gallery main body is divided into pipe trench portion for placing municipal pipeline and drainage channel by central dividing plate, the top of pipe trench portion and drainage channel arranges and is respectively arranged with pipeline cover plate and water drainage cover board, water drainage cover board is provided with some spilled water holes, the below of central dividing plate is connected with the bottom surface of gallery main body by upset bearing pin, is provided with some supports for supporting pipeline in pipe trench portion.The utility model structure is simple, compact to design, can reduce width of roadway and the space of pipe gallery needs, reduce pipe gallery size and investment.

Description

A kind of city integrated piping lane
Technical field
The utility model relates in a kind of urban construction the city integrated piping lane used, and belongs to urban operating mechanism technical field.
Background technology
City integrated piping lane, also referred to as common trench, integrated pipe canal, namely under town road, a underground gallery is built, by included in the lump for the various municipal pipelines such as electric power, communication, heating power and plumbing, and the facilities such as special access hole, dog-house are set, unified implementation management, saves pipeline self independently structure and soil excavation, can the utilizing space resources of active set reduction.But, needing based on management maintenance and maintenance, generally needing to arrange the passage for overhauling wherein, according to code requirement, its channel width should not be less than 0.7 ~ 1.0 meter, and this just causes, and the pipe gallery civil engineering scale of construction is comparatively large, cost is high, which also limits applying of pipe gallery.And in order to collect rainwater on road surface, need to arrange the facilities that catchment such as rainwater gutter or double-edged fine-toothed comb, independently arranging outward at pipe gallery, like this with regard to requiring that town road needs enough width to lay these pipelines and facility, and hence, limit the use of pipe gallery in the region of width of roadway deficiency.
Summary of the invention
The purpose of this utility model is comparatively large in order to solve in prior art the city piping lane civil engineering scale of construction, the shortcoming that cost is higher, provides that a kind of scale of construction is little, city integrated piping lane that reduced investment, little, the easy access of taking up room are safeguarded.
The utility model adopts following technical scheme: a kind of city integrated piping lane, comprise gallery main body, described gallery body interior is provided with central dividing plate, gallery main body is divided into pipe trench portion for placing municipal pipeline and drainage channel by described central dividing plate, the top of described pipe trench portion and drainage channel has been respectively arranged with pipeline cover plate and water drainage cover board, cover plate above described drainage channel is provided with some spilled water holes, and the below of described central dividing plate is connected with the bottom surface of gallery main body by upset bearing pin.
Further, described gallery main body is any one in rectangle, circle or u-shaped cross-section.
Further, described gallery main body is any one in reinforced concrete structure, high density polyethylene (HDPE) or resin concrete.
Further, the quantity of described central dividing plate is 1 or 2.
Further, some supports for supporting pipeline are provided with in described pipe trench portion.
The utility model structure is simple, compact to design, utilize the drainage channel of band spilled water hole to solve existing pipe gallery and cannot collect ground rainwater, need the problem that rainwater collection collector is independently set at pipe gallery outward, greatly reduce width of roadway and the space of pipe gallery needs; And by turnover central dividing plate, access path is utilized as drainage channel, reduces pipe gallery size and capital investment.
Accompanying drawing explanation
Fig. 1 crosses water state sectional schematic diagram containing during 1 central dividing plate in the utility model.
Fig. 2 is containing inspecting state sectional schematic diagram during 1 central dividing plate in the utility model.
Fig. 3 crosses water state sectional schematic diagram containing during 2 central dividing plates in the utility model.
Fig. 4 is containing inspecting state sectional schematic diagram during 2 central dividing plates in the utility model.
Reference numeral: gallery main body 1, central dividing plate 2, first central dividing plate 2-1, the second central dividing plate 2-2, pipeline cover plate 3, first pipeline cover plate 3-1, second pipe cover plate 3-2, water drainage cover board 4, pipe trench portion 5, first pipe trench portion 5-1, the second pipe trench portion 5-2, drainage channel 6, upset bearing pin 7, first overturn bearing pin 7-1, the second upset bearing pin 7-2, support 8, first support 8-1, the second support 8-2, spilled water hole 9.
Detailed description of the invention
Below in conjunction with accompanying drawing, the utility model will be further described.
Design principle of the present utility model is: adopt central dividing plate that gallery body portion is divided into pipe trench portion and drainage channel, requires can insert the various municipal pipelines such as electric power, communication, feedwater, regenerated water, the upper cover plate capping of pipe trench portion in pipe trench portion according to comb; Drainage channel upper cover plate arranges spilled water hole, and when raining, rainwater enters drainage channel through spilled water hole and gets rid of fast, and drainage channel isolate by central dividing plate and pipe trench portion, prevents the interference of rainwater accessible pipe duct portion or pollution pipe trench all the other municipal pipelines interior in drainage channel; When needs overhaul, open cover plate, upset central dividing plate, can utilize drainage channel as space for maintenance to municipal pipeline repair and maintenance in pipe trench portion, and maintenance terminates, and is resetted by central dividing plate, and isolation pipe trench portion and drainage channel recover using function.
As Figure 1-Figure 2, a kind of city integrated piping lane, is provided with 1 central dividing plate for two cabin structure, is made up of gallery main body 1, central dividing plate 2, pipeline cover plate 3 and water drainage cover board 4 in this gallery main body 1.Gallery main body 1 is divided into for pipe trench portion 5 and drainage channel 6 two parts by central dividing plate 2, the bottom of central dividing plate 2 is linked with the bottom surface of gallery main body 1 by upset bearing pin 7, the sidewall in pipe trench portion 5 is provided with some supports 8 for laying all kinds of municipal pipeline, pipeline cover plate 3 is provided with above pipe trench portion, the top of drainage channel 6 is provided with water drainage cover board 4, water drainage cover board 4 is provided with some spilled water holes 9.
When rainy, rainwater enters drainage channel 6 through spilled water hole 9 and gets rid of fast, and drainage channel 6 is isolated with pipe trench portion 5 by central dividing plate 2, prevents rainwater accessible pipe duct portion 5 in drainage channel 6, interference or pollute all the other municipal pipelines in pipe trench portion 5; When needing maintenance, opening conduits cover plate 3 and water drainage cover board 4, upset central dividing plate 2, can utilize drainage channel 6 as space for maintenance to the municipal pipeline repair and maintenance in pipe trench portion 5; Maintenance terminates, and reset central dividing plate 2 isolation pipe trench portion 5 and drainage channel 6, recovers using function.
As Figure 3-Figure 4, a kind of city integrated piping lane, this gallery main body 1 is three cabin structures containing 2 central dividing plates, comprises gallery main body 1, first central dividing plate 2-1, the second central dividing plate 2-2, the first pipeline cover plate 3-1, second pipe cover plate 3-2 and water drainage cover board 4 and forms.First central dividing plate 2-1 and the second central dividing plate 2-2 spaced set will be divided into the first pipe trench portion 5-1 and the second pipe trench portion 5-2 outside gallery main body 1, centre is drainage channel 6.First central dividing plate 2-1 and the second central dividing plate 2-2 is linked with the bottom surface of gallery main body 1 by the first upset bearing pin 7-1 and second upset bearing pin 7-2, the sidewall of the first pipe trench portion 5-1 and the second pipe trench portion 5-2 is respectively arranged with the first support 8-1 for supporting pipeline and the second support 8-2, be provided with the first pipeline cover plate 3-1 above first pipe trench portion 5-1, the top of the second pipe trench portion 5-2 is provided with 3-2.Side is provided with water drainage cover board plate 4 to drainage channel 6, water drainage cover board 4 is arranged spilled water hole 9.
When raining, rainwater enters drainage channel 6 through spilled water hole 9 and gets rid of fast, drainage channel 6 is isolated by the first central dividing plate 2-1 and the second central dividing plate 2-2 and the first pipe trench portion 5-1 and the second pipe trench portion 5-2, prevent rainwater in drainage channel 6 from entering the first pipe trench portion 5-1 and the second pipe trench portion 5-2, disturb or pollute all the other municipal pipelines in pipe trench portion; When needing maintenance, open the first pipeline cover plate 3-1 or second pipe cover plate 3-2 and water drainage cover board 4, overturn the first central dividing plate 2-1 or the second central dividing plate 2-2, drainage channel 6 can be utilized as space for maintenance to municipal pipeline repair and maintenance in the first pipe trench portion 5-1 or the second pipe trench portion 5-2.Maintenance terminates, and the first central dividing plate 2-1 or the second central dividing plate 2-2 resets, and can isolate the first pipe trench portion 5-1 or the second pipe trench portion 5-2 and drainage channel 6, recovers using function.

Claims (5)

1. a city integrated piping lane, it is characterized in that: comprise gallery main body (1), described gallery main body (1) inside is provided with central dividing plate (2), gallery main body (1) is divided into pipe trench portion (5) for placing municipal pipeline and drainage channel (6) by described central dividing plate (2), the top of described pipe trench portion (5) and drainage channel (6) is respectively arranged with pipeline cover plate (3) and water drainage cover board (4), described water drainage cover board (4) is provided with some spilled water holes (9), the below of described central dividing plate (2) is connected with the bottom surface of gallery main body (1) by upset bearing pin (7).
2. city integrated piping lane as claimed in claim 1, is characterized in that: described gallery main body (1) is rectangle, any one in circle or u-shaped cross-section.
3. city integrated piping lane as claimed in claim 1, is characterized in that: described gallery main body (1) is reinforced concrete structure, any one in high density polyethylene (HDPE) or resin concrete.
4. city integrated piping lane as claimed in claim 1, is characterized in that: the quantity of described central dividing plate (2) is 1 or 2.
5. city integrated piping lane as claimed in claim 1, is characterized in that: be provided with some supports for supporting pipeline (8) in described pipe trench portion (5).
CN201420635667.4U 2014-10-29 2014-10-29 A kind of city integrated piping lane Withdrawn - After Issue CN204238243U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201420635667.4U CN204238243U (en) 2014-10-29 2014-10-29 A kind of city integrated piping lane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201420635667.4U CN204238243U (en) 2014-10-29 2014-10-29 A kind of city integrated piping lane

Publications (1)

Publication Number Publication Date
CN204238243U true CN204238243U (en) 2015-04-01

Family

ID=52767756

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201420635667.4U Withdrawn - After Issue CN204238243U (en) 2014-10-29 2014-10-29 A kind of city integrated piping lane

Country Status (1)

Country Link
CN (1) CN204238243U (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104294845A (en) * 2014-10-29 2015-01-21 沈晓铃 City comprehensive pipe gallery
CN104846840A (en) * 2015-04-23 2015-08-19 东北大学 Shallowly-buried soft soil integrated trench reinforcing device and construction method
CN104878777A (en) * 2015-06-08 2015-09-02 李伟 Pipeline connecting case and construction method for temporarily constructing pipelines of municipal foundation facilities
CN105961078A (en) * 2016-05-30 2016-09-28 湖州织里华宁园艺工程有限公司 Multifunctional main supporting structure for garden greenhouse
CN106034824A (en) * 2016-05-30 2016-10-26 湖州织里华宁园艺工程有限公司 Multi-functional horticultural greenhouse framework
CN106921140A (en) * 2017-03-31 2017-07-04 中冶南方城市建设工程技术有限公司 Pipe gallery electric power cabin circuit sinusoidal lays rack arrangement method when right angled triangle is arranged
CN107761763A (en) * 2017-10-18 2018-03-06 西安交通大学 A kind of pipe gallery and its application method
CN108487314A (en) * 2018-05-09 2018-09-04 湖南飞山奇建筑科技有限公司 A kind of city integrated piping lane

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104294845A (en) * 2014-10-29 2015-01-21 沈晓铃 City comprehensive pipe gallery
CN104294845B (en) * 2014-10-29 2016-04-27 沈晓铃 A kind of city integrated piping lane
CN104846840A (en) * 2015-04-23 2015-08-19 东北大学 Shallowly-buried soft soil integrated trench reinforcing device and construction method
CN104878777A (en) * 2015-06-08 2015-09-02 李伟 Pipeline connecting case and construction method for temporarily constructing pipelines of municipal foundation facilities
CN104878777B (en) * 2015-06-08 2016-08-24 李伟 The pipeline connecting box of civilian infrastructure pipeline temporary construction and construction method
CN105961078A (en) * 2016-05-30 2016-09-28 湖州织里华宁园艺工程有限公司 Multifunctional main supporting structure for garden greenhouse
CN106034824A (en) * 2016-05-30 2016-10-26 湖州织里华宁园艺工程有限公司 Multi-functional horticultural greenhouse framework
CN106921140A (en) * 2017-03-31 2017-07-04 中冶南方城市建设工程技术有限公司 Pipe gallery electric power cabin circuit sinusoidal lays rack arrangement method when right angled triangle is arranged
CN107761763A (en) * 2017-10-18 2018-03-06 西安交通大学 A kind of pipe gallery and its application method
CN108487314A (en) * 2018-05-09 2018-09-04 湖南飞山奇建筑科技有限公司 A kind of city integrated piping lane

Similar Documents

Publication Publication Date Title
CN204238243U (en) A kind of city integrated piping lane
CN104294845B (en) A kind of city integrated piping lane
CN204903531U (en) Open -air portable runoff district
CN105089302A (en) Rainwater garden system for community rainwater flow diversion, peak clipping and ecological purification
CN102808449A (en) Energy dissipating well for initial rainwater in ultra-deep storage adjustment pipe
CN203393742U (en) Integrated pipe gallery structure
CN201459901U (en) Collinear bypass type double-layer drainage pipe duct
CN103397662A (en) Comprehensive pipe gallery structure
CN206135372U (en) Multifunctional cable ditch
CN202755380U (en) Tee joint working well for long-distance large-pipe-diameter underground water delivery main pipe system
CN208605197U (en) A kind of building structure that subway driving section is built together with Urban Underground pipe gallery
CN205242594U (en) Collect rain pretreatment of water and overflow in finished product inlet for stom water of an organic whole
CN205242593U (en) Collection oozes to stagnate and holds integral type finished product inlet for stom water of clean row of rainwater
CN203008100U (en) Drainage network of barrier-free drainage facility
CN109763552A (en) A kind of basis is dark to apply gravity type draining regeneration application system and its construction method
CN104088491B (en) The vertical method for arranging of a kind of 220kV transformer station ramp type
CN205636885U (en) Constructed wetland monomer rainwater storage structure based on side slope
CN203049404U (en) Cooling pavement structure with water-accumulating box
CN202220345U (en) Drain pipe system below community driveway
CN204225563U (en) A kind of ecological garage parking
CN205259316U (en) Photovoltaic module water for washing who combines together with green house retrieves system of recycling
CN202139680U (en) Drainage ditch for ash storage yard of power plant
CN207484624U (en) A kind of double-layer drainage pipe duct of rain sewage diversion
CN202298863U (en) Pipe network rainwater collecting cellar
CN206015837U (en) A kind of factory's storm-water system

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20150401

Effective date of abandoning: 20160427

C25 Abandonment of patent right or utility model to avoid double patenting