All weather type temporary tent in building work

Info

Publication number
JPH07305515A
JPH07305515A JP10107294A JP10107294A JPH07305515A JP H07305515 A JPH07305515 A JP H07305515A JP 10107294 A JP10107294 A JP 10107294A JP 10107294 A JP10107294 A JP 10107294A JP H07305515 A JPH07305515 A JP H07305515A
Authority
JP
Japan
Prior art keywords
main body
sheet
body sheet
wire
tent
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP10107294A
Other languages
Japanese (ja)
Inventor
Hisashi Oi
尚志 大井
Yoshio Sugimoto
贊夫 杉本
Nobuo Horiuchi
信男 堀内
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujita Corp
Original Assignee
Fujita Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujita Corp filed Critical Fujita Corp
Priority to JP10107294A priority Critical patent/JPH07305515A/en
Publication of JPH07305515A publication Critical patent/JPH07305515A/en
Pending legal-status Critical Current

Links

Landscapes

  • Tents Or Canopies (AREA)

Abstract

PURPOSE:To provide a tent having interchangeability and easy timber change work by stretching suspending wires for supporting a temporary tent among four pillars constituting a building, and dividing the tent into three sorts, a main body part, a peripheral part, and ridge parts. CONSTITUTION:A peripheral sheet suspending wire 3 and a main body sheet suspending wire 1 are stretched among pillars A of steelwork and the like of a building during construction. The wires 1, 3 are adjustable in tension by winches provided on the beams B of the upper floor. Next, a main body sheet (a) having a collecting part 2 is fitted to the suspending wire 1, and supplementary sheets (b) are fitted between the peripheral wire 3 and the main body sheet (a). Further, ridge covering sheets (c) are fitted to the connection parts with the adjoining supplementary sheets. Even in case of rain fall and the like, working is possible, and the temporary tent is formed so as not to be flapped by a wind and the like. Hereby, a tent having interchangeability and easy timber changing work can be easily provided.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、鉄骨鉄筋コンクリート
造、鉄骨造の建物の構築に際し、天候によって作業が左
右されないように建物を覆う全天候型仮設テントに係る
ものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an all-weather temporary tent for covering a building which is constructed of steel-framed reinforced concrete or steel so as not to be affected by the weather.

【0002】[0002]

【従来の技術】本出願人等は特願平5−94365号に
おいて鉄骨鉄筋コンクリート造における鉄骨躯体を組み
立てた後、作業床の直上階上部における相隣る鉄骨柱に
ワイヤロープを水平に張り巡らし、同ワイヤロープ間に
大型シ−トを展張した全天候型仮設テントを提案した。
2. Description of the Related Art The applicants of the present invention, after assembling a steel frame body in a steel frame reinforced concrete structure in Japanese Patent Application No. 5-94365, horizontally stretch a wire rope around adjacent steel frame columns directly above the working floor, We proposed an all-weather temporary tent with a large sheet stretched between the wire ropes.

【0003】[0003]

【発明が解決しようとする課題】しかしながら前記鉄骨
柱間にワイヤロープを張設し略長方形大型シートを展張
するとシ−トが大きくなる。また互換性がなく、更に風
によるばたつきを抑えにくい。更にまたテントの上階部
材への盛替作業が容易でないという問題点があった。
However, when a wire rope is stretched between the steel columns and a substantially rectangular large sheet is stretched, the sheet becomes large. In addition, it is not compatible and it is difficult to suppress flapping due to wind. Furthermore, there is a problem that it is not easy to transfer the tent to the upper floor member.

【0004】本発明は前記従来技術の有する問題点を解
決するために提案されたもので、その目的とするところ
は、互換性を有し、排水機能を具え、風によるばたつき
がなく、盛替えが容易な全天候型仮設テントを提供する
点にある。
The present invention was proposed in order to solve the problems of the above-mentioned prior art. The object of the present invention is to have compatibility, to have a drainage function, to prevent fluttering due to the wind, and to be able to refill. The point is to provide an easy-to-use all-weather temporary tent.

【0005】[0005]

【課題を解決するための手段】前記の目的を達成するた
め、本発明に係る建築工事における全天候型仮設テント
は、4本の柱間に配設された吊りワイヤ間に張設され
た、中央部をたるませた漏斗状の本体シートと、同本体
シ−トの周縁部と前記柱間に緊張された吊りワイヤとの
間に、張設された補助シ−トと、スパン方向に相隣る同
補助シ−トの対向縁間を覆う棟覆シ−トとから構成され
ている。
In order to achieve the above-mentioned object, an all-weather temporary tent for construction work according to the present invention has a central part stretched between suspension wires arranged between four pillars. A funnel-shaped main body sheet with a slackened portion, an auxiliary seat stretched between the peripheral edge of the main body seat and the suspension wire tensioned between the pillars, and a spanwise adjacent side It is composed of a ridge covering sheet covering the opposite edges of the auxiliary sheet.

【0006】請求項2の発明は、前記本体シ−トの中央
部に集水部を設けるとともに、同集水部に設けた取付部
材に台付ワイヤを取り付け、前記本体シ−トの上方の梁
にウインチを設置して構成され、盛替作業を容易ならし
めるようにしたものである。
According to a second aspect of the present invention, a water collecting portion is provided in the central portion of the main body sheet, and a wire with a stand is attached to a mounting member provided in the water collecting portion, and the water is provided above the main body sheet. It is constructed by installing a winch on the beam to facilitate reassembling work.

【0007】[0007]

【作用】本発明によれば前記したように、本体シ−トが
4本の柱間に配設された吊ワイヤに、中央部をたるませ
た漏斗状に形成されているので雨水が本体シ−トに溜る
ことがなく、排水が容易になる。前記本体シ−トをたる
ませた漏斗状にたるませて柱間に懸吊したことによっ
て、本体シ−トの外周縁に形成された間隙が、同本体シ
−トの周縁部と、柱間に緊張された吊りワイヤとの間に
張設された補助シ−トによって補填され、また同補助テ
ントは水切りテントの用を果たすとともに、前記本体シ
−トの寸法誤差を吸収するものであり、同本体シ−トの
互換性が可能となる。
According to the present invention, as described above, since the main body sheet is formed in a funnel shape with the center portion slackened on the suspension wire arranged between the four pillars, rainwater is absorbed into the main body sheet. -It does not collect in the grate and drains easily. By suspending the main body sheet in the shape of a slackened funnel and suspending the main body sheet between the columns, the gap formed in the outer peripheral edge of the main body sheet forms a gap between the peripheral portion of the main body sheet and the column. Is supplemented by an auxiliary sheet stretched between the tensioning wire and the suspension wire, and the auxiliary tent serves as a draining tent and absorbs a dimensional error of the main body sheet. The compatibility of the main body sheet becomes possible.

【0008】また相隣る補助シ−トの対向縁間が棟覆シ
−トによって被覆されているので、相隣る仮設テント間
の雨仕舞が行なわれるものである。請求項2の発明は、
中央部をたるませた前記本体シ−トの中央に設けた集水
部を利用して、同集水部に設けた取付部材に台付ワイヤ
を取り付け、本体シ−ト上方の梁にウインチを設置した
ことによって、本発明の仮設テントを吊上げ盛り替るこ
とにより盛り替えが容易に行われる。
Further, since the opposing edges of the adjacent auxiliary sheets are covered by the ridge covering sheet, rain between the adjacent temporary tents is performed. The invention of claim 2 is
Using the water collecting portion provided in the center of the main body sheet with the center portion slackened, a wire with a base is attached to a mounting member provided in the water collecting portion, and a winch is attached to a beam above the main body sheet. By installing the temporary tent of the present invention, the temporary tent can be hoisted and refilled to facilitate refilling.

【0009】[0009]

【実施例】以下本発明を図示の実施例について説明す
る。Aは方形の各頂点に位置して配設された鉄骨柱で、
同各鉄骨柱A間に本体シ−トaの吊りワイヤ1が張られ
ている。同吊りワイヤ1を介して中央部をたるませた漏
斗状の本体シ−トaが張設されている。同本体シ−トa
の中央部には集水部2が設けられている。
The present invention will be described below with reference to the illustrated embodiments. A is a steel column arranged at each vertex of the square,
The suspension wire 1 of the main body sheet a is stretched between the steel columns A. A funnel-shaped main body sheet a having a slackened central portion is stretched via the suspension wire 1. Body sheet a
A water collecting portion 2 is provided in the central portion of the.

【0010】前記柱A間には外周シ−ト吊りワイヤ3が
緊張され、同ワイヤ3と前記本体シ−トaの周縁部との
間に亘って補助シ−トbが張設され、相隣るスパンの補
助シ−トb間に棟覆シ−トcが配設されている。図3は
図1の部分Sの詳細を示し、鉄骨柱Aに設けた係止環4
に設けた係止環5に係止金具6を介して本体シ−ト固定
金具7が取り付けられ、同金具7に取付部7aを介して
前記吊りワイヤ1が取付けられるとともに、ボルト8を
介して前記金具7に基端部を固着されたシ−ト挟着金具
9によって本体シ−トaを挟着してボルト10によって
本体シ−トaを固着するものである。
An outer peripheral sheet suspending wire 3 is tensioned between the pillars A, and an auxiliary sheet b is stretched between the wire 3 and the peripheral portion of the main body sheet a. A ridge cover sheet c is arranged between auxiliary sheets b of adjacent spans. FIG. 3 shows the details of the portion S of FIG. 1, and shows the locking ring 4 provided on the steel column A.
The main body sheet fixing metal fitting 7 is attached to the locking ring 5 provided on the mounting metal fitting 6 via the locking metal fitting 6, the hanging wire 1 is mounted to the metal fitting 7 via the mounting portion 7a, and the bolt 8 is also mounted. The main body sheet a is clamped by the sheet clamping metal fitting 9 whose base end is fixed to the metal fitting 7, and the main body sheet a is fixed by the bolt 10.

【0011】図5、図6は図1の部分S1 の詳細を示し
吊りワイヤ1の両端を固定するもので、同ワイヤ1と本
体シ−ト固定金具7との取付部を示し、11,12は吊
りワイヤーを固定するクリップを示す。図中13は前記
固定金具7の吊環部である。図2及び図7は前記本体シ
−トa、補助シ−トb及び棟覆シ−トcの取付部を示
し、補助シ−トbの一端部は外周シ−ト吊りワイヤ3に
ばね状係止環14を介して係止され、他端部は本体シ−
トaの周縁部に係止体15を介して係止されたS字金物
16を介して係止されている。図中17は棟覆シ−トc
と補助シ−トbの取付片である。
FIGS. 5 and 6 show the details of the portion S 1 in FIG. 1 for fixing both ends of the suspension wire 1 and showing the mounting portion between the wire 1 and the main body sheet fixing metal fitting 11, Reference numeral 12 denotes a clip for fixing the hanging wire. Reference numeral 13 in the figure denotes a suspension ring portion of the fixing member 7. 2 and 7 show the mounting portions of the main body sheet a, the auxiliary sheet b, and the ridge cover sheet c, and one end of the auxiliary sheet b is spring-shaped on the outer peripheral sheet hanging wire 3. It is locked through a locking ring 14, and the other end is a body sheet.
It is locked via the S-shaped metal fitting 16 which is locked via the locking body 15 to the peripheral portion of the toe a. In the figure, 17 is a ridge cover sheet c
And an attachment piece of the auxiliary sheet b.

【0012】図8及び図9は集水部及びシ−ト吊上げ部
を示し、本体シ−トaにおける集水部2に配設された集
水凾18の底部には排水管19が垂設され、同排水管1
9に排水ホース20が接続されている。更に集水凾18
の外部に固着された繋ぎ片21に接続金具22に本体シ
−トaの中央集水部が接続されている。前記集水凾18
に吊上杆23が配設され、同吊上杆23と本体シ−トa
との間に水切りシ−トdが接続されている。24は吊上
杆23に固着された水切シ−トdの接続環である。
8 and 9 show a water collecting portion and a seat lifting portion, and a drain pipe 19 is vertically provided at a bottom portion of a water collecting portion 18 arranged in the water collecting portion 2 of the main body sheet a. The same drain pipe 1
A drain hose 20 is connected to 9. Further collecting water 18
The central water collecting portion of the main body sheet a is connected to the connecting piece 22 to the connecting piece 21 fixed to the outside. Water collection 18
The hoisting rod 23 is disposed on the upper part of the hoisting rod 23 and the main body sheet a.
A draining sheet d is connected between the and. Reference numeral 24 is a connecting ring of the draining sheet d fixed to the lifting rod 23.

【0013】前記吊上杆23には吊上金物26が取り付
けられ、同金物26に吊上げ用ワイヤ27が取り付けら
れている。図示の実施例は前記したように構成されてい
るので、前記本体シ−トaによって、同シ−トの下階部
の配筋、コンクリート打設等の作業が天候等に影響され
ることなく行なわれる。前記本体シ−トaは中央部をた
るませた状態で配設されているので、雨水等は本体シ−
トaの中央部の集水部2に集約され、集水凾18、排水
管19、排水ホース20を介して排水される。
A hoisting metal 26 is attached to the hoisting rod 23, and a hoisting wire 27 is attached to the metal 26. Since the illustrated embodiment is configured as described above, the main body sheet a does not affect the work such as the reinforcement of the lower floor of the sheet or the concrete placing work due to the weather or the like. Done. Since the main body sheet a is arranged with the center portion slackened, rainwater and the like are not attached to the main body sheet.
The water is collected in the water collecting section 2 in the central part of the toe a and drained through the water collecting column 18, the drain pipe 19, and the drain hose 20.

【0014】また本体シ−トa外周縁の雨水は前記補助
シ−トbによって本体シ−トa内に集水される。更に相
隣るスパンのテント間の雨水も棟覆シ−トcを介して本
体シ−トaに集中される。なおテントを盛り替える場
合、鉄骨梁B上部に電動ウインチを設置して集水部2の
吊上げワイヤ27を吊り上げると本体シートが上部に移
動し前記と同様に展張するので吊り上げが簡単に所期の
目的が達成される。
Rainwater on the outer peripheral edge of the body sheet a is collected in the body sheet a by the auxiliary sheet b. Further, rainwater between tents of adjacent spans is also concentrated on the main body sheet a via the ridge covering sheet c. When the tent is to be refilled, an electric winch is installed above the steel beam B and the lifting wire 27 of the water collecting part 2 is lifted, and the main body sheet moves to the upper part and expands in the same manner as described above, so the lifting is easy. The purpose is achieved.

【0015】[0015]

【発明の効果】本発明によれば前記したように、4本の
柱間に張設された本体シ−トが中央部をたるませた漏斗
状の本体シ−トによって、雨水が中央部に集約、排水さ
れ、シート下部の作業が天候に左右されることなく行な
われるものである。更に柱間に緊張された吊りワイヤと
前記本体シ−トの周縁部との間に補助シ−トが配設され
ているので、同補助シ−トによって前記本体シ−トの外
周縁の雨水から掩覆され、また同補助シ−トが水切りシ
−トの用を果し、本体シ−ト外周部の雨水が前記本体シ
−トに案内、排除される。更に補助シ−トによって前記
本体シ−トの寸法の誤差が吸収されるものであり、同本
体シ−トの互換性が可能となり、風によるシ−トのばた
つきが防止される。
According to the present invention, as described above, rainwater is concentrated in the central portion by the funnel-shaped main body sheet in which the central portion is stretched between the four pillars. It is concentrated and drained, and the work under the seat is performed without being affected by the weather. Further, since the auxiliary sheet is disposed between the suspension wire which is strained between the pillars and the peripheral portion of the main body sheet, rainwater on the outer peripheral edge of the main body sheet is provided by the auxiliary sheet. The auxiliary sheet serves as a draining sheet, and the rainwater on the outer peripheral portion of the main body sheet is guided to and removed from the main body sheet. Further, the auxiliary sheet absorbs the dimensional error of the main body sheet, the compatibility of the main body sheet becomes possible, and the fluttering of the sheet due to wind is prevented.

【0016】前記スパン方向に相隣る前記棟覆シ−トに
よって、相隣るスパンのテント間も、雨水による影響を
防止される。請求項2の発明は前記本体シ−トの中央部
の集水部に設けた取付部材台付ワイヤを取り付けるとと
もに、上方の梁に同ワイヤ操作用のウインチを設けたこ
とによって、仮設テントの盛替作業が容易になる。
The ridge covering sheets adjacent to each other in the span direction prevent rainwater from affecting the tents of the adjacent spans. According to a second aspect of the present invention, a wire with a mounting member provided in the water collecting portion at the central portion of the main body sheet is attached, and a winch for operating the wire is provided on the upper beam, so that the temporary tent is heaped up. Replacement work becomes easy.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明に係る建築工事における全天候型仮設テ
ントの一実施例の要部を示す平面図である。
FIG. 1 is a plan view showing a main part of an embodiment of an all-weather temporary tent for construction work according to the present invention.

【図2】図1の矢視イ−イ図である。FIG. 2 is an arrow view of FIG.

【図3】図1の部分Sの詳細図である。FIG. 3 is a detailed view of a portion S of FIG.

【図4】図1の部分Sの水平断面図である。FIG. 4 is a horizontal sectional view of a portion S of FIG.

【図5】図1の部分S1 の詳細図である。5 is a detailed view of a portion S 1 of FIG.

【図6】図1の部分S1 の平断面図である。6 is a plan sectional view of a portion S 1 of FIG.

【図7】本体シ−ト、補助シ−ト及び棟覆シ−ト重合部
を示す縦断面図である。
FIG. 7 is a vertical cross-sectional view showing a main body sheet, an auxiliary sheet, and a ridge cover sheet overlapping portion.

【図8】集水部の一部縦断立面図である。FIG. 8 is a vertical sectional elevational view of a part of the water collecting portion.

【図9】図8の一部横断平面図である。9 is a partial cross-sectional plan view of FIG.

【符号の説明】[Explanation of symbols]

A 鉄骨柱 B 鉄骨梁 a 本体シ−ト b 補助シ−ト c 棟覆シ−ト d 水切りシ−ト 1 吊りワイヤ 2 集水部 3 外周シ−ト吊りワイヤ 4 係止環 5 係止環 6 係止金具 7 本体シ−ト固定金具 7a 取付部 8 ボルト 9 シ−ト挟着金具 10 ボルト 11 クリップ 12 クリップ 13 吊環部 14 ばね状係止環 15 係止体 16 S字金物 17 取付片 18 集水凾 19 排水管 20 排水ホース 21 繋ぎ片 22 接続金具 23 吊上杆 24 接続環 26 吊上金物 27 吊上用ワイヤ 28 吊足場 A steel pillar B B steel beam a Main body seat b Auxiliary seat c Building cover seat d Draining seat 1 Suspension wire 2 Water collecting part 3 Outer peripheral seat suspension wire 4 Locking ring 5 Locking ring 6 Locking metal fittings 7 Main body sheet fixing metal fittings 7a Mounting part 8 Bolts 9 Seat clamping metal fittings 10 Bolts 11 Clips 12 Clips 13 Suspension ring parts 14 Spring-like locking rings 15 Locking bodies 16 S-shaped metal fittings 17 Mounting pieces 18 Water tank 19 Drain pipe 20 Drain hose 21 Connecting piece 22 Connecting metal fitting 23 Lifting rod 24 Connection ring 26 Lifting hardware 27 Lifting wire 28 Lifting scaffolding

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 4本の柱間に配設された吊りワイヤ間に
張設された、中央部をたるませた漏斗状の本体シート
と、同本体シ−トの周縁部と前記柱間に緊張された吊り
ワイヤとの間に、張設された補助シ−トと、スパン方向
に相隣る同補助シ−トの対向縁間を覆う棟覆シ−トとか
らなることを特徴とする建築工事における全天候型仮設
テント。
1. A funnel-shaped main body sheet having a slackened central portion, which is stretched between suspension wires arranged between four pillars, and between the peripheral edge of the main body sheet and the pillars. It is characterized by comprising an auxiliary sheet stretched between the tensioned suspension wire and a ridge covering sheet covering between opposite edges of the auxiliary sheets adjacent to each other in the span direction. All-weather temporary tent for construction work.
【請求項2】 前記本体シ−トの中央部に集水部を設け
るとともに、同集水部に設けた取付部材に台付ワイヤを
取り付け、前記本体シ−トの上方の梁にウインチを設置
してなる請求項1記載の建築工事における全天候型仮設
テント。
2. A water collecting portion is provided at the center of the body sheet, a wire with a base is attached to a mounting member provided in the water collecting portion, and a winch is installed on a beam above the body sheet. An all-weather temporary tent for construction work according to claim 1.
JP10107294A 1994-05-16 1994-05-16 All weather type temporary tent in building work Pending JPH07305515A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10107294A JPH07305515A (en) 1994-05-16 1994-05-16 All weather type temporary tent in building work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10107294A JPH07305515A (en) 1994-05-16 1994-05-16 All weather type temporary tent in building work

Publications (1)

Publication Number Publication Date
JPH07305515A true JPH07305515A (en) 1995-11-21

Family

ID=14290907

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10107294A Pending JPH07305515A (en) 1994-05-16 1994-05-16 All weather type temporary tent in building work

Country Status (1)

Country Link
JP (1) JPH07305515A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101229095B1 (en) * 2010-10-29 2013-02-01 주식회사 동아스트 Inner roof system for reactor containment building of nuclear power plant
CN110485757A (en) * 2019-06-17 2019-11-22 天祥建设集团股份有限公司 A kind of steel bar meter field protection canopy

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101229095B1 (en) * 2010-10-29 2013-02-01 주식회사 동아스트 Inner roof system for reactor containment building of nuclear power plant
CN110485757A (en) * 2019-06-17 2019-11-22 天祥建设集团股份有限公司 A kind of steel bar meter field protection canopy

Similar Documents

Publication Publication Date Title
JPH07305515A (en) All weather type temporary tent in building work
CN106545115B (en) The construction method of assembled steel concrete composite slab
JPH06307096A (en) Construction method for temporary roof in building works
CN112942777A (en) Ultrahigh-layer periphery protection cyclic telescopic detachable cantilever structure and mounting method
JPH0340987Y2 (en)
CN212570204U (en) Building quality integration technology model show structure
CN212388802U (en) Keel component and hoisting structure of double-fish belly guy cable curtain wall
CN215888590U (en) Large-span does not have roof truss cable membrane structure
CN213897510U (en) Cable membrane butt-joint tensioning structure and large-span cable membrane storage space
CN218623413U (en) Rainproof pipe truss assembly platform
JP2523419Y2 (en) Crane mast umbrella
JPH06185223A (en) Spreading of temporarily using tent for construction work
JP4665320B2 (en) Membrane roof of storage tank
JPS604955Y2 (en) Floating roof with partition plates to prevent unbalanced loads due to snowfall
CN105926857A (en) Prefabricated pier and application of prefabricated pier to high-rise reversed beam overhanging scaffold construction
JPH0262667B2 (en)
JPH07259018A (en) Cable stiffened water pipe bridge
JP4167377B2 (en) Rainfall installation method for unit housing, tent
JPH09242340A (en) All weather temporary roof
JP2000213175A (en) All weather type outdoor scaffolding and method for spreading sheet thereof
RU2029831C1 (en) Method to mount guy lining in a building of long span
JPH04105371U (en) Retractable temporary roof
JP2601107B2 (en) All-weather temporary roof and its use
CN114033223A (en) Steel hanging platform under overhanging steel truss of ultrahigh air swimming pool and construction method thereof
JP2001355341A (en) All-weather work house