The construction method of assembled steel concrete composite slab
Technical field
The present invention relates to technical field of civil, more particularly to a kind of assembled steel concrete composite slab and its apply
Work method.
Background technique
Currently, traditional roof boarding or floor mostly uses greatly the armored concrete knot such as rib beam type floor and cross beam formula floor
Structure, general beam slab are supported by the pillar or load bearing wall of its underpart, are considered from structural mechanical property and economic angle, this floor
Form should not be used in the biggish building of span, be usually used in residential construction.When building functional requirement its have it is biggish across
When spending, such as stadiums, conference and exhibition center and workshop building, then it must change the structure type of roof boarding, can be used pre-
Stress reinforced concrete girder slab system, Elements of Space Grid Truss or reinforced concrete combination rack system directly adopt steel structure system, but
These methods or still there is significant limitation in span, or fails concrete (preferably compression characteristic) and steel
The material advantage of (preferable tension characteristic) gives full play of.
Common floor structural form has armored concrete rib-beam floor frame and prestressed reinforced concrete superstructure etc. in engineering,
But when the planar dimension of building and column are away from 5~8 times of increase, and interior is without column, if using the building armored concrete Lei Xing again
Lid and prestressed reinforced concrete superstructure are infeasible.Currently, for this large span (80m≤L≤150m) Large Column Spacing
The roof system of (32m≤a≤60m) generally uses plate steel latticed structures, and is designed as three layers more, and steel using amount is larger, reaches
lOOkg/m2More than, project cost is higher.
A kind of Suspendome concrete integrated floor is disclosed in patent (CN101285329A), armoured concrete slab is using pre-
Making sheet, its underpart component are welded to connect by built-in fitting therewith again after being connected with each other, after the installation in place of each component, tensioning steel
Then rope pours post-cast strip between plate, form removal and scaffold, ultimately form Suspendome concrete integrated floor structure system, can
Big across range, construction and installation are convenient.But the armoured concrete slab of the superstructure is thicker floor, floor is from great, floor
Between connecting structure it is unreliable, connection type between strut and floor is complicated and is easy to appear deadlock phenomenon, influences to construct.
Summary of the invention
Technical problem to be solved by the invention is to provide the fast assembled steels-of a kind of reliable construction quality, speed of application
Combined concrete superstructure and its construction method, the present invention can make full use of the material property of concrete and steel, mitigate structure certainly
Weight increases structure and is applicable in span, is particularly suitable for the flooring or roofing system of the long span buildings such as stadiums.
In order to solve the above technical problems, the technical solution used in the present invention is:
Assembled steel concrete composite slab, including several superstructure units, it is in field word that the superstructure unit, which includes four pieces,
The built-in fitting of the precast floor slab of shape arrangement, four precast floor slab intersection lower surfaces is connected by square steel plate, four precast floor slabs
It is connected two-by-two by the built-in fitting in precast floor slab between adjacent surface and adjacent superstructure unit and perfusion mixes in the gap of adjacent surface
It is solidifying native, support rod is equipped at intervals in the square steel plate below every row's superstructure unit, the support rod lower end will be several by steel cable
A superstructure unit series connection is list Pin superstructure, and the steel cable both ends are connected with attachment base, and the attachment base is fixed at single Pin
The lower surface of the two precast floor slab intersections in superstructure end;Several list Pin superstructures, which are sequentially connected, constitutes assembled steel-concrete
Composite floor system;The precast floor slab is steel bar truss floor support plate of the surrounding with girt strip, reinforcing bar and top rebars in the girt strip
Reinforcing bar in truss, which is connected, constitutes steel reinforcement cage, the steel bar girder top rebars of the precast floor slab are exposed, steel bar girder lower part and
Surrounding girt strip is integrated by concrete casting;A Pin superstructure assembling after precast floor slab top and contiguous prefabricated floor gap again
It is poured concrete, forms the concrete cover of integral type at the top of single Pin superstructure.
Preferably, the support rod includes upper strut and lower supporting rod, and the upper strut upper end is fixedly linked with square steel plate, institute
It states strut lower end and lower supporting rod upper end to be pivotally connected by shaft, the lower supporting rod lower end is connected with steel cable.
Preferably, the lower supporting rod lower end is connected by connecting cover plate with steel cable, and the connecting cover plate includes center band
The upper dome plate and lower dome plate of groove, the upper dome plate are fixedly connected with lower supporting rod lower end, the upper dome
Plate and lower dome plate docking rear center's groove form a through-hole, and the steel cable is arranged through through-hole, the upper dome
Plate and lower dome plate are fixed by high-strength bolt.
Preferably, it is connected between contiguous prefabricated floor by frame-type connector, the frame-type connector and precast floor slab
In built-in fitting be connected.
Preferably, the built-in fitting in the precast floor slab is pre-embedded bolt, and the frame-type connector includes the first I-shaped
Steel and junction steel plate, the junction steel plate vertical welding are fixed on the upper lower flange and web two sides of the first I-steel, the company
It connects on steel plate and is symmetrically arranged with connecting hole in opposite webs, connecting hole and pre-embedded bolt cooperate on the junction steel plate.
Preferably, floor is equipped between the upper strut and square steel plate, between upper dome plate and lower supporting rod.
Preferably, the precast floor slab outer end face with attachment base is equipped with the connection structure connecting with pre embedded bolt on wall,
The connection structure includes connecting plate and the second I-steel, and the connecting plate and the built-in fitting of precast floor slab side are fixed, described
Connecting plate is fixed with the upper lower flange of the second I-steel and web vertical welding;Second I-steel lower part edge of a wing be equipped with
The gap of pre embedded bolt cooperation, welding baffle on the outside of the gap.
Preferably, the concrete being perfused between the concrete cover and precast floor slab selects lightweight concrete.
The present invention also provides the construction methods of above-mentioned assembled steel concrete composite slab, include the following steps,
(1), it sets up scaffold and does temporary support;
(2), assemble superstructure unit: junction steel plate is welded on the first I-steel web two by prefabricated frame posture connector
It side will be on the pre-embedded bolt and junction steel plate on contiguous prefabricated floor side two-by-two by four blocks of precast floor slabs in matrix pattern arrangement
Connecting hole cooperate and fix, the pre-embedded bolts of four precast floor slab intersection lower surfaces passes through square steel plate and is secured with nuts, by four
Block precast floor slab is assembled into superstructure unit;
(3), it assembles list Pin superstructure: superstructure unit being sequentially connected in series, the pre-embedded bolt on contiguous prefabricated floor side
With the connecting hole cooperation on junction steel plate and end fastened with nut after fixed, the square steel plate interval welding below superstructure unit
Upper strut and lower supporting rod are pivotally connected by upper strut by shaft, and upper dome plate with groove is welded in lower supporting rod lower end, in both ends building
The pre-embedded bolt of two precast floor slab intersections of cap unit matches to merge with attachment base to be secured with nuts;Steel cable is sequentially passed through
The groove of upper dome plate lower end below square steel plate, lower dome plate with groove are connect by high-strength bolt with upper dome plate
It is fixed, so that the steel cable passed through securely fixes;The both ends of steel cable are connect with attachment base;It is very heavy by tensioning at one end
Top applies prestressing force to steel cable, to make a Pin precast floor slab arch camber to calculated value, in the gap of contiguous prefabricated floor
And upper pouring concrete, complete the assembling of a Pin superstructure;
(4), by the sequence of construction of step (3) next Pin superstructure is made and between two Pin superstructure of concreting
Gap is finally assembled into one, and forms assembled steel concrete composite slab;
(5), after constructing, scaffold is dismantled, the disassembly mode of hand cradle can be used tears open by Pin from one end to the other end
It unloads.
The beneficial effects of adopting the technical scheme are that the present invention uses reinforcing bar purlin of the lower part surrounding with girt strip
Frame floor support plate is precast floor slab, 4 precast floor slabs is formed a superstructure unit first, then in a row connected superstructure unit is used
Steel cable connects into single Pin superstructure, to steel cable stretch-draw prestressing force, is then poured top concrete protective layer again;Assembled by Pin,
It is poured concrete between Pin and Pin, ultimately forms assembled steel concrete composite slab.The present invention and original building without girt strip
Lid is compared, and self weight is greatly reduced, and the globality of structure is more preferable, and safety is more preferable, and span is bigger;It is suitble to standardization extensive simultaneously
Production, precast floor slab quality are stablized, and interchangeability is good, versatile, economical rationality;It is convenient to construct, and construction workload is small, reduces behaviour
Make personnel labor intensity;It is particularly suitable for the roofing system of the long span buildings such as stadiums.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of assembled steel concrete composite slab provided in an embodiment of the present invention;
Fig. 2 is the structural schematic diagram of frame-type connector;
Fig. 3 is the partial enlarged view in Fig. 1 at B;
Fig. 4 is the partial enlarged view in Fig. 1 at C;
Fig. 5 is the connection schematic diagram of four precast floor slabs in superstructure unit;
Fig. 6 be in Fig. 1 A to not being poured concrete state diagram at the top of precast floor slab;
In figure: 1- precast floor slab, 2- square steel plate, 3- support rod, 4- steel cable, 5- attachment base, 6- girt strip, 7- reinforcing bar purlin
Frame, the upper strut of 8-, 9- lower supporting rod, 10- connecting cover plate, 11- upper dome plate, 12- lower dome plate, 13- high-strength bolt, 14-
Pre-embedded bolt, the first I-steel of 15-, 16- junction steel plate, 17- connecting hole, 18- floor, the second I-steel of 19-, 20- gap,
22- shaft, 23- link block.
Specific embodiment
In order to make the objectives, technical solutions, and advantages of the present invention clearer, below in conjunction with attached drawing and specific implementation
Example, the present invention is described in further detail.It should be appreciated that specific embodiment described herein is only used to explain this hair
It is bright, it is not intended to limit the present invention.
As shown in Figure 1,5, assembled steel concrete composite slab provided by the invention, including several superstructure units, institute
Stating superstructure unit includes four blocks of precast floor slabs 1 in matrix pattern arrangement, and the built-in fitting of four 1 intersection lower surfaces of precast floor slab is logical
It crosses square steel plate 2 to be connected, four precast floor slabs 1 are two-by-two by pre-buried in precast floor slab 1 between adjacent surface and adjacent superstructure unit
Part is connected and concrete perfusion in the gap of adjacent surface, is equipped at intervals with support rod 3 in the square steel plate 2 below every row's superstructure unit,
The series connection of several superstructure units is list Pin superstructure, 4 both ends of steel cable and company by steel cable 4 by 3 lower end of support rod
Joint chair 5 is connected, and the attachment base 5 is fixed at the lower surface of two 1 intersections of precast floor slab in single Pin superstructure end;Several
Single Pin superstructure, which is sequentially connected, constitutes assembled steel concrete composite slab;The precast floor slab 1 is reinforcing bar of the surrounding with girt strip 6
Truss floor support plate, the reinforcing bar in the girt strip 6 is connected with the reinforcing bar in top rebars truss 7 constitutes steel reinforcement cage, the prefabricated building
7 top rebars of steel bar girder of plate 1 are exposed, 7 lower part of steel bar girder and surrounding girt strip 6 are integrated by concrete casting, in a Pin
The top and contiguous prefabricated floor gap of precast floor slab 1 are poured concrete again after superstructure assembling, form one at the top of single Pin superstructure
The concrete cover of body formula.
Use steel bar truss floor support plate of the lower part surrounding with girt strip for precast floor slab, self weight substantially reduces, every 4 prefabricated buildings
Board group connects into single Pin superstructure with steel cable at a superstructure unit, then by a row connected superstructure unit, is then poured top again
Portion's concrete cover;It finally is poured concrete by between Pin assembling, Pin and Pin, forms assembled steel concrete composite slab.
This assembled steel-Combined concrete building cover structure globality is more preferable, and safety is more preferable, and span is bigger;It makes full use of simultaneously
The material property of concrete and steel, economical rationality;And it is high using the prefabricated degree of precast floor slab, it is extensive to be more suitable for standardization
Production, more convenient and quicker of constructing.
As shown in figure 3, the support rod 3 includes upper strut 8 and lower supporting rod 9, upper 8 upper end of strut and square steel plate 2 are solid
Fixed to be connected, upper 8 lower end of strut and 9 upper end of lower supporting rod are pivotally connected, and 9 lower end of lower supporting rod is connected with steel cable 4.Split type
The more convenient production of support rod and installing and dismounting, can also reduce its in operation force in radial it is excessive and cause strut with
Square steel plate junction is broken, while being also convenient for the installation of steel cable or being applied prestressing force.
Further, 9 lower end of lower supporting rod is connected by connecting cover plate 10 with steel cable 4, and the connecting cover plate 10 is wrapped
Include center upper dome plate 11 with groove and lower dome plate 12, the upper dome plate 11 and the fixed company in 9 lower end of lower supporting rod
It connects, the upper dome plate 11 and lower dome plate 12 dock rear center's groove and form a through-hole, and the steel cable 4 is through logical
Hole setting, the upper dome plate 11 and lower dome plate 12 are fixed by high-strength bolt 13, so that steel cable 4 tightly be blocked
Extremely.Connecting cover plate selects split type structure design, while facilitating production and installing and dismounting, also reduces production and operation is difficult
Spend coefficient.
In one particular embodiment of the present invention, the upper strut 8, lower supporting rod 9 are round steel pipe, upper 8 lower end of strut
Soldering and sealing circular end plate, end plate lower section two pieces of otic placodes of vertical position welding, 9 upper end of lower supporting rod is flattened and aperture, the otic placode and lower supporting rod of upper strut
It is pivotally connected by shaft 22.In order to reinforce upper strut 8 and lower supporting rod 9, between the upper strut 8 and square steel plate 2, upper dome plate 11
Floor 18 is equipped between lower supporting rod 9.
In a preferred embodiment of the invention, it is connected between contiguous prefabricated floor 1 by frame-type connector, the frame
Posture connector is connected with the built-in fitting in precast floor slab 1.
Wherein, the built-in fitting in the precast floor slab 1 is pre-embedded bolt 14;As shown in Fig. 2, the frame-type connector packet
The first I-steel 15 and junction steel plate 16 are included, 16 vertical welding of junction steel plate is fixed on the upper lower flange of the first I-steel 15
And web two sides, it is symmetrically arranged with connecting hole 17 on the junction steel plate 16 and in opposite webs, is connected on the junction steel plate 16
Hole 17 and pre-embedded bolt 14 cooperate.Such structure is more convenient the connection between precast floor slab.
As shown in fig. 6, with attachment base 51 outer end face of precast floor slab be equipped with pre embedded bolt is connect on wall, on column or beam
Connection structure, the connection structure includes connecting plate and the second I-steel 19, and the connecting plate is pre- with 1 side of precast floor slab
Embedded part is fixed, and the connecting plate is fixed with the upper lower flange of the second I-steel 19 and web vertical welding;Second I-steel
The 19 lower parts edge of a wing are equipped with the gap 20 cooperated with pre embedded bolt, the 20 outside welding baffle of gap.Steel can be selected in connecting plate
Second I-steel of welding steel is mounted on precast floor slab side first by plate, will when precast floor slab gap is poured concrete
Second I-steel and steel plate are also cast in concrete, only lower part reserving hole, by the second I-steel lower part edge of a wing and its under
Side exposes, and reserves installation gap;At the edge of a wing of precast floor slab side the second I-steel lower part on gap and wall, column or beam
After upper pre embedded bolt is secured with nuts with merging, then in lower flange gap outer ledge welding baffle, there is pre embedded bolt along steel
The sliding space in drag-line direction simultaneously prevents it from skidding off.After pre embedded bolt is inserted into gap, backing plate is set at the top of pre embedded bolt, so
Chain intermittent weld baffle, the baffle level are welded on the second I-steel lower part edge of a wing face with gap again on the outside of backing plate afterwards,
Finally by the reserving hole Concrete Filled of assembled steel concrete composite slab side.
In order to mitigate overall weight, the concrete being perfused between the concrete cover and precast floor slab 1 selects lightweight
Concrete.Wherein, haydite concrete, light aggregate concrete or air entrained concrete can be selected in the lightweight concrete.
The present invention also provides the construction methods of above-mentioned assembled steel concrete composite slab, include the following steps,
(1), it sets up scaffold and does temporary support;
(2), assemble superstructure unit: junction steel plate 16 is welded on 15 web of the first I-steel by prefabricated frame posture connector
Two sides, by four blocks of precast floor slabs 1 in matrix pattern arrange, by contiguous prefabricated 1 side of floor two-by-two pre-embedded bolt 14 with connect
Connecting hole 17 on steel plate 16, which cooperates, to be fixed, and the pre-embedded bolt 14 of four 1 intersection lower surfaces of precast floor slab is used across square steel plate 2
Nut is fixed, and is assembled into superstructure unit by four blocks of precast floor slabs 1;
(3), it assembles list Pin superstructure: superstructure unit being sequentially connected in series, the pre-buried spiral shell on contiguous prefabricated 1 side of floor
Connecting hole cooperation and end on bolt 14 and junction steel plate 16 are fixed after being fastened with nut, between the square steel plate 2 below superstructure unit
Every welding upper strut 8, upper strut 8 is pivotally connected with lower supporting rod 9 by shaft 22, top circle with groove is welded in 9 lower end of lower supporting rod
Cover board 11, lower dome plate 12 with groove are connected and fixed by high-strength bolt 13 with upper dome plate 11, upper dome plate 11
Rear center's groove, which is docked, with lower dome plate 12 forms a through-hole;Two 1 intersections of precast floor slab of both ends superstructure unit
Pre-embedded bolt 14 matches to merge with attachment base 5 to be secured with nuts.
As shown in figure 4, the attachment base 5 includes junction steel plate 16 and link block 23, junction steel plate is prefabricated with two first
The pre-embedded bolt of floor intersection is secured with nuts with merging, and the link block end of vertical welding can be with steel in the middle part of junction steel plate
Drag-line is bolted.
Steel cable 4 is sequentially passed through into the through-hole that 2 lower section upper dome plate 11 of square steel plate and lower dome plate 12 form, steel is drawn
4 both ends of rope are connect with attachment base 5;Prestressing force is applied to steel cable 4 by stretch-draw jack, makes a Pin superstructure arch camber to theory
Calculated value forms concrete cover in the gap of contiguous prefabricated floor 1 and upper pouring concrete, completes the group of a Pin superstructure
Dress;
(4), by the sequence of construction of step (3) next Pin superstructure is made and between two Pin superstructure of concreting
Gap is finally assembled into one, and forms assembled steel concrete composite slab;
(5), after constructing, scaffold is dismantled, disassembly mode can be used to be dismantled by Pin from one end to the other end.
Used herein a specific example illustrates the principle and implementation of the invention, and above embodiments are said
It is bright to be merely used to help understand method and its core concept of the invention.It should be pointed out that for the ordinary skill of the art
, without departing from the principle of the present invention, can be with several improvements and modifications are made to the present invention for personnel, these improvement
It is also fallen within the protection scope of the claims of the present invention with modification.