KR101216716B1 - Diaphragm wall and this construction technique - Google Patents
Diaphragm wall and this construction technique Download PDFInfo
- Publication number
- KR101216716B1 KR101216716B1 KR1020100108540A KR20100108540A KR101216716B1 KR 101216716 B1 KR101216716 B1 KR 101216716B1 KR 1020100108540 A KR1020100108540 A KR 1020100108540A KR 20100108540 A KR20100108540 A KR 20100108540A KR 101216716 B1 KR101216716 B1 KR 101216716B1
- Authority
- KR
- South Korea
- Prior art keywords
- wall
- trench
- underground continuous
- continuous wall
- deep trench
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/20—Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
- E02D29/0258—Retaining or protecting walls characterised by constructional features
- E02D29/0275—Retaining or protecting walls characterised by constructional features cast in situ
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/24—Prefabricated piles
- E02D5/28—Prefabricated piles made of steel or other metals
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/24—Prefabricated piles
- E02D5/30—Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/66—Mould-pipes or other moulds
- E02D5/68—Mould-pipes or other moulds for making bulkheads or elements thereof
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0004—Synthetics
- E02D2300/0018—Cement used as binder
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0037—Clays
- E02D2300/004—Bentonite or bentonite-like
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
본 발명은 SCW(Soil Cement Wall)공법과 지하연속벽(Slurry Wall)의 중간 기능을 가진 가설토류벽체 공법으로 트렌치를 굴착한 후, 벤토나이트 안정액을 사용하여 트렌치 공벽을 유지하고, 상기 트렌치 내에 강재파일을 삽입한 후 저강도 콘크리트를 타설하여 지중 연속벽을 시공함으로써, 차수성이 우수하고 단면의 강성이 커서 인접구조물 보호 및 주변지반 침하를 억제하며, 소음 및 진동이 적어 도심지 공사에 적합하며, 호박돌이 함유된 사력층에 시공성이 우수하며, 수직도 관리가 용이하며, 근입 및 수밀성이 우수하여 최악의 지반조건에서도 안전한 지중 연속벽 및 이의 시공방법을 제공하는데 그 목적이 있다.
상기한 목적을 달성하기 위한 본 발명에 따른 지중 연속벽 시공방법은 지중 연속벽을 시공할 예정위치의 지면을 일정한 폭 및 깊이로 굴착하여 얕은 트렌치를 형성하는 단계(Ⅰ); 상기 얕은 트렌치의 양측에 일정한 간격을 두고 거푸집을 각각 설치하고, 상기 거푸집에 철근을 배근함과 동시에 콘크리트를 타설 및 양생시켜 안내벽을 형성하는 단계(Ⅱ); 상기 안내벽의 내측에 하향으로 일정한 깊이를 갖도록 굴착하여 깊은 트렌치를 형성하는 단계(Ⅲ); 상기 얕은 트렌치 상단에 격자형상의 안내프레임을 설치하는 단계(Ⅳ); 다수개의 H빔으로 이루어진 강재파일을 조립하는 단계(Ⅴ); 상기 안내프레임 내의 깊은 트렌치에 강재파일을 삽입하는 단계(Ⅵ); 상기 강재파일이 삽입된 얕은 트렌치 내에 트레미관을 삽입하는 단계(Ⅶ); 상기 트레미관을 이용하여 깊은 트렌치 내 저강도 콘크리트를 타설 및 양생시키는 단계(Ⅷ)를 순차적으로 시행하여 지중 연속벽을 시공함을 특징으로 한다.
또한, 상기한 목적을 달성하기 위한 본 발명에 따른 지중 연속벽은 청구항 1항 기재의 지중 연속벽 시공방법으로 시공된 것을 특징으로 한다.According to the present invention, after excavating the trench by a temporary earth wall method having an intermediate function between a Soil Cement Wall (SCW) method and an underground continuous wall (Slurry Wall), the trench hollow wall is maintained using a bentonite stabilizer, and the steel pile is in the trench. After inserting the low strength concrete, the underground continuous wall is constructed, and it has excellent degree of stiffness and the rigidity of the cross section. The purpose of the present invention is to provide a continuous ground wall and its construction method which are safe in the worst ground conditions because of excellent workability, easy verticality management, and excellent access and water tightness.
The underground continuous wall construction method according to the present invention for achieving the above object comprises the steps of: (I) to form a shallow trench by excavating the ground at a predetermined position and the predetermined position for the underground continuous wall construction; Installing the formwork at regular intervals on both sides of the shallow trench, placing reinforcement to the formwork, and placing and curing concrete to form guide walls (II); Excavating the inner wall of the guide wall to have a predetermined depth downward to form a deep trench (III); (IV) installing a grating-shaped guide frame on the shallow trench; Assembling a steel pile consisting of a plurality of H beams (V); Inserting a steel file into a deep trench in the guide frame (VI); (I) inserting a trailing tube into a shallow trench into which the steel pile is inserted; It is characterized by constructing a continuous underground wall by sequentially performing the step (Ⅷ) of placing and curing low-strength concrete in a deep trench using the tremi tube.
In addition, the underground continuous wall according to the present invention for achieving the above object is characterized in that it was constructed by the underground continuous wall construction method of claim 1.
Description
본 발명은 지중 연속벽 및 이의 시공방법에 관한 것으로, 특히 SCW(Soil Cement Wall)공법과 지하연속벽(Slurry Wall)의 중간 기능을 가진 가설토류벽체 공법으로 트렌치를 굴착한 후, 벤토나이트 안정액을 사용하여 트렌치 공벽을 유지하고, 상기 트렌치 내에 강재파일을 삽입한 후 콘크리트를 타설하여 지중 연속벽을 형성하는 지중 연속벽 및 이의 시공방법에 관한 것이다. The present invention relates to an underground continuous wall and a construction method thereof, and in particular, after excavating a trench by a temporary earth wall method having an intermediate function between a SCW (Soil Cement Wall) method and a slurry wall, a bentonite stabilizer is used. By maintaining the trench hollow wall, and inserting the steel pile into the trench, the present invention relates to an underground continuous wall and a construction method thereof for forming concrete continuous walls by pouring concrete.
일반적으로 지중 연속벽 공법은 굴착된 토량에 비례하여, 안정액을 공급하여 굴착면이 붕괴하는 것을 막아주고, 지하수의 유입을 차단, 토사 굴착에 알맞게 고안된 버킷 또는 트렌치 커터를 설계된 소정의 깊이만큼 굴착한 후, 철근망을 근입하고, 콘크리트를 타설하는 작업을 반복함으로써, 지중에 연속된 철근콘크리트벽이 형성된다.In general, the underground continuous wall method provides a stabilizer to prevent the collapse of the excavation surface by supplying a stabilizer, to block the inflow of groundwater, and to excavate a bucket or trench cutter designed for earth excavation to a predetermined depth. After that, the reinforcing concrete wall is formed in the ground by repeating the operation of pouring the reinforcing bar network and placing concrete.
댐의 기초로 활용되거나 내진벽, 진동차단벽으로서의 탁월한 역할을 한다.It is used as a foundation for dams, or plays an excellent role as a seismic barrier or vibration barrier.
또한, 건축물의 지하구조물을 건설하기 위해 토사를 굴착시 가설 토류벽으로써의 역할을 할 수 있고 가설벽이 아닌 본체벽으로써 많이 활용된다. In addition, when excavating earth and sand to construct the underground structure of the building, it can serve as a temporary earth wall, and is utilized as a main body wall rather than a temporary wall.
트렌치 내의 토사를 굴착할 때 투입하는 안정액은 물보다 비중이 크므로 굴착면의 붕괴를 방지하고 굴착면의 토사 공극에 침투, 차수막을 형성하여 지하수의 차수 효과를 얻게 된다. When excavating the soil in the trench, the stabilizer is more specific than water, preventing the collapse of the excavation surface, penetrating into the soil pores of the excavation surface and forming a barrier film to obtain the order effect of groundwater.
시공방법은 설계된 벽의 두께와 위치에 따라 안내벽을 설치한 후, 엘리먼트 별로 분할, 설정하여 소정의 설계 깊이까지 굴착이 완료되면 트렌치 내의 잔존하는 토립자를 제거하기 위해 서징을 실시한다. In the construction method, after the guide wall is installed according to the thickness and position of the designed wall, it is divided and set for each element, and when excavation is completed to a predetermined design depth, surging is performed to remove the remaining granules in the trench.
조립된 철근망을 근입한 후, 트레미관을 설치한 다음, 굴착된 하단부터 콘크리트 타설을 하면서 안정액을 회수하여 1개의 엘리먼트를 완료한다. After entering the assembled reinforcing bar network, install the trem tube, and then finish the one element by recovering the stabilizer while pouring concrete from the excavated bottom.
상기한 바와 같은 단계로 이루어진 종래의 지중 연속벽 시공방법은 다음과 같은 문제가 있다.Conventional underground continuous wall construction method consisting of the steps as described above has the following problems.
첫째, 종래의 지중 연속벽 시공방법은 일반적인 토류공법에 비해 상대적으로 고가인 문제점이 있다.First, the conventional underground continuous wall construction method has a relatively expensive problem compared to the general earth process.
둘째, 트렌치 굴착면의 안정은 안정액에 의해서 확보되지만 토질이나 지하수의 상황에 따라 안정이 손상되는 문제가 있다.Second, the stability of the trench excavation surface is secured by the stabilizer, but there is a problem that the stability is impaired depending on the condition of the soil or groundwater.
셋째, 안정액 속에 부유상태로 혼합된 토립자가 시간의 경과와 더불어 트렌치 바닥에 가라앉아 침전된 것을 슬라임이라 하며, 이 슬라임을 트렌치 바닥에 남겨 놓은 채 콘크리트를 타설하면 콘크리트 속으로 흘러들어가서 강도의 저하를 초래하거나 시공조인트 부분에 부착되어 누수의 원인이 된다. Third, slime mixed with suspended solids in the stabilizer settled down in the trench with the passage of time, and it is called slime. It may cause water leakage or stick to the joint.
이에, 본 발명은 상기한 바와 같은 제문제점을 해결하기 위해 안출된 것으로, SCW(Soil Cement Wall)공법과 지하연속벽(Slurry Wall)의 중간 기능을 가진 가설토류벽체 공법으로 트렌치를 굴착한 후, 벤토나이트 안정액을 사용하여 트렌치 공벽을 유지하고, 상기 트렌치 내에 강재파일을 삽입한 후 저강도 콘크리트를 타설하여 지중 연속벽을 시공함으로써, 차수성이 우수하고 단면의 강성이 커서 인접구조물 보호 및 주변지반 침하를 억제하며, 소음 및 진동이 적어 도심지 공사에 적합하며, 호박돌이 함유된 사력층에 시공성이 우수하며, 수직도 관리가 용이하며, 근입 및 수밀성이 우수하여 최악의 지반조건에서도 안전한 지중 연속벽 및 이의 시공방법을 제공하는데 그 목적이 있다.Thus, the present invention was devised to solve the problems described above, after excavating the trench by a temporary earth wall method having an intermediate function between the SCW (Soil Cement Wall) method and the slurry wall (Slurry Wall), The bentonite stabilizer is used to maintain the trench hollow wall, insert the steel pile into the trench, and then install the low strength concrete to construct the continuous wall of the underground. It is suitable for urban construction because of low noise and vibration, and it has excellent workability on the sand layer containing amber stone, easy to manage verticality, and excellent access and water tightness. The purpose is to provide a construction method thereof.
상기한 목적을 달성하기 위한 본 발명에 따른 지중 연속벽 시공방법은 지중 연속벽을 시공할 예정위치의 지면을 일정한 폭 및 깊이로 굴착하여 얕은 트렌치를 형성하는 단계(Ⅰ); 상기 얕은 트렌치의 양측에 일정한 간격을 두고 거푸집을 각각 설치하고, 상기 거푸집에 철근을 배근함과 동시에 콘크리트를 타설 및 양생시켜 안내벽을 형성하는 단계(Ⅱ); 상기 안내벽의 내측에 하향으로 일정한 깊이를 갖도록 굴착하여 깊은 트렌치를 형성하는 단계(Ⅲ); 상기 얕은 트렌치 상단에 격자형상의 안내프레임을 설치하는 단계(Ⅳ); 다수개의 H빔으로 이루어진 강재파일을 조립하는 단계(Ⅴ); 상기 안내프레임 내의 깊은 트렌치에 강재파일을 삽입하는 단계(Ⅵ); 상기 강재파일이 삽입된 얕은 트렌치 내에 트레미관을 삽입하는 단계(Ⅶ); 상기 트레미관을 이용하여 깊은 트렌치 내 저강도 콘크리트를 타설 및 양생시키는 단계(Ⅷ)를 순차적으로 시행하여 지중 연속벽을 시공함을 특징으로 한다.The underground continuous wall construction method according to the present invention for achieving the above object comprises the steps of: (I) to form a shallow trench by excavating the ground at a predetermined position and the predetermined position for the underground continuous wall construction; Installing the formwork at regular intervals on both sides of the shallow trench, placing reinforcement to the formwork, and placing and curing concrete to form guide walls (II); Excavating the inner wall of the guide wall to have a predetermined depth downward to form a deep trench (III); (IV) installing a grating-shaped guide frame on the shallow trench; Assembling a steel pile consisting of a plurality of H beams (V); Inserting a steel file into a deep trench in the guide frame (VI); (I) inserting a trailing tube into a shallow trench into which the steel pile is inserted; It is characterized by constructing a continuous underground wall by sequentially performing the step (Ⅷ) of placing and curing low-strength concrete in a deep trench using the tremi tube.
또한, 상기한 목적을 달성하기 위한 본 발명에 따른 지중 연속벽은 청구항 1항 기재의 지중 연속벽 시공방법으로 시공된 것을 특징으로 한다.In addition, the underground continuous wall according to the present invention for achieving the above object is characterized in that it was constructed by the underground continuous wall construction method of claim 1.
이상에서 설명한 바와 같이, 본 발명에 따른 지중 연속벽 및 이의 시공방법은 다음과 같은 효과가 있다.As described above, the underground continuous wall and its construction method according to the present invention has the following effects.
첫째, 본 발명은 차수성이 우수하고 단면의 강성이 커서 인접구조물 보호 및 주변지반 침하를 억제한다.First, the present invention is excellent in the degree of orderability and rigidity of the cross section to protect the adjacent structure and suppress the ground subsidence.
둘째, 본 발명은 소음 및 진동이 적어 도심지 공사에 적합하다.Second, the present invention is suitable for downtown construction because of less noise and vibration.
셋째, 본 발명은 호박돌이 함유된 사력층에 시공성이 우수하다.Third, the present invention is excellent in workability in the history layer containing amber stone.
넷째, 본 발명은 수직도 관리가 용이하다.Fourth, the present invention is easy to manage the verticality.
다섯째, 본 발명은 근입 및 수밀성이 우수하여 최악의 지반조건에서도 안전한 공법이다.Fifth, the present invention is excellent in access and watertightness and is a safe method even in the worst ground conditions.
도 1 내지 도 12는 본 발명에 따른 지중 연속벽 시공순서를 도시한 공정도.1 to 12 is a process chart showing the underground continuous wall construction sequence according to the present invention.
이하, 본 발명을 첨부한 예시도면을 참조하여 상세히 설명한다.Hereinafter, with reference to the accompanying drawings, the present invention will be described in detail.
도 1 내지 도 12는 본 발명에 따른 지중 연속벽 시공순서를 도시한 공정도이다.1 to 12 is a process chart showing the construction sequence of the underground continuous wall according to the present invention.
이들 도면에 도시된 바와 같이, 본 발명에 따른 지중 연속벽 시공방법은 지중 연속벽(W)을 시공할 예정위치의 지면(10)을 일정한 폭 및 깊이로 굴착하여 얕은 트렌치(12)를 형성하는 단계(Ⅰ); 상기 얕은 트렌치(12)의 양측에 일정한 간격을 두고 거푸집(14)을 각각 설치하고, 상기 거푸집(14)에 철근(16)을 배근함과 동시에 콘크리트(18)를 타설 및 양생시켜 안내벽(20)을 형성하는 단계(Ⅱ); 상기 안내벽(20)의 내측에 하향으로 일정한 깊이를 갖도록 굴착하여 깊은 트렌치(22)를 형성하는 단계(Ⅲ); 상기 얕은 트렌치(12) 상단에 격자형상의 안내프레임(24)을 설치하는 단계(Ⅳ); 다수개의 H빔(26)으로 이루어진 강재파일(28)을 조립하는 단계(Ⅴ); 상기 안내프레임(24) 내의 깊은 트렌치(22)에 강재파일(28)을 삽입하는 단계(Ⅵ); 상기 강재파일(28)이 삽입된 얕은 트렌치(12) 내에 트레미관(30)을 삽입하는 단계(Ⅶ); 상기 트레미관(30)을 이용하여 깊은 트렌치(22) 내 저강도 콘크리트(32)를 타설 및 양생시키는 단계(Ⅷ)를 순차적으로 시행하여 지중 연속벽(W)을 시공한다.As shown in these drawings, the underground continuous wall construction method according to the present invention excavates the
여기서, 상기 깊은 트렌치(22)를 형성한 후, 상기 깊은 트렌치(22) 내에 벤토나이트 안정액을 주입하는 단계를 추가한다.Here, after forming the
또한, 상기 저강도 콘크리트(32)는 시멘트 1~2 중량부, 벤토나이트 0.35~0.45 중량부, 물 9.15~9.53 중량부로 구성된다.In addition, the
그리고 상기한 단계(Ⅰ~Ⅷ)를 순차적으로 시행하여 단위벽(W1)을 시공하고, 상기 단위벽(W1)과 일정간격 이격된 위치에 상기한 단계(Ⅰ~Ⅷ)를 반복하여 다른 단위벽(W2)을 시공하고, 상기 단위벽(W1)과 다른 단위벽(W2)간의 가운데에 상기한 단계(Ⅰ~Ⅷ)를 반복하여 연결벽(W3)을 시공하여 지중 연속벽(W)을 시공한다.Then, the above-mentioned steps (I to VII) are sequentially performed to construct the unit wall (W1), and the above-mentioned steps (I to VII) are repeated at different positions from the unit wall (W1) to repeat the other unit walls. Construct (W2), and repeat the above-mentioned steps (I to VII) between the unit wall (W1) and the other unit wall (W2) to construct the connecting wall (W3) to construct the underground continuous wall (W). do.
즉, 본 발명에 따른 지중 연속벽 시공방법은 얕은 트렌치(12) 형성단계(Ⅰ), 안내벽(20) 형성단계(Ⅱ), 깊은 트렌치(22) 형성단계(Ⅲ), 안내프레임(24) 설치단계(Ⅳ), 강재파일(28) 조립단계(Ⅴ), 강재파일(28) 삽입단계(Ⅵ), 트레미관(30) 삽입단계(Ⅶ), 저강도 콘크리트(32) 타설 및 양생단계(Ⅷ)를 순차적으로 시행하여 지중 연속벽(W)을 시공하는 것이다.That is, the underground continuous wall construction method according to the present invention is the
여기서, 상기 트렌치(12) 형성단계(Ⅰ)는 도 1에 도시된 바와 같이, 지중 연속벽(W)을 시공할 예정위치의 지면(10)을 일정한 폭 및 깊이로 굴착하는 단계이다.Here, the
이어서, 상기 안내벽(20) 형성단계(Ⅱ)는 도 2에 도시된 바와 같이, 얕은 트렌치(12)의 양측에 일정한 간격을 두고 거푸집(14)을 각각 설치하고, 상기 거푸집(14)에 철근(16)을 배근함과 동시에 콘크리트(18)를 타설 및 양생시켜 형성한다.Subsequently, in the forming step (II) of the
이어서, 상기 깊은 트렌치(22) 형성단계(Ⅲ)는 도 3에 도시된 바와 같이, 안내벽(20)의 내측에 하향으로 일정한 깊이를 갖도록 굴착한다.Subsequently, the
여기서, 상기 깊은 트렌치(22)를 형성한 후, 상기 깊은 트렌치(22) 내에 벤토나이트 안정액을 주입하는 단계를 추가한다.Here, after forming the
이어서, 상기 안내프레임(24) 설치단계(Ⅳ)는 도 4에 도시된 바와 같이, 얕은 트렌치(12) 상단에 격자형상으로 안내프레임(24)을 설치한다.Subsequently, in the installation step (IV) of the
이어서, 상기 강재파일(28) 조립단계(Ⅴ)는 도 5에 도시된 바와 같이, 다수개의 H빔(26)으로 엮어서 강재파일(28)을 형성한다.Subsequently, assembling the steel pile 28 (V), as shown in FIG. 5, is woven into the plurality of
이어서, 상기 강재파일(28) 삽입단계(Ⅵ)는 도 6에 도시된 바와 같이, 안내프레임(24) 내의 깊은 트렌치(22)에 강재파일(28)을 삽입한다.Subsequently, the
이어서, 상기 트레미관(30) 삽입단계(Ⅶ)는 도 7에 도시된 바와 같이, 강재파일(28)이 삽입된 얕은 트렌치(12) 내에 트레미관(30)을 삽입한다.Subsequently, as shown in FIG. 7, the
이어서, 상기 저강도 콘크리트(32) 타설 및 양생단계(Ⅷ)는 도 8에 도시된 바와 같이, 트레미관(30)에 저강도 콘크리트(32) 주입하여 깊은 트렌치(22) 내를 저강도 콘크리트(32) 타설 및 양생시켜서 도 9에 도시된 바와 같은 단위벽(W1)을 완성한다.Subsequently, as shown in FIG. 8, the low-
한편, 상기한 단계(Ⅰ~Ⅷ)를 순차적으로 시행하여 단위벽(W1)을 시공하고, 상기 단위벽(W1)과 일정간격 이격된 위치에 상기한 단계(Ⅰ~Ⅷ)를 반복하여 다른 단위벽(W2)을 시공하고, 상기 단위벽(W1)과 다른 단위벽(W2)간의 가운데에 상기한 단계(Ⅰ~Ⅷ)를 반복하여 도 10 및 도 11에 도시된 바와 같이, 연결벽(W3)을 시공하여, 도 12에 도시된 바와 같은 지중 연속벽(W)을 시공한다.On the other hand, the above-mentioned steps (I to VII) are carried out sequentially to construct the unit wall (W1), and repeat the above-mentioned steps (I to VII) at a position spaced apart from the unit wall (W1) by another unit. Construct the wall W2, and repeat the above steps I to V in the middle between the unit wall W1 and the other unit wall W2, and as shown in Figs. 10 and 11, the connecting wall W3. ), The underground continuous wall (W) as shown in Figure 12 is constructed.
10: 지면 12: 얕은 트렌치
14: 거푸집 16: 철근
18: 콘크리트 20: 안내벽
22: 깊은 트렌치 24: 안내프레임
26: H빔 28: 강재파일
30: 트레미관 32: 저강도 콘크리트
W1: 제1단위벽 W2: 제2단위벽
W3: 연결벽 W: 지중 연속벽10: Floor 12: Shallow Trench
14: Formwork 16: Rebar
18: concrete 20: guide wall
22: deep trench 24: guide frame
26: H beam 28: steel pile
30: tremi tube 32: low strength concrete
W1: first unit wall W2: second unit wall
W3: connecting wall W: underground continuous wall
Claims (5)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020100108540A KR101216716B1 (en) | 2010-11-03 | 2010-11-03 | Diaphragm wall and this construction technique |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020100108540A KR101216716B1 (en) | 2010-11-03 | 2010-11-03 | Diaphragm wall and this construction technique |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20120046966A KR20120046966A (en) | 2012-05-11 |
KR101216716B1 true KR101216716B1 (en) | 2012-12-28 |
Family
ID=46265873
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020100108540A KR101216716B1 (en) | 2010-11-03 | 2010-11-03 | Diaphragm wall and this construction technique |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR101216716B1 (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101685114B1 (en) | 2016-01-26 | 2016-12-20 | 주식회사 아승이앤씨 | Underground diaphragm wall using embedded plates and coupler and contructing method thereof |
KR102219326B1 (en) | 2020-09-18 | 2021-02-23 | 김인성 | Apparatus for reinforced bar overlay of precast wall and its construction method thereof |
KR102224943B1 (en) | 2020-09-18 | 2021-03-09 | 김인성 | Precast retaing wall structure with improved seismic performance and construction method thereof |
KR102240488B1 (en) | 2020-08-10 | 2021-04-16 | 우창래 | Connecting box for underground continuous wall and construction method using them same |
KR20220019415A (en) | 2020-08-10 | 2022-02-17 | 우창래 | Connecting box for underground continuous wall and construction method using them same |
KR102638704B1 (en) | 2022-10-26 | 2024-02-20 | 주식회사 가우리안 | Continuous steel diaphragm wall technology for underground space wall structure and its construction method |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109518680A (en) * | 2018-10-16 | 2019-03-26 | 中铁二十二局集团轨道工程有限公司 | A kind of construction of diaphragm wall structure and construction method |
KR102254243B1 (en) * | 2019-08-08 | 2021-05-18 | (주)토네이도건설 | Non-utility facilities and non-open cut underground structure and their construction methods |
CN112593546A (en) * | 2020-12-03 | 2021-04-02 | 中铁广州工程局集团有限公司 | Construction method for underground diaphragm wall to penetrate through underground structure |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003027480A (en) * | 2001-07-17 | 2003-01-29 | Daiyo Kiko Kogyo Kk | Method of casting sludge mortar using tremie pipe |
KR100722665B1 (en) * | 2007-03-15 | 2007-05-28 | 삼보지질 주식회사 | Steel guide wall for construction of underground diaphragm wall and construction method of underground diaphragm wall using the same |
-
2010
- 2010-11-03 KR KR1020100108540A patent/KR101216716B1/en active IP Right Grant
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003027480A (en) * | 2001-07-17 | 2003-01-29 | Daiyo Kiko Kogyo Kk | Method of casting sludge mortar using tremie pipe |
KR100722665B1 (en) * | 2007-03-15 | 2007-05-28 | 삼보지질 주식회사 | Steel guide wall for construction of underground diaphragm wall and construction method of underground diaphragm wall using the same |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101685114B1 (en) | 2016-01-26 | 2016-12-20 | 주식회사 아승이앤씨 | Underground diaphragm wall using embedded plates and coupler and contructing method thereof |
KR102240488B1 (en) | 2020-08-10 | 2021-04-16 | 우창래 | Connecting box for underground continuous wall and construction method using them same |
KR20220019415A (en) | 2020-08-10 | 2022-02-17 | 우창래 | Connecting box for underground continuous wall and construction method using them same |
KR102219326B1 (en) | 2020-09-18 | 2021-02-23 | 김인성 | Apparatus for reinforced bar overlay of precast wall and its construction method thereof |
KR102224943B1 (en) | 2020-09-18 | 2021-03-09 | 김인성 | Precast retaing wall structure with improved seismic performance and construction method thereof |
KR102638704B1 (en) | 2022-10-26 | 2024-02-20 | 주식회사 가우리안 | Continuous steel diaphragm wall technology for underground space wall structure and its construction method |
Also Published As
Publication number | Publication date |
---|---|
KR20120046966A (en) | 2012-05-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101216716B1 (en) | Diaphragm wall and this construction technique | |
CN102966108B (en) | Construction method of deep foundation pit close to building and adopting underground structure as internal support | |
KR100722665B1 (en) | Steel guide wall for construction of underground diaphragm wall and construction method of underground diaphragm wall using the same | |
KR101664368B1 (en) | A cast-in place pile arrangement method for head of concrete pile exposed to outside using geo tube | |
KR101112107B1 (en) | The retaining wall using circular PHC pile with catch pit which is had and construction method using thereby | |
KR101612521B1 (en) | Method for constructing underground structures restraining transformation and using external wall | |
KR101041274B1 (en) | Retaining wall grouting structure and method for constructing thereof | |
KR20210009509A (en) | Cast-in-place pile using reinforced grouting and construction method | |
KR101159755B1 (en) | Finishing block and Retaining wall using the same | |
CN115653000A (en) | Gravity pipe gallery in-situ protection structure system in foundation pit range and construction method | |
KR101021915B1 (en) | A method for constructing cut-off temporary structure for sheathing work | |
CN113216213B (en) | Basement waterproof foundation pit structure and construction method | |
WO1984003528A1 (en) | Method and apparatus for constructing reinforced concrete walls in the earth | |
CN114575355A (en) | Soil protection and descent construction method | |
JP6806465B2 (en) | Construction method of foundation structure | |
CN112983461A (en) | Construction method for bias tunnel portal in slope volume | |
CN104480945A (en) | Inversed construction method for foundation pit | |
CN104499489A (en) | Foundation pit construction method | |
KR200362565Y1 (en) | Earth Retaining Wall Structure Using Precast Concrete Pile and Construction Method Thereof | |
CN207828994U (en) | It is a kind of draining and recharge constructing structure | |
KR101267688B1 (en) | The shore protection construction method using a precast finish panel | |
KR100476839B1 (en) | Construction method for installing concrete underground structures | |
KR102021496B1 (en) | Retaining wall construction method and retaining wall structure by the method | |
KR101021913B1 (en) | A method for constructing cut-off temporary structure for sheathing work | |
CN110792440B (en) | Construction method of water-rich loess tunnel penetrating through loess towards valley |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20151211 Year of fee payment: 4 |
|
FPAY | Annual fee payment |
Payment date: 20161212 Year of fee payment: 5 |
|
FPAY | Annual fee payment |
Payment date: 20171219 Year of fee payment: 6 |
|
FPAY | Annual fee payment |
Payment date: 20181219 Year of fee payment: 7 |
|
FPAY | Annual fee payment |
Payment date: 20191219 Year of fee payment: 8 |