CN109518680A - A kind of construction of diaphragm wall structure and construction method - Google Patents

A kind of construction of diaphragm wall structure and construction method Download PDF

Info

Publication number
CN109518680A
CN109518680A CN201811200927.4A CN201811200927A CN109518680A CN 109518680 A CN109518680 A CN 109518680A CN 201811200927 A CN201811200927 A CN 201811200927A CN 109518680 A CN109518680 A CN 109518680A
Authority
CN
China
Prior art keywords
construction
wall
diaphragm
diaphragm wall
continuous
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811200927.4A
Other languages
Chinese (zh)
Inventor
何小送
刘继鹏
庞前凤
李朋辉
张明睿
徐小燕
邹思鹏
高延伟
牛永江
高绍鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 22nd Bureau Group Co Ltd
China Railway 22nd Bureau Group Urban Rail Engineering Co., Ltd.
Original Assignee
China Railway 22nd Bureau Group Co Ltd
China Railway 22nd Bureau Group Urban Rail Engineering Co., Ltd.
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 22nd Bureau Group Co Ltd, China Railway 22nd Bureau Group Urban Rail Engineering Co., Ltd. filed Critical China Railway 22nd Bureau Group Co Ltd
Priority to CN201811200927.4A priority Critical patent/CN109518680A/en
Publication of CN109518680A publication Critical patent/CN109518680A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • E02D5/187Bulkheads or similar walls made solely of concrete in situ the bulkheads or walls being made continuously, e.g. excavating and constructing bulkheads or walls in the same process, without joints

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The invention discloses a kind of construction of diaphragm wall structure and construction method, including foundation reinforcing structure, the foundation reinforcing structure is formed at construction of diaphragm wall;Wall is led, the template for leading wall uses gang form, and the bottom for leading wall and wing plates on two sides perform 5cm thickness C20 concrete bed course;Construction has diaphragm wall connection structure between adjacent continuous wall.Construction of diaphragm wall structure of the invention and construction method are that a large amount of construction experiences are combined on the basis of standard, can shorten construction period, save construction cost, and the construction requirement that entirely appropriate construction site environment is complicated or construction site environment is special.

Description

A kind of construction of diaphragm wall structure and construction method
Technical field
The present invention relates to technical field of building construction, and in particular to a kind of construction of diaphragm wall structure and construction method.
Background technique
In construction, the construction of diaphram wall, diaphram wall have in especially municipal matching operation project The feature that rigidity is big, globality is strong, impervious and good durability, acts not only as building enclosure, plays retaining soil and water Effect, is also used as load-carrying members;Suitable for Various Complex foundation condition, land occupation is few when practice of construction, and effect is high, the duration It is short, reliable in quality, high financial profit.The advantages of due to diaphram wall above series of, so that diaphram wall is further extensive Apply to water content abundant, underground exterior-protected structure of bad ground and require bearing capacity big foundation engineering in.
In the prior art, although diaphragm wall is widely applied in construction work, more and more units in charge of construction are only Be according to the construction of standard (national standard or professional standard) Lai Jinhang diaphragm wall, and it is complex for construction site environment, can not Fully according to the engineering that standard executes, it will increase the difficulty of construction of construction personnel, increase construction cost.
Summary of the invention
The object of the present invention is to provide a kind of saving construction period, ensure that the preferable diaphram wall of construction in later period quality is applied Work structure and construction method.
To achieve the goals above, the invention provides the following technical scheme:
A kind of construction of diaphragm wall structure of the invention, comprising:
Foundation reinforcing structure, the foundation reinforcing structure are formed at construction of diaphragm wall;
Wall is led, the template for leading wall uses gang form, and the bottom for leading wall and wing plates on two sides perform 5cm thickness C20 concrete bed course;
Construction has diaphragm wall connection structure between adjacent continuous wall.
Further, the foundation reinforcing structure includes the place stabilization zone formed by more cement mixing piles, described The surrounding construction of place stabilization zone has the diaphragm wall;
The two sides of the diaphragm wall are formed with cell wall ruggedized construction;
The cell wall ruggedized construction passes through more cement mixing pile compositions;
Diaphragm wall installation foundation pit is formed between the cell wall ruggedized construction, it is described after the cell wall ruggedized construction construction Diaphragm wall is placed in the diaphragm wall installation foundation pit.
Further, the stake of the cement mixing pile of the cement mixing pile and foundation reinforcing structure of the cell wall ruggedized construction is straight Diameter is 0.5m.
Further, the wall of leading uses " ┓ ┏ " type monolithic reinforced concrete structure to lead wall, leads wall vertical depth 1.7m, Thick 0.2m, the width for leading wall are 105cm.
Further, the diaphragm wall connection structure includes continuous wall connector structure and diaphragm wall seam construction;
The continuous wall connector structure uses I-shaped steel joint structure;
The diaphragm wall seam construction uses H profile steel seam construction.
Further, the continuous wall connector structure is welded using steel plate, and the weldering of the continuous wall connector structure Seam is fillet weld, fillet weld size 12mm.
A kind of continuous wall construction method disclosed by the invention, including following construction procedure:
1), preparation of construction;
2), place ruggedized construction and the construction of cell wall ruggedized construction;
3), construction of guide wall;
4), reinforcing bar binding and concreting;
5), continuous wall trench is constructed, step 3) and 4) in lead after wall reaches design strength, carry out continuous wall trench construction, The continuous wall trench construction is using hydraulic grab cell wall machine cooperation percussive drill using mud off using the side for first grabbing backlash Method is constructed;
6), clear slot changes slurry brush wall processing;
7), reinforcing bar cage hoisting;
8), concreting;
9), earth excavation carries out earth excavation after diaphragm wall intensity reaches design standard.
Further, before the cement-soil stirring pile construction in the step 2) in place ruggedized construction and cell wall ruggedized construction It answers first smooth location and carries out temporary drainage facility, sinking and promotion speed when control is stirred are promoted and subsidence velocity control In 0.8~1.2m/min and 1.0~1.5m/min.
Further, the Φ 48mm steel pipe of leading wall behind and can squeeze into the step 3) in construction of guide wall carries out mud jacking and adds Gu.
Further, in the step 5) continuous wall trench construction use two kinds of construction methods, respectively it is pure grab slot and Grab the combination constructing method thereof that slot, impact drill, plane set-hammer repair hole.
In the above-mentioned technical solutions, construction of diaphragm wall structure and construction method provided by the invention have with following Beneficial effect:
Construction of diaphragm wall structure of the invention and construction method are that a large amount of construction experiences, energy are combined on the basis of standard Enough shorten construction period, save construction cost, and entirely appropriate construction site environment is complicated or construction site environment is special Construction requirement.
Detailed description of the invention
In order to illustrate the technical solutions in the embodiments of the present application or in the prior art more clearly, below will be to institute in embodiment Attached drawing to be used is needed to be briefly described, it should be apparent that, the accompanying drawings in the following description is only one recorded in the present invention A little embodiments are also possible to obtain other drawings based on these drawings for those of ordinary skill in the art.
Fig. 1 is a kind of layout drawing of the foundation reinforcing structure of construction of diaphragm wall structure provided in an embodiment of the present invention;
Fig. 2 is a kind of constructing structure schematic diagram for leading wall of construction of diaphragm wall structure provided in an embodiment of the present invention;
Fig. 3 is a kind of connector and seam construction of the adjacent continuous wall of construction of diaphragm wall structure provided in an embodiment of the present invention Effect picture;
Fig. 4 is a kind of construction flow chart of continuous wall construction method provided in an embodiment of the present invention.
Description of symbols:
1, foundation reinforcing structure;2, cell wall ruggedized construction;3, diaphragm wall installs foundation pit;4, cement mixing pile;5, wall is led;6, First diaphragm wall;7, the second diaphragm wall.
Specific embodiment
In order to make those skilled in the art more fully understand technical solution of the present invention, below in conjunction with attached drawing to this hair It is bright to be further detailed.
Referring to shown in Fig. 1 to Fig. 3;
A kind of construction of diaphragm wall structure of the invention, comprising:
Foundation reinforcing structure 1, foundation reinforcing structure 1 are formed at construction of diaphragm wall;
Wall 5 is led, leads the template of wall 5 using gang form, and leads the bottom of wall 5 and wing plates on two sides performs 5cm thickness C20 concrete Bed course;
Construction has diaphragm wall connection structure between adjacent continuous wall.
Preferably, above-mentioned foundation reinforcing structure 1 includes the place stabilization zone formed by more cement mixing piles 4, field The surrounding construction of ground stabilization zone has diaphragm wall;
The two sides of diaphragm wall are formed with cell wall ruggedized construction 2;
Cell wall ruggedized construction 2 is made up of more cement mixing piles 4;
Diaphragm wall installation foundation pit 3, after the construction of cell wall ruggedized construction, the diaphragm wall are formed between cell wall ruggedized construction 2 It is placed in diaphragm wall installation foundation pit 3.
Preferably, the cement mixing pile 4 of the cement mixing pile 4 and foundation reinforcing structure 1 of above-mentioned cell wall ruggedized construction 2 Stake diameter is 0.5m.
Cement mixing pile 4 answers first smooth location and carries out temporary drainage facility before constructing;Under when strict control being answered to stir Heavy and promotion speed, lifting or sinking speed control is in 0.8~1.2m/min and 1.0~1.5m/min, to guarantee reinforcing scope Interior each depth is sufficiently stirred;Using the method repeatedly whitewashed on a small quantity in deep-layer stirring construction, at least guarantee to stir three times Whitewashing is mixed, while it is ensured that stirring number (no less than 2 times) again;Slurries, prepared slurry are prepared in strict accordance with the ratio of mud of design Liquid must be sieved;Should conscientiously be recorded in construction practical mixing pile hole location, hole depth and underground obstacle in drilling, cave, water burst, Not the case where leak and engineering geology report are not inconsistent, and take appropriate measures.
(1) cement uses 42.5 ordinary portland cement of P.O.
(2) in formation of pile, such as stop slurry for some reason and continue that pile extension must be overlapped when construction, pile extension length is no less than 0.5m;If It shuts down more than 3h, grout pipe line should be dismantled, cleaned up, the piling beside former stake position.
(3) the reinforced material discarded in construction should not be discharged arbitrarily;The slurries overflowed in slurry jet agitation stake test pile should be timely Recovery processing prevents pollution environment.
(4) cutting pile crown should not should influence pile integrity using the special equipments such as pile cutting machine, amputation pile crown.
(5) the match ratio mixing that slurries should be determining in strict accordance with component design and test, the slurries prepared should be uniform, no It should isolate.
(6) when mixing pile construction, stopping pulp noodle should be higher than that 30~50cm of designed elevation.
Preferably, wall is led in the present embodiment, wall is led using " ┓ ┏ " type monolithic reinforced concrete structure, lead wall vertical depth 1.7m, thick 0.2m, the width for leading wall is 105cm.
Leading wall 5 is the temporary structure before grooving, but is played an important role to grooving.It leads 5 pairs of wall and holds givey ground surface soil Play retaining wall, while as the benchmark of measurement, it is specified that the position of slot section, in the boundary for leading wall 5 and marking unit groove section Line, also as measurement grooving absolute altitude, the benchmark of verticality and precision.Wall 5 is led also as the bearing of weight, such as rushes stake machine, reinforcing bar The fulcrum that cage etc. is shelved, mud use can also be stored by leading wall 5, if geological conditions is bad, upper formation has thicker miscellaneous fill out Soil, cell wall does not collapse and collapses when to guarantee that the stability for leading wall 5 and slot section are excavated, and leads wall 5 behind and can squeeze into Φ 48mm steel pipe and is pressed Slurry is reinforced, and prevents slot section landslide spillage.Leading wall 5 is the key that guarantee that diaphram wall position is accurate and grooving quality, design are adopted Wall is led with " ┓ ┏ " type monolithic reinforced concrete structure, leads wall 5 vertical depth 1.7m, thick 0.2m, 5 spacing of wall is led and considers to expand Width is 105cm after 5cm.
It leads wall 5 to excavate using mini-excavator excavation, manual amendment cell wall, lead 5 bottom of wall and leads under 5 wing plates on two sides of wall Perform 5cm thickness C20 concrete bed course.Template uses gang form, pours commerical ready-mixed concrete, poker vibrator is made firm by ramming closely knit.Lead wall 5 After demoulding, top and the bottom add 80*80 flitch to support between two panels leads wall immediately, upper and lower twice support level spacing 2m, and it is mixed to lead wall 5 Heavy-duty machinery is forbidden nearby to walk during solidifying soil maintenance, parked or operation.Level of ground water 1.5m should be higher by by leading 5 top surface of wall, with Guarantee that mud face is higher by level of ground water >=1.0m in slot;Displacement and deformation must not be had by leading wall 5.
Select bentonite slurrying that can add CMC and soda ash etc. in right amount to improve the bonding capacity and specific gravity of mud.It is pure Alkali only adds in calcium, magnesia bentonite, is not spiked in sodium bentonite construction.It is as follows to bentonitic technical requirements: fineness 200 mesh sieve margins are not more than 5%;Colloid is not less than 5%;Expansion multiple is not less than 10 times;Adsorbance is not more than 10%.Mud is matched Than being determined finally by test.It is generally may be when just quasi-: bentonite, 8% or so of water weight;CMC, the 0.05% of water weight; Dispersing agent, 0.3% or so of water weight.Match ratio is selected to carry out laboratory test, the performance of each stage mud according to geological condition Mud property table should be met.
Mud production is stirred using slurry mixer, first dilutes CMC immersion in water, and stirring is being added by specified quantity It is stirred together with bentonite, soda ash in cylinder, new stock tank is stored in after being stirred.For the effect for giving full play to mud, after mud stirring Must be stored in 24 hours rears of new stock tank can be used.
The mud of trenching construction changes its technical indicator by soil pollution, should not be re-used for grooving shield Wall.Therefore, the mud extracted out out of slot is introduced into sedimentation basin, by being pumped into mud pit after precipitating, then send to recycling in slot. When the technical indicator of mud varies widely, such as specific gravity > 1.25, when viscosity > 50s, it is necessary to which discarded, discarded slurry uses Closing vehicle is transported to designated place discharge.
Fresh mud will be stored in new stock tank more than for 24 hours, will be constantly with pump stirring during storage.It is wanted in use Continuous measurement match ratio, it is ensured that the indices of mud are qualified.
For different stratum, mud is adjusted at any time, reaches the requirement of retaining wall, operation content is as follows:
(1) construction period, mud face necessarily is greater than 0.5~1m of level of ground water in slot section.
(2) under normal circumstances, guarantee that the performance indicator of mud is met the following requirements, specific gravity 1.04~1.25, viscosity 20~ 24S, pH value 8-9, no specific aim.
Preferably, diaphragm wall connection structure includes continuous wall connector structure and diaphragm wall seam construction in the present embodiment;
Continuous wall connector structure uses I-shaped steel joint structure;
Diaphragm wall seam construction uses H profile steel seam construction.
Specifically, above-mentioned continuous wall connector structure is welded using steel plate, and the weld seam of continuous wall connector structure is Fillet weld, fillet weld size 12mm.
(1) slot section setting-out: the measurement control stake point provided according to design drawing and owner accurately marks segmentation on leading wall Mark line.
(2) common soil layer slot section is excavated
Common soil layer slot section, which is excavated, grabs native grooving using hydraulic grab cell wall machine, and standard cell section is taken three sequence grooving, first dug Both sides, then dig centre.Verticality is surveyed in digging process, and is rectified a deviation in time.
1) after the positioning of hydraulic grab cell wall machine, grab bucket, which is parallel to, leads side within the walls, when grab bucket is transferred, voluntarily crashes into and leads wall It is interior, do not allow strength to be pushed into, to guarantee grooving precision.
2) should not completely bucket cut the earth when soil layer grooving, i.e., every bucket cannot be crowded with the earthwork because soil in mud after squeezing, It will affect quality of mud fluid, increase mud viscosity specific gravity.The grab bucket promotion of dress soil will slightly stop to when leading wall top face, wait upper mud of grabbing bucket It after slurry drip is net, then is promoted to dregs and has bad luck vehicle, to prevent mud contamination place.Fall and leading the soil on wall clearly to outside slot, forbids It shovels in slot.
3) during grab bucket is cut the earth, upper and lower lifting speed is slowly carried out, and grab bucket will also close bucket decentralization, and when excavation opens again It opens, in order to avoid vortex is caused to wash away cell wall, causes the hole that collapses.
4) when grab bucket decentralization is cut the earth, the alignment of grab bucket center is put in the hole location center mark object led on wall, and along leading outside wall Side wall decentralization guarantees that shoveling position is correct.
It is shown in Figure 4, a kind of continuous wall construction method disclosed by the invention, including following construction procedure:
1), preparation of construction;
2), place ruggedized construction 1 and cell wall ruggedized construction 2 are constructed;
3) construction of wall 5, is led;
4), reinforcing bar binding and concreting;
5), continuous wall trench is constructed, step 3) and 4) in lead after wall reaches design strength, carry out continuous wall trench construction, Continuous wall trench construction using hydraulic grab cell wall machine cooperation percussive drill using mud off using first grab the method for backlash into Row construction;
6), clear slot changes slurry brush wall processing;
7), reinforcing bar cage hoisting;
8), concreting;
9), earth excavation carries out earth excavation after diaphragm wall intensity reaches design standard.
Specifically, levelling of the land cell wall carries out leading the positioning of wall, excavation and reinforcing bar binding and concreting after reinforcing, to When leading wall and reaching design strength, continuous wall trench construction is adopted using hydraulic grab cell wall machine cooperation percussive drill using mud off It is constructed with the method for first grabbing backlash, i.e., first uses the grooving of cell wall machine, use percussive drill instead when if can not excavate to rock stratum grab bucket Punching grooving.High-quality bentonite mixing mud off is used when grooving, is stored 24 hours or more and can be used after mud mixing, ground Lower diaphragm wall is constructed using job-hopping method, and adjacent slot section concrete intensity, which reaches 70% or more design strength, to be excavated.At Clear slot is carried out after the completion of slot and changes slurry brush wall processing, is carried out reinforcing bar cage hoisting after qualification to be processed, is carried out concreting after lifting, Ground-connecting-wall carries out earth excavation after reaching design strength.
Preferably, before the cement-soil stirring pile construction in above-mentioned step 2) in place ruggedized construction and cell wall ruggedized construction It answers first smooth location and carries out temporary drainage facility, sinking and promotion speed when control is stirred are promoted and subsidence velocity control In 0.8~1.2m/min and 1.0~1.5m/min.
Preferably, the Φ 48mm steel pipe of leading wall 5 behind and can squeeze into led in above-mentioned step 3) in the construction of wall 5 carries out mud jacking It reinforces.
Preferably, in above-mentioned step 5) continuous wall trench construction use two kinds of construction methods, respectively it is pure grab slot and Grab the combination constructing method thereof that slot, impact drill, plane set-hammer repair hole.
It using the clear slot of the precipitation method, i.e., carries out after slot bottom sediment is directly excavated in grab bucket, fails further to remove grab bucket The tiny native slag excavated.Clear slot uses Dg100 air lift, is suspended in midair by crane into slot, air compressor conveying compression is empty Gas is absorbed with midge crossover-circulating type method and is deposited on the wide soil quarrel mud of slot bottom.
When clear slot starts, crane suspention air lift enters slot, and the suction pipe for hanging air lift cannot be put into quickly Slot bottom depth first carries out examination suction at from 1~2m of slot bottom, prevents the suction inlet of dredging tube to be trapped into native slag and block dredging tube.
When clear bottom, dredging tube from the superficial to the deep will make the horn mouth of air lift in slot section length range from slot bottom Left and right moves up and down at 0.5m, absorbs trench bottom soil slag mud.
The continuity that slurry is the clear slot operation of the precipitation method is changed, native slag is no longer sucked out when air lift is moved back and forth in trench bottom, When surveying the heavy quarrel thickness of slot bottom and being less than 10cm, mobile air lift can be stopped, starting to replace trench bottom and do not meet quality and want The mud asked.After descending reinforcing cage, the clear slot of displacement method is used if slot bottom mud is unqualified.
Whether clear slot changes slurry qualified, is subject to sampling test, when being often incremented by each sample point at 5m depth and slot bottom in slot After mud sampling test data all meets set quota, clear bottom changes slurry and just calculates qualification.It additionally should ensure that slurry is changed 1 hour in clear bottom Afterwards, mud balance is not more than 1.2 in slot bottom 200mm height.
It is changed in slurry overall process in clear slot, controls midge amount and mend the balance of slurry amount, mud cannot be allowed to overflow outside slot or allow Pulp noodle, which are fallen on, leads wall top face or less 30cm.
Connector connection construction quality is directly related to ground-connecting-wall waterproof effect, after construction when row width, to closure width section and Connection width section should carry out connector processing, carry out brush wall with brush wall device, and brush wall reciprocal time should be no less than 30 times, guarantee connector matter Amount, and carry out especially construction original record.Brush wall is first slightly brushed with steel plate surface, then is carefully brushed with steel wire face, and brush wall is reciprocal Number is no less than 30 times, is not easy to brush the clean brush wall number of increase according to the actual situation individually, until brush wall brush to no mud Until skin.
Mud, silt clay and the ballast just dug out allows quick lime to inhale using mixing with a certain number of quick limes After receiving a large amount of moisture, vehicle flowrate hour is made full use of, with common dump truck spoir to specified spoil ground.It is taken for waste pulp Mud-water separation is unearthed in the form of dregs.
In the above-mentioned technical solutions, construction of diaphragm wall structure and construction method provided by the invention have with following Beneficial effect:
Construction of diaphragm wall structure of the invention and construction method are that a large amount of construction experiences, energy are combined on the basis of standard Enough shorten construction period, save construction cost, and entirely appropriate construction site environment is complicated or construction site environment is special Construction requirement.
It is above that certain exemplary embodiments of the invention are only described by way of explanation, undoubtedly, for ability The those of ordinary skill in domain without departing from the spirit and scope of the present invention can be with a variety of different modes to institute The embodiment of description is modified.Therefore, above-mentioned attached drawing and description are regarded as illustrative in nature, and should not be construed as to the present invention The limitation of claims.

Claims (10)

1. a kind of construction of diaphragm wall structure characterized by comprising
Foundation reinforcing structure (1), the foundation reinforcing structure (1) are formed at construction of diaphragm wall;
It leads wall (5), the template for leading wall (5) uses gang form, and the bottom for leading wall (5) and wing plates on two sides perform 5cm thickness C20 concrete bed course;
Construction has diaphragm wall connection structure between adjacent continuous wall.
2. a kind of construction of diaphragm wall structure according to claim 1, which is characterized in that foundation reinforcing structure (1) packet The place stabilization zone formed by more cement mixing piles (4) is included, the surrounding construction of the place stabilization zone has the diaphragm wall;
The two sides of the diaphragm wall are formed with cell wall ruggedized construction (2);
The cell wall ruggedized construction (2) passes through more cement mixing pile (4) compositions;
Diaphragm wall installation foundation pit (3) is formed between the cell wall ruggedized construction (2), after cell wall ruggedized construction (2) construction, The diaphragm wall is placed in diaphragm wall installation foundation pit (3).
3. a kind of construction of diaphragm wall structure according to claim 2, which is characterized in that the cell wall ruggedized construction (2) The stake diameter of the cement mixing pile (4) of cement mixing pile (4) and foundation reinforcing structure (1) is 0.5m.
4. a kind of construction of diaphragm wall structure according to claim 1, which is characterized in that described to lead wall (5) useType monolithic reinforced concrete structure leads wall, leads wall (5) vertical depth 1.7m, thick 0.2m, the width for leading wall (5) For 105cm.
5. a kind of construction of diaphragm wall structure according to claim 1, which is characterized in that the diaphragm wall connection structure includes Continuous wall connector structure and diaphragm wall seam construction;
The continuous wall connector structure uses I-shaped steel joint structure;
The diaphragm wall seam construction uses H profile steel seam construction.
6. a kind of construction of diaphragm wall structure according to claim 5, which is characterized in that the continuous wall connector structure uses Steel plate is welded, and the weld seam of the continuous wall connector structure is fillet weld, fillet weld size 12mm.
7. a kind of continuous wall construction method, which is characterized in that including following construction procedure:
1), preparation of construction;
2), place ruggedized construction (1) and cell wall ruggedized construction (2) construction;
3) wall (5) construction, is led;
4), reinforcing bar binding and concreting;
5), continuous wall trench is constructed, step 3) and 4) in lead after wall (5) reaches design strength, carry out continuous wall trench construction, institute It states continuous wall trench construction and the method for first grabbing backlash is used using mud off using hydraulic grab cell wall machine cooperation percussive drill It constructs;
6), clear slot changes slurry brush wall processing;
7), reinforcing bar cage hoisting;
8), concreting;
9), earth excavation carries out earth excavation after diaphragm wall intensity reaches design standard.
8. a kind of continuous wall construction method according to claim 7, which is characterized in that place reinforces knot in the step 2) First smooth location is answered before cement-soil stirring pile construction in structure (1) and cell wall ruggedized construction (2) and carries out temporary drainage facility, is controlled Sinking and promotion speed when system stirring, are promoted and subsidence velocity control is in 0.8~1.2m/min and 1.0~1.5m/min.
9. a kind of continuous wall construction method according to claim 7, which is characterized in that lead wall (5) in the step 3) and apply Φ 48mm steel pipe of leading wall (5) behind and can squeeze into work carries out grouting reinforcement.
10. a kind of continuous wall construction method according to claim 7, which is characterized in that in the step 5) diaphragm wall at Slot construction uses two kinds of construction methods, respectively pure to grab slot and grab the combination constructing method thereof that slot, impact drill, plane set-hammer repair hole.
CN201811200927.4A 2018-10-16 2018-10-16 A kind of construction of diaphragm wall structure and construction method Pending CN109518680A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811200927.4A CN109518680A (en) 2018-10-16 2018-10-16 A kind of construction of diaphragm wall structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811200927.4A CN109518680A (en) 2018-10-16 2018-10-16 A kind of construction of diaphragm wall structure and construction method

Publications (1)

Publication Number Publication Date
CN109518680A true CN109518680A (en) 2019-03-26

Family

ID=65772239

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811200927.4A Pending CN109518680A (en) 2018-10-16 2018-10-16 A kind of construction of diaphragm wall structure and construction method

Country Status (1)

Country Link
CN (1) CN109518680A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102312445A (en) * 2010-06-29 2012-01-11 中交第三航务工程勘察设计院有限公司 Diaphragm wall and construction method thereof
KR20120046966A (en) * 2010-11-03 2012-05-11 주식회사 동아지질 Diaphragm wall and this construction technique
CN105735236A (en) * 2016-03-17 2016-07-06 中铁十六局集团北京轨道交通工程建设有限公司 Soil mass pre-reinforcement method for trench construction of underground diaphragm wall in thick mud layer
CN105735245A (en) * 2016-03-17 2016-07-06 上海交通大学 Soil body reinforcement method for trenching construction in stratum of seaside hydraulic fill mud layer
CN209293012U (en) * 2018-10-16 2019-08-23 中铁二十二局集团轨道工程有限公司 A kind of construction of diaphragm wall structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102312445A (en) * 2010-06-29 2012-01-11 中交第三航务工程勘察设计院有限公司 Diaphragm wall and construction method thereof
KR20120046966A (en) * 2010-11-03 2012-05-11 주식회사 동아지질 Diaphragm wall and this construction technique
CN105735236A (en) * 2016-03-17 2016-07-06 中铁十六局集团北京轨道交通工程建设有限公司 Soil mass pre-reinforcement method for trench construction of underground diaphragm wall in thick mud layer
CN105735245A (en) * 2016-03-17 2016-07-06 上海交通大学 Soil body reinforcement method for trenching construction in stratum of seaside hydraulic fill mud layer
CN209293012U (en) * 2018-10-16 2019-08-23 中铁二十二局集团轨道工程有限公司 A kind of construction of diaphragm wall structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王如路等: "《普通高等教育"十三五"规划教材 地下工程施工》", vol. 2, 黄河水利出版社, pages: 219 - 220 *

Similar Documents

Publication Publication Date Title
CN107524138B (en) Construction method of ultra-deep foundation pit underground diaphragm wall
CN109680677A (en) A kind of construction of diaphragm wall technique
WO2022096024A1 (en) Construction method for super-long small-diameter hole bored pile
CN107938676A (en) A kind of pile base construction method for passing through full packing type solution cavity
CN109680676A (en) A kind of ventilating shaft building enclosure and its construction method
CN203846485U (en) Long pile percussion drill hole forming construction device
CN110080237A (en) It cheats the shallow earthing subway tunnel pit earthwork in bottom and excavates anti-floating construction method and structure
CN105951711A (en) Enclosing construction method of underground continuous wall of seashore power station
CN108797598A (en) The construction technology of pre-loaded support struts in a kind of deep basal pit
AU2021106928A4 (en) Construction method for excavation of deep pit with triaxial mixing pile waterstop curtains and rotary bored cast-in-place pile supports
CN106759297A (en) A kind of construction method of support pile and three pipe high-pressure rotary jet grouting pile deep basal pits
CN109098175A (en) A kind of tri-axes deep mixing pile construction method
CN110984221A (en) Construction method for reinforcing end socket at initial end of air shaft and guide wall structure
CN109537574A (en) The construction technology of diaphram wall in a kind of extremely hard rock
CN104153371A (en) Grouting-to-stop-water construction method of underwater rubble bed
CN110144887A (en) Vast sky stake bored pile construction method
CN111560958A (en) Construction method of water-rich deep foundation pit in silty clay stratum
CN114108649A (en) Foundation pit reinforcing construction method for mucky soil layer
CN108571000A (en) The construction method of underground water cutting when wearing existing railway under a kind of road of location along the river
CN104695458A (en) Construction method of deep stirring and jet grouting compound pile waterproof curtain
CN209293012U (en) A kind of construction of diaphragm wall structure
CN211898541U (en) Guide wall structure for reinforced structure of air shaft initial end head
CN111455977A (en) Underground continuous wall construction method
CN112695763A (en) Deep sludge stratum foundation pit excavation method
CN103866787B (en) A kind of spacious reverse masonry method concrete cut that digs builds construction technology

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination