CN104499489A - Foundation pit construction method - Google Patents

Foundation pit construction method Download PDF

Info

Publication number
CN104499489A
CN104499489A CN201410753775.6A CN201410753775A CN104499489A CN 104499489 A CN104499489 A CN 104499489A CN 201410753775 A CN201410753775 A CN 201410753775A CN 104499489 A CN104499489 A CN 104499489A
Authority
CN
China
Prior art keywords
diaphragm wall
floor
construction
basement
locking notch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410753775.6A
Other languages
Chinese (zh)
Other versions
CN104499489B (en
Inventor
孔志坚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing No6 Construction Engineering Quality Test Department Co Ltd
Beijing Building Research Institute Corp Ltd of CSCEC
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201410753775.6A priority Critical patent/CN104499489B/en
Priority claimed from CN201310261074.6A external-priority patent/CN103321246B/en
Publication of CN104499489A publication Critical patent/CN104499489A/en
Application granted granted Critical
Publication of CN104499489B publication Critical patent/CN104499489B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2220/00Temporary installations or constructions

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention discloses a foundation pit construction method adopting an underground continuous wall. The foundation pit construction method is characterized in that a basement structure part is constructed from top to bottom while a main body structure part is constructed from bottom to top; the underground continuous wall construction adopts a hydraulic type crab bucket grooving process, and carries out unit slot segment excavating and concrete pouring through a hole jumping method. The foundation pit construction method is characterized in that a specially-made joint box and a fore shaft pipe are adopted and filled in a joint part between adjacent slot widths; the joint box is hung on a slot bottom; the entering ground depth of the bottom end is not less than 50cm; after the fore shaft pipe is in position, in order to prevent concrete from flowing around from the joint box and the fore shaft pipe, soil is utilized to fill and compact the back part of the fore shaft pipe; each layer is subjected to construction based on the area divided along the underground continuous wall. The underground continuous wall, a basement foundation slab and a floor slab are connected in a rigid connection way.

Description

A kind of foundation ditch construction method
Technical field
The present invention relates to a kind of foundation ditch, particularly a kind of foundation ditch construction method.
Background technology
Along with urban underground space continually develop utilization, bracing of foundation pit design and construction technique have also been obtained continuous development, the shallow design of foundation pit of cutting depth 5 ~ 6m and construction are all comparatively ripe, this type of foundation ditch is according to the different characteristics of surrounding enviroment, and conventional bracing of foundation pit scheme puts slope excavation, (compound) soil nail wall, cement mixing method dam body, bored pile in conjunction with the form such as anchor pole or inner support.Vibrate little during construction of diaphragm wall, noise is low, less on surrounding enviroment impact.Diaphragm wall body of wall rigidity is large, during for excavation of foundation pit, can bear very large soil pressure, become Deep Foundation Pit Supporting Project soil-baffling structure of good performance.Diaphragm wall overlapping part often becomes the weak link of load, and the easy seepage in this position, must take measures to strengthen.
Summary of the invention
The technical problem that the present invention solves is to provide a kind of foundation ditch construction method, solves existing technical deficiency.
The present invention is from ± 0.00, and from top to bottom, body structure portion carries out construction from bottom to top to basement structure part simultaneously.Basement first carries out the horizontal structure such as beam, the plate construction of each layer, the more interspersed vertical structure such as post, the shear wall construction carrying out each layer.Before vertical load-carrying members all do not complete and reach design strength, above completed permanent load and working load carry by the interim steel-support post arranged and pass to engineering pile.Every root steel-support post all inserts engineering pile 2.5m, and when drill-pouring Construction of Engineering Pile, after the welding of post reinforcing cage, entirety hangs in hole.For ensureing the standard that steel-support post is installed perpendicularity deviation and is less than its length 1/500, steel-support post on-station position arranges fixing steel plate, ensures the horizontal level of steel-support post, with the Plane Angle of axis, capital absolute altitude and verticality.Behind every root steel-support post lifting location, forbid that heavy mechanical equipment is near stake holes and fixing steel plate, must not remove fixing steel plate in the 48h after pile concrete has watered.Diaphragm wall is that bracing of foundation pit wall is held concurrently as outer wall of basement.
Construction of diaphragm wall adopts fluid pressure type grab chute forming technique, carries out excavation and the concreting of unit groove section with " jumping hole method ".Grooving vertical precision is not more than 1/300.The bad settling amount that can increase diaphragm wall of diaphragm wall sediment process, construction method not only adopt reverse circular technique carry out scarfing cinder, after also adopting into wall, high-pressure injected water method for slurry is reinforced, in every width diaphragm wall reinforcing cage, all pre-buried 2 compaction grouting pipes, carry out grouting and reinforcing to 2m depth bounds at the bottom of diaphragm wall.In addition, spray the little stabilizing solution of proportion by powerful jet pump to bottom land, the sediment at the bottom of hole from a side blow to opposite side, open another suction pump simultaneously, by suction pipe sediment larger for proportion from opposite side sucking-off, thus sediment at the bottom of hole is effectively controlled.
Prevent from concrete from streaming being the difficult point in construction of diaphragm wall process.The present invention adopts special joint case and locking notch pipe, is filled in and adjacent slot width joint.Joint case hangs bottom land, and bottom embedded depth is not less than 50cm.After locking notch pipe is in place, fits well from joint case and locking notch pipe for preventing concrete and stream, closely knit in the earthen backfill of locking notch pipe behind, efficiently avoid because cell wall landslide, concrete stream the dyskinetic construction accident caused to adjacent slot width.Time that pulls of joint case and locking notch pipe considers according to the resistance of concrete strength grade, initial setting time, final setting time, temperature and diaphragm wall, joint case and locking notch pipe is loosened among a small circle after concrete casting 2h, after this loosen once every 15min, to final set, slowly pull up joint case and locking notch pipe.
The speed of pit earthwork excavation progress is the key of restriction basement and whole engineering construction progress.In order to solve the lateral deformation of speed and the reduction diaphragm wall accelerating to cut the earth and ensure the contradiction of workmanship and construction safety, after taking first open cut, tunneling and machinery are cut the earth, concrete steps are as follows: outside the first floor earthwork is wide along diaphragm wall 10m, adopt benzvalene form open cut, dig and cause below underground 1 floor layer; After ± 0.00 floor and underground 1 floor layer have been constructed, then carry out the tunneling of 2, the 3 layers of earthwork in underground; Tunneling soil adopts excavator, utilizes miniature diesel tipping lorry to complete earthwork horizontal transport in foundation ditch, is grabbed bucket and assist small-sized claw bucket sling to be unearthed from floor reserved opening, complete a cubic metre of earth vertical transport by machinery.
Traditional handicraft adopts fetal membrane of laying bricks, concreting bed course makes basement floor, speed of application is slow, concrete surface planeness and presentation quality are also poor, the present invention is by 0.7m below excavation of earthwork to floor soffit, set up framed bent and install template, to accelerate basement construction progress, ensure that the quality of concrete surface.
Excessive in order to prevent diaphragm wall lateral displacement to be out of shape, produce seepage even structural deterioration, every layer is carried out blockette construction along diaphragm wall, the length of every block block is 15 ~ 20m, width is 10 ~ 14m, and accelerate the excavation of each block earthwork and the construction of floor as far as possible, to shorten the Deformation of Diaphragm Wall time, reduce shift value.
The present invention is the construction first carrying out the horizontal structures such as basement floor base plate, more successively the interspersed vertical structure such as post, shear wall that carries out is constructed.Therefore concrete column joint seam is more, and muscle quality of connection as main in post is unreliable, and casting and compacting of concrete leakiness will directly affect the safety of structure.The main muscle of post connect specific practice adopt as follows: first by be connected end reinforced cut flat, the method of cutting is adopted to peel a part off in end reinforced vertical rib to be connected and cross rib screw-rolling machine, then directly rolling goes out silking, couples together with special silking connector, forms the connection of reinforcing bar.Traditional concrete column muscle connects for overlap joint electric welding, and compared with conventional art, its advantage has: 1. strength of joint is high, and energy 100% plays reinforced steel bar strength; 2. silking connector is short, and silking button number is few, does not need torque spanner, easy to operate, and connection speed is fast; 3. material-saving, energy-conservation, economic, saves steel more than 35% than other mechanical connection manner.
If post concrete joint position adopts grouting material mode to connect, complex operation is time-consuming, directly affects the construction speed of superstructure.The present invention takes to connect special bell mouth on column template top, and concrete is once poured onto top, and post four sides arranges punching block extension vibration board and vibrates, and ensure that concrete compactness.
Joint between diaphragm wall two width should reach and bear bending resistance, shearing resistance requirement, should not make it the weak link becoming strength and stiffness; In addition often produce percolating water, therefore traditional underground continuous wall connector is improved.
Diaphragm wall overlapping part water proof structure of the present invention comprises diaphragm wall, anchor rib, steel seal ring, steel plate, expansive concrete, high-strength epoxy resin, anchor rib buried underground by diaphragm wall, anchor rib is 7 fonts, to strengthen anchorage length, anchor rib diameter is 22 ~ 25mm, anchor rib weldable steel seal ring, steel seal ring thickness is 3 ~ 4mm, the width of steel seal ring is 35 ~ 45mm, and steel seal ring has blocked the infiltration path of anchor rib, avoids anchor rib to there is infiltration hidden danger.Outside diaphragm wall, steel plate is set, steel plate thickness is 10 ~ 12mm, steel plate arranges preformed hole, preformed hole diameter is 25 ~ 28mm, and anchor rib is through steel plate preformed hole, and the space filling high-strength epoxy resin between anchor rib and preformed hole is closed, between the steel plate of adjacent diaphragm wall, space is 15 ~ 20mm, build expansive concrete in space, expansive concrete intensity be C35 or more than, expansive concrete effectively can prevent building rear concrete and occur shrinkage crack.
The smooth main path in underground continuous wall face is kept to be control to reduce cell wall landslide in work progress by mud, therefore, before grooving by the sewage in guide groove and dirt removal clean, different soil layers is taked to the proportioning of different slurry coat methods, specific as follows: for clay, the weight proportion of slurry coat method is: water is 100%, and swell soil is 8%, and soda ash is 0.12% ~ 0.15%, sodium carboxymethylcellulose is 0.06% ~ 0.08%; For silty clay, the proportioning of slurry coat method is: water is 100%, and swell soil is 9%, and soda ash is 0.16% ~ 0.19%, sodium carboxymethylcellulose is 0.09% ~ 0.11%; For silt, the proportioning of slurry coat method is: water is 100%, and swell soil is 10%, and soda ash is 0.20% ~ 0.23%, sodium carboxymethylcellulose is 0.12% ~ 0.14%; For sand, the proportioning of slurry coat method is: water is 100%, and swell soil is 8% ~ 12%, and soda ash is 0.24% ~ 0.27%, sodium carboxymethylcellulose is 0.15% ~ 0.17%.
Diaphragm wall of the present invention is bracing of foundation pit wall, and be again outer wall of basement, damp proof insulation barrier performance is poor, needs to arrange bricking wall apart from basement inwall 30cm position inside diaphragm wall.Between in making to be formed between diaphragm wall inwall and brick clamp wall, play water conservancy diversion and moistureproof effect.
The conventional method that diaphragm wall is connected with basement bottom board, floor flexibly connects method, namely at basement floor absolute altitude place, cut by diaphragm wall reinforcement cover; expose main muscle; build together with basement floor again, only transmit horizontal force between the two, do not transmit vertical force and moment of flexure.The present invention adopts rigid connecting connection, namely on the arrangement of reinforcement absolute altitude of basement bottom board and floor, reinforcing bar connector is buried underground at the interior wall of diaphragm wall in advance, after basement excavation when construction base plate and floor, its base plate and floor bar by reinforcing bar connector directly and diaphragm wall be linked to be entirety, become rigid joint, through the underground structure of rigid joint process, the performance in anti-settling, resist displacement etc. all can be improved.Compared with traditional method, the present invention obviously has greatly improved in mechanical property.
For conscientiously improving the effect of temporary support, all temporary support all need when constructing prestressing force of constructing.1. in the installation process such as column braces, horizontal support, increase by 2 steel plates at steel tube end part and strengthen bearing, after steel pipe is in place, adopt hydraulic jack to exert pressure, to steel pipe construction Prestressing; 2. concrete temporary support all mixes TEA micro-expanding agent, to reduce or to avoid shrinking.
Work efficiency of the present invention is high, the duration is short, reliable in quality, high financial profit, has following characteristics:
(1) place of engineering geology and hydrogeology complexity is applicable to.
(2) place that construction plant is narrow and small is applicable to.The construction plant of some engineerings is very narrow, and according to traditional space enclosing structure, piles in row adds cement mixing pile sealing, and considers the scope of operation between enclosure wall and outer wall of basement, then will greatly reduce building usable floor area.And present invention employs the technical scheme of enclosure wall and outer wall of basement unification, then greatly can improve the land utilization ratio in red line.
(3) be applicable to surrounding environment complexity and high area is required to security reliability.Under house owed by a citizen around some engineerings and road, pipe network facilities is intensive, is embedded with responsive gas flue under road, requires very high to the security reliability of bracing of foundation pit.In the present invention, diaphragm wall adds inner support, forms effective retaining design, and rigidity is large, and displacement is little with distortion.
(4) engineering of construction period anxiety is applicable to.The construction period of diaphragm wall adds cement mixing pile than conventional bored pile or rotary churning pile wants much shorter, can shortening for 1/3 ~ 1/2 duration, creating condition for effectively controlling total lever factor.
(5) engineering that the excavation of foundation pit degree of depth is large is applicable to.The excavation of foundation pit degree of depth is larger, and the water and soil lateral pressure suffered by enclosure wall is also larger, more easily produces Seepage, and requires higher to the strength and stiffness of going along with sb. to guard him piling wall adopted, also stricter to the stability requirement of retaining design.And diaphragm wall, in conjunction with inner support, has exactly possessed the advantage of these several respects in the present invention, namely in, stability large at anti-leakage, intensity and toughness and globality, there is unrivaled superiority.
(6) analyze from bracing engineering cost, the technical program adopts enclosure wall and outer wall of basement unification, more cost-saving than conventional method.
Accompanying drawing explanation
Fig. 1 diaphragm wall overlapping part water proof structure schematic diagram.
Accompanying drawing mark: 1, diaphragm wall, 2, anchor rib, 3, steel seal ring, 4, steel plate, 5, expansive concrete, 6, high-strength epoxy resin.
Detailed description of the invention
Describe the present invention below in conjunction with accompanying drawing.
The present embodiment is from ± 0.00, and from top to bottom, body structure portion carries out construction from bottom to top to basement structure part simultaneously.Basement first carries out the horizontal structure such as beam, the plate construction of each layer, the more interspersed vertical structure such as post, the shear wall construction carrying out each layer.Before vertical load-carrying members all do not complete and reach design strength, above completed permanent load and working load carry by the interim steel-support post arranged and pass to engineering pile.Every root steel-support post all inserts engineering pile 2.5m, and when drill-pouring Construction of Engineering Pile, after the welding of post reinforcing cage, entirety hangs in hole.For ensureing the standard that steel-support post is installed perpendicularity deviation and is less than its length 1/500, steel-support post on-station position arranges fixing steel plate, ensures the horizontal level of steel-support post, with the Plane Angle of axis, capital absolute altitude and verticality.Behind every root steel-support post lifting location, forbid that heavy mechanical equipment is near stake holes and fixing steel plate, must not remove fixing steel plate in the 48h after pile concrete has watered.Diaphragm wall 1 is that bracing of foundation pit wall is held concurrently as outer wall of basement.
Diaphragm wall 1 is constructed and is adopted fluid pressure type grab chute forming technique, carries out excavation and the concreting of unit groove section with " jumping hole method ".Grooving vertical precision is not more than 1/300.Construction method not only adopt reverse circular technique carry out scarfing cinder, after also adopting into wall, high-pressure injected water method for slurry is reinforced, in every width diaphragm wall 1 reinforcing cage, all pre-buried 2 compaction grouting pipes, carry out grouting and reinforcing to diaphragm wall 1 end 2m depth bounds.In addition, spray the little stabilizing solution of proportion by powerful jet pump to bottom land, the sediment at the bottom of hole from a side blow to opposite side, open another suction pump simultaneously, by suction pipe sediment larger for proportion from opposite side sucking-off, thus sediment at the bottom of hole is effectively controlled.
The present embodiment adopts special joint case and locking notch pipe, is filled in adjacent slot width joint.Joint case hangs bottom land, and bottom embedded depth is not less than 50cm.After locking notch pipe is in place, fits well from joint case and locking notch pipe for preventing concrete and stream, closely knit in the earthen backfill of locking notch pipe behind.Time that pulls of joint case and locking notch pipe considers according to the resistance of concrete strength grade, initial setting time, final setting time, temperature and diaphragm wall 1, joint case and locking notch pipe is loosened among a small circle after concrete casting 2h, after this loosen once every 15min, to final set, slowly pull up joint case and locking notch pipe.
After pit earthwork excavation takes first open cut, tunneling and machinery are cut the earth, and concrete steps are as follows: outside the first floor earthwork is wide along diaphragm wall 10m, adopt benzvalene form open cut, dig and cause below underground 1 floor layer; After ± 0.00 floor and underground 1 floor layer have been constructed, then carry out the tunneling of 2, the 3 layers of earthwork in underground; Tunneling soil adopts excavator, utilizes miniature diesel tipping lorry to complete earthwork horizontal transport in foundation ditch, is grabbed bucket and assist small-sized claw bucket sling to be unearthed from floor reserved opening, complete a cubic metre of earth vertical transport by machinery.
The present embodiment, by 0.7m below excavation of earthwork to floor soffit, is set up framed bent and is installed template, to accelerate basement construction progress, ensure that the quality of concrete surface.
Excessive in order to prevent diaphragm wall 1 lateral displacement to be out of shape, produce seepage even structural deterioration, every layer is carried out blockette construction along diaphragm wall 1, the length of every block block is 15 ~ 20m, width is 10 ~ 14m, and accelerate the excavation of each block earthwork and the construction of floor as far as possible, to shorten diaphragm wall 1 deformation time, reduce shift value.
The main muscle of post connect specific practice adopt as follows: first by be connected end reinforced cut flat, the method of cutting is adopted to peel a part off in end reinforced vertical rib to be connected and cross rib screw-rolling machine, then directly rolling goes out silking, couples together with special silking connector, forms the connection of reinforcing bar.
If post concrete joint position adopts grouting material mode to connect, complex operation is time-consuming, directly affects the construction speed of superstructure.The present embodiment is taked to connect special bell mouth on column template top, and concrete is once poured onto top, and post four sides arranges punching block extension vibration board and vibrates, and ensure that concrete compactness.
Fig. 1 is diaphragm wall overlapping part water proof structure schematic diagram.The present embodiment diaphragm wall overlapping part water proof structure comprises diaphragm wall 1, anchor rib 2, steel seal ring 3, steel plate 4, expansive concrete 5, high-strength epoxy resin 6, anchor rib 2 buried underground by diaphragm wall 1, anchor rib 2 is 7 fonts, anchor rib 2 diameter is 22mm, anchor rib 2 weldable steel seal ring 3, steel seal ring 3 thickness is 3mm, the width of steel seal ring 3 is 35 ~ 45mm, steel plate 4 is set outside diaphragm wall 1, steel plate 4 thickness is 10mm, steel plate 4 arranges preformed hole, preformed hole diameter is 25mm, anchor rib 2 is through steel plate 4 preformed hole, space filling high-strength epoxy resin 6 between anchor rib 2 and preformed hole is closed, between the steel plate of adjacent diaphragm wall, space is 15 ~ 20mm, expansive concrete is built in space, expansive concrete intensity be C35 or more than, expansive concrete effectively can prevent building rear concrete and occur shrinkage crack.
When diaphragm wall 1 is constructed, different soil layers is taked to the proportioning of different slurry coat methods, specific as follows: for clay, the weight proportion of slurry coat method is: water is 100%, and swell soil is 8%, and soda ash is 0.12% ~ 0.15%, sodium carboxymethylcellulose is 0.06% ~ 0.08%; For silty clay, the proportioning of slurry coat method is: water is 100%, and swell soil is 9%, and soda ash is 0.16% ~ 0.19%, sodium carboxymethylcellulose is 0.09% ~ 0.11%; For silt, the proportioning of slurry coat method is: water is 100%, and swell soil is 10%, and soda ash is 0.20% ~ 0.23%, sodium carboxymethylcellulose is 0.12% ~ 0.14%; For sand, the proportioning of slurry coat method is: water is 100%, and swell soil is 8% ~ 12%, and soda ash is 0.24% ~ 0.27%, sodium carboxymethylcellulose is 0.15% ~ 0.17%.
The present embodiment diaphragm wall 1 is bracing of foundation pit wall, and be again outer wall of basement, damp proof insulation barrier performance is poor, needs to arrange bricking wall apart from basement inwall 30cm position inside diaphragm wall 1.
Diaphragm wall 1 is connected with basement bottom board, floor and adopts rigid connecting connection, namely on the arrangement of reinforcement absolute altitude of basement bottom board and floor, reinforcing bar connector is buried underground at the interior wall of diaphragm wall 1 in advance, after basement excavation when construction base plate and floor, its base plate and floor bar by reinforcing bar connector directly and diaphragm wall 1 be linked to be entirety and become rigid joint.
All temporary support all need when constructing prestressing force of constructing.1. in the installation process such as column braces, horizontal support, increase by 2 steel plates at steel tube end part and strengthen bearing, after steel pipe is in place, adopt hydraulic jack to exert pressure, to steel pipe construction Prestressing; 2. concrete temporary support all mixes TEA micro-expanding agent, to reduce or to avoid shrinking.

Claims (10)

1. adopt a foundation ditch construction method, it is characterized in that from ± 0.00, from top to bottom, body structure portion carries out construction from bottom to top to basement structure part simultaneously; Basement first carries out the horizontal structure such as beam, the plate construction of each layer, the more interspersed vertical structure such as post, the shear wall construction carrying out each layer; Before vertical load-carrying members all do not complete and reach design strength, above completed permanent load and working load carry by the interim steel-support post arranged and pass to engineering pile; Every root steel-support post all inserts engineering pile 2.5m, and when drill-pouring Construction of Engineering Pile, after the welding of post reinforcing cage, entirety hangs in hole; For ensureing the standard that steel-support post is installed perpendicularity deviation and is less than its length 1/500, steel-support post on-station position arranges fixing steel plate, ensures the horizontal level of steel-support post, with the Plane Angle of axis, capital absolute altitude and verticality; Behind every root steel-support post lifting location, forbid that heavy mechanical equipment is near stake holes and fixing steel plate, must not remove fixing steel plate in the 48h after pile concrete has watered.
2., according to the employing foundation ditch construction method shown in claim 1, it is characterized in that construction of diaphragm wall adopts fluid pressure type grab chute forming technique, carry out excavation and the concreting of unit groove section with " jumping hole method "; Grooving vertical precision is not more than 1/300; Construction method not only adopts reverse circular technique carry out scarfing cinder, also adopt into high-pressure injected water method for slurry after wall and reinforce, in every width diaphragm wall reinforcing cage, all pre-buried 2 compaction grouting pipes, carry out grouting and reinforcing to 2m depth bounds at the bottom of diaphragm wall; In addition, spray the little stabilizing solution of proportion by powerful jet pump to bottom land, the sediment at the bottom of hole from a side blow to opposite side, open another suction pump simultaneously, by suction pipe sediment larger for proportion from opposite side sucking-off, thus sediment at the bottom of hole is effectively controlled.
3., according to the employing foundation ditch construction method shown in claim 1, it is characterized in that adopting special joint case and locking notch pipe, be filled in and adjacent slot width joint; Joint case hangs bottom land, and bottom embedded depth is not less than 50cm; After locking notch pipe is in place, fits well from joint case and locking notch pipe for preventing concrete and stream, closely knit in the earthen backfill of locking notch pipe behind; Time that pulls of joint case and locking notch pipe considers according to the resistance of concrete strength grade, initial setting time, final setting time, temperature and diaphragm wall, joint case and locking notch pipe is loosened among a small circle after concrete casting 2h, after this loosen once every 15min, to final set, slowly pull up joint case and locking notch pipe.
4., according to the employing foundation ditch construction method shown in claim 2, it is characterized in that adopting special joint case and locking notch pipe, be filled in and adjacent slot width joint; Joint case hangs bottom land, and bottom embedded depth is not less than 50cm; After locking notch pipe is in place, fits well from joint case and locking notch pipe for preventing concrete and stream, closely knit in the earthen backfill of locking notch pipe behind; Time that pulls of joint case and locking notch pipe considers according to the resistance of concrete strength grade, initial setting time, final setting time, temperature and diaphragm wall, joint case and locking notch pipe is loosened among a small circle after concrete casting 2h, after this loosen once every 15min, to final set, slowly pull up joint case and locking notch pipe.
5. according to the employing foundation ditch construction method shown in claim 1, it is characterized in that every layer is carried out blockette construction along diaphragm wall, the 550m length of every block block is 15 ~ 20m, width is 10 ~ 14m, and accelerates the excavation of each block earthwork and the construction of floor as far as possible.
6. according to the employing foundation ditch construction method shown in claim 2, it is characterized in that every layer is carried out blockette construction along diaphragm wall, the 550m length of every block block is 15 ~ 20m, width is 10 ~ 14m, and accelerates the excavation of each block earthwork and the construction of floor as far as possible.
7. according to the employing foundation ditch construction method shown in claim 3, it is characterized in that every layer is carried out blockette construction along diaphragm wall, the 550m length of every block block is 15 ~ 20m, width is 10 ~ 14m, and accelerates the excavation of each block earthwork and the construction of floor as far as possible.
8. according to the employing foundation ditch construction method shown in claim 1, it is characterized in that diaphragm wall is connected with basement bottom board, floor and adopt rigid connecting connection, namely on the arrangement of reinforcement absolute altitude of basement bottom board and floor, reinforcing bar connector is buried underground at the interior wall of diaphragm wall in advance, after basement excavation when construction base plate and floor, its base plate and floor bar by reinforcing bar connector directly and diaphragm wall be linked to be entirety and become rigid joint.
9. according to the employing foundation ditch construction method shown in claim 2, it is characterized in that diaphragm wall is connected with basement bottom board, floor and adopt rigid connecting connection, namely on the arrangement of reinforcement absolute altitude of basement bottom board and floor, reinforcing bar connector is buried underground at the interior wall of diaphragm wall in advance, after basement excavation when construction base plate and floor, its base plate and floor bar by reinforcing bar connector directly and diaphragm wall be linked to be entirety and become rigid joint.
10. according to the employing foundation ditch construction method shown in claim 3, it is characterized in that diaphragm wall is connected with basement bottom board, floor and adopt rigid connecting connection, namely on the arrangement of reinforcement absolute altitude of basement bottom board and floor, reinforcing bar connector is buried underground at the interior wall of diaphragm wall in advance, after basement excavation when construction base plate and floor, its base plate and floor bar by reinforcing bar connector directly and diaphragm wall be linked to be entirety and become rigid joint.
CN201410753775.6A 2013-06-14 2013-06-14 Foundation pit construction method Active CN104499489B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410753775.6A CN104499489B (en) 2013-06-14 2013-06-14 Foundation pit construction method

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201410753775.6A CN104499489B (en) 2013-06-14 2013-06-14 Foundation pit construction method
CN201310261074.6A CN103321246B (en) 2013-06-14 2013-06-14 Underground diaphragm wall based foundation pit construction method

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201310261074.6A Division CN103321246B (en) 2013-06-14 2013-06-14 Underground diaphragm wall based foundation pit construction method

Publications (2)

Publication Number Publication Date
CN104499489A true CN104499489A (en) 2015-04-08
CN104499489B CN104499489B (en) 2017-01-11

Family

ID=52940932

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410753775.6A Active CN104499489B (en) 2013-06-14 2013-06-14 Foundation pit construction method

Country Status (1)

Country Link
CN (1) CN104499489B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105780780A (en) * 2016-04-15 2016-07-20 肖锐 Pile-wall combination supporting structure
CN105862875A (en) * 2016-04-15 2016-08-17 肖锐 Support structure and construction method thereof
CN108425362A (en) * 2018-02-01 2018-08-21 中建三局集团有限公司 A kind of earthwork transportation system and construction method for base pit engineering
CN112159160A (en) * 2020-09-12 2021-01-01 北京综建科技有限公司 Energy-saving environment-friendly backfill material and construction process thereof

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2390918Y (en) * 1999-09-02 2000-08-09 上海宝钢冶金建设公司 Apparatus for underground continuous wall airlift reverse circulation cleaning out and displacing bulk head stabilizing solution
KR101034398B1 (en) * 2007-06-28 2011-05-16 (주)바로건설기술 Land-side protection wall that use ground structure
CN102561316A (en) * 2012-01-20 2012-07-11 中国建筑第八工程局有限公司 Construction method for diaphragm walls

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2390918Y (en) * 1999-09-02 2000-08-09 上海宝钢冶金建设公司 Apparatus for underground continuous wall airlift reverse circulation cleaning out and displacing bulk head stabilizing solution
KR101034398B1 (en) * 2007-06-28 2011-05-16 (주)바로건설기술 Land-side protection wall that use ground structure
CN102561316A (en) * 2012-01-20 2012-07-11 中国建筑第八工程局有限公司 Construction method for diaphragm walls

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
关雪梅: "《大型深基坑逆作法施工中的若干工艺技术问题研究》", 《中国优秀硕士学位论文全文数据库(电子期刊)》 *
张庆贺等: "《地下连续墙设计和施工新技术》", 《施工技术》 *
杨学林等: "《逆作地下室设计中的若干关键问题》", 《岩土工程学报》 *
王如路等: "《上海地铁监护实践》", 30 April 2013, 同济大学出版社 *
王美华等: "《超大面积深基坑逆作法施工技术的探讨》", 《地下空间与工程学报》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105780780A (en) * 2016-04-15 2016-07-20 肖锐 Pile-wall combination supporting structure
CN105862875A (en) * 2016-04-15 2016-08-17 肖锐 Support structure and construction method thereof
CN108425362A (en) * 2018-02-01 2018-08-21 中建三局集团有限公司 A kind of earthwork transportation system and construction method for base pit engineering
CN112159160A (en) * 2020-09-12 2021-01-01 北京综建科技有限公司 Energy-saving environment-friendly backfill material and construction process thereof

Also Published As

Publication number Publication date
CN104499489B (en) 2017-01-11

Similar Documents

Publication Publication Date Title
CN103321246B (en) Underground diaphragm wall based foundation pit construction method
CN102094425B (en) Foundation pit construction method adopting shallow buried depth Larsen steel plate pile as protective cofferdam
CN107313431B (en) Close on not contour foundation pit method for synchronously constructing
CN106930321B (en) The construction method of underground structure is built in a kind of stake of pipe-jacking with large diameter combination hole
CN104264688A (en) Manual hole digging non-uniform pile support construction technology
CN204491626U (en) The foundation pit enclosure structure that Larsen steel sheet pile and prestressed anchor combine
CN105951711A (en) Enclosing construction method of underground continuous wall of seashore power station
CN203213124U (en) Steel sheet pile and cement-mixed pile combined support
CN107859145A (en) A kind of drainpipe is plugged into construction method under water
CN207512745U (en) A kind of caisson device and its foundation pit structure
CN100510281C (en) Semi-reverse construction method for ultra-large-diameter and ultra-buried depth storage tank
CN110939303B (en) Semi-reverse construction method of cyclone pool
CN108797641A (en) A kind of structure and its construction method of Underground Subway Station construction period full station sealing
CN113266392B (en) Pipe jacking construction method for penetrating through existing anchor cable group
CN101225664A (en) Caisson dock structure and construction method therefor
CN104499489B (en) Foundation pit construction method
CN104480945B (en) A kind of foundation ditch reversed construction method
CN110055973B (en) Foundation pit enclosure structure under high-speed railway bridge with limited construction space and water stopping method
CN100425773C (en) Grille type connection method of rigid joint for underground continuous wall
CN110565686A (en) Construction method for penetrating river channel under pipe gallery
CN211873034U (en) Box-type buckling steel pile supporting structure
CN111560964B (en) Construction method of rear anti-seepage system of foundation pit
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN111335263B (en) Method for building artificial island
CN102425179B (en) Reinforced soil infiltration ditch structure supported by miniature steel pipe cast-in-place pile

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 325000, Wenzhou, Zhejiang Ouhai District, Jingshan Hill street, Jing Chang Group 12, Room 608

Applicant after: Kong Zhijian

Address before: 325000 Zhejiang Province, Wenzhou city Lucheng District Wendilu Eagle Group 9 Room 608

Applicant before: Kong Zhijian

COR Change of bibliographic data
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Wang Shaorui

Inventor after: Xu Dandan

Inventor after: Li Hefei

Inventor after: Kong Zhijian

Inventor before: Kong Zhijian

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20191224

Address after: Room 403, floor 4, building 3, yard 3, Zhonghe Road, Fengtai District, Beijing 100071

Co-patentee after: Beijing NO.6 Construction Engineering Quality Test Department Co., Ltd.

Patentee after: CSCEC Beijing Architectural Science and Technology Research Institute Co., Ltd.

Address before: 325000, Wenzhou, Zhejiang Ouhai District, Jingshan Hill street, Jing Chang Group 12, Room 608

Patentee before: Kong Zhijian