CN104499489B - Foundation pit construction method - Google Patents

Foundation pit construction method Download PDF

Info

Publication number
CN104499489B
CN104499489B CN201410753775.6A CN201410753775A CN104499489B CN 104499489 B CN104499489 B CN 104499489B CN 201410753775 A CN201410753775 A CN 201410753775A CN 104499489 B CN104499489 B CN 104499489B
Authority
CN
China
Prior art keywords
construction
steel
wall
basement
support post
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410753775.6A
Other languages
Chinese (zh)
Other versions
CN104499489A (en
Inventor
孔志坚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing No6 Construction Engineering Quality Test Department Co Ltd
Beijing Building Research Institute Corp Ltd of CSCEC
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201410753775.6A priority Critical patent/CN104499489B/en
Priority claimed from CN201310261074.6A external-priority patent/CN103321246B/en
Publication of CN104499489A publication Critical patent/CN104499489A/en
Application granted granted Critical
Publication of CN104499489B publication Critical patent/CN104499489B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2220/00Temporary installations or constructions

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The invention discloses a foundation pit construction method adopting an underground continuous wall. The foundation pit construction method is characterized in that a basement structure part is constructed from top to bottom while a main body structure part is constructed from bottom to top; the underground continuous wall construction adopts a hydraulic type crab bucket grooving process, and carries out unit slot segment excavating and concrete pouring through a hole jumping method. The foundation pit construction method is characterized in that a specially-made joint box and a fore shaft pipe are adopted and filled in a joint part between adjacent slot widths; the joint box is hung on a slot bottom; the entering ground depth of the bottom end is not less than 50cm; after the fore shaft pipe is in position, in order to prevent concrete from flowing around from the joint box and the fore shaft pipe, soil is utilized to fill and compact the back part of the fore shaft pipe; each layer is subjected to construction based on the area divided along the underground continuous wall. The underground continuous wall, a basement foundation slab and a floor slab are connected in a rigid connection way.

Description

A kind of foundation ditch construction method
Technical field
The present invention relates to a kind of foundation ditch, particularly to a kind of foundation ditch construction method.
Background technology
Along with urban underground space continually develop utilization, foundation pit enclosure design and construction technique have also been obtained not Disconnected development, the shallow design of foundation pit of cutting depth 5~6m and construction are the most ripe, and this type of foundation ditch is according to week The different characteristics of surrounding environment, conventional foundation pit enclosure scheme puts slope excavation, (being combined) soil nail wall, soil cement Mixing pile dam body, cast-in-situ bored pile combine the form such as anchor pole or inner support.Vibrate little during construction of diaphragm wall, Noise is low, less on surrounding enviroment impact.Diaphram wall body of wall rigidity is big, when excavation of foundation pit, and can Bear the biggest soil pressure, have become as Deep Foundation Pit Supporting Project soil-baffling structure of good performance.Underground is continuous Wall overlapping part often becomes the weak link of load, and the easy seepage in this position, it is necessary to take to arrange Apply strong.
Summary of the invention
Present invention solves the technical problem that and be to provide a kind of foundation ditch construction method, solve existing technical deficiency.
The present invention is from the beginning of ± 0.00, basement structure part from top to bottom, body structure portion from lower and Upper carry out construction simultaneously.Basement first carries out the construction of the horizontal structure such as the beam of each layer, plate, then intert carry out each The vertical structure constructions such as the post of layer, shear wall.It is not fully completed in vertical load-carrying members and reaches design strength Before, above completed permanent load and construction loads carried by the interim steel-support post arranged and transmit To engineering pile.Every steel-support post all inserts engineering pile 2.5m, when drill-pouring Construction of Engineering Pile in post steel After the welding of muscle cage, entirety hangs in hole.For ensureing that steel-support post installs perpendicularity deviation less than its length 1/500 Standard, steel-support post on-station position arranges fixing steel plate, it is ensured that the horizontal level of steel-support post, with axis Plane Angle, capital absolute altitude and perpendicularity.Behind every steel-support post lifting location, forbid heavy mechanical equipment Near stake holes and fixing steel plate, fixing steel plate in the 48h after pile concrete has watered, must not be removed.Ground Lower diaphragm wall is that foundation pit enclosure wall is held concurrently as outer wall of basement.
Construction of diaphragm wall uses fluid pressure type grab chute forming technique, carries out unit groove section with " jumping hole method " Excavate and concreting.Grooving vertical precision is not more than 1/300.The process of diaphram wall sediment is bad can be increased The settling amount of big diaphram wall, does not carries out scarfing cinder only with reverse circular technique in construction method, also uses High-pressure injected water method for slurry after wall is become to reinforce, the most pre-buried 2 pressures in every width diaphram wall steel reinforcement cage Close Grouting Pipe, carries out grouting and reinforcing to 2m depth bounds at the bottom of diaphram wall.Additionally, penetrate by powerful Stream pump sprays, to bottom land, the stabilizing solution that proportion is little, the sediment at the bottom of hole from a side blow to opposite side, opens simultaneously Another suction pump, by suction pipe sediment bigger for proportion from opposite side sucking-off, so that sediment obtains at the bottom of hole To effectively controlling.
Preventing concrete from streaming is the difficult point during construction of diaphragm wall.The present invention uses special joint Case and locking notch pipe, be filled in and adjacent slot width joint.Joint case hangs bottom land, and bottom embedded depth is the least In 50cm.After locking notch pipe is in place, for preventing concrete from streaming, at fore shaft from joint case and the locking notch pipe place of fitting well The earthen backfill of pipe behind is closely knit, efficiently avoid because cell wall landslide, concrete stream and cause to adjacent slot width Dyskinetic construction accident.The time that pulls of joint case and locking notch pipe is according to the strength grade of concrete, initial set The resistance of time, final setting time, temperature and diaphram wall considers, and carries out after concrete casting 2h Little scope loosens joint case and locking notch pipe, hereafter loosens once every 15min, slowly pulls up joint to final set Case and locking notch pipe.
The speed of pit earthwork excavation progress, is restriction basement and the key of whole engineering construction progress.For Solve to accelerate the speed cut the earth and reduce the lateral deformation of diaphram wall and ensure that construction quality and construction are pacified Full contradiction, after taking first open cut, tunneling and machinery are cut the earth, and specifically comprise the following steps that the first floor earthwork is along underground even Outside continuous wall 10m width, use benzvalene form open cut, dig below cause underground 1 floor layer;± 0.00 floor and underground After 1 floor layer has been constructed, then carry out the tunneling of 2, the 3 layers of earthwork in underground;Tunneling soil uses excavator, profit Complete the earthwork horizontal transport in foundation ditch with miniature diesel dump truck, machinery grab bucket and assist small-sized claw bucket sling It is unearthed from floor reserved opening, completes a cubic metre of earth vertical transport.
Traditional handicraft uses fetal membrane of laying bricks, and casting concrete bed course makees basement floor, and speed of application is slow, mixed Solidifying soil surface evenness and presentation quality are the most poor, the present invention by 0.7m below excavation of earthwork to floor soffit, Set up framed bent and install template, to accelerate basement construction progress, it is ensured that the quality of concrete surface.
In order to prevent diaphram wall lateral displacement deformation excessive, produce seepage even structural deterioration, every layer of edge Diaphram wall carries out blockette construction, a length of the 15 of every piece of block~20m, width be 10~14m, and Accelerate excavation and the construction of floor of each block earthwork as far as possible, to shorten the Deformation of Diaphragm Wall time, subtract Thin tail sheep value.
The present invention is first to carry out the construction of the horizontal structures such as basement floor base plate, more successively intert carry out post, The vertical structure constructions such as shear wall.Therefore concrete column joint seam is more, and muscle quality of connection as main in post is unreliable, Casting and compacting of concrete leakiness, will directly affect the safety of structure.The main muscle of post connects specific practice and uses as follows: First end reinforced cut flat with to be connected, end reinforced longitudinal rib to be connected and cross rib screw-rolling machine are used and cuts The method cut peels a part off, and then directly rolling goes out silking, couples together with special silking adapter, Form the connection of reinforcing bar.Traditional concrete column muscle is connected as overlapping electric welding, and compared with conventional art, it is excellent Point has: 1. strength of joint is high, can 100% performance reinforced steel bar strength;2. silking adapter is short, and silking button number is few, Being not required to torque spanner, easy to operate, connection speed is fast;3. material-saving, energy-conservation, economic, than other machinery even The mode of connecing saves steel more than 35%.
If post concrete joint position uses grouting material mode to connect, complex operation is time-consuming, directly Affect the construction speed of superstructure.The present invention takes to connect special bell mouth, coagulation on column template top Soil is once poured onto top, and post four sides arranges punching block extension vibration board and vibrates, it is ensured that the degree of compaction of concrete.
Joint between diaphram wall two width should reach to bear bending resistance, shearing resistance requirement, should not make strong Degree and the weak link of rigidity;The most often produce percolating water, therefore traditional underground continuous wall connector is entered Row improves.
Diaphram wall overlapping part water proof structure of the present invention include diaphram wall, anchor rib, steel seal ring, Steel plate, expansive concrete, high-strength epoxy resin, diaphram wall buries anchor rib underground, and anchor rib is 7 fonts, To strengthen anchorage length, anchor rib a diameter of 22~25mm, anchor rib welding steel seal ring, steel seal ring is thick Degree is 3~4mm, and the width of steel seal ring is 35~45mm, and steel seal ring has blocked the infiltration path of anchor rib, Anchor rib is avoided to there is infiltration hidden danger.Arranging steel plate outside diaphram wall, steel plate thickness is 10~12mm, Steel plate arranges preformed hole, preformed hole a diameter of 25~28mm, anchor rib pass steel plate preformed hole, anchor rib and Space filling high-strength epoxy resin between preformed hole is closed, empty between the steel plate of adjacent diaphram wall Gap is 15~20mm, pours expansive concrete in space, expansive concrete intensity be C35 or more than, swollen Swollen concrete can effectively prevent pouring rear concrete and contraction fissure occurs.
The main path keeping underground continuous wall face smooth is to control to reduce groove in work progress by mud Wall collapses, and therefore, by clean to the sewage in guide groove and dirt removal before grooving, takes for different soil layers The proportioning of different slurry coat methods, specific as follows: for clay, the weight proportion of slurry coat method is: water is 100%, bentonite is 8%, and soda is 0.12%~0.15%, sodium carboxymethyl cellulose is 0.06%~0.08%; For silty clay, the proportioning of slurry coat method is: water is 100%, and bentonite is 9%, and soda is 0.16%~0.19%, sodium carboxymethyl cellulose is 0.09%~0.11%;For silt, the proportioning of slurry coat method is: Water is 100%, and bentonite is 10%, and soda is 0.20%~0.23%, sodium carboxymethyl cellulose is 0.12%~0.14%;For sand, the proportioning of slurry coat method is: water is 100%, and bentonite is 8%~12%, Soda is 0.24%~0.27%, sodium carboxymethyl cellulose is 0.15%~0.17%.
Diaphram wall of the present invention is foundation pit enclosure wall, is again outer wall of basement, and damp proof insulation barrier performance is poor, Need to arrange bricking wall away from basement inwall 30cm position inside diaphram wall.Make diaphram wall inwall And between in being formed between brick clamp wall, play water conservancy diversion and moistureproof effect.
The traditional method that diaphram wall is connected with basement bottom board, floor is to flexibly connect method, i.e. in underground At the floor absolute altitude of room, diaphram wall cover to reinforcement is cut, exposes main muscle, then with basement floor one Rise and pour, the most only transmit horizontal force, do not transmit vertical force and moment of flexure.The present invention uses and is rigidly connected Method, i.e. on the arrangement of reinforcement absolute altitude of basement bottom board and floor, interior wall at diaphram wall is buried reinforcing bar underground and is connect in advance Refuting device, after basement excavates when construction base plate and floor, its base plate and floor bar are by reinforcing bar connector Direct and diaphram wall is linked to be entirety, becomes rigid joint, through the underground structure that rigid joint processes, Performance at the aspect such as anti-settling, resist displacement all can be improved.Compared with traditional method, the present invention shows So have greatly improved in mechanical property.
For conscientiously improving the effect of temporary support, all it is both needed to prestressing force of constructing when being temporarily supported above construction.① In the installation process such as column braces, horizontal support, increase by 2 steel plates at steel tube end part and strengthen bearing, steel pipe After in place, use hydraulic jack pressure, Prestressing that steel pipe is constructed;2. concrete temporary support is all mixed TEA micro-expanding agent, to be reduced or avoided contraction.
Work efficiency of the present invention is high, the duration is short, reliable in quality, high financial profit, has the following characteristics that
(1) engineering geology and the place of hydrogeology complexity it are applicable to.
(2) place that construction site is narrow and small it is applicable to.The construction site of some engineerings is the narrowest, according to biography The building enclosure of system, piles in row adds cement mixing pile sealing, and considers enclosure wall and outer wall of basement Between the scope of operation, then will be substantially reduced building usable floor area.And present invention employs enclosure wall and underground The technical scheme of outdoor wall unification, then be greatly improved the land utilization ratio in red line.
(3) area that surrounding is complicated and high to security reliability requirement it is applicable to.The people around some engineerings Under room and road, pipe network facilities is intensive, is embedded with the gas piping of sensitivity under road, can to the safety of foundation pit enclosure Require the highest by property.In the present invention, diaphram wall adds inner support, forms effective retaining design, rigidity Greatly, displacement and deformation are little.
(4) engineering of construction period anxiety it is applicable to.The construction period of diaphram wall is than conventional drill-pouring Stake adds cement mixing pile or rotary churning pile wants much shorter, can shorten for 1/3~1/2 duration, for effectively controlling total lever factor wound Make condition.
(5) engineering that the excavation of foundation pit degree of depth is big it is applicable to.The excavation of foundation pit degree of depth is the biggest, the water and soil suffered by enclosure wall Lateral pressure is the biggest, the most easily produces Seepage, and the strength and stiffness that employing is gone along with sb. to guard him piling wall are wanted Asking the highest, the stability requirement to retaining design is the strictest.And prop up in the present invention, diaphram wall combines Support, the advantage exactly having possessed these several respects, i.e. big at anti-leakage, intensity and toughness, stability and globality Aspect has unrivaled superiority.
(6) analyzing from bracing engineering cost, the technical program uses enclosure wall and outer wall of basement unification, than Traditional method is cost-effective.
Accompanying drawing explanation
Fig. 1 diaphram wall overlapping part water proof structure schematic diagram.
Accompanying drawing mark: 1, diaphram wall, 2, anchor rib, 3, steel seal ring, 4, steel plate, 5, expand Concrete, 6, high-strength epoxy resin.
Detailed description of the invention
Describe the present invention below in conjunction with accompanying drawing.
The present embodiment is from the beginning of ± 0.00, basement structure part from top to bottom, body structure portion under And upper carry out construction simultaneously.Basement first carries out the construction of the horizontal structure such as the beam of each layer, plate, then interts and carry out The vertical structure constructions such as the post of each layer, shear wall.It is not fully completed in vertical load-carrying members and reaches design by force Before degree, above completed permanent load and construction loads carried by the interim steel-support post arranged and pass Pass engineering pile.Every steel-support post all inserts engineering pile 2.5m, when drill-pouring Construction of Engineering Pile in post After steel reinforcement cage welding, entirety hangs in hole.For ensureing that steel-support post installs perpendicularity deviation less than its length 1/500 Standard, steel-support post on-station position arranges fixing steel plate, it is ensured that the horizontal level of steel-support post, with axis Plane Angle, capital absolute altitude and perpendicularity.Behind every steel-support post lifting location, forbid that big machinery sets Standby close stake holes and fixing steel plate, must not remove fixing steel plate in the 48h after pile concrete has watered. Diaphram wall 1 is that foundation pit enclosure wall is held concurrently as outer wall of basement.
Diaphram wall 1 construction uses fluid pressure type grab chute forming technique, carries out unit groove section with " jumping hole method " Excavation and concreting.Grooving vertical precision is not more than 1/300.Construction method is not followed only with counter Ring technique carries out scarfing cinder, and after also using into wall, high-pressure injected water method for slurry is reinforced, at every width diaphram wall 1 In steel reinforcement cage, the most pre-buried 2 compaction grouting pipes, carry out slip casting to diaphram wall 1 end 2m depth bounds and add Gu.Additionally, by powerful jet pump to the bottom land injection little stabilizing solution of proportion, the sediment at the bottom of hole from One side blow, to opposite side, opens another suction pump simultaneously, by suction pipe sediment bigger for proportion from another Side sucking-off, so that sediment is effectively controlled at the bottom of hole.
The present embodiment uses special joint case and locking notch pipe, is filled in adjacent slot width joint.Joint case hangs Putting bottom land, bottom embedded depth is not less than 50cm.After locking notch pipe is in place, for preventing concrete from joint case and The locking notch pipe place of fitting well is streamed, closely knit in the earthen backfill of locking notch pipe behind.Joint case and locking notch pipe pull the time The resistance of strength grade, presetting period, final setting time, temperature and diaphram wall 1 according to concrete is combined Close and consider, after concrete casting 2h, carry out little scope loosen joint case and locking notch pipe, hereafter every 15min pine Move once, to final set, slowly pull up joint case and locking notch pipe.
Pit earthwork excavation takes tunneling and machinery shoveling after first open cut, specifically comprises the following steps that first floor earthwork edge Outside diaphram wall 10m width, use benzvalene form open cut, dig below cause underground 1 floor layer;± 0.00 floor After having constructed with underground 1 floor layer, then carry out the tunneling of 2, the 3 layers of earthwork in underground;Tunneling soil uses and excavates Machine, utilizes miniature diesel dump truck to complete the earthwork horizontal transport in foundation ditch, machinery grabs bucket and assist small-sized Claw bucket sling is unearthed from floor reserved opening, completes a cubic metre of earth vertical transport.
The present embodiment, by 0.7m below excavation of earthwork to floor soffit, is set up framed bent and is installed template, to accelerate Basement construction progress, it is ensured that the quality of concrete surface.
In order to prevent diaphram wall 1 lateral displacement deformation excessive, generation seepage even structural deterioration, every layer Carry out blockette construction along diaphram wall 1, a length of the 15 of every piece of block~20m, width be 10~14m, And accelerate excavation and the construction of floor of each block earthwork as far as possible, to shorten diaphram wall 1 deformation time, Reduce shift value.
The main muscle of post connects specific practice and uses as follows: first end reinforced cut flat with to be connected, by steel to be connected The longitudinal rib of muscle end and cross rib screw-rolling machine use the method for cutting to peel a part off, then directly rolling wire vent Stricture of vagina, couples together with special silking adapter, forms the connection of reinforcing bar.
If post concrete joint position uses grouting material mode to connect, complex operation is time-consuming, directly Affect the construction speed of superstructure.The present embodiment takes to connect special bell mouth on column template top, mixed Solidifying soil is once poured onto top, and post four sides arranges punching block and hangs vibration board and vibrate, it is ensured that concrete closely knit Degree.
Fig. 1 is diaphram wall overlapping part water proof structure schematic diagram.The present embodiment diaphram wall clinch Position water proof structure include diaphram wall 1, anchor rib 2, steel seal ring 3, steel plate 4, expansive concrete 5, High-strength epoxy resin 6, diaphram wall 1 buries anchor rib 2 underground, and anchor rib 2 is 7 fonts, and anchor rib 2 is straight Footpath is 22mm, and anchor rib 2 welds steel seal ring 3, and steel seal ring 3 thickness is 3mm, steel seal ring 3 Width be 35~45mm, steel plate 4 is set outside diaphram wall 1, steel plate 4 thickness is 10mm, steel plate 4 arrange preformed hole, a diameter of 25mm of preformed hole, and anchor rib 2 is through steel plate 4 preformed hole, anchor rib 2 He Space filling high-strength epoxy resin 6 between preformed hole is closed, between the steel plate of adjacent diaphram wall Space is 15~20mm, pours expansive concrete in space, expansive concrete intensity be C35 or more than, Expansive concrete can effectively prevent pouring rear concrete and contraction fissure occurs.
When diaphram wall 1 is constructed, different soil layers is taked to the proportioning of different slurry coat methods, the most such as Under: for clay, the weight proportion of slurry coat method is: water is 100%, and bentonite is 8%, and soda is 0.12%~0.15%, sodium carboxymethyl cellulose is 0.06%~0.08%;For silty clay, joining of slurry coat method Ratio is: water is 100%, and bentonite is 9%, and soda is 0.16%~0.19%, sodium carboxymethyl cellulose is 0.09%~0.11%;For silt, the proportioning of slurry coat method is: water is 100%, and bentonite is 10%, pure Alkali is 0.20%~0.23%, sodium carboxymethyl cellulose is 0.12%~0.14%;For sand, slurry coat method Proportioning is: water is 100%, and bentonite is 8%~12%, and soda is 0.24%~0.27%, carboxymethyl cellulose Sodium is 0.15%~0.17%.
The present embodiment diaphram wall 1 is foundation pit enclosure wall, is again outer wall of basement, damp proof insulation barrier performance Difference, needs to arrange bricking wall away from basement inwall 30cm position inside diaphram wall 1.
Diaphram wall 1 and basement bottom board, floor are connected by the method for being rigidly connected, i.e. at basement bottom board With on the arrangement of reinforcement absolute altitude of floor in advance interior wall at diaphram wall 1 bury reinforcing bar connector underground, open at basement After digging when construction base plate and floor, its base plate and floor bar be direct and diaphram wall 1 by reinforcing bar connector It is linked to be entirety and becomes rigid joint.
All it is both needed to prestressing force of constructing when being temporarily supported above construction.1. column braces, horizontal support etc. were installed Cheng Zhong, increases by 2 steel plates at steel tube end part and strengthens bearing, after steel pipe is in place, uses hydraulic jack pressure, To steel pipe construction Prestressing;2. concrete temporary support all mixes TEA micro-expanding agent, so that receipts are reduced or avoided Contracting.

Claims (1)

1. a foundation ditch construction method, is characterized in that from the beginning of ± 0.00, and from top to bottom, body structure portion carries out construction to basement structure part the most simultaneously;Basement first carries out the beam of each layer, plate level structure construction, then interts and carry out the post of each layer, the construction of shear wall vertical structure;Before vertical load-carrying members are not fully completed and reach design strength, above completed permanent load and construction loads carried by the interim steel-support post arranged and pass to engineering pile;Every steel-support post all inserts engineering pile 2.5m, and when drill-pouring Construction of Engineering Pile, after post steel reinforcement cage welds, entirety hangs in hole;For ensureing that the perpendicularity deviation standard less than its length 1/500 installed by steel-support post, steel-support post on-station position arranges fixing steel plate, it is ensured that the horizontal level of steel-support post, with Plane Angle, capital absolute altitude and the perpendicularity of axis;Behind every steel-support post lifting location, forbid that heavy mechanical equipment must not remove fixing steel plate in stake holes and fixing steel plate, the 48h after pile concrete has watered;
Construction of diaphragm wall uses fluid pressure type grab chute forming technique, carries out excavation and the concreting of unit groove section with " jumping hole method ";Grooving vertical precision is not more than 1/300;Not carrying out scarfing cinder only with reverse circular technique in construction method, also use into high-pressure injected water method for slurry after wall and reinforce, in every width diaphram wall steel reinforcement cage, the most pre-buried 2 compaction grouting pipes, carry out grouting and reinforcing to 2m depth bounds at the bottom of diaphram wall;In addition, by powerful jet pump to spraying the stabilizing solution that proportion is little at the bottom of hole, the sediment at the bottom of hole from a side blow to opposite side, open another suction pump simultaneously, by suction pipe sediment bigger for proportion from opposite side sucking-off, so that sediment is effectively controlled at the bottom of hole.
CN201410753775.6A 2013-06-14 2013-06-14 Foundation pit construction method Active CN104499489B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410753775.6A CN104499489B (en) 2013-06-14 2013-06-14 Foundation pit construction method

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201310261074.6A CN103321246B (en) 2013-06-14 2013-06-14 Underground diaphragm wall based foundation pit construction method
CN201410753775.6A CN104499489B (en) 2013-06-14 2013-06-14 Foundation pit construction method

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201310261074.6A Division CN103321246B (en) 2013-06-14 2013-06-14 Underground diaphragm wall based foundation pit construction method

Publications (2)

Publication Number Publication Date
CN104499489A CN104499489A (en) 2015-04-08
CN104499489B true CN104499489B (en) 2017-01-11

Family

ID=52940932

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410753775.6A Active CN104499489B (en) 2013-06-14 2013-06-14 Foundation pit construction method

Country Status (1)

Country Link
CN (1) CN104499489B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105862875A (en) * 2016-04-15 2016-08-17 肖锐 Support structure and construction method thereof
CN105780780A (en) * 2016-04-15 2016-07-20 肖锐 Pile-wall combination supporting structure
CN108425362A (en) * 2018-02-01 2018-08-21 中建三局集团有限公司 A kind of earthwork transportation system and construction method for base pit engineering
CN112159160A (en) * 2020-09-12 2021-01-01 北京综建科技有限公司 Energy-saving environment-friendly backfill material and construction process thereof

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2390918Y (en) * 1999-09-02 2000-08-09 上海宝钢冶金建设公司 Apparatus for underground continuous wall airlift reverse circulation cleaning out and displacing bulk head stabilizing solution
KR101034398B1 (en) * 2007-06-28 2011-05-16 (주)바로건설기술 Land-side protection wall that use ground structure
CN102561316A (en) * 2012-01-20 2012-07-11 中国建筑第八工程局有限公司 Construction method for diaphragm walls

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2390918Y (en) * 1999-09-02 2000-08-09 上海宝钢冶金建设公司 Apparatus for underground continuous wall airlift reverse circulation cleaning out and displacing bulk head stabilizing solution
KR101034398B1 (en) * 2007-06-28 2011-05-16 (주)바로건설기술 Land-side protection wall that use ground structure
CN102561316A (en) * 2012-01-20 2012-07-11 中国建筑第八工程局有限公司 Construction method for diaphragm walls

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
《地下连续墙设计和施工新技术》;张庆贺等;《施工技术》;19981231(第01期);第18-20页 *
《大型深基坑逆作法施工中的若干工艺技术问题研究》;关雪梅;《中国优秀硕士学位论文全文数据库(电子期刊)》;中国学术期刊电子杂志出版社;20080131;第44-45页 *
《超大面积深基坑逆作法施工技术的探讨》;王美华等;《地下空间与工程学报》;20050831;第1卷(第4期);第599-602页 *
《逆作地下室设计中的若干关键问题》;杨学林等;《岩土工程学报》;20100731;第32卷;第238-244页 *

Also Published As

Publication number Publication date
CN104499489A (en) 2015-04-08

Similar Documents

Publication Publication Date Title
CN103321246B (en) Underground diaphragm wall based foundation pit construction method
CN106958256B (en) A kind of placement layer by layer, the open caisson construction technique repeatedly sunk
CN102094425B (en) Foundation pit construction method adopting shallow buried depth Larsen steel plate pile as protective cofferdam
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN105951711A (en) Enclosing construction method of underground continuous wall of seashore power station
CN207512745U (en) A kind of caisson device and its foundation pit structure
CN106930321B (en) The construction method of underground structure is built in a kind of stake of pipe-jacking with large diameter combination hole
CN107859145A (en) A kind of drainpipe is plugged into construction method under water
CN203213124U (en) Steel sheet pile and cement-mixed pile combined support
CN108457282A (en) Deep water hard rock is without back cover steel sheet pile cofferdam construction method
CN102535441A (en) Construction method of underground diaphragm wall
CN100510281C (en) Semi-reverse construction method for ultra-large-diameter and ultra-buried depth storage tank
CN113266392B (en) Pipe jacking construction method for penetrating through existing anchor cable group
CN110159294A (en) A kind of high steep landform tunnel immediately adjacent to bridge section spreading open cut tunnel construction method
CN108571000A (en) The construction method of underground water cutting when wearing existing railway under a kind of road of location along the river
CN104499489B (en) Foundation pit construction method
CN104631440A (en) Stiffening core lengthening foundation pit support structure for existing large-diameter bored concrete pile and construction method
CN104480945B (en) A kind of foundation ditch reversed construction method
CN106480891B (en) A kind of shaft construction method
CN100425773C (en) Grille type connection method of rigid joint for underground continuous wall
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN212641468U (en) Pit-in-pit rapid construction structure
CN106498951B (en) A kind of shaft excavation construction method
CN110359471B (en) Anti-seepage damage structure of strong water-permeable sandy soil layer of underwater tunnel and construction method
CN113266362B (en) Top pipe cover excavation construction method for penetrating through existing dense anchor cable area

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 325000, Wenzhou, Zhejiang Ouhai District, Jingshan Hill street, Jing Chang Group 12, Room 608

Applicant after: Kong Zhijian

Address before: 325000 Zhejiang Province, Wenzhou city Lucheng District Wendilu Eagle Group 9 Room 608

Applicant before: Kong Zhijian

COR Change of bibliographic data
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information

Inventor after: Wang Shaorui

Inventor after: Xu Dandan

Inventor after: Li Hefei

Inventor after: Kong Zhijian

Inventor before: Kong Zhijian

CB03 Change of inventor or designer information
TR01 Transfer of patent right

Effective date of registration: 20191224

Address after: Room 403, floor 4, building 3, yard 3, Zhonghe Road, Fengtai District, Beijing 100071

Co-patentee after: Beijing NO.6 Construction Engineering Quality Test Department Co., Ltd.

Patentee after: CSCEC Beijing Architectural Science and Technology Research Institute Co., Ltd.

Address before: 325000, Wenzhou, Zhejiang Ouhai District, Jingshan Hill street, Jing Chang Group 12, Room 608

Patentee before: Kong Zhijian

TR01 Transfer of patent right