KR101184773B1 - Constructing method of cable bridge using free cantilever method - Google Patents

Constructing method of cable bridge using free cantilever method Download PDF

Info

Publication number
KR101184773B1
KR101184773B1 KR1020120047342A KR20120047342A KR101184773B1 KR 101184773 B1 KR101184773 B1 KR 101184773B1 KR 1020120047342 A KR1020120047342 A KR 1020120047342A KR 20120047342 A KR20120047342 A KR 20120047342A KR 101184773 B1 KR101184773 B1 KR 101184773B1
Authority
KR
South Korea
Prior art keywords
segment
cable
formwork
support cable
stayed bridge
Prior art date
Application number
KR1020120047342A
Other languages
Korean (ko)
Inventor
김광수
이은철
김승익
김재석
Original Assignee
주식회사 후레씨네코리아
현대건설주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 후레씨네코리아, 현대건설주식회사 filed Critical 주식회사 후레씨네코리아
Priority to KR1020120047342A priority Critical patent/KR101184773B1/en
Application granted granted Critical
Publication of KR101184773B1 publication Critical patent/KR101184773B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D11/00Suspension or cable-stayed bridges
    • E01D11/04Cable-stayed bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/16Suspension cables; Cable clamps for suspension cables ; Pre- or post-stressed cables
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

PURPOSE: A construction method of a cable-stayed bridge for reducing construction time by changing the installation order of a support cable using the temporary connection of segments is provided to reduce time required for constructing an upper structure of a cable-stayed bridge. CONSTITUTION: A construction method of a cable-stayed bridge for reducing construction time by changing the installation order of a support cable using the temporary connection of segments is as follows. A movable form installation device(200) is installed on a first segment(102) and installs a form a second segment(103) is installed on the front of the first segment. The second segment is manufactured by placing concrete in the form. The first and second segments are connected to each other using a temporary connection assembly. The movable form installation device is moved to the second segment before a support cable(300) is connected to the second segment and tensioned. The moved movable form installation device installs a form for a third segment is installed on the front of the second segment. The third segment is manufactured by placing concrete in the form.

Description

세그먼트의 임시 연결에 의한 지지케이블 설치순서의 변경을 통하여 공기를 단축시키는 사장교 시공방법{Constructing Method of Cable Bridge using Free Cantilever Method}Construction method of cable-stayed bridge to shorten air by changing the order of supporting cable installation by temporary connection of segments {Constructing Method of Cable Bridge using Free Cantilever Method}

본 발명은 외팔보 공법에 의해 교량을 시공하는 방법에 관한 것으로서, 구체적으로는 동바리 없이, 이미 시공된 교각 및 교량바닥판 위에서 이동식 거푸집설치장치(Form Traveller)를 사용하여 교량바닥판을 전진 가설하는 외팔보공법 즉, 소위 FCM(Free Cantilever Method)에 의해 사장교를 시공함에 있어서, 새로 설치된 세그먼트를 이미 설치된 세그먼트와 임시 연결한 후, 새로운 세그먼트용 거푸집 설치를 위해 이동식 거푸집설치장치를 이동시키고, 지지케이블을 연결하는 구성을 가짐으로써, 시공속도를 향상시켜서 교량 완공에 필요한 공기를 단축하게 되는 사장교 시공방법에 관한 것이다.
The present invention relates to a method for constructing a bridge by a cantilever method, and specifically a cantilever for advancing a bridge deck using a form traveler on a bridge and a bridge deck that have already been constructed without a circle bar. In the construction of the cable-stayed bridge by the so-called FCM (Free Cantilever Method), the newly installed segment is temporarily connected with the already installed segment, and then the movable formwork is installed to install the formwork for the new segment, and the support cable is connected. By having a constitution, the construction method of the cable-stayed bridge that shortens the air required for the completion of the bridge by improving the construction speed.

사장교(斜張橋)를 시공함에 있어서, 이미 시공된 교각 및 교량바닥판 위에서 이동식 거푸집설치장치(Form Traveller)를 사용하여 교량바닥판을 전진 가설하는 외팔보공법 즉, 소위 FCM(Free Cantilever Method)이 이용되고 있다. 도 1 내지 도 4에는 각각 종래의 FCM에 의해 사장교의 상부구조물을 시공하는 상태의 측면도가 순차적으로 도시되어 있다. 도면에 도시된 것처럼, FCM에서는 교축방향으로 교량 상부구조물을 복수개의 세그먼트로 구분하고, 도 1의 화살표 M방향으로 각각의 세그먼트를 순차적으로 연속 형성하여 전체적인 교량 상부구조물을 시공하게 된다. In the construction of cable-stayed bridges, the cantilevering method, which is a free cantilever method (FCM), that uses a form-former to move the bridge deck forward on the bridges and bridge decks already constructed. It is used. 1 to 4 show side views of the state in which the upper structure of the cable-stayed bridge is constructed by a conventional FCM, respectively. As shown in the drawing, the FCM divides the bridge superstructure into a plurality of segments in the bridge direction, and sequentially forms each segment in the arrow M direction of FIG. 1 to construct the entire bridge superstructure.

종래기술에서는 우선 도 1에 도시된 것처럼, 교량 상부구조물의 제n-2번째 세그먼트(101)와, 그에 연속하는 제n-1번째 세그먼트(102)가 시공된 상태에서, 상기 제n-1번째 세그먼트(102)의 상부 또는 제n-1번째 세그먼트(102)와 제n-2번째 세그먼트(101)의 상부에 이동식 거푸집설치장치(200)를 설치한 후, 제n번째 세그먼트(103)의 제작을 위한 거푸집을 상기 제n-1번째 세그먼트(102)의 전방에 설치하고 콘크리트를 타설하여 제n번째 세그먼트(103)를 제작하게 된다. 도 1에서는 제n번째 세그먼트(103)의 콘크리트가 아직 충분히 양생되지 아니한 상태임을 나타내기 위하여 제n번째 세그먼트(103)는 음영으로 표시하였다. In the prior art, first, as shown in FIG. 1, the n-th segment 101 of the bridge superstructure and the n-th segment 102 subsequent thereto are constructed. After the movable formwork 200 is installed on the upper part of the segment 102 or the n-th segment 102 and the n-second segment 101, the n-th segment 103 is manufactured. Forming the formwork for the front of the n-th segment 102 and the concrete is poured to produce the n-th segment 103. In FIG. 1, the nth segment 103 is shaded to indicate that the concrete of the nth segment 103 is not sufficiently cured yet.

도 2에는 도 1에 도시된 상태에 후속하여 제n번째 세그먼트(103)에 지지케이블(300)을 연결하여 긴장한 상태가 도시되어 있는데, 제n번째 세그먼트(103)의 콘크리트의 충분한 양생기간이 지난 후에는, 제n번째 세그먼트(103)를 지지하기 위한 지지케이블(300)을 상기 제n번째 세그먼트(103)에 연결하여 도 2의 화살표 A방향으로 상기 지지케이블(300)을 긴장하게 된다. FIG. 2 shows a tensioned state in which the support cable 300 is connected to the nth segment 103 after the state shown in FIG. 1, and a sufficient curing period of the concrete of the nth segment 103 has passed. Afterwards, the support cable 300 for supporting the nth segment 103 is connected to the nth segment 103 to tension the support cable 300 in the direction of arrow A of FIG. 2.

이와 같이 제n번째 세그먼트(103)가 지지케이블(300)에 의해 지지된 상태가 되면, 이동식 거푸집설치장치(200)에 의한 하중이 제n번째 세그먼트(103)에 작용하더라도 제n번째 세그먼트(103)와 제n-1번째 세그먼트(102) 간의 일체화가 유지될 수 있으므로, 도 3에 도시된 것처럼 이동식 거푸집설치장치(200)를 제n번째 세그먼트(103) 위로 이동시킨 후에, 제n번째 세그먼트(103)의 전방으로 제n+1번째 세그먼트(104)를 위한 거푸집(210)을 설치하게 된다. 그리고 도 4에 도시된 것처럼, 제n+1번째 세그먼트(104)를 위한 콘크리트를 거푸집(210)에 설치하고 콘크리트를 타설하여 제n번째 세그먼트(103)의 전방으로 제n+1번째 세그먼트(104)를 일체로 제작하여 시공하게 된다. 이와 같은 과정 즉, 도 1 내지 도 4에 도시된 과정을 반복함으로써, 상부구조물을 구축하여 사장교를 시공하게 되는 것이다. In this way, when the n-th segment 103 is supported by the support cable 300, the n-th segment 103 even if the load by the movable formwork 200 acts on the n-th segment 103. ) And the n-th segment 102 can be maintained, so after moving the movable formwork 200 above the n-th segment 103 as shown in FIG. 3, the n-th segment ( In front of 103, the formwork 210 for the n + 1th segment 104 is installed. And, as shown in Figure 4, the concrete for the n + 1 st segment 104 is installed in the formwork 210 and the concrete is poured in front of the n + 1 st segment 104 in front of the n th segment 103 ) Will be manufactured integrally. By repeating the above process, that is, the process illustrated in FIGS. 1 to 4, the superstructure is constructed to build a cable-stayed bridge.

그런데 앞서 살펴본 것처럼, 종래 기술에서는 제n번째 세그먼트(103) 제작에 후속하여 제n+1번째 세그먼트(104)를 제작하기 위해서는, 제n번째 세그먼트(103)에 지지케이블(300)을 연결할 정도로 콘크리트가 충분히 양생되어야 할 뿐만 아니라, 지지케이블(300)이 제n번째 세그먼트(103)에 연결되어 긴장되어 제n번째 세그먼트(103)가 지지케이블(300)에 의해 매달려 지지되어야 한다. 즉, 지지케이블(300)에 의해 제n번째 세그먼트(103)가 지지된 후에야 비로소 이동식 거푸집설치장치(200)가 이동하여 제n번째 세그먼트(103) 위에 탑재될 수 있는 것이다. 그런데 세그먼트에 지지케이블(300)을 연결하고, 지지케이블(300)을 긴장하는 것은 상당한 시간을 소모하는 작업이다. As described above, in the prior art, in order to manufacture the n + 1th segment 104 subsequent to the manufacture of the nth segment 103, the concrete is sufficiently connected to the support cable 300 to the nth segment 103. Not only needs to be sufficiently cured, but the support cable 300 is connected to the nth segment 103 and is tensioned so that the nth segment 103 is supported by the support cable 300 to be suspended. That is, only after the n th segment 103 is supported by the support cable 300, the movable formwork apparatus 200 may move and be mounted on the n th segment 103. By the way, connecting the support cable 300 to the segment, tensioning the support cable 300 is a time-consuming task.

따라서 종래기술에서는 지지케이블(300)에 의해 제n번째 세그먼트(103)가 지지되지 않고서는 이동식 거푸집설치장치(200)가 제n번째 세그먼트(103)로 이동될 수 없고, 지지케이블(300)을 제n번째 세그먼트에 연결하여 긴장하는데는 상당한 시간이 소요되므로, 그만큼 제n번째 세그먼트(103) 위에 이동식 거푸집설치장치(200)를 탑재하여 제n+1째 세그먼트(104)의 제작을 개시하는데 까지 오랜 시간이 소요되고, 제n+1번째 세그먼트(104)를 제작하는 것이 지연되어 전체적인 교량 시공에 소요되는 기간이 늘어나게 되는 문제점이 있다. Therefore, in the prior art, the movable formwork 200 cannot move to the n-th segment 103 without supporting the n-th segment 103 by the support cable 300, and thus, the support cable 300 may not be moved. Since it takes a considerable amount of time to connect to the n-th segment, the mobile formwork 200 is mounted on the n-th segment 103 until the manufacture of the n + 1th segment 104 is started. It takes a long time, there is a problem that the production of the n + 1 st segment 104 is delayed to increase the time required for the overall bridge construction.

대한민국 등록특허공보 제10-0775580호(2007. 11. 15. 공고) 참조.See Republic of Korea Patent Publication No. 10-0775580 (Nov. 15, 2007).

본 발명은 위와 같은 종래 기술의 한계와 문제점을 해결하기 위하여 개발된 것으로서, 구체적으로는 FCM에 의해 사장교의 상부구조물을 시공함에 있어서, 제n번째 세그먼트에 지지케이블을 연결하여, 이동식 거푸집설치장치가 제n번째 세그먼트 위에 탑재되더라도 제n번째 세그먼트가 이동식 거푸집설치장치에 의한 하중을 지지할 수 있는 상태로 만든 후에야 비로소 제n+1번째 세그먼트의 제작이 시작됨으로 인하여 발생하는 공기 지연 문제를 해결하는 것을 목적으로 한다. The present invention was developed to solve the limitations and problems of the prior art as described above, specifically, in the construction of the upper structure of the cable-stayed bridge by FCM, by connecting the support cable to the n-th segment, the mobile formwork installation apparatus Even if it is mounted on the nth segment, it is necessary to solve the air delay problem caused by the manufacture of the n + 1th segment only after the nth segment is made to support the load by the movable formwork. The purpose.

즉, 본 발명에서는 제n번째 세그먼트의 제작이 완료되면, 지지케이블을 제n번째 세그먼트에 연결하여 긴장하는 작업을 수행하기 전의 상태에서도 이동식 거푸집설치장치를 제n번째 세그먼트로 이동 탑재시켜 제n+1번째 세그먼트의 제작을 개시할 수 있도록 함으로써, 사장교의 상부구조물 구축에 소요되는 공기를 단축시키는 것을 목적으로 하는 것이다.
That is, in the present invention, when the manufacturing of the n-th segment is completed, even if the support cable is connected to the n-th segment before the tension work is performed, the movable formwork is moved to the n-th segment and mounted to the n-th segment. It is an object to shorten the air required to construct the superstructure of the cable-stayed bridge by allowing the manufacture of the first segment.

위와 같은 과제를 달성하기 위하여 본 발명에서는, 제n-1번째 세그먼트에 이웃하여 제n번째 세그먼트를 연속하여 설치하고, 후속하여 제n+1번째 세그먼트를 연속 설치하여 복수개의 세그먼트를 순차적으로 제작하여 연속 설치하면서, 각각의 세그먼트에 지지케이블을 연결하고 지지케이블을 긴장함으로서 교각 위에 상부구조물을 구축하는 사장교의 시공방법으로서, 상기 제n-1번째 세그먼트에 이동식 거푸집설치장치를 설치하여 제n번째 세그먼트의 제작을 위한 거푸집을 상기 제n-1번째 세그먼트의 전방에 설치하고 콘크리트를 타설하여 제n번째 세그먼트를 제작하는 제1단계; 제n-1번째 세그먼트와 제n번째 세그먼트 사이를 가설 연결조립체에 의해 연결하여 지지한 후, 상기 제n번째 세그먼트에 지지케이블을 연결하여 긴장하기 전에, 이동식 거푸집설치장치를 이동시켜 제n번째 세그먼트에 이동식 거푸집설치장치가 탑재되도록 하는 작업을 수행하는 제2단계; 및 상기 제n번째 세그먼트에 지지케이블을 연결하여 긴장하는 작업과 병행하여, 이미 제n번째 세그먼트로 이동하여 탑재되어 있던 상기 이동식 거푸집설치장치를 이용하여 제n+1번째 세그먼트를 위한 거푸집을 상기 제n번째 세그먼트의 전방에 설치하고 콘크리트를 타설하여 제n+1번째 세그먼트를 제작하는 제3단계를 반복수행하여 상부구조물을 구축하는 것을 특징으로 하는 사장교의 시공방법이 제공된다. In order to achieve the above object, in the present invention, the n-th segment is continuously installed adjacent to the n-th segment, and subsequently, the n + 1-th segment is continuously installed to manufacture a plurality of segments sequentially. As the installation method of the cable-stayed bridge which connects the supporting cable to each segment and builds the upper structure on the pier by tensioning the supporting cable while being installed continuously, the mobile formwork is installed in the n-1th segment to install the nth segment. A first step of manufacturing a formwork for fabricating the n-th segment by installing concrete in front of the n-th segment and placing concrete; After the n-th segment and the n-th segment are connected and supported by a hypothetical coupling assembly, the movable formwork is moved to the n-th segment by connecting the support cable to the n-th segment before tensioning. A second step of performing a task of mounting the movable formwork installation apparatus on the; And in parallel with the tensioning operation by connecting the support cable to the nth segment, the formwork for the n + 1th segment is moved to the nth segment using the movable formwork installed in the nth segment. The installation method of the cable-stayed bridge is provided by constructing an upper structure by repeating the third step of installing the n + 1th segment by installing concrete in front of the nth segment.

상기한 본 발명에서, 상기 가설 연결조립체는, 서로 이웃하는 세그먼트의 상면에 각각 분해 가능하도록 고정되는 한 쌍의 고정장치와, 상기 한 쌍의 고정장치 사이에 교축방향으로 배치되어 상기 한 쌍의 고정장치를 서로 연결하는 종방향 연결부재를 포함하여 구성될 수 있다.
In the present invention, the hypothetical connection assembly, a pair of fixing devices that are fixed to each of the upper surface of the adjacent segments, and the pair of fixing devices are arranged in the axial direction between the pair of fixing devices fixed to the pair of It may comprise a longitudinal connecting member connecting the devices to each other.

본 발명에 의하면, FCM을 이용하여 사장교의 상부구조물을 형성함에 있어서, 상부구조물을 이루는 복수개의 세그먼트에서, 제n번째 세그먼트의 제작이 완료되면, 지지케이블을 제n번째 세그먼트에 연결하여 긴장하는 작업이 완료되기 전의 상태에서 이동식 거푸집설치장치를 제n번째 세그먼트로 이동 탑재시켜 제n+1번째 세그먼트의 제작을 개시할 수 있게 되므로, 사장교의 상부구조물 구축에 소요되는 공기를 크게 단축시킬 수 있게 되어, 전체적인 사장교 시공에 소요되는 시간을 줄이고, 그에 따라 공사비용을 줄일 수 있게 되는 효과가 발휘된다.
According to the present invention, in forming the upper structure of the cable-stayed bridge using the FCM, in the plurality of segments constituting the upper structure, when the production of the n-th segment is completed, the work to connect the tension to the support cable to the n-th segment In this state before the completion, the mobile formwork is mounted on the nth segment, so that the manufacture of the n + 1th segment can be started. Therefore, the air required for the construction of the upper structure of the cable-stayed bridge can be greatly reduced. Therefore, the time required for the construction of the overall cable-stayed bridge can be reduced, thereby reducing the construction cost.

도 1 내지 도 4는 각각 종래의 FCM에 의해 사장교의 상부구조물을 구축하는 단계를 보여주는 개략적인 측면도이다.
도 5는 본 발명에 따른 시공방법에서, 제n-2번째 세그먼트와 제n-1번째 세그먼트가 시공된 상태에서 이동식 거푸집설치장치에 의해 제n번째 세그먼트를 제작하는 상태를 보여주는 개략적인 측면도이다.
도 6은 도 5에 도시된 상태에 후속하여 제n-1번째 세그먼트와 제n번째 세그먼트를 가설 연결장치로 연결하고 이동식 거푸집설치장치를 제n번째 세그먼트로 이동한 상태를 보여주는 개략적인 측면도이다.
도 7은 도 6의 원 C 부분에 대한 개략적인 발췌 사시도이다.
도 8은 도 6에 도시된 상태에 후속하여 제n번째 세그먼트에 지지케이블을 연결함과 동시에 제n+1번째 세그먼트의 제작을 위한 거푸집을 설치한 상태를 보여주는 개략적인 측면도이다.
도 9는 도 8에 도시된 상태에 후속하여 제n+1세그먼트를 제작한 상태를 보여주는 개략적인 측면도이다.
1 to 4 are schematic side views showing the step of constructing the superstructure of the cable-stayed bridge by the conventional FCM, respectively.
FIG. 5 is a schematic side view illustrating a state in which the n-th segment is manufactured by the movable formwork in the state in which the n-second segment and the n-th segment are constructed in the construction method according to the present invention.
FIG. 6 is a schematic side view illustrating a state in which the n-th segment and the n-th segment are connected by a temporary connecting device and the movable formwork is moved to the n-th segment following the state shown in FIG. 5.
FIG. 7 is a schematic excerpt perspective view of the circle C portion of FIG. 6. FIG.
FIG. 8 is a schematic side view illustrating a state in which a formwork for manufacturing the n + 1th segment is installed at the same time as the support cable is connected to the nth segment subsequent to the state shown in FIG. 6.
FIG. 9 is a schematic side view illustrating a state in which an n + 1 segment is manufactured following the state shown in FIG. 8.

이하, 본 발명의 바람직한 실시예를 첨부한 도면을 참조하여 설명한다. 본 발명은 도면에 도시된 실시예를 참고로 설명되었으나 이는 하나의 실시예로서 설명되는 것이며, 이것에 의해 본 발명의 기술적 사상과 그 핵심 구성 및 작용이 제한되지 않는다. Hereinafter, preferred embodiments of the present invention will be described with reference to the accompanying drawings. Although the present invention has been described with reference to the embodiments shown in the drawings, it is to be understood that the technical idea of the present invention and its essential structure and operation are not limited thereby.

도 5, 도 6, 도 8 내지 도 9는 각각 본 발명에 따라 사장교(斜張橋)의 상부구조물을 FCM에 의해 시공하는 각 단계를 보여주는 개략적인 측면도이다. 도 7은 도 6의 원 C 부분에 대한 개략적인 발췌 사시도이다. 5, 6 and 8 to 9 are schematic side views showing each step of constructing the superstructure of a cable-stayed bridge by FCM according to the present invention, respectively. FIG. 7 is a schematic excerpt perspective view of the circle C portion of FIG. 6. FIG.

도면에 도시된 것처럼, 본 발명에 따른 사장교 시공방법에서는, 교각 위에 구축되는 상부구조물을 소정 길이의 세그먼트로 순차적으로 제작하면서, 각각의 세그먼트에 지지케이블을 연결하고 지지케이블을 긴장하게 되는 FCM을 이용하게 되는데, 도 5 내지 도 9에 도시된 것처럼, 지지케이블을 제n번째 세그먼트에 연결하여 긴장하는 작업을 수행하기 전의 상태에서도 이동식 거푸집설치장치를 제n번째 세그먼트 위로 이동 탑재시켜 제n+1번째 세그먼트의 제작을 개시할 수 있게 된다. 즉, 본 발명에서는 제n번째 세그먼트의 지지케이블 연결/긴장작업이 완료되기 전에 제n번째 세그먼트로의 이동식 거푸집설치장치 이동작업이 이루어지는 것이다. As shown in the figure, in the cable-stayed bridge construction method according to the present invention, while manufacturing the upper structure to be built on the pier sequentially into segments of a predetermined length, using a FCM that connects the support cable to each segment and tension the support cable 5 to 9, the movable formwork is mounted on the nth segment by moving the support cable to the nth segment before the tensioning operation is performed. Production of the segment can be started. That is, in the present invention, before the support cable connection / tensioning operation of the n-th segment is completed, the movable formwork installation apparatus moving operation to the n-th segment is performed.

구체적으로 도 5에 도시된 것처럼, 교량 상부구조물의 제n-2번째 세그먼트(101)와, 그에 연속하는 제n-1번째 세그먼트(102)가 시공된 상태에서, 상기 제n-1번째 세그먼트(102)에 이동식 거푸집설치장치(200)를 이동 탑재한 후, 제n번째 세그먼트(103)의 제작을 위한 거푸집을 상기 제n-1번째 세그먼트(102)의 전방에 설치하고 콘크리트를 타설하여 제n번째 세그먼트(103)를 제작하게 된다. 이동식 거푸집설치장치(200)가 제n-1번째 세그먼트(102)에 설치된다는 것은, 이동식 거푸집설치장치(200)가 제n-1번째 세그먼트(102)의 상면과 제n-2번째 세그먼트(101)의 상면에 걸쳐서 설치되는 상태를 포함하는 것이다. Specifically, as shown in FIG. 5, in the state in which the n-second segment 101 of the bridge superstructure and the n-th segment 102 subsequent thereto are constructed, the n-th segment ( After moving the mobile formwork installation apparatus 200 to 102, the formwork for the manufacture of the n-th segment 103 is installed in front of the n-th segment 102, and the concrete is poured to n-th The second segment 103 is produced. The movable formwork 200 is installed in the n-th segment 102, and the movable formwork 200 is the upper surface of the n-th segment 102 and the n-second segment 101. It is a state including the state installed over the upper surface of).

도 6에는 도 5에 도시된 상태에 후속하여 제n-1번째 세그먼트(102)와 제n번째 세그먼트(103) 사이를 가설 연결조립체(10)에 의해 연결한 후, 이동식 거푸집설치장치(200)를 이동시켜 제n번째 세그먼트(103)의 상부에 이동식 거푸집설치장치(200)가 탑재되어 있는 상태가 도시되어 있는데, 도면에 도시된 것처럼, 본 발명에서는 제n번째 세그먼트(103)의 콘크리트 타설과 양생이 완료되면, 제n-1번째 세그먼트(102)와 제n번째 세그먼트(103)를 가설 연결조립체(10)에 의해 서로 연결시킨 후, 이동식 거푸집설치장치를 이동시켜 제n번째 세그먼트(103) 위에 탑재되도록 한다. In FIG. 6, after the n-th segment 102 and the n-th segment 103 are connected by the temporary connection assembly 10 following the state shown in FIG. 5, the movable formwork apparatus 200 is provided. The state in which the movable formwork mounting apparatus 200 is mounted on the upper part of the n-th segment 103 by moving it is shown. As shown in the drawing, in the present invention, the concrete pouring of the n-th segment 103 is performed. When curing is completed, the n-th segment 102 and the n-th segment 103 are connected to each other by the temporary connection assembly 10, and then the movable formwork is moved to the n-th segment 103. Make sure it is mounted on top.

도 7에는 도 6의 원 C 부분에 대한 개략적인 발췌 사시도가 도시되어 있는데, 상기 가설 연결조립체(10)는 서로 이웃하는 세그먼트의 상면에 각각 고정되는 한 쌍의 고정장치(11)와, 상기 한 쌍의 고정장치(11) 사이에 교축방향으로 배치되어 상기 한 쌍의 고정장치(11)를 서로 연결하는 종방향 연결부재(12)로 이루어진다. 즉, 도면에 도시된 것처럼, 제n-1번째 세그먼트(102)와 제n번째 세그먼트(103) 간의 관계에서, 고정장치(11) 각각은 제n-1번째 세그먼트(102)의 상면과 제n번째 세그먼트(103)에 각각 결합 설치된다. 추후 상기 가설 연결조립체(10)는 세그먼트로부터 분해되어 전방의 세그먼트로 이동 설치될 수 있으므로, 고정장치(11)는 세그먼트의 상면에 분해가 가능한 형태로 설치된다. 예를 들면, 볼트 등의 분해가능한 체결부재에 의해 상기 고정장치(11)가 세그먼트의 상면에 결합 설치될 수 있는 것이다. FIG. 7 shows a schematic perspective view of the circle C portion of FIG. 6, wherein the hypothetical connection assembly 10 includes a pair of fixing devices 11 fixed to the upper surfaces of adjacent segments, respectively, It is composed of a longitudinal connecting member 12 disposed in the axial direction between the pair of fixing devices 11 to connect the pair of fixing devices 11 to each other. That is, as shown in the figure, in the relationship between the n-th segment 102 and the n-th segment 103, each of the fixing devices 11 is the top surface of the n-th segment 102 and the n-th segment. The coupling is installed in the first segment 103, respectively. Since the hypothetical connection assembly 10 can be disassembled from the segment and moved to the front segment, the fixing device 11 is installed in a form that can be disassembled on the upper surface of the segment. For example, the fixing device 11 may be coupled to the upper surface of the segment by a detachable fastening member such as a bolt.

상기 한 쌍의 고정장치(11) 사이에는 종방향 연결부재(12)가 배치되어 상기 종방향 연결부재(11)의 양단은 각각 한 쌍의 고정장치(11) 각각에 결합된다. 상기 종방향 연결부재(11)는 강봉 등의 부재로 이루어질 수도 있지만, 텐던과 같이 긴장력을 부여할 수 있는 부재로 이루어지는 것도 바람직하다. 도 7에는 하나의 가설 연결조립체(10)만이 설치되어 있는 것으로 도시되어 있으나, 교폭방향으로 복수개의 가설 연결조립체(10)가 나란하게 배치될 수도 있다. A longitudinal connecting member 12 is disposed between the pair of fixing devices 11 so that both ends of the longitudinal connecting member 11 are coupled to each of the pair of fixing devices 11. The longitudinal connecting member 11 may be made of a member such as a steel bar, but also preferably made of a member capable of imparting a tension force such as tendon. Although only one hypothetical connection assembly 10 is illustrated in FIG. 7, a plurality of hypothetical connection assemblies 10 may be arranged side by side in the crosswise direction.

이와 같이 제n번째 세그먼트(103)가 제작되고, 제n-1번째 세그먼트(102)와 제n번째 세그먼트(103) 사이에 가설 연결조립체(10)가 설치되면, 제n번째 세그먼트(102)는 지지케이블(300)의 연결 없이도, 이동식 거푸집설치장치(200)의 탑재 하중을 지지할 수 있는 상태가 된다. 즉, 제n번째 세그먼트(103)에 가해지는 하중은 가설 연결조립체(10)에 의해 제n-1번째 세그먼트(102)로 전달되어 지지되는 것이다. In this way, when the n-th segment 103 is manufactured and the temporary connection assembly 10 is installed between the n-th segment 102 and the n-th segment 103, the n-th segment 102 is formed. Even without connection of the support cable 300, it becomes a state which can support the load of the movable formwork installation apparatus 200. FIG. That is, the load applied to the n-th segment 103 is transmitted to and supported by the n-th segment 102 by the temporary connection assembly 10.

따라서 도 6 및 도 8에 도시된 것처럼, 아직 제n번째 세그먼트(103)가 완전하게 지지케이블(300)에 매달려 지지되지 아니한 상태일지라도, 이동식 거푸집설치장치(200)를 이동시켜 제n번째 세그먼트(103)의 상부에 이동식 거푸집설치장치(200)를 탑재할 수 있게 되며, 제n번째 세그먼트(103)에 탑재된 이동식 거푸집설치장치(200)를 이용하여 제n번째 세그먼트(103)의 전방으로 제n+1번째 세그먼트(104)를 위한 거푸집(210)을 설치할 수 있게 된다. 즉, 이동식 거푸집설치장치(200)를 제n번째 세그먼트(103)로 이동시키는 작업이 완료된 상태이므로, 아직 제n번째 세그먼트(103)이 지지케이블(300)에 의해 지지되지 아니한 상태일지라도, 이동식 거푸집설치장치(200)를 이용하여 제n번째 세그먼트(103)의 전방으로 제n+1번째 세그먼트(104)를 위한 거푸집(210)을 설치할 수 있게 되는 것이다. Therefore, as shown in FIGS. 6 and 8, even when the n-th segment 103 is not completely supported by the support cable 300, the movable formwork 200 is moved to move the n-th segment ( The movable formwork apparatus 200 may be mounted on the upper portion of the 103, and the movable formwork apparatus 200 mounted on the nth segment 103 may be mounted in front of the nth segment 103. Formwork 210 for the n + 1 th segment 104 can be installed. That is, since the operation to move the movable formwork 200 to the n-th segment 103 is completed, even if the n-th segment 103 is not yet supported by the support cable 300, the movable formwork By using the installation device 200 it is possible to install the formwork 210 for the n + 1 st segment 104 in front of the n-th segment (103).

한편, 본 발명에서는 이와 같이 이동식 거푸집설치장치(200)의 이동이 완료된 후에는, 새로운 거푸집 설치 작업을 수행과 병행하여 제n번째 세그먼트(103)에 지지케이블(300)을 연결하여 긴장하는 작업을 수행할 수 있게 된다. 즉, 제n번째 세그먼트(103)의 전방으로 제n+1번째 세그먼트(104)를 위한 거푸집(210)을 설치하는 작업과 병행하여, 제n번째 세그먼트(103)에 지지케이블(300)을 연결하여 긴장하는 작업을 수행할 수 있는 것이다. On the other hand, in the present invention, after the movement of the movable formwork installation apparatus 200 is completed in this way, in parallel with performing a new formwork installation work to connect the support cable 300 to the n-th segment 103 to tension the work It can be done. That is, the support cable 300 is connected to the nth segment 103 in parallel with the work of installing the formwork 210 for the n + 1th segment 104 in front of the nth segment 103. To work nervously.

앞서 종래기술과 관련하여 살펴본 것처럼, 세그먼트에 지지케이블을 연결하고 지지케이블을 긴장하는 작업에는 상당한 시간이 소요된다. 종래에는 이와 같이 오랜 시간이 소요되는 세그먼트에 지지케이블을 연결하는 작업과 지지케이블을 긴장하는 작업이 모두 완료되어야만 이동식 거푸집설치장치(200)를 이동시켜서 새로운 세그먼트 제작을 위한 거푸집을 설치할 수 있었지만, 본 발명에서는 이동식 거푸집설치장치(200)를 이동시킨 후에, 지지케이블의 연결 및 긴장 작업이 이루어지므로, 지지케이블의 연결 및 긴장 작업이 진행되는 동안에, 이동식 거푸집설치장치(200)를 이용하여 새로운 세그먼트 제작을 위한 거푸집을 설치하는 작업을 병행하여 수행할 수 있게 된다. 즉, 본 발명에서는 제n번째 세그먼트(103)의 제작이 완료되면, 지지케이블(300)을 제n번째 세그먼트(103)에 연결하여 긴장하는 작업이 완료되기 전의 상태에서도, 제n번째 세그먼트(103)로 이동 탑재된 이동식 거푸집설치장치(200)를 이용하여 제n+1번째 세그먼트(104)의 제작을 개시할 수 있게 되므로, 사장교의 상부구조물 구축에 소요되는 공기를 크게 단축시킬 수 있게 되는 것이다. As discussed above in connection with the prior art, the work of connecting the support cable to the segment and tensioning the support cable takes considerable time. In the related art, only when the work connecting the support cable to the segment that takes a long time and the work for tensioning the support cable are completed, the formwork for manufacturing a new segment can be installed by moving the movable formwork installation apparatus 200. In the present invention, after moving the movable formwork device 200, the connection and tension work of the support cable is made, while the connection and tension work of the support cable, a new segment production using the movable formwork device (200) Installation of the formwork for the work can be done in parallel. That is, in the present invention, when the manufacturing of the n-th segment 103 is completed, the n-th segment 103 is connected even if the support cable 300 is connected to the n-th segment 103 before the tensioning operation is completed. It is possible to start the manufacture of the n + 1 st segment 104 by using the movable formwork mounting device 200 mounted on the move, it will be able to significantly shorten the air required to build the upper structure of the cable-stayed bridge .

제n+1번째 세그먼트(104)를 위한 거푸집(210)이 설치되면, 도 9에 도시된 것처럼, 제n+1번째 세그먼트(104)를 위한 콘크리트를 거푸집(210)에 타설하여 제n번째 세그먼트(103)의 전방으로 제n+1번째 세그먼트(104)를 일체로 제작하여 시공하게 된다. 제n+1번째 세그먼트(104)의 제작이 완료되면, 제n째 세그먼트(103)와 제n+1번째 세그먼트(104) 사이에 앞서 설명한 것처럼, 가설 연결조립체(10)를 설치하고 도 6, 도 8 및 도 9에 도시된 과정을 반복하여 상부구조물을 구축함으로써 사장교를 시공하게 된다. 제n째 세그먼트(103)와 제n+1번째 세그먼트(104) 사이에 가설 연결조립체(10)를 설치할 때에는, 제n-1째 세그먼트(102)와 제n번째 세그먼트(103) 사이에 설치되어 있던 가설 연결조립체(10)를 철거하여 다시 사용하는 것이 바람직하다. When the formwork 210 for the n + 1th segment 104 is installed, as shown in FIG. 9, concrete for the n + 1th segment 104 is poured into the formwork 210 to form the nth segment. In front of the 103, the n + 1th segment 104 is integrally manufactured and constructed. When the fabrication of the n + 1th segment 104 is completed, as described above, the hypothetical coupling assembly 10 is installed between the nth segment 103 and the n + 1th segment 104, and the FIG. By constructing the upper structure by repeating the process shown in Figures 8 and 9 to build a cable-stayed bridge. When installing the temporary connection assembly 10 between the nth segment 103 and the n + 1th segment 104, it is provided between the n-1st segment 102 and the nth segment 103. It is preferable to remove the temporary connection assembly 10 that was present and use it again.

참고로 본 명세서에서 이동식 거푸집설치장치(200)는 단순히 거푸집만을 설치하는 장치를 의미하는 것이 아니라, 거푸집을 설치하고 콘크리트를 타설하여 세그먼트를 제작하는 장치를 의미하는 것으로 이해되어야 한다. For reference, in the present specification, the movable formwork installation apparatus 200 is not merely meant to install only the formwork, but should be understood to mean a device for manufacturing segments by installing formwork and placing concrete.

10: 가설 연결조립체
200: 이동식 거푸집설치장치
300: 지지케이블
10: Hypothetical Connection Assembly
200: movable formwork installation device
300: support cable

Claims (2)

제n-1번째 세그먼트(102)에 이웃하여 제n번째 세그먼트(103)를 연속하여 설치하고, 후속하여 제n+1번째 세그먼트(104)를 연속 설치하여 복수개의 세그먼트를 순차적으로 제작하여 연속 설치하면서, 각각의 세그먼트에 지지케이블을 연결하고 지지케이블을 긴장함으로서 교각 위에 상부구조물을 구축하는 사장교의 시공방법으로서,
상기 제n-1번째 세그먼트(102)에 이동식 거푸집설치장치(200)를 설치하여 제n번째 세그먼트(103)의 제작을 위한 거푸집을 상기 제n-1번째 세그먼트(102)의 전방에 설치하고 콘크리트를 타설하여 제n번째 세그먼트(103)를 제작하는 제1단계;
제n-1번째 세그먼트(102)와 제n번째 세그먼트(103) 사이를 가설 연결조립체(10)에 의해 연결한 후, 상기 제n번째 세그먼트(103)에 지지케이블(300)을 연결하여 긴장하기 전에, 이동식 거푸집설치장치(200)를 이동시켜 제n번째 세그먼트(103)에 이동식 거푸집설치장치(200)가 탑재되도록 하는 작업을 수행하는 제2단계; 및
상기 제n번째 세그먼트(103)에 지지케이블(300)을 연결하여 긴장하는 것과 병행하여, 이미 상기 제n번째 세그먼트(103)로 이동되어 탑재되어 있던 상기 이동식 거푸집설치장치(200)를 이용하여 제n+1번째 세그먼트(104)를 위한 거푸집(210)을 상기 제n번째 세그먼트(103)의 전방에 설치하고 콘크리트를 타설하여 제n+1번째 세그먼트(104)를 제작하는 제3단계를 반복수행하여 상부구조물을 구축하는 것을 특징으로 하는 사장교의 시공방법.
Next, the n-th segment 103 is continuously installed adjacent to the n-th segment 102, and the n + 1th segment 104 is continuously installed, and a plurality of segments are sequentially manufactured and continuously installed. As a construction method of the cable-stayed bridge to connect the support cable to each segment and to build a superstructure on the piers by tensioning the support cable,
The movable formwork installation apparatus 200 is installed on the n-th segment 102 to install the formwork for the manufacture of the n-th segment 103 in front of the n-th segment 102 and the concrete A first step of manufacturing the n-th segment 103 by pouring;
After connecting between the n-th segment 102 and the n-th segment 103 by the temporary connection assembly 10, by connecting the support cable 300 to the n-th segment 103 to tension Before, the second step of moving the movable formwork apparatus 200 to perform the operation to mount the movable formwork apparatus 200 to the n-th segment 103; And
In parallel with the tension by connecting the support cable 300 to the n-th segment 103, the movable formwork apparatus 200, which is already moved and mounted to the n-th segment 103, is used. Repeating the third step of installing the formwork 210 for the n + 1 st segment 104 in front of the n th segment 103 and casting the concrete to produce the n + 1 st segment 104 Construction method of the cable-stayed bridge, characterized in that to build the upper structure.
제1항에 있어서,
상기 가설 연결조립체(10)는,
서로 이웃하는 세그먼트의 상면에 각각 분해 가능하도록 고정되는 한 쌍의 고정장치(11)와,
상기 한 쌍의 고정장치(11) 사이에 교축방향으로 배치되어 상기 한 쌍의 고정장치(11)를 서로 연결하는 종방향 연결부재(12)로 이루어진 것을 특징으로 하는 사장교의 시공방법.
The method of claim 1,
The hypothesis connecting assembly 10,
A pair of fixing devices 11 fixed to the upper surfaces of the segments adjacent to each other,
The construction method of the cable-stayed bridge, characterized in that consisting of a longitudinal connecting member (12) arranged in the axial direction between the pair of fixing devices (11) connecting the pair of fixing devices (11) to each other.
KR1020120047342A 2012-05-04 2012-05-04 Constructing method of cable bridge using free cantilever method KR101184773B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020120047342A KR101184773B1 (en) 2012-05-04 2012-05-04 Constructing method of cable bridge using free cantilever method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020120047342A KR101184773B1 (en) 2012-05-04 2012-05-04 Constructing method of cable bridge using free cantilever method

Publications (1)

Publication Number Publication Date
KR101184773B1 true KR101184773B1 (en) 2012-09-20

Family

ID=47113933

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020120047342A KR101184773B1 (en) 2012-05-04 2012-05-04 Constructing method of cable bridge using free cantilever method

Country Status (1)

Country Link
KR (1) KR101184773B1 (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103132455A (en) * 2013-03-12 2013-06-05 中铁四局集团第二工程有限公司 Three-dimensional combined type cable-stayed bridge body cable duct accurate positioning device and positioning method
CN103741606A (en) * 2013-12-31 2014-04-23 中铁大桥局股份有限公司 Soft traction device rapid cable replacement construction method
CN104652245A (en) * 2014-11-05 2015-05-27 上海市政工程设计研究总院(集团)有限公司 Longitudinal constraint method for cable-stayed bridges
CN105317008A (en) * 2015-09-08 2016-02-10 贵州省公路工程集团有限公司 An overall lifting transport method of steel truss girder sections of a steel truss girder cable-stayed bridge
KR20170014821A (en) 2015-07-31 2017-02-08 대림산업 주식회사 Cable-Stayed Bridge having Precast Core, and Constructing Method thereof
CN106758841A (en) * 2016-12-29 2017-05-31 中交第三航务工程局有限公司 A kind of whole construction process of the double rope face low-pylon cable-stayed bridges of double tower
CN111155441A (en) * 2020-01-21 2020-05-15 浙江交工金筑交通建设有限公司 Bridge construction method and external beam device
CN111254803A (en) * 2020-01-22 2020-06-09 中铁大桥科学研究院有限公司 Cable-free area linear control method for three-span continuous steel box girder suspension bridge
CN112069583A (en) * 2020-09-08 2020-12-11 中国十七冶集团有限公司 Oblique cantilever safe and intelligent construction system and method for finite element synchronous analysis
CN114541240A (en) * 2022-02-14 2022-05-27 中铁十一局集团第一工程有限公司 Reinforcing construction method and device for large-section high web end formwork of cantilever beam

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5185239A (en) 1974-03-22 1976-07-26 Dyckerhoff & Widmann Ag
JPS56135124A (en) 1980-03-26 1981-10-22 Kubota Ltd Indication fixing device

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5185239A (en) 1974-03-22 1976-07-26 Dyckerhoff & Widmann Ag
JPS56135124A (en) 1980-03-26 1981-10-22 Kubota Ltd Indication fixing device

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103132455B (en) * 2013-03-12 2015-06-10 中铁四局集团第二工程有限公司 Three-dimensional combined type cable-stayed bridge body cable duct accurate positioning device and positioning method
CN103132455A (en) * 2013-03-12 2013-06-05 中铁四局集团第二工程有限公司 Three-dimensional combined type cable-stayed bridge body cable duct accurate positioning device and positioning method
CN103741606B (en) * 2013-12-31 2016-10-05 中铁大桥局集团有限公司 The construction method of soft pulling equipment fast quick change rope
CN103741606A (en) * 2013-12-31 2014-04-23 中铁大桥局股份有限公司 Soft traction device rapid cable replacement construction method
CN104652245A (en) * 2014-11-05 2015-05-27 上海市政工程设计研究总院(集团)有限公司 Longitudinal constraint method for cable-stayed bridges
KR20170014821A (en) 2015-07-31 2017-02-08 대림산업 주식회사 Cable-Stayed Bridge having Precast Core, and Constructing Method thereof
CN105317008A (en) * 2015-09-08 2016-02-10 贵州省公路工程集团有限公司 An overall lifting transport method of steel truss girder sections of a steel truss girder cable-stayed bridge
CN105317008B (en) * 2015-09-08 2018-06-29 贵州省公路工程集团有限公司 A kind of Integral lifting method of steel truss girder cable-stayed bridge steel truss girder segment
CN106758841A (en) * 2016-12-29 2017-05-31 中交第三航务工程局有限公司 A kind of whole construction process of the double rope face low-pylon cable-stayed bridges of double tower
CN111155441A (en) * 2020-01-21 2020-05-15 浙江交工金筑交通建设有限公司 Bridge construction method and external beam device
CN111254803A (en) * 2020-01-22 2020-06-09 中铁大桥科学研究院有限公司 Cable-free area linear control method for three-span continuous steel box girder suspension bridge
CN112069583A (en) * 2020-09-08 2020-12-11 中国十七冶集团有限公司 Oblique cantilever safe and intelligent construction system and method for finite element synchronous analysis
CN112069583B (en) * 2020-09-08 2023-10-20 中国十七冶集团有限公司 Finite element synchronous analysis inclined cantilever safe intelligent construction system and method
CN114541240A (en) * 2022-02-14 2022-05-27 中铁十一局集团第一工程有限公司 Reinforcing construction method and device for large-section high web end formwork of cantilever beam
CN114541240B (en) * 2022-02-14 2024-06-04 中铁十一局集团第一工程有限公司 Reinforcing construction method and device for large-section high-web end template of cantilever beam

Similar Documents

Publication Publication Date Title
KR101184773B1 (en) Constructing method of cable bridge using free cantilever method
JP5409178B2 (en) Construction method of concrete bridge and moving work apparatus used in the construction method
JP4777319B2 (en) Bridge erection method
KR100719959B1 (en) Structure reinforcing apparatus and method using stressing apparatus for structure reinforcement
KR101826119B1 (en) Cable-Stayed Bridge having Precast Core, and Constructing Method thereof
JP4937838B2 (en) How to build a bridge
WO2018052030A1 (en) Bridge construction method
JP2017071964A (en) Construction method of cable-stayed bridge
KR20150144384A (en) Form traveler and construction method for fcm bridge using the same
JP6509096B2 (en) Extension method
JP5693869B2 (en) Bridge girder construction method
KR101339367B1 (en) Fabrication and reinforcing method for pre-flex girder
KR20160029277A (en) Construction Method to Create Multi-span Continuity in PSC Bridges
KR20130120096A (en) Girder bridge for pre-tention
KR20150083446A (en) Construction methods for bridges of rahmen types by using precast P.S girder and steel box girder
KR20130090455A (en) Construction method for continuous bridge using confined concrete
KR101245620B1 (en) Incremental launching method using temporary binder
JP2014080823A (en) Spc girder bridge structure
KR100616533B1 (en) Construction method for p.s.c. girder bridges and bridges production it
KR101268375B1 (en) Construction method for bridge using temporary binder
KR20100133653A (en) Tension frame for manufactyring prestressed concrete beam girder of pretension type, and method for installing tendons using tension frame
KR101232706B1 (en) Block supporting inner form and rail used in movable scaffolding system
KR20130020497A (en) Consturuction method for composite girder
CN205223866U (en) A vertical prestressed pipe hoisting device for high mound slip form construction
KR101568846B1 (en) bridge upper-structure equipped with end pylons

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20150821

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20170726

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20180703

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20190704

Year of fee payment: 8