KR101124514B1 - Scaffolding girder introducing prestress using a device generating tension in steel wire and prestress introducing method thereof - Google Patents

Scaffolding girder introducing prestress using a device generating tension in steel wire and prestress introducing method thereof Download PDF

Info

Publication number
KR101124514B1
KR101124514B1 KR1020090033674A KR20090033674A KR101124514B1 KR 101124514 B1 KR101124514 B1 KR 101124514B1 KR 1020090033674 A KR1020090033674 A KR 1020090033674A KR 20090033674 A KR20090033674 A KR 20090033674A KR 101124514 B1 KR101124514 B1 KR 101124514B1
Authority
KR
South Korea
Prior art keywords
steel
girder
steel wire
prestress
temporary
Prior art date
Application number
KR1020090033674A
Other languages
Korean (ko)
Other versions
KR20100115119A (en
Inventor
홍석희
박재홍
Original Assignee
홍석희
주식회사 케이알티씨
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 홍석희, 주식회사 케이알티씨 filed Critical 홍석희
Priority to KR1020090033674A priority Critical patent/KR101124514B1/en
Publication of KR20100115119A publication Critical patent/KR20100115119A/en
Application granted granted Critical
Publication of KR101124514B1 publication Critical patent/KR101124514B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/04Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal
    • E04C3/10Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal prestressed
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/08Members specially adapted to be used in prestressed constructions
    • E04C5/12Anchoring devices
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/16Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/02Bridges characterised by the cross-section of their bearing spanning structure of the I-girder type
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/04Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal
    • E04C2003/0404Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal beams, girders, or joists characterised by cross-sectional aspects
    • E04C2003/0443Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of metal beams, girders, or joists characterised by cross-sectional aspects characterised by substantial shape of the cross-section
    • E04C2003/0452H- or I-shaped

Abstract

본 발명은 가시설 흙막이등의 가시설구조체의 가시설거더에 프리스트레스를 도입하는 방법에 관한 것이다.The present invention relates to a method for introducing prestress into a temporary girder of a temporary structural structure such as a temporary retainer.

즉, 가시설구조체의 흙막이용 프리스트레스트가시설거더의 양단에 스트로크발생장치를 설치하고, 상기 스트로크발생장치가 설치된 외측의 압력조절강재의 측면에 정착구를 설치하고, 상기 가시설거더의 전면에 한 개이상의 하중전달재를 설치하여 하중전달재에 강선이 접하게 설치하면서 강선의 양단이 상기 정착구에 정착되도록 한 다음, 스트로크발생장치로 스트로크를 발생시켜 압력조절강재가 외측으로 밀리면서 강선이 신장되고 상기 스트로크를 고정시키면 강선에 프리스트레스힘이 도입되므로서 하중전달재에 강선의 장력이 전달되어 가시설거더에 프리스트레스가 도입되도록 하거나,      That is, a stroke generating device is installed at both ends of the prestressed temporary girders for the temporary wall of the temporary structural body, and a fixing unit is provided on the side of the pressure regulating steel outside the stroke generating device, and at least one front of the temporary girder is provided. Install a load transfer material so that the steel wires are in contact with the load transfer material so that both ends of the steel wire are settled in the anchorage. Then, a stroke is generated by a stroke generating device so that the pressure regulating steel is pushed outward and the steel wire is extended and the stroke is moved. When fixed, the prestressing force is introduced to the steel wire, and the tension of the steel wire is transmitted to the load transfer material so that the prestress is introduced to the temporary girders.

또는 가시설거더의 전면에 하중전달재를 복수개 설치하면서 강선이 접하게 설치하면서 양단에 설치된 정착구에 정착되도록 하고, 상기 복수의 하중전달재 사이에 설치된 버팀대띠장사이에 스트로크발생장치를 설치하여 스트로크를 발생시키면, 버팀대띠장이 외측으로 밀리면서 하중전달재가 수직으로 되도록 하여 강선의 길이를 신장시키거나, 내측과 외측의 하중전달재에 정착장치를 각각 설치하고, 스트로크강선으로 상호 연결하거나, 하중전달재를 서로 스트로크강선으로 연결하여 정착구로 정착하고, 일측단의 스트로크강선을 각각 긴장하여 하중전달재가 수직으로 서도록 하므로서, 하중전달재에 접하게 설치된 강선이 신장되게 된 다음, 강선 신장을 멈추고 스트로크를 고정시키면 강선에 프리스트레스힘으로 작용케되고, 상기 도입된 장력이 가시설거더에 도입되도록 한 것이거나,Alternatively, when a plurality of load transfer materials are installed on the front of the temporary girder, the steel wires are installed in contact with each other to be fixed to the anchorages installed at both ends, and a stroke generating device is installed between the brace belts installed between the plurality of load transfer materials to generate a stroke. The length of the steel wire by extending the load transfer material vertically as the brace belt is pushed outwards, or by installing the fixing device on the inner and outer load transfer material, interconnecting each other with the stroke steel, or connecting the load transfer material to each other. Connected with stroke steel, settle with anchorage, and tension the steel wire at one end so that the load transfer material stands vertically, so that the steel wire installed in contact with the load transfer material is stretched, and then stop the extension of the steel wire and fix the stroke. Acts as a prestress force and the introduced tension It was to be introduced in gasiseol or girder,

또는 변단면에 설치되는 가시설구조체에 흙막이용 프리스트레스트가시설거더를 설치하고 그 외측에 변단면에 설치된 띠장과의 사이에 중간버팀대를 설치하고, 상기 가시설거더의 전면에 복수개 이상의 하중전달재를 설치하고, 강선으로 접하게 설치하면서 단부가 양측의 가시설거더에 정착구에 의하여 정착되도록 한 다음, 사이 가시설거더의 양단에 설치된 스트로크발생장치에 의하여 발생된 스트로크에 의하여 프리스트레스가 상기 가시설거더에 도입되도록 하고, 상기 도입된 프리스트레스가 다시 중간버팀대에 전달되어 변단면에 설치된 가시설거더에 작용하는 외력을 상쇄되도록 한 강선에 장력을 도입하는 다양한 방법에 의하여 가시설거더에 프리스트레스를 도입하는 가시설구조체에 관한 것이다.Alternatively, install a prestressed temporary girders for the retaining wall on the temporary structure installed on the side of the interfacial section, install an intermediate brace between the bands installed on the side of the interfacial surface, and install a plurality of load transfer materials on the front of the temporary girder. The end is fixed to the temporary girder by both anchors while being installed in contact with the steel wire, and then the prestress is introduced into the temporary girder by the stroke generated by the stroke generating devices installed at both ends of the temporary girder. The prestress is introduced to the intermediate brace again to relieve the external force acting on the girder installed on the side of the sectional structure relates to a temporary structure to introduce the prestress to the girder by a variety of ways to introduce tension.

Description

강선에 신장력을 발생시키는 장치를 이용하여 프리스트레스를 도입한 흙막이용 가시설거더 및 이의 프리스트레스 도입방법 {Scaffolding girder introducing prestress using a device generating tension in steel wire and prestress introducing method thereof}{Scaffolding girder introducing prestress using a device generating tension in steel wire and prestress introducing method}

본 발명은 본체 구조물을 설치하기 위하여 지반을 굴착할 때, 직선부 및 변단면부 굴착주위의 토사가 붕괴되는 것을 방지하면서, 동시에 본체 구조물의 지하 설치를 위한 작업공간을 확보하기 위하여 설치한 가시설 흙막이구조의 띠장거더이거나, 본체 구조물의 설치를 위한 콘크리트타설하중을 지지하기 위하여 설치한 가시설동바리이거나, 또는 가설교량을 지지하는 거더등의 상기 모든 가시설구조체에 설치된 거더를 종합한 가시설거더를 지지하는 버팀대의 간격을 넓히고자 할때에 상기 가시설거더에 작용하는 외력에 의한 응력을 상쇄하기 위하여 가시설거더에 프리스트레스가 도입되도록 가시설거더상에 설치된 강선을 신장하여 프리스트레스힘이 작용하도록 하는 방법에 관한 것이거나, The present invention, when excavating the ground in order to install the main body structure, while preventing the earth and sand around the excavation of the straight portion and the cross-section portion, while at the same time installed to secure a work space for underground installation of the main body structure Supports for supporting temporary girder combined with girder installed in all the above-mentioned temporary structural structures, such as girders of structural structures, temporary bridges installed to support concrete placing loads for the installation of main structures, or girders supporting temporary bridges. In order to offset the stress caused by the external force acting on the temporary girder in order to widen the interval of the present invention, the prestressing force is applied by extending the steel wire installed on the temporary girder so that the prestress is applied.

또는, 가시설흙막이벽이 변단면으로 버팀대 설치가 곤란할 경우, 가시설거더에 프리스트레스를 도입하여 버팀대의 간격을 최대한 넓혀지도록 하면서, 상기 가 시설거더와 변단면의 가시설흙막이 사이에 중간버팀대를 설치하는 방법에 관한 것이다.Or, if the temporary wall is difficult to install the brace to the edge, it is possible to introduce a pre-stress to the temporary girder to maximize the distance of the brace as possible, while installing the intermediate brace between the temporary girder and the temporary wall of the edge It is about.

종래에는 가시설흙막이나 동바리, 기설교량등을 설치할 때, 거더의 강성이 부족하여 거더에 토압, 자중 및 교통하중이 작용할 때 처짐과 과도한 응력이 발생되는 문제점이 있어, 상기와 같은 문제점을 개선하기 위하여 거더의 전면에 강선을 설치하여 강선에 긴장력을 도입하여 거더에 프리스트레스가 도입되도록 한바, 상기 긴장력 도입방법이 케이블단부에서 유압잭으로 긴장 정착한 후, 정착하는 방법이나, 거더의 중간에 위치한 버팀대의 단부에 케이블이 거치되는 지점에 잭을 삽입하여 케이블을 들어올려 긴장력을 도입하는 방법등이 있으나 긴장정착 장치의 대규모화, 중간 수직재 개수의 증가, 잭 삽입 및 탈착에 따른 개수증가 및 공기 증가등의 문제점이 상존하여 왔다.Conventionally, when installing a temporary soil membrane, copper bar, or existing bridge, there is a problem that deflection and excessive stress occurs when the earth pressure, self-weight and traffic load act on the girder due to insufficient rigidity of the girder. The steel wire is installed on the front of the girder to introduce tension to the steel wire so that prestress is introduced to the girder. The tension introduction method is to settle after tensioning from the cable end to the hydraulic jack, or to settle the end of the brace in the middle of the girder. There is a method of introducing tension by inserting jacks at the point where the cable is mounted on the cable, but there are problems such as the increase of tension fixing device, the increase in the number of intermediate vertical members, the increase in the number of jack insertion and removal, and the increase of air. This has existed.

또한, 변단면부의 굴착부분에 거더를 설치할 때 변단면부가 많아, 변단면마다 설치됨에 따라 그 간격이 좁아 강재량과다사용, 본체구조물의 간섭의 과다로 시공성이 저하되고, 버팀대 설치 위치 선정도 대단히 어려운 단점등이 상존하여 왔다.      In addition, when the girders are installed in the excavated portion of the cross section, the cross section is large, and as it is installed at each cross section, the spacing is narrow, resulting in overuse of steel materials and excessive interference of the body structure, resulting in poor workability. Difficult drawbacks have existed.

본 발명은 상기와 같이 제기된 문제점을 개선하기 위하여 제안된 기술인 것이다.The present invention is a technique proposed to improve the problems posed as above.

본 발명은 양단부에 지압지지강판(33)을 설치한 가시설거더에 프리스트레스를 도입하는 다양한 방법으로 강선을 신장시킨 다음, 일정 위치에 고정하여 장력을 발생시켜, 상기 발생된 장력이 가시설거더에 프리스트레스 힘과 편심모멘트로 도입되도록하여 가시설구조체에 작용하는 외력의 응력과 변형의 반대로 작용하여 상호 상쇄 및 회복하도록 한 가시설거더에 프리스트레스를 도입하는 방법에 관한 것이다.The present invention extends the steel wire by various methods of introducing prestress to the temporary girder girders having the acupressure supporting steel plate 33 at both ends, and then fixed to a predetermined position to generate tension, the generated tension is prestressed force to the temporary girder The present invention relates to a method of introducing prestress into a girder girder which is introduced in an eccentric moment so as to counteract and recover from mutual stress and deformation of an external force acting on the temporary structure.

본 발명은 가시설 흙막이등의 가시설구조체의 가시설거더의 양단부에 별도로 설치된 스트로크발생장치의 유압잭을 이용하여 실린더에 스트로크를 발생시켜, 상기 발생된 스트로크에 의하여 압력조절강재를 외측으로 밀면, 상기 압력조절강재의 측면에 설치된 정착구와 가시설거더의 전면에 설치된 하중전달재에 걸쳐 설치된 강선을 신장시키면서, 상기 스트로크를 설계값만큼 작동시키고, 고정하여 잭을 릴리스하면, 상기 강선에 작용하는 신장값이 긴장력인 프리스트레스힘으로 전환하고, 상기 프리스트레스힘에 의해 가시설거더에는 압축력과 편심모멘트가 작용하여 외력에 의한 응력을 상쇄하도록 하는 매카니즘이거나,The present invention is to generate a stroke in the cylinder by using the hydraulic jack of the stroke generating device provided separately at both ends of the temporary girder of the temporary structural structure, such as temporary sack, push the pressure regulating steel to the outside by the generated stroke, the pressure regulating steel While extending the steel wire installed across the anchorage and the load transfer material installed on the front of the temporary girder, the stroke is operated by the design value, and when the jack is released by fixing, the prestress of tension is applied to the steel wire. A mechanism for converting the force into force and applying a compressive force and an eccentric moment to the temporary girder by the prestress force to cancel the stress caused by the external force;

상기와 같이 강선이 늘어나게 하는 방법과는 다른 방법으로 하중전달재와의 사이에 버팀대띠장을 설치하고, 상기 버팀대띠장의 중앙에 스트로크발생장치를 설치하고, 상기 스트로크발생장치에 유압잭을 삽입구동하여, 스트로크를 발생시키면, 상기 하중전달재가 수직방향으로 세워지면서 강선이 늘어나게 하여 발생된 강선의 긴장력이 프리스트레스힘으로 작용하도록 한 것이거나,As described above, a brace belt is installed between the load-carrying member and a stroke generating device in the center of the brace belt, and a hydraulic jack is inserted into the stroke generating device. When the stroke is generated, the load transfer material is erected in the vertical direction, and the steel wire is stretched so that the tension force of the generated steel wire acts as a prestress force.

또는, 상기 가시설거더의 전면에 설치된 외측의 하중전달재에 고정정착구를 설치하고, 상기 가기설거더의 전면이 일정거리 떨어져 스트로크정착구를 설치하고, 상기 고정정착구와 스트로크정착구의 사이에 스트로크강선을 연결정착하고, 상기 스트로크정착구에 정착된 스트로크강선의 단부를 긴장하면, 경사진 하중전달재가 세워지면서 강선이 늘어나 발생된 강선의 긴장력이 프리스트레스힘으로 작용하도록 한 것이거나,Alternatively, a fixed fixture is installed on an external load transfer member installed on the front side of the temporary girder, a stroke fixture is installed at a predetermined distance away from the front surface of the cut girder, and a stroke steel wire is connected between the fixed fixture and the stroke fixture. When the tension is fixed and the end of the stroke steel wire fixed to the stroke anchoring hole, the inclined load transfer material is erected and the steel wire is extended so that the tension force of the steel wire generated is acted as a prestress force.

또는, 상기 하중전달재의 상단부분에서 상기 하중전달재를 상호 스트로크강선으로 연결하고, 상기 스트로크강선 중간에 설치된 스트로크정착구를 조여, 스트로크강선이 당겨지면, 상기 경사지게 설치된 하중전달재가 세워지면서 강선이 늘어나게 되므로, 상기 가시설거더에 프리스트레스 힘과 편심모멘트가 도입되어 외력의 응력과 변형의 반대로 작용하여 상호 상쇄 및 회복하도록 하여 버팀대 간격을 장경간화하여 강재량의 절감과 본체 구조물 시공시 조밀하게 배치된 버팀대에 의한 간섭으로 인하여 공사가 지연되어 발생된 공사기간 연장 및 본체 구조물의 기능성 저하를 방지함과 동시에 공사기간을 단축함으로서 경제적이면서 효율적인 가시설흙막이등의 가시설구조체의 설치가 가능하도록 한 것이다.Alternatively, the load transfer member is connected to each other by a stroke steel wire at an upper end portion of the load transfer material, and the stroke anchoring hole installed in the middle of the stroke steel wire is tightened, and when the stroke steel wire is pulled, the steel wire is stretched while the inclined load transfer material is raised. Prestressing force and eccentric moment are introduced into the temporary girder to counteract and recover the external force by counteracting the external stresses and deformations. It prevents the extension of construction period caused by the delay due to the interference and the deterioration of the function of the main body structure, and at the same time shortens the construction period, so that it is possible to install the temporary structural structures such as the economical and efficient temporary wall.

상기와 같이 가시설거더에 프리스트레스를 도입하면 띠장, 수직재 및 버팀대 의 설치 개수를 절감할 수 있으며, 작업공간을 보다 넓게 확보할 수 있는 장점이 있다.Introducing prestress to the temporary girder as described above can reduce the number of installation of the girders, vertical members and braces, there is an advantage to secure a wider working space.

본 발명은 직선부 및 변단면에 설치된 가시설흙막이등의 가시설구조체의 가시설거더에 유압잭을 이용하여 프리스트레스를 도입하거나, 하중전달재에 설치된 강선에 장력을 도입하여 하중전달재가 수직으로 서지면서 강선이 신장되도록 하여 가시설거더에 프리스트레스를 도입하도록 한 것으로서, 수직파일, 띠장 및 버팀대의 설치개수를 감소시켜 강재사용량을 감소하면서 작업공간을 보다 넓게 확보할 수 있도록 한 것으로서, 이러한 장점에 의하여 공사기간의 단축과 공사비의 절감을 가져 올 수 있도록 한 것이다.The present invention is to introduce a pre-stress by using a hydraulic jack to the temporary girder of the temporary structural structure, such as the temporary construction mud wall installed on the straight portion and the end surface, or by introducing a tension to the steel wire installed in the load transfer material while the load transfer material standing vertically The prestress is introduced to the temporary girder to reduce the number of vertical piles, strips and braces, thereby reducing the steel usage and ensuring more work space. The cost of construction will be reduced.

이하, 본 발명의 구성과 작용을 첨부된 도면에 의하여 상세히 설명하면 다음과 같다.Hereinafter, the configuration and operation of the present invention will be described in detail by the accompanying drawings.

도 1은 본 발명의 흙막이용 프리스트레스트가시설거더의 양측에 스트로크발생장치를 설치하고 그 외측에 압력조절강재에 정착구를 설치하고 상기 가시설거더의 전면에 하중전달재를 설치하고 양측에 설치된 정착구에 강선을 설치하면서 하중전달재에 접하게 설치하여 상기 스트로크발생장치의 잭으로 밀면 강선이 신장되어 그 반력으로 가시설거더에 프리스트레스가 도입되도록 한 가시설흙막이등의 가시설구조체를 설치한 것을 보여주는 도면이며, 도 2는 본 발명의 스트로크발생장치와 강선이 정착구에 의하여 연결된 상태를 보여주는 도면이며, 도 3(a)(b)는 본 발명의 스트로크발생장치의 돌출강관 및 돌출채널과 볼트너트의 결합관계를 보여주는 도면이며, 도 4(a)는 본 발명의 강선가이드장치를 상세히 보여주는 도면이며, 도 4(b)는 본 발명의 강선가이드장치의 또 다른 실시예를 보여주는 도면이며, 도 5는 본 발명의 흙막이용 프리스트레스트가시설거더를 이중으로 설치한 것을 보여주는 도면이며, 도 6은 본 발명의 흙막이용 프리스트레스가시설거더에 프리스트레스를 도입하는 방법으로서, 흙막이용 프리스트레스트가시설거더의 양단에 정착구를 설치하고, 상기 가시설거더의 전면에 설치된 복수의 하중전달재사이에 버팀대띠장을 설치하고, 상기 버팀대띠장 중앙부에 스트로크발생장치를 설치하고, 상기 하중전달재에 강선이 접하게 설치하면서 양측의 정착구에 강선을 정착하고, 상기 스트로크발생장치에 스트로크를 발생시켜 하중전달재가 수직으로 세워지도록 하면, 강선이 신장되어 강선에 프리스트레스힘으로 전환시켜 프리스트레스가 가시설거더에 도입되도록 한 가시설흙막이등의 가시설구조체를 설치한 것을 보여주는 도면이며, 도 7은 본 발명의 흙막이용 프리스트레스트가시설거더에 프리스트레스를 도입하는 다른 방법으로서, 흙막이용 프리스트레스가시설거더의 양단에 정착구를 설치하고, 상기 가시설거더의 전면에 설치된 복수이상의 하중전달재를 설치하고, 상기 양단의 정착구와 하중전달재 단부에 강선을 설치하고, 최외측의 하중전달재에 고정정착구를 설치하고, 거더의 하부에 스트로크정착구를 설치하면서 강선을 연결하고, 상기 스트로크정착구에 정착된 강선의 단부를 긴장하여 하중전달재가 수직으로 세워지도록 하여 강선이 신장되도록 하고, 상기 발생된 강선의 신장력이 프리스트레스힘으로 전환시켜 프리스트레스가 가시설거더에 도입되도록 한 가시설구조체를 설치한 것을 보여주는 도면이며, 도 8은 본 발명의 프리스트레스트가시설거더에 프리스트레스를 도입하는 또 다른 방법으로서, 흙막이용 프리스트레스가시설거더의 양단에 정착구를 설치하고, 상기 가시설거더의 전면에 복수의 하중전달재를 설치하고, 상기 양단의 정착구와 하중전달재 단부에 강선을 설치하고, 상기 하중전달재에 스트로크정착구를 설치하면서 강선을 연결하고, 상기 일측에 설치된 스트로크정착구에 정착된 강선의 단부를 긴장하여, 하중전달재를 수직으로 세워지도록 하여 강선이 신장되도록 하고, 상기 강선에 발생된 신장력이 프리스트레스힘으로 전환시켜 프리스트레스가 가시설거더에 도입되도록 한 가시설구조체를 설치한 것을 보여주는 도면이며, 도 9(a)(b)는 흙막이용 프리스트레스트가시설거더의 측면에 정착구가 설치된 정착브라켓을 양측에 설치하고 강선을 연결하고, 상기 정착브라켓과 접하게 설치하되, 상기 흙막이용 프리스트레스트가시설거더의 플랜지에 접하게 설치된 버팀대띠장의 중앙에 유압잭을 설치하여 프리스트레스를 도입하는 것을 보여주는 것으로서, 외력이 클 경우 타이탄성클립으로 플랜지를 밀착시키도록 한 것을 보여주는 도면이며, 도 10은 변단면에 설치된 띠장과 흙막이용 프리스트레스트가시설거더와의 사이에 중간버팀대를 설치하고, 상기 가시설거더의 양단부에 스트로크발생장치를 설치하고 그 외측에 압력조절장치를 설치하고, 상기 가시설거더의 전면에 복수이상의 하중전달재를 설치하면서 강선을 단부에 접하게 설치하면서 상기 압력조절장치에 설치된 정착구에 강선을 정착한 다음, 스트로크발생장치에 스트로크를 발생시켜 강선이 신장한 다음, 고정시키면 상기 신장력이 프리스트레스힘으로 전환되어 가시설거더에 전달되고, 상기 가시설거더에 전달된 프리스트레스힘이 중간버팀대에 전달되어 변단면에서 발생되는 외압에 저항 및 상쇄되도록 한 변단면가시설흙막이인 변단면가시설구조체를 설치한 것을 보여주는 도면이며, 도 11은 흙막이용 프리스트레스트가시설거더와의 사이에 일반적인 띠장을 설치하여 간격을 보다 넓게 확보하면서 버팀대와 상기 띠장의 양단에 설치된 가시설거더를 상호 연결하여 버팀대와 가시설연결부를 설치한 것을 보여주는 도면이며, 도 12는 흙막이용 프리스트레스트가시설거더와의 사이에 한 개의 버팀대로 지지하도록 한 것을 보여주는 도면이며, 도 13은 흙막이용 프리스트레스트가시설거더의 측면에서 각각 버팀대로 지지하되, 상기 버팀대사이에 중간파일을 설치하여 버팀대가 좌굴되는 현상을 방지하도록 한 것을 보여주는 도면이며, 도 14는 상기 도 1과 같은 흙막이용 프리스트레스트가시설거더의 외측에서 가시설구조체를 보호하기 위한 충돌방호책을 설치한 것을 보여주는 도면이며, 도 15(a)(b)는 도 6, 도 7 및 도 8과 같은 흙막이용 프리스트레스트가시설거더의 전면에 플랜지에 설치된 하중전달재가 스트로크발생장치에 의하여 거동시 하중전달재가 수직으로 세워지면서 모멘트 발생을 방지하기 위하여 슬라이딩볼트결합을 측면과 평면에서 보여주는 도면이다.Figure 1 is installed on both sides of the prestressed girders for earthenware of the present invention and installed on the outside of the pressure regulating steel on the outside of the anchoring device and the load transfer material on the front of the girder girders installed on both sides of the anchorage When the steel wire is installed in contact with the load transfer material and pushed to the jack of the stroke generating device, the steel wire is elongated, and the drawing shows the installation of a temporary structure such as a temporary scaffold such that prestress is introduced into the temporary girder by the reaction force. 3 is a view showing a state in which the stroke generating device and the steel wire of the present invention is connected by the anchorage, Figure 3 (a) (b) is a view showing a coupling relationship of the projecting steel pipe and the protruding channel and the bolt nut of the stroke generating device of the present invention 4 (a) is a view showing in detail the wire guide device of the present invention, Figure 4 (b) is a steel of the present invention Figure 5 is a view showing another embodiment of the guide device, Figure 5 is a view showing a double girder prestress facility girder of the present invention, Figure 6 is a pre-stressed girder prestress facility girders of the present invention As a method of introduction, anchorages are provided at both ends of the prestressed girders for earthen blocks, a brace is installed between a plurality of load transfer members provided on the front of the girder, and a stroke generating device is installed at the center of the braces. When the steel wire is fixed to the anchorages on both sides while the steel wire is in contact with the load transmitting material, and the stroke is generated in the stroke generating device so that the load transmitting material is erected vertically, the steel wire is elongated to convert the steel wire into prestressing force. Such as temporary fences which let prestress be introduced to temporary girder Figure 7 is a view showing the installation of a temporary structure, Figure 7 is another method for introducing a prestress to the prestress temporary girder for the mud wall of the present invention, by installing anchors at both ends of the prestress temporary girder for the mud, Install a plurality of load transfer members on the front, install steel wires at the anchorages and load transfer ends at both ends, install fixed anchorages at the outermost load transfer material, and install the stroke anchors at the bottom of the girders. And tension the ends of the steel wire settled in the stroke anchorage so that the load transfer material is erected vertically so that the steel wire is stretched, and the stretching force of the generated steel wire is converted to prestressing force so that the prestress is introduced into the temporary girder. Figure showing the installation of the temporary structure, Figure 8 is As another method of introducing the prestress to the prefabricated girders of the name of the prestress, the anchorages are provided at both ends of the prestressed girders for the retaining wall, and a plurality of load transfer materials are installed in front of the temporary girders. The steel wire is installed at the end of the load transfer member, the steel wire is connected while the stroke anchoring hole is installed at the load transfer member, and the end of the steel wire settled at the stroke fixing hole installed at the one side is tensioned so that the load transfer member is erected vertically. FIG. 9 (a) (b) shows that a temporary structure is installed so that the steel wire is stretched, and the stretching force generated in the steel wire is converted into a prestress force so that the prestress is introduced into the temporary girder. Install the fixing brackets on both sides of the girders on both sides and open the wire And, it is installed in contact with the fixing bracket, showing the introduction of the prestress by installing a hydraulic jack in the center of the brace strip installed in contact with the flange of the facility girder prestress, when the external force is large, the flange with a tie-elastic clip Figure 10 is a view showing the close contact, Figure 10 is installed between the girdle and the earth prestressed girders installed on the edge of the girder, and install the stroke generating device at both ends of the girder girders outside the outside Install a pressure regulating device, install a plurality of load transfer materials on the front of the temporary girder, and install the steel wire in contact with the end, fix the steel wire to the fixing device installed in the pressure regulating device, and then generate a stroke in the stroke generating device. After the wire is stretched and fixed, the stretching force The prestressing force transferred to the temporary girder is transferred to the temporary girder, and the prestressing force transmitted to the intermediate brace is installed so that the sectional side temporary facility structure, which is the side sectional temporary facility soil wall, is made to resist and offset the external pressure generated at the side sectional area. Figure 11 is a prestress for the earth retainer is installed between the girder and the general girdle to secure a wider gap, while connecting the brace and the girder installed on both ends of the girdle to install the brace and the temporary connection Figure 12 is a view showing one, and Figure 12 is a view showing the support for the retaining prestressed with a girdle between the girders, Figure 13 is a support for the retaining prestressed girders on each side of the girder The brace is buckled by installing an intermediate file between the braces FIG. 14 is a view showing that the phenomenon is prevented, and FIG. 14 is a view showing that a collision protection measure for protecting a temporary structure is installed outside the facility girder prestress such as FIG. 1, and FIG. 15 (a) (b) is a load transfer material installed on the flange of the front girder prestressed girders as shown in Figs. 6, 7 and 8 in order to prevent the generation of moment while the load transfer material is vertically erected by the stroke generating device. Figure showing the sliding bolt coupling from the side and plane.

본 발명은 지중에 설치되는 가시설흙막이의 띠장 또는 가설교량의 거더와 같은 양단부에 지압지지강판(33)을 설치한 가시설거더에 다양한 방법을 이용하여 프리스트레스를 도입하는 방법에 관한 것이며, 이러한 방법을 이용하여 설치한 가시설구조체에 관한 것이다.       The present invention relates to a method of introducing prestress using a variety of methods to the temporary girder provided with acupressure supporting steel plate 33 at both ends, such as girders of temporary reinforcement mud wall installed in the ground or the girder of the temporary bridge. It relates to a temporary construction structure installed.

위에서 설명한바와 같이 본 발명은 지중에 구조물을 설치하기 위하여 지반을 직선 또는 변단면으로 굴착할 때 주변의 토사가 붕괴되는 것을 방지하면서, 작업공 간을 확보하기 위하여 굴착지반에 설치하는 직선 또는 변단면 가시설흙막이 또는 임시로 교통에 사용하기 위하여 설치되는 가설교량등과 같은 가시설구조체(10)에 적용한 가시설거더에 프리스트레스를 도입하기 위한 다양한 방법을 제시하면서 이에 의하여 설치한 것에 관한 것이다.As described above, the present invention is a straight line or sectional surface installed on the excavation ground to secure working space, while preventing the collapse of the surrounding soil when excavating the ground in a straight line or sectional surface to install the structure in the ground The present invention relates to the provision of various methods for introducing pre-stress to the temporary girder applied to the temporary structural structure 10, such as temporary bridges or temporary bridges for temporary use.

이하, 도면에 의하여 본 발명을 상세히 설명하면 다음과 같다.Hereinafter, the present invention will be described in detail with reference to the drawings.

일정한 간격을 두고 다수개 설치된 수직파일(미도시)의 측면 플랜지면에 거더(11)를 설치하고, 상기 양측에 설치된 거더(11)의 중앙에 슬라이딩공간부(22)를 두고 양단부에 지압지지강판(33)을 설치한 흙막이용 프리스트레스트가시설거더(20)를 설치한다.A girder 11 is installed on the side flange surface of a plurality of vertical piles (not shown) at regular intervals, and a sliding chamber 22 is placed at the center of the girders 11 provided on both sides, and acupressure supporting steel sheets at both ends. Install the prestress temporary girder (20) for the mudstone (33).

상기 중앙에 설치된 흙막이용 프리스트레스트가시설거더(20)의 양측단부에 스트로크발생장치(30)가 연결된 압력조절강재(25)를 연결설치한다.The pressure prestressing steel (25) connected to the stroke generating device (30) is installed at both ends of the girder prestressed girder (20) installed in the center.

상기 압력조절강재(25)의 측면에 일정범위에서 이동할 수 있는 슬라이딩공간부(22)를 설치하여 거더와 접하도록 하면서, 상기 거더(11)와 압력조절강재의 버팀대(12)의 측면에서 버팀대(12)와 볼트너트연결하여 지지되도록 하고, 상기 압력조절강재(25)의 측면인 복부에 정착구(23)를 설치한다.On the side of the pressure-controlled steel 25 to install a sliding space portion 22 that can move in a certain range to come in contact with the girder, on the side of the girder 11 and the brace 12 of the pressure-controlled steel ( 12) and the bolt nut to be supported, and the fixing unit 23 is installed in the abdomen which is the side surface of the pressure regulating steel 25.

상기 압력조절강재(25)와 흙막이용 프리스트레스트가시설거더(20) 사이에 스트로크발생장치(30)를 설치한다.The stroke generating device 30 is installed between the pressure regulating steel 25 and the prestressed girders 20 for the earth retainer.

상기 흙막이용 프리스트레스트가시설거더(20)의 전면인 하부 플랜지(14)에 복수개 이상이 하중전달재(24)를 설치하되, 상기 설치된 각각의 하중전달재(24)의 원중심축(26)이 강선 선형의 원중심(27)에 향하도록 배치하고, 상기 하중전달재(24)의 단부에 강선이 유연하게 접하여 설치될 수 있도록 강선가이드장치(40)를 설치하고, 상기 상기 강선가이드장치의 사이를 통과하여 설치된 강선(13)을 양측에 설치된 정착구(23)에 정착한 가시설구조체(10)를 도 1과 같이 설치한다.At least a plurality of load transfer members 24 are installed on the lower flange 14, which is the front surface of the prestress temporary girders 20, and the center of gravity shaft 26 of each of the installed load transfer members 24 is provided. The wire guide device 40 is disposed so as to face the center line 27 of the wire linear, and the wire guide device 40 is installed at the end of the load transfer member 24 so that the wire can be contacted flexibly. The temporary structural structure 10 in which the steel wire 13 provided through the inside is fixed to the fixing fixture 23 provided in both sides is installed like FIG.

상기 슬라이딩공간부(22)는 일정한 가동범위를 설정한 후에 버팀대(12)와 고정시킨 것으로서, 스트로크발생장치(30)의 유압잭(32)의 실린더가 스트로크를 발생시키면, 상기 압력조절강재(25)가 외측인 슬라이딩공간부로 밀리게되는데, 이때 밀리는 범위인 가동범위내에서 압력조절강재(25)가 밀리도록 이동범위를 한정하기 위한 것이다. The sliding space 22 is fixed to the brace 12 after setting a predetermined movable range, when the cylinder of the hydraulic jack 32 of the stroke generating device 30 generates a stroke, the pressure regulating steel 25 Is pushed to the outer sliding space portion, which is to limit the moving range so that the pressure-controlled steel 25 is pushed in the movable range that is pushed.

상기 이동범위는 당초 설계시 가시설거더(20)에 도입되는 프리스트레스량에 따라 그 범위가 한정되도록 한다.The range of movement is to be limited in accordance with the amount of pre-stress introduced into the temporary girder 20 at the time of design.

도 2는 스트로크발생장치(30)를 상세히 보여주는 도면이다.2 is a view showing the stroke generating device 30 in detail.

상기 스트로크발생장치(30)는 압력조절강재(25)와 흙막이용 프리스트레스트가시설거더(20)의 단부에 지압지지강판(33)을 각각 부착하고, 상기 양측의 지압지지강판(33)과의 사이의 중앙에 유압잭(32)을 설치하고, 상기 유압잭(32)의 상하에, 압력조절강재(25)의 단부에 설치된 지압지지강판(33)에 돌출강관 또는 채널(31)을 용접부착하고, 상기 돌출강관 또는 채널(31)에 볼트(34)를 부착하고, 상기 흙막이용 프리스트레스트가시설거더(20)의 단부에 설치된 장나비너트(35)에 상기 볼트(34)를 볼트체결하면서 상기 흙막이용 프리스트레스트가시설거더(20)의 단부에 설치된 지압지지강판(33)을 관통하여 돌출된 볼트(34)단부에 너트(39)로 체결한 것이다.      The stroke generating device 30 is attached to the pressure-bearing steel plate 25 and the pressure-bearing steel plate 33 at the ends of the prestress temporary girders 20 for the retaining wall, respectively, and the pressure-bearing steel plate 33 on both sides The hydraulic jack 32 is provided in the center between the above, and the protruding steel pipe or channel 31 is welded to the acupressure supporting steel plate 33 provided at the end of the pressure regulating steel 25 above and below the hydraulic jack 32, and The bolt 34 is attached to the protruding steel pipe or channel 31, and the bolt 34 is bolted to a long nut 35 installed at an end of the prestressing girder 20. The prestress is fastened with a nut 39 at the end of the bolt 34 protruding through the pressure bearing steel plate 33 provided at the end of the facility girder 20.

상기와 같이 설치된 도 1과 도 2의 가시설구조체(10)의 가시설거더(20)에 프 리스트레스를 도입하는 방법을 설명하면, 다음과 같다.Referring to the method of introducing the prestress to the temporary girder 20 of the temporary structure 10 of Figure 1 and 2 installed as described above, as follows.

먼저 스트로크발생장치(30)의 유압잭(32)의 실린더에 스트로크를 발생시킨다.First, a stroke is generated in the cylinder of the hydraulic jack 32 of the stroke generating device 30.

상기 발생된 스트로크에 의하여 압력조절강재(25)가 슬라이딩공간부(22) 쪽으로 밀리면서 가시설거더(20)에 프리스트레스힘(P)이 발생된다The prestressing force P is generated in the temporary girder 20 while the pressure regulating steel 25 is pushed toward the sliding space 22 by the generated stroke.

상기와 같이 밀리면 상기 압력조절강재(25)의 측면에 부착된 정착구(23)에 정착된 강선(13)이 외측으로 밀리면서 강선이 신장하고, 설계관리치 만큼 스트로크를 가 한 다음, 장나비너트(35)와 너트(39)를 고정하면, 상기 강선을 늘어나게 하던 신장력이 프리스트레스힘(P)으로 전환함과 동시에 하중전달재(24)를 위로 밀어 올리는 외력상쇄반력(PV)이 발생되어 가시설거더(20)에 프리스트레스로 전달된다.        When pushed as described above, the steel wire 13 is pushed outward while the steel wire 13 fixed to the anchorage 23 attached to the side of the pressure regulating steel 25 is pushed outward, and the stroke is applied as much as the design management value, Fixing the (35) and the nut (39) causes the external force offset reaction force (PV) that pushes the load transfer member 24 upward while generating an extension force that causes the wire to be stretched to a prestress force (P). Prestressed at 20.

상기 스트로크발생장치(30)에 하중측정센서(46)를 설치할 수도 있다.A load measuring sensor 46 may be installed in the stroke generating device 30.

상기 하중전달재(24)의 원중심축(26)이 가상의 원중심(27)에 모이도록 설치되었으므로 상기 강선이 강선가이드장치(40)와 마찰력을 최소화하여 전 강선 길이에 균등하게 프리스트레스힘(P)이 도입되게 한 것이다.Since the centroid 26 of the load transfer member 24 is installed to the virtual centroid 27, the wire is minimized friction force with the wire guide device 40 so that the prestress force is equal to the length of the entire wire. P) is introduced.

상기 도 2의 스트로크발생장치(30)와 다른 설치예가 도 3(a)(b)이다.The installation example different from the stroke generating apparatus 30 of FIG. 2 is FIG.3 (a) (b).

도 (a)의 스트로크발생장치(30)는 압력조절강재(25)와 흙막이용 프리스트레스트가시설거더(20)의 단부에 지압지지강판(33)을 각각 부착하고, 상기 양측의 지압지지강판(33)과의 사이의 중앙에 유압잭(32)을 설치하고, 상기 유압잭이 설치된 주위에 하중측정센서(46)을 설치하고, 상기 유압잭(32)의 상하에, 압력조절강재(25)의 단부에 설치된 지압지지강판(33)에 강관(31)을 용접부착하고, 상기 강관(31)에 볼트(34)를 용접부착하고, 설계관리치 만큼 스트로크를 이동시킨 다음, 상기 볼트(34)에 장나비너트(35)를 체결하면서 상기 흙막이용 프리스트레스트가시설거더(20)의 단부에 설치된 지압지지강판(33)을 관통하여 돌출된 볼트(34)단부에 너트(39)로 체결한 것이다.The stroke generating device 30 of FIG. (A) attaches the pressure bearing steel plates 33 to the ends of the pressure regulating steel 25 and the prestress temporary girder 20 for the retaining wall, respectively. A hydraulic jack 32 is provided at the center between the valve 33, a load measuring sensor 46 is installed around the hydraulic jack, and at the end of the pressure regulating steel 25 above and below the hydraulic jack 32. The steel pipe 31 is welded to the provided acupressure supporting steel plate 33, the bolt 34 is welded to the steel pipe 31, the stroke is moved by a design control value, and then a long bow nut (to the bolt 34) is attached. While fastening 35), the prestress for earth retaining is fastened with a nut 39 to the end of the bolt 34 protruding from the pressure bearing steel plate 33 installed at the end of the facility girder 20.

도 (b)의 스트로크발생장치(30)는 압력조절강재(25)와 흙막이용 프리스트레스트가시설거더(20)의 단부에 지압지지강판(33)을 각각 부착하고, 상기 양측의 지압지지강판(33)과의 사이의 중앙에 유압잭(32)을 설치하고, 상기 유압잭이 설치된 주위에 하중측정센서(46)를 설치하고, 상기 유압잭(32)의 상하에, 압력조절강재(25)의 단부에 설치된 지압지지강판(33)에 채널(47)을 용접부착하고, 상기 채널(47)에 볼트(34)를 용접부착하고, 설계관리치 만큼 스트로크를 이동시킨 다음, 상기 볼트(34)에 장나비너트(35)를 체결하면서 상기 흙막이용 프리스트레스트가시설거더(20)의 단부에 설치된 지압지지강판(33)을 관통하여 돌출된 볼트(34)단부에 너트(39)로 체결한 것이다.The stroke generating device 30 of FIG. (B) attaches the pressure bearing steel plates 33 to the ends of the pressure regulating steel 25 and the prestressed girder 20 for the retaining wall, respectively. A hydraulic jack 32 is provided in the center between the valve 33, a load measuring sensor 46 is installed around the hydraulic jack, and the upper and lower portions of the hydraulic jack 32 are disposed at the ends of the pressure regulating steel 25. The channel 47 is welded to the provided acupressure supporting steel plate 33, the bolt 34 is welded to the channel 47, the stroke is moved by a design management value, and then the bow 34 nut ( While fastening 35), the prestress for earth retaining is fastened with a nut 39 to the end of the bolt 34 protruding from the pressure bearing steel plate 33 installed at the end of the facility girder 20.

다음으로, 도 4(a)는 하중전달재(24)의 단부에 설치된 강선가이드장치(40)를 상세히 보여주는 것이다.Next, Figure 4 (a) shows the wire guide device 40 installed in the end of the load transfer member 24 in detail.

상기 강선가이드장치(40)는 하중전달재(24)의 단부에 베이스강판(28)과 보강판을 설치하고, 상기 베이스강판을 포함하는 하중전달재(24)의 양측에 가이드판(41)을 설치하고, 상기 가이드판(41)의 사이의 베이스강판(28)에 부착하여 강선이 접하는 면이 볼록한 곡면을 갖는 곡선새들(42)을 부착설치하고, 상기 곡선새 들(42)의 곡면에 강선을 접촉설치하면서 상기 양측에 설치된 가이드판(41)의 상부를 관통하여 강선이탈방지봉(45)을 설치하여 설치된 강선이 이탈되는 것을 방지한 것이다.The wire guide device 40 is provided with a base steel plate 28 and a reinforcement plate at the end of the load transfer member 24, the guide plate 41 on both sides of the load transfer member 24 including the base steel plate Install, and attach to the base steel plate 28 between the guide plate 41, the curved saddle 42 having a convex curved surface is in contact with the steel wire, the steel wire on the curved surface of the curved bird 42 While installing the contact wire through the upper portion of the guide plate 41 installed on both sides to prevent the separation of the steel wire installed by installing the steel wire escape prevention rod 45.

상기 하중전달재(24)의 원중심축(26)이 강선이 배치된 원형상의 원중심(27)을 향하도록 설치되도록 하면서 곡선새들(42)에 강선(13)이 접하는 부분이 원중심축(26)과 강선(13)의 접선방향(T)에 직각(R)이 되도록 하여 강선이 하중전달재(24)에 설치될때 유연한 원호상을 형성하도록 하여 강선 마찰에 의한 프리스트레스힘(P) 손실을 최소화하고, 강선 전 길이에 균등하게 분포되도록 하기 위한 것이다.While the center of gravity axis 26 of the load transfer material 24 is installed to face the circular center of gravity 27 in which the steel wire is disposed, the portion where the steel wire 13 is in contact with the curved saddle 42 is the central axis ( 26) and a right angle (R) in the tangential direction (T) of the steel wire 13 to form a flexible arc shape when the steel wire is installed in the load transfer member 24 to prevent the loss of prestress force (P) due to steel wire friction. It is to minimize and to distribute evenly over the length of the wire.

상기와 같은 방법에 의하여 강선(13)을 설치하는 경우는 1층으로 설치하는 경우이고, 도 4(b)는 2층으로 강선을 다수개 설치하는 경우에 적용하도록 한 것이다.When the steel wire 13 is installed by the above-described method, the steel wire 13 is installed in the first floor, and FIG. 4B is applied to the case in which a plurality of steel wires are installed in the second floor.

상기 하중전달재(24)의 단부에 베이스강판(28)과 이를 지지하는 보강판(15)을 설치하고 상기 베이스강판(28)을 포함하면서 내측에는 상하로 파이프핀부(44)가 설치된 가이드판(41)을 양측에 설치한다.A guide plate provided with a base steel plate 28 and a reinforcing plate 15 supporting the base steel plate 28 at the end of the load transfer member 24 and including the base steel plate 28 and a pipe pin portion 44 installed up and down inside the base plate 28. 41) on both sides.

상기 가이드판(41)에 설치된 파이프핀부(44)에 강관새들(43)의 측면에 형성된 홈이 삽입되도록 상하로 설치한다.     It is installed up and down so that the groove formed in the side of the steel pipe birds 43 is inserted into the pipe pin 44 provided in the guide plate 41.

상기 강관새들(43)에 접하게 강선(13)을 각각 설치한다.Steel wires 13 are installed in contact with the steel pipe birds 43, respectively.

상기 강선(13)이 상하로 강관새들(43)에 접하게 설치한 후에, 상기 가이드판(41)의 상부에 강선이탈방지봉(45)을 설치하여 강선(13)이 이탈되는 것을 방지한다.After the steel wire 13 is installed in contact with the steel pipe birds 43 up and down, by installing a steel wire escape prevention bar 45 on the upper portion of the guide plate 41 to prevent the steel wire 13 from being separated.

상기 강관새들이 파이프핀부를 축으로 하여 회전되도록 하므로서 강선이 신축작용을 할때 마찰을 최소로 하기 위함이다. In order to minimize the friction when the steel wire is stretched by allowing the steel pipe birds to rotate about the pipe pin.

도 5는 가시설거더를 단열로 할 경우, 외력에 대한 응력부담의 강성이 부족한 경우에 이중으로 연결한 프리스트레스트가시설이중거더(50)를 이용하여 도 1의 흙막이용 프리스트레스트가시설거더(20)에 적용한 것을 보여주는 도면이다.5 is a prestressed girder 20 for the mud wall using the prestressed temporary double girder 50 connected in the case of a stiffness of the stress load against the external force when the insulation girder as a heat insulation; Figure shows the application to).

이때 하중전달재(24)는 가시설거더를 측면에서 상호 연결한 부분에 일렬로 다수개 설치한 것에 의하여 지지되도록 한 것이다.At this time, the load transfer material 24 is to be supported by the installation of a plurality of lines in a line interconnected to the temporary girder.

도 6의 본 발명의 흙막이용 프리스트레스트가시설거더(20)에 강선을 신장시켜 프리스트레스를 도입하는 방법으로서의 한가지 예를 보여주는 것이다.Figure 6 shows one example as a method of introducing the prestress by extending the steel wire to the prestress for facility girder 20 of the present invention.

흙막이용 프리스트레스트가시설거더(20)의 양단부에 정착구(23)가 설치된 강선고정 강재(17)를 연결설치하고, 상기 강선고정 강재(17)의 측면에서 버팀대(12)와 볼트너트결합(38)하여 지지하도록 하고, The steel wire fixing steel (17) provided with anchors (23) are installed at both ends of the prestress temporary girder (20) for the earth retaining, and the brace (12) and the bolt nut coupling (38) on the side of the steel wire fixing steel (17). To support it,

상기 흙막이용 프리스트레스가시설거더(20)의 전면에 복수의 하중전달재(24)와 강선을 설치하고, 상기 하중전달재(24)의 사이에 버팀대띠장(71)을 설치하고, 상기 버팀대띠장(71)의 중앙에 스트로크발생장치(30)인 유압잭(32)을 설치하고, 상기 유압잭(32)에 스트로크를 발생시키면, 상기 상기 플랜지(14)에 슬라이딩볼트결합(73)된 하중전달재(24)가 외측으로 밀리면 하중전달재(24)가 수직방향으로 세워지게되어 결국 강선(13)이 하중전달재에 위쪽으로 올라가면서 강선이 신장하고 설계관리치 만큼 신장하도록 스트로크를 가 한 다음, 고정시키면, 상기 강선의 신장력이 프리스트레스힘(P)으로 전환하고, 상기 힘이 하중전달재를 통해 외력상쇄반력(PV)이 전달되므로서 가시설거더(20)에 프리스트레스로 도입되는 것이다.      A plurality of load transfer members 24 and steel wires are installed on the front surface of the prestress temporary girder 20 for the earth retainer, and a brace belt 71 is installed between the load transfer members 24, and the brace belt ( When the hydraulic jack 32, which is the stroke generating device 30, is installed in the center of the 71, and the stroke is generated in the hydraulic jack 32, the load transfer member 24 in which the sliding bolt is coupled to the flange 14 is formed. When the load is pushed outwards, the load transfer member 24 is erected in the vertical direction. As a result, the steel wire 13 rises upward to the load transfer member, and the steel wire is stretched and the stroke is stretched by the design management value. The extension force of the steel wire is converted into prestress force (P), and the force is introduced into the temporary girder 20 as the prestress while the external force offset reaction force (PV) is transmitted through the load transfer material.

또 다른 방법으로는 도 7과 같이 하중전달재와 강선고정강재(17)에 스트로크강선(74)을 연결하여 긴장하여 강선을 신장시켜 프리스트레스를 도입하는 것이다.Another method is to introduce the prestress by stretching the steel wire by tensioning by connecting the stroke steel wire 74 to the load transfer material and the steel wire fixed steel 17 as shown in FIG.

상기 흙막이용 프리스트레스트가시설거더(20)의 양단부에 정착구(23)가 설치된 강선고정강재(17)를 연결설치하고, 상기 강선고정강재(17)의 측면에서 버팀대(12)와 볼트너트결합(38)하여 지지하도록 하고, The steel wire fixing steel (17) provided with anchors (23) are installed at both ends of the prestress temporary girder (20) for earth retaining, and the brace (12) and bolt nuts are coupled to the side of the steel wire fixing steel (17). 38) to support it,

상기 흙막이용 프리스트레스가시설거더(20)의 전면에 복수개 이상의 하중전달재(24)와 강선을 설치하고, 상기 최외측에 설치된 하중전달재(24)에 고정정착구(75)를 설치하고, 상기 강선고정강재(17)의 플랜지(14)에 스트로크정착구(76)를 각각 설치한 다음, 상기 각각의 정착구(75,76)에 스트로크강선(74)을 상호 연결하여 정착한다.    A plurality of load transfer members 24 and steel wires are installed on the front surface of the prestress temporary girders 20 for the earth retaining wall, and fixed fixing holes 75 are installed on the load transfer members 24 installed on the outermost side. After the stroke fixing holes 76 are installed on the flanges 14 of the fixed steel 17, the steel wires 74 are connected to each other and fixed to the fixing holes 75 and 76, respectively.

상기 스트로크정착구(76)에 연결된 스트로크강선(74)을 긴장하여 고정정착하면 플랜지(14)에 슬라이딩볼트결합(73)된 하중전달재(24)가 외측으로 밀리면서 하중전달재(24)는 수직으로 세워지게된다.    When the steel wire 74 connected to the stroke fixing hole 76 is tensioned and fixed, the load transfer material 24 sliding 73 coupled to the flange 14 is pushed outward and the load transfer material 24 is vertical. To be built.

상기와 같이 수직으로 세워지게되면, 결국 강선(13)이 하중전달재(24)에 위쪽으로 올라가면서 강선이 신장하고, 설게관리치 만큼 신장하도록 스트로크를 가한 다음, 고정시키면, 상기 강선의 신장력이 프리스트레스힘(P)으로 전환하고, 상기 힘이 하중전달재를 통해 외력상쇄빈력(PV)가 전달되므로서 가시설거더(20)에 프리스트레스로 도입되는 것이다.    When it is erected vertically as described above, the steel wire 13 eventually stretches upwards on the load transfer member 24, and the steel wire is stretched, and the stroke is applied to extend as much as the management value, and then fixed. The prestressing force (P) is converted, and the force is introduced into the temporary girder 20 as the prestressing force (PV) is transmitted through the load transfer material.

또 다른 방법으로는 도 8과 같이 한다.Another method is as shown in FIG.

상기 흙막이용 프리스트레스트가시설거더(20)의 양단부에 정착구(23)가 설치된 강선고정강재(17)를 연결설치하고, 상기 강선고정강재(17)의 측면에서 버팀대(12)와 볼트너트결합(38)하여 지지하도록 하고, The steel wire fixing steel (17) provided with anchors (23) are installed at both ends of the prestress temporary girder (20) for earth retaining, and the brace (12) and bolt nuts are coupled to the side of the steel wire fixing steel (17). 38) to support it,

상기 흙막이용 프리스트레스가시설거더(20)의 전면에 복수개의 하중전달재(24)와 강선을 설치하고, 상기 하중전달재(24)의 중간에 스트로크정착구(76)를 설치하고, 상기 양측의 스트로크정착구(76)에 강선(13)을 상호 연결하여 정착한다.      A plurality of load transfer members 24 and steel wires are provided on the front surface of the prestress temporary girders 20 for the retaining wall, and stroke fixing holes 76 are installed in the middle of the load transfer members 24, and the strokes on both sides are provided. The steel wire 13 is connected to and fixed to the fixing unit 76.

상기 스트로크정착구(76)에 연결된 강선(13)을 긴장하여 고정정착하면 플랜지(14)에 슬라이딩볼트결합(73)된 하중전달재가 외측으로 밀리면서 하중전달재(24)는 수직으로 세워지게된다.      When the steel wire 13 connected to the stroke fixing hole 76 is tensioned and fixed, the load transfer material 24 sliding to the flange 14 is pushed outwards, and the load transfer material 24 is vertically erected.

상기와 같이 수직으로 세워지게되면, 결국 강선(13)이 하중전달재에 위쪽으로 올라가면서 강선이 신장하고, 설계관리치만큼 신장하도록 스트로크를 가한 다음, 고정시키면, 상기 강선의 신장력이 프리스트레스힘(P)으로 전환하고, 상기 힘이 하중전달재를 통해 외력상쇄반력(PV)이 전달되므로서 가시설거더(20)에 프리스트레스로 도입되는 것이다.      When the steel wire 13 is erected vertically as described above, the steel wire 13 eventually extends upward to the load transfer member, and the steel wire is stretched, and a stroke is applied to extend the design management value, and then fixed, and the extension force of the steel wire is prestressed. P), the force is introduced into the girder 20 prestressed by the external force offset reaction (PV) is transmitted through the load transfer material.

상기 하중전달재(24)의 설치방법은 위에서 이미 설명한바와 같이 설치하도록 한다.      The installation method of the load transfer material 24 is to be installed as described above.

또 다른 방법으로는 도 9(a)와 같이 흙막이용 프리스트레스트가시설 거더(20)의 측면에 정착구가 설치된 정착브라켓(29)을 양측에 설치하고 강선(13)을 연결하고, 상기 정착브라켓(29)과 접하게 설치하되, 상기 흙막이용 프리스트레스트가시설거더(20)의 플랜지에 접하게 설치된 버팀대띠장(71)의 중앙에 유압잭(32)을 설치하여 유압잭에 스트로크를 발생시켜 버팀대띠장을 양측면의 정착브라켓쪽으로 밀면 상기 정착브라켓이 밀리면서 상기 정착브라켓에 연결된 강선도 동시에 옆으로 밀려 강선이 신장되고, 상기 스트로크를 정지하고 고정정착하면 강선에 도입된 신장력이 외력상쇄반력으로 전환되어 프리스트레스가 도입되도록 하는 것이다.As another method, as shown in FIG. 9 (a), the fixing brackets 29 having fixing fixtures installed on the sides of the prestress temporary girder 20 for earthenware are installed on both sides, and the steel wires 13 are connected to each other. 29) is installed in contact with, but the prestress for the retaining wall is installed in contact with the flange of the girder 20, the hydraulic jack 32 is installed in the center of the hydraulic jack 32 to generate a stroke in the hydraulic jack to fix the brace on both sides When pushed toward the bracket, the fixing bracket is pushed and the wire connected to the fixing bracket is pushed to the side at the same time so that the steel wire is stretched, and when the stroke is stopped and fixed, the extension force introduced into the steel wire is converted into an external force offset reaction force to introduce the prestress. will be.

또한, 상기와 같이 프리스트레스가 작용하면, 외력에 의해 상기 거더(11)가 하부로 변형되어 휘고, 프리스트레스에 의하여는 버팀대띠장(71)이 상부로 휘어, 결국 상기 거더(11)와 버팀대띠장(71)이 상호 밀착되어 일체성으로 결합되는 합성단면을 이루게되어 단면강성이 대폭 증가하게되는 것이다.In addition, when the prestress acts as described above, the girder 11 is deformed downward by the external force, and the brace belt 71 is bent upward by the prestress, and thus the girder 11 and the brace belt 71 are eventually bent. ) Are closely bonded to each other to form a composite cross-section combined to increase the cross-sectional stiffness significantly.

상기와 같이 합성될때 외력이 클 경우에는, 도 (b)와 같이 타이탄성클립(78)으로 거더(11)의 플랜지(14)와 버팀대띠장(71)의 플랜지(14)가 상호 접하는 부분에 오메가 형상인 타이탄성클립(78)의 밀착부(79)를 밀착시키고, 밀착부(79)와 연결된 탄성클립(80)을 관통하여 볼트너트(38)로 결합, 체결하여 상하에서 밀착된 플랜지(14)가 벌어지는 것을 상기 타이탄성클립(78)의 마찰력을 이용하여 결합시키도록 한다. When the external force is large when synthesized as described above, omega at the portion where the flange 14 of the girder 11 and the flange 14 of the brace long 71 are in contact with each other with a rigid elastic clip 78 as shown in (b). A flange 14 that is in close contact with the tightly coupled portion 79 of the shape of the elastic elastic clip 78, penetrates through the elastic clip 80 connected to the tightly coupled portion 79, and is coupled and fastened to the bolt nut 38. ) Is coupled to the gap using the friction force of the elastic elastic clip (78).

본 발명의 가시설구조체(10)를 설치하는 또 다른 방법으로는 도 10과 같이 굴착단면이 변화하는 변단면에 적용하기 위한 것이다.Another method for installing the provisional structure 10 of the present invention is to apply to the side of the excavation cross section as shown in FIG.

변단면을 포함하는 굴착면을 따라 다수개의 수직파일(16)을 설치하고 상기 수직파일에 접하여 거더(11)를 설치하면서 흙막이벽을 동시에 설치한다. A plurality of vertical piles (16) are installed along the excavation surface including the side faces, and the girder (11) is installed in contact with the vertical piles and simultaneously installs the retaining wall.

상기 변단면의 시종점의 단면에 흙막이용 프리스트레스트가시설거더(20)를 설치하고, 그 양측에 압력조절강재(25)를 연결설치한다.      The prestressing girders 20 for the retaining wall is installed on the end surface of the starting point of the end face, and the pressure regulating steel 25 is connected to both sides thereof.

상기 압력조절강재(25)의 측면에 일정범위에서 이동할 수 있는 슬라이딩공간부(22)를 설치하여 거더(11)와 접하도록 하면서, 상기 거더(11)와 압력조절강재(25)의 측면과 버팀대(12)의 측면을 볼트너트결합(38)하여 지지되도록 하고, 상기 압력조절강재(25)의 측면인 복부에 정착구(23)를 설치한다.The side of the girder 11 and the pressure-controlled steel 25 and the brace while installing a sliding space 22 to move in a predetermined range on the side of the pressure-controlled steel 25 to contact with the girder 11 The side of the 12 is supported by the bolt nut coupling 38, and the fixing unit 23 is installed in the abdomen which is the side of the pressure regulating steel 25.

상기 압력조절강재(25)와 흙막이용 프리스트레스트가시설거더(20) 사이에 스트로크발생장치(30)를 설치한다.The stroke generating device 30 is installed between the pressure regulating steel 25 and the prestressed girders 20 for the earth retainer.

상기 변단면 양측의 띠장연장부(49)를 상기 압력조절강재(25)의 측면에 부착설치한다.The strip extension 49 on both sides of the side end face is attached to the side of the pressure regulating steel 25.

상기 변단면의 거더(11)와 흙막이용 프리스트레스가시설거더(20)사이에 다수개의 중간버팀대(61)를 설치하여 지지하도록 한다.A plurality of intermediate braces 61 are installed and supported between the girder 11 and the soil barrier pre-stressed girders 20 on the edges.

상기 흙막이용 프리스트레스트가시설거더(20)의 전면인 하부 플랜지(14)에 복수개 이상이 하중전달재(24)를 설치하되, 상기 설치된 각각의 하중전달재(24)의 원중심축(26)이 강선의 배치형상인 원형상의 원중심(27)에 모이도록 원형이 되도록 배치하고, 상기 하중전달재(24)의 단부에 강선이 유연하게 접하여 설치될 수 있도록 강선가이드장치(40)를 설치하고, 상기 상기 강선가이드장치의 사이를 통과하여 설치된 강선(13)을 양측에 설치된 정착구(23)에 정착한다.At least a plurality of load transfer members 24 are installed on the lower flange 14, which is the front surface of the prestress temporary girders 20, and the center of gravity shaft 26 of each of the installed load transfer members 24 is provided. Arranged so as to be circular so as to gather in a circular center of gravity 27 of the steel wire arrangement shape, and install the wire guide device 40 so that the steel wire can be installed in contact with the end of the load transfer member 24 flexibly Fixing the steel wire 13 installed through the steel wire guide device to the fixing unit 23 provided on both sides.

상기 하중전달재(24)의 단부에서 일정거리 떨어지게 양측에 설치된 버팀대(12)와의 사이에 도 14의 충돌방호책(48)을 설치한 변단면가시설구조체(60)를 도 10과 같이 설치한다.     10 is provided with a side cross-section provision structure structure 60 in which the collision protection measures 48 of FIG. 14 are installed between the braces 12 provided on both sides away from the end of the load transfer member 24 by a predetermined distance.

상기 슬라이딩공간부(22)는 일정한 가동범위를 설정한 후에 버팀대(12)와 고정시킨 것으로서, 스트로크발생장치(30)의 유압잭(32)의 실린더가 스트로크를 발생시키면, 상기 압력조절강재(25)가 외측인 슬라이딩공간부(22)로 밀리게되면, 강선(13)이 위쪽으로 신장하고, 설계관리치 만큼 스트로크를 가한 다음, 고정하면, 상기 강선이 늘어나게 하던 신장력이 프리스트레스힘(P)을 전환함과 동시에 하중전달재를 위로 밀어 올리는 힘인 외력상쇄반력(PV)이 발생되어 가시설거더(20)에 프리스트레스로 전달되는데, 상기 전달된 힘이 다시 중간버팀대(61)로 골고루 전달되어 변단면의 외력을 상쇄하도록 한 것이다.The sliding space 22 is fixed to the brace 12 after setting a predetermined movable range, when the cylinder of the hydraulic jack 32 of the stroke generating device 30 generates a stroke, the pressure regulating steel 25 Is pushed to the outer sliding space portion 22, the steel wire 13 is extended upward, the stroke is applied as much as the design management value, and then fixed, the stretch force that the steel wire is stretched to switch the prestress force (P) At the same time, an external force offset force (PV), which is a force that pushes up the load transfer material, is generated and transmitted to the temporary girder 20 as a prestress, and the transmitted force is evenly transmitted back to the intermediate brace 61 so that the external force of the side face is increased. To offset.

도 11은 가시설거더(20)와의 사이의 간격을 확대하기 위하여 버팀대와 가시설거더연결부(100)를 설치한 것이다.11 is to install the brace and the temporary girder connecting portion 100 in order to enlarge the distance between the temporary girder 20.

양측의 흙막이용 프리스트레스트가시설거더(20)와의 사이에 거더(11)를 설치하고 볼트너트결합(38)하고, 상기 볼트너트결합한 양측 부분의 플랜지(14)에 지압보강대(101)를 설치하면서 중앙에 버팀대(12)를 설치한다.      While installing the girders 11 between the prestressed girders 20 on both sides of the retaining wall and bolt nut coupling 38, and installing the acupressure reinforcement 101 on the flanges 14 on both sides of the bolt nut coupling. Install the brace 12 in the center.

상기 양측의 지압보강대(101)에 경사버팀대(103)를 설치하여 중앙의 버팀대와 상호 연결된 부분에 보강부(21)를 설치하고, 상기 보강부의 외측에 스크류잭(102)을 설치하고 상기 스크류잭의 외측에 버팀대(21)를 설치한 것이다.      Install the inclined brace 103 on the acupressure reinforcement 101 of the both sides to install the reinforcement portion 21 in the portion interconnected with the brace in the center, install the screw jack 102 on the outside of the reinforcement portion and the screw jack On the outside of the brace 21 is installed.

또 다른 방법으로 도 12는 일정한 간격을 두고 양측에 설치된 가시설거더(20)를 한 개의 버팀대(12)로 지지하도록 한 버팀대와 가시설거더연결부(100)를 설치한 것이다.12 is a brace and a temporary girder connecting portion 100 to support the temporary girder 20 installed on both sides with a single brace 12 at regular intervals.

간격 양측에 설치된 흙막이용 프리스트레스트가시설거더(20)의 플랜지를 연결한 지압보강대(101)를 설치하고, 상기 지압보강대(101)의 측면 중앙에 버팀대(12)를 설치하고, 연이어서 스크류잭(21)을 설치하고, 상기 스크류잭의 외측에 버팀대(12)를 연결설치한 것이다.Install the acupressure reinforcement 101 connecting the flanges of the prestressed girders 20 for the earth retaining wall installed on both sides of the gap, and install the brace 12 in the center of the side of the acupressure reinforcement 101, and then successively screw jack (21) is installed, and the brace 12 is connected to the outside of the screw jack.

도 13은 버팀대(12)가 길어질 경우 버팀대가 좌굴되는 것을 방지하기 위한 것이다.FIG. 13 is for preventing the brace from buckling when the brace 12 is long.

일정한 간격을 두고 설치된 양측 흙막이용 프리스트레스트가시설거더(20)의 각각의 플랜지에 버팀대(12)를 각각 연결하고, 상기 연결된 버팀대(12)의 사이에 중간파일(77)을 설치하여 양측에 설치된 버팀대(12)의 좌굴을 방지하면서 지지하도록 한 것이다.Both ends of the prestressed girders (20) installed at regular intervals are connected to each of the braces 12, respectively, and the intermediate pile (77) is installed between the braces 12 connected to each other installed on both sides It is to support while preventing the buckling of the brace (12).

도 14는 도 1, 도 5, 도 6, 도 7, 도 8 및 도 9의 가시설거더(20)의 외측에 설치되어 중장비등으로부터 가시설구조체(10)가 파괴되거나 손상되는 것을 방지하기 위하여 설치한 것이다.FIG. 14 is installed outside the temporary girder 20 of FIGS. 1, 5, 6, 7, 8, and 9 to prevent damage or damage to the temporary structural body 10 from heavy equipment. will be.

흙막이용 프리스트레스트가시설거더(20)를 지지하는 버팀대(12)와의 사이에서 상하로 격자형으로 앵글을 이용하여 설치한 것이다.      Prestress for the earth is installed using an angle in a grid up and down between the brace 12 for supporting the facility girder 20.

버팀대(12)와 버팀대(12) 사이에 수직앵글(54)을 상하로 설치하고, 상기 버팀대(12)와 수직앵글(54)이 상호 만나는 부분에 수평앵글(55)을 설치하여 보강한 충돌방호책(48)인 것이다.      Collision protection measures reinforced by installing a vertical angle 54 between the brace 12 and the brace 12 up and down, and installing a horizontal angle 55 at a portion where the brace 12 and the vertical angle 54 meet each other. (48).

도 15(a)(b)는 가시설거더(20)의 전면에 하중전달재(24)가 설치되어 스트로크발생장치(30)에 의하여 하중전달재(24)가 수직으로 세워질때 하중전달재(24)와 플랜지(14)사이에 활동이 원활하도록 하면서 모멘트가 발생되는 것을 방지하기 위한 것이다.15 (a) and (b) show a load transfer member 24 when the load transfer member 24 is installed on the front of the temporary girder 20 so that the load transfer member 24 is vertically set up by the stroke generating device 30. ) And to prevent the moment is generated while the activity between the flange (14) smoothly.

도 15(a)는 측면도이고, (b)는 평면도로서, 플랜지(14)의 하부에 스테인레스판(53)을 설치하고, 그 다음에 보강판(15)을 설치하고, 그 다음에 하중전달재(24)를 설치하되, 상기 플랜지(14), 스테인레스판(53) 및 보강판(15)에 장공(51)을 형성하여 상호 관통되도록 하고, 상기 장공(51) 외측의 상하부에 와샤(52)를 설치하고, 상기 와샤(52)와 장공(51)을 관통하여 볼트너트결합(38)하도록 한 것이 힌지볼트결합(73)인 것이다.(A) is a side view, (b) is a top view, in which the stainless plate 53 is provided in the lower part of the flange 14, and then the reinforcement board 15 is installed, and then a load transmitting material (24) is installed, but the long hole 51 is formed in the flange 14, the stainless plate 53 and the reinforcing plate 15 so as to penetrate each other, and the washer 52 in the upper and lower parts of the outside of the long hole 51 The hinge bolt coupling (73) is provided so that the bolt nut coupling (38) passes through the washer (52) and the long hole (51).

스트로크발생장치(30)에 의하여 하중전달재(24)가 수직으로 이동할 때 스테인레스판(53)은 마찰을 최소화하여 이동이 원활하게 하고, 상기 장공(51)은 하중전달재(24)가 수직으로 이동할 때 장공(51)의 범위내에서 볼트너트가 이동할 수 있도록 하여 모멘트의 발생을 방지하도록 한 것이다.When the load transfer member 24 is moved vertically by the stroke generating device 30, the stainless plate 53 minimizes friction to facilitate movement, and the long hole 51 has the load transfer member 24 vertically. When moving, it is to prevent the generation of moment by allowing the bolt nut to move within the range of the long hole (51).

상기 강선을 정착하는 정착구의 설치 위치를 띠장 또는 거더의 도심과 일치시켜 편심모멘트의 발생을 방지하도록 한 것이다. The installation position of the anchorage for fixing the steel wire is to match the center of the belt or girders to prevent the occurrence of eccentric moment.

도 1은 본 발명의 흙막이용 프리스트레스트가시설거더의 양측에 스트로크발생장치를 설치하고 그 외측에 압력유동강재에 정착구를 설치하고 상기 가시설거더의 전면에 하중전달재를 설치하고 양측에 설치된 정착구에 강선을 설치하면서 하중전달재에 접하게 설치하여 상기 스트로크발생장치의 잭으로 밀면 강선이 신장되어 그반력으로 가시설거더에 프리스트레스가 도입되도록 한 가시설흙막이등의 가시설구조체를 설치한 것을 보여주는 도면.Figure 1 is installed on both sides of the prestressed girders for earthenware according to the present invention installed on the outside of the girder installed on the outside of the girder girder installed in the pressure flow steel and the load transfer material on the front of the girder Drawing showing the installation of a temporary structure such as a temporary scaffolding so that when the steel wire is installed in contact with the load transfer material and pushed to the jack of the stroke generating device and the steel wire is extended so that prestress is introduced into the temporary girder by the reaction force.

도 2는 본 발명의 스트로크발생장치와 강선이 정착구에 의하여 연결된 상태를 보여주는 도면.2 is a view showing a state in which the stroke generating device and the steel wire of the present invention is connected by a fixing unit.

도 3(a)(b)는 본 발명의 스트로크발생장치의 강관 및 채널에 볼트너트가 각각 결합된 관계를 보여주는 도면.Figure 3 (a) (b) is a view showing a relationship in which the bolt nut is coupled to the steel pipe and the channel of the stroke generating device of the present invention, respectively.

도 4(a)는 본 발명의 강선가이드장치를 상세히 보여주는 도면.Figure 4 (a) is a view showing in detail the wire guide device of the present invention.

도 4(b)는 본 발명의 강선가이드장치의 또 다른 실시예를 보여주는 도면.Figure 4 (b) is a view showing another embodiment of the wire guide device of the present invention.

도 5는 본 발명의 흙막이용 프리스트레스트가시설거더를 이중으로 설치한 것을 보여주는 도면.Figure 5 is a view showing the installation of a double girder prestress girder for the present invention.

도 6은 본 발명의 흙막이용 프리스트레스가시설거더에 프리스트레스를 도입하는 방법으로서, 흙막이용 프리스트레스트가시설거더의 양단에 정착구를 설치하고, 상기 가시설거더의 전면에 설치된 복수의 하중전달재사이에 버팀대를 설치하고, 상기 버팀대 중앙부에 스트로크발생장치를 설치하고, 상기 하중전달재에 강선이 접하게 설치하면서 양측의 정착구에 강선을 정착하고, 상기 스트로크발생장치에 스트로크를 발생시켜 하중전달재가 수직으로 세워지도록 하면, 강선이 신장되어 강선에 프리스트레스힘으로 전환시켜 프리스트레스가 가시설거더에 도입되도록 한 가시설흙막이등의 가시설구조체를 설치한 것을 보여주는 도면. 6 is a method for introducing prestress into the prestress temporary girder for the mud wall of the present invention, the fixing unit is installed on both ends of the prestress temporary girder for the mud, the brace between the plurality of load transfer material installed on the front of the temporary girder And a stroke generating device in the center of the brace, the steel wire is installed in contact with the load transmitting material, the steel wire is fixed in the fixing holes on both sides, and the stroke is generated in the stroke generating device so that the load transmitting material is erected vertically. When the steel wire is extended and the steel wire is converted into prestressing force to install the temporary structural structure such as a temporary earthquake barrier to allow the prestress to be introduced into the temporary girder.

도 7은 본 발명의 흙막이용 프리스트레스트가시설거더에 프리스트레스를 도입하는 다른 방법으로서, 흙막이용 프리스트레스가시설거더의 양단에 정착구를 설치하고, 상기 가시설거더의 전면에 설치된 복수이상의 하중전달재를 설치하고, 상기 양단의 정착구와 하중전달재 단부에 강선을 설치하고, 최외측의 하중전달재에 고정정착구를 설치하고, 거더의 하부에 스트로크정착구를 설치하면서 강선을 연결하고, 상기 스트로크정착구에 정착된 강선의 단부를 긴장하여 하중전달재가 수직으로 세워지도록 하여 강선이 신장되도록 하고, 상기 발생된 강선의 신장력이 프리스트레스힘으로 전환시켜 프리스트레스가 가시설거더에 도입되도록 한 가시설구조체를 설치한 것을 보여주는 도면.Figure 7 is another method for introducing prestress to the prestress temporary girders for the mudguard of the present invention, the fixing unit is installed on both ends of the prestress temporary girders for the mudguard, a plurality of load transfer material is installed on the front of the temporary girder Steel wires are installed at both ends of the anchorage and the load transfer member, fixed anchoring holes are installed at the outermost load transfer member, and steel wires are connected to the bottom of the girder while the stroke anchoring holes are installed. A diagram showing the installation of a provisional structure in which the end of the steel wire is tensioned so that the load transfer material is erected vertically so that the steel wire is stretched, and the stretched force of the generated steel wire is converted into a prestressing force so that the prestress is introduced into the temporary girder.

도 8은 본 발명의 흙막이용 프리스트레스트가시설거더에 프리스트레스를 도입하는 또 다른 방법으로서, 흙막이용 프리스트레스가시설거더의 양단에 정착구를 설치하고, 상기 가시설거더의 전면에 복수의 하중전달재를 설치하고, 상기 양단의 정착구와 하중전달재 단부에 강선을 설치하고, 상기 하중전달재에 스트로크정착구를 설치하면서 강선을 연결하고, 상기 일측에 설치된 스트로크정착구에 정착된 강선의 단부를 긴장하여, 하중전달재를 수직으로 세워지도록 하여 강선이 신장되도록 하고, 상기 강선에 발생된 신장력이 프리스트레스힘으로 전환시켜 프리스트레스가 가시설거더에 도입되도록 한 가시설구조체를 설치한 것을 보여주는 도면.8 is another method for introducing the prestress to the prestress temporary girder for the mud wall of the present invention, the fixing unit is installed on both ends of the prestress temporary girder for the mud, a plurality of load transfer material is installed on the front of the temporary girder. Steel wires are provided at both ends of the anchorage and load transfer member, and the steel wires are connected while the stroke anchoring hole is installed at the load transfer member, and the ends of the steel wire fixed at the stroke anchoring hole installed at the one side are tensioned to transfer the load. A drawing showing the installation of a provisional structure in which the steel is stretched vertically so that the ash is erected, and the stretching force generated in the steel is converted to the prestressing force so that the prestress is introduced into the temporary girder.

도 9(a)(b)는 흙막이용 프리스트레스트가시설거더의 측면에 정착구가 설치된 정착브라켓을 양측에 설치하고 강선을 연결하고, 상기 정착브라켓과 접하게 설치하되, 상기 흙막이용 프리스트레스트가시설거더의 플랜지에 접하게 설치된 버팀대띠장의 중앙에 유압잭을 설치하여 프리스트레스를 도입하는 것을 보여주는 것으로서, 외력이 클 경우 타이탄성클립으로 플랜지를 밀착시키도록 한 것으을 보여주는 도면.Figure 9 (a) (b) is installed on both sides of the fixing bracket is installed on the side of the prestressed girder for the earth retaining girder connected to the wire, and installed in contact with the fixing bracket, the prestressed girder for the earthen It shows the introduction of prestress by installing the hydraulic jack in the center of the support belt installed in contact with the flange of the drawing.

도 10은 변단면에 설치된 거더와 프리스트레스트가시설거더와의 사이에 중간버팀대를 설치하고, 상기 가시설거더의 양단부에 스트로크발생장치를 설치하고 그 외측에 압력유동장치를 설치하고, 상기 가시설거더의 전면에 복수이상의 하중전달재를 설치하면서 강선을 단부에 접하게 설치하면서 상기 압력유동장치에 설치된 정착구에 강선을 정착한 다음, 스트로크발생장치에 스트로크를 발생시켜 강선이 신장한 다음, 고정시키면 상기 신장력이 프리스트레스힘으로 전환되어 가시설거더에 전달되고 , 상기 가시설거더에 전달된 프리스트레스힘이 중간버팀대에 전달되어 변단면에서 발생되는 외압에 저항 및 상쇄되도록 한 변단면가시설흙막이인 변단면가시설구조체를 설치한 것을 보여주는 도면.Figure 10 is installed between the girder and prestressed girders installed on the side of the girder, the stroke generating device is installed on both ends of the girder girders and a pressure flow device is installed on the outside of the girder The steel wire is fixed to the anchorage installed in the pressure flow device while the steel wire is installed in contact with the end while installing a plurality of load transfer materials on the front surface, and then the stroke is generated by the stroke generating device to stretch the steel wire, and then fix the steel wire. The prestressing force is converted into prestressing force and is transferred to the temporary girder, and the prestressing force transmitted to the temporary girder is transferred to the intermediate brace to install and install the side sectional facility structure, which is the side sectional temporary facility soil wall, which resists and offsets the external pressure generated from the side of the temporary girder. Showing drawings.

도 11은 흙막이용 프리스트레스트가시설거더와의 사이에 일반적인 띠장을 설치하여 간격을 보다 넓게 확보하면서 버팀대와 상기 띠장의 양단에 설치된 가시설거더를 상호 연결하여 버팀대와 가시설연결부를 설치한 것을 보여주는 도면.11 is a view showing the installation of a brace and a provisional connection by interconnecting the brace and the girder installed on both ends of the girdle while securing a wider gap by installing a common band between the girder prestress is the facility girder.

도 12는 흙막이용 프리스트레스트가시설거더와의 사이에 한 개의 버팀대로 지지하도록 한 것을 보여주는 도면.FIG. 12 is a view showing that the prestress for the retainer is supported by one brace between the facility girders; FIG.

도 13은 흙막이용 프리스트레스트가시설거더의 측면에서 각각 버팀대로 지지하되, 상기 버팀대사이에 중간파일을 설치하여 버팀대가 좌굴되는 현상을 방지하도록 한 것을 보여주는 도면.Figure 13 shows that the prestress for the earth support each side as a brace on the side of the facility girder, by installing an intermediate pile between the brace to prevent the brace from buckling.

도 14는 상기 도 1과 같은 흙막이용 프리스트레스트가시설거더의 외측에서 가시설구조체를 보호하기 위한 충돌방호책을 설치한 것을 보여주는 도면.FIG. 14 is a view illustrating a collision protection system for protecting a temporary structure from an outer side of a facility girder prestress such as FIG. 1;

도 15(a)(b)는 도 6, 도 7 및 도 8과 같은 흙막이용 프리스트레스트가시설거더의 전면에 플랜지에 설치된 하중전달재가 스트로크발생장치에 의하여 거동시 하중전달재가 수직으로 세워지면서 모멘트 발생을 방지하기 위하여 슬라이딩볼트결합을 측면과 평면에서 보여주는 도면.Figure 15 (a) (b) is a load transfer material installed in the flange on the front of the earth prestressed girders such as Figures 6, 7, and 8 when the load transfer material is vertically erected by the stroke generating device acts as a moment To show the sliding bolt coupling in side and plane to prevent the occurrence.

<도면의 주요 부분에 대한 설명>   Description of the main parts of the drawing

N.A ; 중립축   N.A; Neutral axis

P ; 거더의 프리스트레스힘 P' ; 강선의 프리스트레스힘   P; Girder prestressing force P '; Prestressing force of steel wire

PV ; 외력상쇄반력 PS ; 스트로크강선의 스트로크작용방향   PV; External force offset reaction PS; Stroke action direction of stroke steel

T ; 접선방향 R ; 직각   T; Tangential direction R; right angle

10 ; 가시설구조체 11 ; 거더   10; Temporary structure 11; Girder

12 ; 버팀대 13 ; 강선   12; Brace 13; Liner

14 ; 플랜지 15 ; 보강판   14; Flange 15; Gusset

16 ; 수직파일 17 ; 강선고정강재   16; Vertical pile 17; Steel wire fixed steel

18 ; 쉬스   18; Sheath

20 ; 흙막이용프리스트레스트가시설거더 21 ; 보강부    20; Prestressed girders 21; Reinforcement

22 ; 슬라이딩공간부   22; Sliding space part

23 ; 정착구 24 ; 하중전달재   23; Anchorage 24; Load transfer material

25 ; 압력조절강재 26 ; 원중심축   25; Pressure regulating steel 26; Central axis

27 ; 원중심 28 ; 베이스강판   27; Centroid 28; Base steel

29 ; 정착브라켓    29; Fixing Bracket

30 ; 스트로크발생장치 31 ; 강관    30; Stroke generator 31; Steel pipe

32 ; 유압잭 33 ; 지압지지강판   32; Hydraulic jack 33; Acupressure Supporting Steel Sheet

34 ; 볼트 35 ; 장나비너트   34; Bolt 35; Long Butterfly Nut

36 ; 나사산 37 ; 용접   36; Thread 37; welding

38 ; 볼트너트결합 39 ; 너트    38; Bolt nut coupling 39; nut

40 ; 강선가이드장치 41 ; 가이드판   40; Steel wire guide device 41; Guide plate

42 ; 곡선새들 43 ; 강관새들   42; Curved saddles 43; Steel pipe birds

44 ; 파이프핀부 45 ; 강선이탈방지봉   44; Pipe pin 45; Steel wire escape prevention rod

46 ; 하중측정센서 47 ; 채널   46; Load measuring sensor 47; channel

48 ; 충돌방호책 49 ; 띠장연장부    48; Collision protection measures 49; Sash extension

50 ; 흙막이용 프리스트레스트가시설이중띠장   50; Prestressed Furniture Double Belt

51 ; 장공 52 ; 와샤   51; Long 52; Washa

53 ; 스테인레스판 54 ; 수직앵글   53; Stainless plate 54; Vertical angle

55 ; 수평앵글   55; Horizontal angle

60 ; 변단면가시설구조체 61 ; 중간버팀대   60; Side sectional structure 61; Middle brace

62 ; 배면부    62; Back

71 ; 버팀대띠장 73 ; 슬라이딩볼트결합   71; Brace 73; Sliding Bolt

74 ; 스트로크강선 75 ; 고정정착구   74; Stroke steel 75; Fixing Fixture

76 ; 스트로크정착구 77 ; 중간파일   76; Stroke fitting 77; Intermediate file

78 ; 타이탄성클립 79 ; 밀착부   78; Titanium clip 79; Contact

80 ; 탄성클립   80; Elastic Clip

100 ; 버팀대와 가시설거더연결부 101 ; 지압보강대   100; Brace and temporary girder connection 101; Shiatsu reinforcement

102 ; 스크류잭 103 ; 경사버팀대   102; Screw jack 103; Inclined brace

Claims (37)

양단부에 지압지지강판(33)을 설치한 흙막이용 프리스트레스트가시설거더 (20)와, 상기 흙막이용 프리스트레스트가시설거더(20)와 압력조절강재(25) 사이에 설치된 스트로크발생장치(30)와, 상기 압력조절강재(25)와 거더(11) 사이에 설치된 슬라이딩공간부(22)와, 상기 거더(11)의 일측면과, 압력조절강재(25)의 일측면을 각각 연결한 버팀대(12)와, 상기 압력조절강재(25)의 측면인 복부에 설치된 정착구 (23)와, 상기 흙막이용 프리스트레스트가시설거더(20)의 하부 플랜지(14)에 슬라이딩볼트결합(73)되어 복수개 이상 설치된 하중전달재(24)와, 상기 하중전달재(24)의 단부에 강선이 포물선으로 설치될 수 있도록 설치된 강선가이드장치(40)와, 상기 양측의 정착구(23)에 강선(13)을 연결하면서 강선가이드장치(40)에 강선을 거치한 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 프리스트레스를 도입한 가시설거더.Pre-stressed temporary girders 20 for earth retaining, which is provided with acupressure supporting steel plate 33 at both ends, and the stroke generating device 30 provided between the prestressed temporary girder 20 for earthing and the pressure regulating steel 25 And, the brace connecting the sliding space portion 22 provided between the pressure regulating steel 25 and the girder 11, one side of the girder 11, and one side of the pressure regulating steel 25 ( 12), the fixing fixture 23 provided in the abdomen which is the side of the pressure regulating steel 25, and the sliding bolt coupling 73 to the lower flange (14) of the prestressed temporary girders 20 for the earth retaining plural number or more The wire transfer device 24 is connected to the load transfer member 24 installed, the wire guide device 40 installed at the end of the load transfer member 24 so that the steel wire is installed as a parabola, and the fixing holes 23 at both sides thereof. While exerting force on the steel wire characterized by mounting the steel wire on the wire guide device 40 Temporary girder which adopts prestress including apparatus to make. 양단부에 지압지지강판(33)을 설치한 흙막이용 프리스트레스트가시설거더(20)와, 상기 흙막이용 프리스트레스트가시설거더(20)의 양측단부에 각각 연결설치된 강선고정강재(17)와, 상기 강선고정강재(17)의 측면과 연결한 버팀대(12)와, 상기 강선고정강재(17)의 측면인 복부에 설치된 정착구(23)와, 상기 흙막이용 프리스트레스가시설거더(20)의 전면 플랜지(14)에 슬라이딩볼트결합(73)되어 복수개 설치된 하중전달재(24)와, 상기 설치된 하중전달재(24)사이에 설치된 버팀대띠장(71)과, 상기 버팀대띠장(71)의 사이에 유압잭(32)이 설치된 스트로크발생장치(30)와, 상기 하중전달재(24)의 단부에 강선이 유연한 포물선으로 설치될 수 있도록 설치된 강선가이드장치(40)와, 상기 양측의 정착구(23)에 강선(13)을 연결하면서 강선가이드장치(40)에 강선을 거치한 가시설구조체(10)인 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 프리스트레스를 도입한 가시설거더. Prestressed temporary girders 20 for earth retaining, which is provided with acupressure supporting steel plate 33 at both ends, and the steel wire fixed steel 17 is connected to both ends of the prestressed temporary girder 20 for earthing; Brace 12 connected to the side of the steel wire fixed steel 17, the anchorage 23 is installed on the abdomen that is the side of the steel wire fixed steel 17, and the front flange of the prestress temporary girder 20 for the mud 14, a hydraulic bolt (32) is provided between the load transfer member (24) provided with a plurality of sliding bolts (73) installed between the load transfer member (24) and the support belt (71) installed between the installed load transfer member (24) and the support belt (71). ) Is installed in the stroke generating device 30, the wire guide device 40 is installed so that the steel wire is installed in a flexible parabola at the end of the load transfer material 24, the steel wire 13 to the fixing holes 23 on both sides (2) Fixture zone mounted steel wire to wire guide device (40) while connecting A gasiseol girder introducing a prestress, including apparatus for generating a stretching force to the liner is characterized in that the body (10). 양단부에 지압지지강판(33)을 설치한 흙막이용 프리스트레스트 가시설거더Prestressed girder girders for earthquakes with acupressure bearing steel plates 33 at both ends (20)와, 상기 흙막이용 프리스트레스트가시설거더(20)의 양측단부에 각각 연결설치된 강선고정강재(17)와, 상기 강선고정강재(17)의 측면과 연결한 버팀대(12)와, 상기 강선고정강재(17)의 측면인 복부에 설치된 정착구(23)와, 상기 흙막이용 프리스트레스가시설거더(20)의 전면 플랜지(14)에 슬라이딩볼트결합(73)되어 복수개 이상 설치된 하중전달재(24)와, 상기 최외측에 설치된 하중전달재(24)에 설치된 고정정착구(75)와, 상기 가시설거더(20)의 플랜지(14)에 설치된 스트로크정착구(76)와, 상기 각각의 정착구(75,76)에 상호 연결정착한 스트로크강선(74)과, 상기 하중전달재(24)의 단부에 강선이 유연한 포물선으로 설치될 수 있도록 설치된 강선가이드장치(40)와, 상기 양측의 정착구(23)에 강선(13)을 연결하면서 강선가이드장치(40)에 강선을 거치한 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 프리스트레스를 도입한 가시설거더. (20), the steel wire fixed steel (17) connected to each side end portion of the prestress for masonry girders 20, and the brace 12 connected to the side of the steel wire fixed steel (17), and Load transfer member (24) provided with a plurality of fixing bolts (73) installed in the abdomen, which is the side of the steel wire fixed steel (17), and a plurality of sliding bolts (73) to the front flange (14) of the prestressing girders (20) ), A fixed fixture 75 provided in the outermost load transfer member 24, a stroke anchor 76 provided in the flange 14 of the temporary girder 20, and each of the anchors 75, At the end of the load transfer member 24, the wire guide device 40 installed at the end of the load transfer member 24, and the fixing wire 23 at both sides thereof. While connecting the steel wire 13 is characterized in that the steel wire is mounted on the wire guide device 40 Temporary girder with prestressing including a device that generates elongation force on steel wire. 양단부에 지압지지강판(33)을 설치한 흙막이용 프리스트레스트가시설거더(20)와, 상기 흙막이용 프리스트레스트가시설거더(20)의 양측단부에 각각 연결설치된 강선고정강재(17)와, 상기 강선고정강재(17)의 측면과 연결한 버팀대(12)와, 상기 강선고정강재(17)의 측면인 복부에 설치된 정착구(23)와, 상기 흙막이용 프리스트레스가시설거더 (20)의 전면 플랜지(14)에 슬라이딩볼트결합(73)되어 복수개 설치된 하중전달재 (24)와, 상기 양측에 설치된 하중전달재(24)의 하부에 설치된 스트로크정착구(76)와, 상기 스트로크정착구(76)에 상호 연결정착한 스트로크강선(74)과, 상기 하중전달재(24)의 단부에 강선이 포물선으로 설치될 수 있도록 설치된 강선가이드장치(40)와, 상기 양측의 정착구(23)에 강선(13)을 연결하면서 강선가이드장치(40)에 강선을 거치한 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 프리스트레스를 도입한 가시설거더.Prestressed temporary girders 20 for earth retaining, which is provided with acupressure supporting steel plate 33 at both ends, and the steel wire fixed steel 17 is connected to both ends of the prestressed temporary girder 20 for earthing; Brace 12 connected to the side of the steel wire fixed steel 17, the anchorage 23 is installed on the abdomen that is the side of the steel wire fixed steel 17, and the front flange of the prestress temporary girder 20 for the mud 14) a plurality of load transfer members (24) installed on the sliding bolts (73) and the lower part of the load transfer members (24) provided on both sides thereof, and the stroke fixing holes (76) installed at the lower sides, and interconnected to the stroke fixing holes (76). The steel wire 13 is connected to the fixed stroke steel wire 74, the wire guide device 40 installed so that the steel wire can be installed as a parabola at the end of the load transfer member 24, and the fixing holes 23 on both sides. While the steel wire is mounted on the wire guide device 40 is characterized by A temporary girder with prestressing, including a device for generating elongation in steel wires. 변단면을 포함하는 굴착면을 따라 다수개 설치된 수직파일(16)과, 상기 수직파일에 접하여 거더(11)를 설치한 가시설구조체(10)와, 상기 변단면의 시종점의 단면에 설치된 양단부에 지압지지강판(33)을 설치한 흙막이용 프리스트레스트가시설거더(20)와, 상기 흙막이용 프리스트레스트가시설거더(20)의 양측에 연결설치된 압력조절강재(25)와, 상기 압력조절강재(25)의 측면에 일정범위에서 이동할 수 있도록 형성된 슬라이딩공간부(22)와, 상기 슬라이딩공간부(22)에 접하게 설치된 거더(11)와, 상기 슬라이딩공간부(22)의 좌우에 설치된 거더(11)와 압력조절강재(25)의 일측면과 버팀대(12)의 측면을 볼트너트결합(38)하여 지지하고, 상기 압력조절강재(25)의 측면인 복부에 설치된 정착구(23)와, 상기 압력조절강재(25)와 흙막이용 프리스트레스트가시설거더(20) 사이에 설치된 스트로크발생장치(30)와, 상기 거더(11)의 양측부의 띠장연장부(49)를 상기 압력조절강재(25)의 측면에 부착설치하고, 상기 거더(11)와 흙막이용 프리스트레스가시설거더(20)사이에 다수개 설치된 중간버팀대(61)와, 상기 흙막이용 프리스트레스트가시설거더(20) 전면 플랜지(14)에 슬라이딩볼트결합(73)되어 복수개 이상 설치된 하중전달재(24)와, 상기 하중전달재(24)의 단부에 강선이 접하여 설치될 수 있도록 강선가이드장치(40)를 설치하고, 상기 강선가이드장치의 사이를 통과하여 설치된 강선(13)을 양측에 설치된 정착구(23)에 정착하고, 상기 하중전달재(24)의 단부에서 일정거리 떨어지게 양측에 설치된 버팀대(12)와의 사이에 충돌방호책(48)이 설치된 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 프리스트레스를 도입한 가시설거더.A plurality of vertical piles (16) provided along the excavation surface including the end face, a temporary structural structure (10) provided with a girder (11) in contact with the vertical pile, and at both ends provided in the cross section of the starting point of the end face The prestressed temporary girders 20 for the mudstone and the pressure regulating steel 25 installed on both sides of the prestressed temporary girders 20 for the mudstone, and the pressure regulating steel ( Sliding space 22 formed to move in a predetermined range on the side of the 25, the girder 11 is provided in contact with the sliding space 22, the girder 11 is installed on the left and right of the sliding space 22. ) And one side of the pressure regulating steel 25 and the side of the brace 12 are supported by the bolt nut coupling 38, the fixing unit 23 installed in the abdomen which is the side of the pressure regulating steel 25, and the pressure Between adjustable steel (25) and prestressed girders (20) The installed stroke generating device 30 and the band extension portions 49 on both sides of the girder 11 are attached to the side of the pressure regulating steel 25, and the girder 11 and the prestress provision girder for the mud wall are installed. A plurality of intermediate props (61) installed between the (20) and the load transfer member (24) installed at least a plurality of sliding bolts coupled to the front flange (14) of the prestressed girder (20) for the retaining wall (20); The steel wire guide device 40 is installed so that the steel wire can be installed in contact with the end of the load transfer member 24, and the steel wire 13 installed to pass through between the steel wire guide device to the fixing unit 23 installed on both sides. A prestress including a device for fixing the steel wire, which is characterized in that a collision protection measure 48 is provided between the braces 12 provided on both sides of the rod transfer member 24 at a predetermined distance away from the end of the load transfer member 24. Temporary . 거더(11)의 측면에 설치된 정착구가 설치된 정착브라켓(29)과, 상기 정착브라켓을 상호 연결한 강선(13)과, 상기 정착브라켓(29)과 접하게 설치하되, 양단부에 지압지지강판(33)을 설치한 흙막이용 프리스트레스트가시설거더(20)의 플랜지에 접하게 설치된 버팀대띠장(71)과 상기 버팀대띠장의 중앙에 설치된 유압잭(32)으로 이루어진 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 프리스트레스를 도입한 가시설거더.A fixing bracket (29) having a fixing device installed on the side of the girder (11), a steel wire (13) interconnecting the fixing brackets, and the fixing bracket (29) are installed in contact with the acupressure bearing steel plate (33) at both ends. Prestressing for the earthquake block is installed with a brace jangjang 71 installed in contact with the flange of the facility girder 20 and the hydraulic jack (32) installed in the center of the brace including a device for generating a stretch force in the steel wire Temporary girder with prestress. 제 1항 또는 제 5항에 있어서,The method according to claim 1 or 5, 상기 스트로크발생장치(30)는 압력조절강재(25)와 흙막이용 프리스트레스트가시설거더(20)의 단부에 지압지지강판(33)을 각각 부착하고, 상기 양측의 지압지지강판(33)과의 사이의 중앙에 유압잭(32)을 설치하고, 상기 유압잭(32)의 상하에, 압력조절강재(25)의 단부에 설치된 지압지지강판(33)에 강관(31)을 용접부착하고, 상기 강관(31)에 볼트(34)를 부착하고, 스트로크를 이동시킨 다음, 상기 볼트(34)에 장나비너트 (35)를 체결하면서, 상기 흙막이용 프리스트레스트가시설거더(20)의 단부에 설치된 지압지지강판(33)을 관통하여 돌출된 볼트(34)단부에 너트(39)로 체결한 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 프리스트레스를 도입한 가시설거더.      The stroke generating device 30 is attached to the pressure-bearing steel plate 25 and the pressure-bearing steel plate 33 at the ends of the prestress temporary girders 20 for the retaining wall, respectively, and the pressure-bearing steel plate 33 on both sides The hydraulic jack 32 is provided in the center between them, and the steel pipe 31 is welded to the acupressure supporting steel plate 33 provided at the end of the pressure regulating steel 25 above and below the hydraulic jack 32, and the steel pipe 31 is welded. ) Attaching the bolt 34, the stroke is moved, and then fastening the long bow nut (35) to the bolt (34), the acupressure supporting steel sheet provided at the end of the prestressed girders (20) A temporary girder incorporating a prestress including a device for generating an extension force in a steel wire characterized by fastening with a nut (39) to a bolt (34) end that protrudes through (33). 제 1항 또는 제5항에 있어서The method according to claim 1 or 5 상기 스트로크발생장치(30)는 압력조절강재(25)와 흙막이용 프리스트레스트가시설거더(20)의 단부에 지압지지강판(33)을 각각 부착하고, 상기 양측의 지압지지강판(33)과의 사이의 중앙에 유압잭(32)을 설치하면서 하중측정센서(46)를 설치하고, 상기 유압잭(32)의 상하에, 압력조절강재(25)의 단부에 설치된 지압지지강판(33)에 강관(31)을 용접부착하고, 상기 강관(31)에 볼트(34)를 용접부착하고, 스트로크를 이동시킨 다음, 상기 볼트(34)에 장나비너트(35)를 체결하면서 상기 흙막이용 프리스트레스트가시설거더(20)의 단부에 설치된 지압지지강판(33)을 관통하여 돌출된 볼트(34)단부에 너트(39)로 체결한 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 프리스트레스를 도입한 가시설거더.      The stroke generating device 30 is attached to the pressure-bearing steel plate 25 and the pressure-bearing steel plate 33 at the ends of the prestress temporary girders 20 for the retaining wall, respectively, and the pressure-bearing steel plate 33 on both sides The load measuring sensor 46 is installed while the hydraulic jack 32 is provided at the center between the steel pipes 31 on the pressure bearing steel plate 33 provided at the end of the pressure regulating steel 25 above and below the hydraulic jack 32. ) Welding, attaching the bolt 34 to the steel pipe 31, moving the stroke, and then fastening the long bow nut 35 to the bolt 34, the prestress temporary girders 20 And a prestress incorporating a prestressing device including a device for generating extension force in a steel wire characterized by fastening with a nut (39) to a bolt (34) end that protrudes through the acupressure supporting steel plate (33) provided at the end of the head. 제 1항 또는 제5항에 있어서The method according to claim 1 or 5 상기 스트로크발생장치(30)는 압력조절강재(25)와 흙막이용 프리스트레스트가시설거더(20)의 단부에 지압지지강판(33)을 각각 부착하고, 상기 양측의 지압지지강판(33)과의 사이의 중앙에 유압잭(32)을 설치하면서 하중측정센서(46)를 설치하고, 상기 유압잭(32)의 상하에, 압력조절강재(25)의 단부에 설치된 지압지지강판(33)에 채널(47)을 용접부착하고, 상기 채널(47)에 볼트(34)를 용접부착하고, 상기 흙막이용 프리스트레스트가시설거더(20)의 단부에 설치된 장나비너트(35)에 상기 볼트(34)를 볼트체결하면서 상기 흙막이용 프리스트레스트가시설거더(20)의 단부에 설치된 지압지지강판(33)을 관통하여 돌출된 볼트(34)단부에 너트(39)로 체결한 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 프리스트레스를 도입한 가시설거더.The stroke generating device 30 is attached to the pressure-bearing steel plate 25 and the pressure-bearing steel plate 33 at the ends of the prestress temporary girders 20 for the retaining wall, respectively, and the pressure-bearing steel plate 33 on both sides The load measuring sensor 46 is installed while the hydraulic jack 32 is provided at the center thereof, and the channel 47 is provided on the pressure bearing steel plate 33 provided at the end of the pressure regulating steel 25 above and below the hydraulic jack 32. ), And attaching the bolt 34 to the channel 47, while bolting the bolt 34 to the long butterfly nut 35 provided at the end of the earth girders 20 Apparatus for generating a stretch force in a steel wire characterized in that the prestressing prestress for cladding is fastened with a nut 39 to the end of the bolt (34) protruding through the pressure bearing steel plate 33 installed at the end of the facility girder 20 Incorporating pre-stressed girders, including. 제 1항 내지 제5항중의 어느 한 항에 있어서The method according to any one of claims 1 to 5 상기 하중전달재(24)는 흙막이용 프리스트레스트가시설거더의 전면 플랜지에 설치될때 상기 하중전달재(24)의 원중심축(26)이 강선의 배치 형상인 원형상의 원중심(27)을 향하도록 설치되도록 하면서 곡선새들(42)에 강선(13)이 접하는 부분이 원중심축(26)과 강선(13)의 접선방향(T)에 직각(R)이 되도록 설치한 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 프리스트레스를 도입한 가시설거더.When the load transfer member 24 is installed on the front flange of the facility girders, the central axis 26 of the load transfer member 24 is directed toward the circular center 27 in the shape of the steel wire arrangement. While the steel wire 13 is in contact with the curved saddle 42 while being installed so as to be perpendicular to the tangential direction (T) of the central axis 26 and the steel wire 13 to the steel wire characterized in that the installation Temporary girder with prestressing, including a device that generates elongation. 제 1항 내지 제5항 중의 어느 한 항에 있어서The method according to any one of claims 1 to 5. 상기 강선가이드장치(40)는 하중전달재(24)의 단부에 베이스강판(28)과 보강판(15)을 설치하고, 상기 베이스강판을 포함하는 하중전달재(24)의 양측에 가이드판(41)을 설치하고, 상기 가이드판(41)의 사이의 베이스강판(28)에 부착하여 강선이 접하는 면이 볼록한 곡면을 갖는 곡선새들(42)을 부착설치하고, 상기 곡선새들(42)의 곡면에 강선을 접촉설치하면서 상기 양측에 설치된 가이드판(41)의 상부를 관통하여 강선이탈방지봉(45)을 설치한 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 프리스트레스를 도입한 가시설거더.      The steel wire guide device 40 is provided with a base steel plate 28 and a reinforcing plate 15 at the end of the load transfer member 24, the guide plate (on both sides of the load transfer member 24 including the base steel plate) 41 is installed, and attached to the base steel plate 28 between the guide plate 41, and install the curved birds 42 having a curved surface convex surface of the steel wire, the curved surface of the curved birds 42 A temporary girder incorporating prestressing including a device for generating an extension force in a steel wire characterized by installing a steel wire break-away bar 45 by penetrating upper portions of the guide plates 41 installed on both sides thereof while contacting the steel wire. 제 1항 내지 제5항중의 어느 한항에 있어서 The method according to any one of claims 1 to 5 상기 하중전달재에 강선을 이중으로 설치하는 경우에는 상기 하중전달재(24)의 단부에 베이스강판(28)과 보강판을 설치하고, 상기 베이스강판(28)을 포함하면서 내측에는 상하로 파이프핀부(44)가 설치된 가이드판(41)을 양측에 설치하고, 상기 가이드판(41)에 설치된 파이프핀부(44)에 강관새들(43)의 측면에 형성된 홈이 삽입되도록 상하로 설치하고, 상기 강관새들(43)에 접하게 강선(13)을 각각 설치하고, 상기 강선(13)이 상하로 강관새들(43)에 접하게 설치한 후에, 상기 가이드판(41)의 상부에 강선이탈방지봉(45)을 설치하여 강선(13)이 이탈되는 것을 방지한 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 프리스트레스를 도입한 가시설거더.When the steel wire is installed in the load transfer member in a double manner, a base steel plate 28 and a reinforcement plate are installed at the ends of the load transfer member 24, and the pipe pins are disposed up and down inside the base steel plate 28. The guide plate 41 provided with the 44 is installed on both sides, the pipe pin portion 44 provided in the guide plate 41 is installed up and down so that the groove formed in the side of the steel pipe birds 43 is inserted, the steel pipe After each of the steel wire 13 is installed in contact with the saddle 43, and the steel wire 13 is installed in contact with the steel pipe birds 43 up and down, the steel wire escape prevention bar 45 on the upper portion of the guide plate 41 The provisional girder which introduces the prestress including the apparatus which generate | occur | produces a stretch force in the steel wire which is characterized by installing the steel wire 13 is prevented from being separated. 제 1항 내지 제5항중의 어느 한항에 있어서 The method according to any one of claims 1 to 5 상기 흙막이용 프리스트레스트가시설거더(20)를 측면에서 상호 연결한 부분에 하중전달재(24)를 일렬로 다수개 설치한 것에 의하여 지지되도록 한 흙막이용 프리스트레스트가시설이중거더(50)인 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 프리스트레스를 도입한 가시설거더.      The prestress for the mud prestress is a double girders (50) for the mud prestress to be supported by the installation of a plurality of load transfer material 24 in a line interconnecting the facility girder 20 in the side Temporary girder with prestressing, including a device that generates elongation on characteristic steel wire. 제 1항 내지 제5항중의 어느 한항에 있어서The method according to any one of claims 1 to 5 상기 양측의 흙막이용 프리스트레스트가시설거더(20)와의 사이에 거더(11)를 설치하고 볼트너트결합(38)하고, 상기 볼트너트결합한 양측 부분의 플랜지(14)에 지압보강대(101)를 설치하고, 상기 지압보강대(101)의 중앙에 버팀대(12)를 설치하고, 상기 양측의 지압보강대(101)에 경사버팀대(103)를 설치하고, 상기 중앙의 버팀대(12)의 연장부와 양측의 경사버팀대(103)가 만나는 부분에 보강부(21)를 설치하고, 상기 보강부(21)의 외측에 스크류잭(102)를 설치하고, 상기 스크류잭의 외측에 버팀대(12)를 설치하여 상호 연결하여 지지되도록 버팀대와 가시설거더연결부(100)를 설치한 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 프리스트레스를 도입한 가시설거더.      The girders 11 are installed between the prestressed girders 20 on both sides of the earthen board and bolt nut coupling 38, and the acupressure reinforcement 101 is installed on the flanges 14 at both sides of the bolt nut coupling. The brace 12 is installed at the center of the acupressure reinforcement 101, and the inclined brace 103 is provided at the acupressure reinforcement 101 at both sides, and the extensions and both sides of the central brace 12 are provided. The reinforcement part 21 is installed in the part where the inclined brace 103 meets, the screw jack 102 is installed in the outer side of the reinforcement part 21, and the brace 12 is installed in the outer side of the screw jack, and mutually Reinforced girder with a prestress including a device for generating a stretch force in the steel wire characterized by the installation of the brace and the temporary girder connecting portion 100 to be connected and supported. 제 1항 내지 제5항 중의 어느 한 항에 있어서The method according to any one of claims 1 to 5. 소정의 간격을 두고 설치된 양측 흙막이용 프리스트레스트가시설거더(20)의 플랜지를 연결한 지압보강대(101)를 설치하고, 상기 지압보강대(101)의 측면 중앙에 버팀대(12)를 설치하고, 연이어서 스크류잭(21)을 설치하고, 그 외측에 버팀대(12)를 연결설치하여 지지되도록 한 버팀대와 가시설거더연결부(100)를 설치한 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 프리스트레스를 도입한 가시설거더.      Install acupressure reinforcement 101 connecting the flanges of the prestressed girders 20 on both sides of the mudguard at a predetermined interval, and install a support 12 at the center of the side of the acupressure reinforcement 101, Subsequently, a prestress including a device for generating extension force in a steel wire characterized by installing a screw jack 21 and installing a brace and a temporary girder connecting portion 100 to be supported by connecting and installing a brace 12 on the outside thereof. Introduced temporary girder. 제 1항 내지 제5항 중의 어느 한 항에 있어서The method according to any one of claims 1 to 5. 소정의 간격을 두고 설치된 양측 흙막이용 프리스트레스트가시설거더(20)의 각각의 플랜지에 버팀대(12)를 각각 연결하고, 상기 연결된 버팀대(12)의 사이에 중간파일(77)을 설치하여 양측에 설치된 버팀대(12)의 좌굴을 방지하면서 지지하도록 한 버팀대와 가시설거더연결부(100)를 설치한 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 프리스트레스를 도입한 가시설거더.The braces 12 are connected to the flanges of the prestressed girders 20 on both sides installed at predetermined intervals, respectively, and intermediate piles 77 are installed between the braces 12 connected to both sides. Reinforced girder including pre-stress including a device for generating a stretch force in the steel wire characterized by the installation of the brace and the temporary girder connecting portion 100 to support while preventing buckling of the installed brace (12). 제 1항 내지 제 5항 중의 어느 한 항에 있어서The method according to any one of claims 1 to 5. 상기 버팀대(12)와 버팀대(12) 사이에 수직앵글(54)을 상하로 설치하고, 상기 버팀대(12)와 수직앵글(54)이 상호 만나는 부분에 수평앵글(55)을 설치하여 보강한 충돌방호책(48)인 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 프리스트레스를 도입한 가시설거더.      Collision reinforced by installing a vertical angle 54 between the brace 12 and the brace 12 up and down, and installing a horizontal angle 55 at the portion where the brace 12 and the vertical angle 54 meet each other. The temporary girder which introduced the prestress which included the apparatus which generate | occur | produces a stretch force in the steel wire which is characterized by being the protection measure 48. 제1항 내지 제5항중의 어느 한 항에 있어서 The method according to any one of claims 1 to 5 상기 슬라이딩볼트결합(73)은 플랜지(14)의 하부에 스테인레스판(53)을 설치하고, 그 다음에 보강판(15)을 설치하고, 그 다음에 하중전달재(24)를 설치하되, 상기 플랜지(14), 스테인레스판(53) 및 보강판(15)에 장공(51)을 형성하여 상호 관통되도록 하고, 상기 장공(51) 외측의 상하부에 와샤(52)를 설치하고, 상기 와샤(52)와 장공(51)을 관통한 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 프리스트레스를 도입한 가시설거더.      The sliding bolt coupling 73 is provided with a stainless plate 53 in the lower portion of the flange 14, and then install the reinforcement plate 15, and then install a load transfer material 24, A long hole 51 is formed in the flange 14, the stainless plate 53, and the reinforcing plate 15 so as to penetrate each other. A washer 52 is provided at an upper and lower part of the outside of the long hole 51, and the washer 52 And a pre-stressed girder including a device for generating an elongation force on a steel wire characterized by penetrating the hole and the long hole (51). 제 6항에 있어서,The method of claim 6, 상기 거더(11)와 버팀대띠장이 강합성되는 것은 외력이 작용될때 상기 거더(11)가 하부로 변형되어 휘고, 프리스트레스에 의하여는 버팀대띠장(71)이 상부로 휘어, 상기 거더(11)와 버팀대띠장(71)이 상호 밀착되어 일체성으로 결합되어 합성단면을 이루게되도록 한 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 프리스트레스를 도입한 가시설거더.      When the girder 11 and the brace are rigidly combined, the girder 11 is deformed downward when the external force is applied, and the brace 11 is bent upward by the prestress, and the girder 11 and the brace Girder 71 is a pre-stressed girders including a device for generating an elongation force in the steel wire characterized by the close contact with each other to be integrally coupled to form a synthetic cross-section. 제 19항에 있어서,The method of claim 19, 상기와 같이 합성될때 외력이 클 경우에는, 상기 거더(11)의 플랜지(14)와 버팀대띠장(71)의 플랜지(14)가 상호 접하는 부분에 오메가 형상인 타이탄성클립(78)의 밀착부(79)를 밀착시키고, 밀착부(79)와 연결된 탄성클립(80)을 관통하여 볼트너트(38)로 결합, 체결한 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 프리스트레스를 도입한 가시설거더.       When the external force is large when synthesized as described above, the contact portion of the titanium elastic clip 78 having an omega shape in a portion where the flange 14 of the girder 11 and the flange 14 of the brace long 71 are in contact with each other ( 79) and a pre-stressed girder including a device for generating an elongation force in a steel wire characterized by being coupled and fastened with a bolt nut 38 through the elastic clip 80 connected to the close contact portion 79. . 흙막이용 프리스트레스트 가시설거더(20)의 양측단부에 압력조절강재(25)를 연결설치하고, The pressure regulating steel (25) is connected to both ends of the prestressed temporary girder (20) for the earth retainer, 상기 압력조절강재(25)의 측면에 일정범위에서 이동할 수 있는 슬라이딩공간부(22)를 설치하고,       On the side of the pressure regulating steel 25 is installed a sliding space 22 which can move in a certain range, 상기 압력조절강재와 거더(11)의 측면에서 버팀대(12)와 연결하고,     Connect with the brace 12 in the side of the pressure-controlled steel and the girder 11, 상기 압력조절강재(25)의 측면인 복부에 정착구(23)를 설치하고,       The fixing port 23 is installed in the abdomen which is a side surface of the pressure regulating steel 25, 상기 압력조절강재(25)와 양단부에 지압지지강판(33)을 설치한프리스트레스트가시설거더(20) 사이에 형성된 간격내에 스트로크발생장치(30)를 설치하고,       The stroke generating device 30 is installed within the gap formed between the pressure regulating steel 25 and the prestressing steel plate 33 provided at both ends of the facility girder 20, 상기 흙막이용 프리스트레스트가시설거더(20)의 하부 플랜지(14)에 복수개 이상 하중전달재(24)를 슬라이딩볼트결합(73)으로 설치하고,       A plurality of load transfer members 24 are installed on the lower flange 14 of the prestress temporary girder 20 for the earth retainer by sliding bolt coupling 73, 상기 하중전달재(24)의 단부에 강선이 포물선으로 설치될 수 있도록 강선가이드장치(40)를 설치하고,       Install the wire guide device 40 so that the wire can be installed as a parabola at the end of the load transfer material 24, 상기 양측의 정착구(23)에 강선(13)을 연결하면서 강선가이드장치(40)에 강선을 거치한 다음, 상기 스트로크발생장치의 유압잭에 스트로크를 발생시켜 압력조절강재를 슬라이딩공간부로 밀어내면 상기 압력조절강재에 정착된 강선이 신장하고 스트로크를 가한 다음, 고정하면, 상기 강선을 늘어나게하던 신장력이 프리스트레스힘으로 전환함과 동시에 하중전달재를 위로 올리는 외력상쇄반력(PV)의 힘이 작용하여 흙막이용 프리스트레스가시설거더에 프리스트레스로 전달되도록 한 가시설구조체(10)인 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 가시설거더에 프리스트레스를 도입하는 방법.The steel wire is mounted on the wire guide device 40 while connecting the steel wire 13 to the fixing holes 23 on both sides, and then a stroke is generated in the hydraulic jack of the stroke generating device to push the pressure regulating steel into the sliding space. When the steel wire settled in the control steel is stretched and applied, and then fixed, the stretch force that stretches the steel wire is converted to prestress force and at the same time, the force of external force offset reaction force (PV) that lifts the load transfer material is applied. A method of introducing prestress into a girder girder comprising a device for generating a stretching force on a steel wire characterized by the prestress being a temporary structural body (10) adapted to be delivered to the girder as a prestress. 흙막이용 프리스트레스트 가시설거더(20)의 양측단부에 각각 강선고정강재(17)를 연결하고,Connect the steel wire fixed steel (17) to both side ends of the prestressed temporary girders (20) for retaining, 상기 강선고정강재(17)의 측면에서 버팀대(12)와 연결하고, In connection with the brace 12 in the side of the steel wire fixed steel 17, 상기 강선고정강재(17)의 측면인 복부에 정착구(23)를 설치하고,       A fixing unit 23 is installed in the abdomen which is a side surface of the steel wire fixed steel 17, 양단부에 지압지지강판(33)을 설치한 흙막이용 프리스트레스가시설거더(20)의 전면 플랜지(14)에 슬라이딩볼트결합(73)으로 복수개의 하중전달재(24)를 설치하고, A plurality of load transfer members 24 are provided by sliding bolt couplings 73 on the front flange 14 of the prestress temporary girder 20 for the retaining wall having the acupressure supporting steel plates 33 at both ends thereof. 상기 하중전달재(24)사이에 버팀대띠장(71)을 설치함과 동시에 상기 버팀대띠장(71)의 사이에 유압잭(32)인 스트로크발생장치(30)를 설치하고,       While installing the support belt 71 between the load transfer member 24 and the stroke generating device 30 that is the hydraulic jack 32 between the support belt 71, 상기 하중전달재(24)의 단부에 강선이 포물선으로 설치될 수 있도록 강선가이드장치(40)를 설치하고,      Install the wire guide device 40 so that the wire can be installed as a parabola at the end of the load transfer material 24, 상기 양측의 정착구(23)에 강선(13)을 연결하면서 강선가이드장치(40)에 강선을 거치한 다음, 상기 유압잭에 스트로크를 발생시켜 버팀대띠장을 외측으로 밀면, 상기 하중전달재가 수직으로 세워지면서 동시에 강선이 위로 올라가는 힘이 발생되고, 고정하면, 상기 위로 올라가는 외력상쇄반력(PV)이 하중전달재에 전달되고, 상기 힘이 흙막이용 프리스트레스트가시설거더에 프리스트레스로 도입되도록 한 가시설구조체(10)인 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 가시설거더에 프리스트레스를 도입하는 방법.       While connecting the steel wire 13 to the fixing fixtures 23 on both sides, the steel wire is mounted on the wire guide device 40, and then a stroke is generated in the hydraulic jack to push the brace to the outside, and the load transfer material is erected vertically. At the same time, the steel wire is raised upward force, and when fixed, the external force offset reaction force (PV) rising upward is transmitted to the load transfer material, the force structure so that the prestress for the mud wall is introduced into the girder pre-stress (10) A method of introducing prestress into a girder girder including an apparatus for generating a stretching force on a steel wire characterized by 흙막이용 프리스트레스트 가시설거더(20)의 양측단부에 각각 강선고정강재(17)를 연결하고,Connect the steel wire fixed steel (17) to both side ends of the prestressed temporary girders (20) for retaining, 상기 강선고정강재(17)의 측면에서 버팀대(12)와 연결하고, In connection with the brace 12 in the side of the steel wire fixed steel 17, 상기 강선고정강재(17)의 측면인 복부에 정착구(23)를 설치하고,       A fixing unit 23 is installed in the abdomen which is a side surface of the steel wire fixed steel 17, 양단부에 지압지지강판(33)을 설치한 흙막이용 프리스트레스가시설거더(20)의 전면 플랜지(14)에 슬라이딩볼트결합(73)으로 복수개 이상의 하중전달재(24)를 설치하고,A plurality of load transfer members 24 are provided by sliding bolt couplings 73 on the front flanges 14 of the prestress temporary girder 20 for the retaining wall having the acupressure supporting steel plates 33 at both ends thereof. 상기 최외측에 설치된 하중전달재(24)에 고정정착구(75)를 설치함과 동시에, 상기 흙막이용 프리스트레스트 가시설거더(20)의 플랜지(14)에 스트로크정착구(76)를 설치하고,The fixed anchoring holes 75 are installed at the load transfer member 24 provided at the outermost side, and the stroke anchoring holes 76 are installed at the flanges 14 of the prestressed girder 20 for the retaining wall. 상기 각각의 정착구(75,76)에 스트로크강선(74)을 상호 연결정착하고,       Connecting and fixing the stroke steel 74 to each of the fixing holes 75 and 76, 상기 하중전달재(24)의 단부에 강선이 포물선으로 설치될 수 있도록 강선가이드장치(40)를 설치하고,     Install the wire guide device 40 so that the wire can be installed as a parabola at the end of the load transfer material 24, 상기 양측의 정착구(23)에 강선(13)을 연결하면서 강선가이드장치(40)에 강선을 거치한 다음, 상기 스트로크정착구에 정착된 스트로크강선을 긴장정착하면, 상기 하중전달재가 외측으로 밀리면서 수직으로 세워지게되고, 이때 강선이 위로 작용하는 힘이 발생되어 하중전달재에 전달되고, 고정하면, 상기 하중전달재에 전달된 상향의 외력상쇄반력(PV) 힘이 흙막이용 프리스트레스트가시설거더에 전달되어 프리스트레스가 도입되도록 한 가시설구조체(10)인 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 가시설거더에 프리스트레스를 도입하는 방법.      When the steel wire is mounted on the steel wire guide device 40 while connecting the steel wire 13 to the fixing holes 23 on both sides, and then the steel wire fixed to the stroke fixing hole is fixedly fixed, the load transfer material is pushed outward and vertically. When the steel wire acts upward, the force is generated and transmitted to the load transfer material, and when fixed, the upward force offset force (PV) force transmitted to the load transfer material is prestressed to the facility girder. A method of introducing prestress into a girder girder comprising a device for generating a stretching force on a steel wire characterized by being a temporary structural body (10) to which the prestress is introduced. 흙막이용 프리스트레스트 가설거더(20)의 양측단부에 각각 강선고정강재(17)를 설치하고, Steel wire fixing steels (17) are respectively installed at both ends of the prestress temporary girder (20) for the earth barrier, 상기 강선고정강재(17)의 측면에서 버팀대(12)와 연결하고, In connection with the brace 12 in the side of the steel wire fixed steel 17, 상기 강선고정강재(17)의 측면인 복부에 정착구(23)를 설치하고, A fixing unit 23 is installed in the abdomen which is a side surface of the steel wire fixed steel 17, 양단부에 지압지지강판(33)을 설치한 흙막이용 프리스트레스가시설거더(20)의 전면 플랜지(14)에 슬라이딩볼트결합(73)으로 복수개의 하중전달재(24)를 설치하고, A plurality of load transfer members 24 are provided by sliding bolt couplings 73 on the front flange 14 of the prestress temporary girder 20 for the retaining wall having the acupressure supporting steel plates 33 at both ends thereof. 상기 양측에 설치된 하중전달재(24)의 하부에 스트로크정착구(76)를 설치하고,      The stroke fixing hole 76 is provided at the lower part of the load transfer member 24 provided at both sides, 상기 스트로크정착구(76)에 스트로크강선(74)을 상호 연결하고,      The stroke steel wire 74 is interconnected to the stroke fixing hole 76, 상기 하중전달재(24)의 단부에 강선이 포물선으로 설치될 수 있도록 강선가이드장치(40)를 설치하고,     Install the wire guide device 40 so that the wire can be installed as a parabola at the end of the load transfer material 24, 상기 양측의 정착구(23)에 강선(13)을 연결하면서 강선가이드장치(40)에 강선을 거치한 다음, 상기 스트로크정착구에 정착된 강선을 긴장하면, 상기 하중전달재가 내측으로 모여지고, 상기 하중전달재가 내측으로 모이면서 동시에 하중전달재가 수직으로 세워지면서 동시에 강선이 위로 올라가는 힘이 발생되어 하중전달재에 전달되고, 고정하면, 상기 위로 오르는 외력상쇄반력(PV)이 전달된 하중전달재에 의하여 흙막이용 프리스트레스트가시설거더에 전달되어 프리스트레스가 도입되도록 한 가시설구조체(10)인 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 가시설거더에 프리스트레스를 도입하는 방법.     When the steel wire is mounted on the steel wire guide device 40 while connecting the steel wire 13 to the fixing holes 23 on both sides, and the steel wire fixed to the stroke fixing hole is tensioned, the load transfer material is collected inward, and the load The transfer material gathers inward and at the same time the load transfer material is erected vertically and at the same time the force of the steel wire is raised and transmitted to the load transfer material. A method of introducing prestress into a temporary girder comprising an apparatus for generating an extension force on a steel wire characterized by being a temporary structural body (10) in which a prestress for earth retaining is transmitted to a facility girder to introduce a prestress. 변단면을 포함하는 굴착면을 따라 다수개 수직파일(16)을 설치하고,Install a plurality of vertical piles (16) along the excavation surface including the side surface, 상기 수직파일에 접하여 거더(11)를 설치한 가시설구조체(10)를 설치하고,Install the temporary structural structure 10 is installed in contact with the vertical pile girders 11, 상기 변단면의 시종점의 단면에 양단부에 지압지지강판(33)을 설치한 흙막이용 프리스트레스트가시설거더(20)를 설치하고, The prestress temporary girder 20 for the mudstone having the acupressure supporting steel plate 33 is installed at both ends in the end face of the starting point of the end face, 상기 흙막이용 프리스트레스트가시설거더(20)의 양측에 압력조절강재(25)를 연결설치하고,Connect the pressure regulating steel 25 to both sides of the prestressed girders 20 for the earth retaining, 상기 압력조절강재(25)의 측면에 일정범위에서 이동할 수 있도록 슬라이딩공간부(22)를 설치하고, Sliding space 22 is installed on the side of the pressure control steel 25 to move in a certain range, 상기 슬라이딩공간부(22)에 접하게 거더(11)를 설치하고,       The girder 11 is installed in contact with the sliding space 22, 상기 거더(11)와 압력조절강재(25)의 측면에서 버팀대(12)와 볼트너트결합(38)하여 지지하고,      On the side of the girder 11 and the pressure regulating steel 25 is supported by the brace 12 and the bolt nut coupling 38, 상기 압력조절강재(25)의 측면인 복부에 정착구(23)를 설치하고,     The fixing port 23 is installed in the abdomen which is a side surface of the pressure regulating steel 25, 상기 압력조절강재(25)와 흙막이용 프리스트레스트가시설거더(20) 사이에 스트로크발생장치(30)를 설치하고,     A stroke generating device 30 is installed between the pressure regulating steel 25 and the prestressed girder 20 for the soil barrier, 상기 거더(11)의 양측부의 띠장연장부(49)를 상기 압력조절강재(25)의 측면에 부착설치하고,      The belt extension parts 49 of both sides of the girder 11 are attached to the side of the pressure regulating steel 25, 상기 거더(11)와 흙막이용 프리스트레스가시설거더(20)사이에 다수개 중간버팀대(61)를 설치하고,     Installing a plurality of intermediate braces 61 between the girder 11 and the pre-stressed temporary girder 20 for the soil barrier, 상기 흙막이용 프리스트레스트가시설거더(20) 전면 플랜지(14)에 복수개 이상 하중전달재(24)를 슬라이딩볼트결합(73)으로 설치하고,      A plurality of load transfer members 24 are installed on the front flange 14 of the prestress temporary girder 20 for the earth retainer by sliding bolt couplings 73, 상기 하중전달재(24)의 단부에 강선이 접하여 설치될 수 있도록 강선가이드장치(40)를 설치하고, 상기 강선가이드장치의 사이를 통과하여 설치된 강선(13)을 양측에 설치된 정착구(23)에 정착하고, 상기 하중전달재(24)의 단부에서 일정거리 떨어지게 양측에 설치된 버팀대(12)와의 사이에 충돌방호책(48)을 설치한 다음, 상기 스트로크발생장치의 유압잭에 스트로크를 발생시켜 압력조절강재를 슬라이딩공간부로 밀어내면 상기 압력조절강재에 정착된 강선이 위로 올라가면서 하중전달재에 위로 올리는 힘이 작용하고, 고정하면, 상기 위로 향하는 외력상쇄반력(PV)이 흙막이용 프리스트레스가시설거더에 전달되면, 상기의 전달된 힘이 다시 중간버팀대에 전달되어 변단면의 거더(11)에 작용하는 외력을 상쇄하도록 한 변단면가시설구조체(60)인 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 가시설거더에 프리스트레스를 도입하는 방법.     The steel wire guide device 40 is installed so that the steel wire can be installed in contact with the end of the load transfer member 24, and the steel wire 13 installed to pass through between the steel wire guide device to the fixing unit 23 installed on both sides. After fixing, the collision protection measure 48 is installed between the braces 12 provided on both sides away from the end of the load transfer member 24, and then a stroke is generated in the hydraulic jack of the stroke generating device to generate pressure stroke. When pushed to the sliding space portion of the steel wire is fixed to the pressure regulating steel is raised up the force acting on the load transfer material, and when fixed, the external force offset reaction force (PV) is transmitted to the pre-stressed facility girder for the mud wall When the transmitted force is transmitted to the intermediate brace again, it is characterized in that the side cross-facing facility structure 60 to offset the external force acting on the girder 11 of the side cross section. A method for introducing a prestress in gasiseol girders including apparatus for generating a stretching force to the liner. 제 21항 또는 제 25항에 있어서,The method of claim 21 or 25, 상기 스트로크발생장치(30)는 압력조절강재(25)와 흙막이용 프리스트레스트가시설거더(20)의 단부에 지압지지강판(33)을 각각 부착하고, 상기 양측의 지압지지강판(33)과의 사이의 중앙에 유압잭(32)을 설치하고, 상기 유압잭(32)의 상하에, 압력조절강재(25)의 단부에 설치된 지압지지강판(33)에 강관(31)을 용접부착하고, 상기 강관(31)에 볼트(34)를 부착하고, 스트로크를 이동시킨 다음, 상기 볼트(34)에 장나비너트(35)를 체결하면서 상기 흙막이용 프리스트레스트가시설거더(20)의 단부에 설치된 지압지지강판(33)을 관통하여 돌출된 볼트(34)단부에 너트(39)로 체결한 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 가시설거더에 프리스트레스를 도입하는 방법.      The stroke generating device 30 is attached to the pressure-bearing steel plate 25 and the pressure-bearing steel plate 33 at the ends of the prestress temporary girders 20 for the retaining wall, respectively, and the pressure-bearing steel plate 33 on both sides The hydraulic jack 32 is provided in the center between them, and the steel pipe 31 is welded to the acupressure supporting steel plate 33 provided at the end of the pressure regulating steel 25 above and below the hydraulic jack 32, and the steel pipe 31 is welded. Attach the bolt 34 to the bolt, move the stroke, and then fasten the long bow nut 35 to the bolt 34 while the acupressure supporting steel sheet installed at the end of the prestressed girders 20 for the retaining wall ( 33) A method for introducing prestress into a girder girder including a device for generating an extension force on a steel wire characterized by fastening with a nut (39) to a bolt (34) end that protrudes through (33). 제 21항 또는 제25항에 있어서The method according to claim 21 or 25. 상기 스트로크발생장치(30)는 압력조절강재(25)와 흙막이용 프리스트레스트가시설거더(20)의 단부에 지압지지강판(33)을 각각 부착하고, 상기 양측의 지압지지강판(33)과의 사이의 중앙에 유압잭(32)을 설치하면서 하중측정센서(46)을 설치하고, 상기 유압잭(32)의 상하에, 압력조절강재(25)의 단부에 설치된 지압지지강판(33)에 강관(31)을 용접부착하고, 상기 강관(31)에 볼트(34)를 용접부착하고, 스트로크를 이동시킨 다음, 상기 볼트(34)에 장나비너트(35)를 체결하면서 상기 흙막이용 프리스트레스트가시설거더(20)의 단부에 설치된 지압지지강판(33)을 관통하여 돌출된 볼트(34)단부에 너트(39)로 체결한 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 가시설거더에 프리스트레스를 도입하는 방법.The stroke generating device 30 is attached to the pressure-bearing steel plate 25 and the pressure-bearing steel plate 33 at the ends of the prestress temporary girders 20 for the retaining wall, respectively, and the pressure-bearing steel plate 33 on both sides The load measuring sensor 46 is installed while the hydraulic jack 32 is installed in the center thereof, and the steel pipe 31 is mounted on the pressure bearing steel plate 33 provided at the end of the pressure regulating steel 25 above and below the hydraulic jack 32. ) Welding, attaching the bolt 34 to the steel pipe 31, moving the stroke, and then fastening the long bow nut 35 to the bolt 34, the prestress temporary girders 20 A method of introducing prestress into a girder including a device for generating an extension force in a steel wire characterized by fastening with a nut 39 to a bolt 34 end projecting through the acupressure supporting steel plate 33 installed at the end of . 제 21항 또는 제25항에 있어서The method according to claim 21 or 25. 상기 스트로크발생장치(30)는 압력조절강재(25)와 흙막이용 프리스트레스트가시설거더(20)의 단부에 지압지지강판(33)을 각각 부착하고, 상기 양측의 지압지지강판(33)과의 사이의 중앙에 유압잭(32)을 설치하면서 하중측정센서(46)를 설치하고, 상기 유압잭(32)의 상하에, 압력조절강재(25)의 단부에 설치된 지압 지지강판(33)에 채널(47)을 용접부착하고, 상기 채널(47)에 볼트 (34)를 용접부착하고, 스트로크를 이동시킨 다음, 상기 볼트(34)에 장나비너트(35)를 체결하면서 상기 프리스트레스트가시설거더(20)의 단부에 설치된 지압지지강판(33)을 관통하여 돌출된 볼트(34)단부에 너트(39)로 체결한 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 가시설거더에 프리스트레스를 도입하는 방법.The stroke generating device 30 is attached to the pressure-bearing steel plate 25 and the pressure-bearing steel plate 33 at the ends of the prestress temporary girders 20 for the retaining wall, respectively, and the pressure-bearing steel plate 33 on both sides The load measuring sensor 46 is installed while the hydraulic jack 32 is provided at the center thereof, and the channel 47 is provided on the pressure bearing steel plate 33 provided at the end of the pressure regulating steel 25 above and below the hydraulic jack 32. ), Weld the bolts 34 to the channel 47, move the stroke, and then fasten the long nut 35 to the bolts 34 of the prestressed girder 20. A method for introducing prestress into a girder including a device for generating an extension force in a steel wire characterized by fastening with a nut (39) to a bolt (34) end projecting through a pressure bearing steel plate (33) provided at an end. 제 21항 내지 제25항중의 어느 한 항에 있어서The method according to any one of claims 21 to 25. 상기 하중전달재(24)는 흙막이용 프리스트레스트가시설거더의 전면 플랜지에 설치될때 상기 하중전달재(24)의 원중심축(26)이 강선의 배치형상인 원형상의 원중심(27)을 향하도록 설치되도록 하면서 곡선새들(42)에 강선이 접하는 부분 또는 강관새들(43)에 강선(13)이 접하는 부분이 원중심축(26)과 강선(13)의 접선방향(T)에 직각(R)이 되도록 설치한 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 가시설거더에 프리스트레스를 도입하는 방법.When the load transfer member 24 is installed on the front flange of the facility girders, the central axis 26 of the load transfer member 24 is directed toward the circular center 27 in the shape of the steel wire arrangement. The portion where the steel wire is in contact with the curved birds 42 or the portion where the steel wire 13 is in contact with the steel pipe birds 43 is perpendicular to the tangential direction T of the central axis 26 and the steel wire 13 while being installed so as to be installed in such a manner as to be installed thereon. A method of introducing prestress into a girder girder including a device for generating a stretching force on a steel wire characterized by being installed). 제 21항 내지 제25항 중의 어느 한항에 있어서The method according to any one of claims 21 to 25. 상기 강선가이드장치(40)는 하중전달재(24)의 단부에 베이스강판(28)과 보강판을 설치하고, 상기 베이스강판을 포함하는 하중전달재(24)의 양측에 가이드판(41)을 설치하고, 상기 가이드판(41)의 사이의 베이스강판(28)에 부착하여 강선이 접하는 면이 볼록한 곡면을 갖는 곡선새들(42)을 부착설치하고, 상기 곡선새들(42)의 곡면에 강선을 접촉설치하면서 상기 양측에 설치된 가이드판(41)의 상부를 관통하여 강선이탈방지봉(45)을 설치한 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 가시설거더에 프리스트레스를 도입하는 방법.The wire guide device 40 is provided with a base steel plate 28 and a reinforcement plate at the end of the load transfer member 24, the guide plate 41 on both sides of the load transfer member 24 including the base steel plate And attaching to the base steel plate 28 between the guide plates 41 and attaching curved saddles 42 having convex curved surfaces where the steel wires are in contact with each other, and placing the steel wires on the curved surfaces of the curved birds 42. A method of introducing prestress into a girder girder including a device for generating an extension force on a steel wire characterized in that a steel wire break-away bar (45) is provided through the upper portions of the guide plates (41) provided on both sides while being installed in contact. 제 21항 내지 제25항 중의 어느 한 항에 있어서 The method according to any one of claims 21 to 25. 상기 하중전달재에 강선을 이중으로 설치하는 경우에는 상기 하중전달재(24)의 단부에 베이스강판(28)과 보강판을 설치하고, 상기 베이스강판(28)을 포함하면서 내측에는 상하로 파이프핀부(44)가 설치된 가이드판(41)을 양측에 설치하고, 상기 가이드판(41)에 설치된 파이프핀부(44)에 강관새들(43)의 측면에 형성된 홈이 삽입되도록 상하로 설치하고, 상기 강관새들(43)에 접하게 강선(13)을 각각 설치하고, 상기 강선(13)이 상하로 강관새들(43)에 접하게 설치한 후에, 상기 가이드판(41)의 상부에 강선이탈방지봉(45)을 설치하여 강선(13)이 이탈되는 것을 방지한 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 가시설거더에 프리스트레스를 도입하는 방법.When the steel wire is installed in the load transfer member in a double manner, a base steel plate 28 and a reinforcement plate are installed at the ends of the load transfer member 24, and the pipe pins are disposed up and down inside the base steel plate 28. The guide plate 41 provided with the 44 is installed on both sides, the pipe pin portion 44 provided in the guide plate 41 is installed up and down so that the groove formed in the side of the steel pipe birds 43 is inserted, the steel pipe After each of the steel wire 13 is installed in contact with the saddle 43, and the steel wire 13 is installed in contact with the steel pipe birds 43 up and down, the steel wire escape prevention bar 45 on the upper portion of the guide plate 41 A method of introducing prestress into a girder girder including an apparatus for generating a stretching force in a steel wire characterized by installing a steel wire to prevent the steel wire from being separated. 제 21항 내지 제25항중의 어느 한항에 있어서 The method according to any one of claims 21 to 25. 상기 흙막이용 프리스트레스트가시설거더(20)를 측면에서 이중으로 연결제작한 흙막이용 프리스트레스트가시설이중거더(50)인 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 가시설거더에 프리스트레스를 도입하는 방법.Prestress is introduced to a temporary girder including a device for generating a stretch force on the steel wire characterized in that the prestress for masonry is a double girder (50) made by connecting the prestress temporary girder 20 in the side. How to. 제 21항 내지 제25항중의 어느 한항에 있어서The method according to any one of claims 21 to 25. 상기 양측의 흙막이용 프리스트레스트가시설거더(20)와의 사이에 거더(11)를 설치하고 볼트너트결합(38)하고, 상기 볼트너트결합한 양측 부분의 플랜지(14)에 지압보강대(101)를 설치하고, 상기 지압보강대(101)의 중앙에 버팀대(12)를 설치하고, 상기 양측의 지압보강대(101)에 경사버팀대(103)를 설치하고, 상기 중앙의 버팀대(12)의 연장부와 양측의 경사버팀대(103)가 만나는 부분에 보강부(21)를 설치하고, 상기 보강부(21)의 외측에 스크류잭(102)를 설치하고, 상기 스크류잭의 외측에 버팀대(12)를 설치하여 상호 연결하여 지지되도록 버팀대와 가시설거더연결부(100)를 설치한 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 흙막이용 프리스트레스트가시설거더에 프리스트레스를 도입하는 방법.The girders 11 are installed between the prestressed girders 20 on both sides of the earthen board and bolt nut coupling 38, and the acupressure reinforcement 101 is installed on the flanges 14 at both sides of the bolt nut coupling. The brace 12 is installed at the center of the acupressure reinforcement 101, and the inclined brace 103 is provided at the acupressure reinforcement 101 at both sides, and the extensions and both sides of the central brace 12 are provided. The reinforcement part 21 is installed in the part where the inclined brace 103 meets, the screw jack 102 is installed in the outer side of the reinforcement part 21, and the brace 12 is installed in the outer side of the screw jack, and mutually Method for introducing pre-stress to the prestressed girders for earthquakes including a device for generating a stretch force in the steel wire characterized by the installation of the brace and the temporary girder connecting portion (100) to be connected and supported. 제 21항 내지 제25항 중의 어느 한 항에 있어서The method according to any one of claims 21 to 25. 소정의 간격을 두고 설치된 상기 양측 흙막이용 프리스트레스트가시설거더(20)의 플랜지를 연결한 지압보강대(101)를 설치하고, 상기 지압보강대(101)의 측면 중앙에 버팀대(12)를 설치하고, 연이어서 스크류잭(21)을 설치하고, 상기 스크류잭(21)에 연이서서 버팀대(12)를 연결설치하여 지지되도록 한 버팀대와 가시설거더연결부(100)를 설치한 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 가시설거더에 프리스트레스를 도입하는 방법.      Install the acupressure reinforcement base 101 connecting the flanges of the prestressed girders 20 for both mud walls installed at predetermined intervals, and install a brace 12 at the center of the side of the acupressure reinforcement base 101, Next, the screw jack 21 is installed in succession, and the brace and the temporary girders connecting part 100 are installed so that the screw jack 21 is connected to and installed in the screw jack 21 so as to be supported. A method of introducing prestress to a girder including a generating device. 제 21항 내지 제25항 중의 어느 한 항에 있어서The method according to any one of claims 21 to 25. 소정의 간격을 두고 설치된 상기 양측 흙막이용 프리스트레스트가시설거더(20)의 각각의 플랜지에 버팀대(12)를 각각 연결하고, 상기 연결된 버팀대(12)의 사이에 중간파일(77)을 설치하여 양측에 설치된 버팀대(12)의 좌굴을 방지하면서 지지하도록 한 버팀대와 가시설거더연결부(100)를 설치한 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 가시설거더에 프리스트레스를 도입하는 방법.The braces 12 are respectively connected to the flanges of the prestressed girders 20 for both sides of the mudguards installed at predetermined intervals, and intermediate piles 77 are installed between the connected braces 12 to both sides. A method of introducing prestress to a girder including a device for generating a stretching force on a steel wire characterized by the installation of a brace and a temporary girder connecting portion (100) to support while preventing buckling of the brace (12) installed in the. 제 21항 내지 제 25항 중의 어느 한 항에 있어서The method according to any one of claims 21 to 25. 상기 버팀대(12)와 버팀대(12) 사이에 수직앵글(54)을 상하로 설치하고, 상기 버팀대(12)와 수직앵글(54)이 상호 만나는 부분에 수평앵글(55)을 설치하여 보강한 충돌방호책(48)인 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 가시설거더에 프리스트레스를 도입하는 방법. Collision reinforced by installing a vertical angle 54 between the brace 12 and the brace 12 up and down, and installing a horizontal angle 55 at the portion where the brace 12 and the vertical angle 54 meet each other. A method of introducing prestress into a girder girder including a device for generating a stretching force on a steel wire characterized by being a protective measure (48). 제21항 내지 제25항중의 어느 한 항에 있어서 The method according to any one of claims 21 to 25. 상기 슬라이딩볼트결합(73)은 플랜지(14)의 하부에 스테인레스판(53)을 설치하고, 그 다음에 보강판(15)을 설치하고, 그 다음에 하중전달재(24)를 설치하되, 상기 플랜지(14), 스테인레스판(53) 및 보강판(15)에 장공(51)을 형성하여 상호 관통되도록 하고, 상기 장공(51) 외측의 상하부에 와샤(52)를 설치하고, 상기 와샤(52)와 장공(51)을 관통한 것에 특징이 있는 강선에 신장력을 발생시키는 장치를 포함한 가시설거더에 프리스트레스를 도입하는 방법.      The sliding bolt coupling 73 is provided with a stainless plate 53 in the lower portion of the flange 14, and then install the reinforcement plate 15, and then install a load transfer material 24, A long hole 51 is formed in the flange 14, the stainless plate 53, and the reinforcing plate 15 so as to penetrate each other. A washer 52 is provided at an upper and lower part of the outside of the long hole 51, and the washer 52 And a prestress in a girder girder including a device for generating an elongation force on a steel wire characterized by having penetrated through the hole and 51).
KR1020090033674A 2009-04-17 2009-04-17 Scaffolding girder introducing prestress using a device generating tension in steel wire and prestress introducing method thereof KR101124514B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020090033674A KR101124514B1 (en) 2009-04-17 2009-04-17 Scaffolding girder introducing prestress using a device generating tension in steel wire and prestress introducing method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020090033674A KR101124514B1 (en) 2009-04-17 2009-04-17 Scaffolding girder introducing prestress using a device generating tension in steel wire and prestress introducing method thereof

Publications (2)

Publication Number Publication Date
KR20100115119A KR20100115119A (en) 2010-10-27
KR101124514B1 true KR101124514B1 (en) 2012-03-15

Family

ID=43134088

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090033674A KR101124514B1 (en) 2009-04-17 2009-04-17 Scaffolding girder introducing prestress using a device generating tension in steel wire and prestress introducing method thereof

Country Status (1)

Country Link
KR (1) KR101124514B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108560563A (en) * 2018-05-24 2018-09-21 东南大学 A kind of deep foundation pit support prestressing force fish belly sill that drag-line can be locked
CN108677964A (en) * 2018-05-24 2018-10-19 东南大学 A kind of prestressing force fish belly sill of the deep foundation pit support with anti-rotation rope
RU2740608C1 (en) * 2020-09-07 2021-01-15 Федеральное государственное бюджетное образовательное учреждение высшего образования "Петербургский государственный университет путей сообщения Императора Александра I" Crane beam
KR20210023044A (en) * 2019-08-21 2021-03-04 선진정공 주식회사 Steel wire pre-tensioning apparatus for manufacturing prestressed concrete products having steel wire saving part

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101308992B1 (en) * 2011-07-01 2013-09-17 지에스건설 주식회사 Tention typed cable-stayed bridge construction method
KR101682010B1 (en) * 2016-05-30 2016-12-02 (주)신흥이앤지 Girder type for assembling in-site having reinforced anti-buckling
CN107724244B (en) * 2017-10-26 2023-07-18 中铁第四勘察设计院集团有限公司 Temporary T-shaped structure formed by bridge sections of continuous rigid frame edges without support and construction method of temporary T-shaped structure
CN110158768A (en) * 2019-06-06 2019-08-23 哈尔滨工业大学建筑设计研究院 Prestressing force brace reinforced concrete frame conversion layer
KR102552442B1 (en) * 2023-01-12 2023-07-06 신한산업 주식회사 Hybrid waterway system using culvert and U-shaped plume and its construction method
CN116439844B (en) * 2023-03-07 2024-03-15 极限人工智能有限公司 Automatic steel wire deformation compensation mechanism, medical instrument and method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060095149A (en) * 2005-02-28 2006-08-31 이선구 Dead load composite system by temporary tensioning method

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20060095149A (en) * 2005-02-28 2006-08-31 이선구 Dead load composite system by temporary tensioning method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108560563A (en) * 2018-05-24 2018-09-21 东南大学 A kind of deep foundation pit support prestressing force fish belly sill that drag-line can be locked
CN108677964A (en) * 2018-05-24 2018-10-19 东南大学 A kind of prestressing force fish belly sill of the deep foundation pit support with anti-rotation rope
KR20210023044A (en) * 2019-08-21 2021-03-04 선진정공 주식회사 Steel wire pre-tensioning apparatus for manufacturing prestressed concrete products having steel wire saving part
KR102245182B1 (en) * 2019-08-21 2021-04-27 선진정공 주식회사 Steel wire pre-tensioning apparatus for manufacturing prestressed concrete products having steel wire saving part
RU2740608C1 (en) * 2020-09-07 2021-01-15 Федеральное государственное бюджетное образовательное учреждение высшего образования "Петербургский государственный университет путей сообщения Императора Александра I" Crane beam

Also Published As

Publication number Publication date
KR20100115119A (en) 2010-10-27

Similar Documents

Publication Publication Date Title
KR101124514B1 (en) Scaffolding girder introducing prestress using a device generating tension in steel wire and prestress introducing method thereof
KR100991208B1 (en) Prestress composite wale for earth retaining scaffolding and this construction technique
KR101728700B1 (en) Reinforcement apparatus for earth retaining temporary facility and temporary structure having the same
KR101160615B1 (en) Prestressed wale girder introducing prestress using stroke generator and camber steel plate installed between inclined supports supporting wale girder to be inclined, and prestress introducing method
KR100812722B1 (en) Bracket and Support for Prestressed Scaffolding System
US20060070803A1 (en) Prestressed scaffolding system
KR100908321B1 (en) Prestress composition wale construction method for sheathing work
KR100659744B1 (en) Stiffening the side of foundation pits and sheathing board
CN101310078A (en) Apparatus for fixing a wale
KR100188465B1 (en) Apparatus for stiffening the side of foundation pits and sheathing board
KR100776643B1 (en) Constructing method of steel cable stayed bridge omitting negative reaction bridge seat
KR101323945B1 (en) Wale for construction method for defending earthusing prestress
KR100778137B1 (en) Bracket and Support for Prestressed Scaffolding System
KR100808939B1 (en) wire-reinforced structure for underground pre-scaffolding system
JP6621243B2 (en) Yamadome frame and its construction method
KR20100061932A (en) A shoring structure using arch plate pile
KR20120131996A (en) Structure of temporary installation for land-side protection wall, and construction method thereof
KR102039928B1 (en) Arched Wale Structure with Improved Load-bearing Capacity and Rigidity
JP2019108701A (en) Fence for safety measures of reinforced soil wall construction
KR20090067339A (en) A tight connection between steel pipe strut and center pile
JP6918613B2 (en) Wall structure and wall construction method
KR20130038461A (en) Variable supporting device for sheathing work pile
KR101298020B1 (en) Special prestressed method
KR102444554B1 (en) Prestressed wale and it&#39;s construction method
KR200496654Y1 (en) Bracket for iron beam and guardrail

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
AMND Amendment
E601 Decision to refuse application
AMND Amendment
J201 Request for trial against refusal decision
B701 Decision to grant
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20150213

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20160215

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20161226

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20180103

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20190110

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20200214

Year of fee payment: 9