KR101045663B1 - Wall-Foundation system - Google Patents
Wall-Foundation system Download PDFInfo
- Publication number
- KR101045663B1 KR101045663B1 KR1020080109923A KR20080109923A KR101045663B1 KR 101045663 B1 KR101045663 B1 KR 101045663B1 KR 1020080109923 A KR1020080109923 A KR 1020080109923A KR 20080109923 A KR20080109923 A KR 20080109923A KR 101045663 B1 KR101045663 B1 KR 101045663B1
- Authority
- KR
- South Korea
- Prior art keywords
- wall
- mud
- members
- blocking wall
- supporting members
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/02—Sheet piles or sheet pile bulkheads
- E02D5/03—Prefabricated parts, e.g. composite sheet piles
- E02D5/04—Prefabricated parts, e.g. composite sheet piles made of steel
- E02D5/06—Fitted piles or other elements specially adapted for closing gaps between two sheet piles or between two walls of sheet piles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/02—Improving by compacting
- E02D3/10—Improving by compacting by watering, draining, de-aerating or blasting, e.g. by installing sand or wick drains
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/02—Sheet piles or sheet pile bulkheads
- E02D5/03—Prefabricated parts, e.g. composite sheet piles
- E02D5/04—Prefabricated parts, e.g. composite sheet piles made of steel
- E02D5/08—Locking forms; Edge joints; Pile crossings; Branch pieces
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/18—Bulkheads or similar walls made solely of concrete in situ
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Composite Materials (AREA)
- Chemical & Material Sciences (AREA)
- Agronomy & Crop Science (AREA)
- Environmental & Geological Engineering (AREA)
- Soil Sciences (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
본 발명의 이중 연속벽은 흙막이 설치영역에 소정의 간격으로 설치되는 제1지지부재들과, 상기 제 1지지부재들의 사이에 설치되는 제 1흙막이 판들을 구비한 제 1흙막이 차단벽과, 상기 제 1흙막이 차단벽과 이격되도록 전면에 설치되는 것으로 소정의 간격으로 설치되는 제2지지부재들과, 상기 제 2지지부재들의 사이에 설치되는 제 2흙막이 판들을 구비한 제 2흙막이 차단벽과, 상기 제1,2지지부재들을 상호 연결하는 복수개의 연결부재들과, 연결부재들에 의해 연결된 제 1,2흙막이 차단벽의 사이에 채워지는 채움부재를 구비한다.The double continuous wall of the present invention includes a first mud blocking wall including first supporting members installed at predetermined intervals in a mud installation region, first mud plates disposed between the first supporting members, and the first mud blocking wall. A second mud blocking wall having second supporting members installed at a predetermined interval so as to be spaced apart from the blocking wall, the second supporting member being installed at predetermined intervals, and the second supporting plate installed between the second supporting members; A plurality of connecting members for interconnecting the first and second support members, and the first and second soil membranes connected by the connecting members is filled between the blocking wall.
지하, 연속벽, 옹벽, 토압, 흙막이 Underground, Continuous Wall, Retaining Wall, Earth Pressure, Earth Block
Description
본 발명은 이중 연속벽에 관한 것으로, 더 상세하게는 공사 시, 지하 터파기 공사 또는 옹벽 공사 시 흙이 무너지는 것을 방지하고 인접하는 건물을 보호 할 수 있는 이중 연속벽에 관한 것이다. The present invention relates to a double continuous wall, and more particularly, to a double continuous wall that can prevent the collapse of the soil during construction, underground trench construction or retaining wall construction and protect adjacent buildings.
일반적으로 토목공사, 중,대형 건축물 지하구조물 등의 설치를 위하여 터파기 공사를 하는 경우 지하 벽체로부터 토사가 유출되거나 무너지는 것을 방지하기 위한 흙막이 공사를 시공하게 된다. In general, when digging work for the installation of civil engineering works, underground structures of large, large buildings, etc., construction of the earthquake blocks to prevent the soil from leaking or collapsing from the underground walls.
이러한 흙막이 공사는 터파기를 하면서 시공하거나 지중에 미리 차단벽을 설치한 상태에서 시행하게 되며, 이 터파기 공사는 주위의 환경, 지중의 토질 상태, 공사장 주위의 건물 배치에 따라 다양한 방법으로 시공되고 있다. Such earthquake construction is carried out while digging or installing a barrier in the ground in advance, and this excavation work is carried out in various ways depending on the surrounding environment, the soil condition of the ground, and the layout of buildings around the construction site. .
대한민국 공개 특허 제2003-0051477호에는 지하 연속벽 시공방법이 개시되어 있다. 게시된 연속 시공방법은 커터 등의 장비를 이용하여 철근 콘크리트벽을 반복타설하여 지하 연속벽체를 시공하고, 상기 지하 연속벽체를 지지하는 흙막이 시설을 설치하는 방법으로, 상기 지하연속벽체를 시공한 장비로 지하연속벽체에 접하면서 지하연속벽체에 직각되는 방향으로 다수개의 버팀벽을 타설하여 지하 연속 벽체를 지지한다.Korean Unexamined Patent Publication No. 2003-0051477 discloses an underground continuous wall construction method. The published continuous construction method is a method of constructing an underground continuous wall by repeatedly placing reinforced concrete walls using equipment such as a cutter, and installing an earth barrier facility supporting the underground continuous wall. In order to support the continuous continuous wall by placing a plurality of bracing walls in the direction perpendicular to the underground continuous wall while contacting the underground continuous wall.
등록 실용신안 제 20-0229224호에는 흙막이 공사용 토류판 설치 구조가 게시되어 있다. 게시된 설치구조는 흙벽 내측에 간격을 두고 매립 설치된 다수개의 기초 말뚝과, 상기 기초 말뚝의 일측면에 적층되어 토사가 붕괴되거나 유출됨을 방지하도록 견고한 재질로 이루어진 토류판과, 기초말뚝에 토류판을 결합 및 분리 가능하게 하는 결합수단을 구비한다.Registered Utility Model No. 20-0229224 discloses a structure for installing earthen boards for earthquake construction. The posted installation structure includes a plurality of foundation piles installed at intervals inside the soil wall, a earth plate made of a solid material laminated on one side of the foundation pile to prevent the soil from being collapsed or spilled, and the earth plate coupled to the foundation pile. It is provided with a coupling means to be detachable.
상기와 같이 흙막이 공사용 토류판 설치공사는 기초 말뚝에 토류판을 설치하여야 하므로 단일 시공이 어렵고, 터파기를 하지 않은 상태에서 시공이 불가능하다. 또한 상기 토류판은 목재로 이루어져 있으므로 장시간을 사용 시 수분에 의해 휘어지거나 부식이 발생되고, 만약 부식이 되지 않는다 하더라도 흙벽과 토류판 사이를 매우는 작업으로 인하여 지중에 매설되므로 회수가 불가능하다. 따라서, 종래의 토류판은 재활용이 불가능하므로 자원이 낭비되고, 비용이 증대되는 문제점이 있다. As mentioned above, the earthen board installation work for earthquake construction is required to install the earthen board on the foundation pile, so that the single construction is difficult, and the construction is impossible without the trench. In addition, since the earth plate is made of wood, it is bent or eroded by moisture when used for a long time, and even if it is not corroded, it is impossible to recover because it is buried in the ground due to the work between the earth wall and the earth plate. Therefore, the conventional earth plate is not recycled, there is a problem that resources are wasted, the cost is increased.
또한 한국 등록특허 제 10-0401330호에는 건축용 흙막이 공법의 다른 예가 게시되어 있다. 게시된 흙막이 공법은 H형강에 엄지 말뚝들을 지반에 천공한 구멍에 박고, 엄지말뚝들의 상단부에 버팀보용 띠장을 고정하는 단계와, 엄지말뚝들의 앞쪽에서 엄지말뚝들 사이를 터파기 한 다음 그 뒤쪽에 뒤 패널을 삽입하고, 보강철근의 양쪽을 엄지말뚝들의 연결철근과 연결하며, 엄지말뚝의 앞쪽에는 패널을 밀착시키고 터파기 한 곳을 되메우는 단계와, 앞 패널과 뒤패널 사이에 콘트리트를 타설 한 직후 뒤 패널을 뽑아내어 뒤 패널이 있던 자리에도 콘트리트가 채워지도록 하면서 콘크리트를 양생시키는 단계를 포함한다. In addition, Korean Patent No. 10-0401330 discloses another example of the building construction method. The posted piling method involves placing the thumb piles in the H-beams in perforated holes in the ground, securing the braces to the upper ends of the thumb piles, and digging between the thumb piles in front of the thumb piles and then behind them. Insert the rear panel, connect both sides of the reinforcing bar with connecting bars of the thumb piles, close the panel in front of the thumb pile and backfill the trench, and place concrete between the front panel and the rear panel. Immediately removing the rear panel and curing the concrete while filling the concrete where the rear panel was.
이러한 방법은 별도로 앞패널과 뒷패널을 엄지 말뚝에 결합 및 분리하여야 하므로 시공 시 많은 작업공수가 소요되는 문제점이 있다. 이러한 시공의 복잡성은 인건비를 증가시킴으로써 공사비용을 높이는 원인이 된다.This method has a problem that requires a lot of work during construction because the front panel and the rear panel must be coupled to and separated from the thumb pile. The complexity of such construction causes the cost of construction to increase by increasing labor costs.
한편, 상기와 같은 종래의 흙막이 벽은 주의의 건물들에 의해 심한 토압을 받는 경우 지지력이 약하여 붕괴의 우려가 있다. 특히 토압을 견디지 못하는 경우 주위의 건물에 크랙이 발생되는 문제점이 있다. 특히 공사장 또는 공사장의 주위로부터 토압이 전달되어 토루벽이 무너지거나 인접하는 건물이 손상되는 것을 근본적으로 방지할 수 있다. On the other hand, the conventional retaining wall as described above has a weak bearing capacity when there is severe earth pressure by the buildings of caution there is a fear of collapse. In particular, there is a problem that cracks occur in the surrounding buildings when the earth pressure cannot be tolerated. In particular, it is possible to fundamentally prevent the earth pressure from being transmitted from the construction site or the surroundings of the construction site, causing the mound wall to collapse or damage the adjacent building.
본 발명은 상술한 바와 같은 문제점을 해결하기 위한 것으로, 토압에 의해 붕괴되는 것을 근본적으로 방지할 수 있으며, 토압에 대한 지지력을 높일 수 있는 이중 연속벽을 제공함에 그 목적이 있다.The present invention is to solve the problems described above, it is possible to fundamentally prevent the collapse by the earth pressure, and to provide a double continuous wall that can increase the bearing capacity for earth pressure.
본 발명의 다른 목적은 공사장으로부터 주위의 건물 또는 주위로부터 공사장으로 진동이 전달되는 것을 방지할 수 있으며, 공사장 주위의 가설도로로 이용 가능한 이중 연속벽을 제공함에 있다. Another object of the present invention is to provide a double continuous wall which can prevent the transmission of vibration from the construction site around the construction site or from the construction site, and can be used as a temporary road around the construction site.
상기와 같은 목적을 달성하기 위한 본 발명의 이중연속벽은, Double continuous wall of the present invention for achieving the above object,
흙막이 설치영역에 소정의 간격으로 설치되는 제1지지부재들과, 상기 제 1지 지부재들의 사이에 설치되는 제 1흙막이 판들을 구비한 제 1흙막이 차단벽과,A first mud blocking wall including first supporting members installed at predetermined intervals in the mud installation region, and first mud plates provided between the first supporting members;
상기 제 1흙막이 차단벽과 이격되도록 전면에 설치되는 것으로 소정의 간격으로 설치되는 제2지지부재들과, 상기 제 2지지부재들의 사이에 설치되는 제 2흙막이 판들을 구비한 제 2흙막이 차단벽과,A second mud blocking wall having second supporting members installed at a predetermined interval so that the first mud film is spaced apart from the blocking wall, and second mud plates provided between the second supporting members; ,
상기 제1,2지지부재들을 상호 연결하는 복수개의 연결부재들과, A plurality of connection members interconnecting the first and second support members;
연결부재들에 의해 연결된 제 1,2흙막이 차단벽의 사이에 채워지는 채움부재를 구비한다.The first and second soil films connected by the connecting members are provided with filling members between the blocking walls.
본 발명에 있어서, 상기 제1,2지지부재는 날개가 대향되도록 설치되는 H 빔으로 이루어지며 상기 제1,2흙막이 판은 목재 또는 철판, 콘크리트 패널로 이루어질 수 있다. 상기 제 1지지부재와 제 1흙막이판 또는 제 2지지부재와 2흙막이 판은 그라우팅 된 콘크리트 기둥으로 이루어진다. 그리고 상기 제1,2흙막이 차단벽 사이에 배수를 위한 유공관이 수직으로 설치될 수 있다.In the present invention, the first and second support members are made of H beams installed so that the wings are opposed to each other, and the first and second earthen boards may be made of wood or iron plates or concrete panels. The first support member and the first support plate or the second support member and the second support plate is made of a grouted concrete pillar. In addition, a hole for drainage may be vertically installed between the first and second soil barrier walls.
본 발명의 이중 연속벽은 흙막이 공사 시 토압에 의해 붕괴되거나 지반의 약화로 인하여 무너지는 것을 방지할 수 있으며, 나아가서는 토압의 지지력을 향상시켜 주변의 건물에 크랙이 발생되는 것을 근본적으로 방지할 수 있다. 공사 중 진동이 주위의 건물로 전달되는 것을 방지할 수 있다. The double continuous wall of the present invention can prevent the earthquake from collapsing due to earth pressure or collapse due to the weakening of the ground, and furthermore, it is possible to fundamentally prevent the occurrence of cracks in the surrounding buildings by improving the bearing capacity of the earth pressure. have. Vibration can be prevented from being transferred to surrounding buildings during construction.
본 발명에 따른 이중연속벽은 건물의 신축, 도로, 항만 등의 공사 시 절결지에 설치되어 토압에 의해 절결지가 무너지는 것을 방지하기 위한 것으로, 그 일 실시예를 도 1 및 도 2에 나타내 보였다.The double continuous wall according to the present invention is installed at a cutout place during construction of a new building, a road, a harbor, and the like to prevent the cutout from being collapsed by earth pressure. An embodiment thereof is illustrated in FIGS. 1 and 2.
도면을 참조하면, 이중연속벽(10)은 굴착 또는 절결지의 토사 무너짐을 방지하기 위한 흙막이를 설치하고자 하는 영역에 소정의 간격 약 1.5m 내지 2.5m의 간격으로 설치되는 제 1지지부재(21)들과 이 제1지지부재(21)들의 사이에 설치되는 제1흙막이판(22)들을 구비한 제 1흙막이 차단벽(20)과, 상기 제 1흙막이 차단벽(20)과 이격되도록 전면에 설치되는 것으로 소정의 간격으로 설치되는 제2지지부재(31)들과, 상기 제 2지지부재(31)들의 사이에 설치되는 제 2흙막이 판(32)들을 구비한 제 2흙막이 차단벽(30)을 구비한다. 여기에서 상기 제 1,2지지부재(21)(31)를 소정의 간격으로 시공한 상태에서 이들의 사이를 굴삭하면서 상기 제 1,2흙막이판(22)(32)을 설치한다. Referring to the drawings, the double
상기 제 1지지부재(21)와 제 2지지부재(31)은 H 형강으로 이루어질 수 있는데, 이 때에 상기 H 형강들의 날개는 상호 대향되는 방향으로 설치되어 상기 제1,2흙막이 판(22)(32)들의 가장자리가 지지되도록 함이 바람직하다. 그리고 상기 제1,2흙막이 판(22)(32)은 단일의 판들이 적층되어 이루어지거나 H 형강 사이의 폭을 가지는 흙막이 판들을 길이 방향으로 연결하여 이루어질 수 있는데, 이는 목재 또는 철판, 콘크리트 패널로 이루어질 수 있다. The
그리고 상기 제 1,2지지부재(21)(31)들은 상호 연결부재(40)들에 의해 연결되는데, 상기 연결부재(40)들은 형강 또는 와이어로 이루어질 수 있다. The first and second supporting
상술한 바와 같이 연결부재(40)에 의해 상호 연결되는 제 1,2흙막이 차단벽(20)(30)이 완성되면 제1흙막이 차단벽의 뒤와, 제 1,2흙막이 차단벽(20)(30)의 사이에 마사토, 모래, 흙, 잡석 등의 채움부재(50)가 채워진다. 이때에 상기 채움부재(50)는 잡석과 마사토 모래를 순차적으로 적층하여 배수가 원활하게 이루어질 수 있도록 함이 바람직하며, 진동을 흡수할 수 있도록 자갈과 모래를 배합하여 뒷채움함이 바람직하다. 그리고 상기 제 1,2흙막이 차단벽(20)(30)의 사이에는 배수가 원활하게 이루어질 수 있도록 다수의 관통공(61)이 형성된 유공관(60) 또는 맹배수관이 설치될 수 있다. As described above, when the first and second
도 2에는 본 발명에 따른 이중 연속벽의 다른 실시예를 나타내 보였다.Figure 2 shows another embodiment of a double continuous wall according to the present invention.
도면을 참조하면, 이중연속벽(10)은 굴착 또는 절결지의 토사 무너짐을 방지하기 위한 흙막이를 설치하고자 하는 영역에 그라우팅 된 제1콘크리트 기둥(71)을 연속하여 형성함으로써 제1흙막이 차단벽(70)을 형성하고, 이의 전면에 그라우팅 된 제2콘크리트 기둥(81)을 연속하여 형성함으로써 제1흙막이 차단벽(70)과 소정간격 이격되는 제 2흙막이 차단벽(80)을 형성한다. 여기에서 상기 제2콘크리트 기둥(81)은 그라우팅하여 형성할 수 없는 경우 기 제작된 파일을 연속하여 박아 형성 할 수 있다.Referring to the drawings, the double
그리고 상기 제 1,2콘크리트 기둥(71)(81)의 상호 대향되는 면에는 고리(72)(82)들을 형성하고, 이들 고리(72)(82)를 연결부재(90)인 와이어를 이용하여 연결한다. 여기에서 상기 연결부재(90)는 형강 또는 양측단부에 걸고리가 형성된 콘크리트 블록으로 이루어질 수 있다. In addition, the surfaces of the first and
상기 제 1,2콘크리트 기둥(71)(81)의 연결은 도 3에 도시된 바와 같이 제 1,2콘트리트 기둥(71)(81)의 외측에 지지바(84)(85)를 설치하고 이들을 로프 또는 연결바(86)에 의해 이루어질 수 있다.Connection of the first and
상술한 바와 같이 연결부재(90)에 의해 상호 연결되는 제 1,2흙막이 차단벽(70)(80)이 완성되면 제1흙막이 차단벽의 뒤와, 제 1,2흙막이 차단벽(70)(80)의 사이에 마사토, 모래, 흙, 잡석 등의 채움부재(50)가 채워진다. 그리고 상기 제 1,2흙막이 차단벽(70)(80)의 차단벽 사이의 표층에는 포장이 되어 공사를 위한 건설장비가 이동될 수 있도록 함이 바람직하며, 채움부재(50)의 내부 즉, 상기 제 1,2흙막이 차단벽(70)(80) 사이에 채워진 채움부재(50)의 내부에는 배수를 위해 다수의 관통공이 형성된 유공관(60)이 매립될 수 있다.As described above, when the first and second
한편, 도 4에 도시되 바와 같이 일측의 흙막이 차단벽이 상대적으로 높은 토압을 받는 경우 앙카부재(101)을 이용한 이용한 별도의 지지수단(100)을 설치할 수 있다.On the other hand, as shown in Figure 4, when the earth blocking wall of one side receives a relatively high earth pressure may be provided a separate support means 100 using the
상기와 같이 구성된 지하 연속벽은 절결지 또는 토목공사, 중, 대형 건축물 지하구조물 등의 설치를 위하여 터파기 공사를 하는 경우 지하 벽체로부터 토사가 유출되거나 무너질 우려가 있는 영역에 설치되어 절결지 또는 지하 구조물의 설치 영역이 무너지는 것을 방지할 수 있다. 특히 상기 이중 연속벽은 제 1흙막이 차단벽(20)(30)에 의해 일차적으로 토압이 차단되는데, 상기 제 1흙막이 차단벽(20)과 제 2흙막이 차단벽(30)의 사이에는 채움부재(50)가 설치되어 있으므로 토압에 대한 지지력을 높일 수 있다. 특히 상기 제 1흙막이 차단벽(20)과 제 2흙막이 차단벽(30)은 소정간격 이격되고 이들의 사이에 채움부재(50)가 채워져 있으므로 상대적으로 토압을 차단하기 위한 두꺼운 벽이 설치된 것과 같은 효과를 얻을 수 있어 토압에 의해 절결지가 무너지거나 주위의 건물이 손상되는 것을 방지할 수 있다. 특히 공사현장으로부터 외부로 진동이 전달되는 것을 차단할 수 있다. 또한 흙막이 공사 시공 시, 터파기 시 토압에 의해 차단벽이 밀리거나 흙이 무너져 주위의 건물이 손상되는 것을 방지할 수 있으며, 지반에 관계없이 시공할 수 있으므로 이중 연속벽의 설계에 따른 및 공사 제약을 줄일 수 있다. The underground continuous wall configured as described above is installed in the area where soil may leak or collapse from the underground wall when the construction work is carried out for the installation of cutout ground or civil works, underground structures of large and large buildings. It is possible to prevent the installation area of the structure from collapsing. In particular, the double continuous wall is the earth pressure is primarily blocked by the first mud blocking wall (20, 30), the filling member (between the first
본 발명은 도면에 도시된 일 실시예를 참고로 설명되었으나 이는 예시적인 것에 불과하며, 당해 기술 분야에서 통상의 지식을 가진 자라면 이로부터 다양한 변형 및 균등한 실시예가 가능하다는 점을 이해할 것이다.While the present invention has been particularly shown and described with reference to exemplary embodiments thereof, it will be understood by those skilled in the art that various changes and modifications may be made without departing from the scope of the invention.
따라서 본 발명의 진정한 보호 범위는 첨부된 청구범위에 의해서만 정해져야 할 것이다. Therefore, the true scope of protection of the present invention should be defined only by the appended claims.
본 발명의 이중 연속벽은 각종 토목공사, 건축공사, 절결지 등의 흙막이 벽으로써 널리 이용가능하다. The double continuous wall of the present invention can be widely used as an earth wall for various civil works, building works, cutouts and the like.
도 1은 본 발명에 따른 이중 연속벽을 나타내 보인 사시도,1 is a perspective view showing a double continuous wall according to the present invention,
도 2 및 도 3은 본 발명에 따른 이중연속벽의 다른 실시예들를 나타내 보인 사시도,2 and 3 are perspective views showing other embodiments of the double continuous wall according to the present invention,
도 4는 본 발명에 따른 이중연속벽의 또 다른 실시예를 나타내 보인 사시도,Figure 4 is a perspective view showing another embodiment of the double continuous wall according to the present invention,
Claims (3)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020080109923A KR101045663B1 (en) | 2008-11-06 | 2008-11-06 | Wall-Foundation system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020080109923A KR101045663B1 (en) | 2008-11-06 | 2008-11-06 | Wall-Foundation system |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20100050832A KR20100050832A (en) | 2010-05-14 |
KR101045663B1 true KR101045663B1 (en) | 2011-06-30 |
Family
ID=42276775
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020080109923A KR101045663B1 (en) | 2008-11-06 | 2008-11-06 | Wall-Foundation system |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR101045663B1 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR102610495B1 (en) * | 2022-10-04 | 2023-12-05 | 임주은 | Construction method of self-supporting retaining wall |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100411990B1 (en) | 2000-12-15 | 2003-12-24 | 주식회사 동우 이앤씨 건축사사무소 | Method for Underground constrution outside waterproofing in limited space |
KR100669530B1 (en) | 2004-06-02 | 2007-01-15 | 박광민 | Construction method of a rataining well |
KR100669527B1 (en) | 2004-06-02 | 2007-01-15 | 박광민 | Construction apparatus of a rataining well |
KR100775552B1 (en) | 2005-02-01 | 2007-12-13 | 상록종합건설주식회사 | Sheet pile and it's construction method |
-
2008
- 2008-11-06 KR KR1020080109923A patent/KR101045663B1/en not_active IP Right Cessation
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100411990B1 (en) | 2000-12-15 | 2003-12-24 | 주식회사 동우 이앤씨 건축사사무소 | Method for Underground constrution outside waterproofing in limited space |
KR100669530B1 (en) | 2004-06-02 | 2007-01-15 | 박광민 | Construction method of a rataining well |
KR100669527B1 (en) | 2004-06-02 | 2007-01-15 | 박광민 | Construction apparatus of a rataining well |
KR100775552B1 (en) | 2005-02-01 | 2007-12-13 | 상록종합건설주식회사 | Sheet pile and it's construction method |
Also Published As
Publication number | Publication date |
---|---|
KR20100050832A (en) | 2010-05-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101173045B1 (en) | Earth retaining-cum-retaining wall, and construction method thereof | |
US7500807B2 (en) | Method of construction using sheet piling sections | |
KR100633796B1 (en) | Connecting structure of mid supporting beam for temporary soil sheathing work | |
US8898996B2 (en) | Method for forming a retaining wall, and corresponding retaining wall | |
KR101331261B1 (en) | Underground prefabricated precast concrete rainwater recycling facility using precast concrete continuous wall in strut structure or earth anchor and construction method of the same | |
EP3521514B1 (en) | Permanent prefabricated braced wall | |
KR100722665B1 (en) | Steel guide wall for construction of underground diaphragm wall and construction method of underground diaphragm wall using the same | |
KR100927186B1 (en) | Method of constructing cantilevered continuous wallsfor retaining earth and cutting off water | |
WO2011114507A1 (en) | Method of constructing underground structure to be newly built | |
KR20160131410A (en) | Temporary construction and originally construction the outer layer of a 2-layer wall type underground road building method | |
KR100831332B1 (en) | Underground retaining wall for public works and method for constructing the same | |
KR101843023B1 (en) | Shear connector for temporary retaining wall file and building outer wall, and method for constructing an underground structure using thereof | |
KR101975297B1 (en) | Multi-wall construction method using multi-wall construction supporting files and supporting files used for construction of harbors, rivers, dams and concrete that can prevent the inflow of soil and water | |
KR101296857B1 (en) | Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same | |
JP2009180035A (en) | Method of connecting caisson | |
KR101045663B1 (en) | Wall-Foundation system | |
KR20210055980A (en) | Underground roadway by top-down method using steel continuous wall in the earth without traffic control and temporary road and method for constructing the same | |
KR20080025219A (en) | Underground outer wall construction method using deck-plate and deck-plate for constructing underground outer wall | |
KR100808977B1 (en) | Connecting structure of corner supporting beam for temporary soil sheathing work | |
KR102021496B1 (en) | Retaining wall construction method and retaining wall structure by the method | |
KR102150531B1 (en) | Retaining wall structure using vertical underground insert and its construction method | |
KR20220160419A (en) | Retaining wall system combine H-piles with steel reinforcement structure | |
KR100659997B1 (en) | Method and structure land-side protection wall using h-beam | |
KR100327547B1 (en) | Composite retaining wall construction method | |
KR100493516B1 (en) | Micro pile and assembly foundation reinforcement structure member and its method for pier |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20140624 Year of fee payment: 4 |
|
FPAY | Annual fee payment |
Payment date: 20151001 Year of fee payment: 5 |
|
FPAY | Annual fee payment |
Payment date: 20160607 Year of fee payment: 6 |
|
LAPS | Lapse due to unpaid annual fee |