KR101034007B1 - A soundproof tunnel and a method for installing the same - Google Patents

A soundproof tunnel and a method for installing the same Download PDF

Info

Publication number
KR101034007B1
KR101034007B1 KR1020100062071A KR20100062071A KR101034007B1 KR 101034007 B1 KR101034007 B1 KR 101034007B1 KR 1020100062071 A KR1020100062071 A KR 1020100062071A KR 20100062071 A KR20100062071 A KR 20100062071A KR 101034007 B1 KR101034007 B1 KR 101034007B1
Authority
KR
South Korea
Prior art keywords
cross
soundproof
cap
end member
row
Prior art date
Application number
KR1020100062071A
Other languages
Korean (ko)
Inventor
봉용범
Original Assignee
주식회사 태건
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 태건 filed Critical 주식회사 태건
Priority to KR1020100062071A priority Critical patent/KR101034007B1/en
Application granted granted Critical
Publication of KR101034007B1 publication Critical patent/KR101034007B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01FADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
    • E01F8/00Arrangements for absorbing or reflecting air-transmitted noise from road or railway traffic
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01FADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
    • E01F8/00Arrangements for absorbing or reflecting air-transmitted noise from road or railway traffic
    • E01F8/0005Arrangements for absorbing or reflecting air-transmitted noise from road or railway traffic used in a wall type arrangement
    • E01F8/0017Plate-like elements
    • EFIXED CONSTRUCTIONS
    • E06DOORS, WINDOWS, SHUTTERS, OR ROLLER BLINDS IN GENERAL; LADDERS
    • E06BFIXED OR MOVABLE CLOSURES FOR OPENINGS IN BUILDINGS, VEHICLES, FENCES OR LIKE ENCLOSURES IN GENERAL, e.g. DOORS, WINDOWS, BLINDS, GATES
    • E06B3/00Window sashes, door leaves, or like elements for closing wall or like openings; Layout of fixed or moving closures, e.g. windows in wall or like openings; Features of rigidly-mounted outer frames relating to the mounting of wing frames
    • E06B3/54Fixing of glass panes or like plates
    • E06B3/5454Fixing of glass panes or like plates inside U-shaped section members
    • EFIXED CONSTRUCTIONS
    • E06DOORS, WINDOWS, SHUTTERS, OR ROLLER BLINDS IN GENERAL; LADDERS
    • E06BFIXED OR MOVABLE CLOSURES FOR OPENINGS IN BUILDINGS, VEHICLES, FENCES OR LIKE ENCLOSURES IN GENERAL, e.g. DOORS, WINDOWS, BLINDS, GATES
    • E06B3/00Window sashes, door leaves, or like elements for closing wall or like openings; Layout of fixed or moving closures, e.g. windows in wall or like openings; Features of rigidly-mounted outer frames relating to the mounting of wing frames
    • E06B3/54Fixing of glass panes or like plates
    • E06B3/58Fixing of glass panes or like plates by means of borders, cleats, or the like
    • E06B3/60Fixing of glass panes or like plates by means of borders, cleats, or the like of clamping cleats of metal
    • E06B3/605Fixing of glass panes or like plates by means of borders, cleats, or the like of clamping cleats of metal made of sheet metal
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating

Abstract

PURPOSE: A soundproof tunnel and a construction method thereof are provided to improve the convenience and speed of construction work for a soundproof tunnel. CONSTITUTION: A soundproof tunnel comprises H-beams, longitudinal members(20), first transverse members(50), second transverse members(60), soundproof panels(40), longitudinal member caps(30), and transverse member caps(70). The H-beams are fixed with reinforcing concrete to a ground structure. The longitudinal members are fixed to the top of the H-beams and formed with stepped portions on both upper sides thereof. The first and second transverse members are arranged to cross the H-beams and the longitudinal members at the right angle and engaged with each other via the longitudinal outer sides thereof. The soundproof panels comprise two longitudinal parts in which the longitudinal inner sides of the first and second transverse members are respectively connected and two transverse parts which are hung on the stepped portions of the adjacent longitudinal members. The longitudinal member caps are fixed to the top of the longitudinal members to hold the longitudinal members and the transverse part of the soundproof panels. The transverse member caps cover the top of the engaged first and second transverse members.

Description

방음터널 및 방음터널의 설치방법{A soundproof tunnel and a method for installing the same}Soundproof tunnel and a method for installing the same}

본 발명은 도로 등에 설치되는 방음터널 및 방음터널의 설치방법에 관한 것이다.The present invention relates to a soundproof tunnel and a soundproof tunnel installed in the road.

도 1 및 도 2 에는 대한민국 등록실용신안 제331601호의 방음터널이 도시되어 있는바, 도 2 는 도 1 의 II부분을 확대하여 도시한 것이다. 도시된 바와 같이 상기 종래의 방음터널에서는, 방음터널의 뼈대가 되는 H빔(5) 위에 지지부재(4)가 설치된 후에, 지지부재 상에 투명판(2)을 지지하는 프레임(1)이 고정되되, 이 때 서로 인접한 프레임(1)들은 충전재(8)가 채워지는 부분의 아래에서 서로 겹쳐지도록 배치된 구성을 가지고 있다.1 and 2 shows a soundproof tunnel of the Republic of Korea Utility Model Model No. 331601, Figure 2 shows an enlarged portion II of FIG. As shown in the conventional soundproof tunnel, after the support member 4 is installed on the H beam 5 serving as a skeleton of the soundproof tunnel, the frame 1 supporting the transparent plate 2 on the support member is fixed. In this case, the frames 1 adjacent to each other have a configuration arranged to overlap each other under the portion where the filler 8 is filled.

이와 같은 구조의 방음터널의 경우에는, 상기 프레임(1)들이 겹쳐진 상태에서 이들을 함께 관통하도록 못(9)을 박아야 하고, 또한 그 위에 충전재(8)를 채워 넣어야 하기 때문에, 상기 투명판(2)과 프레임(1)에 의하여 구성되는 방음패널들이 H빔 위에 설치된 상태에서 작업자가 방음패널 위에 올라가서 작업해야 한다.In the case of the soundproof tunnel having such a structure, it is necessary to nail the nails 9 to penetrate them together in the overlapping state of the frames 1, and to fill the filler 8 thereon, so that the transparent plate 2 ) And the worker should climb and work on the sound insulation panel with the soundproof panels constituted by the frame 1 installed on the H beam.

그러나, 이와 같이 작업자가 방음패널 위에 올라가서 작업해야 하는 경우(특히 방음터널이 고가도로 등에 설치되는 경우)에는, 강풍에 의한 추락사고의 위험이 있다는 문제가 있고, 이와 같은 위험으로 인하여 작업자가 안전에 유의하면 작업 속도가 느려져서 공사 기간의 길게 된다는 문제가 있다. 특히, 작업자가 안전용 로프를 착용하고 작업하면 추락사고의 위험은 다소 저감될 수 있지만, 작업상의 불편 및 이로 인하여 작업 속도가 낮다는 문제는 여전히 해결되지 못한다는 문제가 있다.However, when a worker needs to work on a soundproof panel (especially when a soundproof tunnel is installed on an elevated road, etc.), there is a problem of a fall accident due to a strong wind. There is a problem that the work speed becomes slow and the construction period becomes long. In particular, if the worker wears the safety rope to work the risk of falling accidents can be somewhat reduced, there is a problem that the work inconvenience and thereby the problem of low work speed is still not solved.

본 발명은 상기와 같은 문제점을 해결하여, 작업자가 안전하게 작업하여 설치할 수 있고, 작업자의 작업이 편리하여 작업 속도가 신속하게 될 수 있는 방음터널 및 방음터널의 설치방법을 제공하는 것을 목적으로 한다.An object of the present invention is to provide a method for installing a soundproof tunnel and soundproof tunnel that can be installed by working safely, the operator can work quickly to solve the problems as described above.

상기 목적을 달성하기 위하여, 본 발명은 지상구조물에 고정된 복수의 H빔들을 구비한 방음터널을 제공하는바, 상기 방음터널은: H빔을 따라서 H빔의 상면에 고정되고, 양쪽 상측 측부에 단차부가 형성된 종단부재; H빔에 횡단하도록 배치되고, 종방향 외측이 서로 맞물릴 수 있는 제1 횡단부재 및 제2 횡단부재; 상기 제1 횡단부재 및 제2 횡단부재의 종방향 내측이 각기 개별적으로 결합되는 2개의 종단부들, 및 인접한 종단부재의 대향된 단차부들에 걸쳐지는 2개의 횡단부들을 구비한 방음판; 상기 종단부재와 함께 방음판의 횡단부를 파지하도록 상기 종단부재 위에 고정되는 종단부재 캡; 및 서로 맞물린 제1 횡단부재 및 제2 횡단부재의 상측부를 함께 덮는 횡단부재 캡;을 포함한다.In order to achieve the above object, the present invention provides a soundproof tunnel having a plurality of H-beams fixed to the ground structure, the sound-proof tunnel: is fixed to the upper surface of the H-beams along the H-beams, on both upper sides A termination member having a stepped portion; A first traversing member and a second traversing member disposed to traverse the H-beam, the longitudinal outer sides being able to engage each other; A sound insulation board having two end portions each of which the longitudinal inner sides of the first cross member and the second cross member are individually coupled, and two cross portions extending across opposite step portions of the adjacent end member; An end member cap fixed to the end member to hold a cross section of a sound insulation plate together with the end member; And a cross member cap covering upper portions of the first cross member and the second cross member engaged with each other.

상기 제1 횡단부재, 제2 횡단부재, 및 방음판은 함께 하나의 방음패널을 형성하도록 미리 조립되는 것이 바람직하다.Preferably, the first traverse member, the second traverse member, and the sound insulation plate are assembled in advance so as to form one soundproof panel together.

상기 종단부재는, H빔의 상면에 용접된 보조부재에 체결구에 의하여 결합됨에 의하여 H빔의 상면에 고정될 수 있다.The termination member may be fixed to an upper surface of the H beam by being coupled to the auxiliary member welded to the upper surface of the H beam by a fastener.

상기 제1 횡단부재 및 제2 횡단부재 각각과 상기 방음판의 종단부가 결합되는 부분과, 상기 종단부재 및 종단부재 캡에 의하여 상기 방음판의 횡단부가 파지되는 부분에는, 탄성을 갖는 밀착부재가 배치되는 것이 바람직하다.Wherein each of the first cross-section member and the second cross-member and the end portion of the sound insulation plate is coupled, and the contact portion having elasticity is disposed in the portion where the cross section of the sound insulation plate is gripped by the end member and the end member cap. desirable.

또한 상기 목적을 달성하기 위하여, 본 발명은 방음터널의 설치방법을 제공하는바, 이 설치방법은: 양쪽 상측 측부에 단차부가 형성된 종단부재가 H빔의 상면에 고정된 상태에서 지상구조물에 복수의 H빔들을 설치하는, H빔 설치단계; 상기 H빔에 대한 종방향 외측이 서로 맞물릴 수 있는 제1 횡단부재와 제2 횡단부재, 및 상기 제1 횡단부재 및 제2 횡단부재의 종방향 내측이 각기 개별적으로 결합되는 방음판을 조립하는, 방음패널 조립단계; 및 상기 H빔과 동등하거나 그보다 낮은 위치에 있는 작업자에 의하여 상기 복수의 H빔들 사이에 형성된 열들에 방음패널들이 순차적으로 설치되는, 방음패널 설치단계;를 포함한다.In addition, in order to achieve the above object, the present invention provides a method of installing a soundproof tunnel, the installation method: a plurality of terrestrial structures in the ground structure in a state in which the termination member is formed on the upper side of the H beam fixed to the upper surface of both sides; H beam installation step of installing the H beam; Assembling a soundproof plate in which longitudinal cross-sections of the first cross-member and second cross-members, which can be engaged with each other in the longitudinal direction with respect to the H-beam, and longitudinally inner sides of the first cross-member and the second cross-member are respectively combined; Soundproof panel assembly step; And a soundproof panel installation step of sequentially installing soundproof panels in rows formed between the plurality of H beams by an operator at a position equal to or lower than the H beam.

상기 방음패널 설치단계는: 일 열의 일측의 종단부재에 종단부재 캡이 고정된 상태에서, 일 열의 방음패널들을 순차적으로 배열하는, 방음패널 배열단계; 일 열의 인접한 제1 횡단부재와 제2 횡단부재의 상측부들이 함께 덮이도록 횡단부재 캡을 장착하는, 횡단부재 캡 장착단계; 일 열의 타측의 종단부재에 종단부재 캡을 고정시키는, 종단부재 캡 고정단계; 및 다음 열에 대하여 상기 방음패널 배열단계, 횡단부재 캡 장착단계, 및 종단부재 캡 고정단계를 수행하는, 다음 열 설치단계;를 포함하는 것이 바람직하다.The soundproof panel installation step may include: sequentially arranging soundproof panels of a row in a state in which a termination member cap is fixed to one end member of a row of soundproof panels; A transverse member cap mounting step of mounting a transverse member cap such that the upper portions of the adjacent first cross member and the second cross member in a row are covered together; Fixing the end member cap to the end member of the other side of the row, the end member cap fixing step; And a next row installation step of performing the sound insulation panel arrangement step, the cross member cap mounting step, and the end member cap fixing step with respect to the next row.

상기 방음패널 배열단계는, 일 열의 일측에 있는 종단부재와 종단부재 캡 사이에 방음패널의 일 횡단부를 끼우고, 일 열의 타측에 있는 종단부재의 단차부에 방음패널의 다른 횡단부를 배치시키며, 설치 중인 방음패널을 동일한 열에서 앞서 설치된 방음패널에 대하여 밀어서 설치 중인 방음패널의 제2 횡단부재가 앞서 설치된 방음패널의 제1 횡단부재에 맞물리도록 수행되는 것이 바람직하다.In the sound insulation panel arrangement step, one cross section of the sound insulation panel is sandwiched between the end member and the end member cap on one side of one row, and the other cross section of the soundproof panel is disposed on the stepped portion of the end member on the other side of the one row. It is preferable that the second cross member of the soundproof panel being installed is engaged with the first cross member of the previously installed soundproof panel by pushing the soundproof panel in the same row with respect to the previously installed soundproof panel.

상기 종단부재 캡 고정단계는, 종단부재 캡이 종단부재와 함께 방음판의 횡단부를 파지하도록 배치된 상태에서, 종단부재 캡과 종단부재를 체결구에 의하여 고정시킴으로써 수행될 수 있다.The terminating member cap fixing step may be performed by fixing the terminating member cap and the terminating member by a fastener in a state where the terminating member cap is arranged to grip the transverse of the sound insulation plate together with the terminating member.

상기 방음패널 조립단계에서는, 상기 제1 횡단부재 및 제2 횡단부재 각각과 상기 방음판의 종단부가 결합되는 부분에 탄성을 갖는 밀착부재가 배치되는 것이 바람직하다.In the soundproof panel assembly step, it is preferable that a close contact member having elasticity is disposed at a portion where each of the first cross member and the second cross member and the end portion of the sound insulation plate are coupled to each other.

상기 H빔 설치단계에서는, 상기 종단부재가 체결구에 의하여, H빔의 상면에 용접된 보조부재에 고정될 수 있다.In the H beam installation step, the termination member may be fixed to the auxiliary member welded to the upper surface of the H beam by the fastener.

본 발명에 의하여, 작업자가 안전하게 작업하여 설치할 수 있고, 작업자의 작업이 편리하여 작업 속도가 신속하게 될 수 있는 방음터널 및 방음터널의 설치방법이 제공된다.According to the present invention, there is provided an installation method of a soundproof tunnel and a soundproof tunnel which can be installed safely by the operator, the operator's work is convenient and the speed of work can be quickly.

도 1 은 종래기술인 대한민국 등록실용신안 제331601호의 도 1 을 도시하는 부분절개 사시도이고,
도 2 는 도 1 의 II부분을 확대하여 도시한 것으로서 대한민국 등록실용신안 제331601호의 도 4a 에 해당하고,
도 3 은 본 발명의 방음패널들이 설치되는 H빔들을 도시하는 사시도이고,
도 4 는 도 3 의 Y방향으로 본 사시도로서, 본 발명에 따른 방음패널들이 설치되는 중의 모습이 도시되어 있고,
도 5 는 도 4 의 V-V선을 따라 취한 단면도이고,
도 6 은 도 4 의 VI-VI선을 따라 취한 단면도이고,
도 7 은 본 발명의 방음패널을 도시하는 사시도이다.
1 is a partial cutaway perspective view of FIG. 1 of the Republic of Korea Utility Model Model No. 331601 of the prior art,
FIG. 2 is an enlarged view of part II of FIG. 1 and corresponds to FIG. 4A of Korean Utility Model Registration No. 331601,
3 is a perspective view showing H beams to which sound insulation panels of the present invention are installed;
Figure 4 is a perspective view of the Y direction in Figure 3, the sound insulation panel according to the present invention is shown being installed,
5 is a cross-sectional view taken along the line VV of FIG. 4,
6 is a cross-sectional view taken along the line VI-VI of FIG. 4,
7 is a perspective view showing a sound insulation panel of the present invention.

이어서, 첨부된 도면들을 참조하여 본 발명의 실시예를 상세히 설명한다.Next, embodiments of the present invention will be described in detail with reference to the accompanying drawings.

본 발명에 따른 방음터널은, H빔(10)들, 종단부재(20), 제1 횡단부재(50), 제2 횡단부재(60), 방음판(40), 종단부재 캡(30), 및 횡단부재 캡(70)을 포함한다.Soundproof tunnel according to the invention, H beams 10, the termination member 20, the first crossing member 50, the second crossing member 60, the soundproof plate 40, the termination member cap 30, and And a traverse member cap 70.

H빔(10)들은 철근콘크리트 등에 의하여 지상에 설치된 지상구조물(1)에 고정되는 것으로서, 예를 들어 그 지상구조물의 형성 시에 지상구조물 내에 매립설치된 앵커(anchor)에 의하여 고정될 수 있다. 참고적으로, 도 3 에 도시된 H빔(10)들 사이에는 간격 유지를 위한 소형 H빔이 배치되는 것이 통상적이지만, 본 출원의 도면에서는 간명화를 위하여 생략되었다.The H beams 10 are fixed to the ground structure 1 installed on the ground by reinforced concrete or the like, and may be fixed by anchors embedded in the ground structure, for example, when the ground structure is formed. For reference, a small H beam for maintaining a gap is conventionally disposed between the H beams 10 shown in FIG. 3, but is omitted for simplicity in the drawings of the present application.

도 4 에는 상기 H빔(10)과 종단부재(20)의 상대적인 배치상태가 도시되어 있고, 도 5 에는 종단부재(20)의 단면이 상세히 도시되어 있다. 도 4 에 도시된 바와 같이, 종단부재(20)는 H빔(10)을 따라서 H빔의 상면에 고정된다.4 shows a relative arrangement of the H beam 10 and the termination member 20, and FIG. 5 shows a cross section of the termination member 20 in detail. As shown in FIG. 4, the termination member 20 is fixed to the top surface of the H beam along the H beam 10.

종단부재(20)를 H빔의 상면에 고정시키는 수단은 다양한 것들이 있을 수 있으나, 도시된 실시예에서는 H빔의 상면에 상대적으로 작은 단면을 갖는 보조부재(20a)를 용접에 의하여 먼저 고정시키고, 종단부재(20)의 하측에 보조부재(20a)의 수용을 위한 보조부재 수용부(20c)를 형성하여, 보조부재(20a)가 보조부재 수용부(20c) 내에 수용된 상태에서 체결구(20b)에 의하여 보조부재와 종단부재(20)를 결합시킴으로써, 종단부재(20)가 H빔(10)에 고정되도록 한다. 여기에서 체결구란, 도시된 바와 같은 나사못에 한정되지 않고, 예를 들어 기계적 타격장치에 의하여 대상물에 박히는 소위 피스(piece)라 불리는 것도 이에 포함된다.Means for fixing the termination member 20 to the upper surface of the H-beam may be a variety of things, in the illustrated embodiment first to fix the auxiliary member 20a having a relatively small cross-section to the upper surface of the H-beam by welding, The auxiliary member receiving part 20c for accommodating the auxiliary member 20a is formed in the lower side of the termination member 20, and the fastener 20b is provided in the state in which the auxiliary member 20a is accommodated in the auxiliary member receiving part 20c. By coupling the auxiliary member and the termination member 20 by the, the termination member 20 is to be fixed to the H beam (10). The fastener herein is not limited to a screw as shown, but includes, for example, a so-called piece that is embedded in an object by a mechanical striking device.

상기 종단부재(20)의 양쪽 상측 측부에는 단차부(21)가 형성되어 있는데, 이에 관하여는 후술하기로 한다.Stepped portions 21 are formed on both upper sides of the termination member 20, which will be described later.

제1 횡단부재(50) 및 제2 횡단부재(60)는 도 4 의 중앙 상측에 간략히 도시된 바와 같이 H빔(10) 및 종단부재(20)에 대해 횡단하도록, 즉 실질적으로 직각으로 배치되는 것으로서, 도 6 에는 종방향 외측이 서로 맞물려 있는 제1 횡단부재(50) 및 제2 횡단부재(60)가 도시되어 있다. 여기에서 제1 횡단부재(50)와 제2 횡단부재(60)의 맞물림은 제1 횡단부재의 요부(51)와 제2 횡단부재의 돌출부(61)가 서로 맞물림에 의하여 이루어진다. 위에서, '종방향 외측'이란, H빔(10)과 방음판(40)을 기준으로 하는 방향표현으로서, H빔(10)에 대해 종방향인 방향에서 방음판(40)을 중심으로 볼 때에 외측임을 의미한다. 이와 같은 방향표현은 후술되는 '종방향 내측'에 대하여도 마찬가지로 적용된다.The first traverse member 50 and the second traverse member 60 are arranged to traverse the H beam 10 and the termination member 20, ie substantially perpendicularly, as shown briefly above the center of FIG. 4. As shown in FIG. 6, a first cross member 50 and a second cross member 60 are shown in which the longitudinal outer sides are engaged with each other. In this case, the first cross member 50 and the second cross member 60 are engaged with each other by engaging the recess 51 of the first cross member and the protrusion 61 of the second cross member. In the above, the "outward longitudinal direction" is a direction expression based on the H beam 10 and the soundproof plate 40, and is an outer side when viewed from the soundproof plate 40 in the longitudinal direction with respect to the H beam 10. it means. This direction expression is likewise applied to the "vertical inner side" described later.

상기 방음판(40)은 소음을 차폐하기 위한 판으로서, 통상적으로는 빛이 투과할 수 있는 투명한 방음판이 이용되지만, 이에 한정되는 것은 아니며, 필요에 따라서 반투명 또는 불투명의 방음판이 이용될 수 있다.The sound insulation board 40 is a plate for shielding noise, and generally, a transparent sound insulation board through which light can pass is used, but is not limited thereto. A translucent or opaque sound insulation board may be used as necessary.

상기 방음판(40)은, 도 7 에 도시된 바와 같이, 상기 제1 횡단부재(50) 및 제2 횡단부재(60)의 종방향 내측이 각기 개별적으로 결합되는 2개의 종단부(42)들, 및 인접한 종단부재(20)의 대향된 단차부(21)들에 걸쳐지는 2개의 횡단부(41)들을 구비한다. 도 7 에 도시된 바와 같이, 방음판(40)의 횡단부(41)들은 방음판의 종방향으로 끝까지 연장되지만, 방음판의 종단부(42)들은 횡단부(41)들에 의하여 그 한계가 정해진다. 상기 횡단부(41)들이 종단부재(20)의 단차부(21)에 걸쳐짐에 있어서 제1 횡단부재(50) 및 제2 횡단부재(60)에 의해 방해받지 않도록 하기 위한 것이다.As shown in FIG. 7, the soundproof plate 40 includes two end portions 42 each of which the longitudinal inner sides of the first crossing member 50 and the second crossing member 60 are individually coupled to each other. And two transverse portions 41 spanning the opposing step portions 21 of the adjacent termination member 20. As shown in FIG. 7, the cross sections 41 of the sound insulation board 40 extend all the way in the longitudinal direction of the sound insulation board, but the ends 42 of the sound insulation board are limited by the cross sections 41. The cross sections 41 are provided so as not to be disturbed by the first cross member 50 and the second cross member 60 in the stepped portion 21 of the termination member 20.

상기 제1 횡단부재(50), 제2 횡단부재(60), 및 방음판(40)은, H빔들 사이에 설치되기 전에, 함께 하나의 방음패널(100)을 형성하도록 미리 조립되는 것이 바람직한데, 이로써 제1 횡단부재(50), 제2 횡단부재(60), 및 방음판(40)을 H빔들 사이에 설치함에 있어서 소요되는 전체적인 시간이 현저히 절감된다.The first traverse member 50, the second traverse member 60, and the sound insulation plate 40 is preferably assembled in advance to form a sound insulation panel 100 together, before being installed between the H beams, As a result, the overall time required for installing the first cross member 50, the second cross member 60, and the soundproof plate 40 between the H beams is significantly reduced.

도 6 에 도시된 바와 같이, 상기 제1 횡단부재(50) 및 제2 횡단부재(60) 각각과 상기 방음판의 종단부(42)가 결합되는 부분(즉, 제1 횡단부재(50)와 종단부(42)의 사이들과, 제2 횡단부재(60)와 종단부(42)의 사이들)에는 탄성을 갖는 밀착부재(80)가 배치되는 것이 바람직한데, 이것은 제1 횡단부재(50) 및 제2 횡단부재(60)와 방음판 사이로 소음이 누설되는 것을 방지하고, 나아가 방음판(40) 위로 낙하된 빗물 등이 방음터널의 하측으로 낙하하는 것을 방지하기 위한 것이다.As shown in FIG. 6, each of the first cross member 50 and the second cross member 60 and the end portion 42 of the sound insulation plate are coupled to each other (ie, the first cross member 50 and the end portion). Between the portion 42, and between the second cross member 60 and the end portion 42) it is preferable that the elastic contact member 80 is disposed, which is the first cross member 50 And it is to prevent the leakage of noise between the second cross member 60 and the sound insulation plate, and further to prevent the rain water and the like falling over the sound insulation plate 40 to fall to the lower side of the soundproof tunnel.

도 6 에는 제1 횡단부재(50)의 상측부(52)와 제2 횡단부재(60)의 상측부(62)를 함께 덮는 횡단부재 캡(70)이 상세히 도시되어 있는데, 이것은 제1 횡단부재(50)와 제2 횡단부재(60) 사이로 소음이 누설되는 것을 방지하고, 나아가 제1 횡단부재(50)와 제2 횡단부재(60) 위로 낙하된 빗물 등이 방음터널의 하측으로 낙하하는 것을 방지하기 위한 것이다.6 shows in detail a transverse member cap 70 covering the upper portion 52 of the first traverse member 50 and the upper portion 62 of the second traverse member 60, which is the first traverse member. The noise is prevented from leaking between the 50 and the second crossing member 60, and further, the rain water falling on the first crossing member 50 and the second crossing member 60 falls to the lower side of the soundproof tunnel. It is to prevent.

도 5 에 상세히 도시된 종단부재 캡(30)은, 상기 종단부재(20)와 함께 방음판의 횡단부(41)를 파지하기 위한 것으로서, 방음판의 횡단부(41)가 종단부재의 단차부(21) 상에 놓여진 상태에서 종단부재 위에 고정된다. 종단부재 캡(30)가 종단부재(20)에 고정되는 방식은, 종단부재(20)와 보조부재(20a)에 고정되는 방식과 동일할 수도 있고 상이할 수도 있다.The end member cap 30 shown in detail in FIG. 5 is for holding the cross section 41 of the soundproof plate together with the end member 20, and the cross section 41 of the soundproof plate has a stepped portion 21 of the end member. It is fixed on the end member in a state placed on the). The way in which the end member cap 30 is fixed to the end member 20 may be the same as or different from the way in which the end member 20 is fixed to the end member 20 and the auxiliary member 20a.

또한, 도 5 에 도시된 바와 같이, 종단부재(20) 및 종단부재 캡(30)에 의하여 상기 방음판의 횡단부(41)가 파지되는 부분(즉, 종단부재의 단차부(21)와 방음판의 횡단부(41) 사이와, 종단부재 캡(30)과 방음판의 횡단부(41) 사이)에도 밀착부재(80)가 배치되는 것이 바람직하다.
In addition, as shown in Figure 5, by the end member 20 and the end member cap 30, the portion of the cross section 41 of the soundproof plate is held (that is, the stepped portion 21 of the end member and the soundproof plate of The close contact member 80 is preferably arranged between the cross sections 41 and between the end member cap 30 and the cross section 41 of the soundproof plate.

이하에서는, 위와 같은 구성을 갖는 방음터널의 설치방법에 관하여 설명한다. 본 발명에 따른 방음터널의 설치방법은 H빔 설치단계, 방음패널 조립단계, 및 방음패널 설치단계를 포함한다.Hereinafter, the installation method of the soundproof tunnel having the above configuration will be described. The installation method of the soundproof tunnel according to the present invention includes an H beam installation step, a soundproof panel assembly step, and a soundproof panel installation step.

H빔 설치단계는 지상구조물(1)에 H빔(10)들을 설치하는 단계로서, 이 때에는 전술된 방식으로 상기 종단부재(20)가 H빔의 상면에 고정된 상태에서, 지상구조물(1)에 H빔(10)들을 설치하며, 이 때에는 종단부재의 단차부(21)에 밀착부재(80)를 미리 장착해 두는 것이 바람직하다.The H beam installation step is to install the H beams 10 on the ground structure 1, in which case the terminating member 20 is fixed to the upper surface of the H beam in the above-described manner, the ground structure 1 H-beams 10 are installed in this case. In this case, it is preferable to attach the contact member 80 to the stepped portion 21 of the termination member in advance.

방음패널 조립단계는 상기 제1 횡단부재(50), 제2 횡단부재(60), 및 방음판(40)을 조립하는 단계로서, 이들을 H빔(10)에 설치하기 전에 미리 조립해 둠으로써, 공사 전체에 소요되는 시간이 현저히 절감될 수 있다.Soundproof panel assembling step is a step of assembling the first cross member 50, the second cross member 60, and the soundproof plate 40, by assembling them before installation in the H beam 10, construction Overall time can be significantly reduced.

방음패널 조립단계에서는, 방음판(40)의 2개의 종단부들에 제1 횡단부재(50)와 제2 횡단부재(60)를 각각 결합시키는데, 이 결합을 수행하기 전에 제1 횡단부재(50) 및 제2 횡단부재(60)에 도 6 에 도시된 바와 같이 밀착부재(80)를 장착해 두는 것이 바람직하다.In the soundproof panel assembly step, the first traverse member 50 and the second traverse member 60 are respectively coupled to the two end portions of the soundproof plate 40, before the first transverse member 50 and It is preferable to attach the contact member 80 to the second crossing member 60 as shown in FIG.

방음패널 설치단계는, 상기 H빔(10)과 동등하거나 그보다 낮은 위치에 있는(예를 들어, 지상의 크레인 등에 의하여 지지되는 작업대(2) 상에 있는) 작업자(W; 도 4 참조)가 상기 복수의 H빔(10)들 사이에 형성된 열들(201, 202)에 방음패널(100)들을 순차적으로 설치하는 단계이다. 여기에서 '순차적'이라 함은, 예를 들어 제1열(201)에 방음패널(100)들을 설치한 후에, 제2열(202)에 방음패널들을 설치한다는 것을 의미한다.
In the soundproof panel installation step, the worker W (see FIG. 4) at the position equal to or lower than the H beam 10 (for example, on the work bench 2 supported by a crane on the ground, etc.) In this step, the sound insulation panels 100 are sequentially installed in the columns 201 and 202 formed between the plurality of H beams 10. Here, "sequential" means that the sound insulation panels 100 are installed in the second row 202 after the sound insulation panels 100 are installed in the first row 201.

아래에서는 방음패널 설치단계를 보다 상세히 설명하기로 한다.The following describes the soundproofing panel installation step in more detail.

방음패널 설치단계는, 방음패널 배열단계, 횡단부재 캡 장착단계, 종단부재 캡 고정단계, 및 다음 열 설치단계를 포함한다.The soundproof panel installation step includes a soundproof panel arrangement step, a transverse member cap mounting step, an end member cap fixing step, and a next row installation step.

방음패널 배열단계는, 일 열(예를 들어, 제1열(201))의 일측(도 4 에서 우측에서 첫 번째)의 종단부재(20)에 종단부재 캡(30)이 고정된 상태에서, 일 열의 방음패널들을 순차적으로(예를 들어 도 4 의 상측에서 하측으로) 배열하는 단계이다.In the sound insulation panel arrangement step, in a state in which the termination member cap 30 is fixed to the termination member 20 of one side (for example, the first from the right in FIG. 4) of one row (eg, the first row 201), Arranging the rows of sound insulation panels sequentially (for example, from top to bottom in FIG. 4).

방음패널 배열단계에서는, 작업자(W)가 방음패널(100)을 들어서(A; 도 4 의 중앙 부분 참조), 일 열(예를 들어, 제1열(201))의 일측(도 4 에서 우측에서 첫 번째)에 있는 종단부재(20)와 종단부재 캡(30) 사이에 방음패널의 일 횡단부(41)(예를 들어, 도 7 의 우상측에 있는 횡단부(41))를 끼우고(B), 일 열(예를 들어, 제1열(201))의 타측(도 4 에서 우측에서 두 번째)에 있는 종단부재(20)의 단차부(21)에 방음패널의 다른 횡단부(예를 들어, 도 7 의 좌하측에 있는 횡단부(41))를 올려놓고(C), 현재 설치 중인 방음패널을 동일한 열(예를 들어, 제1열(201))에서 앞서 설치된 방음패널(Y방향에 있는 방음패널)에 대하여 밀어서(D), 현재 설치 중인 방음패널의 제2 횡단부재(60)가 앞서 설치된 방음패널의 제1 횡단부재(50)에 맞물리도록 수행된다.In the sound insulation panel arrangement step, the worker W lifts the sound insulation panel 100 (A; see the center portion of FIG. 4), and one side (for example, the first row 201) of one side (the right side in FIG. 4). Between the end member 20 and the end member cap 30 in the first in the (a) the one cross section 41 of the sound insulation panel (for example, the cross section 41 on the upper right side of Figure 7) (B), the other transverse section of the soundproof panel in the stepped portion 21 of the termination member 20 on the other side (for example, the first row 201) (the second from the right in FIG. 4). For example, the transverse part 41 on the lower left side of FIG. 7 is placed (C), and the soundproof panel currently installed in the same row (for example, the first row 201) is installed in the same soundproof panel (for example, the first row 201). Pushing against the soundproof panel in the Y direction (D), the second traverse member 60 of the soundproof panel currently being installed is performed to engage the first traverse member 50 of the soundproof panel previously installed.

횡단부재 캡 장착단계는, 일 열(예를 들어, 제1열(201))에서 서로 인접한 제1 횡단부재(50)와 제2 횡단부재(60)의 상측부들(52, 62)이 함께 덮이도록 횡단부재 캡(70)을 장착하는 단계인데, 도 4 에서 제1열(201)에 대하여 상기 방음패널 배열단계가 종료된 상태에서는 도 4 의 우측에서 두 번째에 도시된 종단부재 캡(30)이 아직 설치되지 않은 상태이므로, 횡단부재 캡(70)을 도 4 의 우측(X방향)으로 밀어 끼움으로써 상기 장착이 쉽게 수행될 수 있다.The mounting of the cross member cap may include covering the first cross member 50 and the upper portions 52 and 62 of the second cross member 60 adjacent to each other in one row (eg, the first row 201). Mounting the transverse member cap 70 so as to, the end member cap 30 shown in the second from the right side of Figure 4 in the state that the sound insulation panel arrangement step is completed for the first row 201 in FIG. Since this is not yet installed, the mounting can be easily performed by pushing the cross member cap 70 to the right (X direction) of FIG.

종단부재 캡 고정단계는 일 열(예를 들어, 제1열(201))의 타측(도 4 에서 우측에서 두 번째)의 종단부재에 종단부재 캡(30)을 고정시키는 단계이다. 참고적으로, 본 단계의 수행 직전과 수행 직후에는, 제1열(201)의 방음패널(100)들은 모두 배열된 상태이고, 제2열(202)의 방음패널들은 모두 배열되지 않은 상태이다.The end member cap fixing step is a step of fixing the end member cap 30 to the end member of the other side (for example, the second from the right in FIG. 4) of one row (eg, the first row 201). For reference, immediately before and after the execution of this step, the sound insulation panels 100 of the first row 201 are all arranged, and the sound insulation panels of the second row 202 are not all arranged.

상기 종단부재 캡 고정단계는, 종단부재 캡(30)이 종단부재(20)와 함께 방음판의 횡단부(41)를 파지하도록 배치된 상태에서, 종단부재 캡과 종단부재를 체결구(20b)에 의하여 고정시킴으로써 수행된다. 종단부재 캡 고정단계가 완료되면 제1열(201)에 대한 방음패널들의 설치가 완료되고, 이 후에는 다음 열, 즉 제2열(202)에 방음패널(100)들을 설치하는 다음 열 설치단계가 수행된다.In the end member cap fixing step, the end member cap 30 and the end member cap and the end member to the fastener 20b in a state in which the end member cap 30 is arranged to grip the transverse portion 41 of the soundproof plate together with the end member 20. By fixation. When the termination member cap fixing step is completed, the installation of the sound insulation panels for the first row 201 is completed, and thereafter, the next row installation step for installing the sound insulation panels 100 in the next row, that is, the second row 202. Is performed.

다음 열 설치단계에서는, 방음패널(100)들이 설치되는 열이 변경(제1열(201)로부터 제2열(202)로 변경)되는바, 다음 열에 대하여 상기 방음패널 배열단계, 횡단부재 캡 장착단계, 및 종단부재 캡 고정단계가 수행된다. 이 때, 위에서 설명된 일 열(제1열(201))의 타측(도 4 에서 방음패널에 대하여 좌측)은 다음 열(제2열(202)의 일측(도 4 에서 방음패널에 대하여 우측)과 동일한 방향을 지칭하게 된다. H빔(10)들 사이에 있는 열마다 다음 열 설치단계를 수행한다.In the next row installation step, the column in which the sound insulation panels 100 are installed is changed (change from the first row 201 to the second row 202), the sound insulation panel arrangement step for the next row, mounting the cross member cap Step, and the end member cap fixing step are performed. At this time, the other side (the left side with respect to the sound insulation panel in FIG. 4) of one row (the first column 201) described above is the next column (the right side with respect to the sound insulation panel in FIG. 4) the next row. It refers to the same direction as the next column installation step for each column between the H beams (10).

본 발명에 따르면, 작업자(W)가 난간(2a) 등에 의하여 안전이 확보된 작업대(2) 상에서 방음패널을 설치할 수 있으므로, 무엇보다도 작업자의 안전이 확보되고, 상기 작업대(2)에는 미리 제작된 방음패널(100)들을 많이 적재할 수 있으므로 종래기술에 비하여 작업 효율이 현저히 향상된다.According to the present invention, since the worker W can install the soundproof panel on the worktable 2 secured by the handrail 2a or the like, above all, the safety of the worker is ensured, and the worktable 2 is prepared in advance. Since the sound insulation panels 100 can be loaded a lot, the work efficiency is remarkably improved as compared with the related art.

본 발명은 도면에 도시된 실시예를 참고로 설명되었으나 이는 예시적인 것에 불과하며, 본 기술 분야의 통상의 지식을 가진 자라면 이로부터 다양한 변형 및 균등한 다른 실시예가 가능하다는 점을 이해할 것이다. 따라서, 본 발명의 진정한 기술적 보호 범위는 첨부된 특허청구범위의 기술적 사상에 의하여 정해져야 할 것이다.Although the present invention has been described with reference to the embodiments shown in the drawings, this is merely exemplary, and it will be understood by those skilled in the art that various modifications and equivalent other embodiments are possible. Therefore, the true technical protection scope of the present invention will be defined by the technical spirit of the appended claims.

10: H빔
20: 종단부재
30: 종단부재 캡
40: 방음판
50: 제1 횡단부재
60: 제2 횡단부재
70: 횡단부재 캡
10: H beam
20: termination member
30: termination member cap
40: soundproof plate
50: first cross member
60: second cross member
70: cross member cap

Claims (10)

지상구조물에 고정된 복수의 H빔들을 구비한 방음터널로서,
H빔을 따라서 H빔의 상면에 고정되고, 양쪽 상측 측부에 단차부가 형성된 종단부재;
H빔에 횡단하도록 배치되고, 종방향 외측이 서로 맞물릴 수 있는 제1 횡단부재 및 제2 횡단부재;
상기 제1 횡단부재 및 제2 횡단부재의 종방향 내측이 각기 개별적으로 결합되는 2개의 종단부들, 및 인접한 종단부재의 대향된 단차부들에 걸쳐지는 2개의 횡단부들을 구비한 방음판;
상기 종단부재와 함께 방음판의 횡단부를 파지하도록 상기 종단부재 위에 고정되는 종단부재 캡; 및
서로 맞물린 제1 횡단부재 및 제2 횡단부재의 상측부를 함께 덮는 횡단부재 캡;을 포함하고,
상기 제1 횡단부재, 제2 횡단부재, 및 방음판은 함께 하나의 방음패널을 형성하도록 조립되는, 방음터널.
Soundproof tunnel having a plurality of H-beams fixed to the ground structure,
A termination member fixed to an upper surface of the H beam along the H beam, and having a stepped portion at both upper sides thereof;
A first traversing member and a second traversing member disposed to traverse the H-beam, the longitudinal outer sides being able to engage each other;
A sound insulation board having two end portions each of which the longitudinal inner sides of the first cross member and the second cross member are individually coupled, and two cross portions extending across opposite step portions of the adjacent end member;
An end member cap fixed to the end member to hold a cross section of a sound insulation plate together with the end member; And
And a cross member cap covering upper portions of the first cross member and the second cross member engaged with each other.
And the first crossing member, the second crossing member, and the soundproof plate are assembled to form one soundproof panel together.
삭제delete 제 1 항에 있어서,
상기 종단부재는, H빔의 상면에 용접된 보조부재에 체결구에 의하여 결합됨에 의하여 H빔의 상면에 고정되는, 방음터널.
The method of claim 1,
The termination member is fixed to the upper surface of the H beam by being coupled to the auxiliary member welded to the upper surface of the H beam by the fastener, soundproof tunnel.
제 1 항 또는 제 3 항에 있어서,
상기 제1 횡단부재 및 제2 횡단부재 각각과 상기 방음판의 종단부가 결합되는 부분과, 상기 종단부재 및 종단부재 캡에 의하여 상기 방음판의 횡단부가 파지되는 부분에는, 탄성을 갖는 밀착부재가 배치되는, 방음터널.
The method according to claim 1 or 3,
Wherein each of the first cross-section member and the second cross-member and the end portion of the soundproof plate is coupled, the contact portion having elasticity is disposed in the portion where the cross section of the soundproof plate is gripped by the end member and the end member cap, Soundproof tunnel.
방음터널의 설치방법으로서,
양쪽 상측 측부에 단차부가 형성된 종단부재가 H빔의 상면에 고정된 상태에서 지상구조물에 복수의 H빔들을 설치하는, H빔 설치단계;
상기 H빔에 대한 종방향 외측이 서로 맞물릴 수 있는 제1 횡단부재와 제2 횡단부재, 및 상기 제1 횡단부재 및 제2 횡단부재의 종방향 내측이 각기 개별적으로 결합되는 방음판을 조립하는, 방음패널 조립단계; 및
상기 H빔과 동등하거나 그보다 낮은 위치에 있는 작업자에 의하여 상기 복수의 H빔들 사이에 형성된 열들에 방음패널들이 순차적으로 설치되는, 방음패널 설치단계;를 포함하는, 방음터널 설치방법.
As a soundproof tunnel installation method,
An H-beam installation step of installing a plurality of H-beams on the ground structure in a state in which the end members having the stepped portions formed on both upper sides thereof are fixed to the upper surface of the H-beam;
Assembling a soundproof plate in which longitudinal cross-sections of the first cross-member and second cross-members, which can be engaged with each other in the longitudinal direction with respect to the H-beam, and longitudinally inner sides of the first cross-member and the second cross-member are respectively combined; Soundproof panel assembly step; And
And a soundproof panel installation step of sequentially installing soundproof panels in rows formed between the plurality of H beams by an operator at a position equal to or lower than the H beam.
제 5 항에 있어서,
상기 방음패널 설치단계는:
일 열의 일측의 종단부재에 종단부재 캡이 고정된 상태에서, 일 열의 방음패널들을 순차적으로 배열하는, 방음패널 배열단계;
일 열의 인접한 제1 횡단부재와 제2 횡단부재의 상측부들이 함께 덮이도록 횡단부재 캡을 장착하는, 횡단부재 캡 장착단계;
일 열의 타측의 종단부재에 종단부재 캡을 고정시키는, 종단부재 캡 고정단계; 및
다음 열에 대하여 상기 방음패널 배열단계, 횡단부재 캡 장착단계, 및 종단부재 캡 고정단계를 수행하는, 다음 열 설치단계;를 포함하는, 방음터널 설치방법.
The method of claim 5, wherein
The soundproofing panel installation step:
A soundproof panel arrangement step of sequentially arranging soundproof panels in a row in a state in which the end member cap is fixed to one end member in a row;
A transverse member cap mounting step of mounting a transverse member cap such that the upper portions of the adjacent first cross member and the second cross member in a row are covered together;
Fixing the end member cap to the end member of the other side of the row, the end member cap fixing step; And
And a next row installation step of performing the sound insulation panel arrangement step, the cross member cap mounting step, and the end member cap fixing step with respect to a next row.
제 6 항에 있어서,
상기 방음패널 배열단계는, 일 열의 일측에 있는 종단부재와 종단부재 캡 사이에 방음패널의 일 횡단부를 끼우고, 일 열의 타측에 있는 종단부재의 단차부에 방음패널의 다른 횡단부를 배치시키며, 설치 중인 방음패널을 동일한 열에서 앞서 설치된 방음패널에 대하여 밀어서 설치 중인 방음패널의 제2 횡단부재가 앞서 설치된 방음패널의 제1 횡단부재에 맞물리도록 수행되는, 방음터널 설치방법.
The method according to claim 6,
In the sound insulation panel arrangement step, one cross section of the sound insulation panel is sandwiched between the end member and the end member cap on one side of one row, and the other cross section of the soundproof panel is disposed on the stepped portion of the end member on the other side of the one row. A soundproof tunnel installation method, wherein the soundproof panel being pushed against the soundproof panel previously installed in the same row is engaged with the first crossmember of the soundproof panel installed before.
제 7 항에 있어서,
상기 종단부재 캡 고정단계는, 종단부재 캡이 종단부재와 함께 방음판의 횡단부를 파지하도록 배치된 상태에서, 종단부재 캡과 종단부재를 체결구에 의하여 고정시킴으로써 수행되는, 방음터널 설치방법.
The method of claim 7, wherein
The end member cap fixing step is performed by fixing the end member cap and the end member by the fastener in a state in which the end member cap is arranged to grip the transverse of the sound insulation plate together with the end member.
제 5 항 내지 제 8 항 중의 어느 한 항에 있어서,
상기 방음패널 조립단계에서는, 상기 제1 횡단부재 및 제2 횡단부재 각각과 상기 방음판의 종단부가 결합되는 부분에 탄성을 갖는 밀착부재가 배치되는, 방음터널 설치방법.
The method according to any one of claims 5 to 8,
In the soundproof panel assembly step, the sound insulation tunnel installation method, the elastic member is disposed in the portion where the end of each of the first cross member and the second cross member and the sound insulating plate is coupled.
제 9 항에 있어서,
상기 H빔 설치단계에서는, 상기 종단부재가 체결구에 의하여, H빔의 상면에 용접된 보조부재에 고정되는, 방음터널 설치방법.
The method of claim 9,
In the H beam installation step, the termination member is fixed to the auxiliary member welded to the upper surface of the H beam by fasteners, soundproof tunnel installation method.
KR1020100062071A 2010-06-29 2010-06-29 A soundproof tunnel and a method for installing the same KR101034007B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020100062071A KR101034007B1 (en) 2010-06-29 2010-06-29 A soundproof tunnel and a method for installing the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020100062071A KR101034007B1 (en) 2010-06-29 2010-06-29 A soundproof tunnel and a method for installing the same

Publications (1)

Publication Number Publication Date
KR101034007B1 true KR101034007B1 (en) 2011-05-11

Family

ID=44365880

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020100062071A KR101034007B1 (en) 2010-06-29 2010-06-29 A soundproof tunnel and a method for installing the same

Country Status (1)

Country Link
KR (1) KR101034007B1 (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101466859B1 (en) * 2012-03-07 2014-12-03 이근식 A large block soundproof plate
KR101441809B1 (en) * 2013-06-10 2014-12-11 김보경 A tunnel type soundproofing walls
KR101473997B1 (en) * 2013-06-07 2015-02-16 도아기업주식회사 A tunnel type soundproofing walls
KR101914092B1 (en) * 2018-04-04 2018-11-01 솔로몬산업 주식회사 Fixing equipments for soundproof panel of noise barrier tunnel
KR101916003B1 (en) * 2018-04-04 2018-11-07 솔로몬산업 주식회사 Fixing equipments for soundproof panel of noise barrier tunnel
KR20190101029A (en) * 2018-02-22 2019-08-30 신영기술개발(주) Solar panel construction structure for sound proof tunnel and construction method
CN110241748A (en) * 2019-06-21 2019-09-17 山西尚风科技股份有限公司 A kind of totally-enclosed sound barrier can intelligent opening method
KR20200034495A (en) * 2018-09-21 2020-03-31 봉용범 Frame for supporting sound-absorbing panel with adjustable distance

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100654281B1 (en) * 2004-09-01 2006-12-08 명성산업개발 주식회사 Soundproof member
JP2007146640A (en) * 2005-11-07 2007-06-14 Nippon Steel & Sumikin Metal Products Co Ltd Sound insulation wall
KR100861265B1 (en) * 2008-04-04 2008-10-01 주식회사 다롬 Soundproofing walls

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100654281B1 (en) * 2004-09-01 2006-12-08 명성산업개발 주식회사 Soundproof member
JP2007146640A (en) * 2005-11-07 2007-06-14 Nippon Steel & Sumikin Metal Products Co Ltd Sound insulation wall
KR100861265B1 (en) * 2008-04-04 2008-10-01 주식회사 다롬 Soundproofing walls

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101466859B1 (en) * 2012-03-07 2014-12-03 이근식 A large block soundproof plate
KR101473997B1 (en) * 2013-06-07 2015-02-16 도아기업주식회사 A tunnel type soundproofing walls
KR101441809B1 (en) * 2013-06-10 2014-12-11 김보경 A tunnel type soundproofing walls
KR20190101029A (en) * 2018-02-22 2019-08-30 신영기술개발(주) Solar panel construction structure for sound proof tunnel and construction method
KR102071306B1 (en) * 2018-02-22 2020-01-30 신영기술개발(주) Solar panel construction structure for sound proof tunnel and construction method
KR101914092B1 (en) * 2018-04-04 2018-11-01 솔로몬산업 주식회사 Fixing equipments for soundproof panel of noise barrier tunnel
KR101916003B1 (en) * 2018-04-04 2018-11-07 솔로몬산업 주식회사 Fixing equipments for soundproof panel of noise barrier tunnel
KR20200034495A (en) * 2018-09-21 2020-03-31 봉용범 Frame for supporting sound-absorbing panel with adjustable distance
KR102147395B1 (en) * 2018-09-21 2020-08-24 봉용범 Frame for supporting sound-absorbing panel with adjustable distance
CN110241748A (en) * 2019-06-21 2019-09-17 山西尚风科技股份有限公司 A kind of totally-enclosed sound barrier can intelligent opening method
CN110241748B (en) * 2019-06-21 2021-03-30 山西尚风科技股份有限公司 Method for intelligently opening fully-closed sound barrier

Similar Documents

Publication Publication Date Title
KR101034007B1 (en) A soundproof tunnel and a method for installing the same
KR101185974B1 (en) Reinforcing apparatus for panel-zone of beam and column member using bracing member and structure reinforcing method therewith
JP2015098683A (en) Temporary frame and construction method for structure
KR101489848B1 (en) Structure for seismic-proofing opening parts by pretensioning to steel frame using wire rope, and construction method for the same
KR101473997B1 (en) A tunnel type soundproofing walls
JP2016023476A (en) Concrete mold for aseismic and vibration control reinforcement of concrete structure, and aseismic and vibration control reinforcement method for concrete structure using the same
JPH10227122A (en) Attaching construction for scaffolding doubling as sound-absorbing member for viaduct
KR101876511B1 (en) Window seismic system using Steel Frame with Slit
JP2014111864A (en) Beam reinforcing member and installation structure of stud in existing building
JP4310812B1 (en) Protective fence reinforcement method
JP2007170044A (en) Steel floor slab reinforcing structure and existing steel floor slab reinforcing method
KR100648046B1 (en) Beam and Girder Reinforcing Apparatus using External Post-Tension and Reinforcing Method using the same
JP6130678B2 (en) Reinforcement method
KR20220090968A (en) Multifunctional curtain wall system
JP3807695B2 (en) Damping structure of reinforced concrete building and its construction method
KR20100119950A (en) Seismic reinforcement device, structure and method of existing column
JP6293207B2 (en) Installation structure of studs in existing building
JP3193860U (en) Lightweight steel roof structure with wire mesh net for scaffolding
JP2004003186A (en) Building structure with track guide disposed therein
JPH0542553B2 (en)
KR102657703B1 (en) safety canopy structure of temporary soundproofing wall
JP7137915B2 (en) Roof repair method for existing buildings
JP2001012092A (en) Garage deck
JP3829458B2 (en) Attaching the vibration control device to the building
JP4072274B2 (en) Building unit

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20140218

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20150224

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20160211

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20180316

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20190314

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20200226

Year of fee payment: 10