KR101031053B1 - The movable equipment for the re-construction of damage part in paved road - Google Patents

The movable equipment for the re-construction of damage part in paved road Download PDF

Info

Publication number
KR101031053B1
KR101031053B1 KR1020080037713A KR20080037713A KR101031053B1 KR 101031053 B1 KR101031053 B1 KR 101031053B1 KR 1020080037713 A KR1020080037713 A KR 1020080037713A KR 20080037713 A KR20080037713 A KR 20080037713A KR 101031053 B1 KR101031053 B1 KR 101031053B1
Authority
KR
South Korea
Prior art keywords
pavement
road
damaged
vehicle
cylindrical body
Prior art date
Application number
KR1020080037713A
Other languages
Korean (ko)
Other versions
KR20090112040A (en
Inventor
허명선
안세천
정동진
전용덕
이승택
Original Assignee
(주)화인코왁
서울특별시시설관리공단
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)화인코왁, 서울특별시시설관리공단 filed Critical (주)화인코왁
Priority to KR1020080037713A priority Critical patent/KR101031053B1/en
Publication of KR20090112040A publication Critical patent/KR20090112040A/en
Application granted granted Critical
Publication of KR101031053B1 publication Critical patent/KR101031053B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C23/00Auxiliary devices or arrangements for constructing, repairing, reconditioning, or taking-up road or like surfaces
    • E01C23/06Devices or arrangements for working the finished surface; Devices for repairing or reconditioning the surface of damaged paving; Recycling in place or on the road
    • E01C23/12Devices or arrangements for working the finished surface; Devices for repairing or reconditioning the surface of damaged paving; Recycling in place or on the road for taking-up, tearing-up, or full-depth breaking-up paving, e.g. sett extractor
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C23/00Auxiliary devices or arrangements for constructing, repairing, reconditioning, or taking-up road or like surfaces
    • E01C23/06Devices or arrangements for working the finished surface; Devices for repairing or reconditioning the surface of damaged paving; Recycling in place or on the road
    • E01C23/09Devices or arrangements for working the finished surface; Devices for repairing or reconditioning the surface of damaged paving; Recycling in place or on the road for forming cuts, grooves, or recesses, e.g. for making joints or channels for markings, for cutting-out sections to be removed; for cleaning, treating, or filling cuts, grooves, recesses, or fissures; for trimming paving edges
    • E01C23/0966Devices or arrangements for working the finished surface; Devices for repairing or reconditioning the surface of damaged paving; Recycling in place or on the road for forming cuts, grooves, or recesses, e.g. for making joints or channels for markings, for cutting-out sections to be removed; for cleaning, treating, or filling cuts, grooves, recesses, or fissures; for trimming paving edges for filling or priming, with or without working the surface of the filling or applying particulate material thereto, e.g. for filling the joints of stone-sett paving

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Repair (AREA)
  • Road Paving Machines (AREA)

Abstract

본 발명은 이동식 포장 도로 훼손 부분 재시공 장치에 관한 것으로, 차체에 장비한 원동기를 동력원으로 하면서 트레일러(120)가 연결된 차량(100); 상기 차량(100)의 트레일러(120)에 설치하되, 중앙에 나합된 상태로 승강 가능하도록 외부에 나사산이 형성되면서 하부는 도로 포장과 접하여 내부가 밀폐되도록 하는 원통형 몸체(201), 상기 원통형 몸체(201)를 승강시키기 위하여 모터(202) 축상에 연결된 웜기어(203), 지지대(204) 상에 회동 가능하도록 설치된 가열수단(210), 굴삭수단(220) 및 다짐수단(230)을 구비하는 도로 훼손부 시공수단(200); 상기 도로 훼손부 시공수단(200)의 전방에 설치되고, 도로 포장재를 투입하는 도로 포장재 투입수단(300); 및 상기 도로 훼손부 시공수단(200)의 후방에 설치되고, 굴삭된 폐 포장재를 보관하는 보관수단(400);으로 구성됨에 따라, 도로 포장이 훼손된 부분에 도로 훼손부 시공수단(200)이 위치하도록 차량(100)을 이동시킨 다음, 도로 훼손부 시공수단(200)을 하강시켜 훼손된 도로 포장과 접하여 내부가 밀폐되도록 한 후, 가열수단(210)을 이용하여 훼손된 포장의 굴삭이 용이하도록 가열하고, 굴삭수단(220)을 이용하여 굴삭하여 폐 포장재를 보관수단(400)으로 이송한 후, 도로 포장재 투입수단(300)으로부터 도로 포장재를 투입하고 다짐수단(230)으로 마무리 시공이 가능하도록 하여 많은 인력이 필요하지 않으면서도 간단한 방법으로 용이하게 포장 도로의 훼손 부분을 재시공할 수 있는 효과를 얻을 수 있다.

Figure R1020080037713

이동식, 포장 도로, 훼손 부분, 재시공 장치

The present invention relates to a mobile pavement damaged part reconstruction device, comprising: a vehicle (100) connected to a trailer (120) while a prime mover equipped with a vehicle body as a power source; It is installed in the trailer 120 of the vehicle 100, but the screw thread is formed on the outside to be ascended in the center in the center, the lower portion is in contact with the road pavement cylindrical body 201, the cylindrical body ( Road damage provided with a worm gear 203 connected to the shaft of the motor 202, a heating means 210, a digging means 220, and a compaction means 230, which are rotatably mounted on the support 204, to lift the 201. Secondary construction means (200); Road pavement inserting means (300) installed in front of the road damage construction means (200), and for injecting pavement; And a storage means 400 installed at the rear of the road damage construction means 200 and storing the excavated waste pavement material. As a result, the road damage construction means 200 is located at a portion of the road pavement damaged. After moving the vehicle 100 so as to lower the road damage construction means 200 to contact the damaged road pavement to seal the inside, using the heating means 210 is heated to facilitate the excavation of the damaged pavement After excavation using the excavation means 220, the waste pavement is transferred to the storage means 400, and then the road pavement is introduced from the road pavement input means 300, and the finishing work can be completed by the compaction means 230. It is possible to easily reconstruct damaged parts of the pavement in a simple way without requiring manpower.

Figure R1020080037713

Removable, Pavement, Damaged, Rebuilt Device

Description

이동식 포장 도로 훼손 부분 재시공 장치{The movable equipment for the re-construction of damage part in paved road}The movable equipment for the re-construction of damage part in paved road}

본 발명은 이동식 포장 도로 훼손 부분 재시공 장치에 관한 것으로, 좀 더 구체적으로는 차체에 장비한 원동기를 동력원으로 하면서 트레일러(120)가 연결된 차량(100); 상기 차량(100)의 트레일러(120)에 설치하되, 중앙에 나합된 상태로 상하 승강 가능하도록 외부에 나사산이 형성되면서 하부는 도로 포장과 접하여 내부가 밀폐되도록 하는 원통형 몸체(201), 상기 원통형 몸체(201)를 승강시키기 위하여 모터(202) 축상에 연결된 웜기어(203), 지지대(204) 상에 회동 가능하도록 설치된 가열수단(210), 굴삭수단(220) 및 다짐수단(230)을 구비하는 도로 훼손부 시공수단(200); 상기 도로 훼손부 시공수단(200)의 전방에 설치되고, 도로 포장재를 투입하는 도로 포장재 투입수단(300); 및 상기 도로 훼손부 시공수단(200)의 후방에 설치되고, 굴삭된 폐 포장재를 보관하는 보관수단(400);으로 구성됨에 따라, 도로 포장이 훼손된 부분에 도로 훼손부 시공수단(200)이 위치하도록 차량(100)을 이동시킨 다음, 도로 훼손부 시공수단(200)을 하강시켜 훼손된 도로 포장과 접하여 내부가 밀폐되도록 한 후, 가열수단(210)을 이용하여 훼손된 포장의 굴삭이 용이하도록 가열하고, 굴삭수단(220)을 이용하여 굴삭하여 폐 포장재를 보관수단(400)으로 이송한 후, 도로 포장재 투입수단(300)으로부터 도로 포장재를 투입하고 다짐수단(230)으로 마무리 시공이 가능하도록 하여 많은 인력이 필요하지 않으면서도 간단한 방법으로 용이하게 포장 도로의 훼손 부분을 재시공할 수 있는 포장 도로의 훼손 부분 재시공 장치에 관한 것이다.The present invention relates to a mobile pavement damaged part reconstruction device, more specifically, the vehicle 100 is connected to the trailer 120 while the prime mover mounted on the vehicle body as a power source; Cylindrical body 201, which is installed on the trailer 120 of the vehicle 100, the lower end is in contact with the road pavement while the thread is formed on the outside to be able to move up and down in the state of the center, the cylindrical body 201, the cylindrical body A road including a worm gear 203 connected to the shaft of the motor 202, a heating means 210, a digging means 220, and a compaction means 230 installed on the support 204 so as to elevate the 201. Damage construction means (200); Road pavement inserting means (300) installed in front of the road damage construction means (200), and for injecting pavement; And a storage means 400 installed at the rear of the road damage construction means 200 and storing the excavated waste pavement material. As a result, the road damage construction means 200 is located at a portion of the road pavement damaged. After moving the vehicle 100 so as to lower the road damage construction means 200 to contact the damaged road pavement to seal the inside, using the heating means 210 is heated to facilitate the excavation of the damaged pavement After excavation using the excavation means 220, the waste pavement is transferred to the storage means 400, and then the road pavement is introduced from the road pavement input means 300, and the finishing work can be completed by the compaction means 230. The present invention relates to an apparatus for reconstructing a damaged part of a pavement that can be easily rebuilt in a simple way without requiring a manpower.

일반적으로 도로의 포장은 도로면을 보호 및 강화하고 평탄성을 높여 사람의 통행과 차량의 주행을 편리하게 하기 위하여 처리된 노면구조물로서, 여러 층으로 이루어진 층구조이며, 각 층은 각각의 역할을 분담하게 된다.In general, the pavement of the road is a road structure that is processed to protect and strengthen the road surface and to improve the flatness and to facilitate the passage of people and the driving of the vehicle. It is a multi-layered layer structure, and each layer shares its role. Done.

도로의 포장은 표층부의 재질에 따라 역청계(아스팔트) 포장, 콘크리트계 포장 및 블록 포장의 세 가지로 크게 분류된다. 상기 역청계 포장은 표층부가 아스팔트 또는 타르에 의해 고결된 쇄석 등의 골재로 된 것으로서, 아스팔트 포장, 타르 포장 등으로 불리고 있다. 상기 역청계 포장은 현재 세계 각국의 도로 중 대부분을 차지하고 있으며 그 종류도 대단히 많다.Road pavement is classified into three categories according to the surface material: bitumen pavement, concrete pavement, and block pavement. The bitumen pavement is made of aggregate such as crushed stone, which is surface layer portion solidified by asphalt or tar, and is called as asphalt pavement, tar pavement, or the like. The bitumen pavement currently occupies most of the roads around the world, and there are many kinds.

그러나 역청계 포장 도로는 강우시 우수의 침투, 지하수의 이동, 특정 부분에 대한 투과수의 과다 유출로 인하여 불규칙한 침하가 발생하거나 부분 유실이 일어나면서 표층의 균열이나 손상 및 침하로 이어져 도로 포장의 훼손을 초래하게 된다.However, bitumen-based pavement is damaged by pavement, damage, and subsidence due to irregular settlement or partial loss due to rainwater infiltration, groundwater movement, and excessive outflow of permeate to certain areas. Will result.

또한, 역청계 포장 도로는 기온차이에 의하여 도로 포장이 수축과 팽창을 반복하면서 균열이 발생하는데 이와 같은 균열 발생이 심해지면서 도로 포장이 훼손될 수 있고, 과적 차량 또는 차량 통행량의 과다로 인하여 도로 포장에 과도한 하중이 작용하여 훼손될 수 있으며, 도로 포장에 이물질이 놓인 상태에서 차량이 이를 통과할 때 일시적으로 도로 포장에 과도한 하중이 작용하여 훼손될 수 있다.In addition, in the case of bitumen-based pavement, cracks occur while the pavement is repeatedly contracted and expanded due to the temperature difference, and the pavement may be damaged due to such crack occurrence, and the pavement may be caused by excessive traffic or excessive traffic volume. Excessive load on the road pavement may be damaged, and when the vehicle passes through it while foreign matter is placed on the pavement, excessive load may be temporarily damaged on the pavement.

도로 포장의 훼손은 차량을 손상시킬 뿐만 아니라 교통사고의 주요한 원인으로도 작용하기 때문에 훼손된 부분만이라도 재시공해야 하고, 도로 포장의 훼손이 과도하면 전면적인 재시공도 불가피하다.Damage to the pavement not only damages the vehicle, but also acts as a major cause of traffic accidents, so only the damaged parts must be rebuilt. If the pavement is excessively damaged, full reconstruction is inevitable.

도로 포장의 훼손된 부분을 부분적으로 재시공하는 종래 방법은 훼손된 부분의 표면을 절단하거나 훼손된 부분의 다수 지점을 천공한 다음, 훼손된 부분을 포함한 절단부 또는 천공부를 굴삭한 후, 굴삭된 바닥을 다지고, 도로 포장 시공법에 따라 자갈, 쇄석 등의 골재, 모래 등을 투입하여 다진 후, 역청계 포장재를 투입하고 다져서 완료한다.The conventional method of partially reconstructing a damaged part of a road pavement cuts the surface of the damaged part or drills a plurality of points of the damaged part, and then excavates a cut or perforated part including the damaged part, and then compacts the excavated floor, According to the paving method, aggregates such as gravel, crushed stone, sand, etc. are added and chopped.

그러나 종래 포장 도로 훼손 부분 재시공 방법에 의하면 많은 인력이 소요될 뿐만 아니라 도로 포장의 절단수단, 천공 수단, 굴삭기, 다짐기 등과 같은 장치를 필요로 하고, 많은 시간이 소요되는 등의 단점이 있었다.However, the conventional pavement damaged part reconstruction method requires not only a lot of manpower, but also requires a device such as cutting means, drilling means, excavators, compactors, etc., and takes a lot of time.

따라서, 본 발명의 목적은 많은 인력과 시간이 필요하지 않고, 여러 가지의 장비가 필요하지 않으면서도 간단한 방법으로 용이하게 포장 도로의 훼손 부분을 재시공할 수 있는 이동식 포장 도로 훼손 부분 재시공 장치를 제공하는 데 있다.Accordingly, an object of the present invention is to provide a mobile pavement damaged part reconstruction device that does not require a lot of manpower and time, and can easily reconstruct a damaged part of the pavement in a simple manner without the need for a variety of equipment There is.

삭제delete

상기 목적들뿐만 아니라 용이하게 표출되는 다른 목적들을 달성하기 위하여 본 발명에서는 차체에 장비한 원동기를 동력원으로 하면서 트레일러(120)가 연결된 차량(100); 상기 차량(100)의 트레일러(120)에 설치하되, 중앙에 나합된 상태로 상하 승강 가능하도록 외부에 나사산이 형성되면서 하부는 도로 포장과 접하여 내부가 밀폐되도록 하는 원통형 몸체(201), 상기 원통형 몸체(201)를 승강시키기 위하여 모터(202) 축상에 연결된 웜기어(203), 지지대(204) 상에 회동 가능하도록 설치된 가열수단(210), 굴삭수단(220) 및 다짐수단(230)을 구비하는 도로 훼손부 시공수단(200); 상기 도로 훼손부 시공수단(200)의 전방에 설치되고, 도로 포장재를 투입하는 도로 포장재 투입수단(300); 및 상기 도로 훼손부 시공수단(200)의 후방에 설치되고, 굴삭된 폐 포장재를 보관하는 보관수단(400);으로 구성됨에 따라, 도로 포장이 훼손된 부분에 도로 훼손부 시공수단(200)이 위치하도록 차량(100)을 이동시킨 다음, 도로 훼손부 시공수단(200)을 하강시켜 훼손된 도로 포장과 접하여 내부가 밀폐되도록 한 후, 가열수단(210)을 이용하여 훼손된 포장의 굴삭이 용이하도록 가열하고, 굴삭수단(220)을 이용하여 굴삭하여 폐 포장재를 보관수단(400)으로 이송한 후, 도로 포장재 투입수단(300)으로부터 도로 포장재를 투입하고 다짐수단(230)으로 마무리 시공이 가능하도록 하여 많은 인력이 필요하지 않으면서도 간단한 방법으로 용이하게 포장 도로의 훼손 부분을 재시공할 수 있다.In order to achieve the above objects as well as other objects that can be easily expressed in the present invention, the vehicle 100 is connected to the trailer 120 while the prime mover equipped with the vehicle body as a power source; Cylindrical body 201, which is installed on the trailer 120 of the vehicle 100, the lower end is in contact with the road pavement while the thread is formed on the outside to be able to move up and down in the state of the center, the cylindrical body 201, the cylindrical body A road including a worm gear 203 connected to the shaft of the motor 202, a heating means 210, a digging means 220, and a compaction means 230 installed on the support 204 so as to elevate the 201. Damage construction means (200); Road pavement inserting means (300) installed in front of the road damage construction means (200), and for injecting pavement; And a storage means 400 installed at the rear of the road damage construction means 200 and storing the excavated waste pavement material. As a result, the road damage construction means 200 is located at a portion of the road pavement damaged. After moving the vehicle 100 so as to lower the road damage construction means 200 to contact the damaged road pavement to seal the inside, using the heating means 210 is heated to facilitate the excavation of the damaged pavement After excavation using the excavation means 220, the waste pavement is transferred to the storage means 400, and then the road pavement is introduced from the road pavement input means 300, and the finishing work can be completed by the compaction means 230. You can easily rebuild damaged sections of the pavement in a simple way without the need for manpower.

본 발명에 따른 이동식 포장 도로 훼손 부분 재시공 장치는 많은 인력과 시간이 필요하지 않고, 여러 가지의 장비가 필요하지 않으면서도 간단한 방법으로 용이하게 포장 도로의 훼손 부분을 재시공할 수 있는 효과를 얻을 수 있었다.The mobile pavement damaged part reconstruction device according to the present invention does not require a lot of manpower and time, and can be easily reconstructed the damaged part of the pavement in a simple way without the need for various equipment .

본 발명을 첨부 도면에 의거하여 좀 더 구체적으로 설명하면 다음과 같다.Hereinafter, the present invention will be described in more detail with reference to the accompanying drawings.

도 1은 본 발명에 따른 이동식 포장 도로 훼손 부분 재시공 장치의 개략적인 사시도이고, 도 2는 본 발명에 따른 이동식 포장 도로 훼손 부분 재시공 장치의 개략적인 측면도이며, 도 3은 굴삭수단(220)의 개략적인 작동상태를 나타내는 도면이다.1 is a schematic perspective view of a mobile pavement damaged part reconstruction device according to the present invention, Figure 2 is a schematic side view of a mobile pavement damaged part reconstruction device according to the invention, Figure 3 is a schematic view of an excavation means 220 It is a figure which shows the operating state.

본 발명에 따른 이동식 포장 도로 훼손 부분 재시공 장치는 차체에 장비한 원동기를 동력원으로 하면서 트레일러(120)가 연결된 차량(100); 상기 차량(100)의 트레일러(120)에 설치하되, 중앙에 나합된 상태로 상하 승강 가능하도록 외부에 나사산이 형성되면서 하부는 도로 포장과 접하여 내부가 밀폐되도록 하는 원통형 몸체(201), 상기 원통형 몸체(201)를 승강시키기 위하여 모터(202) 축상에 연결된 웜기어(203), 지지대(204) 상에 회동 가능하도록 설치된 가열수단(210), 굴삭수단(220) 및 다짐수단(230)을 구비하는 도로 훼손부 시공수단(200); 상기 도로 훼손부 시공수단(200)의 전방에 설치되고, 도로 포장재를 투입하는 도로 포장재 투입수단(300); 및 상기 도로 훼손부 시공수단(200)의 후방에 설치되고, 굴삭된 폐 포장재를 보관하는 보관수단(400);으로 구성되는 것이 특징이다.The mobile pavement damaged part reconstruction device according to the present invention includes a vehicle 100 to which a trailer 120 is connected while a prime mover equipped with a vehicle body is a power source; Cylindrical body 201, which is installed on the trailer 120 of the vehicle 100, the lower end is in contact with the road pavement while the thread is formed on the outside to be able to move up and down in the state of the center, the cylindrical body 201, the cylindrical body A road including a worm gear 203 connected to the shaft of the motor 202, a heating means 210, a digging means 220, and a compaction means 230 installed on the support 204 so as to elevate the 201. Damage construction means (200); Road pavement inserting means (300) installed in front of the road damage construction means (200), and for injecting pavement; And a storage means 400 installed at the rear of the road damage construction means 200 and storing the excavated waste pavement material.

삭제delete

삭제delete

삭제delete

도 1 내지 도 3에 도시된 이동식 포장 도로 훼손 부분 재시공 장치에서 사용되는 차량(100)은 차체에 장비한 원동기를 동력원으로 하는 공지의 세미 트레일러 차량을 사용하는 것이 바람직하며, 지지력과 견인력을 갖는 트랙터(110)와 트레일러(120)가 연결기(130)에 의하여 연결 구성됨으로써, 트레일러(120)와 트렉터(110)의 상대운동, 연결 및 분리가 수월하도록 하는 것이 효과적이다.As the vehicle 100 used in the mobile pavement damaged part reconstruction device shown in Figs. 1 to 3, it is preferable to use a known semi-trailer vehicle using a prime mover equipped with a vehicle body, and a tractor having a supporting force and a traction force. Since the 110 and the trailer 120 are configured to be connected by the connector 130, it is effective to facilitate the relative movement, connection and separation of the trailer 120 and the tractor 110.

특히, 트레일러(120)상에 구비되는 장비들 즉, 도로 훼손부 시공수단(200), 도로 포장재를 투입하는 도로 포장재 투입수단(300) 및 굴삭된 폐 포장재를 보관하는 보관수단(400)의 동력은 트렉터(110)의 동력을 이용한다.In particular, the power of the equipment provided on the trailer 120, that is, road damage construction means 200, road pavement input means 300 for injecting the road paving material and storage means 400 for storing the excavated waste pavement Uses the power of the tractor 110.

상기 도로 훼손부 시공수단(200)은 차량(100)의 트레일러(120)에 설치하되, 중앙에 상하로 승강이 가능하고 하부가 도로 포장의 표면과 접하여 내부가 밀폐되도록 하면서 가열수단(210), 굴삭수단(220) 및 다짐수단(230)이 구비된다.The road damage construction means 200 is installed on the trailer 120 of the vehicle 100, and can be elevated up and down in the center and heating means 210, while excavating the lower portion in contact with the surface of the road pavement Means 220 and compaction means 230 are provided.

즉, 도로 훼손부 시공수단(200)은 트레일러(130)에 나합되도록 외부에 나사산이 형성된 원통형의 몸체(201), 몸체(201)를 승강시키기 위하여 모터(202) 축상에 연결된 웜기어(203), 지지대(204) 상에 회동 가능하게 설치된 가열수단(210), 굴삭수단(220) 및 다짐수단(230)이 구비된다.That is, the road damage construction unit 200 is a cylindrical body 201 having a screw thread formed to the outside of the trailer 130, the worm gear 203 connected to the motor 202 shaft to lift the body 201, The heating means 210, the excavating means 220, and the compacting means 230 are rotatably installed on the support 204.

상기 몸체(201)의 하단부는 도로 포장에 접한 상태에서 하강하여 상기 도로 포장을 절단 가능하도록 날을 형성하는 것이 바람직하다. 상기 몸체(201)를 승강시키는 수단은 모터(202)와 웜기어(203)로 구성되는 수단 이외에 본 발명이 속하는 기술 분야에서 통상적으로 사용되는 승강 수단을 적용할 수 있다.The lower end of the body 201 is preferably lowered in contact with the road pavement to form a blade to cut the road pavement. The means for elevating the body 201 may be applied to elevating means commonly used in the art to which the present invention pertains, in addition to the means consisting of the motor 202 and the worm gear 203.

또한, 상기 가열수단(210)은 원판형으로 형성되어 몸체(201) 내부로 승강 가능하도록 구성되면서 적외선, 고주파 또는 전자기파를 이용한 가열장치가 구비된다. 상기 굴삭수단(220)은 중심에 모터(221)가 장착되고, 상기 모터의 축과 연결된 굴삭익(222)이 구비되며, 상기 굴삭익(222)은 접철 가능하도록 끝부분이 호형으로 형성되고, 상기 굴삭익(222)을 접철하기 위한 접철 장치가 상기 지지대(204)에 구비된다. 상기 다짐수단(230)은 자유 낙하에 의해 하강하면서 자체 중량으로 다짐이 가능하도록 형성되고, 유압실린더(231)에 의해 상승한다.In addition, the heating means 210 is formed in a disc shape and configured to be elevated in the body 201 is provided with a heating device using infrared, high frequency or electromagnetic waves. The excavating means 220 is a motor 221 is mounted at the center, the excavating blade 222 is connected to the shaft of the motor, the excavating blade 222 is formed in an arc shape so that the end is foldable, A folding device for folding the excavator blades 222 is provided in the support 204. The compaction means 230 is formed to be compacted by its own weight while descending by free fall, and is raised by the hydraulic cylinder 231.

한편, 상기 도로 훼손부 시공수단(200)의 전,후에는 도로 포장재를 투입하는 도로 포장재 투입수단(300)과 굴삭된 폐 포장재를 보관하는 보관수단(400)이 구비된다. 상기 도로 포장재 투입수단(300)은 도로 포장재의 투입이 용이하도록 하부가 경사지게 구성되어 있고, 종류가 다른 포장재를 분리하여 보관할 수 있도록 구획되어 있다.On the other hand, before and after the road damage construction means 200 is provided with a road pavement inserting means 300 for injecting road pavement and storage means 400 for storing the excavated waste pavement. The road pavement inserting means 300 is configured to be inclined at a lower portion so as to easily insert road pavement, and is partitioned to separate and store pavement having different types.

상기와 같이 구성되는 본 발명의 이동식 포장 도로 훼손 부분 재시공 장치를 이용한 재시공 방법을 설명하면 다음과 같다.Referring to the reconstruction method using a mobile pavement damaged part reconstruction device of the present invention configured as described above are as follows.

먼저, 차량(100)을 이동시켜 도로 훼손부 시공수단(200)이 도로 포장의 훼손된 부분에 위치하도록 한 다음, 몸체(201)를 하강시키고, 가열수단(210)을 몸체(201) 내부로 하강시키되, 도로 포장과 일정한 간격을 두도록 하강시킨 후에 가열하여 몸체(201) 내부의 도로 포장을 용이하게 굴삭하도록 한다. 이때 가열수단(210)에 의하여 도로 포장을 가열함으로써, 몸체(201)를 더욱 하강시켜 역청계 재질의 포장 표층이 절단되도록 한다.First, by moving the vehicle 100 so that the road damage construction unit 200 is located in the damaged portion of the road pavement, the body 201 is lowered, the heating means 210 is lowered into the body 201 However, after descending so as to have a predetermined distance from the pavement to heat it to easily excavate the pavement inside the body 201. At this time, by heating the pavement by the heating means 210, the body 201 is further lowered so that the pavement surface layer of bitumen material is cut.

도로 포장의 표층이 절단되고, 그 내부에 역청계 재질의 포장이 녹은 상태에서 가열수단(210)을 상승시키고 회동시킨 다음, 굴삭수단(220)을 몸체(201) 중앙으로 회동하여 하강시키고, 모터(201)의 회전력을 이용하여 굴삭익(222)을 회전시킴으로써 도로 포장의 훼손 부분을 파낸 후, 굴삭익(222)을 접철하여 파내진 폐 도로 포장재를 모은 다음, 굴삭수단(220)을 상승시키고 폐 포장재를 보관하는 보관수단(400)의 상부로 회동시키고 접철된 굴삭익(222)을 펴서 파내진 폐 도로 포장재를 보관수단(400)으로 이송한다.The surface layer of the road pavement is cut, the heating means 210 is raised and rotated in a state where the pavement material is melted therein, and the excavating means 220 is rotated to the center of the body 201 and lowered, and the motor After digging out the damaged part of the road pavement by rotating the excavator blades 222 using the rotational force of 201, folding the excavator pavement 222, collecting the excavated road pavement material, and then raising the excavator means 220. It rotates to the upper portion of the storage means 400 for storing the waste pavement and stretches the folded excavation blade 222 to transfer the excavated waste road pavement to the storage means 400.

상기와 같은 공정을 반복하여 도로 포장의 훼손된 부분을 파낸 후, 파낸 깊이에 따라 골재, 모래 또는 포장재를 도로 포장재 투입수단(300)으로부터 투입한 다음, 다짐수단(230)을 몸체(201) 중앙으로 회동시키고 자유 낙하시켜 포장재들이 다져지도록 한다.After digging out the damaged part of the road pavement by repeating the above process, injecting aggregate, sand or pavement from the road pavement inserting means 300 according to the excavation depth, and then the compaction means 230 to the center of the body 201 Rotate and free fall to allow packing material to chop.

삭제delete

삭제delete

삭제delete

삭제delete

삭제delete

상기와 같은 방법에 의하여 도로의 훼손된 부분을 용이하게 재시공할 수 있게 된다.By the above method, it is possible to easily reconstruct the damaged part of the road.

삭제delete

도 1은 본 발명에 따른 이동식 포장 도로 훼손 부분 재시공 장치의 개략적인 사시도이고,1 is a schematic perspective view of a mobile pavement damaged part reconstruction device according to the present invention,

도 2는 본 발명에 따른 이동식 포장 도로 훼손 부분 재시공 장치의 개략적인 측면도이며,2 is a schematic side view of a mobile pavement damaged part reconstruction device according to the present invention,

도 3은 굴삭수단(220)의 개략적인 작동상태를 나타내는 도면이다.3 is a view showing a schematic operating state of the excavating means 220.

삭제delete

삭제delete

삭제delete

* 도면의 주요 부분에 대한 부호의 설명* Explanation of symbols for the main parts of the drawings

100. 차량 200. 도로 훼손부 시공수단100. Vehicle 200. Road damage construction means

210. 가열수단 220. 굴삭수단210. Heating means 220. Excavating means

230. 다짐수단 240. 정리수단230. Compaction means 240. Arrangement means

300. 포장재 투입수단 400. 보관수단300. Packing material input means 400. Storage means

Claims (6)

차체에 장비한 원동기를 동력원으로 하면서 트레일러(120)가 연결된 차량(100);A vehicle 100 to which the trailer 120 is connected while the prime mover mounted on the vehicle body is a power source; 상기 차량(100)의 트레일러(120)에 설치하되, 중앙에 나합된 상태로 승강 가능하도록 외부에 나사산이 형성되면서 하부는 도로 포장과 접하여 내부가 밀폐되도록 하는 원통형 몸체(201), 상기 원통형 몸체(201)를 승강시키기 위하여 모터(202) 축상에 연결된 웜기어(203), 지지대(204) 상에 회동 가능하도록 설치된 가열수단(210), 굴삭수단(220) 및 다짐수단(230)을 구비하는 도로 훼손부 시공수단(200);It is installed in the trailer 120 of the vehicle 100, but the screw thread is formed on the outside to be ascended in the center in the center, the lower portion is in contact with the road pavement cylindrical body 201, the cylindrical body ( Road damage provided with a worm gear 203 connected to the shaft of the motor 202, a heating means 210, a digging means 220, and a compaction means 230, which are rotatably mounted on the support 204, to lift the 201. Secondary construction means (200); 상기 도로 훼손부 시공수단(200)의 전방에 설치되고, 도로 포장재를 투입하는 도로 포장재 투입수단(300); 및Road pavement inserting means (300) installed in front of the road damage construction means (200), and for injecting pavement; And 상기 도로 훼손부 시공수단(200)의 후방에 설치되고, 굴삭된 폐 포장재를 보관하는 보관수단(400);으로 구성되는 것을 특징으로 하는 이동식 포장 도로 훼손 부분 재시공 장치.Removable pavement damaged part reconstruction device, characterized in that consisting of ;; is installed at the rear of the road damage construction means 200, the storage means for storing the excavated waste pavement (400). 삭제delete 청구항 1에 있어서, 상기 원통형 몸체(201)의 하단부는 도로 포장에 접한 상태에서 하강하여 상기 도로 포장을 절단 가능하도록 날이 형성된 것을 특징으로 하는 이동식 포장 도로 훼손 부분 재시공 장치.The method of claim 1, wherein the lower end of the cylindrical body (201) is moved down the state in contact with the pavement, the mobile pavement damaged part reconstruction device, characterized in that the blade is formed to be able to cut the road pavement. 청구항 1에 있어서, 상기 가열수단(210)은 원판형으로 형성되어 원통형 몸체(201) 내부로 승강 가능하도록 구성되면서 고주파 또는 전자기파를 이용한 가열장치가 구비되고,The method according to claim 1, wherein the heating means 210 is formed in a disc shape and configured to be elevated in the cylindrical body 201 is provided with a heating device using high frequency or electromagnetic waves, 상기 굴삭수단(220)은 중심에 모터(221)가 장착되고, 상기 모터의 축과 연결된 굴삭익(222)이 구비되어 상기 원통형 몸체(201) 내부로 승강 가능하도록 하되, 상기 굴삭익(222)은 접철 가능하도록 끝부분이 호형으로 형성되며, 상기 굴삭익(222)을 접철하기 위한 접철 장치가 상기 지지대(204)에 구비되고,The excavating means 220 is equipped with a motor 221 at the center, the excavating blade 222 connected to the shaft of the motor is provided to enable the lifting into the cylindrical body 201, the excavating blade 222 The end portion is formed in an arc shape so as to be foldable, a folding device for folding the excavator blades 222 is provided in the support 204, 상기 다짐수단(230)은 자유 낙하에 의해 몸체(201) 내부로 하강하면서 자체 중량으로 다짐이 가능하도록 하고, 유압실린더(231)에 의해 상승하도록 형성된 것을 특징으로 하는 이동식 포장 도로 훼손 부분 재시공 장치.The compaction means 230 is a pavement damage reconstruction device, characterized in that it is formed to be lowered into the body 201 by the free fall, while being compacted by its own weight, by the hydraulic cylinder (231). 삭제delete 삭제delete
KR1020080037713A 2008-04-23 2008-04-23 The movable equipment for the re-construction of damage part in paved road KR101031053B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020080037713A KR101031053B1 (en) 2008-04-23 2008-04-23 The movable equipment for the re-construction of damage part in paved road

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020080037713A KR101031053B1 (en) 2008-04-23 2008-04-23 The movable equipment for the re-construction of damage part in paved road

Publications (2)

Publication Number Publication Date
KR20090112040A KR20090112040A (en) 2009-10-28
KR101031053B1 true KR101031053B1 (en) 2011-04-25

Family

ID=41553274

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020080037713A KR101031053B1 (en) 2008-04-23 2008-04-23 The movable equipment for the re-construction of damage part in paved road

Country Status (1)

Country Link
KR (1) KR101031053B1 (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101254955B1 (en) * 2013-02-07 2013-04-16 (주)한동알앤씨 Asphalt pavement crack repairing equipment mounted truck using infrared heating apparatus in field
KR101254956B1 (en) * 2013-02-07 2013-04-16 (주)한동알앤씨 Construction method using asphalt pavement crack repair equipment with infrared heating apparatus in field
CN104947575B (en) * 2015-07-24 2017-05-31 黄河养护集团有限公司 A kind of high-precision road construction device
CN106012783B (en) * 2016-07-15 2018-02-02 山西省交通科学研究院 A kind of double-layer stress absorption band integrated construction train
CN110616627B (en) * 2019-09-26 2021-08-06 湖南交通职业技术学院 Quick patching device of bituminous paving crack
CN112647397A (en) * 2020-12-17 2021-04-13 王伟华 Asphalt pavement repairing device
CN113585031A (en) * 2021-08-14 2021-11-02 杭州大江东城市设施管养有限公司 Highway maintenance equipment

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06228912A (en) * 1993-02-01 1994-08-16 Mitsubishi Heavy Ind Ltd Asphalt repairing method and repairing machine
KR950014587B1 (en) * 1993-03-15 1995-12-09 서일수 Heating device & repair, re-pavement method of asphalt concrete road
JPH0813414A (en) * 1994-07-04 1996-01-16 Toyo Doro Kogyo Kk Method of repairing asphalt pavement
JPH1018216A (en) 1996-07-04 1998-01-20 Oobayashi Doro Kk Movable asphalt mixer

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06228912A (en) * 1993-02-01 1994-08-16 Mitsubishi Heavy Ind Ltd Asphalt repairing method and repairing machine
KR950014587B1 (en) * 1993-03-15 1995-12-09 서일수 Heating device & repair, re-pavement method of asphalt concrete road
JPH0813414A (en) * 1994-07-04 1996-01-16 Toyo Doro Kogyo Kk Method of repairing asphalt pavement
JPH1018216A (en) 1996-07-04 1998-01-20 Oobayashi Doro Kk Movable asphalt mixer

Also Published As

Publication number Publication date
KR20090112040A (en) 2009-10-28

Similar Documents

Publication Publication Date Title
KR101031053B1 (en) The movable equipment for the re-construction of damage part in paved road
CN110644324A (en) Splicing construction method for reconstructing and expanding new road and old road
CN104343077A (en) Asphalt concrete pavement reflection crack treatment method
CN101311418A (en) Exchange filling method for deep-foundation pit and large area equipment foundation
CN110924254A (en) Construction process for filling carbonaceous shale roadbed
CN116815733A (en) Construction process for quality control of high-fill roadbed in collapsible loess area
WO2011124887A2 (en) Pot hole repairing machine
CN214271987U (en) Soil-shifting, soil-scattering and soil-pressing integrated device for soil-paving engineering
CN106930327A (en) Well lid construction installation method
CN111535103B (en) Municipal roadbed construction method
CN112627168A (en) High-density polymer grouting reinforcement method for roadbed at sunken part of bridge and culvert butt strap
RU2593669C1 (en) Road machine
CN210238226U (en) Road and bridge road surface construction equipment
CN113914162B (en) Rapid construction method for partial filling of widened roadbed of highway
CN113957874B (en) Construction method for constructing road on soft soil foundation
CN113638299B (en) Construction method for repairing temporary asphalt pavement
FI90107C (en) Method and apparatus for making surface openings
CN211142675U (en) Roadbed structure of expressway filled with muck type construction waste
Raymond et al. Evaluation and suggested improvements to highway edge drains incorporating geotextiles
JPS60261810A (en) Attachment apparatus used through attachment to support vehicle
CN103898824A (en) Method for treating substrate of roadbed with plastic drain boards in high-cold permafrost regions
CN111058346B (en) Carbon rock roadbed structure and construction method thereof
CN113931050B (en) Highway pavement repairing structure and repairing method thereof
RU129512U1 (en) SELF-PROPELLED ROAD-BUILDING UNIT
CN113235714B (en) Gravel blind ditch reverse-filtration geotextile laying method

Legal Events

Date Code Title Description
A201 Request for examination
N231 Notification of change of applicant
E902 Notification of reason for refusal
AMND Amendment
E601 Decision to refuse application
AMND Amendment
J201 Request for trial against refusal decision
B701 Decision to grant
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20140417

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20160411

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20170516

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20180418

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20190416

Year of fee payment: 9