KR100964995B1 - Soil retaining method for two rows pile using raker - Google Patents

Soil retaining method for two rows pile using raker Download PDF

Info

Publication number
KR100964995B1
KR100964995B1 KR1020080016743A KR20080016743A KR100964995B1 KR 100964995 B1 KR100964995 B1 KR 100964995B1 KR 1020080016743 A KR1020080016743 A KR 1020080016743A KR 20080016743 A KR20080016743 A KR 20080016743A KR 100964995 B1 KR100964995 B1 KR 100964995B1
Authority
KR
South Korea
Prior art keywords
row
thumb
pile
lacquer
piles
Prior art date
Application number
KR1020080016743A
Other languages
Korean (ko)
Other versions
KR20090091467A (en
Inventor
손성곤
심재욱
Original Assignee
코오롱건설주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 코오롱건설주식회사 filed Critical 코오롱건설주식회사
Priority to KR1020080016743A priority Critical patent/KR100964995B1/en
Publication of KR20090091467A publication Critical patent/KR20090091467A/en
Application granted granted Critical
Publication of KR100964995B1 publication Critical patent/KR100964995B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2220/00Temporary installations or constructions
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0061Production methods for working underwater
    • E02D2250/0076Drilling
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/30Miscellaneous comprising anchoring details

Abstract

본 발명은, 굴착영역(1)의 경계선을 따라 제1열 엄지말뚝(100)을 근입하는 제1열 엄지말뚝 근입단계; 제1열 엄지말뚝(100)의 외측에 간격을 두고 제2열 엄지말뚝(200)을 근입하는 제2열 엄지말뚝 근입단계; 제1열 엄지말뚝(100) 및 제2열 엄지말뚝(200)이 일체로 거동하도록 연결부재(300)에 의해 상호 연결하는 연결단계; 굴착영역(1)을 굴착하면서, 제1열 엄지말뚝(100)의 사이에 흙막이 부재(10)를 설치하여 흙막이 구조물을 형성하는 흙막이 구조물 형성단계; 흙막이 구조물에 대하여 레이커(400)를 설치하는 레이커 설치단계;를 포함하는 레이커를 이용한 2열 엄지말뚝 흙막이 공법을 제시함으로써, 고심도의 터파기 작업을 수행하는 경우에도 배후토사의 토압에 충분히 저항하도록 하고, 흙막이 구조물의 전체적인 변위의 발생을 억제할 수 있도록 한다.The present invention relates to a method for manufacturing a pneumatic tire, comprising: a first row of thumb piles (100) for fitting a first row of thumb piles (100) along a boundary line of an excavation region (1); A second row of thumb thumb piles adjacent to the second row thumb pile 200 spaced apart from the first row of thumb piles 100; A connecting step in which the first row thumb pile 100 and the second row thumb pile 200 are interconnected by the connecting member 300 so as to integrally move; Forming an earth retaining structure by excavating the excavation region (1) and installing a securing member (10) between the first heat thumb piles (100) to form a securing structure; A two-row thumb pile retention method using a lacquer including a lacquer installation step in which a lacquer (400) is installed on a securing structure is proposed so that even when a severe earthquake is carried out, So that the occurrence of the overall displacement of the retaining structure can be suppressed.

흙막이, 엄지말뚝, 레이커 Retaining wall, Thumb pile, Lakers

Description

레이커를 이용한 2열 엄지말뚝 흙막이 공법{SOIL RETAINING METHOD FOR TWO ROWS PILE USING RAKER}BACKGROUND OF THE INVENTION 1. Field of the Invention [0001] The present invention relates to a two-row pile retention method using a lacquer,

본 발명은 건설 분야에 관한 것으로서, 상세하게는, 배후토사의 토압의 영향을 감소시켜 공기단축 및 공사비 절감효과를 얻을 수 있도록 하는 엄지말뚝 흙막이 공법에 관한 것이다.TECHNICAL FIELD The present invention relates to a construction field, and more particularly, to a thumb pile cladding method for reducing the effect of earth pressure on back soil gravel to reduce air shortening and construction cost.

엄지말뚝 흙막이 공법이란 개착식 흙막이 공법의 일종으로서, 일정간격으로 엄지말뚝(H-Pile)을 항타하거나 천공 후 삽입하는 방식에 의해 근입하고, 터파기를 진행하면서 토류판 등의 흙막이 부재를 엄지말뚝 사이에 끼워 넣어 벽체를 형성하는 공법을 말하며, 엄지말뚝 토류판 공법, 시트파일 공법, SCW, CIP 등이 이에 해당한다.Thumb pile retention is a type of retention type retention method that is applied by a method of hitting a pile (H-Pile) at regular intervals or by inserting it after perforation, and moving the soil retaining member such as soil plate between the thumb piles This is a method of forming a wall by sandwiching, such as a pile piling method, a sheet pile method, SCW, CIP, and the like.

도 1은 종래의 흙막이 공법 중 엄지말뚝 토류판 공법에 의한 흙막이 구조물의 구성을 개략적으로 도시한 구성도이다.FIG. 1 is a schematic view showing the construction of a retaining structure according to a thumb pile erosion preventing method in a conventional retaining method.

이는 상호 홈부가 마주 보도록 수직하게 설치된 복수개의 엄지말뚝(H 빔)(1)과, 상기 홈부에 삽입지지되어 후방의 흙더미 등이 전방을 향하여 무너지는 것을 방지하기 위한 토류판(10)에 의해 구성된다.This is constituted by a plurality of thumb piles (H beams) 1 vertically installed so as to face each other with their mutual grooves facing each other, and a soil plate 10 inserted and supported in the grooves so as to prevent the rear soil from collapsing forward .

토류판(10)으로는 소정 규격의 목재판 또는 강재판이 사용되며, 이를 적층하여 벽체를 형성하고, 그 적층된 토류판을 고정하기 위하여 끼움목(쐐기)을 설치한 구조를 채용하는 것이 일반적이었다.As the current plate 10, a wood plate or a steel plate of a predetermined standard is used, and it is common to employ a structure in which a wall is formed by laminating it and a wedge is provided for fixing the laminated plate.

이와 같은 종래의 엄지말뚝 흙막이 공법은 다음과 같은 점에서 문제로 지적되어 왔다.Such a conventional pile cladding method has been pointed out as a problem in the following points.

첫째, 고심도의 터파기 공사를 수행하는 경우, H 빔만으로는 배후토사의 토압에 저항할 수 없으므로, 이를 보강하기 위하여 많은 수의 지보재(Strut, Earth Anchor, Raker 등)를 사용해야 하는데, 이러한 방식은 비경제적일 뿐만 아니라, 작업공간의 확보를 어렵게 하고, 구조적으로 비효율적이므로 주변지반 침하의 우려가 있다는 점이다.First, in case of severe earthquake construction, H beam alone can not resist the earth pressure of back soil, so a lot of supporting materials (Strut, Earth Anchor, Raker, etc.) should be used to reinforce it. Not only is it not economical, it makes it difficult to secure a work space, and it is structurally inefficient and there is a fear of subsidence in the surrounding ground.

둘째, 종래의 공법에 의한 흙막이 구조물은 강성체로서 토류벽 역할을 할 수는 있으나, 상부두부 변위가 상대적으로 크게 발생하므로 배면부 지반의 이완이 크게 발생한다는 점이다.Second, although the retaining structure of the conventional method can act as a rigid body, it has a relatively large upper head displacement, so that the loosening of the backside ground occurs largely.

본 발명은 상기와 같은 문제점을 해결하기 위하여 안출된 것으로서, 고심도의 터파기 작업을 수행하는 경우에도 배후토사의 토압에 충분히 저항하도록 하고, 흙막이 구조물의 전체적인 변위의 발생을 억제할 수 있도록 하는 2열 엄지말뚝 흙막이 공법을 제시하는 것을 그 목적으로 한다.SUMMARY OF THE INVENTION It is an object of the present invention to solve the above-mentioned problems and to provide a method and a system for securing sufficient resistance to the earth pressure of rear soil, The purpose of this paper is to propose a heat - staking pile cladding method.

본 발명은 상술한 바와 같은 목적을 달성하기 위하여, 굴착영역(1)의 경계선을 따라 제1열 엄지말뚝(100)을 근입하는 제1열 엄지말뚝 근입단계; 상기 제1열 엄지말뚝(100)의 외측에 간격을 두고 제2열 엄지말뚝(200)을 근입하는 제2열 엄지말뚝 근입단계; 상기 제1열 엄지말뚝(100) 및 제2열 엄지말뚝(200)이 일체로 거동하도록 연결부재(300)에 의해 상호 연결하는 연결단계; 상기 굴착영역(1)을 굴착하면서, 상기 제1열 엄지말뚝(100)의 사이에 흙막이 부재(10)를 설치하여 흙막이 구조물을 형성하는 흙막이 구조물 형성단계; 상기 흙막이 구조물에 대하여 레이커(400)를 설치하는 레이커 설치단계;를 포함하는 레이커를 이용한 2열 엄지말뚝 흙막이 공법을 제시한다.In order to accomplish the above-mentioned object, the present invention provides a method for manufacturing a pneumatic tire, comprising: a first heat thumb pile pouring step of moving a first heat thumb pile 100 along a boundary line of an excavation region 1; A second row of thumb thumb piles adjacent to the second row of thumb thumb piles 200 spaced apart from the first row of thumb thumb piles 100; A connecting step of interconnecting the first heat thumb pile 100 and the second heat thumb pile 200 by the connecting member 300 so that the first heat thumb pile 100 and the second heat thumb pile 200 integrally move; Forming an earth retaining structure by excavating the excavation region (1) and installing a securing member (10) between the first heat thumb piles (100) to form a securing structure; And a lacquer installing step of installing a lacquer (400) on the retaining structure. The present invention proposes a two-row thumb pile retention method using a lacquer.

상기 레이커 설치단계는 상기 흙막이 구조물에 대하여 상기 레이커(400)의 상단을 정착하는 레이커 상단 정착단계; 상기 굴착영역(1)의 저면에 레이커 지지부(410)를 형성하는 레이커 지지부 형성단계; 상기 레이커 지지부(410)에 상기 레이커(400)의 하단을 정착하는 레이커 하단 정착단계;를 포함하는 것이 바람직하다.The lacquer installing step may include a rake top fixing step of fixing the upper end of the lacquer 400 to the securing structure; Forming a laker support part (410) on a bottom surface of the excavation area (1); And a lower lacquer fixing step of fixing the lower end of the lacquer 400 to the lacquer supporting part 410.

상기 레이커 상단 정착단계는 상기 제1열 엄지말뚝(100)의 전방에 띠장(420)을 설치하는 띠장 설치단계; 상기 띠장(420)에 대하여 상기 레이커(400)의 상단을 정착하는 단계;를 포함하는 것이 바람직하다.The rake top fixing step may include a wale installation step of installing a wale 420 in front of the first heat thumb pile 100; And fixing the upper end of the laker 400 to the wale 420.

상기 레이커 지지부 형성단계는 지지말뚝(411)을 상하방향으로 근입하는 단계; 상기 레이커(400)의 하단을 지지하도록, 상기 지지말뚝(411)의 상단에 좌우방향으로 지지파일(412)을 설치하는 단계; 상기 지지말뚝(411) 및 지지파일(412)의 주위에 콘크리트를 타설하여 콘크리트 블록(413)을 형성하는 단계;를 포함하는 것이 바람직하다.The forming of the lacquer supporting part comprises: vertically supporting the supporting pile 411; Installing a support pile (412) in a lateral direction on the upper end of the support pile (411) to support the lower end of the laker (400); And forming a concrete block 413 by pouring concrete around the support pile 411 and the support pile 412.

상기 레이커 지지부 형성단계는 상기 지지말뚝(411)의 주위 지반에 강화제를 주입하는 단계를 더 포함하는 것이 바람직하다.The lacquer support forming step may further include injecting a reinforcing agent into the surrounding ground of the support pile 411.

상기 흙막이 구조물 형성단계는 상기 제1열 엄지말뚝(100)과 제2열 엄지말뚝(200)의 사이에 내측을 향하는 경사면(2)이 형성되도록 굴착하는 경사면 형성단계를 더 포함하는 것이 바람직하다.The forming of the retaining structure may further include a step of forming a slope so that an inclined surface 2 facing inward between the first row of thumb piles 100 and the second row of thumb piles 200 is formed.

상기 경사면 형성단계는 상기 제1열 엄지말뚝(100)과 제2열 엄지말뚝(200)의 사이 영역이 안정된 사면을 형성하는 한계 심도(L)까지 내측으로 경사지게 굴착함과 아울러, 상기 굴착영역(1)을 상기 한계 심도(L)까지 굴착하는 것이 바람직하다.The inclined surface forming step may be performed such that the area between the first heat thumb pile 100 and the second heat thumb pile 200 is sloped inwardly to a critical depth L forming a stable slope, 1) to the limit depth (L).

상기 경사면 형성단계는 상기 제1열 엄지말뚝(100)과 제2열 엄지말뚝(200)의 사이 영역 및 상기 굴착영역(1)을 1차 설계 심도(H1)까지 굴착하면서, 상기 제2열 엄지말뚝(200)의 사이에 제2열 흙막이 부재(20)를 설치하여 제2열 흙막이 구조물을 형성하는 제2열 흙막이 구조물 형성단계; 상기 1차 설계 심도(H1) 이하에서, 상기 제1열 엄지말뚝(100)과 제2열 엄지말뚝(200)의 사이 영역이 안정된 사면을 형성하는 2차 설계 심도(H2)까지 내측으로 경사지게 굴착함과 아울러, 상기 굴착영역(1)을 상기 2차 설계 심도(H2)까지 굴착하는 단계;를 포함하는 것이 바람직하다.The slope forming step may include excavating the area between the first row of thumb piles 100 and the second row of thumb piles 200 and the excavation area 1 up to the first design depth H1, Forming a second thermal retention structure by providing a second thermal retention member (20) between the piles (200) to form a second thermal retention structure; Below the primary design depth H1, the area between the first row of thumb piles 100 and the second row of thumb piles 200 is sloped inward to the second design depth H2 forming a stable slope And excavating the excavation region 1 up to the secondary design depth H2.

상기 연결단계는 전후방향 연결부재(310)에 의해 상기 제1열 엄지말뚝(100) 및 제2열 엄지말뚝(200)의 상부를 상호 연결하는 것이 바람직하다.Preferably, the connecting step interconnects the upper portion of the first heat thumb pile 100 and the upper portion of the second heat thumb pile 200 by the anteroposterior connecting member 310.

상기 연결단계는 상기 제1열 엄지말뚝(100)을 제1열 좌우방향 연결부재(321)에 의해 상호 연결하는 단계; 상기 제2열 엄지말뚝(200)을 제2열 좌우방향 연결부재(322)에 의해 상호 연결하는 단계; 상기 제1열 좌우방향 연결부재(321)와 상기 제2열 좌우방향 연결부재(322)를 상기 전후방향 연결부재(310)에 의해 상호 연결하는 단계;를 포함하는 것이 바람직하다.The connecting step comprises interconnecting the first row thumb piles 100 by a first row left-right connecting member 321; Interconnecting said second row thumb piles (200) by a second row lateral linking member (322); And connecting the first row left-right direction linking member 321 and the second row left-right direction linking member 322 by the front-rear direction connecting member 310. [

상기 제1열 좌우방향 연결부재(321) 및 제2열 좌우방향 연결부재(322)는 각각 상기 제1열 엄지말뚝(100) 및 제2열 엄지말뚝(200)의 상단에 설치하고, 상기 전후방향 연결부재(310)는 상기 제1열 좌우방향 연결부재(321) 및 제2열 좌우방향 연결부재(322)의 상부에 설치하는 것이 바람직하다.The first row left-right direction connecting member 321 and the second row left-right direction connecting member 322 are installed at the upper ends of the first row thumb pile 100 and the second row thumb pile 200, Direction connecting member 310 may be installed on the first row left-right direction connecting member 321 and the second row left-right direction connecting member 322.

본 발명은 고심도의 터파기 작업을 수행하는 경우에도 배후토사의 토압에 충분히 저항하도록 하고, 흙막이 구조물의 전체적인 변위의 발생을 억제할 수 있도록 하는 2열 엄지말뚝 흙막이 공법을 제시한다.The present invention proposes a two-row thumb pile cladding method which can sufficiently resist the earth pressure of the back soil and suppress the occurrence of the overall displacement of the cladding structure even when performing a severe trenching operation.

이하, 첨부도면을 참조하여 본 발명의 실시예에 관하여 상세히 설명한다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 2 이하에 도시된 바와 같이, 본 발명에 의한 엄지말뚝 흙막이 공법은 기본적으로 다음과 같은 공정에 의해 구성된다.As shown in FIG. 2 and subsequent drawings, the thumb pile retention method according to the present invention is basically composed of the following processes.

굴착영역(1)의 경계선을 따라 제1열 엄지말뚝(100)을 근입하고, 그 제1열 엄지말뚝(100)의 외측에 간격을 두고 제2열 엄지말뚝(200)을 근입한다(도 2).The first row thumb pile 100 is inserted along the boundary line of the excavation region 1 and the second row thumb pile 200 is inserted at the outer side of the first row thumb pile 100 ).

제1열 엄지말뚝(100) 및 제2열 엄지말뚝(200)이 일체로 거동하도록 연결부재(300)에 의해 상호 연결한다(도 3).The first row of thumb piles 100 and the second row of thumb piles 200 are interconnected by a connecting member 300 so as to act integrally (FIG. 3).

더욱 구체적으로는, 터파기의 진행에 의해 제1열 엄지말뚝(100)과 제2열 엄지말뚝(200)의 상부가 지반 위로 노출되면, 그 상단에 제1열 좌우방향 연결부재(321)와 제2열 좌우방향 연결부재(322)를 각각 설치하고, 제1열 좌우방향 연결부재(321) 및 제2열 좌우방향 연결부재(322)의 상부에 전후방향 연결부재(310)를 설치하는 것이 바람직하다.More specifically, when the first row of thumb piles 100 and the upper portion of the second row thumb pile 200 are exposed on the ground by the progress of the tearing, the first row left-right direction connecting member 321 and the first row left- And the front-rear direction connecting member 310 is installed on the upper portion of the first row left-right direction connecting member 321 and the second row left-right direction connecting member 322, desirable.

굴착영역(1)을 굴착하면서, 제1열 엄지말뚝(100)의 사이에 흙막이 부재(10)를 순차적으로 설치하여 흙막이 구조물을 형성한다(도 4,5).The excavation region 1 is excavated and the earth retaining member 10 is sequentially installed between the first row thumb piles 100 to form a retaining structure (FIGS.

상기 흙막이 구조물에 대하여 레이커(400)를 설치한다(도 4,5).The lacquer 400 is installed on the retaining structure (Figs. 4 and 5).

즉, 제1열 엄지말뚝(100)에 흙막이 부재(10)가 설치된 흙막이 구조물에 더하여, 외측에 제2열 엄지말뚝(200)을 근입하고 제1열 엄지말뚝(100)을 이와 일체로 거동하도록 설치하는 한편, 제1열 엄지말뚝(100)에 의한 흙막이 구조물에 레이커(400)를 설치하여 보강한 것이다.That is, in addition to the retaining structure in which the earth retaining member 10 is installed on the first row thumb pile 100, the second row thumb pile 200 is inserted into the outer side and the first row thumb pile 100 is moved in unison with the retaining structure And the lacquer 400 is installed on the retaining structure of the first row thumb pile 100 to reinforce it.

이는 종래의 일반적인 흙막이 공법에 비해 다음과 같은 장점을 갖는다.This has the following advantages as compared with the conventional conventional earth retaining method.

첫째, 제2열 엄지말뚝(200)이 배후토체의 전단파괴를 방지하는 사면의 억지 말뚝 역할을 수행하므로, 흙막이 구조물의 변위 발생을 극소화할 수 있다.First, since the second row thumb pile 200 serves as a constraining pile for preventing the shear failure of the rear soil body, the displacement of the retaining structure can be minimized.

둘째, 주변 여건상 어스 앵커 등 배면 보강공법을 사용할 충분한 공간의 여유가 없는 경우, 제2열 엄지말뚝(200) 및 레이커(400)의 복합 구조에 의해, 배면에 대한 보강을 최소화하면서도, 전체적인 흙막이 구조물의 구조적 안정성을 충분히 확보할 수 있다.Secondly, the composite structure of the second row thumb pile 200 and the lacquer 400 minimizes the reinforcement to the back surface, while the overall construction of the retaining pillar 200 and the lacquer 400, The structural stability of the structure can be sufficiently secured.

셋째, 제1열 엄지말뚝(100), 제2열 엄지말뚝(200), 연결부재(300), 레이커(400)가 일체로 거동하여, 각 부재의 강도를 충분히 발휘할 수 있도록 하는바, 동일한 강도 및 양의 자재를 사용하면서도 고심도의 터파기가 가능하므로, 경제적이다.Third, the first row thumb pile 100, the second row thumb pile 200, the connecting member 300, and the lacquer 400 behave as a single body so that the strength of each member can be sufficiently exhibited, And it is economical because it is possible to use a high-grade tough material while using a positive material.

이하, 레이커(400)의 시공에 관한 구체적 실시예에 대하여 설명한다.Hereinafter, concrete examples of the construction of the lacquer 400 will be described.

레이커 설치단계는 기본적으로, 흙막이 구조물에 대하여 레이커(400)의 상단을 정착하는 레이커 상단 정착단계; 굴착영역(1)의 저면에 레이커 지지부(410)를 형성하는 레이커 지지부 형성단계; 레이커 지지부(410)에 레이커(400)의 하단을 정착하는 레이커 하단 정착단계;를 포함하여 구성된다.The lacquer installing step basically includes a rake top fixing step of fixing the upper end of the lacquer 400 to the securing structure; Forming a laker support part (410) on a bottom surface of the excavation area (1); And a lower lacquer fixing step of fixing the lower end of the lacquer 400 to the lacquer supporting portion 410.

흙막이 구조물에 대하여 레이커(400)를 시공하는 방식은, 띠장에 설치하는 방식, 띠장없이 제1열 엄지말뚝(100)에 직접 설치하는 방식 중 어느 것을 사용해도 관계없으나, 본 발명에 의한 공법의 경우 제1열 엄지말뚝(100)에는 제2열 엄지말뚝(200) 및 연결부재(300)에 의해 많은 하중이 재하되므로, 제1열 엄지말뚝(100)을 더욱 보강하는 의미에서, 띠장(420)을 설치하고 이에 레이커(400)를 설치하는 방식을 적용하는 것이 바람직하다.The method of installing the lacquer 400 on the retaining structure may be either a method of installing the lacquer 400 on the wale band or a method of directly installing the lacquer 400 on the first row thumb pile 100 without wales. Since the first row of thumb piles 100 is loaded with a large load by the second row thumb pile 200 and the connecting member 300, And the lacquer 400 is installed thereon.

즉, 제1열 엄지말뚝(100)의 전방에 띠장(420)을 설치하고, 그 띠장(420)에 대하여 레이커(400)의 상단을 정착하는 방식을 취하는 것이 바람직한 것이다(도 4,5).That is, it is preferable to provide a wristband 420 in front of the first row of thumb piles 100 and fix the upper end of the lacquer 400 to the wristband 420 (FIGS. 4 and 5).

레이커 지지부(100)는 도 5에 도시된 바와 같이, 지지말뚝(411)을 상하방향으로 근입하고, 지지말뚝(411)의 상단에 좌우방향으로 지지파일(412)을 설치한 후, 지지말뚝(411) 및 지지파일(412)의 주위에 콘크리트를 타설하여 콘크리트 블록(413)을 형성하고, 레이커(400)의 하단이 위 지지파일(412)에 의해 지지되는 구성을 취하는 것이 구조적 안정성 측면에서 바람직하다.5, the lacquer supporting portion 100 is constructed such that the supporting pile 411 is vertically inserted and the supporting pile 412 is installed in the upper portion of the supporting pile 411 in the left and right direction, It is preferable that the concrete block 413 is formed by placing concrete around the support pile 411 and the support pile 412 and that the lower end of the lakere 400 is supported by the upper support pile 412, Do.

연약지반의 경우에는, 지지말뚝(411)의 주위 지반에 강화제를 주입하여 지반을 강화하는 공정이 추가되는 것이 좋다.In the case of a soft ground, it is advisable to add a step of strengthening the ground by injecting a strengthening agent into the surrounding ground of the support pile 411.

이하, 도 6,7을 참조하여, 경사면(2)이 형성된 경우에 관한 실시예에 대하여 설명한다.Hereinafter, referring to Figs. 6 and 7, description will be given of an embodiment relating to the case where the inclined surface 2 is formed.

위 흙막이 구조물 형성단계에서, 제1열 엄지말뚝(100)과 제2열 엄지말뚝(200)의 사이에 내측을 향하는 경사면(2)이 형성되도록 굴착하는 공정을 더 포함하는 것이 바람직하다.It is preferable to further include a step of excavating the inclined surface 2 facing inward between the first row thumb pile 100 and the second row thumb pile 200 in the formation of the upper retaining structure.

이와 같이 흙막이 공사를 수행하는 경우, 도 7에 도시된 바와 같은 흙막이 구조물을 형성할 수 있는데, 이는 종래의 흙막이 구조물에 비해 제1열 엄지말뚝(100)과 제2열 엄지말뚝(200) 사이의 상부에 경사면(2)이 형성된다는 점에서 특징이 있다.7, it is possible to form a retaining structure between the first row of thumb piles 100 and the second row of thumb piles 200 in comparison with the conventional retaining structure, And the inclined surface 2 is formed on the upper portion.

즉, 본 실시예에 의한 공법을 적용하는 경우, 종래의 구조에 비해 경사면(2) 상부 영역(S)에 해당하는 만큼의 토괴가 제거된 구조를 얻을 수 있으므로, 그만큼의 토압이 감소되어, 동일한 강도의 자재를 사용하는 경우에는 더욱 고심도의 흙막이 구조물을 얻을 수 있고, 동일한 심도의 흙막이 구조물을 시공하는 경우에는 자재를 절약할 수 있다는 효과를 얻을 수 있는 것이다.In other words, when the method according to the present embodiment is applied, the structure in which the masses corresponding to the upper region S of the slope 2 are removed can be obtained as compared with the conventional structure, When a material having a high strength is used, a more advanced retention structure can be obtained, and when the retention structure with the same depth is used, the material can be saved.

위 경사면(2)의 형성작업을 더욱 구체적으로 설명하면, 제1열 엄지말뚝(100)과 제2열 엄지말뚝(200)의 사이 영역이 안정된 경사의 사면을 형성하는 한계 심도(L)까지 내측으로 경사지게 굴착하는 한편, 굴착영역(1)을 그 한계 심도(L)까지 굴착하는 것이 바람직하다(도 6).The region between the first row of thumb piles 100 and the second row of thumb thumb piles 200 is formed in the inner side to a limit depth L forming a slope having a stable inclination, It is preferable to excavate the excavation region 1 to its limit depth L (Fig. 6).

한계 심도(L) 이후부터는, 제1열 엄지말뚝(100)에 흙막이 부재(10)를 설치하면서 설계 심도까지 굴착하고, 상술한 바와 같이 레이커(400)를 설치한다(도 7).After the limit depth L, the soil retaining member 10 is installed on the first row thumb pile 100 and the lakers 400 are installed as described above (FIG. 7).

도 8 내지 10은 본 발명에 2열 엄지말뚝 흙막이 공법의 또 다른 실시예를 도시한 것이다.8 to 10 illustrate another embodiment of the two-row thumb pile cladding method according to the present invention.

이는 기본적인 공정은 위 실시예와 동일하나, 경사면 형성단계가 다소 상이하다.This is basically the same as the above embodiment, but the step of forming the inclined surface is somewhat different.

본 실시예에 있어서의 경사면 형성단계는 다음과 같이 구성된다.The inclined plane forming step in this embodiment is configured as follows.

제1열 엄지말뚝(100)과 제2열 엄지말뚝(200)의 사이 영역 및 굴착영역(1)을 1차 설계 심도(H1)까지 굴착하면서, 제2열 엄지말뚝(200)의 사이에 제2열 흙막이 부재(20)를 설치한다(도 8).The area between the first row thumb pile 100 and the second row thumb pile 200 and the excavation area 1 are excavated up to the first design depth H1, And a two-column earth retaining member 20 is installed (Fig. 8).

1차 설계 심도(H1) 이하에서, 제1열 엄지말뚝(100)과 제2열 엄지말뚝(200)의 사이 영역이 안정된 사면을 형성하는 2차 설계 심도(H2)까지 내측으로 경사지게 굴 착함과 아울러, 굴착영역(1)을 2차 설계 심도(H2)까지 굴착한다(도 9).Below the first design depth H1, the area between the first row of thumb piles 100 and the second row of thumb piles 200 is inclined inward to the second design depth H2, which forms a stable slope, In addition, the excavation area 1 is excavated up to the secondary design depth H2 (FIG. 9).

2차 설계 심도(H2) 이하에서는, 제1열 엄지말뚝(100)에 흙막이 부재(10)를 설치하면서 설계 심도까지 굴착하고, 상술한 바와 같이 레이커(400)를 설치한다(도 10).Below the secondary design depth H2, the soil retaining member 10 is installed on the first row of thumb piles 100, and the lakers 400 are installed as described above (FIG. 10).

이와 같이 흙막이 공사를 수행하는 경우, 도 10에 도시된 바와 같은 흙막이 구조물을 형성할 수 있는데, 이는 제1열 엄지말뚝(100)과 제2열 엄지말뚝(200) 사이의 상부 경사면(2) 위에 또 다른 제2열 흙막이 구조물이 형성된다는 특징이 있다.10 may be formed on the upper sloped surface 2 between the first row of thumb piles 100 and the second row of thumb piles 200. In this case, Another second heat retaining structure is formed.

이러한 제2열 흙막이 구조물은 제1열 엄지말뚝(100)과 제2열 엄지말뚝(200) 사이에 형성되는 경사면(2)을 안정시키는 역할을 하므로, 그 경사면(2)의 상부 영역(S)을 더욱 크게 형성할 수 있도록 한다.The second heat retaining structure serves to stabilize the inclined surface 2 formed between the first heat thumb pile 100 and the second heat thumb pile 200 so that the upper region S of the inclined surface 2 is formed, As shown in Fig.

따라서, 도 7의 실시예에 비해 더욱 많은 영역(S)의 토괴가 제거된 구조를 얻을 수 있으므로, 더욱 큰 토압 감소효과를 얻을 수 있고, 이로 인하여 동일한 강도의 자재를 사용하는 경우에는 더욱 고심도의 흙막이 구조물을 얻을 수 있고, 동일한 심도의 흙막이 구조물을 시공하는 경우에는 자재를 절약할 수 있다는 효과를 더욱 크게 얻을 수 있는 것이다.Therefore, since the structure in which the mass of the region S is removed more than in the embodiment of FIG. 7 can be obtained, a greater earth pressure reduction effect can be obtained. Therefore, when the same strength material is used, It is possible to obtain a retaining structure of the same depth, and in the case of constructing the retaining structure of the same depth, the effect of saving the material can be further increased.

이하, 도 4,5를 참조하여 위 연결단계에 적용되는 연결부재(300)의 실시예에 대하여 설명한다.Hereinafter, referring to FIGS. 4 and 5, an embodiment of the connecting member 300 applied to the connecting step will be described.

연결부재(300)는 제1열 엄지말뚝(100) 및 제2열 엄지말뚝(200)이 상호 일체화하도록 연결하는 것이므로, 전후방향으로 이들을 연결하는 구조가 필요하고, 상 술한 흙막이 부재 구조물의 상부두부 변위의 발생문제를 최소화하기 위해서는, 전후방향 연결부재(310)에 의해 제1열 엄지말뚝(100) 및 제2열 엄지말뚝(200) 상부를 상호 연결하는 구조를 취하는 것이 바람직하다.The connecting member 300 connects the first row thumb pile 100 and the second row thumb pile 200 so that the first row thumb pile 100 and the second row thumb pile 200 are integrated with each other. In order to minimize the occurrence of the displacement, it is preferable that the front and rear connecting members 310 interconnect the first heat thumb pile 100 and the second heat thumb pile 200 with each other.

이러한 전후방향 연결부재(310)는 다수의 제1열 엄지말뚝(100) 및 제2열 엄지말뚝(200) 중 각각의 엄지말뚝(100,200)을 상호 연결하는 구조를 취할 수도 있으나, 흙막이 구조물 전체의 구조적 안정성 증대를 위해서는, 다음과 같이 전체가 일체화된 구성을 취하는 것이 더욱 바람직하다.The front-and-back connecting member 310 may connect the thumb piles 100 and 200 of the plurality of first heat thumb piles 100 and the second heat thumb piles 200 to each other, In order to increase the structural stability, it is more preferable to take the whole integrated structure as follows.

즉, 제1열 엄지말뚝(100)을 제1열 좌우방향 연결부재(321)에 의해 상호 연결하고, 제2열 엄지말뚝(200)을 제2열 좌우방향 연결부재(322)에 의해 상호 연결한 후, 제1열 좌우방향 연결부재(321)와 제2열 좌우방향 연결부재(322)를 전후방향 연결부재(310)에 의해 상호 연결하는 것이 그것이다.That is, the first row of thumb piles 100 are interconnected by a first row lateral linking member 321 and the second row of thumb-piles 200 are interconnected by a second row lateral linking member 322 The first row left-right direction connecting member 321 and the second row left-right direction connecting member 322 are interconnected by the front-rear direction connecting member 310.

이러한 구조를 취하는 경우에도, 상술한 상부두부 변위의 발생문제를 해소하기 위해서는, 제1열 좌우방향 연결부재(321) 및 제2열 좌우방향 연결부재(322)는 각각 제1열 엄지말뚝(100) 및 제2열 엄지말뚝(200)의 상단에 설치하고, 전후방향 연결부재(310)는 제1열 좌우방향 연결부재(321) 및 제2열 좌우방향 연결부재(322)의 상부에 설치하는 구성을 취하는 것이 바람직하다.In order to solve the problem of the above-mentioned top head displacement, the first row left-right direction connecting member 321 and the second row left-right direction connecting member 322 may be formed of the first row thumb pile 100 And the front-rear direction connecting member 310 is installed on the upper part of the first row left-right direction connecting member 321 and the second row left-right direction connecting member 322 It is preferable to adopt a configuration.

이상은 본 발명에 의해 구현될 수 있는 바람직한 실시예의 일부에 관하여 설명한 것에 불과하므로, 주지된 바와 같이 본 발명의 범위는 위의 실시예에 한정되어 해석되어서는 안 될 것이며, 위에서 설명된 본 발명의 기술적 사상과 그 근본을 함께 하는 기술적 사상은 모두 본 발명의 범위에 포함된다고 할 것이다.It will be apparent to those skilled in the art that various modifications and variations can be made in the present invention without departing from the spirit or scope of the invention as defined in the appended claims. It is to be understood that both the technical idea and the technical spirit of the invention are included in the scope of the present invention.

도 1은 종래의 엄지말뚝 흙막이 구조물의 사시도.1 is a perspective view of a conventional thumb pile cladding structure.

도 2 내지 10은 본 발명에 의한 2열 엄지말뚝 흙막이 공법을 설명하기 위한 도면으로서,2 to 10 are views for explaining a two-row thumb pile retention method according to the present invention,

도 2 내지 4는 제1실시예의 공정도.2 to 4 are process drawings of the first embodiment.

도 5는 제1실시예에 의한 흙막이 구조물의 단면도.5 is a cross-sectional view of the earth retaining structure according to the first embodiment.

도 6,7는 제2실시예의 공정도.6 and 7 are process drawings of the second embodiment.

도 8 내지 10은 제3실시예의 공정도.8 to 10 are process drawings of the third embodiment.

**도면의 주요부분에 대한 부호의 설명**DESCRIPTION OF REFERENCE NUMERALS

1 : 굴착영역 2 : 경사면1: excavation area 2: slope

10 : 흙막이 부재 100 : 제1열 엄지말뚝10: earth retaining member 100: first row thumb pile

200 : 제2열 엄지말뚝 300 : 연결부재200: second row thumb pile 300: connecting member

310 : 전후방향 연결부재 321 : 제1열 좌우방향 연결부재310: front-rear direction connecting member 321: first-row left-right direction connecting member

322 : 제2열 좌우방향 연결부재 400 : 레이커322: second row left-right direction connecting member 400:

410 : 레이커 지지부 411 : 지지말뚝410: lacquer supporting part 411: support pile

412 : 지지파일 413 : 콘크리트 블록412: support file 413: concrete block

420 : 띠장 L : 한계 심도420: Welt L: Limit depth

H1 : 1차 설계 심도 H2 : 2차 설계 심도H1: 1st design depth H2: 2nd design depth

Claims (11)

굴착영역(1)의 경계선을 따라 제1열 엄지말뚝(100)을 근입하는 제1열 엄지말뚝 근입단계;A first row of thumb pegs adjacent to the first row of thumb piles 100 along a boundary line of the excavation region 1; 상기 제1열 엄지말뚝(100)의 외측에 간격을 두고 제2열 엄지말뚝(200)을 근입하는 제2열 엄지말뚝 근입단계;A second row of thumb thumb piles adjacent to the second row of thumb thumb piles 200 spaced apart from the first row of thumb thumb piles 100; 상기 제1열 엄지말뚝(100) 및 제2열 엄지말뚝(200)이 일체로 거동하도록 연결부재(300)에 의해 상호 연결하는 연결단계;A connecting step of interconnecting the first heat thumb pile 100 and the second heat thumb pile 200 by the connecting member 300 so that the first heat thumb pile 100 and the second heat thumb pile 200 integrally move; 상기 굴착영역(1)을 굴착하면서, 상기 제1열 엄지말뚝(100)의 사이에 흙막이 부재(10)를 설치하여 흙막이 구조물을 형성하는 흙막이 구조물 형성단계;Forming an earth retaining structure by excavating the excavation region (1) and installing a securing member (10) between the first heat thumb piles (100) to form a securing structure; 상기 흙막이 구조물에 대하여 레이커(400)를 설치하는 레이커 설치단계;를 포함하고,And a lacquer installing step of installing a lacquer (400) on the retaining structure, 상기 흙막이 구조물 형성단계는The retaining structure forming step 상기 제1열 엄지말뚝(100)과 제2열 엄지말뚝(200)의 사이에 내측을 향하는 경사면(2)이 형성되도록 굴착하는 경사면 형성단계를 더 포함하며,The method of claim 1, further comprising: forming an inclined surface (2) between the first heat thumb pile (100) and the second heat thumb pile (200) 상기 경사면 형성단계는The slope forming step 상기 제1열 엄지말뚝(100)과 제2열 엄지말뚝(200)의 사이 영역 및 상기 굴착영역(1)을 1차 설계 심도(H1)까지 굴착하면서, 상기 제2열 엄지말뚝(200)의 사이에 제2열 흙막이 부재(20)를 설치하여 제2열 흙막이 구조물을 형성하는 제2열 흙막이 구조물 형성단계;The area between the first heat thumb pile 100 and the second heat thumb pile 200 and the area between the first heat thumb pile 200 and the second heat thumb pile 200 while excavating the excavation area 1 to the first design depth H1. Forming a second thermal retention structure by providing a second thermal retention member 20 between the first and second thermal retention members; 상기 1차 설계 심도(H1) 이하에서, 상기 제1열 엄지말뚝(100)과 제2열 엄지말뚝(200)의 사이 영역이 안정된 사면을 형성하는 2차 설계 심도(H2)까지 내측으로 경사지게 굴착함과 아울러, 상기 굴착영역(1)을 상기 2차 설계 심도(H2)까지 굴착하는 단계;를 포함하는 것을 특징으로 하는 레이커를 이용한 2열 엄지말뚝 흙막이 공법.Below the primary design depth H1, the area between the first row of thumb piles 100 and the second row of thumb piles 200 is sloped inward to the second design depth H2 forming a stable slope And excavating the excavation area (1) to the secondary design depth (H2). 제1항에 있어서,The method according to claim 1, 상기 레이커 설치단계는The laker installation step 상기 흙막이 구조물에 대하여 상기 레이커(400)의 상단을 정착하는 레이커 상단 정착단계;A rake top fixing step of fixing the upper end of the lacquer 400 to the securing structure; 상기 굴착영역(1)의 저면에 레이커 지지부(410)를 형성하는 레이커 지지부 형성단계;Forming a laker support part (410) on a bottom surface of the excavation area (1); 상기 레이커 지지부(410)에 상기 레이커(400)의 하단을 정착하는 레이커 하 단 정착단계;를 And fixing the lower end of the lacquer (400) to the lacquer supporting part (410); 포함하는 것을 특징으로 하는 레이커를 이용한 2열 엄지말뚝 흙막이 공법.A two-row thumb pile retention method using a lacquer characterized by comprising 제2항에 있어서,3. The method of claim 2, 상기 레이커 상단 정착단계는The rake top settlement step 상기 제1열 엄지말뚝(100)의 전방에 띠장(420)을 설치하는 띠장 설치단계;Installing a wale 420 in front of the first row thumb pile 100; 상기 띠장(420)에 대하여 상기 레이커(400)의 상단을 정착하는 단계;를Fixing the upper end of the laker (400) to the wristband (420); 포함하는 것을 특징으로 하는 레이커를 이용한 2열 엄지말뚝 흙막이 공법.A two-row thumb pile retention method using a lacquer characterized by comprising 제2항에 있어서,3. The method of claim 2, 상기 레이커 지지부 형성단계는The lacquer support forming step 지지말뚝(411)을 상하방향으로 근입하는 단계;Supporting the pile 411 vertically; 상기 레이커(400)의 하단을 지지하도록, 상기 지지말뚝(411)의 상단에 좌우방향으로 지지파일(412)을 설치하는 단계;Installing a support pile (412) in a lateral direction on the upper end of the support pile (411) to support the lower end of the laker (400); 상기 지지말뚝(411) 및 지지파일(412)의 주위에 콘크리트를 타설하여 콘크리트 블록(413)을 형성하는 단계;를Forming a concrete block 413 by placing concrete around the support pile 411 and the support pile 412; 포함하는 것을 특징으로 하는 레이커를 이용한 2열 엄지말뚝 흙막이 공법.A two-row thumb pile retention method using a lacquer characterized by comprising 제4항에 있어서,5. The method of claim 4, 상기 레이커 지지부 형성단계는The lacquer support forming step 상기 지지말뚝(411)의 주위 지반에 강화제를 주입하는 단계를 더 포함하는 것을 특징으로 하는 레이커를 이용한 2열 엄지말뚝 흙막이 공법.Further comprising the step of injecting a reinforcing agent into the surrounding ground of the support pile (411). 삭제delete 삭제delete 삭제delete 제1항 내지 제5항 중 어느 한 항에 있어서,6. The method according to any one of claims 1 to 5, 상기 연결단계는The connecting step 전후방향 연결부재(310)에 의해 상기 제1열 엄지말뚝(100) 및 제2열 엄지말뚝(200)의 상부를 상호 연결하는 것을 특징으로 하는 레이커를 이용한 2열 엄지말뚝 흙막이 공법.And the upper part of the first heat thumb pile 100 and the upper part of the second heat thumb pile 200 are connected to each other by the front and rear direction connecting member 310. [ 제9항에 있어서,10. The method of claim 9, 상기 연결단계는The connecting step 상기 제1열 엄지말뚝(100)을 제1열 좌우방향 연결부재(321)에 의해 상호 연결하는 단계;Interconnecting the first row thumb piles 100 by a first row lateral linking member 321; 상기 제2열 엄지말뚝(200)을 제2열 좌우방향 연결부재(322)에 의해 상호 연결하는 단계;Interconnecting said second row thumb piles (200) by a second row lateral linking member (322); 상기 제1열 좌우방향 연결부재(321)와 상기 제2열 좌우방향 연결부재(322)를 상기 전후방향 연결부재(310)에 의해 상호 연결하는 단계;를Connecting the first row left-right direction connecting member 321 and the second row left-right direction connecting member 322 by the front-rear direction connecting member 310; 포함하는 것을 특징으로 하는 레이커를 이용한 2열 엄지말뚝 흙막이 공법.A two-row thumb pile retention method using a lacquer characterized by comprising 제10항에 있어서,11. The method of claim 10, 상기 제1열 좌우방향 연결부재(321) 및 제2열 좌우방향 연결부재(322)는 각각 상기 제1열 엄지말뚝(100) 및 제2열 엄지말뚝(200)의 상단에 설치하고, The first row left-right direction connecting member 321 and the second row left-right direction connecting member 322 are installed at the upper ends of the first row thumb pile 100 and the second row thumb pile 200, 상기 전후방향 연결부재(310)는 상기 제1열 좌우방향 연결부재(321) 및 제2열 좌우방향 연결부재(322)의 상부에 설치하는 것을 특징으로 하는 레이커를 이용한 2열 엄지말뚝 흙막이 공법.The front-and-rear direction connecting member 310 is installed on the first row left-right direction connecting member 321 and the second row left-right direction connecting member 322.
KR1020080016743A 2008-02-25 2008-02-25 Soil retaining method for two rows pile using raker KR100964995B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020080016743A KR100964995B1 (en) 2008-02-25 2008-02-25 Soil retaining method for two rows pile using raker

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020080016743A KR100964995B1 (en) 2008-02-25 2008-02-25 Soil retaining method for two rows pile using raker

Publications (2)

Publication Number Publication Date
KR20090091467A KR20090091467A (en) 2009-08-28
KR100964995B1 true KR100964995B1 (en) 2010-06-21

Family

ID=41208859

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020080016743A KR100964995B1 (en) 2008-02-25 2008-02-25 Soil retaining method for two rows pile using raker

Country Status (1)

Country Link
KR (1) KR100964995B1 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102704489A (en) * 2012-05-02 2012-10-03 广州市鲁班建筑集团有限公司 Foundation pit support structure and construction method thereof
KR101310677B1 (en) 2011-09-05 2013-09-24 주식회사 한빛구조엔지니어링 Top down method using precast composite retaining wall and raker in slope
CN103498475A (en) * 2013-10-12 2014-01-08 中国建筑股份有限公司 Foundation pit supporting structure for controlling existing building deformation and construction method for excavating foundation pit
KR101732133B1 (en) * 2014-09-03 2017-05-12 이기환 Reinforcement structure for pile and construction method of reinforcement structure for pile using the same
KR20220120392A (en) * 2021-02-23 2022-08-30 박주용 Earth wall for earthwork
KR20230119579A (en) 2022-02-07 2023-08-16 김기철 Pre-stressed rectangular pile structure for rataining wall and rataining wall constructing method using the pre-stressed rectangular pile structure

Families Citing this family (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101117924B1 (en) * 2011-08-04 2012-02-22 박기경 Composite type steel temporary construction and construction method thereof
CN103114592B (en) * 2011-11-16 2014-11-19 龙信建设集团有限公司 Method for deep excavation pit combination support construction close to subway station
CN103669364A (en) * 2012-08-30 2014-03-26 深圳市工勘岩土工程有限公司 Pit-in-pit horizontal supporting structure in deep foundation pit and construction method thereof
CN103074899B (en) * 2013-01-18 2014-12-24 周文松 Subdepot pier-type foundation pit support structure and construction method
CN103195069B (en) * 2013-04-01 2016-01-20 北京工业大学 Pre-stress type double-row pile strong constraint method for supporting deep foundation pit
KR102068320B1 (en) * 2017-11-03 2020-01-20 홍예진 block assembly of module type and construction method of tunnel
CN108951659B (en) * 2018-08-27 2020-06-02 广东耀南建筑工程有限公司 Foundation pit supporting structure based on row piles and inner supports and construction method thereof
CN109667273A (en) * 2018-12-22 2019-04-23 广州市天作建筑规划设计有限公司 A kind of construction method of deep foundation pit supporting structure
CN110159296A (en) * 2019-06-14 2019-08-23 中国建筑一局(集团)有限公司 A kind of structural system and its construction method of the deformation of control Shield-bored tunnels
CN110359463A (en) * 2019-06-24 2019-10-22 麦廊建设有限公司 It tiltedly throws the construction method of support supporting and tiltedly throws support supporting
CN110306559A (en) * 2019-06-26 2019-10-08 广州穗岩土木科技股份有限公司 A kind of construction method of subway entrance support pile
CN111101524B (en) * 2020-01-17 2021-05-18 顺康基础建设有限公司 Temporary supporting structure for foundation pit construction and temporary supporting construction method
KR102195203B1 (en) * 2020-02-13 2020-12-28 주식회사 이에스지오 Soil blocking method using horizontal Strut and slope Strut
CN113445515B (en) * 2021-07-23 2022-08-23 中国建筑第二工程局有限公司 Construction method for reverse construction of three-row pile support of ultra-deep foundation pit
KR102456100B1 (en) * 2022-04-28 2022-10-18 건창산업(주) Prestressed beam assembly and method for installing self-standing retaining temporary facilities using the same
KR102456102B1 (en) * 2022-04-28 2022-10-18 건창산업(주) Assembly of temporary retaining facilities using 3-way piles and construction method of retaining temporary facilities using 3-way piles using the same
KR102544134B1 (en) * 2023-03-06 2023-06-16 (주) 동인지테크 Raker Supporting Structure for Retaining Wall having Variable Supporting Angle and Variable Supporting Position, and Retaining Wall having such Raker Supporting Structure, and Constructing Method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05179647A (en) * 1991-12-27 1993-07-20 Haseko Corp Supporting structure for earth retaining wall
JPH09264024A (en) * 1996-03-29 1997-10-07 Kawasaki Steel Corp Retaining or coffering method
KR20060032823A (en) * 2004-10-13 2006-04-18 코오롱건설주식회사 Soil retaining method using two rows pile
KR100635331B1 (en) * 2006-03-16 2006-10-18 (주)써포텍 Raker support structure for underground pre-scaffolding system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05179647A (en) * 1991-12-27 1993-07-20 Haseko Corp Supporting structure for earth retaining wall
JPH09264024A (en) * 1996-03-29 1997-10-07 Kawasaki Steel Corp Retaining or coffering method
KR20060032823A (en) * 2004-10-13 2006-04-18 코오롱건설주식회사 Soil retaining method using two rows pile
KR100635331B1 (en) * 2006-03-16 2006-10-18 (주)써포텍 Raker support structure for underground pre-scaffolding system

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101310677B1 (en) 2011-09-05 2013-09-24 주식회사 한빛구조엔지니어링 Top down method using precast composite retaining wall and raker in slope
CN102704489A (en) * 2012-05-02 2012-10-03 广州市鲁班建筑集团有限公司 Foundation pit support structure and construction method thereof
CN102704489B (en) * 2012-05-02 2015-03-18 广州市鲁班建筑集团有限公司 Foundation pit support structure and construction method thereof
CN103498475A (en) * 2013-10-12 2014-01-08 中国建筑股份有限公司 Foundation pit supporting structure for controlling existing building deformation and construction method for excavating foundation pit
CN103498475B (en) * 2013-10-12 2015-04-22 中国建筑股份有限公司 Foundation pit supporting structure for controlling existing building deformation and construction method for excavating foundation pit
KR101732133B1 (en) * 2014-09-03 2017-05-12 이기환 Reinforcement structure for pile and construction method of reinforcement structure for pile using the same
KR20220120392A (en) * 2021-02-23 2022-08-30 박주용 Earth wall for earthwork
KR102490856B1 (en) * 2021-02-23 2023-01-20 박주용 Earth wall for earthwork
KR20230119579A (en) 2022-02-07 2023-08-16 김기철 Pre-stressed rectangular pile structure for rataining wall and rataining wall constructing method using the pre-stressed rectangular pile structure

Also Published As

Publication number Publication date
KR20090091467A (en) 2009-08-28

Similar Documents

Publication Publication Date Title
KR100964995B1 (en) Soil retaining method for two rows pile using raker
KR100964993B1 (en) Soil retaining method for two rows pile
KR100966573B1 (en) Soil retaining method for two rows pile using strut
KR100969996B1 (en) Soil retaining method for two rows pile using earth anchor
KR100776373B1 (en) Soil retaining method using two rows pile
KR100956095B1 (en) Prestressed h-pile and soil retaining method for two rows pile using the same
KR100971198B1 (en) Soil retaining method for two rows pile using soil nailing
KR101652163B1 (en) Concrerte pannel for retaining wall and method for constructing retaining wall using the same
KR101641293B1 (en) Double line retaining wall self-reliance composite wall construction method for reinforcement pile wall
KR101695715B1 (en) Construction method for underground structure
KR20140069845A (en) Retaining wall using diagonal reinforcement member
KR101095700B1 (en) Retaining Wall Structure and Constructing Method thereof
KR101884663B1 (en) Construction method for soil retaining wall using cap slab
KR101988528B1 (en) Self-supporting pile structure using anchor
KR102076969B1 (en) Top-down construction method for concrete building structure using steel pile underground wall and shear support plate
JP6905387B2 (en) Construction method of earth retaining structure
KR102649098B1 (en) Soil retaning structure for two rows pile using prestressed wale
KR100995503B1 (en) Soil retaining structure and method for two rows pile having passage
KR101015610B1 (en) Tunnel having inclined plate
JPH07119548B2 (en) Reinforcement structure of eyeglass type tunnel
KR101218825B1 (en) Method of land-side protection wall using bracing
JP4502442B2 (en) Seismic foundation, seismic building, and pile reinforcement method
KR101732133B1 (en) Reinforcement structure for pile and construction method of reinforcement structure for pile using the same
KR102490879B1 (en) Reinforced earth retaining wall and construction method using H pile
CN219081601U (en) Primary support structure organically combined with hole support pile

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130611

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20140414

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20150611

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20160613

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20170426

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20190425

Year of fee payment: 10