KR100971198B1 - Soil retaining method for two rows pile using soil nailing - Google Patents

Soil retaining method for two rows pile using soil nailing Download PDF

Info

Publication number
KR100971198B1
KR100971198B1 KR1020080016737A KR20080016737A KR100971198B1 KR 100971198 B1 KR100971198 B1 KR 100971198B1 KR 1020080016737 A KR1020080016737 A KR 1020080016737A KR 20080016737 A KR20080016737 A KR 20080016737A KR 100971198 B1 KR100971198 B1 KR 100971198B1
Authority
KR
South Korea
Prior art keywords
row
thumb pile
soil
pile
thumb
Prior art date
Application number
KR1020080016737A
Other languages
Korean (ko)
Other versions
KR20090091463A (en
Inventor
손성곤
심재욱
Original Assignee
코오롱건설주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 코오롱건설주식회사 filed Critical 코오롱건설주식회사
Priority to KR1020080016737A priority Critical patent/KR100971198B1/en
Publication of KR20090091463A publication Critical patent/KR20090091463A/en
Application granted granted Critical
Publication of KR100971198B1 publication Critical patent/KR100971198B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/10Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/80Ground anchors
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2220/00Temporary installations or constructions
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/40Miscellaneous comprising stabilising elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

본 발명은, 굴착영역(1)의 경계선을 따라 제1열 엄지말뚝(100)을 근입하는 제1열 엄지말뚝 근입단계; 제1열 엄지말뚝(100)의 외측에 간격을 두고 제2열 엄지말뚝(200)을 근입하는 제2열 엄지말뚝 근입단계; 제1열 엄지말뚝(100) 및 제2열 엄지말뚝(200)이 일체로 거동하도록 연결부재(300)에 의해 상호 연결하는 연결단계; 굴착영역(1)을 굴착하면서, 제1열 엄지말뚝(100)의 사이에 흙막이 부재(10)를 설치하여 흙막이 구조물을 형성하는 흙막이 구조물 형성단계; 흙막이 구조물에 대하여 소일 네일(400)을 설치하는 소일 네일 설치단계;를 포함하는 소일 네일링을 이용한 2열 엄지말뚝 흙막이 공법을 제시함으로써, 고심도의 터파기 작업을 수행하는 경우에도 배후토사의 토압에 충분히 저항하도록 하고, 흙막이 구조물의 전체적인 변위의 발생을 억제할 수 있도록 한다.The present invention, the first row thumb pile indentation step of entering the first row thumb pile 100 along the boundary line of the excavation region (1); A second row thumb pile indentation step of entering the second row thumb pile 200 at intervals outside the first row thumb pile 100; A connection step of connecting the first row of thumb piles 100 and the second row of thumb piles by the connecting member 300 so as to be integrally behaved; An excavation structure forming step of installing excavation region 1 to form an excavation structure by installing an excavation member 10 between the first row thumb piles 100; Soil nail installation step of installing the soil nail 400 for the soil structure; by presenting a two-row thumb pile earthquake method using a soil nailing, including the earth pressure of the rearing soil even when performing a deep trench work It is to be sufficiently resistant to, and to suppress the occurrence of the overall displacement of the structure.

흙막이, 엄지말뚝, 소일 네일 Crust, Thumb Pile, Soil Nail

Description

소일 네일링을 이용한 2열 엄지말뚝 흙막이 공법{SOIL RETAINING METHOD FOR TWO ROWS PILE USING SOIL NAILING}SOIL RETAINING METHOD FOR TWO ROWS PILE USING SOIL NAILING}

본 발명은 건설 분야에 관한 것으로서, 상세하게는, 배후토사의 토압의 영향을 감소시켜 공기단축 및 공사비 절감효과를 얻을 수 있도록 하는 엄지말뚝 흙막이 공법에 관한 것이다.The present invention relates to the field of construction, and more particularly, to a thumb pile masonry method to reduce the effect of the earth pressure of the earth and sand to obtain the effect of reducing the air and construction costs.

엄지말뚝 흙막이 공법이란 개착식 흙막이 공법의 일종으로서, 일정간격으로 엄지말뚝(H-Pile)을 항타하거나 천공 후 삽입하는 방식에 의해 근입하고, 터파기를 진행하면서 토류판 등의 흙막이 부재를 엄지말뚝 사이에 끼워 넣어 벽체를 형성하는 공법을 말하며, 엄지말뚝 토류판 공법, 시트파일 공법, SCW, CIP 등이 이에 해당한다.Thumb pile earth block method is a kind of detachable earth block method. It is entered by the method of driving the thumb pile (H-Pile) or inserting it after drilling at regular intervals. It refers to a method of embedding the wall forming method, the thumb pile earth plate method, sheet pile method, SCW, CIP and the like.

도 1은 종래의 흙막이 공법 중 엄지말뚝 토류판 공법에 의한 흙막이 구조물의 구성을 개략적으로 도시한 구성도이다.Figure 1 is a schematic diagram showing the configuration of the structure of the earth block by the thumb pile earth plate method of the conventional earth block method.

이는 상호 홈부가 마주 보도록 수직하게 설치된 복수개의 엄지말뚝(H 빔)(1)과, 상기 홈부에 삽입지지되어 후방의 흙더미 등이 전방을 향하여 무너지는 것을 방지하기 위한 토류판(10)에 의해 구성된다.It is constituted by a plurality of thumb piles (H beams) 1 installed vertically so that the mutual groove portions face each other, and an earth plate 10 inserted into the groove portion to prevent the pile of dirt from behind falling down toward the front. .

토류판(10)으로는 소정 규격의 목재판 또는 강재판이 사용되며, 이를 적층하여 벽체를 형성하고, 그 적층된 토류판을 고정하기 위하여 끼움목(쐐기)을 설치한 구조를 채용하는 것이 일반적이었다.As the earth plate 10, a wood plate or a steel plate of a predetermined standard is used, and it has been common to adopt a structure in which fittings (wedges) are installed in order to form a wall by stacking them, and to fix the laminated earth plate.

이와 같은 종래의 엄지말뚝 흙막이 공법은 다음과 같은 점에서 문제로 지적되어 왔다.Such a conventional thumb pile clogging method has been pointed out as a problem in the following points.

첫째, 고심도의 터파기 공사를 수행하는 경우, H 빔만으로는 배후토사의 토압에 저항할 수 없으므로, 이를 보강하기 위하여 많은 수의 지보재(Strut, Earth Anchor, Raker 등)를 사용해야 하는데, 이러한 방식은 비경제적일 뿐만 아니라, 작업공간의 확보를 어렵게 하고, 구조적으로 비효율적이므로 주변지반 침하의 우려가 있다는 점이다.First, in the case of high-depth excavation work, since the H beam alone cannot resist the earth pressure of the rearing soil, a large number of support materials (Strut, Earth Anchor, Raker, etc.) must be used to reinforce it. Not only is it uneconomical, it is difficult to secure a working space and structurally inefficient, so there is a fear of subsidence.

둘째, 종래의 공법에 의한 흙막이 구조물은 강성체로서 토류벽 역할을 할 수는 있으나, 상부두부 변위가 상대적으로 크게 발생하므로 배면부 지반의 이완이 크게 발생한다는 점이다.Second, the earthquake structure according to the conventional construction method can act as an earth wall as a rigid body, but because the displacement of the upper head is relatively large, the loosening of the back ground occurs largely.

본 발명은 상기와 같은 문제점을 해결하기 위하여 안출된 것으로서, 고심도의 터파기 작업을 수행하는 경우에도 배후토사의 토압에 충분히 저항하도록 하고, 흙막이 구조물의 전체적인 변위의 발생을 억제할 수 있도록 하는 2열 엄지말뚝 흙막이 공법을 제시하는 것을 그 목적으로 한다.The present invention has been made to solve the above problems, even when performing a high-depth digging work to sufficiently resist the earth pressure of the rearing soil, and to suppress the occurrence of the overall displacement of the earthen structure 2 The purpose of this article is to present a ten-pile pile masonry method.

본 발명은 상술한 바와 같은 목적을 달성하기 위하여, 굴착영역(1)의 경계선을 따라 제1열 엄지말뚝(100)을 근입하는 제1열 엄지말뚝 근입단계; 상기 제1열 엄지말뚝(100)의 외측에 간격을 두고 제2열 엄지말뚝(200)을 근입하는 제2열 엄지말뚝 근입단계; 상기 제1열 엄지말뚝(100) 및 제2열 엄지말뚝(200)이 일체로 거동하도록 연결부재(300)에 의해 상호 연결하는 연결단계; 상기 굴착영역(1)을 굴착하면서, 상기 제1열 엄지말뚝(100)의 사이에 흙막이 부재(10)를 설치하여 흙막이 구조물을 형성하는 흙막이 구조물 형성단계; 상기 흙막이 구조물에 대하여 소일 네일(400)을 설치하는 소일 네일 설치단계;를 포함하는 소일 네일링을 이용한 2열 엄지말뚝 흙막이 공법을 제시한다.In order to achieve the object as described above, the present invention includes a first row thumb pile indentation step of indenting the first row thumb pile 100 along the boundary line of the excavation region 1; A second row thumb pile indentation step of indenting the second row thumb pile 200 at intervals outside the first row thumb pile 100; A connection step of interconnecting the first row thumb pile 100 and the second row thumb pile 200 by a connection member 300 so as to be integrated with each other; An earthquake structure forming step of forming an earthquake structure by installing the earthquake member 10 between the first row thumb piles 100 while excavating the excavation region 1; It proposes a two-row thumb pile earth block construction method using a soil nailing, including; a soil nail installation step for installing the soil nail 400 for the earth structure.

상기 흙막이 구조물 형성단계 및 소일 네일 설치단계는 상기 소일 네일(400)이 삽입되도록, 상기 제1열 엄지말뚝(100) 및 제2열 엄지말뚝(200)의 사이 영역에 천공 홀(410)을 형성하는 천공단계; 상기 흙막이 부재(10) 및 상기 천공 홀(410)에 소일 네일(400)을 설치하는 소일 네일(400) 설치단계; 상기 천공 홀(410)에 그라우 트를 주입하는 그라우팅 단계;를 포함하는 것이 바람직하다.In the step of forming the soil structure and installing the soil nail, the drilling hole 410 is formed in a region between the first row thumb pile 100 and the second row thumb pile 200 so that the soil nail 400 is inserted. Perforating step; Soil nail 400 installation step of installing the soil nail 400 in the earth member 10 and the drilling hole (410); And a grouting step of injecting grout into the drilling hole 410.

상기 흙막이 구조물 형성단계는 상기 제1열 엄지말뚝(100)과 제2열 엄지말뚝(200)의 사이에 내측을 향하는 경사면(2)이 형성되도록 굴착하는 경사면 형성단계를 더 포함하는 것이 바람직하다.The step of forming the retaining structure preferably further includes an inclined surface forming step of digging so that the inclined surface 2 facing inward is formed between the first row thumb pile 100 and the second row thumb pile 200.

상기 경사면 형성단계는 상기 제1열 엄지말뚝(100)과 제2열 엄지말뚝(200)의 사이 영역이 안정된 사면을 형성하는 한계 심도(L)까지 내측으로 경사지게 굴착함과 아울러, 상기 굴착영역(1)을 상기 한계 심도(L)까지 굴착하는 것이 바람직하다.The inclined surface forming step is to excavate inclined inward to the limit depth (L) to form a stable slope between the area between the first row thumb pile 100 and the second row thumb pile 200, the excavation area ( It is preferable to excavate 1) to the said limit depth L.

상기 경사면 형성단계는 상기 제1열 엄지말뚝(100)과 제2열 엄지말뚝(200)의 사이 영역 및 상기 굴착영역(1)을 1차 설계 심도(H1)까지 굴착하면서, 상기 제2열 엄지말뚝(200)의 사이에 제2열 흙막이 부재(20)를 설치하여 제2열 흙막이 구조물을 형성하는 제2열 흙막이 구조물 형성단계; 상기 1차 설계 심도(H1) 이하에서, 상기 제1열 엄지말뚝(100)과 제2열 엄지말뚝(200)의 사이 영역이 안정된 사면을 형성하는 2차 설계 심도(H2)까지 내측으로 경사지게 굴착함과 아울러, 상기 굴착영역(1)을 상기 2차 설계 심도(H2)까지 굴착하는 단계;를 포함하는 것이 바람직하다.The inclined surface forming step includes excavating an area between the first row thumb pile 100 and the second row thumb pile 200 and the excavation region 1 to a primary design depth H1, and the second row thumb. A second row mudstone structure forming step of installing a second row mudstone member 20 between the piles 200 to form a second row mudstone structure; Below the first design depth H1, the region between the first row thumb pile 100 and the second row thumb pile 200 is inclined inwardly to a secondary design depth H2 that forms a stable slope. In addition, the excavation region 1 is excavated to the secondary design depth H2.

상기 경사면 형성단계는 상기 제2열 흙막이 구조물에 대하여 제2열 소일 네일(500)을 설치하는 제2열 소일 네일 설치단계를 더 포함하는 것이 바람직하다.The inclined surface forming step may further include a second row soil nail installation step of installing a second row soil nail 500 with respect to the second row soil structure.

상기 제2열 소일 네일 설치단계는 상기 1차 설계 심도(H1) 내의 영역에서 상기 제2열 소일 네일(500)이 삽입되도록 천공 홀(510)을 형성하는 천공단계; 상기 제2열 흙막이 부재(20) 및 상기 천공 홀(510)에 제2열 소일 네일(500)을 설치하는 제2열 소일 네일 설치단계; 상기 천공 홀(510)에 그라우트를 주입하는 그라우팅 단 계;를 포함하는 것이 바람직하다.The second row soil nail installation step may include a drilling step of forming a drilling hole 510 to insert the second row soil nail 500 in a region within the first design depth H1; A second row soil nail installation step of installing a second row soil nail 500 on the second row soil member 20 and the drilling hole 510; And a grouting step of injecting grout into the drilling hole 510.

상기 연결단계는 전후방향 연결부재(310)에 의해 상기 제1열 엄지말뚝(100) 및 제2열 엄지말뚝(200)의 상부를 상호 연결하는 것이 바람직하다.In the connecting step, it is preferable to interconnect the upper portions of the first row thumb pile 100 and the second row thumb pile 200 by the front-rear connecting member 310.

상기 연결단계는 상기 제1열 엄지말뚝(100)을 제1열 좌우방향 연결부재(321)에 의해 상호 연결하는 단계; 상기 제2열 엄지말뚝(200)을 제2열 좌우방향 연결부재(322)에 의해 상호 연결하는 단계; 상기 제1열 좌우방향 연결부재(321)와 상기 제2열 좌우방향 연결부재(322)를 상기 전후방향 연결부재(310)에 의해 상호 연결하는 단계;를 포함하는 것이 바람직하다.The connecting step may include connecting the first row thumb pile 100 by a first row left and right connecting member 321; Interconnecting the second row of thumb piles by a second row of left and right connecting members 322; And connecting the first row left and right connecting members 321 and the second row left and right connecting members 322 to each other by the front and rear connecting members 310.

상기 제1열 좌우방향 연결부재(321) 및 제2열 좌우방향 연결부재(322)는 각각 상기 제1열 엄지말뚝(100) 및 제2열 엄지말뚝(200)의 상단에 설치하고, 상기 전후방향 연결부재(310)는 상기 제1열 좌우방향 연결부재(321) 및 제2열 좌우방향 연결부재(322)의 상부에 설치하는 것이 바람직하다.The first row of left and right connecting members 321 and the second row of left and right connecting members 322 are respectively installed on tops of the first row of thumb piles 100 and the second row of thumb piles 200, Directional connecting member 310 is preferably installed on the upper portion of the first row left and right connecting member 321 and the second row left and right connecting member 322.

본 발명은 고심도의 터파기 작업을 수행하는 경우에도 배후토사의 토압에 충분히 저항하도록 하고, 흙막이 구조물의 전체적인 변위의 발생을 억제할 수 있도록 하는 2열 엄지말뚝 흙막이 공법을 제시한다.The present invention proposes a two-row thumb pile clogging method to sufficiently resist the earth pressure of the rearing soil even when carrying out a high-depth excavation work, and to suppress the occurrence of the overall displacement of the clogging structure.

이하, 첨부도면을 참조하여 본 발명의 실시예에 관하여 상세히 설명한다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 2 이하에 도시된 바와 같이, 본 발명에 의한 엄지말뚝 흙막이 공법은 기본적으로 다음과 같은 공정에 의해 구성된다.As shown in Figure 2, the thumb pile earth block method according to the present invention is basically configured by the following process.

굴착영역(1)의 경계선을 따라 제1열 엄지말뚝(100)을 근입하고, 그 제1열 엄지말뚝(100)의 외측에 간격을 두고 제2열 엄지말뚝(200)을 근입한다(도 2).The first row thumb pile 100 is driven along the boundary line of the excavation area 1, and the second row thumb pile 200 is inserted at intervals outside the first row thumb pile 100 (FIG. 2). ).

제1열 엄지말뚝(100) 및 제2열 엄지말뚝(200)이 일체로 거동하도록 연결부재(300)에 의해 상호 연결한다(도 3).The first row thumb pile 100 and the second row thumb pile 200 are interconnected by the connection member 300 so as to be integrally formed (FIG. 3).

더욱 구체적으로는, 터파기의 진행에 의해 제1열 엄지말뚝(100)과 제2열 엄지말뚝(200)의 상부가 지반 위로 노출되면, 그 상단에 제1열 좌우방향 연결부재(321)와 제2열 좌우방향 연결부재(322)를 각각 설치하고, 제1열 좌우방향 연결부재(321) 및 제2열 좌우방향 연결부재(322)의 상부에 전후방향 연결부재(310)를 설치하는 것이 바람직하다.More specifically, when the upper portion of the first row thumb pile 100 and the second row thumb pile 200 is exposed to the ground by the progress of the trench, the first row of left and right connecting members 321 and Installing the second row of left and right connecting members 322, respectively, the first row of the left and right connecting members 321 and the second row of the left and right connecting members 322 to install the front and rear connecting members 310. desirable.

굴착영역(1)을 굴착하면서, 제1열 엄지말뚝(100)의 사이에 흙막이 부재(10)를 순차적으로 설치하여 흙막이 구조물을 형성한다(도 4,5,6).While excavating the excavation region 1, the earth block member 10 is sequentially installed between the first row thumb piles 100 to form the earth block structure (FIGS. 4, 5 and 6).

상기 흙막이 구조물에 대하여 소일 네일(400)을 설치한다(도 4,5,6).Soil nail 400 is installed with respect to the earth structure (FIGS. 4, 5, 6).

즉, 제1열 엄지말뚝(100)에 흙막이 부재(10)가 설치된 흙막이 구조물에 더하여, 외측에 제2열 엄지말뚝(200)을 근입하고 제1열 엄지말뚝(100)을 이와 일체로 거동하도록 설치하는 한편, 제1열 엄지말뚝(100)에 의한 흙막이 구조물에 소일 네일링에 의해 보강한 것이다.That is, in addition to the masonry structure in which the masonry member 10 is installed in the first column of the thumb pile 100, the second column of the thumb pile 200 is driven outside and the first column of the thumb pile 100 is behaved integrally therewith. On the other hand, it is reinforced by soil nailing to the earth structure of the first row thumb pile 100.

이는 종래의 일반적인 흙막이 공법에 비해 다음과 같은 장점을 갖는다.This has the following advantages over the conventional general clogging method.

첫째, 제2열 엄지말뚝(200) 및 소일 네일(400)의 조합에 의해, 배후토체의 전단파괴를 방지하는 사면의 억지말뚝 역할을 수행하므로, 흙막이 구조물의 변위 발생을 극소화할 수 있다.First, by the combination of the second row thumb pile 200 and the soil nail 400, it serves as an interference pile of the slope to prevent shear destruction of the rearing soil body, it is possible to minimize the occurrence of displacement of the earth structure.

둘째, 제1열 엄지말뚝(100), 제2열 엄지말뚝(200), 연결부재(300), 소일 네일(400)이 일체로 거동하여, 각 부재의 강도를 충분히 발휘할 수 있도록 하는바, 동일한 강도 및 양의 자재를 사용하면서도 고심도의 터파기가 가능하므로, 경제적이다.Second, the first row thumb pile 100, the second row thumb pile 200, the connecting member 300, the soy nail 400 is integrally behave, so that the strength of each member can be sufficiently exhibited, the same It is economical because high-depth destruction is possible while using strength and quantity of materials.

셋째, 고심도의 흙막이 공법을 수행하면서도, 스트럿과 같은 별도의 지보재가 필요 없으므로, 작업공간의 충분한 확보가 가능하다.Third, while performing a high-definition earthquake construction method, it is possible to secure a sufficient working space because no separate support material such as a strut is needed.

넷째, 소일 네일 만으로 시공하는 일반 흙막이 공법에 비해, 제2열 엄지말뚝(200)의 하중 부담으로 인하여 소일 네일의 근입장을 축소할 수 있으므로, 인접 구조물 등에 대한 영향을 최소화할 수 있다.Fourth, compared to the general earthquake construction method using only the soil nail, it is possible to reduce the near-entry of the soil nail due to the load of the second row thumb pile 200, it is possible to minimize the impact on the adjacent structure.

이하, 소일 네일(400)의 시공에 관한 구체적 실시예에 대하여 설명한다.Hereinafter, specific embodiments of the construction of the soil nail 400 will be described.

흙막이 구조물에 대하여 소일 네일(400)을 시공하는 방식은 다양할 것이나, 본 발명에 의한 공법의 경우 제1열 엄지말뚝(100)의 후방에 제2열 엄지말뚝(200)이 위치하므로, 이와의 간섭을 피하기 위해서는 제1열 엄지말뚝(100) 및 제2열 엄지말뚝(200)의 사이 영역에 천공 홀(410)을 형성하고 이에 대하여 소일 네일(400)을 시공하는 방식을 적용하는 것이 바람직하다.Soil nail 400 for the construction of the soil structure will be various, but in the case of the method according to the present invention because the second row of the pile 200 is located behind the first row of the pile 100, In order to avoid interference, it is preferable to apply a method of forming a drill hole 410 in the region between the first row thumb pile 100 and the second row thumb pile 200, and constructing the soil nail 400. .

도 4 내지 6을 참조하여 본 실시예를 설명하면 다음과 같다.The present embodiment will be described with reference to FIGS. 4 to 6.

소일 네일(400)이 삽입되도록, 제1열 엄지말뚝(100) 및 제2열 엄지말뚝(200)의 사이 영역에 천공 홀(410)을 형성한다.The hole nail 410 is formed in an area between the first row thumb pile 100 and the second row thumb pile 200 so that the small nail 400 is inserted therein.

흙막이 부재(10) 및 천공 홀(410)에 소일 네일(400)을 설치하고, 천공 홀(410)에 그라우트를 주입한다.Soil nail 400 is installed in the soil blocking member 10 and the drilling hole 410, and the grout is injected into the drilling hole 410.

흙막이 부재(10)에 대하여 소일 네일(400)의 두부를 정착하는 방법으로서, 흙막이 부재(10)에 정착공을 형성하고 소일 네일(400)을 이에 삽입하여 정착되는 방식, 흙막이 부재(10)의 가장자리부를 소일 네일(400)의 두부에 의해 지지하는 방식 기타 어떠한 방식을 사용하더라도 무방하다.As a method of fixing the head of the soil nail 400 with respect to the soil member 10, a fixing hole is formed in the soil member 10, and the soil nail 400 is inserted into the soil nail member 10 to fix the head of the soil nail member 10. The edge portion may be supported by the head of the sole nail 400 or any other method.

이로써, 소일 네일(400), 띠장(420), 제1열 엄지말뚝(100), 연결부재(300), 제2열 엄지말뚝(200)이 일체로 설치된 견고한 구조의 흙막이 구조물을 얻을 수 있다.As a result, the soil nail structure 400 having a solid structure in which the sole nail 400, the strip 420, the first row thumb pile 100, the connection member 300, and the second row thumb pile 200 are integrally installed may be obtained.

이하, 도 7 내지 9를 참조하여, 경사면(2)이 형성된 경우에 관한 실시예에 대하여 설명한다.Hereinafter, with reference to FIGS. 7-9, the Example regarding the case where the inclined surface 2 was formed is demonstrated.

위 흙막이 구조물 형성단계에서, 제1열 엄지말뚝(100)과 제2열 엄지말뚝(200)의 사이에 내측을 향하는 경사면(2)이 형성되도록 굴착하는 공정을 더 포함하는 것이 바람직하다.In the above structure structure forming step, it is preferable to further include a step of excavating so that the inclined surface (2) toward the inner side is formed between the first row thumb pile 100 and the second row thumb pile 200.

이와 같이 흙막이 공사를 수행하는 경우, 도 7 내지 9에 도시된 바와 같은 흙막이 구조물을 형성할 수 있는데, 이는 종래의 흙막이 구조물에 비해 제1열 엄지말뚝(100)과 제2열 엄지말뚝(200) 사이의 상부에 경사면(2)이 형성된다는 점에서 특징이 있다.In this way, when performing the earthquake construction, it is possible to form the earthquake structure as shown in Figures 7 to 9, which is the first row thumb pile 100 and the second row thumb pile 200 compared to the conventional soil structure It is characteristic in that the inclined surface 2 is formed in the upper part in between.

즉, 본 실시예에 의한 공법을 적용하는 경우, 종래의 구조에 비해 경사면(2) 상부 영역(S)에 해당하는 만큼의 토괴가 제거된 구조를 얻을 수 있으므로, 그만큼의 토압이 감소되어, 동일한 강도의 자재를 사용하는 경우에는 더욱 고심도의 흙막이 구조물을 얻을 수 있고, 동일한 심도의 흙막이 구조물을 시공하는 경우에는 자 재를 절약할 수 있다는 효과를 얻을 수 있는 것이다.That is, in the case of applying the method according to the present embodiment, a structure in which the ingots corresponding to the upper region S of the inclined surface 2 is removed as compared with the conventional structure can be obtained. In case of using the material of high strength, it is possible to obtain a high-definition earthquake structure, and when constructing a high-definition earthquake structure, the material can be saved.

위 경사면(2)의 형성작업을 더욱 구체적으로 설명하면, 제1열 엄지말뚝(100)과 제2열 엄지말뚝(200)의 사이 영역이 안정된 경사의 사면을 형성하는 한계 심도(L)까지 내측으로 경사지게 굴착하는 한편, 굴착영역(1)을 그 한계 심도(L)까지 굴착하는 것이 바람직하다(도 8).In more detail, the operation of forming the inclined surface 2, the area between the first row thumb pile 100 and the second row thumb pile 200 is formed to a limit depth L that forms a slope of a stable slope. It is preferable to excavate at an inclined angle, and to excavate the excavation area | region 1 to the limit depth L (FIG. 8).

한계 심도(L) 이후부터는, 제1열 엄지말뚝(100)에 흙막이 부재(10)를 설치하고, 소일 네일(400)을 설치하면서 설계 심도까지 굴착한다(도 9).After the limit depth L, the earth-block member 10 is installed in the first row thumb pile 100, and the soil nail 400 is installed to excavate to the design depth (FIG. 9).

도 10 내지 12는 본 발명에 2열 엄지말뚝 흙막이 공법의 또 다른 실시예를 도시한 것이다.10 to 12 show another embodiment of the two-row thumb pile earth construction method in the present invention.

이는 기본적인 공정은 위 실시예와 동일하나, 경사면 형성단계가 다소 상이하다.The basic process is the same as in the above embodiment, but the inclined surface forming step is slightly different.

본 실시예에 있어서의 경사면 형성단계는 다음과 같이 구성된다.The inclined surface forming step in this embodiment is constituted as follows.

제1열 엄지말뚝(100)과 제2열 엄지말뚝(200)의 사이 영역 및 굴착영역(1)을 1차 설계 심도(H1)까지 굴착하면서, 제2열 엄지말뚝(200)의 사이에 제2열 흙막이 부재(20)를 설치한다(도 10).Excavating the area between the first row thumb pile 100 and the second row thumb pile 200 and the excavation region 1 to the primary design depth H1, and between the second row thumb pile 200 A two-row mudguard member 20 is installed (FIG. 10).

1차 설계 심도(H1) 이하에서, 제1열 엄지말뚝(100)과 제2열 엄지말뚝(200)의 사이 영역이 안정된 사면을 형성하는 2차 설계 심도(H2)까지 내측으로 경사지게 굴착함과 아울러, 굴착영역(1)을 2차 설계 심도(H2)까지 굴착한다(도 11).Below the primary design depth H1, the area between the first row thumb pile 100 and the second row thumb pile 200 is inclined inwardly to a secondary design depth H2 that forms a stable slope and In addition, the excavation region 1 is excavated to the secondary design depth H2 (FIG. 11).

2차 설계 심도(H2) 이하에서는, 제1열 엄지말뚝(100)에 흙막이 부재(10)를 설치하고, 소일 네일(400)을 설치하면서 설계 심도까지 굴착한다(도 12).Below the 2nd design depth H2, the earth-block member 10 is installed in the 1st row | middle thumb pile 100, and it excavates to design depth while installing the soil nail 400 (FIG. 12).

이와 같이 흙막이 공사를 수행하는 경우, 도 12에 도시된 바와 같은 흙막이 구조물을 형성할 수 있는데, 이는 제1열 엄지말뚝(100)과 제2열 엄지말뚝(200) 사이의 상부 경사면(2) 위에 또 다른 제2열 흙막이 구조물이 형성된다는 특징이 있다.In this way, when performing the earthquake construction, it is possible to form the earthquake structure as shown in Figure 12, which is on the upper inclined surface (2) between the first row thumb pile 100 and the second row thumb pile 200 Another second row mudstone structure is formed.

이러한 제2열 흙막이 구조물은 제1열 엄지말뚝(100)과 제2열 엄지말뚝(200) 사이에 형성되는 경사면(2)을 안정시키는 역할을 하므로, 그 경사면(2)의 상부 영역(S)을 더욱 크게 형성할 수 있도록 한다.Since the second row soil structure serves to stabilize the inclined surface 2 formed between the first row thumb pile 100 and the second row thumb pile 200, the upper region S of the inclined surface 2. To make it larger.

따라서, 도 9의 실시예에 비해 더욱 많은 영역(S)의 토괴가 제거된 구조를 얻을 수 있으므로, 더욱 큰 토압 감소효과를 얻을 수 있고, 이로 인하여 동일한 강도의 자재를 사용하는 경우에는 더욱 고심도의 흙막이 구조물을 얻을 수 있고, 동일한 심도의 흙막이 구조물을 시공하는 경우에는 자재를 절약할 수 있다는 효과를 더욱 크게 얻을 수 있는 것이다.Therefore, compared with the embodiment of FIG. 9, since a structure in which more ingots in the region S are removed can be obtained, a greater earth pressure reduction effect can be obtained, and thus, a higher depth when using materials of the same strength is obtained. It is possible to obtain the structure of the earthquake, and when constructing the earthquake structure of the same depth, it is possible to obtain a greater effect of saving material.

도 13은 본 발명에 의한 흙막이 공법의 또 다른 실시예를 도시한 것이다.Figure 13 shows another embodiment of a retaining method according to the present invention.

이는 기본적인 공정은 위 실시예와 동일하나, 제2열 엄지말뚝(200)에 형성된 제2열 흙막이 구조물에 대해서도 제2열 소일 네일(500)을 설치한다는 점이 추가된 것이다.The basic process is the same as in the above embodiment, but it is added that the second row soil nail 500 is also installed for the second row soil structure formed on the second row thumb pile 200.

이러한 구성을 취하는 경우, 위 실시예서 제2열 흙막이 구조물의 구조적 안정성을 더욱 강화할 수 있어, 경사면(2)의 상부 영역(S)을 더욱 크게 형성할 수 있으므로, 더욱 큰 토압 감소효과를 얻을 수 있고, 이로 인하여 위 실시예에 의한 효과를 더욱 극대화하여 얻을 수 있다.In this case, the structural stability of the second row mudstone structure in the above embodiment can be further strengthened, so that the upper region S of the inclined surface 2 can be made larger, and thus a greater earth pressure reduction effect can be obtained. Therefore, it can be obtained by further maximizing the effect according to the above embodiment.

제2열 흙막이 구조물에 대하여 제2열 소일 네일(500)을 시공하는 경우에는, 위 제1열 엄지말뚝(100)에 시공하는 경우와 달리 배후에 간섭을 이루는 구조가 없으므로, 더욱 자유로운 시공이 가능하다.In the case of constructing the second row soil nail 500 for the second row soil structure, unlike the construction in the first row of the pile 100, there is no structure that interferes with the rear, so more free construction is possible. Do.

즉, 1차 설계 심도(H1) 내의 영역에서 제2열 소일 네일(500)이 삽입되도록 천공 홀(510)을 형성하고, 제2열 흙막이 부재(20) 및 천공 홀(510)에 제2열 소일 네일(500)을 설치한 후, 천공 홀(510)에 그라우트를 주입함으로써 제2열 소일 네일(500)을 시공이 이루어진다.That is, the perforation hole 510 is formed to insert the second row soil nail 500 in the region within the primary design depth H1, and the second row is formed in the second row soil member 20 and the perforation hole 510. After installing the soil nail 500, the second row soil nail 500 is constructed by injecting grout into the drilling hole 510.

이하, 도 3,4를 참조하여 위 연결단계에 적용되는 연결부재(300)의 실시예에 대하여 설명한다.Hereinafter, an embodiment of the connection member 300 applied to the above connection step will be described with reference to FIGS. 3 and 4.

연결부재(300)는 제1열 엄지말뚝(100) 및 제2열 엄지말뚝(200)이 상호 일체화하도록 연결하는 것이므로, 전후방향으로 이들을 연결하는 구조가 필요하고, 상술한 흙막이 부재 구조물의 상부두부 변위의 발생문제를 최소화하기 위해서는, 전후방향 연결부재(310)에 의해 제1열 엄지말뚝(100) 및 제2열 엄지말뚝(200) 상부를 상호 연결하는 구조를 취하는 것이 바람직하다.Since the connecting member 300 connects the first row thumb pile 100 and the second row thumb pile 200 to be integrated with each other, a structure for connecting them in the front-rear direction is required, and the upper head of the above-mentioned mud member structure In order to minimize the occurrence of the displacement, it is preferable to take a structure that interconnects the first row thumb pile 100 and the second row thumb pile 200 by the front and rear connecting member 310.

이러한 전후방향 연결부재(310)는 다수의 제1열 엄지말뚝(100) 및 제2열 엄지말뚝(200) 중 각각의 엄지말뚝(100,200)을 상호 연결하는 구조를 취할 수도 있으나, 흙막이 구조물 전체의 구조적 안정성 증대를 위해서는, 다음과 같이 전체가 일체화된 구성을 취하는 것이 더욱 바람직하다.The front and rear connecting member 310 may take a structure for interconnecting each of the thumb piles 100 and 200 of the plurality of first row thumb piles 100 and the second row thumb piles 200, In order to increase the structural stability, it is more preferable to take the structure integrated as follows.

즉, 제1열 엄지말뚝(100)을 제1열 좌우방향 연결부재(321)에 의해 상호 연결하고, 제2열 엄지말뚝(200)을 제2열 좌우방향 연결부재(322)에 의해 상호 연결한 후, 제1열 좌우방향 연결부재(321)와 제2열 좌우방향 연결부재(322)를 전후방향 연결부재(310)에 의해 상호 연결하는 것이 그것이다.That is, the first row thumb pile 100 is interconnected by the first row of left and right connecting members 321, and the second row thumb pile 200 is interconnected by the second row of left and right connecting members 322. After that, the first row of left and right connecting members 321 and the second row of left and right connecting members 322 are interconnected by the front and rear connecting members 310.

이러한 구조를 취하는 경우에도, 상술한 상부두부 변위의 발생문제를 해소하기 위해서는, 제1열 좌우방향 연결부재(321) 및 제2열 좌우방향 연결부재(322)는 각각 제1열 엄지말뚝(100) 및 제2열 엄지말뚝(200)의 상단에 설치하고, 전후방향 연결부재(310)는 제1열 좌우방향 연결부재(321) 및 제2열 좌우방향 연결부재(322)의 상부에 설치하는 구성을 취하는 것이 바람직하다.Even with this structure, in order to solve the above-mentioned problem of the upper head displacement, the first row of left and right connecting members 321 and the second row of left and right connecting members 322 are respectively arranged in the first row of the thumb pile 100. ) And the second row of thumb piles 200, and the front and rear connecting members 310 are installed on the first row of left and right connecting members 321 and the second row of left and right connecting members 322. It is desirable to take the configuration.

이상은 본 발명에 의해 구현될 수 있는 바람직한 실시예의 일부에 관하여 설명한 것에 불과하므로, 주지된 바와 같이 본 발명의 범위는 위의 실시예에 한정되어 해석되어서는 안 될 것이며, 위에서 설명된 본 발명의 기술적 사상과 그 근본을 함께 하는 기술적 사상은 모두 본 발명의 범위에 포함된다고 할 것이다.Since the above has been described only with respect to some of the preferred embodiments that can be implemented by the present invention, the scope of the present invention, as is well known, should not be construed as limited to the above embodiments, the present invention described above It will be said that both the technical idea and the technical idea which together with the base are included in the scope of the present invention.

도 1은 종래의 엄지말뚝 흙막이 구조물의 사시도.1 is a perspective view of a conventional thumb pile earth structure.

도 2 내지 13은 본 발명에 의한 2열 엄지말뚝 흙막이 공법을 설명하기 위한 도면으로서,2 to 13 is a view for explaining a two-row thumb pile earth construction method according to the present invention,

도 2 내지 4는 제1실시예의 공정도.2 to 4 are process diagrams of the first embodiment.

도 5는 제1실시예에 의한 흙막이 구조물의 단면도.5 is a cross-sectional view of the retaining structure according to the first embodiment.

도 6은 제1실시예에 의한 흙막이 구조물의 부분사시도.Figure 6 is a partial perspective view of the retaining structure according to the first embodiment.

도 7은 제2실시예에 의한 흙막이 구조물의 부분사시도.Figure 7 is a partial perspective view of the retaining structure according to the second embodiment.

도 8,9는 제2실시예의 공정도.8 and 9 are process diagrams of the second embodiment.

도 10 내지 12는 제3실시예의 공정도.10 to 12 are process diagrams of a third embodiment.

도 13은 제4실시예에 의한 흙막이 구조물의 단면도.13 is a cross-sectional view of the retaining structure according to the fourth embodiment.

**도면의 주요부분에 대한 부호의 설명**DESCRIPTION OF REFERENCE NUMERALS

1 : 굴착영역 2 : 경사면1: excavation area 2: slope

10 : 흙막이 부재 100 : 제1열 엄지말뚝10: earth block member 100: first row thumb pile

200 : 제2열 엄지말뚝 300 : 연결부재200: second row thumb pile 300: connection member

310 : 전후방향 연결부재 321 : 제1열 좌우방향 연결부재310: front and rear connecting member 321: first row left and right connecting member

322 : 제2열 좌우방향 연결부재 400 : 소일 네일322: second row left and right connecting member 400: Soil Nail

410 : 천공 홀 500 : 제2열 소일 네일410: punched hole 500: second row soil nail

510 : 천공 홀 L : 한계 심도510: hole punch L: limit depth

H1 : 1차 설계 심도 H2 : 2차 설계 심도H1: 1st design depth H2: 2nd design depth

Claims (10)

굴착영역(1)의 경계선을 따라 제1열 엄지말뚝(100)을 근입하는 제1열 엄지말뚝 근입단계;A first row thumb pile indentation step of indenting the first row thumb pile 100 along a boundary line of the excavation region 1; 상기 제1열 엄지말뚝(100)의 외측에 간격을 두고 제2열 엄지말뚝(200)을 근입하는 제2열 엄지말뚝 근입단계;A second row thumb pile indentation step of indenting the second row thumb pile 200 at intervals outside the first row thumb pile 100; 상기 제1열 엄지말뚝(100) 및 제2열 엄지말뚝(200)이 일체로 거동하도록 연결부재(300)에 의해 상호 연결하는 연결단계;A connection step of interconnecting the first row thumb pile 100 and the second row thumb pile 200 by a connection member 300 so as to be integrated with each other; 상기 굴착영역(1)을 굴착하면서, 상기 제1열 엄지말뚝(100)의 사이에 흙막이 부재(10)를 설치하여 흙막이 구조물을 형성하는 흙막이 구조물 형성단계;An earthquake structure forming step of forming an earthquake structure by installing the earthquake member 10 between the first row thumb piles 100 while excavating the excavation region 1; 상기 흙막이 구조물에 대하여 소일 네일(400)을 설치하는 소일 네일 설치단계;를 포함하고,Soil nail installation step for installing the soil nail 400 for the earthen structure; includes, 상기 흙막이 구조물 형성단계는The earth block structure forming step 상기 제1열 엄지말뚝(100)과 제2열 엄지말뚝(200)의 사이에 내측을 향하는 경사면(2)이 형성되도록 굴착하는 경사면 형성단계를 더 포함하며,Further comprising an inclined surface forming step of excavating such that the inclined surface (2) toward the inner side between the first row thumb pile 100 and the second row thumb pile 200 is formed, 상기 경사면 형성단계는The inclined surface forming step 상기 제1열 엄지말뚝(100)과 제2열 엄지말뚝(200)의 사이 영역 및 상기 굴착영역(1)을 1차 설계 심도(H1)까지 굴착하면서, 상기 제2열 엄지말뚝(200)의 사이에 제2열 흙막이 부재(20)를 설치하여 제2열 흙막이 구조물을 형성하는 제2열 흙막이 구조물 형성단계;While digging the area between the first row thumb pile 100 and the second row thumb pile 200 and the excavation region 1 to the first design depth H1, the second row thumb pile 200 A second row soil structure forming step of installing a second row soil member 20 between the second row soil structure; 상기 1차 설계 심도(H1) 이하에서, 상기 제1열 엄지말뚝(100)과 제2열 엄지말뚝(200)의 사이 영역이 안정된 사면을 형성하는 2차 설계 심도(H2)까지 내측으로 경사지게 굴착함과 아울러, 상기 굴착영역(1)을 상기 2차 설계 심도(H2)까지 굴착하는 단계;를 포함하고,Below the first design depth H1, the region between the first row thumb pile 100 and the second row thumb pile 200 is inclined inwardly to a secondary design depth H2 that forms a stable slope. And digging the excavation region 1 to the secondary design depth H2. 상기 경사면 형성단계는The inclined surface forming step 상기 제2열 흙막이 구조물에 대하여 제2열 소일 네일(500)을 설치하는 제2열 소일 네일 설치단계를 더 포함하는 것을 특징으로 하는 소일 네일링을 이용한 2열 엄지말뚝 흙막이 공법.The second row soil pile construction method using a soil nailing, characterized in that it further comprises a second row soil nail installation step for installing a second row soil nail 500 for the second row soil structure. 제1항에 있어서,The method of claim 1, 상기 흙막이 구조물 형성단계 및 소일 네일 설치단계는The earth block structure forming step and the Soil Nail installation step 상기 소일 네일(400)이 삽입되도록, 상기 제1열 엄지말뚝(100) 및 제2열 엄지말뚝(200)의 사이 영역에 천공 홀(410)을 형성하는 천공단계;A drilling step of forming a drilling hole 410 in a region between the first row thumb pile 100 and the second row thumb pile 200 so that the soil nail 400 is inserted; 상기 흙막이 부재(10) 및 상기 천공 홀(410)에 소일 네일(400)을 설치하는 소일 네일(400) 설치단계;Soil nail 400 installation step of installing the soil nail 400 in the earth member 10 and the drilling hole (410); 상기 천공 홀(410)에 그라우트를 주입하는 그라우팅 단계;를 포함하는 것을 특징으로 하는 소일 네일링을 이용한 2열 엄지말뚝 흙막이 공법.Grouting step of injecting grout into the drilling hole (410); Two-row thumb pile earthwork using a nail nailing method comprising a. 삭제delete 삭제delete 삭제delete 삭제delete 제1항에 있어서,The method of claim 1, 상기 제2열 소일 네일 설치단계는 The second row soil nail installation step 상기 1차 설계 심도(H1) 내의 영역에서 상기 제2열 소일 네일(500)이 삽입되도록 천공 홀(510)을 형성하는 천공단계;A perforation step of forming a perforation hole (510) to insert the second row soil nail (500) in an area within the first design depth (H1); 상기 제2열 흙막이 부재(20) 및 상기 천공 홀(510)에 제2열 소일 네일(500)을 설치하는 제2열 소일 네일 설치단계;A second row soil nail installation step of installing a second row soil nail 500 on the second row soil member 20 and the drilling hole 510; 상기 천공 홀(510)에 그라우트를 주입하는 그라우팅 단계;를 Grouting step of injecting grout into the drilling hole (510) 포함하는 것을 특징으로 하는 소일 네일링을 이용한 2열 엄지말뚝 흙막이 공법.Two-row thumb pile earthquake method using a soy nailing, characterized in that it comprises. 제1항, 제2항 또는 제7항 중 어느 한 항에 있어서,The method according to any one of claims 1, 2 or 7, 상기 연결단계는The connecting step 전후방향 연결부재(310)에 의해 상기 제1열 엄지말뚝(100) 및 제2열 엄지말뚝(200)의 상부를 상호 연결하는 것을 특징으로 하는 소일 네일링을 이용한 2열 엄지말뚝 흙막이 공법.A two-row thumb pile mudstone construction method using a soil nailing, characterized in that the interconnection of the upper portion of the first row thumb pile 100 and the second row thumb pile 200 by the front and rear connecting member 310. 제8항에 있어서,The method of claim 8, 상기 연결단계는The connecting step 상기 제1열 엄지말뚝(100)을 제1열 좌우방향 연결부재(321)에 의해 상호 연결하는 단계;Interconnecting the first row of thumb piles by a first row of left and right connecting members 321; 상기 제2열 엄지말뚝(200)을 제2열 좌우방향 연결부재(322)에 의해 상호 연결하는 단계;Interconnecting the second row of thumb piles by a second row of left and right connecting members 322; 상기 제1열 좌우방향 연결부재(321)와 상기 제2열 좌우방향 연결부재(322)를 상기 전후방향 연결부재(310)에 의해 상호 연결하는 단계;를Connecting the first row left and right connecting members 321 and the second row left and right connecting members 322 to each other by the front and rear connecting members 310; 포함하는 것을 특징으로 하는 소일 네일링을 이용한 2열 엄지말뚝 흙막이 공법.Two-row thumb pile earthquake method using a soy nailing, characterized in that it comprises. 제9항에 있어서,10. The method of claim 9, 상기 제1열 좌우방향 연결부재(321) 및 제2열 좌우방향 연결부재(322)는 각각 상기 제1열 엄지말뚝(100) 및 제2열 엄지말뚝(200)의 상단에 설치하고, The first row of left and right connecting members 321 and the second row of left and right connecting members 322 are respectively installed on tops of the first row of thumb piles 100 and the second row of thumb piles 200. 상기 전후방향 연결부재(310)는 상기 제1열 좌우방향 연결부재(321) 및 제2열 좌우방향 연결부재(322)의 상부에 설치하는 것을 특징으로 하는 소일 네일링을 이용한 2열 엄지말뚝 흙막이 공법.The front and rear direction connecting member 310 is a two-row thumb pile mud using a soil nailing, characterized in that installed on the top of the first row left and right connecting member 321 and the second row left and right connecting member 322. Method.
KR1020080016737A 2008-02-25 2008-02-25 Soil retaining method for two rows pile using soil nailing KR100971198B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020080016737A KR100971198B1 (en) 2008-02-25 2008-02-25 Soil retaining method for two rows pile using soil nailing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020080016737A KR100971198B1 (en) 2008-02-25 2008-02-25 Soil retaining method for two rows pile using soil nailing

Publications (2)

Publication Number Publication Date
KR20090091463A KR20090091463A (en) 2009-08-28
KR100971198B1 true KR100971198B1 (en) 2010-07-20

Family

ID=41208856

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020080016737A KR100971198B1 (en) 2008-02-25 2008-02-25 Soil retaining method for two rows pile using soil nailing

Country Status (1)

Country Link
KR (1) KR100971198B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111155534A (en) * 2020-01-18 2020-05-15 赵利 Anchor-shotcreting support construction method in foundation pit construction
KR20210020573A (en) * 2019-08-16 2021-02-24 (주)대안소일텍 Double line retaining wall self-reliance composite wall construction method for reinforcement pile wall

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103758132B (en) * 2014-01-08 2016-03-02 湖北中南勘察基础工程有限公司 The construction technology of the cantilever soldier pile retaining structure on slope is put in a kind of combination
CN103758133B (en) * 2014-01-13 2016-01-20 河海大学 A kind of method of deep soft soil foundation pit reinforcement
CN104831734B (en) * 2015-04-24 2016-08-17 正坚建设有限公司 A kind of deep basal pit building rotary churning pile Composition Soil Nailing Walls construction method
CN107268635A (en) * 2017-07-07 2017-10-20 中铁大桥局集团第二工程有限公司 Deep foundation pit supporting structure and construction method of the karst area adjacent to existing structure
CN108360558A (en) * 2018-01-09 2018-08-03 济南城建集团有限公司 Shallow-depth-excavation tunnel hole inner termination wall piled anchor one supporting construction and its construction technology
CN110528523A (en) * 2019-09-02 2019-12-03 湖南宏禹工程集团有限公司 A kind of highly permeable stratum building foundation pit horizontal grouting back cover construction method
CN113047318A (en) * 2021-04-13 2021-06-29 兰州理工大学 Slope prestressed pile-wall-anchor composite supporting structure and construction method
CN115404871B (en) * 2022-10-11 2023-07-25 中建八局第一建设有限公司 Construction method for connecting existing underground structure of deep foundation pit

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030041389A (en) * 2001-11-20 2003-05-27 채순기 Prepartion and application of porcine small intestine submucosa for tissue regeneration
KR200341389Y1 (en) 2003-11-13 2004-02-14 최영근 Reinforced structure of underground excavation construction and lasting wall type reinforced panel
KR100776373B1 (en) 2004-10-13 2007-11-16 코오롱건설주식회사 Soil retaining method using two rows pile

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030041389A (en) * 2001-11-20 2003-05-27 채순기 Prepartion and application of porcine small intestine submucosa for tissue regeneration
KR200341389Y1 (en) 2003-11-13 2004-02-14 최영근 Reinforced structure of underground excavation construction and lasting wall type reinforced panel
KR100776373B1 (en) 2004-10-13 2007-11-16 코오롱건설주식회사 Soil retaining method using two rows pile

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20210020573A (en) * 2019-08-16 2021-02-24 (주)대안소일텍 Double line retaining wall self-reliance composite wall construction method for reinforcement pile wall
KR102285635B1 (en) * 2019-08-16 2021-08-05 (주)대안소일텍 Double line retaining wall self-reliance composite wall construction method for reinforcement pile wall
CN111155534A (en) * 2020-01-18 2020-05-15 赵利 Anchor-shotcreting support construction method in foundation pit construction
CN111155534B (en) * 2020-01-18 2021-08-20 西北电力建设第一工程有限公司 Anchor-shotcreting support construction method in foundation pit construction

Also Published As

Publication number Publication date
KR20090091463A (en) 2009-08-28

Similar Documents

Publication Publication Date Title
KR100969996B1 (en) Soil retaining method for two rows pile using earth anchor
KR100971198B1 (en) Soil retaining method for two rows pile using soil nailing
KR100964995B1 (en) Soil retaining method for two rows pile using raker
KR100964993B1 (en) Soil retaining method for two rows pile
KR101379088B1 (en) Soil retaining structure of two rows pile and construction method for soil retaining structure
KR100776373B1 (en) Soil retaining method using two rows pile
KR100966573B1 (en) Soil retaining method for two rows pile using strut
JP6632028B2 (en) Concrete assembly retaining wall
KR100995503B1 (en) Soil retaining structure and method for two rows pile having passage
KR102195203B1 (en) Soil blocking method using horizontal Strut and slope Strut
KR100567853B1 (en) Structure for retaining wall
KR101597542B1 (en) Self-supported type earth retaining wall structure and construction method thereof
KR20120128345A (en) A Prevention Plate of the Ground Subsidence and Construction Method
KR101384586B1 (en) Underground structure and structure for protecting landslide using the same
KR101283663B1 (en) Method for digging two arch type tunnel
KR101218825B1 (en) Method of land-side protection wall using bracing
KR200369479Y1 (en) The land-side protection wall panel
JP5800765B2 (en) Rock fall prevention structure
KR102194381B1 (en) Pile for Earth self-retaining wall using double I beam
KR101465111B1 (en) Reinforcing structure for protecting landslide and construction method structure for protecting landslide using the same
KR101266161B1 (en) Retaining method using two rows pile and connector of two rows pile for the same
JP4529631B2 (en) Underground structure and construction method of underground structure
KR20200029077A (en) Pile for earth self-retaining wall using cast in place concrete pile with double I beam
KR101266160B1 (en) Retaining method using two rows pile and connector of two rows pile for the same
KR100732944B1 (en) Assembly for retaining wall

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130715

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20140522

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20150713

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20160713

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20170612

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20190704

Year of fee payment: 10