KR100945655B1 - A tight connection between steel pipe strut and center pile - Google Patents

A tight connection between steel pipe strut and center pile Download PDF

Info

Publication number
KR100945655B1
KR100945655B1 KR1020070134962A KR20070134962A KR100945655B1 KR 100945655 B1 KR100945655 B1 KR 100945655B1 KR 1020070134962 A KR1020070134962 A KR 1020070134962A KR 20070134962 A KR20070134962 A KR 20070134962A KR 100945655 B1 KR100945655 B1 KR 100945655B1
Authority
KR
South Korea
Prior art keywords
steel pipe
support
steel
brace
pile
Prior art date
Application number
KR1020070134962A
Other languages
Korean (ko)
Other versions
KR20090067339A (en
Inventor
나승민
이용주
황민오
김진국
이종구
Original Assignee
주식회사 포스코
재단법인 포항산업과학연구원
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 포스코, 재단법인 포항산업과학연구원 filed Critical 주식회사 포스코
Priority to KR1020070134962A priority Critical patent/KR100945655B1/en
Publication of KR20090067339A publication Critical patent/KR20090067339A/en
Application granted granted Critical
Publication of KR100945655B1 publication Critical patent/KR100945655B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • E02D17/083Shoring struts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2220/00Temporary installations or constructions
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Foundations (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

본 발명은 가설 굴착 흙막이벽에서 버팀보와 중간말뚝을 연결하는 상세에 관한 것으로서, 보다 상세하게는 강관 버팀보와 중간말뚝을 연결시키기 위하여 ㄷ형강이나 H형강 위에 강관과 곡률이 같은 지지대를 볼트로 연결하고 그 위에 강관 버팀보를 올려놓고 강판을 절곡하여 제작한 강판덮개를 씌워 강결함으로써 유격을 최소화하는 강결형 강관버팀보와 중간말뚝 연결구조를 제공하고자 한다. The present invention relates to the details of connecting the brace and the middle pile in the temporary excavation earthen wall, more specifically to connect the steel pipe and the support of the same curvature on the c-beam or H-beam with bolts to connect the steel pipe brace and the middle pile The steel pipe brace is placed on top of it, and the steel plate cover is made by bending the steel plate to be stiffened to provide a rigid steel pipe brace and intermediate pile connection structure to minimize the play.

본 발명의 강관버팀보와 중간말뚝 연결구조는 ㄷ형강 또는 H형강 위에 지지대를 설치하고, 상기 지지대 위에 강관 버팀보를 올려놓고, 강판덮개를 씌우는 형태인 것을 특징으로 한다. Steel pipe brace and the intermediate pile connection structure of the present invention is characterized in that the support is installed on the c-shaped steel or H-shaped steel, put the steel pipe brace on the support, and cover the steel plate cover.

강관 버팀보, 형강보, 연결부 Steel pipe brace, section steel beam, connection part

Description

강결형 강관버팀보와 중간말뚝 연결구조{A tight connection between steel pipe strut and center pile}A tight connection between steel pipe strut and center pile}

본 발명은 가설 굴착 흙막이벽에서 버팀보와 중간말뚝을 연결하는 연결구조에 관한 것으로서, 보다 상세하게는 강관 버팀보와 중간말뚝을 연결시키기 위하여 ㄷ형강이나 H형강 위에 강관과 곡률이 같은 지지대를 볼트로 연결하고 그 위에 강관 버팀보를 올려놓고 강판을 절곡하여 제작한 강판덮개를 씌워 강결함으로써 유격을 최소화하는 강결형 강관버팀보와 중간말뚝 연결구조를 제공하고자 한다. The present invention relates to a connection structure for connecting the brace and the middle pile in the temporary excavation earthen wall, more specifically, to connect the steel pipe and the support of the same curvature on the c-beam or H-beam with bolts to connect the steel pipe brace and the middle pile The steel pipe brace is placed on it, and the steel plate cover is made by bending the steel plate, and the steel plate is stiffened.

건설현장에서 지하에 건물의 기초, 지하실 또는 콘크리트 벽체를 축조하기 위하여 해당 지반을 굴토한 후, 굴토면이 토압에 의해 붕괴되는 것을 방지하기 위하여 흙막이 공사를 하게 된다.At the construction site, the ground is excavated to build the foundation, basement, or concrete wall in the basement, and then the earthen block is constructed to prevent the earth surface from collapse by earth pressure.

이러한 흙막이는 소정 간격으로 지반에 설치되는 H파일에 굴토면을 받치는 토류벽을 형성하고 H파일의 일측면에 상하로 일정 간격을 가지면서 수평되게 복수의 띠장이 설치되며, 서로 마주보는 띠장과 띠장 사이에 일정간격으로 수평되게 버 팀보가 설치된다.These mudguards are formed in the earth wall to support the pit soil surface in the H pile installed on the ground at predetermined intervals, and a plurality of bands are horizontally installed at regular intervals up and down on one side of the H pile, between the bands and the bands facing each other. Vertibo is installed horizontally at regular intervals.

이때, H파일 사이가 먼 경우에는 버팀보와 버팀보가 수평으로 연결되어 버팀보의 길이가 연장된다.At this time, when the H file is far apart, the brace and the brace is horizontally connected to extend the length of the brace.

그런데, 종래에는 버팀보로 H형강을 사용하고 H형강 버팀보의 연결시 H형강 버팀보에 기초판이나 이음판을 직접 용접하므로 체결이 불편하고 이음구조와 버팀보의 재활용에 문제가 있었다.However, in the related art, H-shaped steel is used as a brace, and when the H-beam brace is connected, the base plate or the joint plate is directly welded to the H-beam brace, so that the fastening is inconvenient and there is a problem in recycling the joint structure and the brace.

도 1은 종래의 강관 버팀보와 중간말뚝 연결부를 나타내는 도면이다. 1 is a view showing a conventional steel pipe brace and the intermediate pile connection.

종래의 강관 버팀보에서는 절곡된 U볼트를 이용하여 중간말뚝과 연결된 ㄷ형강이나 H형강에 볼트 연결하는데, 종래의 강관 버팀보와 중간말뚝 연결부 도면을 참조하면, 이는 2개의 U볼트만으로 접합되는 형식이므로 연결부에서 유격이 발생할 수 있으며, 버팀보에 예상치 못한 하중이 작용할 경우에 부분적으로 손상될 수 있는 문제점이 발생하였다. Conventional steel pipe braces are bolted to the c-beams or H-beams connected to the intermediate piles using bent U bolts. Referring to the drawings of the conventional steel pipe braces and the intermediate piles, these are connected to only two U bolts. There is a problem in that the play may occur, and it may be partially damaged when an unexpected load is applied to the brace.

본 발명에서는 강관 버팀보와 중간말뚝을 연결시키기 위하여 ㄷ형강이나 H형강 위에 강관과 곡률이 같은 지지대를 볼트로 연결하고, 그 위에 강관 버팀보를 올려놓고 강판을 절곡하여 제작한 덮개를 씌워 강결함으로써 유격을 최소화하고자 하는 목적이 있다. In the present invention, to connect the steel pipe brace and the middle pile by connecting the support of the same curvature with the steel pipe on the c-beam or H-beam with bolts, put the steel pipe brace on the cover and bending the steel plate to cover the steel plate The aim is to minimize this.

상기와 같은 목적을 달성하기 위한 기술적인 구성으로서 본 발명은, 강관버팀보와 중간말뚝 연결부에 있어서 ㄷ형강이나 H형강 위에 지지대를 설치하고 지지대 위에 강관 버팀보를 올려 놓고 강판덮개를 씌우는 형태의 강관버팀보와 중간말뚝 연결부를 포함하여 구성되는 것을 특징으로 한다. As a technical configuration for achieving the above object, the present invention, in the steel pipe brace and the middle pile connection portion, the support is installed on the c-beam or H-beam and put the steel pipe brace on the support and the steel pipe brace in the form of a steel plate cover Characterized in that it comprises a middle pile connection.

본 발명에 따르면, 강관버팀보와 중간말뚝 연결부를 통하여 버팀보의 시공 중 중간말뚝과의 연결부에서 유격을 최소화하여 전체적인 가설 버팀보 시스템의 안정성을 확보하고 예상치 못한 하중이 작용한 경우에도 손상을 방지할 수 있는 효과가 있다. According to the present invention, by securing the stability of the overall hypothesis support system by minimizing the play at the connection with the intermediate pile during the construction of the support through the steel pipe support and the intermediate pile connection and prevent damage even when an unexpected load is applied It works.

이하, 첨부된 도면에 따라 본 발명인 강결형 강관버팀보와 중간말뚝 연결구조에 대하여 설명한다. Hereinafter, with reference to the accompanying drawings, the present invention will be described for the steel-type steel pipe support and the intermediate pile connection structure.

도 2는 강결형 강관 버팀보와 중간말뚝 연결구조를 나타내는 도면이다. Figure 2 is a view showing the structure of the steel pipe brace and the intermediate pile connection.

상기 도 2에 도시된 바와 같이, ㄷ형강이나 H형강 위에 강관과 곡률이 같은 지지대(10)를 볼트 접합한 후 그 위에 강관 버팀보(20)를 설치하고 강판덮개(30)를 씌운 후 상기 강판덮개(30)와 상기 지지대(10)를 볼트 부재(55)로 연결하는 강결형 강관버팀보와 중간말뚝 연결부이다. As shown in FIG. 2, the bolt 10 is the same curvature 10 as the steel pipe on the c-shaped steel or the H-shaped steel, and then a steel pipe brace 20 is installed thereon and the steel plate cover 30 is covered with the steel plate. The 30 and the support 10 is a rigid steel pipe support and intermediate pile connecting portion connecting the bolt member 55.

즉, ㄷ 형강이나 H 형강위에 강관과 곡률이 같은 상기 지지대(10)를 볼트부재에 의하여 접합시키고, 그의 상부에 강관 버팀보(20)를 설치하여, 상기 강판덮개(30)를 씌운 후 상기 강판덮개(30)와 상기 지지대(10)를 볼트부재(35)로 연결하도록 하여, 강관 버팀보와 중간말뚝 연결부를 통하여 버팀보의 시공 중 중간말뚝과의 연결부에서의 유격을 최소화 하여 전체적인 가설 버팀보 시스템의 안정성을 확보하고, 예상치 못한 하중이 작용하는 경우에도 손상을 방지하도록 한다. That is, the support 10 having the same curvature as the steel pipe on the c-beam or H-beam is joined by a bolt member, and a steel pipe brace 20 is installed on the upper portion thereof, and the steel plate cover 30 is covered with the steel plate cover. 30 and the support 10 to be connected to the bolt member 35, through the steel pipe brace and the intermediate pile connection to minimize the gap in the connection with the middle pile during the construction of the brace to ensure the stability of the overall temporary brace system Secure and prevent damage in case of unexpected loads.

상기 본 발명에 따른 강관버팀보와 중간말뚝 연결구조는, ㄷ형강 또는 H형강 위에 지지대(10)를 설치하고, 상기 지지대 위에 강관 버팀보(20)를 올려 놓고, 강판덮개(30)를 씌우는 형태로서, 연결부에서의 유격을 최소화 하도록 한다. Steel pipe support and the intermediate pile connection structure according to the present invention, the support 10 is installed on the c-beam or H-beam, put the steel pipe support 20 on the support, and cover the steel plate 30, Minimize play at the connection.

이때, 상기 강관버팀보(20)와 동일한 곡률로 제작하여 강관과 밀착성이 좋으며, 상기 강관버팀보(20)와 ㄷ형강 또는 H형강에 볼트부재로 접합을 하고, 상기 지지대(10)와 상기 강판덮개(30)가 볼트부재(35)로 연결되도록 하여 가설 버팀보 시스템의 안정성을 확보하도록 한다. At this time, the steel tube is made of the same curvature as the support 20, and good adhesion with the steel pipe, the steel pipe support 20 and the c-shaped steel or H-shaped steel bonded to the bolt member, the support 10 and the steel plate ( 30) is connected to the bolt member 35 to ensure the stability of the temporary support system.

이상과 같이, 본 발명은 비록 한정된 실시 예와 도면에 의해 설명되었으나, 본 발명은 이것에 의해 한정되지 않으며, 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자에 의해, 본 발명의 기술사상과 아래에 기재될 특허청구범위의 균등범위 내에서 다양한 수정 및 변형이 가능함은 물론이다.As described above, although the present invention has been described by means of a limited embodiment and drawings, the present invention is not limited thereto, and should be understood by those of ordinary skill in the art to which the present invention pertains. Of course, various modifications and variations are possible within the scope of the claims to be described below.

도 1은 기존 강관 버팀보와 중간말뚝 연결부 도면.1 is a view of the existing steel pipe brace and the middle pile connection.

도 2는 본 발명에 따른 강결형 강관 버팀보와 중간말뚝 연결부 도면. Figure 2 is a view of the steel pipe brace and the intermediate pile connection according to the invention.

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

10 : 지지대 20 : 강관 버팀보10: support 20: steel pipe brace

30 : 강판덮개 30: steel plate cover

Claims (3)

강관버팀보와 중간말뚝 연결구조에 있어서,In the connection structure between the steel pipe brace and the middle pile, ㄷ형강 또는 H형강 위에 지지대(10)를 설치하고, 상기 지지대 위에 강관 버팀보(20)를 올려 놓고, 강판덮개(30)를 씌우는 형태인 것을 특징으로 하고, It is characterized in that the support 10 is installed on the c-shaped steel or H-shaped steel, the steel pipe brace 20 is placed on the support, and covers the steel plate cover 30, 상기 지지대(10)는, 상기 강관버팀보(20)와 동일한 곡률로 제작하여 강관과 밀착성이 좋으며 ㄷ형강 또는 H형강에 볼트부재로 접합하는 형태인 것을 특징으로 하는 강관버팀보와 중간말뚝 연결구조.The support 10 is made of the same curvature as the steel pipe support 20, the steel pipe support and the intermediate pile connection structure, characterized in that the adhesion to the steel pipe and the form of a bolt member to the c-shaped steel or H-shaped steel. 삭제delete 제 1항에 있어서,The method of claim 1, 상기 지지대(10)는, 상기 강관버팀보(20)를 밀착성 있게 감싸서 덮으며, 상기 지지대(10)와 상기 강판덮개(30)가 볼트부재(35)로 연결되는 것을 특징으로 하는 강관버팀보와 중간말뚝 연결구조.The support (10), the steel pipe support 20 is wrapped around the cover tightly, the support 10 and the steel plate cover 30 is characterized in that the steel pipe support and the middle pile is connected to the bolt member 35 Connection structure.
KR1020070134962A 2007-12-21 2007-12-21 A tight connection between steel pipe strut and center pile KR100945655B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020070134962A KR100945655B1 (en) 2007-12-21 2007-12-21 A tight connection between steel pipe strut and center pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020070134962A KR100945655B1 (en) 2007-12-21 2007-12-21 A tight connection between steel pipe strut and center pile

Publications (2)

Publication Number Publication Date
KR20090067339A KR20090067339A (en) 2009-06-25
KR100945655B1 true KR100945655B1 (en) 2010-03-04

Family

ID=40995071

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020070134962A KR100945655B1 (en) 2007-12-21 2007-12-21 A tight connection between steel pipe strut and center pile

Country Status (1)

Country Link
KR (1) KR100945655B1 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104099931A (en) * 2014-07-01 2014-10-15 中交一航局第一工程有限公司 Steel cylinder vibration sinking guide system
CN109629576B (en) * 2018-12-29 2021-02-09 浙江恒鸿建设有限公司 Suspension protection system for water supply pipe crossing foundation pit and construction method
KR102506533B1 (en) * 2021-03-08 2023-03-06 김희영 A fixing device for vibration and noise prevention of the ventilation duct
CN113431051B (en) * 2021-07-06 2023-06-16 中建八局第一建设有限公司 Inter-pile soil protection device and construction method thereof

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030096811A (en) * 2002-06-17 2003-12-31 염동신 Strut .omitted

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20030096811A (en) * 2002-06-17 2003-12-31 염동신 Strut .omitted

Also Published As

Publication number Publication date
KR20090067339A (en) 2009-06-25

Similar Documents

Publication Publication Date Title
KR100838736B1 (en) Connection and junction apparatus of steel pipe for strut
JP4698491B2 (en) Temporary closing method and structure of underwater structure
KR102071225B1 (en) Construction method of sheathing temporary facility using steel sheet pile
US20060070803A1 (en) Prestressed scaffolding system
KR100698878B1 (en) Y Type Connecting Structure of Steel Pipe Struts
KR100855098B1 (en) Strut structure as temporary system using a vertical truss at the end and the method thereof
KR100998253B1 (en) Temporary Structure For Land-Side Protection Wall
KR20090029993A (en) Underground structure and its construction method with retaining wall supported by rigid diaphragm
JP2018127834A (en) Foundation reinforcing structure, reinforced foundation structure, and method for reinforcing foundation
KR100945655B1 (en) A tight connection between steel pipe strut and center pile
KR100383268B1 (en) method for underground construction of building by using permanent structural member as strut for support retaining wall
KR100958426B1 (en) Fixing device for support beam
KR20100001516A (en) Joint structure for connecting slant supporter and square steel strut for temporary soil sheathing work
JP2006316495A (en) Foundation structure of bridge pier and its construction method
JP6477565B2 (en) Reinforcing structure and reinforcing method of existing steel sheet pile wall
KR101198286B1 (en) Non-wale strut system for top-down construction and top-down construction method thereby
KR100797185B1 (en) Construction method and the apparatus of a ground retaining structures or walls
KR20100126648A (en) Method of the bridge construction which connects the steel pipe pile of abutment substituion and the precast girder with a fixation
JP4798203B2 (en) Reinforcement structure and reinforcement method for existing foundation
KR101354171B1 (en) Friction welding connetion structure of strut
KR101545713B1 (en) Composite type cutoff wall of steel temporary facility and construction method of the same
KR101218825B1 (en) Method of land-side protection wall using bracing
KR100744972B1 (en) Earth of building land-side protection wall structure
CN218437087U (en) Foundation pit supporting structure
CN110792103A (en) Underground pipeline with integrated supporting piles and pipeline wall and construction method

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130225

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20140213

Year of fee payment: 5

FPAY Annual fee payment
FPAY Annual fee payment

Payment date: 20160224

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20170217

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20180209