KR100927578B1 - 쉬트파일을 이용한 교각기초 보강공법 - Google Patents
쉬트파일을 이용한 교각기초 보강공법 Download PDFInfo
- Publication number
- KR100927578B1 KR100927578B1 KR1020090048478A KR20090048478A KR100927578B1 KR 100927578 B1 KR100927578 B1 KR 100927578B1 KR 1020090048478 A KR1020090048478 A KR 1020090048478A KR 20090048478 A KR20090048478 A KR 20090048478A KR 100927578 B1 KR100927578 B1 KR 100927578B1
- Authority
- KR
- South Korea
- Prior art keywords
- sheet pile
- sheet
- pile
- guide
- foundation
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D22/00—Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/02—Piers; Abutments ; Protecting same against drifting ice
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/28—Stressing the soil or the foundation structure while forming foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/52—Submerged foundations, i.e. submerged in open water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/02—Sheet piles or sheet pile bulkheads
- E02D5/03—Prefabricated parts, e.g. composite sheet piles
- E02D5/04—Prefabricated parts, e.g. composite sheet piles made of steel
Abstract
Description
또한 쉬트파일(18)의 내측면 전체에 비닐시트(29)가 부착되어 있으므로 쉬트파일(18)을 원활하게 인발시킬 수 있다.
Claims (4)
- 교각기초(10) 주위에 각종 중장비(14)가 장착된 바지선(12)을 띄운 상태로 상기 바지선(12)의 중장비(14)를 이용하여 가이드파일(16)을 항타하는 단계(Ⅰ);상기 가이드파일(16)의 사이에 쉬트파일(18)을 항타하는 단계(Ⅱ);상기 쉬트파일(18) 내부의 물을 펌프(20)로 양수하는 단계(Ⅲ);상기 쉬트파일(18)의 내부를 소정의 깊이까지 크람쉘(22)로 터파기(24)를 실시하는 단계(Ⅳ);상기 쉬트파일(18)내 터파기(24)에 콘크리트(26)를 타설하는 단계(Ⅴ);상기 쉬트파일(18)을 인발하는 단계(Ⅵ)로 이루어짐을 특징으로 하는 쉬트파일을 이용한 교각기초 보강공법.
- 제 1항에 있어서,상기 쉬트파일(18)을 항타한 후, 가이드파일(16)을 인발하는 단계(Ⅱ-1)를 추가함을 특징으로 하는 쉬트파일을 이용한 교각기초 보강공법.
- 제 1항에 있어서,상기 크람쉘(22)로 터파기(24)를 실시한 후, 쉬트파일(18)의 내측면에 일정한 두께를 갖는 철판(28)을 설치하고, 상기 철판(28)이 부착된 쉬트파일(18)의 내측면 전체에 비닐시트(29)를 부착하는 단계(Ⅳ-1)를 추가함을 특징으로 하는 쉬트파일을 이용한 교각기초 보강공법.
- 제 1항에 있어서,상기 쉬트파일(18)을 인발한 후, 교각기초(10)에 세굴방지공(30)을 실시하는 단계(Ⅵ-1)를 추가함을 특징으로 하는 쉬트파일을 이용한 교각기초 보강공법.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020090048478A KR100927578B1 (ko) | 2009-06-02 | 2009-06-02 | 쉬트파일을 이용한 교각기초 보강공법 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020090048478A KR100927578B1 (ko) | 2009-06-02 | 2009-06-02 | 쉬트파일을 이용한 교각기초 보강공법 |
Publications (1)
Publication Number | Publication Date |
---|---|
KR100927578B1 true KR100927578B1 (ko) | 2009-11-23 |
Family
ID=41605209
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020090048478A KR100927578B1 (ko) | 2009-06-02 | 2009-06-02 | 쉬트파일을 이용한 교각기초 보강공법 |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR100927578B1 (ko) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110485313A (zh) * | 2019-08-08 | 2019-11-22 | 中国海洋大学 | 桥墩流空区加固方法 |
CN110886248A (zh) * | 2019-12-17 | 2020-03-17 | 中交路桥建设有限公司 | 用于既有桥台拼宽施工临时支护的施工方法 |
KR102201969B1 (ko) | 2020-02-13 | 2021-01-12 | 김석곤 | 간극 보강 장치 및 그의 방법 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20010038534A (ko) * | 1999-10-26 | 2001-05-15 | 장재근 | 교각 보수 방법 |
KR20010076800A (ko) * | 2000-01-28 | 2001-08-16 | 김길용 | 교량기초 보수공법 |
KR200232748Y1 (ko) | 2001-02-02 | 2001-10-26 | (주) 정도엔지니어링 | 교량의 구조물 기초 보수공사용 강재 케이슨 |
KR100665563B1 (ko) | 2006-09-20 | 2007-01-09 | 채상훈 | 교각 보수장치 및 그를 이용한 보수공법 |
-
2009
- 2009-06-02 KR KR1020090048478A patent/KR100927578B1/ko active IP Right Grant
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20010038534A (ko) * | 1999-10-26 | 2001-05-15 | 장재근 | 교각 보수 방법 |
KR20010076800A (ko) * | 2000-01-28 | 2001-08-16 | 김길용 | 교량기초 보수공법 |
KR200232748Y1 (ko) | 2001-02-02 | 2001-10-26 | (주) 정도엔지니어링 | 교량의 구조물 기초 보수공사용 강재 케이슨 |
KR100665563B1 (ko) | 2006-09-20 | 2007-01-09 | 채상훈 | 교각 보수장치 및 그를 이용한 보수공법 |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110485313A (zh) * | 2019-08-08 | 2019-11-22 | 中国海洋大学 | 桥墩流空区加固方法 |
CN110886248A (zh) * | 2019-12-17 | 2020-03-17 | 中交路桥建设有限公司 | 用于既有桥台拼宽施工临时支护的施工方法 |
KR102201969B1 (ko) | 2020-02-13 | 2021-01-12 | 김석곤 | 간극 보강 장치 및 그의 방법 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
EP3118374A1 (en) | Hollow cylindrical pier for fixing offshore platform structure to bed and method of installing and constructing same | |
CN110359476B (zh) | 一种钢板桩围堰内支撑与钻孔桩钢护筒安装用施工平台的施工方法 | |
CN105350526B (zh) | 钢平台的搭设方法 | |
KR100927578B1 (ko) | 쉬트파일을 이용한 교각기초 보강공법 | |
CN101289867B (zh) | 水上基坑拆除施工工艺 | |
CN101289861B (zh) | 坞口水上基坑桩基施工方法 | |
JP5390044B1 (ja) | 水中における土留め工法 | |
CN108951431A (zh) | 桥梁用预制混凝土围堰及桥墩建造工艺 | |
KR100914650B1 (ko) | 교각 보강용 강재 케이슨을 이용한 우물통 시공방법 | |
CN110130342B (zh) | 一种水下钢筋混凝土预制板桩施工的打桩设备及打桩方法 | |
JPH07216844A (ja) | 水中骨組構造物とその施工方法 | |
KR100450309B1 (ko) | 말뚝 기초를 이용한 방파제 | |
JP4845537B2 (ja) | 水中構造物用杭打ち工法 | |
KR100961181B1 (ko) | 교각 보강용 강재 케이슨을 이용한 우물통 시공방법 | |
JP6241167B2 (ja) | 桟橋の耐震補強方法 | |
Swatek Jr | Cellular cofferdam design and practice | |
CN111155540A (zh) | 一种双壁钢围堰施工方法 | |
CN111335313B (zh) | 一种码头桩沉桩工艺 | |
CN213596935U (zh) | 一种长江侧靠船墩钢膜护筒 | |
CN113136889B (zh) | 一种海上箱式预制承台的施工方法 | |
CN110861754B (zh) | 抛投船链条沉放液压锁定装置和方法 | |
CN217174859U (zh) | 一种拉锚板桩护岸导梁与拉锚头浇筑连结结构 | |
CN210562232U (zh) | 一种用于围堰的锁口止水装置及围堰 | |
CN209023077U (zh) | 挖机水上施工用装配式作业平台 | |
CN212316961U (zh) | 水下承台的围堰结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
A302 | Request for accelerated examination | ||
E902 | Notification of reason for refusal | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20121105 Year of fee payment: 4 |
|
FPAY | Annual fee payment |
Payment date: 20131030 Year of fee payment: 5 |
|
FPAY | Annual fee payment |
Payment date: 20141106 Year of fee payment: 6 |
|
FPAY | Annual fee payment |
Payment date: 20151105 Year of fee payment: 7 |
|
FPAY | Annual fee payment |
Payment date: 20161109 Year of fee payment: 8 |
|
FPAY | Annual fee payment |
Payment date: 20171107 Year of fee payment: 9 |
|
FPAY | Annual fee payment |
Payment date: 20181105 Year of fee payment: 10 |
|
FPAY | Annual fee payment |
Payment date: 20191106 Year of fee payment: 11 |