KR100767093B1 - Structure lifting method using pile adjustable the length - Google Patents

Structure lifting method using pile adjustable the length Download PDF

Info

Publication number
KR100767093B1
KR100767093B1 KR1020070012633A KR20070012633A KR100767093B1 KR 100767093 B1 KR100767093 B1 KR 100767093B1 KR 1020070012633 A KR1020070012633 A KR 1020070012633A KR 20070012633 A KR20070012633 A KR 20070012633A KR 100767093 B1 KR100767093 B1 KR 100767093B1
Authority
KR
South Korea
Prior art keywords
press
pipe
guide tube
fit
indentation
Prior art date
Application number
KR1020070012633A
Other languages
Korean (ko)
Inventor
정언섭
Original Assignee
정언섭
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 정언섭 filed Critical 정언섭
Priority to KR1020070012633A priority Critical patent/KR100767093B1/en
Application granted granted Critical
Publication of KR100767093B1 publication Critical patent/KR100767093B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D35/00Straightening, lifting, or lowering of foundation structures or of constructions erected on foundations
    • E02D35/005Lowering or lifting of foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D37/00Repair of damaged foundations or foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/52Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/64Repairing piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • E02D7/20Placing by pressure or pulling power
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/003Injection of material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

A method for lifting a structure by using a pile capable of adjusting depth is provided to pull the subsiding structure efficiently by forming a bulb in the lower part of the steel pipe pile, and to construct the steel pipe pile easily by adjusting the depth of the pile with a connecting pipe. A pile(400) is driven into the ground by connecting plural press pipes, and a connecting pipe(410) is installed between the press pipes. The connecting pipe comprises a socket connecting unit(411) fitted to the press pipe, and a body(412) formed as large as the diameter of the press pipe. The depth of the press pipe is adjusted by regulating the length of the body, and a second fixing unit hole is formed around a first guide pipe hole to space the press pipe inserted to a guide pipe from a fixing unit. A horizontal fixing unit is formed in the lower end of a vertical reinforcing bar(221), inserted to the first and second holes and formed integrally with a structure by injecting grouting material(130) including non-shrinkage mortar into the second hole.

Description

깊이 조절이 가능한 압입체를 이용한 구조물 인상공법{STRUCTURE LIFTING METHOD USING PILE ADJUSTABLE THE LENGTH}Structural LIFTING METHOD USING PILE ADJUSTABLE THE LENGTH

도 1은 종래 압입유도체, 압입체 및 상판지지체가 설치된 상태를 사시도로 도시한 것이다.1 is a perspective view showing a state in which the conventional indentation guide, indentation body and the upper plate support is installed.

도 2a, 도 2b, 도 2c, 도 2d 및 도 2e는 본 발명에 따른 구조물 인상방법을 순서대로 도시한 것이다.Figures 2a, 2b, 2c, 2d and 2e shows the structure pulling method according to the invention in order.

도 3a 및 도 3b는 본 발명의 다른 고정구에 따른 구조물 인상방법을 도시한 것이다.3A and 3B illustrate a structure lifting method according to another fastener of the present invention.

도 4는 본 발명에 따른 구근형성을 이용한 구조물 인상방법을 도시한 것이다.Figure 4 illustrates a structure lifting method using the bulb formation according to the present invention.

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

100:구조물 110:구조물 저판100: structure 110: structure bottom plate

120:천공홀 121:천공홀 1120: drilled hole 121: drilled hole 1

122:천공홀 2 200:세팅부재122: drilling hole 2 200: setting member

210:가이드관 220:고정구210: Guide tube 220: Fixture

221:수직철근 222:수평고정구221: vertical rebar 222: horizontal fixture

223:수평철근 230:유압실린더223: horizontal rebar 230: hydraulic cylinder

240:유압펌프 300:상단지지체240: hydraulic pump 300: upper support

310:상판 320:연결너트310: top 320: connection nut

330:지지철근 340:체결너트330: Reinforcing bar 340: Tightening nut

400:압입체 410:연결관400: indent 410: connector

411:소켓연결부 412:몸통부411: socket connection 412: body

420:철근조립체 430:충진재420: Rebar assembly 430: Filler

440:패킹재 450:주입관440: packing material 450: injection pipe

500:압입수단 600:인상지지판500: indentation means 600: impression support plate

610:지지판 620:너트610: support plate 620: nut

700:지반700: ground

본 발명은 깊이 조절이 가능한 압입체를 이용한 구조물 인상공법에 관한 것이다. 더욱 구체적으로 아파트 지하실, 공장과 같이 폐쇄되고 제한된 공간을 가진 구조물 내부에서 파일과 같은 압입체, 상판지지체 및 인상지지판을 임의로 설치하여 침하된 구조물을 인상하고, 필요 시 추후 재 인상 시킬 수 있도록 하되 압입체의 압입 깊이를 조정할 수 있는 구조물 인상공법에 관한 것이다.The present invention relates to a structure lifting method using a press-fitting body that can be adjusted in depth. More specifically, indented structures such as piles, upper plate supports, and impression support plates are installed arbitrarily inside structures that are closed and confined spaces such as apartment basements and factories, so that the sinked structures can be raised and, if necessary, repressed later. It relates to a structure impression method that can adjust the depth of the indentation of the three-dimensional.

시공된 구조물에 침하가 발생되거나 기초보강을 하여야 하는 경우 지금까지는 대부분 지반에 시멘트 액이나 모르터 등을 주입하는 방법을 사용하여 왔으나, 시공결과에 대한 품질확보 및 평가가 곤란하고, 주입방법에 의한 지금까지의 기술은 추가침하의 억제가 대부분이었으며, 구조물의 기초보강이나 인상이 가능하다 할지라도 연약지반 층이 두껍거나, 인상하여야 할 높이가 큰 경우에는 과다한 비용이 소요된다는 문제점이 있었다.In case of subsidence or reinforcement of the constructed structure, most of the methods have been used to inject cement solution or mortar into the ground.However, it is difficult to secure and evaluate the quality of the construction results. Most of the techniques up to this point were suppression of additional settlement, and even if the foundation reinforcement or raising of the structure was possible, there was a problem that excessive cost was required when the soft ground layer was thick or the height to be raised was large.

이에 반하여 강관파일 압입에 의한 방법은 무진동 무소음의 친환경방법으로 강관파일을 소요의 경질지층까지 압입한 후 압입한 파일에 의하여 침하된 구조물의 인상과 기초보강이 동시에 이루어질 뿐만 아니라 파일선단 지층의 내력 및 압입파일의 내력도 정확하게 파악되는 등 기존의 제반 문제점들을 해결할 수 있는 공법이라 할 수 있다.On the contrary, the steel pipe pile press-in method is a vibration-free, noise-free, environmentally friendly method that presses the steel pipe pile up to the required hard strata, and simultaneously raises and strengthens the structure settled by the pressed pile. It can be said that it is a method that can solve all the existing problems, such as the accuracy of the indentation pile is accurately understood.

하지만 지중에 위치한 구조물이 침하되었을 경우, 개방되지 않은 제한된 폐쇄공간에서 위와 같은 강관파일 압입에 의한 방법을 적용함에 있어서는 파일압입을 위한 지지체 및 인상을 위한 구체적인 공법개발이 없었고, 또한 추후 구조물이 재침하가 발생될 경우 다시 구조물 재인상이 용이한 공법개발의 필요성이 대두되었다.However, when the underground structures were submerged, there was no specific method for supporting and pulling the pile in the application of the steel pipe pile press-fit method in the confined space that was not opened. In the event of a fire, a need arises for the development of a process that is easy to re-raise the structure.

이에 침하가 발생된 구조물에 대한 기초 보강 및 인상을 통해서 구조물의 기능을 회복시킬 수 있도록 하되, 추후 재인상이 가능한 구조물 인상 및 재인상이 가능한 공법이 종래 개발된 바 있다. 이에 이를 구체적으로 살펴보면 도 1과 같다.In order to restore the function of the structure by reinforcing and raising the foundation for the structure is settled, the construction method that can be raised and re-raised in the future can be re-raised. This will be described in detail with reference to FIG. 1.

먼저, 압입체(40)를 구조물(10)의 하부 지반(60)에 압입시키기 위한 초기 세팅 및 후술되는 상단지지체(30)와 함께 반력수단으로서 설치되는 세팅부재(20)를 미리 준비하게 된다.First, the setting member 20 which is installed as a reaction means together with the initial setting for press-fitting the indenter 40 into the lower ground 60 of the structure 10 and the upper support 30 to be described below is prepared in advance.

상기 세팅부재(20)는 원형 강관과 같은 가이드관(21)과 상기 가이드관(21) 주위를 감싸도록 철근망(22)으로 구성되어 있다.The setting member 20 is composed of a guide tube 21, such as a circular steel pipe and a reinforcing bar 22 to surround the guide tube 21.

이때 가이드관(21)의 길이는 적어도 구조물(10)의 두께보다 더 길게 형성되도록 하되, 가이드관(21)의 직경은 압입체(40)가 삽입될 수 있을 정도의 직경을 가지도록 한다.At this time, the length of the guide tube 21 is to be formed at least longer than the thickness of the structure 10, the diameter of the guide tube 21 to have a diameter enough to be inserted into the indenter (40).

이러한 가이드관(21)의 주위에는 가이드관(21)과 용접 등의 방법으로 일체화된 철근망(22)이 장착된다. Around the guide tube 21, the reinforcing bar 22 integrated with the guide tube 21 and the welding method is mounted.

이때 철근망(22)은 가이드관(21) 전체를 상하로 이격되어 장착되는 다수의 수평 원형철근(22b) 및 상기 수평 원형철근(22b)을 서로 상하로 결속시켜주는 다수의 수직철근(22a)을 포함하여 형성되며, At this time, the reinforcing bar 22 is a plurality of vertical reinforcing bars (22a) to bind the plurality of horizontal circular reinforcing bars (22b) and the horizontal circular reinforcing bars (22b) are vertically spaced up and down the whole guide tube 21 It is formed to include,

상기 수직철근(22a)은 서로 이격되어 가이드관(21)을 감싸도록 설치되면서, 그 하단은 가이드관(21) 하단부보다 연장된 상태에서 바깥쪽으로 구부려 형성되도록 하고, 그 상단은 가이드관(21) 상단부보다 연장되어 상방 돌출되도록 형성된다.The vertical reinforcing bar (22a) is spaced apart from each other is installed to surround the guide tube 21, the lower end is formed to be bent outward in an extended state than the lower end of the guide tube 21, the upper end of the guide tube 21 It extends from the upper end portion and is formed to protrude upward.

이러한 세팅부재(20)는 공장 또는 현장 부근에서 미리 다수를 제작함으로서 구조물(10) 인상에 즉각 이용될 수 있도록 하게 된다.The setting member 20 is to be used immediately to raise the structure 10 by manufacturing a large number in advance near the factory or the site.

위와 같이 제작된 세팅부재(20)를 설치하기 위하여 먼저 구조물(10) 저판(11) 표면을 일부 절취한 후, 천공장비를 이용하여 구조물 저판(11)에 천공홀(12)을 형성시키게 된다.In order to install the setting member 20 manufactured as described above, first, a part of the surface of the bottom plate 11 is cut off, and then a perforation hole 12 is formed in the bottom plate 11 by using a drilling equipment.

이때, 천공홀(12)은 상부의 직경이 좀 더 크고 연장된 하부의 직경은 좀 더 크게 형성되도록 하여, 후술되는 상단지지체(30)를 세팅부재(20)에 설치할 수 있는 공간이 형성되도록 하게 된다.At this time, the hole 12 is larger in diameter and the upper portion of the lower diameter is formed to be larger, so that the space for installing the upper support 30 to be described later to the setting member 20 is formed do.

이에 세팅부재(20)를 천공홀(12) 내측에 삽입시키게 되며, The setting member 20 is inserted into the drilling hole 12,

상기 세팅부재(20)의 철근망(22)이 상기 돌출부재(13)에 걸쳐지도록 한 상태에서 용접 등의 방법으로 세팅부재(20)와 돌출부재(13)가 최종 일체화되도록 한다.The setting member 20 and the protruding member 13 are finally integrated by welding or the like in a state where the reinforcing bar 22 of the setting member 20 spans the protruding member 13.

이에 천공홀(12)의 직경은 상기 세팅부재(20)와 돌출부재(13)를 서로 일체화시킬 수 있는 공간이 확보되도록 해야 한다.The diameter of the drilling hole 12 should be such that a space for integrating the setting member 20 and the protruding member 13 to each other is secured.

다음으로는 세팅부재(20)와 구조물(10)이 서로 일체화되도록 하기 위하여 천공홀(12) 내부와 구조물(10) 저판(11) 일부에 미 도시된 모르타르가 충진되도록 하여, 모르타르가 경화되면 세팅부재(20)가 구조물(10)과 서로 일체화되도록 한다.Next, in order for the setting member 20 and the structure 10 to be integrated with each other, the mortar, which is not shown, is filled in the inner part of the hole 12 and the bottom plate 11 of the structure 10, and the mortar is cured. Allow member 20 to be integral with structure 10.

이때, 세팅부재(20)를 구성하는 수직철근(22a)의 구부러진 하단은 일종의 고정수단으로서 스토퍼(STOPPER) 역할을 하여 세팅부재(20)가 인발되려고 할 때 인발을 저항할 수 있는 구성으로 작용하게 된다.At this time, the bent lower end of the vertical reinforcing bar (22a) constituting the setting member 20 serves as a stopper (STOPPER) as a kind of fixing means to act as a configuration capable of resisting the drawing when the setting member 20 is to be drawn out. do.

다음으로는 압입체(40)를 상기 세팅부재(20)의 가이드관(21) 내부에 삽입시켜 세팅하게 된다. Next, the press-fit body 40 is inserted into the guide tube 21 of the setting member 20 to be set.

이때 상기 압입체(40)는 구조용 파일로서 제작된 콘크리트 파일을 이용한다.At this time, the press-fit body 40 uses a concrete pile produced as a structural pile.

다음으로는 세팅부재(20)에 본 발명의 상단지지체(30)를 장착시키게 된다.Next, the upper support 30 of the present invention is mounted on the setting member 20.

이때 상기 상단지지체(30)는 원형의 상판(31) 및 상기 상판을 관통한 일단부가 너트(32)에 의하여 상판(31)에 체결되고, 타단이 하부로 연장되도록 형성된 지지철근(33)으로 구비된다.At this time, the upper support 30 is provided with a support bar 33 formed so that the circular upper plate 31 and one end penetrating the upper plate is fastened to the upper plate 31 by a nut 32 and the other end extends downward. do.

즉, 압입체(40)로서 콘크리트 파일을 세팅부재(20)에 초기 세팅한 상태에서, 압입체 두부보강판(34) 상면에 소정의 용량을 가진 유압실린더와 같은 압입수단(50)을 설치한다.That is, in the state where the concrete pile is initially set in the setting member 20 as the indenting body 40, the indenting means 50, such as a hydraulic cylinder having a predetermined capacity, is installed on the upper surface of the indenting body reinforcing plate 34. .

다음으로는 세팅부재(20)를 구성하는 수직철근(22a)의 상단을 상단지지체(30)의 지지철근(33)과 체결되도록 하며, 이러한 체결은 연결너트(35)에 의하여 간단하게 기계적으로 체결되도록 하게 된다.Next, the upper end of the vertical reinforcing bar (22a) constituting the setting member 20 is to be fastened with the supporting bar (33) of the upper support (30), this fastening is simply mechanically fastened by the connecting nut (35) Will be done.

다음으로는 압압체(40)가 구조물 하부 지반(60)에 압입되도록 한다.Next, the press body 40 is pressed into the lower ground structure 60.

즉, 유압실린더와 같은 압입수단(50)의 작동을 구조물(10)과 일체화된 세팅부재(20), 상기 세팅부재(20)와 연결, 설치된 상단지지체(30)가 구속함으로서 그 반력으로 압입체(40)인 콘크리트 파일이 천공홀(12) 하부 지반(60)에 압입되도록 하는 것이다.That is, the operation of the press-fit means 50 such as the hydraulic cylinder is connected to the setting member 20 and the setting member 20 and the setting member 20 integrated with the structure 10, and the upper support body 30 is installed to restrain the press-in body by the reaction force. The concrete pile 40 is to be press-fitted into the lower ground 60 of the drilling hole 12.

이에 다수의 콘크리트 파일을 소정의 깊이까지 압입시키면서 최종 콘크리트 파일의 선단이 구조물 하부 지반의 견질지지층까지 다다르도록 한다.In order to press the plurality of concrete piles to a predetermined depth to the end of the final concrete pile to reach the hard support layer of the ground under the structure.

위와 같이 견질지지층에 그 선단이 압입된 압입체(40)에 추가적인 압입력이 지속적으로 전달되면, 압입체(40)는 견질지지층에 더 이상 압입되지는 않기 때문에, 그 반력의 형태로 구조물(10)이 압입체(40)에 의하여 인상될 수 있게 되는 것이다.If additional pressurization is continuously transmitted to the indenter 40 in which the tip is press-fitted to the hard support layer as described above, the indenter 40 is no longer press-fitted to the hard support layer, and thus the structure 10 in the form of reaction force. ) Can be raised by the indenter (40).

결국, 다수의 압입체(40)를 하부 지반(60)에 모두 압입 완료 시키게 되면, 침하된 구조물(10)을 원하는 정도까지 최종 인상시킬 수 있게 된다. 이러한 최종 구조물 인상이 확인되면, 압입수단(50)의 작동을 멈추도록 한다.As a result, when the entire indentation body 40 is pressed in the lower ground 60 all completed, it is possible to finally raise the settled structure 10 to the desired degree. When the final structure impression is confirmed, stop the operation of the indentation means (50).

하지만, 상기 압입체(40)를 가이드관(21)에 세팅하고 압입시키는 과정에서 세팅부재(20)를 구성하는 철근망(22)이 가이드관(21)과 너무 근접되어 있어 가이드관에 삽입되는 압입체 설치에 있어 시공성을 떨어뜨린다는 문제점이 지적되었으며,However, in the process of setting and press-fitting the press fitting body 40 to the guide tube 21, the reinforcing bar 22 constituting the setting member 20 is too close to the guide tube 21 and inserted into the guide tube. It has been pointed out that the problem of poor workability in indentation installation,

압입체(40)는 구조물 내부에서 운반, 설치가 용이하도록 개략 1.5m 정도로 제작한 것을 이용하게 되는데, 이러한 압입체(40)를 최종 압입시킨 상태에 있어 저판(11)으로부터 필요 이상으로 상방 돌출될 경우가 많아 그 두부처리(커팅) 작업이 매우 번거롭고, 지반 하부 견질지지층까지의 도달 깊이가 너무 깊은 경우 압입체를 무작정 압입시킬 수 없어 최적의 압입체 사용이 가능한 방법이 요구되었다.The press-fit body 40 is used to produce a roughly 1.5m to facilitate the transport and installation inside the structure, in the state that the press-in body 40 is finally pushed in, the projecting upward from the bottom plate 11 than necessary. In many cases, the tofu treatment (cutting) is very cumbersome, and when the depth of reach to the subsurface solid support layer is too deep, the indenter cannot be inadvertently inadvertently pushed for a method capable of using an optimal indenter.

본 발명은 상기 종래기술의 문제점을 해결하기 위한 것으로서 본 발명의 목적은 침하가 발생된 구조물에 대한 기초 보강 및 인상을 통해서 구조물의 기능을 회복시킬 수 있도록 하고, 추후 재인상이 가능한 구조물 인상 및 재인상이 가능한 공법을 제공하되, 압입체 시공 시 그 압입깊이를 조정할 수 있도록 하여 자재사용량을 최적화하고 구조물 인상공종에 있어 시공성이 증진될 수 있으며, 견질지지층이 지반 하부 깊이 위치할 경우에도 용이하게 적용할 수 있는 깊이 조절이 가능한 압입체를 이용한 구조물 인상공법을 제공하는 것이라 할 수 있다.The present invention is to solve the problems of the prior art as an object of the present invention to restore the function of the structure through the basic reinforcement and impression of the structure is settled, and to raise and re-raise the structure can be re-raised later Provides a method that can be pulled up, but it is possible to adjust the press-in depth during construction of the press-fitted body to optimize the material usage and to improve the workability in the lifting work of the structure, easy to apply even when the hard support layer is located below the ground It can be said to provide a structure impression method using a press-fit body that can be adjusted in depth.

상기 기술적과제를 달성하기 위하여 본 발명은 The present invention to achieve the above technical problem

기본적으로 압입체(400)를 구조물 저판(110)에 형성시킨 천공홀(120)에 삽입시켜 압입시키기 위한 세팅부재(200)와 상기 세팅부재(200) 상부에 연결, 설치되는 상단지지체(300)와 압입수단(500) 및 구조물 인상상태를 유지하기 위한 인상지지 판(600)을 그대로 이용하게 된다. 이때, 본 발명은 Basically, the upper support 300 which is connected to and installed on the setting member 200 and the setting member 200 for inserting the press-fit member 400 into the drilling hole 120 formed in the structure bottom plate 110 and press-fitted. And the press support means 500 and the impression support plate 600 for maintaining the structure lifting state is used as it is. At this time, the present invention

첫째, 압입체(400)로서 강관을 이용하여 그 절삭 등에 의한 두부커팅이 용이하도록 함과 더불어, 상기 강관은 폐쇄된 구조물 내부에서 운반, 시공이 용이하도록 개략 1.5m 정도의 길이를 가지도록 제작하되, 최종 강관이 견질 지지층까지 압입된 상태에서 저판 상부로 돌출되는 높이를 조정할 수 있도록 강관과 강관 사이에 소켓형 연결관(410)이 이용될 수 있도록 하였다.First, using a steel pipe as the indenting body 400 to facilitate the cutting of the head by its cutting, etc., the steel pipe is manufactured to have a length of approximately 1.5m to facilitate transportation and construction in the closed structure, In addition, the socket-type connecting pipe 410 may be used between the steel pipe and the steel pipe so that the height of the protruding portion of the bottom plate may be adjusted while the final steel pipe is pressed into the rigid support layer.

즉, 상기 소켓형 연결관(410)의 길이를 조정함으로서 전체 강관 사용량을 최적화할 수 있고 불필요한 강관 두부 커팅에 의한 시공성 및 작업성의 저하를 방지할 수 있도록 하였다.That is, by adjusting the length of the socket-type connection pipe 410 it is possible to optimize the overall steel pipe usage and to prevent the deterioration of workability and workability by cutting unnecessary steel pipe head.

둘째, 상기 세팅부재(200)를 구성하는 고정구(220)의 형성위치가 압입체(400)의 압입 시공을 방해하지 않도록 저판(110)에 천공홀(120)을 형성시킬 때, 상기 고정구가 삽입되는 천공홀과 가이드관이 삽입되는 천공홀을 각각 별도(천공홀 1,2)로 형성되도록 하였다.Second, when forming the drilling hole 120 in the bottom plate 110 so that the formation position of the fixture 220 constituting the setting member 200 does not interfere with the indentation construction of the indenter 400, the fixture is inserted The punched holes to be inserted into the drill holes and the guide tube is inserted (punched holes 1,2).

셋째, 압입체(400)인 강관을 저판 하부 지반에 압입시킬 때, 견질지지층까지의 깊이가 과도하게 깊을 경우 강관을 통해 콘크리트와 같은 충진재가 지반 하부에 형성되도록 하여 임의의 구근(710)이 지반에 형성되도록 함으로서, 압입체가 견질지지층까지 도달하지 않아도 충분히 구조물용 기초파일로서 작용하도록 하였다.Third, when press-fitting the steel pipe, which is the indenting body 400 to the bottom plate bottom, if the depth to the hard support layer is excessively deep, the filling material such as concrete is formed in the bottom of the ground through the steel pipe arbitrary bulb 710 is ground In order to be formed in the indenter, the indenter was sufficiently made to function as a foundation pile for the structure even without reaching the rigid support layer.

본 발명을 보다 명확하고 용이하게 설명하기 위해서 이하 본 발명의 최선의 실시예를 첨부도면에 의하여 상세하게 설명하며, 본 발명에 따른 실시예는 여러 가지 다른 형태로 변형될 수 있으므로, 본 발명의 범위가 아래에서 설명되는 실시예 에 한정되지 않는다.BRIEF DESCRIPTION OF DRAWINGS To describe the present invention more clearly and easily, the following describes the best embodiments of the present invention in detail with reference to the accompanying drawings. Is not limited to the embodiments described below.

도 2a 내지 도 2e는 본 발명에 따른 구조물 인상공법을 순서대로 도시한 것이며,2a to 2e shows the structure impression method in order according to the present invention,

도 3a 및 도 3b는 구조물을 구성하는 저판의 두께 및 고정구에 따른 본 발명의 구조물 인상공법의 다른 예를 도시한 것이며,3A and 3B illustrate another example of the structure pulling method of the present invention according to the thickness and the fixture of the bottom plate constituting the structure,

도 4는 압입체를 시공함에 있어 구근이 형성되도록 한 본 발명의 시공예를 도시한 것이다.Figure 4 shows a construction example of the present invention that the bulb is formed in the construction of the indenter.

먼저, 본 발명은 기본적으로 아파트 또는 빌딩과 같은 건축구조물의 지하실 바닥면 또는 공장구조물의 바닥면과 같은 구조물(100) 저판(110)으로부터 그 하부 지반에 강관과 같은 압입체(400)를 압입시키는 방식으로 시공된다. 이에 기본적으로 유압실린더를 포함하는 압입수단(500)에 의한 반력으로 압입체(400)를 지반에 압입시키는 파일 압입공법을 이용하게 된다.First, the present invention basically press-fitting the indenter 400, such as steel pipe from the bottom plate 110 of the structure 100, such as the basement floor surface of the building structure, such as apartments or buildings or the bottom plate 110 of the factory structure. It is constructed in the way. This basically uses a pile pressing method for press-fitting the press body 400 to the ground by the reaction force by the pressing means 500 including the hydraulic cylinder.

이에 먼저, 압입체(400)를 구조물(100)의 하부 지반에 압입시기 위한 초기 세팅 및 후술되는 상단지지체(300)와 함께 반력수단으로서 설치되는 세팅부재(200)를 미리 준비하게 된다.First, the setting member 200 to be installed as a reaction means together with the initial setting for pressing the indenter 400 into the lower ground of the structure 100 and the upper support 300 to be described later is prepared in advance.

도 2a를 기준으로 살펴보면, 먼저 구조물(100)의 저판(110)에 천공홀(120)을 형성시키게 된다.Referring to FIG. 2A, first, a perforation hole 120 is formed in the bottom plate 110 of the structure 100.

이러한 천공홀(120)은 크게 세팅부재(200)를 구성하는 가이드관(210)용 천공홀 1(121)과 세팅부재(200)를 구성하는 고정구(220)용 천공홀 2(122)로 구분하여 구조물(100) 저판(110) 표면을 일부 절취한 후, 천공장비를 이용하여 구조물 저 판(110)에 천공홀 1(121) 및 천공홀 2(122)를 형성시키게 된다.The drilling hole 120 is largely divided into a drilling hole 1 121 for the guide tube 210 constituting the setting member 200 and a drilling hole 2 122 for the fixture 220 constituting the setting member 200. After cutting the surface of the bottom plate 110 part of the structure 100 by using the drilling equipment, the drilling hole 1 (121) and the drilling hole 2 (122) are formed in the structure bottom plate (110).

이때 상기 천공홀 2(122)는 천공홀 1(121)과 접하여 그 둘레에 형성되도록 하여 아령 단면 형태로 천공홀(120)이 최종 형성되도록 한다.At this time, the drilling hole 2 (122) is in contact with the drilling hole 1 (121) to be formed in the circumference so that the drilling hole 120 in the form of a cross-section of the dumbbell to be finally formed.

또한 상기 천공홀(120)과 별도로 저판(110) 하부에 후술되는 세팅부재(200)가 용이하게 세팅될 수 있도록 저판(110) 하부 지반을 추가로 터파기 방식으로 일정공간이 확보되도록 한다.In addition, the bottom plate 110, so that the setting member 200 to be described later separately from the bottom of the bottom plate 110 to be easily set so that a predetermined space is secured by the additional digging method.

다음으로는 천공홀 1,2(121,122)에 세팅부재(200)를 삽입시켜 세팅하게 된다.Next, the setting member 200 is inserted into the drilling holes 1,2 and 121 and 122 to be set.

도 2a 및 도 2b를 기준으로 살펴보면 상기 세팅부재(200)는 원형의 강관과 같은 가이드관(210)과 상기 가이드관(210) 주위에 설치되는 고정구(220)로 구성된다.Referring to FIGS. 2A and 2B, the setting member 200 includes a guide tube 210 such as a round steel pipe and a fixture 220 installed around the guide tube 210.

상기 가이드관(210)은 강관을 이용하되 그 길이는 적어도 구조물(100)의 두께(d)보다 더 길게 형성되도록 하고, 가이드관(210)의 직경은 후술되는 압입체(400)가 삽입될 수 있을 정도의 직경을 가지도록 한다.The guide tube 210 uses a steel pipe, but the length thereof is formed to be longer than at least the thickness (d) of the structure 100, the diameter of the guide tube 210 can be inserted into the indenter 400 to be described later Make sure you have enough diameter.

상기 고정구(220)는 수직철근(221) 2개가 서로 이격되어 형성되도록 하되, 하부 단부에는 수평고정구(222)가 형성되도록 하되, 수직철근(221)에는 상, 하로 곡면 형태의 수평철근(223)이 이격되어 다수 설치되도록 함으로서, 고정구(220)가 원형 단면의 관통홀 2(122) 내측면에 밀착되어 설치될 수 있도록 한다.The fixture 220 is to be formed so that the two vertical reinforcing bars 221 are spaced apart from each other, the lower end to the horizontal fixing sphere 222 is formed, the vertical reinforcing bars 221, the horizontal reinforcing bars of the curved shape By allowing a plurality of spaced apart from each other, the fixture 220 can be installed in close contact with the inner surface of the through hole 2 (122) of the circular cross section.

위와 같은 세팅부재(200)를 설치하는 순서를 살펴보면 먼저,Looking at the order of installing the setting member 200 as described above,

고정구(220)를 도 2a와 같이 각각 1개씩 관통홀 2(122) 각각에 먼저 삽입시 키게 된다.As shown in FIG. 2A, one fixture 220 is first inserted into each of the through holes 2 122.

다음으로는 도 2b와 같이 유압실린더(230) 및 유압펌프(240)를 이용하여 고정구(220)가 천공홀 2(122)에 밀착되도록 함과 더불어 고정구(220)의 수평철근(221)은 구조물 저판(110) 저면에 걸려 설치되도록 하게 된다.Next, as shown in FIG. 2B, the fixture 220 is in close contact with the drilling hole 2 122 using the hydraulic cylinder 230 and the hydraulic pump 240, and the horizontal rebar 221 of the fixture 220 is formed. The bottom plate 110 is to be installed hanging on the bottom.

이에 강관인 가이드관(210)을 천공홀 1(121)에 삽입시키게 된다. 따라서 고정구(220)와 가이드관(210)은 서로 이격된 천공홀 1,2에 각각 설치됨으로서 서로 이격되어 배치될 수 있어 고정구(220) 때문에 압입체(400)의 압입시공이 방해되는 현상을 방지할 수 있게 된다.The guide pipe 210 is a steel pipe is inserted into the drill hole 1 (121). Therefore, the fixture 220 and the guide tube 210 may be disposed to be spaced apart from each other by being installed in each of the drilling holes 1,2 spaced apart from each other to prevent the phenomenon that the indentation of the indentation body 400 is disturbed because of the fixture 220. You can do it.

도 3a에 의하면 가이드관(210)의 외주면에 고정구(220)가 용접에 의하여 장착되어 있음을 알 수 있는데, 고정구(220)를 별도로 설치하는 수고로움을 덜기 위함이라 할 수 있다.According to Figure 3a it can be seen that the fixture 220 is mounted on the outer circumferential surface of the guide tube 210 by welding, it can be said to reduce the trouble of installing the fixture 220 separately.

즉, 고정구(220)를 구성하는 수직철근(221)이 곡면형태의 수평철근(223)에 의하여 가이드관(210)으로부터 이격되어 위치하도록 하고, 수평고정구(222)는 일측면이 가이드관(210)의 외주면에 접하도록 함으로서, 세팅부재(200)가 한꺼번에 시공될 수 있도록 하게 된다.That is, the vertical reinforcing bar 221 constituting the fixture 220 is positioned so as to be spaced apart from the guide pipe 210 by the horizontal reinforcing bar 223 of the curved shape, the horizontal fixture 222 is one side of the guide pipe 210 By making contact with the outer circumferential surface of the), the setting member 200 can be constructed at once.

이에 따르면 세팅부재(200)는 가이드관(210)과 고정구(220)를 일체로 미리 제작하여 일체로 시공할 수도 있고, 고정구(220)와 가이드관(210)을 각각 별도로 제작하여 각각을 별도로 시공할 수도 있음을 알 수 있다.According to this, the setting member 200 may be pre-fabricated by constructing the guide tube 210 and the fixture 220 in advance, and may be integrally constructed, and separately manufacture the fixture 220 and the guide tube 210 separately. It can be seen that.

나아가, 상기 천공홀(120)의 개략 중간 부위에는 천공홀 내측면으로부터 철근을 포함한 미 도시된 돌출부재가 미리 설치되도록 할 수 있다.In addition, a roughly middle portion of the drilling hole 120 may be pre-installed, not shown protrusion member including the reinforcing bar from the inner surface of the drilling hole.

이러한 돌출부재에 고정구(220)의 수직철근(221) 또는 수평철근(223)이 결속되도록 함으로서 초기 고정구의 위치를 세팅할 수 있도록 할 수 있을 것이다.The vertical reinforcing bar 221 or horizontal reinforcing bar 223 of the fastener 220 may be bound to the protruding member so that the position of the initial fastener may be set.

다음으로는 세팅부재(200)와 구조물(100)이 서로 일체화되도록 하기 위하여 도 2c와 같이 천공홀(120) 내부와 구조물(100) 저면 일부에 모르타르와 같은 그라우팅재(130)가 그라우팅되도록 하여, 모르타르가 경화되면 세팅부재(200)가 구조물(100)과 서로 일체화되도록 한다.Next, in order for the setting member 200 and the structure 100 to be integrated with each other, as shown in FIG. 2C, the grouting material 130 such as mortar is grouted on the inside of the drilling hole 120 and a portion of the bottom surface of the structure 100. When the mortar is cured, the setting member 200 is integrated with the structure 100.

이때, 세팅부재(200)를 구성하는 수평고정구(222)는 고정수단으로서 스토퍼(STOPPER) 역할을 하여 세팅부재(200)가 인발되려고 할 때 인발을 저항할 수 있는 구성으로 작용하게 된다.At this time, the horizontal fixture 222 constituting the setting member 200 serves as a stopper (STOPPER) as a fixing means to act as a configuration that can withdraw the drawing when the setting member 200 is to be drawn out.

이때, 도 3a와 같이 고정구(220)를 가이드관(210)과 함께 제작하는 경우라면, 도 3b와 같이 그라우팅재(130)를 천공홀 2에 그라우팅시킬 수 있을 것이다.At this time, if the fixture 220 is manufactured together with the guide tube 210 as shown in Figure 3a, as shown in Figure 3b, the grouting material 130 may be grouted to the drilling hole 2.

이로서, 가이드관은 상기 그라우팅재(130)를 그라우팅시키기 위한 거푸집 역할도 함을 알 수 있다.As such, it can be seen that the guide tube also serves as a formwork for grouting the grouting material 130.

다음으로는 압입체(400)를 상기 세팅부재(200)의 가이드관(210) 내부에 삽입시켜 세팅하게 된다. Next, the indenter 400 is inserted into the guide tube 210 of the setting member 200 to be set.

이때 상기 압입체(400)는 구조용 파일로서 제작된 강관(STEEL PIPE)을 이용하게 된다. 이러한 강관은 지반(700)에 압입됨으로서 그 자체로서 구조물(100)의 기초보강부재로 작용하게 되며, 이러한 의미에서 강관을 압입관으로 지칭할 수 있을 것이다.At this time, the indenter 400 is to use a steel pipe (STEEL PIPE) produced as a structural pile. Such a steel pipe is pressed into the ground 700 to act as a basic reinforcing member of the structure 100 itself, and in this sense, the steel pipe may be referred to as a press-fit pipe.

이에 상기 강관인 압입체(400)를 구조물(100) 하부 지반에 후술되는 상단지 지체(300) 및 압입수단(500)을 이용하여 계속 압입시키게 되면 그 선단이 최종 지반 하부의 견질지지층에 다다르게 되고, 추가적인 압입에 의하여 일종의 반력이 발생하게 되는데, 이러한 반력은 구조물(100)과 일체화된 세팅부재(200)에 의하여 구속되어 결국 침하된 구조물을 인상시킬 수 있게 된다.Accordingly, when the press-fit member 400, which is the steel pipe, is continuously press-fitted into the lower ground of the structure 100 using the upper support member 300 and the press-fit means 500, the tip reaches the hard support layer under the bottom of the final ground. And, a kind of reaction force is generated by the additional indentation, the reaction force is constrained by the setting member 200 integrated with the structure 100, it is possible to raise the submerged structure.

나아가 이러한 강관은 구조물(100)의 천정높이 및 운반을 고려한 길이로 제작된 것을 이용하되 그 직경은 가이드관보다 작은 것을 이용하게 된다.Further, the steel pipe is used to be made in the length considering the ceiling height and transport of the structure 100, but the diameter is smaller than the guide pipe.

이러한 강관이 견질지지층까지 다다르게 될 때까지는 후술하는 바와 같이 소켓형 연결관(410)을 이용하여 서로 연결되면서 압입되도록 하게 되며, 세팅부재(200)에 의하여 초기 압입되는 압입체(400)는 수직으로 초기 세팅될 수 있으므로 압입 시 그 직진성을 확보할 수 있으므로 그 작업성 및 시공성을 충분히 확보할 수 있게 된다.Until the steel pipe reaches the rigid support layer, as described below, the steel pipe is press-fitted while being connected to each other using the socket-type connecting pipe 410, and the press-fit member 400 initially press-fitted by the setting member 200 is vertically Since it can be set initially, the straightness can be secured at the time of indentation, so that the workability and workability can be sufficiently secured.

상기 연결관(410)은 도 2c와 같이 소켓관 방식으로 제작된 것을 이용하게 되는데, 상, 하 소켓연결부(411)와 양 소켓연결부(411)와 일체화된 몸통부(412)로 구성된다.The connection pipe 410 is to use the one produced in the socket tube method as shown in Figure 2c, it consists of the upper and lower socket connection portion 411 and the body portion 412 integrated with both socket connection portion 411.

즉, 상기 소켓연결부(411)는 연결된 강관에 소켓방식으로 삽입되어 상기 내측면에 밀착되도록 형성되며, 소켓연결부(411)와 일체화된 몸통부(412)는 강관의 직경과 동일한 직경으로 형성되도록 하여 강관이 연속성을 충분히 확보할 수 있도록 하게 된다.That is, the socket connection part 411 is inserted into the connected steel pipe in a socket manner and formed to be in close contact with the inner surface, and the body part 412 integrated with the socket connection part 411 is formed to have the same diameter as that of the steel pipe. The steel pipe is to ensure sufficient continuity.

이때, 연결관(410)과 연결되는 강관은 단순 기계식으로 끼워지는 방식으로 서로 연결되도록 할 수도 있고, 접착제 또는 용접에 의한 추가적인 부착력이 확보 되도록 할 수도 있다.At this time, the steel pipes connected to the connection pipe 410 may be connected to each other in a simple mechanically fitted manner, or may be to ensure an additional adhesion by adhesive or welding.

이러한 연결관(410)은 그 몸통부(412)의 높이를 조정하여 제작할 수 있는데, 이러한 높이 조정을 통해, 최종 압입된 강관의 두부가 천공홀(120)로부터 너무 상방 돌출되지 않도록 하여 불필요한 강관 두부 커팅작업이 발생하지 않도록 할 수 있게 되며, The connecting pipe 410 may be manufactured by adjusting the height of the body portion 412. Through such height adjustment, the head of the finally press-fitted steel pipe does not protrude too upward from the drilling hole 120 so that the unnecessary steel pipe head To prevent the cutting work,

연결관을 사용함으로서 강관을 보다 용이하게 서로 연결될 수 있도록 할 수 있음을 알 수 있다.It can be seen that by using the connecting pipe can be connected to the steel pipes more easily.

다음으로는 도 2c와 같이 세팅부재(200)에 상단지지체(300)를 장착시키게 된다.Next, the upper support 300 is mounted on the setting member 200 as shown in FIG. 2C.

이때 상기 상단지지체(300)는 천공홀의 형상에 따른 아령형의 상판(310) 및 상기 상판을 관통한 일단부가 연결너트(320)에 의하여 상판(310)에 체결되고, 타단이 하부로 연장되도록 형성된 지지철근(330)으로 구비된다.At this time, the upper support 300 is formed so that the upper end of the dumbbell-shaped upper plate 310 and the upper portion through the upper plate 310 is fastened to the upper plate 310 by the connection nut 320, the other end is extended to the lower portion It is provided with a support reinforcement 330.

즉, 압입체(400)로서 연결관(410)에 의하여 서로 연결 시공되는 강관을 세팅부재(200)에 초기 세팅한 상태에서, 강관 두부에 두부보강판(360)을 선택적으로 설치하고, 두부보강판(360) 상면에 소정의 용량을 가진 유압실린더와 같은 압입수단(500)을 설치한다.That is, the head reinforcing plate 360 is selectively installed on the head of the steel pipe in a state where the steel pipes connected to each other by the connection pipe 410 are initially set in the setting member 200 as the indenter 400, and the head reinforcement is provided. An indentation means 500 such as a hydraulic cylinder having a predetermined capacity is installed on the upper surface of the plate 360.

다음으로는 세팅부재(200)를 구성하는 고정구(220)의 수직철근(221)의 상단을 상단지지체(300)의 지지철근(330)과 체결되도록 하며, 이러한 체결은 체결너트(340)에 의하여 간단하게 기계적으로 체결되도록 하여 작업성을 확보하도록 하며, Next, the upper end of the vertical reinforcement 221 of the fixture 220 constituting the setting member 200 to be fastened with the support reinforcement 330 of the upper support 300, such fastening by the fastening nut 340 Simple mechanical fastening ensures workability,

이로서 압입수단(500)의 상부는 상단지지체(300)를 구성하는 상판(310)의 저면과 접하도록 설치되며, 상단지지부재(350)에 의하여 접지면적이 크도록 함이 바람직하다.Thus, the upper portion of the press-in means 500 is installed in contact with the bottom surface of the upper plate 310 constituting the upper support 300, it is preferable to have a large ground area by the upper support member (350).

다음으로는 압압체(400)가 구조물 하부 지반(700)에 압입되도록 한다.Next, the press body 400 is press-fitted into the lower structure 700 of the structure.

즉, 유압실린더와 같은 압입수단(500)의 작동을 구조물(100)과 일체화된 세팅부재(200), 상기 세팅부재(200)와 연결, 설치된 상단지지체(300)가 구속함으로서 그 반력으로 압입체(400)인 콘크리트 파일이 천공홀(120) 하부 지반(700)에 압입되도록 하는 것이다.That is, the operation of the press-fit means 500 such as the hydraulic cylinder is connected to the setting member 200 and the setting member 200 and the setting member 200 integrated with the structure 100, the upper support member 300 is restrained by the reaction force by the reaction force The concrete pile 400 is to be press-fitted into the lower ground 700 of the drilling hole (120).

압입수단(500)의 1 스트로크에 의한 1회 압입량을 측정하면서 다수의 강관을 소정의 깊이까지 압입시키면서 최종 강관의 선단이 구조물 하부 지반의 견질지지층까지 다다르도록 한다.While measuring the amount of indentation by one stroke of the indentation means 500 while pressing a plurality of steel pipe to a predetermined depth to the front end of the final steel pipe to reach the rigid support layer of the lower ground of the structure.

위와 같이 견질지지층에 그 선단이 압입된 압입체(400)에 추가적인 압입력이 지속적으로 전달되면, 압입체(400)는 견질지지층에 더 이상 압입되지는 않게 되므로 압입수단(500)의 작동을 멈추도록 한다.When the additional pressurization input is continuously transmitted to the press-fit member 400 in which the tip is press-fitted to the callus support layer as described above, the press-fit body 400 is no longer press-fitted to the call-support layer and stops the operation of the press-fit means 500. To do that.

이때, 도 2d와 같이 강관인 압입체(400)를 최종 압입시킨 다음에는, 강관 내부에 철근조립체(420)를 더 설치하고, 강관내부에 철근조립체(420)가 매립되도록 추가적으로 콘크리트와 같은 충진재(430)를 주입시키게 된다. 이때 상기 충진재가 경화됨으로서 강관과 충진재는 서로 합성되어 강관은 일종의 콘크리트 및 철근조립체가 합성된 강관으로 이용가능하게 된다.At this time, after the final indentation of the indentation body 400, which is a steel pipe as shown in Figure 2d, the reinforcing bar assembly 420 is further installed inside the steel pipe, additionally filling material such as concrete so that the reinforcing bar assembly 420 is embedded in the steel pipe ( 430 is injected. At this time, as the filler is hardened, the steel pipe and the filler are synthesized with each other, so that the steel pipe can be used as a steel pipe in which a kind of concrete and a reinforced assembly are synthesized.

위와 같이 압입체(400)의 압입, 압입체 내부에 철근조립체 및 충진재를 충진 시키는 작업이 구조물에 따라 다수 완료하게 되면 압입체에 추가적인 압입력을 가함으로서 반력형태로 구조물이 동시에 인상되도록 함과 더불어 그 구조물 인상상태를 유지할 필요가 있게 된다.As described above, when the indentation of the indenter 400 and the filling of the reinforcing bar assembly and the filling material in the indenter are completed according to the structure, the structure is simultaneously raised in a reaction force by applying an additional press input to the indenter. It is necessary to maintain the structure lift state.

이에, 도 2e와 같이 압입체(400)를 둘러싸고 있는 세팅부재(200)에 인상지지판(600)을 설치하게 된다.Thus, as shown in FIG. 2E, the impression supporting plate 600 is installed on the setting member 200 surrounding the press-fit body 400.

즉, 체결너트(340)를 풀어 상단지지체(300)와 세팅부재(200)가 연결된 상태를 해체하고 나서, 상기 세팅부재(200)를 구성하는 수직철근(221)이 아령 형태의 지지판(610)을 관통하여 상방 돌출되도록 하고, 너트(620)를 지지판(610)에 미체결 상태로 설치하게 된다.That is, after the fastening nut 340 is released to dismantle the state in which the upper support member 300 and the setting member 200 are connected, the vertical reinforcing bar 221 constituting the setting member 200 is a dumbbell-shaped support plate 610. Through and to protrude upward, the nut 620 is installed in the unsupported state to the support plate 610.

다음으로는 다시 수직철근(221)에 상단지지체(300)를 설치함과 더불어 상단지지체(300)와 인상지지판(600) 사이에 압입수단(500)을 다시 설치한 후, 동시에 시공된 모든 압입체에 추가 압입력을 가하게 되며, 이러한 추가 압입력에 의하여 구조물(100)은 일시에 인상될 수 있게 된다.Next, the upper support 300 is installed on the vertical rebar 221 again, and the indenting means 500 is installed again between the upper support 300 and the impression support plate 600, and all the indenters are constructed at the same time. An additional pressing force is applied to the structure, and by this additional pressing force, the structure 100 can be pulled up at a time.

위와 같이 구조물 인상이 일시에 완료되면, 그 인상 상태를 유지할 필요가 있게 된다.When the structure is completed in a temporary manner as described above, it is necessary to maintain the pulling state.

이를 위해, 재 설치된 상단지지체(300) 및 압입수단(500)을 해체하고 나서, 지지판(610)을 수직철근(221)에 너트(620)에 고정시켜 결국, 최종 구조물의 인상상태가 인상지지판(600)에 의하여 유지될 수 있게 된다.To this end, after dismantling the upper support member 300 and the press-fit means 500, the support plate 610 is fixed to the nut 620 to the vertical reinforcing bar 221, and finally, the lifting state of the final structure is the lifting support plate ( 600 can be maintained.

결국, 구조물(100)이 인상되도록 작용된 추가 압입력은 인상지지판(600)에 의하여 최종 구속됨으로서 구조물(100) 인상상태를 계속 유지할 수 있게 됨을 알 수 있다.As a result, it can be seen that the additional pressing force acted to raise the structure 100 is finally restrained by the lifting support plate 600 so that the structure 100 can be maintained in the pulling state.

또한, 시간이 경과하게 되면, 여러 외부적인 영향에 의하여 구조물(100)이 다시 침하할 여지가 있게 된다.In addition, as time passes, there is room for the structure 100 to sink again due to various external influences.

이에 본 발명에서는 인상지지판(600)이 영구 마감 처리되지 않도록 하여 추가 구조물(100) 인상이 가능하도록 하였다.Thus, in the present invention, the impression supporting plate 600 is not to be permanently finished so that the additional structure 100 can be raised.

즉, 설치된 인상지지판(600)의 너트(620)를 풀고, 체결너트(340)를 이용하여 다시 상판(310) 및 지지철근(330)으로 구성된 상단지지체(300)를 재 설치함과 더불어 압입수단(500)을 상단지지체(300)와 강관인 압입체(400) 사이에 설치하게 된다.That is, the nut 620 of the installed impression support plate 600 is loosened, and the upper support body 300 composed of the upper plate 310 and the support reinforcement 330 is reinstalled by using the fastening nut 340, and the press-fitting means The 500 is installed between the upper support member 300 and the press-fit member 400 which is a steel pipe.

이에 상기 압입수단(500)을 작동시키게 되면, 그 압입력에 의하여 침하된 구조물을 다시 인상시킬 수 있게 된다.When the press means 500 is operated, it is possible to raise the structure settled by the press input again.

통상, 재침하된 구조물(100)의 침하량은 부위에 따라 차이가 있을 수 있으므로 미도시된 추가적인 압입체를 이용하여 구조물(100) 재인상이 가능할 수 있을 것이다.In general, since the settling amount of the re-settled structure 100 may vary depending on the site, it may be possible to re-impress the structure 100 by using an additional indenter not shown.

이에 최종 재인상이 완료되면, 지지판(610)을 너트(620)로 수직철근(221)에 고정시키고 상단지지체(300) 및 압입수단(500)을 해체한다.When the final re-impression is completed, the support plate 610 is fixed to the vertical rebar 221 with a nut 620, and the upper support member 300 and the press-in means 500 are dismantled.

도 4는 특히 압입체(400)로서 강관을 견질지지층까지 다다르도록 압입시킴에 있어 특히, 압입깊이가 상당할 때 고가인 강관을 사용할 수 없을 정도일 경우에 특히, 강관 내부에 콘크리트와 같은 충진재를 충진시킬 때, 패킹재(440)를 강관 상단 내측에 설치하고, 상기 패킹재(440)를 관통하는 구근형성용 주입관(450)을 설치한 후, 상기 주입관을 통해 구근용 충진재를 통해 압입관 하부에 구근(710)이 형성되 도록 한 것인데, 4 is particularly in press fitting the steel pipe to the support layer as a press-fit 400, in particular, when the press-depth depth is not enough to use expensive steel pipe, in particular the filling material such as concrete inside the steel pipe When filling, the packing material 440 is installed inside the upper end of the steel pipe, and the bulb injection tube 450 for penetrating the packing material 440 is installed, and then press-filled through the bulb filler through the injection pipe. Bulb 710 is formed in the lower part of the tube,

이럴 경우, 구근(710)이 강관 하부 지반에 형성되고 있음을 확인할 수 있으며, 이러한 구근에 강관 선단부가 지지되고 있음을 알 수 있다.In this case, it can be seen that the bulb 710 is formed in the lower ground of the steel pipe, and it can be seen that the steel pipe tip is supported by the bulb.

즉, 강관 선단 하부 지반에 견질지지층 역할을 하는 구근을 임의로 형성시킴으로서 구근이 견질지지층 역할을 할 수 있도록 한 것이라 할 수 있다.That is, by forming a bulb which serves as a hard support layer on the ground of the lower end of the steel pipe can be said that the bulb can act as a hard support layer.

본 발명에 의하여 구조물 지하와 같이 폐쇄된 공간에서, 구조물의 영구기초보강재로 기능하는 콘크리트 파일인 압입체를 이용하여 침하된 구조물의 인상 및 재인상이 가능하도로 함으로서 보다 효율적이며, 재사용이 가능한 구조물의 인상공법이 제공되며, 압입체의 시공이 세팅부재에 의하여 간섭되지 않아 압입시공의 효율성 및 시공성 및 작업성을 증진시킬 수 있으며,According to the present invention, a more efficient and reusable structure is made possible by using a press-fitting body, which is a concrete pile functioning as a permanent foundation reinforcement of the structure, in a closed space such as a structure underground. The impression method is provided, and the construction of the press-fitted body is not interfered by the setting member, thereby improving the efficiency, workability and workability of the press-fitted work.

압입체로서 강관을 이용함에 있어 그 연결시공이 용이할 뿐만 아니라, 전체 압입깊이를 연결관으로 조정함으로서 효율적인 강관 두부처리가 가능하게 되고,In the use of steel pipe as a press-fit body, not only the connection construction is easy, but also the effective steel pipe head treatment is possible by adjusting the overall press-in depth to the connecting pipe.

압입깊이가 큰 경우 구근을 함께 형성시킴으로서 보다 경제적이고 효율적인 구조물 인상이 가능하게 된다. 앞에서 설명되고, 도면에 도시된 본 발명의 일 실시예는 본 발명의 술적사상을 한정하는 것으로 해석되어서는 안 된다. 본 발명의 기술분야에서 통상의 지식을 가진 자는 본 발명의 기술적 사상을 다양한 형태로 개량 변경하는 것이 가능하다. 따라서 이러한 개량 및 변경은 통상의 지식을 가진 자에게 자명한 것인 한 본 발명의 보호범위에 속하게 된다.If the indentation depth is large, the bulbs are formed together to allow more economic and efficient structure impression. An embodiment of the present invention described above and illustrated in the drawings should not be construed as limiting the technical spirit of the present invention. Those skilled in the art of the present invention can change and change the technical idea of the present invention in various forms. Therefore, such improvements and modifications fall within the protection scope of the present invention as long as it will be apparent to those skilled in the art.

Claims (5)

구조물 저면에 형성된 천공홀 내측에 구조물과 일체화되도록 가이드관과 상단지지체 고정용 철근을 포함하는 고정구를 포함하는 세팅부재를 먼저 설치하고, 상기 가이드관의 내부로 압입체를 삽입시켜 그 위치를 세팅한 후, 상기 고정구 상단부를 상단지지체에 연결 설치하되, 상기 압입체 상단과 상단지지체 사이에 압입수단을 설치 작동시켜 압입체를 구조물 하부 지반에 압입시킴과 더불어 구조물을 인상시키는 구조물 인상방법에 있어서,First, a setting member including a fixture including a guide tube and an upper support fixing reinforcing bar is installed inside the drilling hole formed at the bottom of the structure, and the position is set by inserting a press-fit into the guide tube. In the structure lifting method of connecting the upper end of the fixture to the upper support, the press-fitting means is installed between the upper end of the press and the upper support to operate and press the indenter to the lower ground of the structure and to raise the structure, 상기 압입체는 강관을 포함하는 압입관을 다수 연결시켜 가면서 압입시키되, 압입관과 압입관 사이에 연결관을 설치하고, 상기 연결관은 압입관 내측면에 끼워지는 소켓연결부와 압입관과 동일한 단면크기로 형성된 몸통부로 형성되도록 하여, 상기 몸통부의 형성 길이 조정을 통해 압입관의 압입깊이를 조정할 수 있도록 하고,The press-fit body is press-fitted while connecting a plurality of press-fit pipe including a steel pipe, install a connection pipe between the press-fit pipe and the press-fit pipe, the connection pipe is inserted into the inner surface of the press-fit pipe and the same end as the press-fit pipe It is to be formed in the body portion formed in size, to adjust the depth of indentation of the indentation pipe by adjusting the forming length of the body portion, 상기 천공홀은 가이드관용 천공홀 1과 고정구용 천공홀 2로 형성되도록 하되, 천공홀 2는 천공홀 1과 접하여 그 둘레에 형성되도록 함으로서 가이드관 및 가이드관에 삽입되는 압입관과 고정구가 서로 이격되어 위치되도록 하는 것을 특징으로 하는 깊이 조절이 가능한 압입체를 이용한 구조물 인상공법.The drilling hole is formed to be a guide hole 1 for the guide pipe and a hole 2 for the fixture, the hole 2 is formed in the periphery of the contact hole 1 and the indentation pipe and the fixture inserted into the guide tube and the guide tube spaced apart from each other Structural impression method using a press-fit the depth can be characterized in that the position to be positioned. 삭제delete 제 1항에 있어서, 상기 고정구는 수직철근의 하부단부에 형성시킨 수평고정구로 형성시키되, According to claim 1, The fastener is formed of a horizontal fixture formed on the lower end of the vertical reinforcement, 가이드관과 일체로 형성되어 천공홀 1,2에 삽입되도록 한 후, 천공홀 2에 무수축 모르타르를 포함하는 그라우팅재를 그라우팅시켜 구조물과 일체화되도록 하거나,After being formed integrally with the guide tube to be inserted into the drilling holes 1,2, grouting the grouting material including the non-shrink mortar in the drilling hole 2 to be integrated with the structure, or 가이드관과 별도로 천공홀 2에 삽입시킨 후 구조물 저면 하부에 수평고정구가 위치되도록 한 후, 가이드관을 천공홀 1에 삽입시키고, 무수축 모르타르를 포함하는 그라우팅재를 그라우팅시켜 구조물과 일체화 되도록 하는 것을 특징으로 하는 깊이 조절이 가능한 압입체를 이용한 구조물 인상공법.Insert the guide tube into the drill hole 2 separately from the guide tube and place the horizontal fixture on the bottom of the structure, and then insert the guide tube into the drill hole 1 and grout the grouting material including the non-shrink mortar to be integrated with the structure. Structural impression method using a press-fitting body that can be adjusted depth. 제 1항 또는 제 3항에 있어서, 상기 압입관 내부에는 철근조립체가 더 설치되며, 상기 압입관 내부에 철근조립체가 매립되도록 콘크리트를 포함하는 충진재를 추가로 더 충진 시키는 것을 특징으로 하는 깊이 조절이 가능한 압입체를 이용한 구조물 인상공법.According to claim 1 or claim 3, wherein the reinforcing bar assembly is further installed in the indentation pipe, the depth control is characterized in that the additional filling of the filler including concrete so that the reinforcing bar is embedded in the indentation pipe. Structural impression method using possible indents. 제 4항에 있어서, 상기 압입관은 견질 지지층에 도달될 때까지 압입시키거나, 철근조립체 설치 이전에 압입관 상단내부에 패킹재를 설치하고, 상기 패킹재를 관통하는 구근형성용 주입관을 설치하여 상기 주입관을 통해 구근용 충진재를 통해 압입관 하부에 구근이 형성되도록 하는 것을 특징으로 하는 깊이 조절이 가능한 압입체를 이용한 구조물 인상공법.According to claim 4, The indentation pipe is press-fitted until reaching the hard support layer, or before the installation of the reinforcing bar is installed a packing material in the upper end of the indentation pipe, the bulb injection tube for penetrating the packing material is installed Structural impression method using a depth-adjustable indenter characterized in that the bulb is formed in the lower part of the indentation pipe through the filler for filling through the injection tube.
KR1020070012633A 2007-02-07 2007-02-07 Structure lifting method using pile adjustable the length KR100767093B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020070012633A KR100767093B1 (en) 2007-02-07 2007-02-07 Structure lifting method using pile adjustable the length

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020070012633A KR100767093B1 (en) 2007-02-07 2007-02-07 Structure lifting method using pile adjustable the length

Publications (1)

Publication Number Publication Date
KR100767093B1 true KR100767093B1 (en) 2007-10-18

Family

ID=38814787

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020070012633A KR100767093B1 (en) 2007-02-07 2007-02-07 Structure lifting method using pile adjustable the length

Country Status (1)

Country Link
KR (1) KR100767093B1 (en)

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100824688B1 (en) 2007-10-25 2008-04-24 주식회사고려이엔시 Bogie for reinforcing underground structure
KR100879621B1 (en) * 2008-09-19 2009-01-21 이동훈 Basement reinforcing and structure restoration method using piling appratus
KR101127931B1 (en) 2007-11-16 2012-03-23 한우코리아(주) Basement construction method using the steel pipe
KR101133771B1 (en) 2009-09-16 2012-04-09 변항용 Structure consecutive lifting apparatus and lifting method using that
KR101217489B1 (en) * 2012-01-31 2013-01-02 박영수 Pile installing apparatus to press framework using protruding hoof
KR101395828B1 (en) * 2013-09-26 2014-05-15 황규원 Pile anchoring apparatus using support pipe and foundation reinforcing method therewith
KR101427340B1 (en) * 2013-01-09 2014-08-06 (주)센구조연구소 Apparatus and method for pressing steel pipe
KR101445372B1 (en) 2011-09-09 2014-10-06 주식회사고려이엔시 The anchor structure which has round root and the foundation structure construction method which use this
WO2015133720A1 (en) * 2014-03-05 2015-09-11 (주)센구조연구소 Pile driving device and pile driving method
KR101574663B1 (en) * 2014-04-17 2015-12-04 (주)센벡스 Apparatus and method for penetrating pile
KR101582901B1 (en) * 2014-12-03 2016-01-07 (주)철도안전연구소 Method for restoration of subsided railroad track
KR101608835B1 (en) * 2015-08-25 2016-04-05 원우산업개발 주식회사 Pile construction method for concrete structure using cutting apparatus for groove
KR20160038428A (en) * 2014-09-30 2016-04-07 김인호 Reactive device with gear motor and pile construction method therewith
KR101720744B1 (en) * 2016-04-14 2017-03-29 황규원 Pile anchoring apparatus attached sheet and foundation reinforcing method therewith
KR101733507B1 (en) * 2016-07-12 2017-05-11 원우산업개발 주식회사 Structure reinforcing method using shear support frame fixed to under slab soil
KR101745380B1 (en) * 2016-02-15 2017-06-09 (주)나다건설 Device and method for H-section pile installation
KR101819016B1 (en) * 2016-02-15 2018-02-28 (주)나다건설 Device and method for loading newly installed pile
KR101834962B1 (en) * 2017-05-15 2018-04-19 (주)나다건설 Device and method for loading newly installed pile
KR102123747B1 (en) * 2018-12-18 2020-06-16 남윤옥 Hydraulic jack module system used in floor reinforcement method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5234287A (en) * 1989-07-27 1993-08-10 Rippe Jr Dondeville M Apparatus and process for stabilizing foundations
KR100654228B1 (en) 2006-08-24 2006-12-06 정언섭 Structure lifting method possible to be re-lifting using pile member

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5234287A (en) * 1989-07-27 1993-08-10 Rippe Jr Dondeville M Apparatus and process for stabilizing foundations
KR100654228B1 (en) 2006-08-24 2006-12-06 정언섭 Structure lifting method possible to be re-lifting using pile member

Cited By (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100824688B1 (en) 2007-10-25 2008-04-24 주식회사고려이엔시 Bogie for reinforcing underground structure
KR101127931B1 (en) 2007-11-16 2012-03-23 한우코리아(주) Basement construction method using the steel pipe
KR100879621B1 (en) * 2008-09-19 2009-01-21 이동훈 Basement reinforcing and structure restoration method using piling appratus
KR101133771B1 (en) 2009-09-16 2012-04-09 변항용 Structure consecutive lifting apparatus and lifting method using that
KR101445372B1 (en) 2011-09-09 2014-10-06 주식회사고려이엔시 The anchor structure which has round root and the foundation structure construction method which use this
KR101217489B1 (en) * 2012-01-31 2013-01-02 박영수 Pile installing apparatus to press framework using protruding hoof
KR101427340B1 (en) * 2013-01-09 2014-08-06 (주)센구조연구소 Apparatus and method for pressing steel pipe
KR101395828B1 (en) * 2013-09-26 2014-05-15 황규원 Pile anchoring apparatus using support pipe and foundation reinforcing method therewith
KR101583271B1 (en) * 2014-03-05 2016-01-07 (주)센구조연구소 Apparatus and method for penetrating pile
WO2015133720A1 (en) * 2014-03-05 2015-09-11 (주)센구조연구소 Pile driving device and pile driving method
KR20150104277A (en) * 2014-03-05 2015-09-15 (주)센구조연구소 Apparatus and method for penetrating pile
KR101574663B1 (en) * 2014-04-17 2015-12-04 (주)센벡스 Apparatus and method for penetrating pile
KR20160038428A (en) * 2014-09-30 2016-04-07 김인호 Reactive device with gear motor and pile construction method therewith
KR101650485B1 (en) 2014-09-30 2016-09-05 김인호 Reactive device with gear motor and pile construction method therewith
KR101582901B1 (en) * 2014-12-03 2016-01-07 (주)철도안전연구소 Method for restoration of subsided railroad track
KR101608835B1 (en) * 2015-08-25 2016-04-05 원우산업개발 주식회사 Pile construction method for concrete structure using cutting apparatus for groove
KR101745380B1 (en) * 2016-02-15 2017-06-09 (주)나다건설 Device and method for H-section pile installation
KR101819016B1 (en) * 2016-02-15 2018-02-28 (주)나다건설 Device and method for loading newly installed pile
KR101720744B1 (en) * 2016-04-14 2017-03-29 황규원 Pile anchoring apparatus attached sheet and foundation reinforcing method therewith
KR101733507B1 (en) * 2016-07-12 2017-05-11 원우산업개발 주식회사 Structure reinforcing method using shear support frame fixed to under slab soil
KR101834962B1 (en) * 2017-05-15 2018-04-19 (주)나다건설 Device and method for loading newly installed pile
KR102123747B1 (en) * 2018-12-18 2020-06-16 남윤옥 Hydraulic jack module system used in floor reinforcement method

Similar Documents

Publication Publication Date Title
KR100767093B1 (en) Structure lifting method using pile adjustable the length
KR100654228B1 (en) Structure lifting method possible to be re-lifting using pile member
KR100621669B1 (en) Structure lifting and foundation strengthening method using the steel pipe
KR100917044B1 (en) Concrete retaining wall construction method with dual wall jointed by anchor
KR100957573B1 (en) Helical-pile for direct-boring grouting and using methods thereof
KR100894988B1 (en) Reinforcing method using helical-pile for direct-boring grouting
KR100807810B1 (en) Structure lifting method by foundation strengthening
KR101206344B1 (en) Precast panel for retaining wall and construction method therewith
US10221558B1 (en) Foundation connection device for use during construction of concrete wall panels
KR101065626B1 (en) Microsoft pile and construction methods
KR101284289B1 (en) The foundation for retaining wall blocks combined structure and the foundation used a block retaining reinforcement
KR100923587B1 (en) Micro pile construction method using anchorage appratus of micro pile
KR101809111B1 (en) Apparatus for pressing pile and method for reinforcing building base using this same
JP2016216975A (en) Installation method of earth anchor
KR101138298B1 (en) Anchor typed concrete filled pile and construction method using the same
KR101377019B1 (en) Reactive forcing device using guide rail and foundation reinforcing method therewith
KR20090050997A (en) Basement construction method using the steel pipe
KR101633289B1 (en) Head anchor device of micro pile and reinforced method of foundation concrete using the same
KR101133771B1 (en) Structure consecutive lifting apparatus and lifting method using that
KR100381454B1 (en) The sheet pile with water proof grouting groove and injection method of water proof grouting
KR101358636B1 (en) Foundation reinforcement construction method with guide tube
KR102113859B1 (en) Pile with head reinforcing device and method therefor
KR20140147247A (en) Foundation slab reinforcement method for integral behavior with existing building and structure of the same
KR20180131042A (en) Pile and method for constucting same
WO2013115677A2 (en) Screw injection pile and method for producing same

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
N231 Notification of change of applicant
GRNT Written decision to grant
G170 Publication of correction
FPAY Annual fee payment

Payment date: 20120925

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20130809

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20141007

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20151006

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20161006

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20171110

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20190910

Year of fee payment: 13