KR100765375B1 - 토류벽 시공시 사용된 에이취 빔 인출장치 - Google Patents
토류벽 시공시 사용된 에이취 빔 인출장치 Download PDFInfo
- Publication number
- KR100765375B1 KR100765375B1 KR1020060096928A KR20060096928A KR100765375B1 KR 100765375 B1 KR100765375 B1 KR 100765375B1 KR 1020060096928 A KR1020060096928 A KR 1020060096928A KR 20060096928 A KR20060096928 A KR 20060096928A KR 100765375 B1 KR100765375 B1 KR 100765375B1
- Authority
- KR
- South Korea
- Prior art keywords
- auxiliary
- wedges
- sides
- wedge
- casing
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D11/00—Methods or apparatus specially adapted for both placing and removing sheet pile bulkheads, piles, or mould-pipes
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D13/00—Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D9/00—Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof
- E02D9/02—Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof by withdrawing
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
Description
Claims (2)
- 지상에 고정 설치되는 베이스본체와, 베이스본체의 상방에서 상,하로 승강작동이 가능하게 설치되어 H빔을 인출하게 되는 인출작동체와, 상기 베이스본체의 상면 양측에는 피스톤로드의 선단이 고정 부착되고 실린더몸체는 상기 인출작동체의 양측에 고정 부착된 채 상향으로 돌출 형성되어 있는 양측 메인 승강실린더와, 상기 인출작동체에 내측경사면이 서로 마주하도록 고정 설치되어 있는 양측 쐐기가이더와, 상기 양측 쐐기가이더의 내측경사면에 외측경사면이 당접된 상태로 상,하로 이동가능하게 설치되어 H빔의 중간연결부 양면을 압착하여 H빔을 인출시키는 작동을 담당하는 양측 작동쐐기와, 상기 양측 작동쐐기를 H빔의 중간연결부에 압착시키기 위한 양측 쐐기작동용 유압실린더를 구비하여 구성된 H빔 인출장치에 있어서,상기 인출작동체의 좌,우측에 설치된 양측 메인승강실린더를 기준할 때 상기 인발작동체의 상면 전,후측에 수직상으로 입설되는 양측 보조 승강실린더와;상기한 H빔을 감싼 상태로 수용할 수 있도록 하부는 개구되고 상부에는 H빔 수용공이 형성되어 있으며, 상기 인출작동체에 설치된 양측 작동쐐기의 상방에 위치하여 상기 양측 보조 승강실린더 각각의 피스톤로드의 출몰작동에 따라 상,하로 승강작동이 가능하게 설치되는 보조 인출케이싱과;상기 보조 인출케이싱의 내부 좌,우측 각각에 서로 대칭상으로 형성된 고정핀축에 회전가능하게 설치되는 양측 작동링크와;상기 양측 작동링크의 자유단 각각에 지지된 회전핀축에 회전가능하도록 연 결 부착되어 H빔의 중간연결부 양면을 압착하여 H빔을 인출시키는 작동을 담당하게 되는 양측 보조쐐기;를 더 포함하여 구성된 것을 특징으로 하는 토류벽 시공시 사용된 H빔 인출장치.
- 제 1 항에 있어서,상기 양측 보조쐐기는 고정핀축의 수직중심선을 기준하여 볼 때 H빔의 중간연결부를 향해 30∼60°의 경사각도범위내에 위치하여 보조 인출케이싱의 상승작동시에는 H빔의 중간연결부 양측면을 향해 회전하려는 가압작동으로 압착토록 하는 한편, 보조 인출케이싱의 하강작동시에는 H빔의 중간연결부 양측면에서 멀어지는 방향으로 회전하려는 해제작동으로 보조 인출케이싱의 하강작동을 허용하도록 구성되어 있는 것을 특징으로 하는 토류벽 시공시 사용된 H빔 인출장치.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020060096928A KR100765375B1 (ko) | 2006-10-02 | 2006-10-02 | 토류벽 시공시 사용된 에이취 빔 인출장치 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020060096928A KR100765375B1 (ko) | 2006-10-02 | 2006-10-02 | 토류벽 시공시 사용된 에이취 빔 인출장치 |
Publications (1)
Publication Number | Publication Date |
---|---|
KR100765375B1 true KR100765375B1 (ko) | 2007-10-10 |
Family
ID=39419769
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020060096928A KR100765375B1 (ko) | 2006-10-02 | 2006-10-02 | 토류벽 시공시 사용된 에이취 빔 인출장치 |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR100765375B1 (ko) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100783472B1 (ko) * | 2007-01-30 | 2007-12-07 | 한두희 | 토류벽 시공시 사용된 에이취 빔 인출장치 |
CN107023010A (zh) * | 2017-06-02 | 2017-08-08 | 郑州大学 | 一种水泥搅拌墙的工字钢拔出装置 |
US10000903B1 (en) * | 2017-09-12 | 2018-06-19 | Han Joo Engineering & Construction Co., Ltd. | Casing assembly for forming CIP retaining wall and method for forming CIP retaining walls using the casing assembly |
KR101863526B1 (ko) | 2018-04-03 | 2018-06-29 | 황선복 | 에이치빔 인발 장치 |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003072354A (ja) * | 2001-09-04 | 2003-03-12 | Zexel Valeo Climate Control Corp | 車両用空調装置 |
JP2004008256A (ja) * | 2002-06-03 | 2004-01-15 | Sankyo Kk | 遊技機 |
-
2006
- 2006-10-02 KR KR1020060096928A patent/KR100765375B1/ko active IP Right Grant
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003072354A (ja) * | 2001-09-04 | 2003-03-12 | Zexel Valeo Climate Control Corp | 車両用空調装置 |
JP2004008256A (ja) * | 2002-06-03 | 2004-01-15 | Sankyo Kk | 遊技機 |
Non-Patent Citations (2)
Title |
---|
국내등록실용신안공보 제20-0372354호 |
국내등록실용신안공보 제20-0408256호 |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100783472B1 (ko) * | 2007-01-30 | 2007-12-07 | 한두희 | 토류벽 시공시 사용된 에이취 빔 인출장치 |
CN107023010A (zh) * | 2017-06-02 | 2017-08-08 | 郑州大学 | 一种水泥搅拌墙的工字钢拔出装置 |
US10000903B1 (en) * | 2017-09-12 | 2018-06-19 | Han Joo Engineering & Construction Co., Ltd. | Casing assembly for forming CIP retaining wall and method for forming CIP retaining walls using the casing assembly |
KR101863526B1 (ko) | 2018-04-03 | 2018-06-29 | 황선복 | 에이치빔 인발 장치 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101026731B1 (ko) | 준공된 건축물의 지하실 시공방법 | |
CN113614315A (zh) | 建造结构的方法 | |
CN109440778B (zh) | 主动式双向倾斜排桩基坑支护方法 | |
KR20120093547A (ko) | 톱다운식 지하증축 시공방법 | |
KR100765375B1 (ko) | 토류벽 시공시 사용된 에이취 빔 인출장치 | |
JP2684155B2 (ja) | 地下構造物の築造に用いる開削工法 | |
JP5038170B2 (ja) | 構造物の建て替え方法 | |
JP2011017184A (ja) | 擁壁及びその施工方法 | |
KR100765374B1 (ko) | 토류벽 시공시 사용된 에이취 빔 인출장치 | |
KR102522619B1 (ko) | 상승식 지하층 구조물 철거공법 | |
US6948885B2 (en) | Method for constructing foundation | |
JP5367452B2 (ja) | 地下壁体構築方法および地下壁体 | |
CN114809134A (zh) | 一种筏板基础的多层混凝土建筑顶升纠偏施工方法 | |
AU2020100004A4 (en) | A Method Of Constructing A Column, A Subterranean Structure, And A Structure Made From The Method | |
CN109440779B (zh) | 主动式x形双排桩基坑支护方法 | |
KR100783472B1 (ko) | 토류벽 시공시 사용된 에이취 빔 인출장치 | |
CN110374191B (zh) | 一种带支护功能的地下室外墙构件及其施工方法 | |
KR102199641B1 (ko) | 신축 구조물용 압입 파일 시공 방법 | |
JPH0960311A (ja) | リフトアップ解体工法 | |
JP7364105B2 (ja) | 位置調整装置及び構真柱の位置調整方法 | |
CN216896074U (zh) | 一种适用于浅埋无稳定后靠的管道顶进平台 | |
CN111074930B (zh) | 一种电梯基础结构的施工方法 | |
JP3117307U (ja) | サンドポスト | |
KR100781809B1 (ko) | 지하 구조물 축조 공법 | |
CN107059907B (zh) | 一种利用顶管机头开挖的拼装式筒形结构的施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20121002 Year of fee payment: 6 |
|
FPAY | Annual fee payment |
Payment date: 20131002 Year of fee payment: 7 |
|
FPAY | Annual fee payment |
Payment date: 20141002 Year of fee payment: 8 |
|
FPAY | Annual fee payment |
Payment date: 20150930 Year of fee payment: 9 |
|
FPAY | Annual fee payment |
Payment date: 20160920 Year of fee payment: 10 |
|
FPAY | Annual fee payment |
Payment date: 20171010 Year of fee payment: 11 |
|
FPAY | Annual fee payment |
Payment date: 20181001 Year of fee payment: 12 |
|
FPAY | Annual fee payment |
Payment date: 20190930 Year of fee payment: 13 |