KR100760332B1 - Temporary cantilever resources, construction method of structure using the same and dismantling method for the same - Google Patents

Temporary cantilever resources, construction method of structure using the same and dismantling method for the same

Info

Publication number
KR100760332B1
KR100760332B1 KR1020060083084A KR20060083084A KR100760332B1 KR 100760332 B1 KR100760332 B1 KR 100760332B1 KR 1020060083084 A KR1020060083084 A KR 1020060083084A KR 20060083084 A KR20060083084 A KR 20060083084A KR 100760332 B1 KR100760332 B1 KR 100760332B1
Authority
KR
South Korea
Prior art keywords
horizontal
fixing
fixing nut
plate
vertical
Prior art date
Application number
KR1020060083084A
Other languages
Korean (ko)
Inventor
이호형
Original Assignee
이호형
주식회사 진림건설
진용상
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 이호형, 주식회사 진림건설, 진용상 filed Critical 이호형
Priority to KR1020060083084A priority Critical patent/KR100760332B1/en
Application granted granted Critical
Publication of KR100760332B1 publication Critical patent/KR100760332B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges

Abstract

A cantilever temporary material, a structure construction method using the same, and a dismantling method of the same are provided to reduce dismantling cost and time by releasing a horizontal tensile bolt and dismantling a connecting plate, a vertical material, a slant strut, and a horizontal material at one time. A cantilever temporary material comprises a vertical material(10), a connecting plate(20), a horizontal material, a horizontal tensile bolt(40), a slant strut, a supporting member, a first fixing nut(70), a second fixing nut(80), and a third fixing nut. The horizontal tensile bolt is fitted to a hollow part of the horizontal material, projected to both ends of the horizontal material, and formed with a male thread on the outer peripheral surface. The slant strut has a lower end coupled with the lower end of the vertical material, and an upper end coupled with the horizontal material. The third fixing nut is coupled with the rear end of the horizontal tensile bolt to fix the horizontal material. The first fixing nut includes a hollow projection(75), and the second fixing nut includes a hollow projection(85).

Description

캔틸레버형 가설재, 이를 이용한 구조물 축조방법 및 이의 해체방법{Temporary cantilever resources, Construction method of structure using the same and Dismantling method for the same} Cantilever-type temporary material, construction method and dismantling method using same {Temporary cantilever resources, Construction method of structure using the same and Dismantling method for the same}

도1a 내지 도1e는 본 발명에 따른 캔틸레버형 가설재를 이용한 구조물 축조방법을 단계별로 도시한 것이다.Figures 1a to 1e shows step by step the structure construction method using the cantilever type temporary material according to the present invention.

도2는 고정재, 연결판, 수평인장볼트, 제1고정너트 및 제2고정너트 연결부위를 상세히 도시한 것이다.Figure 2 shows in detail the fixing member, connecting plate, horizontal tensioning bolt, the first fixing nut and the second fixing nut.

도3a 및 도3b는 캔틸레버형 가설재의 해체방법을 단계별로 도시한 것이다.3A and 3B illustrate step-by-step methods of disassembling the cantilevered temporary material.

<도면의 주요부분에 대한 부호의 설명> <Description of the symbols for the main parts of the drawings>

1 : 기 축조 구조물 2 : 구조재1: Pre-built structure 2: Structural material

3 : 장선 4 : 프리캐스트 콘크리트패널3: joist 4: precast concrete panel

5 : 안전 난간대 6 : 측벽거푸집5: safety railing 6: sidewall formwork

7 : 구체콘크리트7: Concrete concrete

10 : 수직재 20 : 연결판10: vertical member 20: connecting plate

30 : 수평재 40 : 수평인장볼트30: horizontal member 40: horizontal tension bolt

50 : 경사버팀대 60 : 고정재50: inclined brace 60: fixing material

70 : 제1고정너트 75 : 중공형 돌출부(제1고정너트)70: first fixing nut 75: hollow protrusion (first fixing nut)

80 : 제2고정너트 85 : 중공형 돌출부(제2고정너트)80: second fixing nut 85: hollow protrusion (second fixing nut)

90 : 제3고정너트90: third fixing nut

본 발명은 교량상판, 고층건물 등의 수직경사버팀대 상부에 수평경사버팀대을 축조하기 위해 설치하는 가설재에 관한 것으로서, 고정재, 수직재, 수평재, 경사버팀대, 수평인장볼트 등을 조립하여 설치하고, 상기 수평인장볼트를 풀어냄으로서 간단히 해체되는 캔틸레버형 가설구조에 관한 것이다.The present invention relates to a temporary material installed to build a horizontal tilt brace on top of a vertical tilt brace such as a bridge plate, a high-rise building, and installs a fixed material, a vertical material, a horizontal material, an inclined brace, a horizontal tensioning bolt, and the like, and the horizontal tension It relates to a cantilever type temporary structure which is simply dismantled by loosening a bolt.

교량상판, 고층건물의 상부 등의 상부 구조물 구축을 위해서는, 공사 중의 구체콘크리트, 작업인력 등의 하중을 지지하고, 공사 후에 해체되는 가설재가 필요하다. 가설재의 형태는 여러 가지가 있는데, 교량, 건축물 등의 구조형태, 현장지형, 가설높이, 교량하부 등의 교통상태, 공기 및 공사비 등의 여러 종합적인 요소를 고려하여 선정하게 된다. In order to construct upper structures such as bridge decks and upper parts of high-rise buildings, temporary materials that support loads such as concrete concrete and workforce during construction are dismantled after construction. There are many types of temporary materials, which will be selected in consideration of various general factors such as the structure of bridges and buildings, site topography, height of construction, traffic conditions such as the bottom of bridges, air and construction costs.

종래에는 교량상판, 고층건물의 상부 등 상부 구조물을 설치하기 위한 가설 공법으로는, 이미 축조된 교각 사이에 거더를 지지하기 위한 가교각을 설치하고 교각 하부 지반으로부터 시스템 서포트 등을 사용하여 동바리를 설치한 후 그 상부로 슬래브 콘크리트 타설을 위한 거푸집을 설치하는 동바리 공법, 교각 상부로 목재 동바리를 설치하는 목재 동바리 공법 또는 기계화된 동바리공과 거푸집을 사용하여 1스팬을 한번에 시공하는 이동식 비계 공법 등을 주로 적용해 왔다.Conventionally, as a temporary construction method for installing upper structures such as bridge decks and upper parts of high-rise buildings, bridge bridges are installed to support girders between bridges already constructed, and copper bars are installed by using system supports from lower foundations. After that, it mainly applies to the dong-bar method for installing the slab concrete at the upper part, the wood-bar method for installing the wooden club at the top of the pier, or the mobile scaffolding method for constructing one span at a time using mechanized copper ball and formwork. I have been.

하지만 교각 하부 지반으로부터 동바리를 설치하는 동바리 공법은 가설높이가 높아지면 많은 자재와 인력을 필요로 하고 형하공간이 가설공간으로 확보되어야 하는 단점이 뒤따르며, 동바리 및 거푸집의 설치 및 해체를 위한 작업공간 및 안전성을 확보하기 위해서 거더 상부에 돌출된 스터드 볼트에서 철선을 연결한 후 측면으로 내려 단관비계를 묶어 작업발판 또는 안전망 등의 가설재를 설치하는 비계작업이 선행되어야만 한다. However, the Dongbari method of installing Dongbari from the bottom of the bridge has a disadvantage of requiring a lot of materials and manpower when the height of the construction is high, and the geometry space to be secured as a temporary space, and a work space for the installation and dismantling of the Dongbari and the formwork. And to ensure safety, the scaffolding work to install a temporary scaffold, such as work scaffolding or safety nets, by connecting the iron wires from the stud bolts protruding on the girder and lowering the side pipe scaffolding.

한편, 목재 동바리를 설치하는 공법은 거더와 거더사이에 작업대 및 슬래브 동바리를 소요간격으로 설치한 후 합판 등으로 슬래브 거푸집을 조립하는 방식으로 이루어지는데, 목재 동바리는 가공성이 좋고 초기 비용이 저렴한 반면 부재 자체의 강성이 좋지 않아 좁은 간격으로 설치되어야 하고 설치와 해체작업이 반복되면서 쉽게 파손되어 전용율을 떨어뜨리며 결과적으로 가설공사비를 증대시킨다. On the other hand, the construction method for installing wood clubs is to install the workbench and slab clubs between the girders and girders at required intervals, and then assemble the slab formwork with plywood, etc. Due to its poor rigidity, it must be installed at narrow intervals, and it is easily damaged due to repeated installation and dismantling operations, which lowers the capacity ratio and consequently increases the construction cost.

또한, 이동식 비계 공법에서는 지반에서부터 동바리를 설치할 필요가 없어 형하공간이나 지반 등의 조건에 좌우되지 않고 시공할 수 있으나 설치작업이 복잡하고 대형장비의 투입이 필수적이다. In addition, in the mobile scaffolding method, it is not necessary to install the copper bar from the ground, so it can be installed without being influenced by the conditions of the mold space or the ground, but the installation work is complicated and the input of large equipment is essential.

한편, 가설재는 공사 완료 후 해체되어야 하므로 가설재의 해체작업도 설치작업 못지 않게 중요하며, 가설재를 해체하는데 소요되는 비용, 시간, 인력 등은 교량, 건물 등의 전체 공사비, 공기 등에 큰 영향을 미칠 수 있다. On the other hand, the temporary material should be dismantled after the construction is completed, so the dismantling work of the temporary material is just as important as the installation work, and the cost, time, and manpower required for dismantling the temporary material can have a big influence on the overall construction cost of the bridge, building, etc have.

따라서 본 발명자는 가설재 해체를 위한 별도의 비계나 대형장비 등이 없이 간단한 조작으로 해체작업을 수행함으로서, 해체작업에 소요되는 비용 및 시간을 대폭 줄일 수 있는 가설구조를 개발하였다. Therefore, the present inventors have developed a temporary structure that can significantly reduce the cost and time required for dismantling by performing the dismantling operation by a simple operation without separate scaffolding or large equipment for dismantling the temporary material.

본 발명의 목적은 별도의 비계 또는 인양장비 없이 간단한 조작만으로 해체할 수 있는 가설재, 상기 가설재를 이용하여 지상작업이 어려운 교량 상부 구조 등의 시공방법 및 상기 가설재의 해체 방법을 제공하여 가설재 해체에 소요되는 비용 및 시간을 대폭 줄일 수 있도록 하는 것이다.An object of the present invention is to provide a construction method such as a bridge superstructure difficult to ground work using the temporary construction material, the construction method and the method of dismantling the temporary construction material, which can be dismantled by simple operation without a separate scaffolding or lifting equipment. To significantly reduce the cost and time required.

본 발명은 교각, 빌딩 등의 기 축조 구조물 위에 교량상판, 상부 슬래브 등 지상작업이 어려운 상부 구조물을 축조하기 위해 설치하는 가설재에서, 소정의 길 이를 갖는 수직재; 상기 수직재의 상단과 결합하는 연결판; 소정의 길이를 갖으며, 길이방향으로 중공(中空)부가 형성되어 있는 수평재; 상기 수평재 중공부에 끼워져 상기 수평재의 양단으로 돌출하는 봉형부재로서, 외주면에 수나사산이 형성되어 있는 수평인장볼트; 소정의 길이를 갖으며, 하단은 상기 수직재의 하단과 결합하고, 상단은 상기 수평재와 결합하는 경사버팀대; 직각결합하는 수직판과 수평판으로 구성된 고정재; 상기 고정재 수직판의 전면에 배치되는 제1고정너트; 상기 연결판의 배면에 용접되어 부착된 제2고정너트; 및 상기 수평인장볼트 후단과 결합하여 상기 수평재를 고정시키는 제3고정너트; 를 포함하여 구성되되, 상기 고정재 수평판은 기 축조 구조물의 상단에 고정되고, 상기 수평인장볼트의 전단은 상기 제1고정너트, 상기 고정재 수직판 및 상기 연결판을 차례로 관통하여 상기 제2고정너트와 결합하는 것을 특징으로 하는 캔틸레버형 가설재를 제공한다.The present invention is a temporary material installed to build an upper structure difficult to work on the ground, such as a bridge top plate, an upper slab on a base construction structure such as a bridge, a building, a vertical member having a predetermined length; A connecting plate coupled to an upper end of the vertical member; A horizontal member having a predetermined length and having a hollow portion formed in the longitudinal direction; A bar-shaped member inserted into the horizontal member hollow part and projecting to both ends of the horizontal member, the horizontal tension bolt having a male thread formed on an outer circumferential surface thereof; It has a predetermined length, the lower end is coupled to the lower end of the vertical member, the upper end is inclined brace to combine with the horizontal member; Fixing member consisting of a vertical plate and a horizontal plate to be perpendicularly coupled; A first fixing nut disposed on the front surface of the fixing member vertical plate; A second fixing nut welded to the rear surface of the connecting plate; And a third fixing nut coupled to the rear end of the horizontal tension bolt to fix the horizontal member. It is configured to include, wherein the fixing member horizontal plate is fixed to the top of the base structure, the front end of the horizontal tensioning bolt through the first fixing nut, the fixing member vertical plate and the connecting plate in turn to the second fixing nut It provides a cantilever type temporary material, characterized in that coupled with.

한편, 청구항 제1항 내지 제3항의 캔틸레버형 가설재를 이용하여 교각, 빌딩 등의 기 축조 구조물 위에 교량상판, 상부 슬래브 등 지상작업이 어려운 상부 구조물을 축조하는 방법에서, (a) 상기 고정재를 작업면에 배치하고, 상기 제2고정너트가 용접되어 있는 연결판에 다수개의 상기 수직재를 일정간격으로 배치하여 결합시키고, 상기 수직재마다 상기 경사버팀대를 연결시키는 단계; (b) 상기 경사버팀대마다 상기 수평재를 연결시키고, 상기 수평인장볼트를 상기 수평재 중공부에 끼우고, 상기 수평인장볼트의 전단은 상기 제1고정너트, 상기 고정재 수직판 및 상기 연결판을 차례로 관통하여 상기 제2고정너트와 결합하도록 하고, 후단은 상기 제3 고정너트와 결합시켜 캔틸레버형 가설재의 조립을 완성하는 단계; (c) 상기 고정재의 수평판을 상기 기 축조 구조물 상단에 고정시켜 상기 캔틸레버형 가설재를 상기 기 축조 구조물에 설치하는 단계; (d) 상기 다수개의 수평재를 가로지르는 장선을 다수개 설치하고, 상기 장선 위에 프리캐스트 콘크리트패널을 설치하는 하는 단계; (e) 상기 수평재 위에 안전 난간대 및 측벽거푸집을 설치하고 구체콘크리트를 타설, 양생하여 상기 상부 구조물을 축조하는 단계; 를 포함하는 것을 특징으로 하는 캔틸레버형 가설재를 이용한 구조물 축조방법을 제공한다.On the other hand, using the cantilever-type temporary material of claim 1 to claim 3 in the method of building an upper structure difficult to work on the ground, such as bridge deck, upper slab on the existing structure of bridges, buildings, etc. (a) working the fixing material Arranging the plurality of vertical members at predetermined intervals on the connecting plate to which the second fixing nut is welded, and connecting the inclined braces to the vertical members; (b) connecting the horizontal member to each of the inclined braces, and inserting the horizontal tension bolt to the hollow of the horizontal member, and the front end of the horizontal tension bolt passes through the first fixing nut, the fixing member vertical plate, and the connecting plate in order. By coupling to the second fixing nut, the rear end is coupled to the third fixing nut to complete the assembly of the cantilever type temporary material; (c) fixing the horizontal plate of the fixing member to an upper end of the base structure to install the cantilever type temporary member on the base structure; (d) installing a plurality of joists crossing the plurality of horizontal members, and installing a precast concrete panel on the joists; (e) constructing the upper structure by installing a safety handrail and sidewall formwork on the horizontal member and placing and curing concrete concrete; It provides a structure construction method using a cantilever-type temporary material, characterized in that it comprises a.

또한, 본 발명은 청구항 제1항 내지 제3항 중 어느 한 항의 캔틸레버형 가설재를 이용하여 교각, 빌딩 등의 기 축조 구조물 위에 교량상판, 상부 슬래브 등의 상부 구조물을 축조한 후 상기 캔틸레버형 가설재를 해체하는 방법에서, (a) 상기 제3고정너트를 풀어 상기 수평재를 이완시키는 단계; 및 (b) 상기 수평인장볼트를 풀면서 인발하여 상기 고정재로부터 일체화된 연결판, 수직재, 경사버팀대 및 수평재를 한번에 해체시키는 단계; 를 포함하여 구성되는 캔틸레버형 가설재 해체방법을 제공한다.In addition, the present invention by using the cantilever-type temporary member of any one of claims 1 to 3 to build an upper structure, such as a bridge top plate, upper slab, etc. on the existing construction structures such as bridges, buildings, and the like cantilever-type temporary material In the disassembling method, (a) loosening the horizontal member by loosening the third fixing nut; And (b) dismounting the connecting plate, vertical member, inclined brace, and horizontal member integrated from the fixing member by pulling while unwinding the horizontal tensioning bolt. It provides a cantilever type temporary material dismantling method comprising a.

도1a 내지 도1e는 본 발명에 따른 캔틸레버형 가설재를 이용한 구조물 축조방법을 단계별로 도시한 것이다. 도2는 고정재, 연결판, 수평인장볼트, 제1고정너트 및 제2고정너트 연결부위를 상세히 도시한 것이다. 도3a 및 도3b는 캔틸레버형 가설재의 해체방법을 단계별로 도시한 것이다.Figures 1a to 1e shows step by step the structure construction method using the cantilever type temporary material according to the present invention. Figure 2 shows in detail the fixing member, connecting plate, horizontal tensioning bolt, the first fixing nut and the second fixing nut. 3A and 3B illustrate step-by-step methods of disassembling the cantilevered temporary material.

이하, 각 도면과 함께 본 발명의 내용을 상세히 설명하기로 한다.Hereinafter, the content of the present invention will be described in detail with reference to the drawings.

이하에서는 본 특허출원명세서에서는 이미 축조된 교각, 건물 등은 "기 축조 구조물"이라 하고, 가설재에 의해 축조되는 교량상판, 빌딩의 상부 슬래브 등은 "상부 구조물"이라 한다.Hereinafter, in the present patent application specification, bridges, buildings, and the like, which have already been constructed, are referred to as "base construction structures", and bridge tops and upper slabs of buildings constructed by temporary materials are referred to as "upper structures".

Ⅰ. I. 캔틸레버형Cantilever Type 가설구조 Construction

본발명에 따른 캔틸레버형 가설재가 기 축조 구조물에 설치된 상태는 도1c에 도시되었다. 상기 캔틸레버형 가설재는 상부 구조물 축조 작업시의 하중을 직접 받는 수평재(30), 상기 하중에 의한 회전모멘트를 수직재로 전달하는 경사버팀대(50), 상기 회전모멘트를 받아 기 축조 구조물의 측벽으로 전달하는 수직재(10)로 구성되며, 상기 수직재(10)와 수평재(30)를 연결하여 가설재를 기 축조 구조물(1)에 설치하기 위한 고정재(60), 연결판(20), 수평인장볼트(40), 제1고정너트(70), 제2고정너트(80)를 포함하여 구성된다.A state in which the cantilever type temporary material according to the present invention is installed in the base structure is shown in FIG. 1C. The cantilever-type temporary material is a horizontal member 30 directly receiving a load during the construction of the upper structure, an inclined brace 50 for transmitting the rotation moment by the load to the vertical member, and receives the rotation moment to the side wall of the base construction structure Consists of the vertical member 10, connecting the vertical member 10 and the horizontal member 30, the fixing member 60, the connecting plate 20, horizontal tension bolt 40 for installing the temporary member to the base structure (1) The first fixing nut 70 and the second fixing nut 80 are configured.

상기 수직재(10)와 수평재(30)는 각파이프를 사용할 수 있으며, 필요에 따라 길이를 조절할 수 있다. 특히, 상기 수평재(30)에는 후술할 수평인장볼트(40)가 삽입될 수 있도록 길이방향으로 중공부가 형성되어 있어야 한다. 상기 경사버팀대(50)는 하단은 상기 수직재(10)의 하단과 결합하고 상단은 상기 수평재(30)와 결 합하게 되는데, 상기 경사버팀대(50)도 길이를 조절할 수 있도록 구성하고 수직재(10)와 수평재(30)에 연결되는 각 절점은 힌지형으로 구성하여 미세한 조절이 가능하도록 하는 것이 바람직하다. The vertical member 10 and the horizontal member 30 may use an angle pipe, and the length may be adjusted as necessary. In particular, the horizontal member 30 should be a hollow portion in the longitudinal direction so that the horizontal tension bolt 40 to be described later to be inserted. The inclined brace 50 is coupled to the bottom and the bottom of the vertical member 10 and the top is coupled to the horizontal member 30, the inclined brace 50 is also configured to adjust the length and vertical member (10) And each node connected to the horizontal member 30 is preferably configured in the hinge type to enable fine adjustment.

상기 고정재(60)는 가설재를 기 축조 구조물(1)에 고정시키기 위한 부재로서 직각결합하는 수직판(61)과 수평판(62)으로 구성된다. 상기 고정재 수평판(62)은 상기 기 축조 구조물(1)의 상단에 고정되는데, 구체적으로는 교량의 보, 건축물의 골조 등에 부착 설치된다.The fixing member 60 is composed of a vertical plate 61 and a horizontal plate 62 to be perpendicularly coupled as a member for fixing the temporary member to the base structure (1). The fixing member horizontal plate 62 is fixed to the upper end of the base construction structure 1, specifically, is attached to the beam of the bridge, the frame of the building, and the like.

상기 연결판(20)은 상기 수직재의 상단에 결합되는 판재로서, 상기 연결판(20)과 수직재는 용접하여 일체화시키는 것이 바람직하다. The connecting plate 20 is a plate that is coupled to the upper end of the vertical member, the connecting plate 20 and the vertical member is preferably welded to integrate.

상기 수평인장볼트(40)는 외주면에 수나사산이 형성되어 있고, 상기 수평재(30) 중공부에 끼워 상기 수평재의 양단으로 돌출하도록 한다. 상기 수평인장볼트(40)의 전단은 상기 제1고정너트(70), 상기 고정재 수직판(61) 및 상기 연결판(20)을 차례로 관통한 후 상기 제2고정너트(80)와 결합, 고정됨으로서, 상기 고정재(60), 연결판(20), 수직재(10), 수평재(30)를 하나의 구조체로 결합시키는 역할을 한다.(도2 참조) The horizontal tension bolt 40 has a male thread formed on the outer circumferential surface thereof, and is inserted into the hollow of the horizontal member 30 so as to protrude to both ends of the horizontal member. The front end of the horizontal tensioning bolt 40 passes through the first fixing nut 70, the fixing member vertical plate 61, and the connecting plate 20 in turn, and then is coupled to and fixed to the second fixing nut 80. As a result, the fixing member 60, the connecting plate 20, the vertical member 10, and the horizontal member 30 serve to combine the structure into one structure (see FIG. 2).

부연설명하면, 상기 고정재(60)의 수직판(61)과 연결판(20)은 맞닿아 있어야 하는데, 상기 수직판(61)의 전면에는 제1고정너트(70)를 배치하고 상기 연결판(20) 의 배면에는 제2고정너트(80)를 용접하여 일체화시켜 두어, 상기 수평인장볼트(40)의 전단이 상기 제1,2고정너트(70, 80)에 의해 고정되도록 하는 것이다.In detail, the vertical plate 61 and the connecting plate 20 of the fixing member 60 should be in contact with each other, and the first fixing nut 70 is disposed on the front surface of the vertical plate 61 and the connecting plate ( The second fixing nut 80 is welded and integrated on the rear surface of the 20 so that the front end of the horizontal tensioning bolt 40 is fixed by the first and second fixing nuts 70 and 80.

이 때, 상기 고정재의 수직판(61) 및 연결판(20)의 판면에는 상기 수평인장볼트의 관통부위에 각각 체결공을 형성시켜 두면 상기 수평인장볼트(40)의 결합을 용이하게 할 수 있다. At this time, the fastening holes may be formed in the penetrating portions of the horizontal tensioning bolts on the plate surface of the vertical plate 61 and the connecting plate 20 of the fixing member, thereby facilitating the coupling of the horizontal tensioning bolts 40. .

또한, 상기 제1고정너트(70)에는, 상기 고정재 수직판(61)의 체결공에 끼워지고, 상기 수직판(61)의 두께 이상의 폭을 갖으며, 내주면의 암나사산은 너트홀의 암나사산과 연속되도록 구성된 중공(中空)형 돌출부(75)를 형성시키고, 상기 제2고정너트(80)에는, 상기 연결판(20) 체결공에 끼워지고, 상기 연결판(20)의 두께와 대응하는 폭을 갖으며, 내주면의 암나사산은 너트홀의 암나사산과 연속되도록 구성된 중공(中空)형 돌출부(85)를 형성시키면 상기 수평인장볼트(40) 외주면의 수나사산의 파손 및 마모를 막을 수 있다.In addition, the first fixing nut 70 is fitted into the fastening hole of the fixing plate vertical plate 61, has a width greater than or equal to the thickness of the vertical plate 61, and the female thread of the inner circumferential surface is continuous with the female thread of the nut hole. The hollow hollow protrusion 75 is formed, and the second fixing nut 80 is fitted into the connection hole of the connecting plate 20 and has a width corresponding to the thickness of the connecting plate 20. The female thread of the inner circumferential surface of the inner thread surface can prevent breakage and wear of the male thread of the outer circumferential surface of the horizontal tension bolt 40 by forming a hollow protrusion 85 configured to be continuous with the female thread of the nut hole.

위와 같은 제1,2고정너트의 중공형 돌출부(75, 85)가 없다면 상기 고정재 수직판(61) 및 연결판(20)을 관통하는 부위에서는 상부 구조물로 인한 전단하중을 수평인장볼트(40)가 그대로 받게 되고, 특히, 수평인장볼트(40)의 해체시 제1,2고정너트(70, 80)의 조임에 의해 일부 분산되는 전단하중까지도 순간적으로 고정재 수직판(61) 및 연결판(20)의 관통부위에 쏠리게 되어 상기 수평인장볼트(40) 외주면의 수나사산이 훼손될 가능성이 있다.If there is no hollow protrusions 75 and 85 of the first and second fixing nuts as described above, the shear load due to the upper structure is the horizontal tension bolt 40 at the portion passing through the fixing plate vertical plate 61 and the connecting plate 20. In particular, even when the horizontal tension bolt 40 is dismantled, even when the shear load is partially distributed by tightening the first and second fixing nuts 70 and 80, the fixing member vertical plate 61 and the connecting plate 20 ), The male thread on the outer peripheral surface of the horizontal tension bolt 40 may be damaged.

따라서, 상기 제1,2고정너트의 중공형 돌출부(75, 85)는 각각 고정재 수직판 (61)및 연결판(20)의 관통부위를 감싸 보호하는 형태이므로 상기 수평인장볼트(40) 외주면의 수나사산이 보호되는 것이고, 이에 따라 수평인장볼트(40)의 전용횟수를 늘려 자재절감의 효과도 누릴 수 있게 된다.Therefore, since the hollow protrusions 75 and 85 of the first and second fixing nuts are formed to surround and protect the through portions of the fixing member vertical plate 61 and the connecting plate 20, respectively, the outer peripheral surface of the horizontal tension bolt 40 The male thread is protected, thereby increasing the number of times of the horizontal tensioning bolt 40 to enjoy the effect of material savings.

Ⅱ. II. 캔틸레버형Cantilever Type 가설재를 이용한 구조물 축조방법 Structure construction method using temporary materials

본 발명에 따른 캔틸레버형 가설재를 이용한 상부 구조물 축조방법은, 교량상판, 고층건물의 상부 등 지상작업이 어려운 상부 구조물을 축조하는 방법으로서 (a)단계 내지 (e)단계를 포함한다.The upper structure construction method using the cantilever-type temporary material according to the present invention, a method for constructing the upper structure difficult to ground work, such as a bridge top plate, a high-rise building includes a step (a) to (e).

상기 (a)단계는 상기 고정재(60)를 작업면에 배치하고, 상기 제2고정너트(80)가 용접되어 있는 연결판(20)에 다수개의 상기 수직재(10)를 일정간격으로 배치하여 결합시키고, 상기 수직재(10)마다 상기 경사버팀대(50)를 연결시키는 단계이다. (도1a 참조)In the step (a), the fixing member 60 is disposed on the working surface, and the plurality of vertical members 10 are disposed at predetermined intervals on the connecting plate 20 to which the second fixing nut 80 is welded. And, the step of connecting the inclined brace 50 for each of the vertical member (10). (See Figure 1a)

상기 (b)단계는 상기 경사버팀대(50)마다 상기 수평재(30)를 연결시키고, 상기 수평인장볼트(40)를 상기 수평재(30) 중공부에 끼우고, 상기 수평인장볼트(40)의 전단은 상기 제1고정너트(70), 상기 고정재 수직판(61) 및 상기 연결판(20)을 관통하여 상기 제2고정너트(80)와 결합하도록 하고, 후단은 상기 제3고정너트(90) 와 결합시켜 가설재를 조립하는 단계이다. (도1b 참조)In the step (b), the horizontal member 30 is connected to each of the inclined braces 50, and the horizontal tension bolt 40 is inserted into the hollow of the horizontal member 30, and the front end of the horizontal tension bolt 40 is removed. The first fixing nut 70, the fixing member vertical plate 61 and the connecting plate 20 to be coupled to the second fixing nut 80, the rear end of the third fixing nut 90 Assembling the temporary material by combining with. (See Figure 1b)

상기 (c)단계는 상기 고정재의 수평판(62)을 기 축조 구조물(1) 상단에 고정시켜 상기 가설재를 상기 기 축조 구조물(1)에 부착 설치하는 단계이다. 상기 고정재(60)는 교량의 보, 건축물의 골조 등의 상부 구조재(2)와 결합하여 가설재 전체를 고정시켜 주는 것이므로 상기 수평판(62)과 기 축조 구조물(1)의 접촉 면적은 충분히 확보되어야 한다. (도1c 참조)In the step (c), the horizontal plate 62 of the fixing member is fixed to the upper end of the base construction structure 1 to attach the temporary construction material to the base construction structure 1. Since the fixing member 60 is fixed to the temporary construction material by combining with the upper structural member 2, such as a bridge of a bridge, a frame of a building, the contact area between the horizontal plate 62 and the base construction structure 1 should be sufficiently secured. do. (See Figure 1c)

상기 (d)단계는 상기 다수개의 수평재(30)를 가로지르는 장선(3)을 다수개 설치하고, 상기 장선(3) 위에 프리캐스트 콘크리트패널(4)을 설치하는 하는 단계이다. 상기 프리캐스트 콘크리트패널(4)은 슬래브거푸집널의 역할을 수행하며 구체콘크리트(7) 타설, 양생 후 상부 구조물와 일체화된다. 상기 장선(3)은 상기 프리캐스트 콘크리트패널(4)에 미치는 하중을 고르게 분산시키는 역할을 한다. (도1d 참조)In the step (d), a plurality of joists 3 crossing the plurality of horizontal members 30 are installed, and a precast concrete panel 4 is installed on the joists 3. The precast concrete panel 4 serves as a slab formwork and is integrated with the upper structure after placing and curing concrete concrete (7). The joist 3 serves to evenly distribute the load on the precast concrete panel 4. (See Figure 1D)

상기 (e)단계는 상기 수평재 위에 안전 난간대(5) 및 측벽거푸집(6)을 설치하고 구체콘크리트(7)를 타설, 양생하여 상부 구조물을 축조하는 단계이다. 이 때, 상기 수평재(30)의 길이는 필요에 따라 연장하여 콘크리트 관리용 통로로 이용할 수 있다. (도1e 참조)The step (e) is a step of constructing the upper structure by installing a safety handrail 5 and side wall formwork 6 on the horizontal member, and placing and curing concrete concrete 7. At this time, the length of the horizontal member 30 can be used as a concrete management passage extending as necessary. (See Figure 1e)

Ⅲ. III. 캔틸레버형Cantilever Type 가설재 해체방법 Dismantling Method

본 발명에 따른 캔틸레버형 가설재 해체방법은 별도의 비계 또는 인양장비 없이 간단한 조작만으로 가설재를 해체할 수 있는 방법으로서 다음과 같은 (a)단계 및 (b)단계를 포함한다.The cantilever type temporary material dismantling method according to the present invention includes a method of dismantling the temporary material by a simple operation without a separate scaffolding or lifting equipment, and includes the following steps (a) and (b).

상기 (a)단계는 제3고정너트(90)를 풀어 상기 수평재를 이완시키는 단계이다. 청구항 제1항 내지 제3항 중 어느 한 항의 캔틸레버형 가설재를 이용하여 교량, 고층건물 등의 상부에 구조물을 축조한 후, 작업자가 상기 상부 구조물 위에서 측벽거푸집(6)과 안전 난간대(5)를 해체하고 상기 제3고정너트(90)를 풀어낼 수 있으며, 제3고정너트(90)가 풀리면 수평재가 이완되어, 상기 수평재를 가로지르도록 배치된 장선(3)을 해체할 수 있게 된다. (도3a 참조)Step (a) is to loosen the horizontal member by loosening the third fixing nut (90). After constructing a structure on the upper part of a bridge, a high-rise building, etc. using the cantilever-type temporary material of any one of Claims 1-3, an operator places the side wall formwork 6 and the safety railing 5 on the said upper structure. It is possible to disassemble and release the third fixing nut 90. When the third fixing nut 90 is released, the horizontal member is relaxed to dismantle the joists 3 arranged to cross the horizontal member. (See Figure 3a)

상기 (b)단계는 상기 수평인장볼트(40)를 풀면서 인발하여 상기 고정재(60)로부터 일체화된 연결판(20), 수직재(10), 경사버팀대(50) 및 수평재(30)를 한번에 해체시키는 단계로서 본 (b)단계 작업의 수행을 통해 가설재 해체작업은 완료된다. 이 때. 상부 구조물에 매립되어 남아 있는 고정재(60)를 제외한 다른 가설부재는 다시 조립하여 사용할 수 있다. (도3b 참조)In the step (b), the horizontal tensioning bolt 40 is pulled out to disassemble the connecting plate 20, the vertical member 10, the inclined brace 50, and the horizontal member 30 that are integrated from the fixing member 60 at one time. The temporary dismantling work is completed by performing this step (b). At this time. Other temporary members other than the fixing member 60 embedded in the upper structure may be reassembled and used. (See Figure 3b)

상기한 바와 같은 본 발명에 따르면 다음과 같은 효과가 있다.According to the present invention as described above has the following effects.

1. 교량이나 고층건물 같이 별도의 비계 또는 인양장비 등이 필요한 여건에서는 기존의 가설재의 경우 해체비가 설치비의 100 ~ 150% 가량을 실행원가로 산정하는 것이 일반적이나, 본 발명에 따른 캔틸레버형 가설재를 이용하면, 작업자가 축조 완료된 경사버팀대 위에서 수평인장볼트를 풀어냄으로서 수직재 등이 한번에 해체되도록 할 수 있어, 해체비 및 해체시간을 크게 줄일 수 있다.1. In a situation where a separate scaffold or lifting equipment is required, such as a bridge or a high-rise building, the dismantling cost of the existing temporary material is generally estimated to be 100 to 150% of the installation cost as the execution cost, but the cantilever type temporary material according to the present invention In this case, the worker can dismantle the vertical tensioning bolts at one time by releasing the horizontal tensioning bolts on the inclined brace that is completed, thereby greatly reducing the dismantling cost and dismantling time.

2. 중공형 돌출부가 형성되어 있는 제1,2고정너트를 사용하면 수직재 해체를 위해 수평인장볼트를 풀 때 및 수평인장볼트 해체를 위해 수평인장볼트를 축방향 바깥쪽으로 인발할 경우에 수직재와 수평인장볼트간에 걸려있는 전단하중으로 인한 수평인장볼트 외주면의 수나사산의 파손 또는 마모를 방지할 수 있다.2. If the first and second fixing nuts with hollow protrusions are used, the vertical member and the horizontal member are removed when the horizontal tension bolt is released for dismantling the vertical material and when the horizontal tension bolt is pulled outward in the axial direction for dismantling the horizontal tension bolt. It can prevent the damage or wear of external thread on the outer peripheral surface of horizontal tension bolt due to shear load between tension bolts.

Claims (5)

교각, 빌딩 등의 기 축조 구조물 위에 교량상판, 상부 슬래브 등 지상작업이 어려운 상부 구조물을 축조하기 위해 설치하는 가설재에서,In the temporary material installed to build upper structures such as bridge decks and upper slabs, which are difficult to work on the ground, on top of existing structures such as bridges and buildings, 소정의 길이를 갖는 수직재;A vertical member having a predetermined length; 상기 수직재의 상단과 결합하는 연결판;A connecting plate coupled to an upper end of the vertical member; 소정의 길이를 갖으며, 길이방향으로 중공(中空)부가 형성되어 있는 수평재;A horizontal member having a predetermined length and having a hollow portion formed in the longitudinal direction; 상기 수평재 중공부에 끼워져 상기 수평재의 양단으로 돌출하는 봉형부재로서, 외주면에 수나사산이 형성되어 있는 수평인장볼트;A bar-shaped member inserted into the horizontal member hollow part and projecting to both ends of the horizontal member, the horizontal tension bolt having a male thread formed on an outer circumferential surface thereof; 소정의 길이를 갖으며, 하단은 상기 수직재의 하단과 결합하고, 상단은 상기 수평재와 결합하는 경사버팀대; It has a predetermined length, the lower end is coupled to the lower end of the vertical member, the upper end is inclined brace to combine with the horizontal member; 직각결합하는 수직판과 수평판으로 구성된 고정재;Fixing member consisting of a vertical plate and a horizontal plate to be perpendicularly coupled; 상기 고정재 수직판의 전면에 배치되는 제1고정너트;A first fixing nut disposed on the front surface of the fixing member vertical plate; 상기 연결판의 배면에 용접되어 부착된 제2고정너트; 및A second fixing nut welded to the rear surface of the connecting plate; And 상기 수평인장볼트 후단과 결합하여 상기 수평재를 고정시키는 제3고정너트; 를 포함하여 구성되되,A third fixing nut coupled to the rear end of the horizontal tension bolt to fix the horizontal member; Consists of including 상기 고정재 수평판은 상기 기 축조 구조물의 상단에 고정되고, The fixing member horizontal plate is fixed to the top of the base construction structure, 상기 수평인장볼트의 전단은 상기 제1고정너트, 상기 고정재 수직판 및 상기 연결판을 차례로 관통하여 상기 제2고정너트와 결합하는 것을 특징으로 하는 캔틸레버형 가설재.The front end of the horizontal tension bolt cantilever-type temporary member, characterized in that through the first fixing nut, the fixing member vertical plate and the connecting plate in order to combine with the second fixing nut. 제1항에서,In claim 1, 상기 고정재 수직판 및 연결판의 판면에는 상기 수평인장볼트가 관통하는 부위에 각각 체결공이 형성되어 있는 것을 특징으로 하는 캔틸레버형 가설재.Cantilever-type temporary material, characterized in that the fastening hole is formed in each of the fixing plate vertical plate and the plate surface of the horizontal tension bolt penetrates. 제2항에서,In claim 2, 상기 제1고정너트는, 상기 고정재 수직판 체결공에 끼워지고, 상기 수직판의 두께 이상의 폭을 갖으며, 내주면에는 너트홀의 암나사산과 연속되는 암나사산이 형성된 중공(中空)형 돌출부가 포함되어 구성되고,The first fixing nut is inserted into the fixing plate vertical plate fastening hole, has a width greater than or equal to the thickness of the vertical plate, the inner circumferential surface comprises a hollow protrusion formed with a female thread continuous with the female thread of the nut hole , 상기 제2고정너트는, 상기 연결판 체결공에 끼워지고, 상기 연결판의 두께와 대응하는 폭을 갖으며, 내주면에는 너트홀의 암나사산과 연속되는 암나사산이 형성된 중공(中空)형 돌출부가 포함되어 구성되는 것을 특징으로 하는 캔틸레버형 가설재.The second fixing nut is fitted into the connecting plate fastening hole, has a width corresponding to the thickness of the connecting plate, and the inner peripheral surface includes a hollow protrusion formed with a female thread continuous with the female thread of the nut hole. Cantilever type temporary material, characterized in that. 제1항 내지 제3항 중 어느 한 항의 캔틸레버형 가설재를 이용하여 교각, 빌딩 등의 기 축조 구조물 위에 교량상판, 상부 슬래브 등 지상작업이 어려운 상부 구조물을 축조하는 방법에서,In the method of constructing an upper structure, such as bridge deck, upper slab, difficult to ground work on the existing construction structures such as bridges, buildings, etc. using the cantilever-type temporary material of any one of claims 1 to 3, (a) 상기 고정재를 작업면에 배치하고, 상기 제2고정너트가 용접되어 있는 연결판에 다수개의 상기 수직재를 일정간격으로 배치하여 결합시키고, 상기 수직재마다 상기 경사버팀대를 연결시키는 단계;(a) arranging the fixing member on a working surface, arranging the plurality of vertical members at a predetermined interval to the connecting plate on which the second fixing nut is welded, and connecting the inclined braces to the vertical members; (b) 상기 경사버팀대마다 상기 수평재를 연결시키고, 상기 수평인장볼트를 상기 수평재 중공부에 끼우고, 상기 수평인장볼트의 전단은 상기 제1고정너트, 상기 고정재 수직판 및 상기 연결판을 차례로 관통하여 상기 제2고정너트와 결합하도록 하고, 후단은 상기 제3고정너트와 결합시켜 캔틸레버형 가설재의 조립을 완성하는 단계;(b) connecting the horizontal member to each of the inclined braces, and inserting the horizontal tension bolt to the hollow of the horizontal member, and the front end of the horizontal tension bolt passes through the first fixing nut, the fixing member vertical plate, and the connecting plate in order. By coupling to the second fixing nut, the rear end is coupled to the third fixing nut to complete the assembly of the cantilever type temporary material; (c) 상기 고정재의 수평판을 상기 기 축조 구조물 상단에 고정시켜 상기 캔틸레버형 가설재를 상기 기 축조 구조물에 설치하는 단계;(c) fixing the horizontal plate of the fixing member to an upper end of the base structure to install the cantilever type temporary member on the base structure; (d) 상기 다수개의 수평재를 가로지르는 장선을 다수개 설치하고, 상기 장선 위에 프리캐스트 콘크리트패널을 설치하는 하는 단계;(d) installing a plurality of joists crossing the plurality of horizontal members, and installing a precast concrete panel on the joists; (e) 상기 수평재 위에 안전 난간대 및 측벽거푸집을 설치하고 구체콘크리트를 타설, 양생하여 상기 상부 구조물을 축조하는 단계; 를 포함하는 것을 특징으로 하는 캔틸레버형 가설재를 이용한 구조물 축조방법. (e) constructing the upper structure by installing a safety handrail and sidewall formwork on the horizontal member and placing and curing concrete concrete; Structure construction method using a cantilever type temporary material, comprising a. 제1항 내지 제3항 중 어느 한 항의 캔틸레버형 가설재를 이용하여 교각, 빌딩 등의 기 축조 구조물 위에 교량상판, 상부 슬래브 등의 상부 구조물을 축조한 후 상기 캔틸레버형 가설재를 해체하는 방법에서,In the method of dismantling the cantilever-type temporary material after the construction of the upper structure, such as the bridge deck, upper slab, etc. on the base structure of the bridge, building, etc. using the cantilever-type temporary material of any one of claims 1 to 3. (a) 상기 제3고정너트를 풀어 상기 수평재를 이완시키는 단계; 및(a) releasing the third fixing nut to relax the horizontal member; And (b) 상기 수평인장볼트를 풀면서 인발하여 상기 고정재로부터 일체화된 연결판, 수직재, 경사버팀대 및 수평재를 한번에 해체시키는 단계; 를 포함하여 구성되는 캔틸레버형 가설재 해체방법.(b) dismounting the connecting plate, vertical member, inclined brace and the horizontal member integrated from the fixing member by pulling the horizontal tensioning bolt while pulling it; Cantilever-type temporary material dismantling method comprising a.
KR1020060083084A 2006-08-30 2006-08-30 Temporary cantilever resources, construction method of structure using the same and dismantling method for the same KR100760332B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020060083084A KR100760332B1 (en) 2006-08-30 2006-08-30 Temporary cantilever resources, construction method of structure using the same and dismantling method for the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020060083084A KR100760332B1 (en) 2006-08-30 2006-08-30 Temporary cantilever resources, construction method of structure using the same and dismantling method for the same

Publications (1)

Publication Number Publication Date
KR100760332B1 true KR100760332B1 (en) 2007-09-20

Family

ID=38738346

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020060083084A KR100760332B1 (en) 2006-08-30 2006-08-30 Temporary cantilever resources, construction method of structure using the same and dismantling method for the same

Country Status (1)

Country Link
KR (1) KR100760332B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101353048B1 (en) 2013-08-08 2014-01-20 피씨엠건설(주) Mold for manufacturing of precast concrete

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20000017809A (en) * 1999-07-06 2000-04-06 김희자 Over Brige Gentlever Slide Steel Form
KR20010010000A (en) * 1999-07-15 2001-02-05 송영수 Pre-cast element conjunction
JP2001140221A (en) 1999-11-15 2001-05-22 Katayose Kogyo:Kk Repair method for overhanging floor slab, and support construction for form
KR20010044894A (en) * 1999-11-01 2001-06-05 이하영 Slab sheeting construction-method for bridge

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20000017809A (en) * 1999-07-06 2000-04-06 김희자 Over Brige Gentlever Slide Steel Form
KR20010010000A (en) * 1999-07-15 2001-02-05 송영수 Pre-cast element conjunction
KR20010044894A (en) * 1999-11-01 2001-06-05 이하영 Slab sheeting construction-method for bridge
JP2001140221A (en) 1999-11-15 2001-05-22 Katayose Kogyo:Kk Repair method for overhanging floor slab, and support construction for form

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101353048B1 (en) 2013-08-08 2014-01-20 피씨엠건설(주) Mold for manufacturing of precast concrete

Similar Documents

Publication Publication Date Title
JP2603178B2 (en) Formwork equipment
US20090025309A1 (en) Seismic support and reinforcement systems
KR101011417B1 (en) System Formwork for FSM
KR102243984B1 (en) Non-supporting formwork system for retaining wall using self-supporting form and construction method thereof
US11306492B2 (en) Load bearing components and safety deck of an integrated construction system
US20230103321A1 (en) Cantilever enabled joist beam
KR100760332B1 (en) Temporary cantilever resources, construction method of structure using the same and dismantling method for the same
JPH08284439A (en) Heavy load type form timbering and member thereof
KR100373783B1 (en) A temporary bracket for construction of precast concrete beam bridge and the temporary work method using the same
JP5033334B2 (en) Tower crane support method
JP6831714B2 (en) Tower crane foundation and tower crane
KR20120003729U (en) System support Head
KR200392341Y1 (en) Fixing Device for Aerial Scaffolding
KR100469638B1 (en) Support construction for slab of prestressed concrete beam of bridge
JP3889676B2 (en) Slip form method
JP2654935B2 (en) Construction method of ribbed slab and spacer for rib reinforcement
CA3085940A1 (en) Integrated construction system
JP2004270377A (en) Column-beam preassembled reinforcement body, and preassembled reinforcement method using the same
CN218893957U (en) Temporary supporting and fixing device for butt joint of steel beams
KR200201606Y1 (en) The psc bridge beam which can institute slab mold and safety net
KR102372473B1 (en) Constuction Structure for Joint of PC-Colunm and PC-Girder Using Temporay Bracket
CN210105249U (en) Scaffold
KR200307607Y1 (en) Temporang construction sfuctare for culvating slad
KR100859194B1 (en) A safety net device for pier
JPS6133173Y2 (en)

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20120912

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20130910

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20150817

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20160823

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20180820

Year of fee payment: 12