KR100755946B1 - Composite temporary bridge - Google Patents

Composite temporary bridge Download PDF

Info

Publication number
KR100755946B1
KR100755946B1 KR1020060019785A KR20060019785A KR100755946B1 KR 100755946 B1 KR100755946 B1 KR 100755946B1 KR 1020060019785 A KR1020060019785 A KR 1020060019785A KR 20060019785 A KR20060019785 A KR 20060019785A KR 100755946 B1 KR100755946 B1 KR 100755946B1
Authority
KR
South Korea
Prior art keywords
steel
mold
span
point
branch
Prior art date
Application number
KR1020060019785A
Other languages
Korean (ko)
Inventor
양난경
Original Assignee
양난경
(주)트리탄코리아
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 양난경, (주)트리탄코리아 filed Critical 양난경
Priority to KR1020060019785A priority Critical patent/KR100755946B1/en
Application granted granted Critical
Publication of KR100755946B1 publication Critical patent/KR100755946B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D15/00Movable or portable bridges; Floating bridges
    • E01D15/12Portable or sectional bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/30Metal
    • E01D2101/32Metal prestressed

Abstract

A composite temporary bridge is provided to perform construction work economically by increasing the stiffness of a main girder installed on a support effectively and optimizing a cross section of a main girder installed on a span. A composite temporary bridge for a temporary bridge for increasing the stiffness of a main girder installed on a support(A) effectively contains an I-shaped main girder(100) for a support formed by composing an upper steel and a lower steel to an upper flange and a lower flange in the longitudinal direction, a cross beam(200) installed between a main girder for a support and a main girder for a span in the horizontal direction, a deck plate(300) for a support supported to the upper side of the cross beam and extended adjacently to the side of the upper steel in the longitudinal direction, and a deck plate(500) for a span installed on a main girder(400) for a span in the horizontal direction to abut on two ends of the deck plate for a support.

Description

합성가설교량{COMPOSITE TEMPORARY BRIDGE}Synthetic Temporary Bridge {COMPOSITE TEMPORARY BRIDGE}

도 1은 종래의 가설교량을 도시한 것이다.1 illustrates a conventional temporary bridge.

도 2a 및 도 2b는 본 발명의 지점부주형을 도시한 것이다.2A and 2B show the point mould of the present invention.

도 3은 본 발명의 합성가설교량의 설치상태도를 도시한 것이다.Figure 3 shows the installation state diagram of the synthetic temporary bridge of the present invention.

도 4a 및 도 4b는 본 발명의 합성가설교량의 정면도 및 부분측면도를 도시한 것이다.4A and 4B show front and partial side views of the synthetic temporary bridge of the present invention.

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

100:지점부주형 110:상부플랜지100: branch casting mold 110: upper flange

120:복부 130:하부플랜지120: Abdomen 130: Lower Flange

140:상연강재(T형강) 150:정착판140: stranded steel (T-shaped steel) 150: fixing plate

160:지점부상부긴장재 170:하연강재(T형강)160: branch upper part tension material 170: lower stranded steel (T-shaped steel)

200:가로보 210:브레이싱재200: grouse 210: Bracing material

300:지점부복공판 400:경간부주형300: branch cover plate 400: span section mold

500:경간부복공판 600:경간부하부긴장재500: span section plate 600: span section tension material

본 발명은 합성가설교량에 관한 것이다. 더욱 구체적으로 가설벤트에 주형을 길이방향으로 설치한 뒤, 주형 상부면에 복공판을 얹어 임시로 교통을 소통시킬 수 있는 가설교량에 관한 것이다.The present invention relates to a synthetic hypothesis bridge. More specifically, after installing the mold in the longitudinal direction to the temporary vents, and puts a perforated plate on the mold upper surface relates to a temporary bridge that can temporarily communicate traffic.

종래의 가설교량은 주형과 복공판에 의하여 시공된다.The conventional temporary bridge is constructed by a mold and a perforated plate.

즉, 도 1과 같이 가설벤트와 같은 임시지지구조물(10)을 소정의 간격을 두고 지반에 설치한 후, 상기 임시지지구조물(10) 상부면에 길이방향으로 I형 강재와 같은 주형(20)을 설치한 후, 상기 주형(20) 상부면에 얹어져 설치되는 복공판(30)을 횡방향으로 설치하되, 길이방향으로 다수의 복공판을 연속하여 설치함으로써 가설교량이 완성될 수 있도록 한다.That is, as shown in Figure 1, after installing the temporary support structure 10, such as a temporary tent on the ground at a predetermined interval, the mold 20, such as I-type steel in the longitudinal direction on the upper surface of the temporary support structure (10) After the installation, while installing the perforated plate 30 installed on the upper surface of the mold 20 in the transverse direction, by installing a plurality of perforated plates in the longitudinal direction in order to complete the temporary bridge.

이때, 복공판(30)은 단순히 주형(20) 상부면에 얹어져 설치될 뿐이므로, 주형과 복공판이 합성되어 일체로 외부하중에 저항하도록 설계하지 못하고, 오히려 복공판은 주형에 그 자중만을 부가시킬 뿐이어서 구조적으로 매우 비효율적인 주형 단면설계가 이루어질 수 밖에 없다는 문제점이 지적되었다.At this time, since the perforated plate 30 is simply installed on the upper surface of the mold 20, the mold and the perforated plate are not synthesized and are not designed to resist external loads integrally, but rather the perforated plate only adds its own weight to the mold. It was pointed out that structurally very inefficient mold cross section design had to be achieved.

또한, 가설교량의 지간경간부에 외력(교통하중 등)에 의하여 발생하는 휨 모멘트는 지점부(가설벤트 설치부)에 전달되어, 결국 지점부 휨 모멘트에 효과적으로 저항하기 위한 방법에 대해 연구 및 실험이 필요하였으나 마땅히 가교와 관련하여 효과적인 대안이 제시되고 있지 않고 있다는 문제점이 있었다.In addition, the bending moment generated by the external force (traffic load, etc.) in the span section of the temporary bridge is transmitted to the branch part (temporary vent installation part), and eventually researches and experiments on a method for effectively resisting the bending moment of the branch bridge. Although this was necessary, there was a problem that no effective alternative has been proposed in relation to crosslinking.

본 발명은 상기 종래기술의 문제점을 해결하기 위한 것으로써, The present invention is to solve the problems of the prior art,

본 발명의 목적은 지점부에 설치되는 주형의 강성을 보다 효과적으로 증진시 키되, 이러한 강성증가가 주형의 구성을 복잡하게 하지 않으면서 복공판의 역할도 할 수 있도록 하여 경제적이고 효율적인 주형단면설계가 가능한 가설교량시공방법을 제공하는 것이다.An object of the present invention is to increase the rigidity of the mold installed in the branch portion more effectively, the hypothesis that such an increase in rigidity can also serve as a perforated plate without complicating the configuration of the mold to enable economic and efficient mold cross-section design It is to provide a bridge construction method.

상기 기술적과제를 달성하기 위하여, 본 발명은In order to achieve the above technical problem, the present invention

첫째, 지점부를 기준으로 길이방향으로 연장 설치되는 I형 강재로 제작되는 주형에 있어서, 상기 주형은 I형 단면으로 구성하되, 상부플랜지에 상연강재를 설치하여 상연강재와 주형이 합성되도록 하되, 상기 상연강재가 복공판의 역할도 할 수 있도록 하였으며, 상기 주형의 하부플랜지에도 역시 하연강재를 설치하여 주형에 합성되도록 함으로써 지점부에 있어 주형의 강성이 극대화 되도록 하였다.First, in the mold made of I-type steel extending in the longitudinal direction based on the point portion, the mold is composed of I-shaped cross-section, the upper flange is installed on the upper flange so that the upper strand and the mold is synthesized, The upper stranded steel was also able to play a role of the perforated plate, and also the lower flange of the mold was also installed in the lower stranded steel to be synthesized in the mold to maximize the rigidity of the mold at the point.

둘째, 상기 지점부에 설치되는 강형의 상연강재가 복공판의 역할을 함으로써 종래의 복공판과는 달리 지점부를 기준으로 양 측방으로 연장되는 지점부복공판이 길이방향으로 설치되도록 하였으며, 상기 길이방향의 지점부복공판의 설치를 위하여 지점부 강형과 강형 사이에는 가로보가 설치될 수 있도록 하였다.Second, unlike the conventional perforated plate, the steel streaked steel installed in the branch part serves as the perforated plate so that the branch part perforated plate extending in both sides based on the branch part is installed in the longitudinal direction, and the branch part in the longitudinal direction is provided. For the installation of the perforated plate, the cross beams can be installed between the point steel and the steel.

셋째, 상기 지점부에 설치되는 강형의 상연강재에는 길이방향으로 긴장재를 설치하여, 지점부에 발생하는 휨 모멘트에 보다 효과적으로 저항할 수 있도록 하였으며, 지간경간부의 경우 주형의 하부에 긴장재를 추가로 설치함으로써 보다 효과적인 프리스트레싱이 주형에 도입되도록 하였다.Third, in the longitudinal stator steel of the type installed in the point portion is provided with a tension member in the longitudinal direction, so as to more effectively resist the bending moment generated in the point portion, in the case of the span section additional to the lower portion of the mold. The installation allows more effective prestressing to be introduced into the mold.

이하, 본 발명에 따른 합성가설교량을 도면에 도시된 실시예를 참조하여 상세하게 설명하기로 한다.Hereinafter, the synthetic hypothesis bridge according to the present invention will be described in detail with reference to the embodiment shown in the drawings.

도 2a 및 도 2b는 본 발명의 지점부주형을 도시한 것이다.2A and 2B show the point mould of the present invention.

도 3은 본 발명의 합성가설교량에 설치되는 상연 및 하연강재가 설치된 지점부주형, 지점부복공판 및 경간부복공판의 설치상태도를 도시한 것이다.Figure 3 shows the installation state diagram of the point mould, the spot covering plate and the span section slab installed in the upper and lower steel materials installed in the synthetic temporary bridge of the present invention.

도 4a 및 도 4b는 본 발명의 합성가설교량의 정면도 및 부분측면도를 도시한 것이다.4A and 4B show front and partial side views of the synthetic temporary bridge of the present invention.

본 발명의 합성가설교량은 The synthetic hypothesis bridge of the present invention

가설벤트를 포함하는 임시지지구조물 상부에 설치되는 복수개의 주형 및 복공판을 포함하는 가설교량에 있어서,In the temporary bridge including a plurality of molds and perforated plate is installed on the temporary support structure including a temporary vent,

복공판이 형성될 부위에 설치되도록 세팅된 상연강재가 상부플랜지에 길이방향으로 합성되며, 하연강재가 하부플랜지에 추가로 길이방향으로 합성된 I형 단면의 지점부주형(100);Branch cast mold 100 of the I-shaped cross-section is composed of the upper strand is synthesized in the longitudinal direction on the upper flange, the lower strand is further synthesized in the longitudinal direction in addition to the lower flange set to be installed in the site where the perforated plate is to be formed;

상기 지점부주형과 지점부주형의 상면 측방 사이에 횡방향으로 설치된 가로보(200);A cross beam 200 installed in a transverse direction between the top side of the point mold and the point mold;

가로보 상부면에 지지되어 상기 상연강재의 측면에 접하여 길이방향으로 연장되어 설치된 지점부복공판(300); 및A branch part covering plate 300 which is supported on a horizontal beam upper surface and is extended in a longitudinal direction in contact with a side surface of the upper strand steel; And

상기 지점부복공판 양 단부면에 접하도록 경간부주형(400)에 얹어져 횡방향으로 설치된 경간부복공판(500);을 포함한다.Includes; span portion plate plate 500 mounted on the span portion mold 400 to be in contact with both end surfaces of the branch portion plate plate in the transverse direction.

본 발명의 합성가설교량은 가설교량에 적용되는 것으로써, 기본적으로 가설벤트와 같은 임시지지구조물(10)이 먼저 설치되며 임시지지구조물 상부면에 주형이 설치되며, 주형 상부면에 복공판이 설치된다. 이때 상기 가설벤트가 설치되는 부위 는 구조적으로 지점부(A)로 형성된다.Synthetic temporary bridge of the present invention is to be applied to the temporary bridge, the temporary support structure 10, such as a temporary tent is basically installed first, the mold is installed on the upper surface of the temporary support structure, the perforated plate is installed on the mold upper surface . At this time, the site where the temporary vent is installed is structurally formed as a branch (A).

이러한 지점부(A)에 본 발명의 지점부주형(100)이 설치되는데, 지점부(A)를 기준으로 개략 본 발명의 지점부주형(100) 중앙부가 지지되도록 설치된다. The point portion mold 100 of the present invention is installed in this point portion A, and the center portion of the point portion mold 100 of the present invention is schematically installed based on the point portion A.

상기 지점부주형(100)은 도 2a 및 도 2b와 같이, I형 단면의 형강으로 제작된 강형을 이용하게 된다.2A and 2B, the point portion mold 100 uses a steel mold made of a section steel having an I-shaped cross section.

즉, 상부플랜지(110), 복부(120) 및 하부플랜지(130)로 구성된 강형에 T형강인 상연강재(140)가 용접에 의하여 더 설치된다. That is, the upper malleable steel material 140, which is a T-shaped steel, is further installed by welding in the steel formed of the upper flange 110, the abdomen 120, and the lower flange 130.

이러한 상연강재(140)에 의하여 강형의 전체높이가 증가되므로 강형의 전체 강성은 상당히 증가되게 된다. 이로써 지간경간부로부터 전달되는 휨 모멘트를 효과적으로 분담할 수 있게 된다.Since the overall height of the steel is increased by the staging steel 140, the overall rigidity of the steel is significantly increased. This makes it possible to effectively share the bending moment transmitted from the span section.

이러한 T형강인 상연강재(140)는 복부(141)가 상부플랜지 상면에 접하도록 하고, 상부(142)가 상기 복부(141)에 수평으로 연장되도록 하되, 바람직하게는 도 2b와 같이 강형의 상부플랜지 폭(D1)보다 상기 상연강재의 상부의 폭(D2)이 적게 되도록 함으로써 상연강재(140)에 의한 강형의 중립축 상향이동을 최소화 하는 것이 바람직하다.The upper strand steel 140, which is a T-shaped steel, allows the abdomen 141 to contact the upper flange upper surface, and the upper part 142 to extend horizontally to the abdomen 141, preferably as shown in FIG. 2B It is preferable to minimize the neutral axis upward movement of the steel by the staging steel 140 by making the width D2 of the upper portion of the staging steel material smaller than the flange width D1.

또한 상기 상연강재(140)가 강형에 안정적으로 합성될 수 있도록 스티프너(143)를 상부(142)와 상부플랜지(110) 상부면 사이에 수직으로 설치할 수 있도록 하며 이러한 스티프너는 후술되는 지점부상부강재의 긴장 정착에 의한 강형의 비틀림강성을 증가시키게 된다.In addition, the stiffener 143 can be vertically installed between the upper 142 and the upper flange 110, the upper stiffener so that the staging steel 140 can be stably synthesized in the steel, and the stiffener is a point portion steel material described later The torsional stiffness of the steel due to the settling of tension increases.

결국, 상연강재(140)와 강형은 서로 일체화되어 구조적으로 합성되며, 이로 써 상연강재(140)와 강형은 외력에 대하여 일체로 저항할 수 있어 강형의 전체적인 강성이 증가될 수 있게 된다.As a result, the upper strand steel 140 and the steel mold is integrated with each other and structurally synthesized, whereby the upper strand steel 140 and the steel mold can be integrally resisted against external force, thereby increasing the overall rigidity of the steel mold.

나아가 본 발명의 상연강재(140)는 단순히 강형의 강성을 증가시키는 역할을 넘어, 복공판의 역할을 하도록 하였다.Furthermore, the upper staging steel 140 of the present invention was to serve as a perforated plate, not merely to increase the rigidity of the steel.

즉, 종래와 같이 상기 상연강재(140) 상부면에 다시 복공판을 추가로 설치하는 것이 아니라, 도 3 및 도 4b와 같이 강형과 합성된 상연강재(140) 자체가 복공판의 역할을 할 수 있도록 하였다. 이로써 지점부주형의 강성은 증가하더라도 추가적인 복공판을 설치할 필요가 없어 매우 경제적인 지점부 복공판 설치가 가능하게 되며, 형하공간 제약이 있는 경우라도 용이하게 적용할 수 있게 된다.That is, instead of installing the perforated plate additionally on the upper surface of the upper malleable steel 140 as in the related art, as shown in FIG. 3 and FIG. 4B, the malleable steel 140 itself synthesized with the steel can serve as the perforated plate. . As a result, even if the rigidity of the branch casting mold increases, it is not necessary to install an additional perforated plate, and thus it is possible to install a very economical branch perforated plate, and can be easily applied even when there is a space limitation of the mold.

이렇게 상연강재(140)가 복공판의 역할을 가지게 됨으로써 후술되는 바와 같이 본 발명의 지점부에는 상연강재(140)와 동일하게 길이방향으로 설치되는 지점부복공판(300)이 설치된다.As described above, the upper malleable steel 140 has a role of the perforated plate, and thus, the branch portion of the branched plate 300 is installed in the longitudinal direction in the same manner as the upper malleable steel 140.

즉, 통상의 복공판(30)이 도 1과 같이 횡방향으로 주형(20)에 얹어져 설치되는 반면, 본 발명의 지점부(A)에는 도 3과 같이 길이방향으로 지점부복공판(300)이 연장 설치되게 된다.That is, while the normal perforated plate 30 is installed on the mold 20 in the transverse direction as shown in FIG. 1, the point portion A in the longitudinal direction as shown in FIG. Extension will be installed.

또한 상연강재(140)는 양 쪽 단부면에 정착판(150)이 더 설치되어, 정착판(150) 사이에 지점부상부긴장재(160)를 배치하고, 지점부상부긴장재(160)를 긴장, 정착시킴으로써 지점부주형(100)에 소요의 프리스트레스가 도입되도록 한다. 이로써, 지점부주형(100)이 지점부(A)에 설치되기 때문에 발생하는 휨 부모멘트(M-)에 보다 효과적으로 저항할 수 있게 된다.In addition, the upper strand steel material 140 is further provided with fixing plates 150 on both end surfaces, to arrange the point portion upper tension member 160 between the fixing plate 150, tension the point upper tension member 160, By fixing, the required prestress is introduced into the branch casting mold 100. This makes it possible to more effectively resist the bending parent moment M- generated because the point portion mold 100 is installed in the point portion A. FIG.

하지만 지점부상부긴장재(160)를 설치함에 있어 상연강재(140)가 강형 상부에 위치하는 이유로 강형의 중립축이 상방으로 상당히 이동된 상태가 된다. 즉, 구조적으로 지점부상부긴장재(160)와 강형의 중립축까지의 편심거리가 크지 않아 편심효과가 적어 강형의 단면력확보에 있어 다소 비효율적일 수 있다.However, in installing the upper portion tension member 160, the neutral axis of the steel is in a state that is moved considerably upwards because the upper strand steel 140 is located in the upper portion of the steel. That is, since the eccentric distance between the point injury portion tension material 160 and the neutral shaft of the steel is not large, the eccentric effect is small and may be somewhat inefficient in securing the cross-sectional force of the steel.

이에 본 발명에서는 강형의 하부플랜지(130)에 역시 T형 하연강재(170)를 더 설치시켜 합성시킴으로써, 강형의 중립축을 하향 이동시켜, 상기 지점부상부긴장재(160)에 의한 편심효과를 극대화함으로써 지점부주형(100)에 있어 보다 경제적이고 효율적인 단면설계가 가능하도록 하였다.Therefore, in the present invention, by further installing the T-type lower stranded steel 170 in the lower flange 130 of the steel composite, by moving the neutral axis of the steel downward, by maximizing the eccentric effect by the point portion upper tension member 160 In the point mold 100, more economical and efficient cross-sectional design was made possible.

이때 상기 하연강재(170)도 복부(171)가 하부플랜지 하면에 접하도록 하고, 하부(172)가 상기 복부(171)에 수평으로 연장되도록 하되, 바람직하게는 상연강재(140)와는 달리 하부플랜지 폭(D3)과 거의 동일한 폭(D4)을 가지도록 함으로써 상연강재(140)에 의한 강형의 중립축 상향 이동을 최소화하여 최종 편심효과를 극대화 시킴이 바람직하다.In this case, the lower lead steel material 170 also allows the abdomen 171 to contact the lower flange bottom surface, and the lower 172 extends horizontally to the abdomen 171, preferably unlike the upper flange steel 140 It is preferable to maximize the final eccentric effect by minimizing upward movement of the neutral axis of the steel by the upper strand steel 140 by having the width D4 substantially equal to the width D3.

또한 상기 하연강재(170)가 강형에 안정적으로 합성될 수 있도록 스티프너(173)를 하부(172)와 하부플랜지(130) 상부면 사이에 수직으로 설치할 수 있도록 한다.In addition, the stiffener 173 may be vertically installed between the lower 172 and the upper surface of the lower flange 130 so that the lower lead steel 170 may be stably synthesized in the steel mold.

이에 상연강재(140) 및 하연강재(170)가 상부플랜지(110) 및 하부플랜지(130)에 설치되어 합성된 상태의 강형은 그 강성이 증가되어 외력에 효과적으로 저항할 수 있게 되며, 이를 본 발명에서는 지점부주형(100)으로서 이용된다.The upper and lower steels 140 and 170 are installed in the upper flange 110 and the lower flange 130, the steel of the synthesized state is increased rigidity can effectively resist external forces, the present invention Is used as the point casting mold 100.

이러한 지점부주형(100)은 개략 중앙 하부가 볼트, 너트와 같은 기계적 체결구에 의하여 가설벤트를 포함하는 임시지지구조물(10)에 고정되도록 설치됨으로써, 지점부(A)를 기준으로 하면 도 3과 같이 지점부 양측(길이방향)으로 연장돌출 되도록 설치된다.The point portion mold 100 is installed to be fixed to the temporary support structure 10 including the temporary vents by a mechanical fastener such as a bolt, nut, roughly, based on the point (A) Figure 3 It is installed to protrude outwards on both sides (length direction) of the point portion.

물론 지점부(A)에 있어서 횡방향으로 다수의 지점부주형(100)이 병렬로 설치되는데 이는 가설교량의 폭에 따라 적의 선택할 수 있을 것이다.Of course, in the point A, a plurality of point molds 100 are installed in parallel in the transverse direction, which may be appropriately selected according to the width of the temporary bridge.

본 발명의 지점부주형(100)의 상연강재(140)는 길이방향으로 연장되어 복공판의 역할을 하게 되므로 이러한 상연강재의 연장길이에 대응하여 지점부복공판(300)이 지점부(A)에 설치된다.Since the upper malleable steel 140 of the branch portion mold 100 of the present invention extends in the longitudinal direction to serve as a perforated plate, the branch portion overlapping plate 300 is installed in the branch portion A in correspondence to the extension length of the malleable steel. do.

도 3을 기준으로 하면 상기 지점부복공판(300)은 지점부주형(100) 상부에 길이방향으로 연장되어 설치되는데, 이를 위해 본 발명의 지점부주형과 지점부주형 사이에는 가로보(200)가 설치된다.Referring to Figure 3, the branch covering plate 300 is installed to extend in the longitudinal direction on the upper portion of the branch mold 100, for this purpose, a horizontal beam 200 is installed between the branch portion mold and the branch portion mold of the present invention. do.

상기 가로보(200)는 지점부주형 사이에 설치되도록 하되 도 4b와 같이 가로보(200) 상면이 강형의 상부플랜지 상부면과 동일 높이가 되도록 설치되어, 지점부복공판(300)의 저면이 가로보 상면에 접하여 지지되도록 한다.The horizontal beams 200 are installed between the point portion molds, but are installed such that the upper surface of the horizontal beams 200 is the same height as the upper surface of the upper flange of the steel, as shown in Figure 4b, the bottom surface of the branch covering plate 300 on the upper surface of the horizontal beams To be supported by contact.

이는 통상의 가로보가 주형의 전도 방지등을 위해 주형의 복부 사이에 횡방향으로 설치되는 것과는 구별되는 것으로써, 이는 본 발명의 지점부복공판(300)이 길이방향으로 연장 설치되기 때문에 이를 지지할 수 있도록 가로보(200)가 설치되어야 하기 때문이라 할 수 있다.This is distinguished from the conventional cross beam is installed in the transverse direction between the abdomen of the mold for preventing the fall of the mold, etc., which can support the branch covering plate 300 of the present invention because it is installed extending in the longitudinal direction This may be because the horizontal beam 200 should be installed to be.

이러한 가로보(200)는 지점부(A)에 있어 지점부주형(100) 사이에 횡방향으로 다수가 설치될 수 있으며, 지점부주형(100)의 연장길이에 걸쳐 길이방향으로 서로 이격되어 설치될 수 있을 것이다.The horizontal beams 200 may be installed in the transverse direction between the point portion mold 100 in the point portion (A), spaced apart from each other in the longitudinal direction over the extension length of the point portion mold (100) Could be.

나아가, 이러한 가로보(200)와 지점부주형(100)의 연결부에는 예컨대 대각선 방향으로 브레이싱재(210)를 더 설치하여 지점부복공판(300)의 안정적인 지지가 가능하도록 함과 더불어 지점부주형(100)과 가로보(200)의 격자형 구조를 보강함으로써 보다 안전한 지점부 구조가 되도록 한다.In addition, the connection portion of the cross beam 200 and the point portion mold 100 is further provided with a bracing material 210 in a diagonal direction, for example, to enable a stable support of the branch covering plate 300 and the point portion mold 100 ) And the lattice structure of the cross beam 200 to be a safer point structure.

이로써, 지점부(A)에 지점부주형(100), 가로보(200) 및 지점부복공판(300)이 설치된 상태에서는 지점부와 지점부 사이에 추가적으로 경간부주형(400)이 지간부주형(100)과 덧댐판 및 볼트와 너트 등을 이용하여 서로 연결되도록 하고, 이러한 경간부주형(400) 상부면에는 통상의 복공판이 횡방향으로 설치되도록 하며 통상의 가로보를 경간부주형 사이에 설치할 수 있다. 이러한 경간부주형(400)에 설치되는 복공판을 본 발명에서는 경간부복공판(500)이라 지칭한다.Thus, in the state in which the branch part mold 100, the cross beam 200, and the branch parting plate 300 are installed in the branch part A, the span part mold 400 is additionally formed between the branch part and the branch part. ) And the back plate and bolts and nuts to be connected to each other, such that the upper surface of the span portion 400, the normal perforated plate is installed in the transverse direction and can be installed between the span cross mold. The perforated plate installed in the span part mold 400 is referred to as the span part perforated plate 500 in the present invention.

이러한 경간부복공판(500)의 경우, 지점부복공판(300)의 높이와 일치하도록 함으로써, 가설교량의 상부면에 턱이 형성되지 않도록 한다.In the case of such a span part plate 500, by matching the height of the point portion plate 300, the jaw is not formed on the upper surface of the temporary bridge.

경간부주형(400)은 그 연장길이가 길어짐에 따라 휨 정모멘트(M+)가 커질 수밖에 없고 이로써 처짐이 발생할 여지가 많아 단면크기를 크게 할 수밖에 없는 상황이 될 수도 있다.As the span length 400 extends, the bending constant moment (M +) is inevitably increased as the extension length thereof becomes longer, and thus, there may be a situation in which a large cross-sectional size may be increased due to a large amount of deflection.

이러한 현상을 방지하기 위하여, 본 발명에서는 도 4a와 같이 경간부주형(400) 하부면에 길이방향으로 경간부하부긴장재(600)를 긴장, 정착시켜 소요의 프리스트레스가 경간부주형에 도입되도록 한다.In order to prevent such a phenomenon, in the present invention, as shown in FIG. 4A, the span-loading tensioning material 600 is tensioned and fixed to the lower surface of the span-mold mold 400 so that the required prestress is introduced into the span-mold mold.

이때, 상기 경간부하부긴장재(600)는 경간부주형(400) 저면에 정착구(610)를 이격시켜 고정시킨 후, 경간부하부긴장재(600)의 양 단부를 긴장, 정착시키거나, 일 단부를 고정한 후 타단부를 긴장, 정착하여 정착시킬 수 있다.At this time, the spanning load tensioning material 600 is fixed to the bottom of the spanning mold 400, spaced apart by the fixing unit 610, and then tension or fix both ends of the spanning load tensioning material 600, or one end After fixing, the other end can be tensioned and fixed.

이러한 프리스트레스는 휨 정모멘트(M+)에 저항하기 위하여 도입되는 것이므로 지점부주형의 휨 부모멘트(M-)에 저항하기 위하여 도입되는 지점부상부긴장재(160)에 의한 프리스트레스와는 구별될 수 있으며, 이러한 프리스트레스가 가설교량에 모두 도입되는 경우를 지칭하여 본 발명에서는 더블 프리스트레싱이라 한다.Since the prestress is introduced to resist the bending constant moment (M +), it can be distinguished from the prestress by the point portion upper tension member 160 introduced to resist the bending parent moment (M−) of the point casting mold. Such prestressing refers to a case where all of the prestresses are introduced into the temporary bridge, and is referred to as double prestressing in the present invention.

이러한 경간부하부긴장재(600)에 의한 프리스트레스는 본 발명에 있어 선택적으로 실시할 수 있는 것으로서 지간이 작은 가설교량에 있어서는 굳이 경간부하부긴장재(600)를 설치할 필요는 없을 것이다.The prestress by the span load tensioning material 600 can be selectively implemented in the present invention, and it is not necessary to install the span load tensioning material 600 in a temporary bridge having a small span.

본 발명의 합성가설교량에 의하여, 지점부에 있어 보다 강성이 증가되도록 상연강재 및 하연강재가 합성된 강형을 사용할 수 있도록 함으로써 지점부에 있어 보다 안전한 구조를 가질 수 있도록 할 수 있으며, 상대적으로 지간 사이의 경강부강형의 단면적을 경제적으로 설계할 수 있다.By the synthetic hypothesis bridge of the present invention, it is possible to have a more secure structure in the branch portion by using the steel combined with the upper and lower steels so that the rigidity is increased in the branch portion, and relatively The cross-sectional area of the rigid steel between the two sections can be designed economically.

또한 지점부주형의 상연강재가 복공판의 역할을 동시에 할 수 있어 보다 경제적이면서도 효율적인 가설교량의 지점부 구조를 형성시킬 수 있으며,In addition, it is possible to form the branch structure of temporary bridges more economically and efficiently because the staging steel of the branch casting mold can play the role of a perforated plate at the same time.

지점부주형의 상연강재에 소요의 프리스트레스가 도입될 수 있도록 함으로써 지점부에 발생하는 휨 부모멘트에 효과적으로 저항할 수 있게 된다.By allowing the required prestress to be introduced into the upper cast steel of the point portion mold, it is possible to effectively resist the bending moment generated in the point portion.

앞에서 설명되고, 도면에 도시된 본 발명의 일 실시예는 본 발명의 기술적사상을 한정하는 것으로 해석되어서는 안 된다. 본 발명의 기술분야에서 통상의 지 식을 가진 자는 본 발명의 기술적 사상을 다양한 형태로 개량 변경하는 것이 가능하다. 따라서 이러한 개량 및 변경은 통상의 지식을 가진 자에게 자명한 것인 한 본 발명의 보호범위에 속하게 된다.An embodiment of the present invention described above and illustrated in the drawings should not be construed as limiting the technical spirit of the present invention. Those skilled in the art of the present invention can change and change the technical spirit of the present invention in various forms. Therefore, such improvements and modifications fall within the protection scope of the present invention as long as it will be apparent to those skilled in the art.

Claims (4)

가설벤트를 포함하는 임시지지구조물 상부에 설치되는 복수개의 주형 및 복공판을 포함하는 가설교량에 있어서,In the temporary bridge including a plurality of molds and perforated plate is installed on the temporary support structure including a temporary vent, 복공판이 형성될 부위에 설치되도록 세팅된 상연강재가 상부플랜지에 길이방향으로 합성되며, 하연강재가 하부플랜지에 추가로 길이방향으로 합성된 I형 단면의 지점부주형; 상기 지점부주형과 지점부주형의 상면 측방 사이에 횡방향으로 설치된 가로보; 가로보 상부면에 지지되어 상기 상연강재의 측면에 접하여 길이방향으로 연장되어 설치된 지점부복공판; 및 상기 지점부복공판 양 단부면에 접하도록 경간부주형에 얹어져 횡방향으로 설치된 경간부복공판;을 포함하되,A point mould having an I-type cross section in which the upper malleable steel set to be installed at the site where the perforated plate is to be formed is longitudinally synthesized in the upper flange, and the lower stranded steel is further longitudinally synthesized in the lower flange; A cross beam installed in a transverse direction between the point side mold and the top surface side of the point portion mold; Point covering plate is installed on the horizontal beam upper surface is extended in the longitudinal direction in contact with the side of the upper strand steel; And a span part rest plate installed on the span part mold so as to be in contact with both end faces of the branch part rest plate. 상기 상연강재는 양 단부에 설치된 정착판 사이에 PC 강선 또는 강봉을 포함하는 지점부상부긴장재가 더 설치되어 긴장후 정착되는 것을 특징으로 하는 합성가설교량.Said staging steel material is a synthetic hypothesis bridge, characterized in that the point portion upper tension material including a PC steel wire or steel rod is installed between the fixing plates installed at both ends is fixed after the tension. 제 1항에 있어서, 상기 가로보와 지점부주형과의 연결부 사이에 브레이싱재가 더 설치되는 것을 특징으로 하는 합성가설교량.2. The synthetic hypothesis bridge according to claim 1, wherein a bracing material is further provided between the connecting portion of the cross beam and the point portion mold. 제 1항 또는 제 2항에 있어서, 상기 상연강재 또는 하연강재는 T형강인 것을 특징으로 하는 합성가설교량.The synthetic temporary bridge according to claim 1 or 2, wherein the upper or lower steel is T-shaped steel. 제 3항에 있어서, 상기 지점부와 지점부 사이의 경간부주형 하부면에 서로 이격된 정착구 사이에 PC 강선 또는 강봉을 포함하는 경간부하부긴장재가 더 설치되어 긴장후 정착되는 것을 특징으로 하는 합성가설교량.According to claim 3, Synthesis characterized in that the span portion tensioning device including a PC steel wire or steel rod is further installed between the anchorage spaced apart from each other on the lower portion of the span portion between the branch portion and the branch portion is fixed after tension Temporary bridge.
KR1020060019785A 2006-03-02 2006-03-02 Composite temporary bridge KR100755946B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020060019785A KR100755946B1 (en) 2006-03-02 2006-03-02 Composite temporary bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020060019785A KR100755946B1 (en) 2006-03-02 2006-03-02 Composite temporary bridge

Publications (1)

Publication Number Publication Date
KR100755946B1 true KR100755946B1 (en) 2007-09-06

Family

ID=38736658

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020060019785A KR100755946B1 (en) 2006-03-02 2006-03-02 Composite temporary bridge

Country Status (1)

Country Link
KR (1) KR100755946B1 (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100979218B1 (en) 2006-12-06 2010-08-31 에이버겔디 지 빔 피티와이 리미티드 Continuous span structure
KR101074352B1 (en) 2011-05-30 2011-10-17 우경기술주식회사 Temporary bridge and its construction method
KR101083255B1 (en) * 2008-10-28 2011-11-14 신광에코로드이엔씨 주식회사 Environmental steel bridge type eco-bridge
KR101173044B1 (en) * 2012-02-17 2012-08-13 주식회사 스페이스테크놀로지 Temporary Bridge
KR101208435B1 (en) 2011-03-30 2012-12-05 박시우 Temporary bridge and constructing method thereof for increase supporting power
KR101682442B1 (en) * 2016-02-19 2016-12-05 장영철 Temporary bridge
KR101893863B1 (en) * 2017-05-02 2018-08-31 주식회사 하이텍코리아 Bridge and construction method thereof
CN111945545A (en) * 2020-08-12 2020-11-17 董礼 Bridge facility that modularization was assembled

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020057058A (en) * 2000-12-30 2002-07-11 박재만 Bridge reinforcement apparatus using h beam
KR200281077Y1 (en) 2002-03-15 2002-07-13 최일용 A temporaty bridge for continuous type long span
KR20030086222A (en) * 2003-01-08 2003-11-07 노윤근 temporaty bridge using prestressed compuond double girder and method for building the temporary bridge
KR20040099015A (en) * 2003-05-17 2004-11-26 노윤근 Temporary bridge composed of selectively prestressed bridge girder, apparatus for preventing falling off bridge and supporting apparatus having multiple supporting points, and installing method thereof
KR100511343B1 (en) 2005-02-24 2005-08-30 주식회사 누리플랜 Prestressed continue steel-frame bridge and method for constructing thereof
KR20050118111A (en) * 2005-03-15 2005-12-15 (주) 포유엔지니어링 Temporary bridge
KR20060098739A (en) * 2005-03-07 2006-09-19 영창중공업 주식회사 Prestressed girder for temporary bridge having supports for string

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020057058A (en) * 2000-12-30 2002-07-11 박재만 Bridge reinforcement apparatus using h beam
KR200281077Y1 (en) 2002-03-15 2002-07-13 최일용 A temporaty bridge for continuous type long span
KR20030086222A (en) * 2003-01-08 2003-11-07 노윤근 temporaty bridge using prestressed compuond double girder and method for building the temporary bridge
KR20040099015A (en) * 2003-05-17 2004-11-26 노윤근 Temporary bridge composed of selectively prestressed bridge girder, apparatus for preventing falling off bridge and supporting apparatus having multiple supporting points, and installing method thereof
KR100511343B1 (en) 2005-02-24 2005-08-30 주식회사 누리플랜 Prestressed continue steel-frame bridge and method for constructing thereof
KR20060098739A (en) * 2005-03-07 2006-09-19 영창중공업 주식회사 Prestressed girder for temporary bridge having supports for string
KR20050118111A (en) * 2005-03-15 2005-12-15 (주) 포유엔지니어링 Temporary bridge

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100979218B1 (en) 2006-12-06 2010-08-31 에이버겔디 지 빔 피티와이 리미티드 Continuous span structure
KR101083255B1 (en) * 2008-10-28 2011-11-14 신광에코로드이엔씨 주식회사 Environmental steel bridge type eco-bridge
KR101208435B1 (en) 2011-03-30 2012-12-05 박시우 Temporary bridge and constructing method thereof for increase supporting power
KR101074352B1 (en) 2011-05-30 2011-10-17 우경기술주식회사 Temporary bridge and its construction method
KR101173044B1 (en) * 2012-02-17 2012-08-13 주식회사 스페이스테크놀로지 Temporary Bridge
KR101682442B1 (en) * 2016-02-19 2016-12-05 장영철 Temporary bridge
KR101893863B1 (en) * 2017-05-02 2018-08-31 주식회사 하이텍코리아 Bridge and construction method thereof
CN111945545A (en) * 2020-08-12 2020-11-17 董礼 Bridge facility that modularization was assembled

Similar Documents

Publication Publication Date Title
KR100755946B1 (en) Composite temporary bridge
KR100679664B1 (en) Steel framed girder and slab structure for bridge and the construction method
KR101178876B1 (en) Prestressed composit rahmen bridge construdtion method
KR100569028B1 (en) Box-type temporary bridge
KR101391349B1 (en) Rebar structure of void concrete slab
KR100615471B1 (en) Steel plate girder bridge and it&#39;s construction method is using a steel composite horizontal beam
KR100728106B1 (en) Cantilever construction structure of slab for bridge and the method thereof
KR100758994B1 (en) Reinforced beam with vertical h-steel or i-steel for stiffness, the construction structure and bridge construction method using the same
KR101165572B1 (en) Middle span plate girder bridge and construction method thereof
KR100931317B1 (en) Bridge using strut and tie member and construction method
KR101243777B1 (en) Rahmen bridge using composite structure of corrugated steel web and concrete member and constructing method thereof
KR20120050940A (en) Constrution method of prestressed composite truss girder with internal hinge structure
KR102163560B1 (en) Girdir and bridge having soundproof wall using the same
KR100871831B1 (en) Prestressed temporary bridge preloaded by cable-tie and method thereof
CN104562944A (en) Large span composite beam cable-stayed bridge side steel box temporary anchorage system
KR100931318B1 (en) Temporary bridges with branches of truss structure and construction method
KR20100115117A (en) Scaffolding structure using compositive section beam introducing prestress by maximizing rigidity and eccentricity by combination of various sections
JP3847604B2 (en) Floor slab replacement method
KR20050118111A (en) Temporary bridge
KR20200013911A (en) Cross section stiffnesses enhanced saddle sttached temporary bridge and method of structure using the same
KR102132338B1 (en) Steel Composite PSC Girder Including Arched Reinforcement
KR101046941B1 (en) Rahmen bridge construction method without hunch
JP2010159568A (en) Structure and method for reinforcing existing simple girder bridge
KR20140106861A (en) Temporary bridge and construction method using pile and fabricated girder
KR200435765Y1 (en) End cutoff type prestressed composition bridge which stairs type strain equipment possesses

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
N231 Notification of change of applicant
GRNT Written decision to grant
G170 Publication of correction
J206 Request for trial to confirm the scope of a patent right
J121 Written withdrawal of request for trial
FPAY Annual fee payment

Payment date: 20130304

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20130829

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20140815

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20150829

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20160907

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20170705

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20190624

Year of fee payment: 13