KR100665876B1 - The prestressed opening trapezoid waveform still girder construction method of having installed concrete caisson in the upper flange - Google Patents

The prestressed opening trapezoid waveform still girder construction method of having installed concrete caisson in the upper flange Download PDF

Info

Publication number
KR100665876B1
KR100665876B1 KR1020060046073A KR20060046073A KR100665876B1 KR 100665876 B1 KR100665876 B1 KR 100665876B1 KR 1020060046073 A KR1020060046073 A KR 1020060046073A KR 20060046073 A KR20060046073 A KR 20060046073A KR 100665876 B1 KR100665876 B1 KR 100665876B1
Authority
KR
South Korea
Prior art keywords
concrete
upper flange
caisson
flange
corrugated steel
Prior art date
Application number
KR1020060046073A
Other languages
Korean (ko)
Inventor
노윤근
정상욱
Original Assignee
우경건설 주식회사
노윤근
정상욱
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 우경건설 주식회사, 노윤근, 정상욱 filed Critical 우경건설 주식회사
Application granted granted Critical
Publication of KR100665876B1 publication Critical patent/KR100665876B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/28Concrete reinforced prestressed
    • E01D2101/285Composite prestressed concrete-metal

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

A construction method for a prestressed open-top type wavy steel girder bridge by installing a concrete caisson on an upper flange is provided to decrease the cross section of an upper flange by having excellent stress distribution and absorbing the stress of an upper flange using a concrete caisson. A construction method for a prestressed open-top type wavy steel girder bridge by installing a concrete caisson on an upper flange comprises the steps of welding a lower flange(14) composed of a steel plate having the appointed size on each lower part of a pair of wavy steel plates(12), welding an upper flange(16) composed of a steel plate having the appointed size on each upper part of the wavy steel plates to be separable, manufacturing an open-top type wavy steel girder(10) and installing all over a span of a bridge, placing bottom concrete on the top of the lower flange in the open-top type wavy steel girder and placing a rectangular or U-shaped concrete caisson(20) on the top of the upper flange simultaneously, unifying the lower flange and the bottom concrete with a shear connector and curing concrete, placing a strand on the bottom concrete through a pre-laid sheathe pipe, applying prestress partially, placing deck concrete on the upper flange, unifying the upper flange and the deck concrete using a shear connector and curing the concrete, applying prestress on the remaining strands buried under the bottom concrete, and applying prestress on the deck concrete in the tension area of a support.

Description

상부플랜지에 콘크리트케이슨을 설치한 프리스트레스트 개구제형 파형 스틸거더교의 시공방법{The prestressed opening trapezoid waveform still girder construction method of having installed concrete caisson in the upper flange} The prestressed opening trapezoid waveform still girder construction method of having installed concrete caisson in the upper flange}

도 1은 종래의 개구제형 파형 스틸거더를 도시한 사시도,1 is a perspective view showing a conventional opening type corrugated steel girder,

도 2는 도 1의 하부플랜지 상면에 바닥콘크리트가 타설 양생된 상태를 도시한 정면도,FIG. 2 is a front view illustrating a state in which bottom concrete is poured on the upper surface of the lower flange of FIG. 1;

도 3은 도 2의 상부플랜지 상부에 콘크리트케이슨이 형성되지 않은 경우의 응력분포 상태를 도시한 예시도,3 is an exemplary view showing a stress distribution state when the concrete caisson is not formed on the upper flange of FIG.

도 4는 도 2의 바닥콘크리트에 프리스트레스를 도입한 상태를 도시한 측면도,Figure 4 is a side view showing a state in which prestress is introduced to the bottom concrete of FIG.

도 5는 도 2의 상부플랜지에 교량상부데크콘크리트가 타설 양생된 상태를 도시한 정면도,5 is a front view illustrating a state in which the upper deck concrete is poured into the upper flange of FIG.

도 6은 도 5의 바닥콘크리트와 교량상부데크콘크리트에 프리스트레스를 도입한 상태를 도시한 측면도,FIG. 6 is a side view illustrating a state in which prestress is introduced into floor concrete and bridge upper deck concrete of FIG. 5;

도 7은 도 6의 교량상부데크콘크리트에 상부 2차 사하중인 포장, 난간 등을 재하한 상태를 도시한 정면도,FIG. 7 is a front view showing a state in which the upper secondary dead concrete pavement, railing, etc. are loaded on the deck upper concrete of FIG. 6;

도 8은 본 발명에 따른 상부플랜지에 전단연결재로 일체화한 콘크리트케이슨 이 형성된 개구제형 파형 스틸거더를 도시한 사시도, 8 is a perspective view showing an opening-type corrugated steel girder formed with a concrete caisson integrated with a shear connector in the upper flange according to the present invention,

도 9는 도 8의 상부플랜지 상면과 하부플랜지 상면에 콘크리트가 타설되어 콘크리트케이슨과 바닥콘크리트가 형성된 상태를 도시한 정면도,9 is a front view illustrating a state in which concrete caisson and bottom concrete are formed by placing concrete on the upper surface of the upper flange and the lower flange of FIG. 8;

도 10은 도 9의 상부플랜지에 콘크리트케이슨이 합성된 경우의 응력분포를 도시한 예시도,10 is an exemplary view showing a stress distribution when the concrete caisson is synthesized in the upper flange of FIG.

도 11은 도 9의 콘크리트케이슨에 교량상부데크콘크리트를 형성한 상태를 도시한 정면도,FIG. 11 is a front view illustrating a state in which bridge deck concrete is formed on the concrete caisson of FIG. 9; FIG.

도 12는 도 9의 콘크리트케이슨에 교량상부데크콘크리트 타설시 미경화 교량상부데크콘크리트 하중에 의한 개구제형 스틸거더의 모멘트도,12 is a moment diagram of the opening-type steel girders due to the uncured bridge upper deck concrete load when the upper deck concrete is placed on the concrete caisson of FIG.

도 13은 본 발명에 따른 상부플랜지에 콘크리트케이슨을 형성한 프리스트레스트 개구제형 파형 스틸거더가 지점부상에 설치된 상태를 도시한 사시도,13 is a perspective view illustrating a state in which a prestressed opening type corrugated steel girder having a concrete caisson formed on an upper flange according to the present invention is installed on a point portion;

도 14는 도 13의 지점 하강에 의한 개구제형 스틸거더의 모멘트도,FIG. 14 is a moment diagram of an opening-type steel girder by the point lowering in FIG. 13;

도 15는 도 13의 지점 하강에 의한 개구제형 스틸거더의 모멘트 변화도, FIG. 15 is a moment change diagram of an opening-type steel girder due to the point lowering in FIG. 13;

도 16은 본 발명에 따른 상부플랜지에 콘크리트케이슨을 형성한 프리스트레스트 개구제형 파형 스틸거더를 도시한 측면도,16 is a side view showing a prestressed opening type corrugated steel girder formed with a concrete caisson on the upper flange according to the present invention,

도 17은 도 16의 A-A선 단면도,17 is a cross-sectional view taken along the line A-A of FIG.

도 18은 도 16의 "A"부분을 확대 도시한 상세도,FIG. 18 is an enlarged detailed view of a portion “A” of FIG. 16;

도 19는 상부플랜지에 콘크리트케이슨의 유무에 따른 응력분포를 도시한 비교도,19 is a comparison showing the stress distribution according to the presence or absence of concrete caisson in the upper flange,

도 20은 본 발명에 따른 개구제형 파형 스틸거더에 콘크리트케이슨을 형성하 기 위해 파형강판 복부에 거푸집을 고정 설치한 상태를 도시한 정면도,20 is a front view showing a state in which formwork is fixed to the corrugated steel sheet to form a concrete caisson in the opening-type corrugated steel girder according to the present invention,

도 21은 본 발명에 따른 개구제형 파형 스틸거더의 하부플랜지에 바닥콘크리트 타설시 상부플랜지에 정착구를 용접 접합하고, PS강재로 지점부 부모멘트를 인장하여 압축력을 도시한 상태를 도시한 측면도, Figure 21 is a side view showing a state showing the compressive force by welding the anchorage to the upper flange when the bottom flange to the bottom flange of the opening-form corrugated steel girder according to the present invention, the tension of the portion of the parent portion with PS steel,

도 22는 콘크리트케이슨의 매립형 정착구를 도시한 측면도,22 is a side view showing a buried anchorage of the concrete caisson;

도 23은 콘크리트케이슨의 단일 매립형 정착구를 도시한 평면도,23 is a plan view showing a single buried anchorage of the concrete caisson,

도 24는 콘크리트케이슨의 복수 매립형 정착구를 도시한 평면도,24 is a plan view showing a plurality of embedded anchorage of the concrete caisson;

도 25는 콘크리트케이슨의 돌출형 정착구를 도시한 측면도,25 is a side view showing a protruding anchorage of the concrete caisson;

도 26은 콘크리트케이슨의 단일 돌출형 정착구를 도시한 평면도,26 is a plan view showing a single protruding anchorage of the concrete caisson;

도 27은 콘크리트케이슨의 복수 돌출형 정착구를 도시한 평면도,27 is a plan view showing a plurality of projecting anchorage of the concrete caisson;

도 28은 상부플랜지에 단일 정착구가 설치된 상태를 도시한 사시도,28 is a perspective view showing a state in which a single fixing unit is installed on the upper flange,

도 29는 상부플랜지에 복수 정착구가 설치된 상태를 도시한 사시도.29 is a perspective view illustrating a state in which a plurality of fixing units are installed in the upper flange.

- 도면의 주요부분에 대한 부호의 설명--Explanation of the symbols for the main parts of the drawings-

10: 개구제형 파형 스틸거더 12: 파형강판10: opening shaped corrugated steel girders 12: corrugated steel sheet

14: 하부플랜지 16: 상부플랜지14: lower flange 16: upper flange

20: 콘크리트케이슨 22: 바닥콘크리트20: concrete caisson 22: floor concrete

30: 교량상부데크콘크리트 40: 프리스트레스30: deck upper concrete 40: prestress

50: 지점부 60: 난간50: branch 60: handrail

62: 포장 70: PS강재62: packing 70: PS steel

74: 요철형 거푸집 설치용 끼움판 76: 거푸집74: Uneven formwork mounting plate 76: Formwork

80: 콘크리트 다이아프램 82: 정모멘트 정착구80: concrete diaphragm 82: constant moment anchor

84: 부모멘트 정착구 86: 고정쐐기84: parent anchorage fixture 86: fixing wedge

88: 강재거푸집 90: 환봉88: steel die 90: round bar

92: 볼트 94: 전단연결재92: bolt 94: shear connector

96: 철근 98: 강재정착구96: rebar 98: steel anchorage

100: 프리스트레스트 개구제형 파형 스틸거더교100: prestressed opening type corrugated steel girder bridge

본 발명은 상부플랜지에 콘크리트케이슨을 설치한 프리스트레스트 개구제형 파형 스틸거더교의 시공방법에 관한 것으로, 특히 개구제형 파형 스틸거더의 상부플랜지에 직사각형 또는 제형의 콘크리트케이슨을 합성시켜 미경화 교량상부데크콘크리트 하중을 받으므로 상부플랜지의 응력을 콘크리트케이슨에 흡수시켜 상부플랜지 단면을 절감시키도록 한 상부플랜지에 콘크리트케이슨을 설치한 프리스트레스트 개구제형 파형 스틸거더교의 시공방법에 관한 것이다.The present invention relates to a method of constructing a prestressed open-form corrugated steel girder bridge in which a concrete caisson is installed on an upper flange. Particularly, an uncured bridge upper deck concrete is synthesized by synthesizing a concrete caisson of rectangular or formulation to an upper flange of an open-form corrugated steel girder. The present invention relates to a construction method of a prestressed opening type corrugated steel girder bridge in which a concrete caisson is installed in an upper flange to absorb the stress of the upper flange into the concrete caisson to reduce the cross section of the upper flange.

일반적으로 파형강판을 이용한 프리스트레스 합성형 교량의 가설순서는 도 1 내지 도 7에 도시된 바와 같이, 복부를 한 쌍의 파형강판(12)으로 하고, 상기 한 쌍의 파형강판(12)의 하부에 일정한 크기의 강판으로 이루어진 하부플랜지(14)를 용접 접합하며, 상기 파형강판(12)의 각각의 상부에 일정한 크기를 갖는 강판으로 이루어진 상부플랜지(16)를 각각 분리되게 용접 접합하여, 파형 스틸거더(10)를 제작하고(도1 참조), 이 제작된 파형 스틸거더(10)를 교량 전경간에 걸쳐서 설치한다.In general, the construction order of the prestressed composite bridge using corrugated steel sheet is as shown in Figs. 1 to 7, the abdomen is a pair of corrugated steel sheet 12, the lower portion of the pair of corrugated steel sheet 12 Welding the lower flange 14 made of a steel plate of a constant size, and welding the upper flange 16 made of a steel sheet having a predetermined size on each upper portion of the corrugated steel sheet 12 separately welded, corrugated steel girders (10) is fabricated (see Fig. 1), and the fabricated corrugated steel girder 10 is installed over the bridge foreground.

이어서, 상기 파형 스틸거더(10)내 하부플랜지(14) 상면에 바닥콘크리트(22)를 타설하고(도 2, 도 3 참조), 상기 하부플랜지(14)와 바닥콘크리트(22)를 전단연결재로 일체화하여 콘크리트를 양생시킨 후, 상기 바닥콘크리트(22)에 미리 매립된 쉬스관을 통해 강연선을 포설하고, 그 일부에 대해 프리스트레스(40)를 도입한다.(도 4 참조)Subsequently, the bottom concrete 22 is placed on the upper surface of the lower flange 14 in the corrugated steel girder 10 (see FIGS. 2 and 3), and the lower flange 14 and the bottom concrete 22 are sheared as connecting materials. After integrally curing the concrete, the strand is laid through a sheath pipe which is pre-embedded in the bottom concrete 22, and a prestress 40 is introduced into a portion thereof (see FIG. 4).

이어서, 상기 상부플랜지(16) 상부에 교량상부데크콘크리트(30)를 타설하고(도 5 참조), 상기 상부플랜지(16)와 교량상부데크콘크리트(30)를 전단연결재로서 일체화하여 양생시킨 후, 상기 바닥콘크리트(22)에 매립된 잔여분의 강연선에 대해서 프리스트레스(40)를 도입하는 한편, 지점부(50)의 인장영역에서 교량상부데크콘크리트(30)에도 프리스트레스(40)를 도입한다.(도 6 참조)Subsequently, the upper deck concrete 30 is poured over the upper flange 16 (see FIG. 5), and the upper flange 16 and the bridge upper deck concrete 30 are integrally cured as a shear connector, and then cured. The prestress 40 is introduced into the remaining portion of the strand of the concrete embedded in the bottom concrete 22, while the prestress 40 is also introduced into the upper deck concrete 30 in the tension zone of the point portion 50. 6)

이어서, 상기 교량상부데크콘크리트(30) 상면에 난간(60) 및 포장(62) 등을 시공한다.(도 7 참조)Subsequently, handrail 60, pavement 62, etc. are constructed on the upper surface of the bridge deck concrete 30. (See FIG. 7).

상기한 바와 같은 단계로 시공되는 파형강판(12)을 이용한 프리스트레스 합성형 교량 시공방법은 교량 가설단계중 개구제형 파형 스틸거더(10)의 하부플랜지(14)만 바닥콘크리트(22)로 합성이 되고, 프리스트레스(40)가 도입된 채로 상부플랜지(16) 상부에 미경화 교량상부데크콘크리트(30) 하중을 받게 되므로 상부플랜 지(16)가 과도한 응력을 받으므로 파형 스틸거더(10)의 상부플랜지(16)의 강재 단면이 크게 요구되는 단점이 있다.In the prestressed composite bridge construction method using the corrugated steel sheet 12 constructed as described above, only the lower flange 14 of the opening-type corrugated steel girder 10 is synthesized into the bottom concrete 22 during the bridge construction step. Since the prestress 40 is introduced, the upper deck 16 receives an uncured bridge on the upper deck concrete 30, and thus the upper flange 16 is subjected to excessive stress, so the upper flange of the corrugated steel girder 10 is exposed. There is a disadvantage that the steel cross section of (16) is greatly required.

즉, 종래의 파형강판을 이용한 프리스트레스 합성형 교량 시공방법은 상부플랜지에 콘크리트케이슨이 없는 경우는 바닥콘크리트만 합성되므로 중립축이 하향되어 상부플랜지의 응력이 상대적으로 크게 상승되는 문제점이 있다.That is, the conventional prestressed composite bridge construction method using corrugated steel sheet has a problem that the stress of the upper flange is relatively increased because the neutral axis is lowered because only the bottom concrete is synthesized when there is no concrete caisson in the upper flange.

이에, 본 발명은 상기한 바와 같은 제문제점을 해결하기 위해 안출된 것으로써, 본 발명에 따른 상부플랜지에 콘크리트케이슨을 설치한 프리스트레스트 개구제형 파형 스틸거더교의 시공방법의 제1 목적은 하부플랜지 상면에 바닥콘크리트를 타설할 때 상부플랜지 상면에도 직사각형 또는 제형의 콘크리트케이슨을 동시에 타설 양생하여, 교량상부데크콘크리트 타설시 상부데크콘크리트의 하중을 받을 때 주형의 중립축이 콘크리트케이슨으로 인해 상향되므로 양호한 응력분포를 가지며, 상부플랜지의 응력이 콘크리트케이슨으로 흡수되어 상부플랜지 강재단면을 절감하도록 하는 것이다. Accordingly, the present invention has been made to solve the problems described above, the first object of the construction method of the prestressed opening type corrugated steel girder bridge installed concrete caisson in the upper flange according to the present invention is the upper surface of the lower flange When placing concrete on the upper flange, the concrete flange of rectangular or formulation is cast on the upper surface of the upper flange at the same time. The upper flange stress is absorbed into the concrete caisson to reduce the upper flange steel cross section.

또한, 본 발명에 따른 상부플랜지에 콘크리트케이슨을 설치한 프리스트레스트 개구제형 파형 스틸거더교의 시공방법의 제2 목적은 스틸과 바닥콘크리트 그리고 상부플랜지와 콘크리트케이슨으로 구성된 연속형의 합성부재가 시공중 교량상부데크콘크리트 하중을 받을 때 중간지점인 부모멘트부는 콘크리트케이슨에 과도한 인장응력이 시공중 발생될 수 있는데 이를 제어하기 위해서 시공중 지점하강에 의한 프리틀렉션을 하여 인장응력을 줄이는 방법과 또는 콘크리트케이슨에서 상부플 랜지에 강결시킨 정착구에 의해 직접 프리스트레스를 줌으로써 인장응력을 상쇄하는 방법으로 구분할 수 있는 것이다.In addition, a second object of the construction method of the prestressed opening type corrugated steel girder bridge in which the concrete caisson is installed on the upper flange according to the present invention is a bridge during construction of a continuous composite member composed of steel and floor concrete and the upper flange and concrete caisson When the upper deck concrete load is applied, the parent moment part, which is the intermediate point, may generate excessive tensile stress in the concrete caisson during construction. To control this, the method of reducing tensile stress by pre-traction by the point drop during construction and / or concrete caisson It can be divided into the method of offsetting the tensile stress by direct prestressed by the anchorage hardened to the upper flange in.

상기한 목적을 달성하기 위한 본 발명에 따른 상부플랜지에 콘크리트케이슨을 설치한 프리스트레스트 개구제형 파형 스틸거더교의 시공방법은 복부를 한 쌍의 파형강판으로 하고, 상기 한 쌍의 파형강판의 하부에 일정한 크기의 강판으로 이루어진 하부플랜지를 용접 접합하며, 상기 파형강판의 각각의 상부에 일정한 크기를 갖는 강판으로 이루어진 상부플랜지를 각각 분리되게 용접 접합하여, 스틸거더를 제작하고, 이 제작된 스틸거더를 교량 전경간에 걸쳐서 설치한 후, 상기 스틸거더내 하부플랜지 상부에 바닥콘크리트를 타설하고, 상기 하부플랜지와 바닥콘크리트를 전단연결재로 일체화하여 콘크리트를 양생시킨 후, 상기 바닥콘크리트에 미리 매립된 쉬스관을 통해 강연선을 포설하고, 그 일부에 대해 프리스트레스를 도입한 후, 상기 상부플랜지 상부에 교량상부데크콘크리트를 타설하고, 상기 상부플랜지와 교량상부데크콘크리트를 전단연결재로서 일체화하여 양생시킨 후, 상기 바닥콘크리트에 매립된 잔여분의 강연선에 대해서 프리스트레스를 도입하는 한편, 지점부의 인장영역에서 교량상부데크콘크리트에도 프리스트레스를 도입하여 시공하는 파형강판을 이용한 프리스트레스 합성형 교량 시공방법에 있어서, The construction method of the prestressed opening type corrugated steel girder bridge in which the concrete caisson is installed on the upper flange according to the present invention for achieving the above object is to make the abdomen as a pair of corrugated steel sheets, and to be fixed to the lower portion of the pair of corrugated steel sheets. Welding and welding the lower flange made of a steel sheet of size, by welding the upper flange made of a steel sheet having a constant size to each upper portion of the corrugated steel sheet separately to produce a steel girder, bridge the manufactured steel girder bridge After installation over the foreground, after placing the bottom concrete on the lower flange in the steel girder, and curing the concrete by integrating the bottom flange and the bottom concrete with a shear connector, through the sheath pipe pre-embedded in the bottom concrete After laying the strand and introducing prestress to a part of the strand, The upper deck concrete is bridged on the upper part of the bridge, the upper flange and the upper deck concrete are bridged together as a shear connector to cure, and the prestress is introduced to the remaining strands embedded in the bottom concrete, In the prestress composite bridge construction method using corrugated steel sheet which is constructed by introducing prestress to the upper deck concrete of bridge

상기 하부플랜지 상면에 바닥콘크리트 타설시 상부플랜지 상면에 직사각형 또는 제형의 콘크리트케이슨을 동시에 타설 양생함을 특징으로 한다.When placing the bottom concrete on the upper surface of the lower flange is characterized in that the curing of the concrete caisson of the rectangular or formulation on the upper flange at the same time.

이하, 본 발명을 첨부한 예시도면을 참조하여 상세히 설명한다.Hereinafter, with reference to the accompanying drawings, the present invention will be described in detail.

도 8은 본 발명에 따른 개구제형 파형 스틸거더를 도시한 사시도이며, 도 9는 도 8의 상부플랜지 상면과 하부플랜지 상면에 콘크리트가 타설되어 콘크리트케이슨과 바닥콘크리트가 형성된 상태를 도시한 정면도이며, 도 10은 도 9의 상부플랜지에 콘크리트케이슨이 합성된 경우의 응력분포를 도시한 예시도이며, 도 11은 도 9의 콘크리트케이슨에 교량상부데크콘크리트를 형성한 상태를 도시한 정면도이며, 도 12는 도 9의 콘크리트케이슨에 교량상부데크콘크리트 타설시 미경화 교량상부데크콘크리트 하중에 의한 개구제형 스틸거더의 모멘트도이며, 도 13은 본 발명에 따른 상부플랜지에 콘크리트케이슨을 설치한 프리스트레스트 개구제형 파형 스틸거더가 지점부상에 설치된 상태를 도시한 사시도이며, 도 14는 도 13의 지점 하강에 의한 개구제형 스틸거더의 모멘트도이며, 도 15는 도 13의 지점 하강에 의한 개구제형 스틸거더의 모멘트 변화도이며, 도 16은 본 발명에 따른 상부플랜지에 콘크리트케이슨을 설치한 프리스트레스트 개구제형 파형 스틸거더를 도시한 측면도이며, 도 17은 도 16의 A-A선 단면도이며, 도 18은 도 16의 "A"부분을 확대 도시한 상세도이다.8 is a perspective view showing an opening-type corrugated steel girder according to the present invention, Figure 9 is a front view showing a state in which the concrete caisson and the bottom concrete is formed by placing concrete on the upper surface and the upper flange of the upper flange of Figure 8, FIG. 10 is an exemplary view illustrating a stress distribution when a concrete caisson is synthesized in the upper flange of FIG. 9, and FIG. 11 is a front view illustrating a state in which upper deck concrete is formed on the concrete caisson of FIG. 9. FIG. 9 is a moment diagram of an opening-type steel girder due to uncured bridge upper deck concrete load when the upper deck concrete is poured into the concrete caisson of FIG. 9, and FIG. 13 is a prestressed opening type which is installed with a concrete caisson on the upper flange according to the present invention. Fig. 14 is a perspective view showing a state in which a corrugated steel girder is installed on a point portion, and Fig. 14 is an opening-type steel by the point lowering of Fig. 13. FIG. 15 is a moment change diagram of an opening steel girder due to the point lowering of FIG. 13, and FIG. 16 illustrates a prestressed opening steel corrugated steel girder having a concrete caisson installed on an upper flange according to the present invention. It is a side view, FIG. 17 is sectional drawing along the AA line of FIG. 16, and FIG. 18 is the detailed view which expands the "A" part of FIG.

이들 도면에 도시된 바와 같이, 본 발명에 따른 상부플랜지에 콘크리트케이슨을 설치한 프리스트레스트 개구제형 파형 스틸거더교의 시공방법은 복부를 한 쌍의 파형강판(12)으로 하고, 상기 한 쌍의 파형강판(12)의 하부에 일정한 크기의 강판으로 이루어진 하부플랜지(14)를 용접 접합하며, 상기 파형강판(12)의 각각의 상부에 일정한 크기를 갖는 강판으로 이루어진 상부플랜지(16)를 각각 분리되게 용접 접합하여, 개구제형 파형 스틸거더(10)를 제작하고, 이 제작된 개구제형 파형 스틸 거더(10)를 교량 전경간에 걸쳐서 설치한 후, 상기 개구제형 파형 스틸거더(10)내 하부플랜지(14) 상면에 바닥콘크리트(22)를 타설하고, 상기 하부플랜지(14)와 바닥콘크리트(22)를 전단연결재로 일체화하여 콘크리트를 양생시킨 후, 상기 바닥콘크리트(22)에 미리 매립된 쉬스관을 통해 강연선을 포설하고, 그 일부에 대해 프리스트레스(40)를 도입한 후, 상기 상부플랜지(16) 상부에 교량상부데크콘크리트(30)를 타설하고, 상기 상부플랜지(16)와 교량상부데크콘크리트(40)를 전단연결재로서 일체화하여 양생시킨 후, 상기 바닥콘크리트(22)에 매립된 잔여분의 강연선에 대해서 프리스트레스(40)를 도입하는 한편, 지점부(50)의 인장영역에서 교량상부데크콘크리트(30)에도 프리스트레스(40)를 도입하여 시공하는 파형강판을 이용한 프리스트레스 합성형 교량 시공방법에 있어서,As shown in these figures, the construction method of the prestressed opening type corrugated steel girder bridge in which the concrete caisson is installed on the upper flange according to the present invention, the abdomen is a pair of corrugated steel sheet 12, the pair of corrugated steel sheet A lower flange 14 made of a steel plate of a constant size is welded to the lower part of the 12, and the upper flange 16 made of a steel plate having a predetermined size is welded to each upper portion of the corrugated steel sheet 12 separately. After joining, an open shaped corrugated steel girder 10 is manufactured, and the prepared open shaped corrugated steel girder 10 is installed over the bridge foreground, and then the lower flange 14 in the open shaped corrugated steel girder 10. The bottom concrete 22 is poured on the upper surface, the lower flange 14 and the bottom concrete 22 are integrated with a shear connecting material to cure concrete, and then the sheath previously embedded in the bottom concrete 22. After laying the strand through the pipe, the prestress 40 is introduced to a portion thereof, and the upper deck concrete bridge 30 is placed on the upper flange 16, and the upper flange 16 and the upper deck deck bridge After the concrete 40 is integrated and cured as a shear connector, the prestress 40 is introduced with respect to the remaining strand of the concrete embedded in the bottom concrete 22, while the upper deck concrete in the bridge portion in the tension region of the branch portion 50 is introduced. In the prestress composite bridge construction method using a corrugated steel sheet in which the prestress 40 is also introduced and constructed at (30),

상기 하부플랜지(14) 상면에 바닥콘크리트(22) 타설시 상부플랜지(16) 상면에 직사각형 또는 제형의 콘크리트케이슨(20)을 동시에 타설 양생한다.When placing the bottom concrete 22 on the upper surface of the lower flange 14, the concrete caisson 20 of the rectangular or formulation is simultaneously poured on the upper surface of the upper flange 16.

여기서, 상기 콘크리트케이슨(20)을 형성하는 이유는 프리스트레스트 개구제형 파형 스틸거더(10) 시공중 하부플랜지(14)만 바닥콘크리트(22)로 합성하고, 프리스트레스(40)가 도입된 채로 미경화 교량상부데크콘크리트(30) 하중을 받으면 상부플랜지(16)가 과도한 응력을 받게 되므로 상부플랜지(16)의 단면이 크게 요구된다.Here, the reason for forming the concrete caisson 20 is that the lower flange 14 during the construction of the prestressed opening-type corrugated steel girder 10 is synthesized with the bottom concrete 22 and uncured while the prestress 40 is introduced. When the upper deck concrete 30 is loaded, the upper flange 16 is subjected to excessive stress, so the cross section of the upper flange 16 is greatly required.

이를 해결하기 위하여 상부플랜지(16)에 직사각형 또는 제형의 콘크리트케이슨(20)을 형성하여 아직 미경화 교량상부데크콘크리트(30) 하중을 받으므로 상부플랜지(16)의 응력을 콘크리트케이슨(20)에 흡수시킴으로써 상부플랜지(16)의 강재단 면을 절감시키도록 하기 위함이다.In order to solve this problem, the concrete caisson 20 of the rectangular or formulation is formed on the upper flange 16 and is still subjected to the load of the upper deck concrete 30, so that the stress of the upper flange 16 is applied to the concrete caisson 20. This is to reduce the steel cross section of the upper flange 16 by absorbing.

즉, 상부플랜지(16)에 콘크리트케이슨(20)이 있는 경우는 바닥콘크리트(22) 뿐만 아니라 콘크리트케이슨(20)까지 합성되므로 중립축이 상향되어 도 10에 도시된 바와 같이, 상부플랜지(19)의 응력이 줄어들어 양호한 응력분포를 이룬다.That is, when the concrete caisson 20 on the upper flange 16 is synthesized not only to the bottom concrete 22 but also to the concrete caisson 20, the neutral axis is upward, as shown in FIG. 10, of the upper flange 19. The stress is reduced to achieve a good stress distribution.

한편, 상기한 콘크리트케이슨(20)은 콘크리트의 재료특성상 압축영역에서는 강하게 저항할 수 있으나, 인장영역에서는 저항력이 약하게 된다.On the other hand, the concrete caisson 20 may be strongly resistant in the compression region due to the material properties of the concrete, but the resistance is weak in the tensile region.

즉, 상기 콘크리트케이슨(20) 상부에 교량상부데크콘크리트(30) 타설시 부모멘트부가 되는 연속형교의 지점부(50)에서는 교량상부데크콘크리트(30)가 미경화 상태로 교량상부데크콘크리트(30) 재하시 콘크리트케이슨(20)에 인장응력이 일시적으로 크게 증가된다.That is, in the point portion 50 of the continuous bridge that becomes the parent portion when placing the upper deck concrete 30 bridge on the concrete caisson 20, the upper deck concrete 30 is the bridge upper deck concrete (30) The tensile stress on the concrete caisson 20 is temporarily increased significantly.

이를 완화시키기 위해서는 콘크리트케이슨 인장영역에 직접 프리스트레스를 도입하는 방법과
지점부(50)를 하강시켜서 지점부(50)의 부모멘트 크기를 줄이고 콘크리트케이슨(20)에 압축응력이 발생되는 지간 중앙 정모멘트부의 모멘트를 증가시켜서 재료특성에 맞도록 휨을 조정하는 프리플랙션을 도입하여, 상부플랜지(16)에 콘크리트케이슨(20) 단면에서 발생하는 인장응력을 줄일 수 있다.
즉, 지점부를 하강시키고, 프리플랙션을 도입한 것을 특징을 한다.
In order to alleviate this, the prestress is introduced directly into the concrete caisson tension zone.
Preflection to reduce the size of the parent moment of the point portion 50 by lowering the point portion 50 and to increase the moment of the center moment of the inter-gear region in which the compressive stress is generated in the concrete caisson 20 to adjust the bending to match the material properties By introducing, it is possible to reduce the tensile stress generated in the cross section of the concrete caisson 20 on the upper flange (16).
That is, it is characterized by lowering the point portion and introducing prefraction.

또한, 상기 지점부(50)에는 정모멘트부 바닥콘크리트(22) 보다 두껍게 부모멘트부 바닥콘크리트(22a) 타설 양생한다.In addition, the point portion 50 is thickened than the constant moment bottom concrete 22 is poured into the parent cement portion bottom concrete (22a).

즉, 상기 바닥콘크리트(22) 타설시 부모멘트부 바닥콘크리트(22a)에 정모멘트부 바닥콘크리트(22) 보다 두껍게 타설하기 위해 파형강판(12)의 양측면에 요철형 거푸집 설치용 끼움판(74)을 부착하고, 상기 요철형 거푸집 설치용 끼움판(74)의 내측에 거푸집(76)을 끼우고, 부모멘트부에 바닥콘크리트(22a)를 타설 양생하여 바닥콘크리트(22a)를 형성한다.That is, when placing the bottom concrete 22, the mounting plate 74 for installing the uneven formwork on both sides of the corrugated steel sheet 12 in order to pour thicker than the constant moment bottom concrete 22 on the parent concrete portion bottom concrete 22a. Attaching, inserting the formwork 76 to the inside of the uneven form mounting plate 74, the bottom concrete (22a) is poured into the parent portion to form the bottom concrete (22a).

또한, 지간 중앙 정모멘트부는 하부플랜지(14)측 바닥콘크리트(22)에 프리스트레스 쉬스관을 배치하고, 지점부 부모멘트부는 상부플랜지(16)측 교량상부데크콘크리트(30)에 프리스트레스 쉬스관을 배치한다. 정착구의 배치는 상기와 같다.In addition, the inter-center central moment is arranged prestressed sheath pipe on the bottom flange 22 of the lower flange 14, the branch parent portion is prestressed sheath pipe on the upper deck concrete 30 bridge of the upper flange (16) side do. The arrangement of the anchorage is as described above.

그리고, 도 19는 상부플랜지에 콘크리트케이슨의 유무에 따른 응력분포를 도시한 비교도로서, 종래의 상부플랜지(16)에 콘크리트케이슨(20)이 없는 경우는 바닥콘크리트(22)만 합성되므로 중립축이 하향되어 상부플랜지(16) 응력이 상대적으로 크게 상승되나, 본 발명의 상부플랜지(16)에 콘크리트케이슨(20)이 있는 경우는 바닥콘크리트(22) 뿐만 아니라 콘크리트케이슨(20)까지 합성되므로 중립축이 상향되어 상부플랜지(16)의 응력이 줄어들어 양호한 응력분포를 가짐을 알 수 있으며, 이점이 본 발명의 기술적 핵심을 밝혀두는 바이다.And, Figure 19 is a comparative view showing the stress distribution according to the presence or absence of concrete caisson in the upper flange, in the case where there is no concrete caisson 20 in the conventional upper flange 16, since only the bottom concrete 22 is synthesized neutral axis When the upper flange 16 is lowered to be relatively high, but the concrete caisson 20 is present in the upper flange 16 of the present invention, the neutral shaft is synthesized because not only the bottom concrete 22 but also the concrete caisson 20 are synthesized. It can be seen that the upward stress is reduced in the upper flange 16 has a good stress distribution, the advantage is to reveal the technical core of the present invention.

또한, 도 20은 본 발명에 따른 개구제형 파형 스틸거더에 콘크리트케이슨을 형성하기 위해 파형강판 복부에 거푸집을 고정 설치한 상태를 도시한 정면도이며, 도 21은 본 발명에 따른 개구제형 파형 스틸거더의 하부플랜지에 바닥콘크리트 타설시 상부플랜지에 정착구를 용접 접합하고, PS강재로 지점부 부모멘트를 인장하여 압축력을 도시한 상태를 도시한 측면도이며, 도 22는 콘크리트케이슨의 매립형 정착구를 도시한 측면도이며, 도 23은 콘크리트케이슨의 단일 매립형 정착구를 도시한 평면도이며, 도 24는 콘크리트케이슨의 복수 매립형 정착구를 도시한 평면도이며, 도 25는 콘크리트케이슨의 돌출형 정착구를 도시한 측면도이며, 도 26은 콘크 리트케이슨의 단일 돌출형 정착구를 도시한 평면도이며, 도 27은 콘크리트케이슨의 복수 돌출형 정착구를 도시한 평면도이며, 도 28은 상부플랜지에 단일 정착구가 설치된 상태를 도시한 사시도이며, 도 29는 상부플랜지에 복수 정착구가 설치된 상태를 도시한 사시도이다.20 is a front view showing a state in which the form is fixed to the abdomen of the corrugated steel sheet to form a concrete caisson in the opening-form corrugated steel girder according to the present invention, Figure 21 is a view of the opening-form corrugated steel girder according to the present invention When the bottom concrete is placed on the bottom concrete, the anchorage is welded to the upper flange and the compressive force is shown by tensioning the parent portion with PS steel, and FIG. 22 is a side view showing the embedded anchorage of the concrete caisson. 23 is a plan view showing a single buried anchorage of the concrete caisson, FIG. 24 is a plan view showing a plurality of buried anchorages of the concrete caisson, FIG. 25 is a side view showing a protruding anchorage of the concrete caisson, and FIG. 26 is a cone A plan view showing a single protruding anchorage of the litcaisson, and FIG. 27 shows a plurality of protruding anchorages of the concrete caisson. 28 is a perspective view illustrating a state in which a single fixing unit is installed in the upper flange, and FIG. 29 is a perspective view illustrating a state in which a plurality of fixing units are installed in the upper flange.

이들 도면에 도시된 바와 같이, 본 발명에 따른 상부플랜지에 콘크리트케이슨을 설치한 프리스트레스트 개구제형 파형 스틸거더교의 콘크리트케이슨(20) 시공은 바닥콘크리트(22) 타설시 파형강판(12)의 복부 상부 양면에 고정쐐기(86)를 부착하고, 상기 고정쐐기(86)에 L형 강재거푸집(88)을 용접 설치하고, 상기 L형 강재거푸집(88)의 상면을 고정환봉(90)과 볼트(92)로 고정한 후, 상기 L형 강재거푸집(88) 내측에 전단연결재(94)와 철근(96)을 배근하고, 상기 L형 강재거푸집(88)에 콘크리트를 타설 양생시켜 시공한다.As shown in these figures, the construction of the concrete caisson 20 of the prestressed opening-type corrugated steel girder bridge in which the concrete caisson is installed on the upper flange according to the present invention is the upper part of the abdomen of the corrugated steel sheet 12 when the bottom concrete 22 is placed The fixing wedge 86 is attached to both sides, and the L-shaped steel formwork 88 is welded and installed on the fixing wedge 86, and the upper surface of the L-shaped steel formwork 88 is fixed to the stationary rod 90 and the bolt 92. After fixing to), the shear connecting member 94 and the reinforcing bars 96 are placed inside the L-shaped steel formwork 88, and concrete is poured into the L-shaped steel formwork 88 to be constructed.

한편, 상기 상부플랜지(16)에 콘크리트케이슨(20)을 설치할 때, 콘크리트케이슨(20)에 발생되는 인장응력을 감소시키는 방법은 상부플랜지(16)에 일정한 간격을 두고 전단연결재(94)를 설치하고, 내측 지점부(50) 상부플랜지(16)의 부모멘트 구간 양측에 강재정착구(98)를 용접 접합하고, 상기 강재정착구(98)간에 PS강재(70)를 고정 설치함과 동시에 지점부 부모멘트를 인장하여 압축력을 도입하여, 바닥콘크리트(22) 타설시 지점부 상부플랜지(16)에 인장응력이 발생되는 것을 제어한다.On the other hand, when installing the concrete caisson 20 on the upper flange 16, the method for reducing the tensile stress generated in the concrete caisson 20 is installed in the upper flange 16, the shear connecting member 94 at regular intervals. And welding the steel anchoring holes 98 to both sides of the parent section of the inner branch portion 50 and the upper flange 16, and fixing the PS steel 70 between the steel anchoring holes 98 and at the same time. By tensioning the cement, a compressive force is introduced to control the occurrence of tensile stress on the upper flange 16 of the point portion when the bottom concrete 22 is placed.

즉, 본 발명에 따른 상부플랜지에 콘크리트케이슨을 설치한 프리스트레스트 개구제형 파형 스틸거더교의 시공방법은 상부플랜지(16)에 일정한 간격을 두고 전 단연결재(94)를 설치하여 합성 콘크리트케이슨(20)을 구성하고, 내측 지점부인 부모멘트 구간 양측에 강재정착구(98)를 용접 접합하고, 상기 강재정착구(98)간에 PS강재(70)를 고정 설치함과 동시에 지점부 부모멘트를 인장하여 압축력을 도입하여, 바닥콘크리트 타설시 지점부 상부플랜지(16)와 콘크리트케이슨(20)에 과도하게 발생하는 인장응력을 조절 및 제어한다.That is, in the construction method of the prestressed opening type corrugated steel girder bridge in which the concrete caisson is installed on the upper flange according to the present invention, the composite concrete caisson 20 is installed by installing the shear connecting member 94 at regular intervals on the upper flange 16. The steel anchoring holes 98 are welded and joined to both sides of the inner portion of the parent cement section, and the PS steel 70 is fixedly installed between the steel anchoring holes 98 and at the same time, the compressing force is introduced by tensioning the branch portions. By controlling the tensile stress generated excessively in the upper flange 16 and the concrete caisson 20 at the time of placing the concrete floor.

여기서, 상기 상부플랜지(16)에는 그 상면에 강재정착구(98)가 용접으로 강결 연결되며, 프리스트레스 도입 정착시 강재정착구(98)와 콘크리트의 지압으로서 동시에 저항할 수 있는 구조로서, Here, the upper flange 16 is a steel anchoring hole 98 is firmly connected to the upper surface by welding, and the structure that can simultaneously resist the steel anchoring hole 98 and the pressure of the concrete at the time of pre-stress introduction and fixing,

상기 상부플랜지(16)에 콘크리트로 타설 형성되는 콘크리트케이슨(20)에 매립 또는 일정부분 돌출되도록 설치된다.The upper flange 16 is installed so as to be embedded or protrudes in a concrete caisson 20 formed of concrete.

또한, 상기 강재정착구(98)는 PS강재(70)의 고정에 따라 단일형 또는 복수형으로 이루어진 것을 사용한다.In addition, the steel fixing hole 98 uses a single type or a plurality of types according to the fixing of the PS steel 70.

이상에서 설명한 바와 같이, 본 발명에 따른 상부플랜지에 콘크리트케이슨을 설치한 프리스트레스트 개구제형 파형 스틸거더교의 시공방법은 다음과 같은 효과가 있다.As described above, the construction method of the prestressed opening type corrugated steel girder bridge provided with a concrete caisson on the upper flange according to the present invention has the following effects.

첫째, 본 발명은 상부플랜지에 상면에 직사각형 또는 제형의 콘크리트케이슨을 합성시켜서 미경화 교량상부데크콘크리트 하중을 받을 때, 양호한 응력 분포를 가지며, 더구나 상부플랜지의 응력이 콘크리트케이슨에 흡수됨으로써, 상부플랜지의 강재 단면을 줄이는 효과가 있다.First, the present invention has a good stress distribution when the concrete caisson of the rectangular or formulation on the upper flange on the upper flange to receive an uncured bridge upper deck concrete load, the stress of the upper flange is absorbed by the concrete caisson, Has the effect of reducing the steel cross section.

둘째, 본 발명은 시공중 지점하강에 의한 프리플렉션에 의해 지점부의 부모멘트 크기를 줄이고 대신 콘크리트케이슨에 압축응력이 발생되는 중앙부 정모멘트부의 모멘트를 증가시켜서 재료특성에 맞도록 휨을 조정함으로써, 콘크리트케이슨의 단면 크기를 감소시키는 효과가 있다.Secondly, the present invention reduces the size of the parent moment by the preflection due to the point drop during construction, and instead increases the moment of the central moment moment in which the compressive stress is generated in the concrete caisson, thereby adjusting the bending to match the material properties. There is an effect of reducing the cross-sectional size of.

셋째, 본 발명은 내측 지점부 상부플랜지 부모멘트 구간에서 상부플랜지에 강결된 강재정착구를 설치하여 PS강재를 인장함에 따라 부모멘트부 상단에 압축력을 도입하여 상부플랜지 및 콘크리트케이슨의 단면을 감소시키는 효과가 있다.Third, the present invention is to install the steel anchoring hole in the upper flange in the upper flange parent section of the inner point portion to reduce the cross-section of the upper flange and concrete caisson by introducing a compressive force on the top of the parent cement portion as the PS steel is tensioned There is.

넷째, 본 발명은 내측 지점부 부모멘트 구간 하부플랜지 상면에 타설되는 콘크리트는 정모멘트 구간에 타설되는 콘크리트 보다 두껍게 형성함으로써 내측 지점부 하부에서 발생되는 압축응력에 효율적으로 저항할 수 있는 이점이 있다.Fourth, the present invention has the advantage that it can effectively resist the compressive stress generated in the inner point portion by forming the concrete placed on the upper surface of the lower flange portion of the inner portion of the parent portion section thicker than the concrete placed in the constant moment section.

Claims (7)

복부를 한 쌍의 파형강판으로 하고, 상기 한 쌍의 파형강판의 하부에 일정한 크기의 강판으로 이루어진 하부플랜지를 용접 접합하며, 상기 파형강판의 각각의 상부에 일정한 크기를 갖는 강판으로 이루어진 상부플랜지를 각각 분리되게 용접 접합하여, 스틸거더를 제작하고, 이 제작된 스틸거더를 교량 전경간에 걸쳐서 설치한 후, 상기 스틸거더내 하부플랜지 상부에 바닥콘크리트를 타설하고, 상기 하부플랜지와 바닥콘크리트를 전단연결재로 일체화하여 콘크리트를 양생시킨 후, 상기 바닥콘크리트에 미리 매립된 쉬스관을 통해 강연선을 포설하고, 그 일부에 대해 프리스트레스를 도입한 후, 상기 상부플랜지 상부에 교량상부데크콘크리트를 타설하고, 상기 상부플랜지와 교량상부데크콘크리트를 전단연결재로서 일체화하여 양생시킨 후, 상기 바닥콘크리트에 매립된 잔여분의 강연선에 대해서 프리스트레스를 도입하는 한편, 지점부의 인장영역에서 교량상부데크콘크리트에도 프리스트레스를 도입하여 시공하는 파형강판을 이용한 프리스트레스 합성형 교량 시공방법에 있어서,The abdomen is a pair of corrugated steel sheets, and a lower flange made of a steel plate of a constant size is welded to the lower portion of the pair of corrugated steel sheets, and an upper flange made of a steel plate having a constant size on each upper portion of the corrugated steel sheet. Welded to separate, respectively, to produce a steel girder, install the produced steel girder over the bridge foreground, and then the bottom concrete is placed on the upper top of the lower flange in the steel girder, and the bottom flange and the bottom concrete shear connecting material After curing the concrete by integrating the furnace, the strands are laid through the sheath pipe pre-embedded in the bottom concrete, the prestress is introduced into a portion thereof, and the upper deck concrete is poured into the upper flange, and the upper After the flange and the upper deck concrete of the bridge is integrated and cured as a shear connector, the bar In introducing a prestress with respect to the strands of the embedded residue on the other hand concrete, prestressed composite bridge construction method using the corrugated steel plate of the construction by introducing a prestress in the upper bridge deck concrete in the tension zone branch portion, 상기 하부플랜지 상면에 바닥콘크리트 타설시 상부플랜지 상면에 직사각형 또는 제형의 콘크리트케이슨을 동시에 타설 양생함을 특징으로 하는 상부플랜지에 콘크리트케이슨을 설치한 프리스트레스트 개구제형 파형 스틸거더교의 시공방법.Construction method of the pre-stressed opening type corrugated steel girder bridge with the concrete caisson installed on the upper flange, characterized in that when the bottom concrete is placed on the upper flange, the concrete caisson of the rectangular or formulated casting on the upper flange at the same time. 제 1항에 있어서,The method of claim 1, 상기 콘크리트케이슨 형성은 바닥콘크리트 타설시 파형강판의 복부 상부양면에 고정쐐기를 부착하고, 상기 고정쐐기에 L형 강재거푸집을 용접 설치하고, 상기 L형 강재거푸집의 상면을 고정환봉과 볼트로 고정한 후, 상기 L형 강재거푸집 내측에 전단연결재와 철근을 배근하고, 상기 L형 강재거푸집에 콘크리트를 타설 양생시켜 시공함을 특징으로 하는 상부플랜지에 콘크리트케이슨을 설치한 프리스트레스트 개구제형 파형 스틸거더교의 시공방법.The concrete caisson is formed by attaching a fixed wedge to the upper both sides of the upper abdomen of the corrugated steel plate when the bottom concrete is poured, install the L-shaped steel formwork to the fixed wedge, and fix the upper surface of the L-shaped steel formwork with a fixed round bar and bolt Construction of a prestressed opening type corrugated steel girder bridge with concrete caisson installed on the upper flange, characterized in that the reinforcement of the shear connecting material and the reinforcing bar inside the L-shaped steel formwork, and cast concrete to the L-shaped steel formwork. Way. 제 1항에 있어서, The method of claim 1, 상기 콘크리트케이슨의 단면 크기를 감소시키기 위해 지점부를 하강시켜서 지점부의 부모멘트 크기를 감소시킴과 동시에 콘크리트케이슨에 압축응력이 발생되는 지간 중앙 정모멘트부의 모멘트를 증가시켜 휨을 조정하는 프리플랙션을 도입함을 특징으로 하는 상부플랜지에 콘크리트케이슨을 설치한 프리스트레스트 개구제형 파형 스틸거더교의 시공방법.In order to reduce the cross-sectional size of the concrete caisson, the point portion is lowered to reduce the size of the parent moment, and at the same time, the pre-fraction for adjusting the bending by increasing the moment of the center moment of the inter-region in which the compressive stress is generated in the concrete caisson is introduced. Construction method of the prestressed opening type corrugated steel girder bridge with a concrete caisson installed on the upper flange. 제 1항에 있어서,The method of claim 1, 상기 지점부에는 부모멘트 바닥콘크리트를 정모멘트 바닥콘크리트 보다 두껍게 타설 양생함을 특징으로 하는 상부플랜지에 콘크리트케이슨을 설치한 프리스트레스트 개구제형 파형 스틸거더교의 시공방법.The point portion of the construction method of the prestressed opening type corrugated steel girder bridge with a concrete caisson installed on the upper flange, characterized in that the curing of the parent cement floor concrete thicker than the bottom moment concrete. 제 4항에 있어서,The method of claim 4, wherein 상기 바닥콘크리트 타설시 부모멘트부 바닥콘크리트에 정모멘트부 바닥콘크리트 보다 두껍게 타설하기 위해 파형강판의 양측면에 요철형 거푸집 설치용 끼움판을 부착하고, 상기 요철형 거푸집 설치용 끼움판의 내측에 거푸집을 끼우고, 부모멘트부에 콘크리트를 타설 양생하여 바닥콘크리트를 형성함을 특징으로 하는 상부플랜지에 콘크리트케이슨을 설치한 프리스트레스트 개구제형 파형 스틸거더교의 시공방법.In order to pour thicker than the constant moment bottom concrete on the bottom concrete when the floor concrete is poured, attach the mounting plate for the uneven formwork on both sides of the corrugated steel sheet, and insert the formwork inside the mounting plate for the uneven formwork installation The construction method of the prestressed opening type corrugated steel girder bridge in which the concrete caisson is installed on the upper flange, characterized in that the bottom concrete is formed by pouring concrete into the parent part. 제 1항에 있어서,The method of claim 1, 상기 상부플랜지에 일정한 간격을 두고 전단연결재를 설치하여 합성 콘크리트케이슨을 구성하고, 내측 지점부인 부모멘트 구간 양측에 강재정착구를 용접 접합하고, PS강재에 의해 지점부 부모멘트부의 콘크리트케이슨에 과도하게 발생하는 인장응력을 상쇄시킴을 특징으로 하는 상부플랜지에 콘크리트케이슨을 설치한 프리스트레스트 개구제형 파형 스틸거더교의 시공방법.Shear joints are installed at regular intervals on the upper flange to form a composite concrete caisson, welded steel fixtures on both sides of the parent cement section, which are inner branches, and are excessively generated on the concrete caissons of the parent portions of the branch by PS steel. Construction method of the prestressed opening type corrugated steel girder bridge with a concrete caisson installed on the upper flange, characterized in that to cancel the tensile stress. 제 6항에 있어서,The method of claim 6, 상기 상부플랜지에는 그 상면에 강재정착구가 용접으로 강결 접합되며, 프리스트레스 도입 정착시 강재정착구와 콘크리트의 지압으로서 동시에 저항할 수 있는 구조로서, 상기 상부플랜지에 콘크리트로 타설 형성되는 콘크리트케이슨에 매립 또는 일정부분 돌출되도록 강재정착구가 설치됨을 특징으로 하는 콘크리트케이슨을 설치한 프리스트레스트 개구제형 파형 스틸거더교의 시공방법.The upper flange is rigidly joined to the upper surface of the steel fixture by welding, and when the prestress is introduced into the fixed structure and can resist at the same time as the anchorage of the steel fixture and concrete, embedded in the concrete caisson which is poured into the upper flange formed concrete A method of constructing a prestressed opening shaped corrugated steel girder bridge with a concrete caisson characterized in that the steel fittings are installed to partially protrude.
KR1020060046073A 2006-03-31 2006-05-23 The prestressed opening trapezoid waveform still girder construction method of having installed concrete caisson in the upper flange KR100665876B1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR20060029703 2006-03-31
KR1020060029703 2006-03-31

Publications (1)

Publication Number Publication Date
KR100665876B1 true KR100665876B1 (en) 2007-01-09

Family

ID=37867212

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020060046073A KR100665876B1 (en) 2006-03-31 2006-05-23 The prestressed opening trapezoid waveform still girder construction method of having installed concrete caisson in the upper flange

Country Status (1)

Country Link
KR (1) KR100665876B1 (en)

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100800393B1 (en) 2007-09-14 2008-02-01 노윤근 Steel synthetic concrete u girder
KR100811203B1 (en) 2007-01-12 2008-03-07 휘선건설(주) Prestressed composite beam
KR100881921B1 (en) 2008-04-21 2009-02-04 노윤근 Opening trapezoid steel synthetic ugirder construction technique
KR100948358B1 (en) 2009-07-16 2010-03-22 노윤근 Construction technique of steel box girder bridge and this
KR101011443B1 (en) 2010-12-06 2011-01-28 (주) 태평양지질 Structure with integrated slab beam bridge and method of manufacturing thereof
KR101172442B1 (en) 2011-11-18 2012-08-08 삼표건설 주식회사 Construction method for girder using confined concrete
KR101174098B1 (en) 2011-11-18 2012-08-16 삼표건설 주식회사 Construction method for girder using confined concrete
KR101191647B1 (en) 2010-05-28 2012-10-17 (주)삼현피에프 Constructing method of continuous bridge with complex upper structure
KR101251118B1 (en) * 2011-07-08 2013-04-04 주식회사 인터컨스텍 A manufacturing method of a composite steel box girder using prestressed concrete for a positive moment area of a bridge
CN103321137A (en) * 2013-06-19 2013-09-25 江苏科技大学 Groove-shaped bridge beam
KR101358877B1 (en) 2012-02-06 2014-02-06 삼표건설 주식회사 Construction method for continuous bridge using confined concrete
KR101476290B1 (en) * 2014-05-09 2014-12-24 우경기술주식회사 Steel composite PSC corrugated steel plate U girder
KR20180091582A (en) 2017-02-07 2018-08-16 한국철도기술연구원 Composite through bridge and the construction method thereof
RU182810U1 (en) * 2018-04-20 2018-09-04 Федеральное государственное казенное военное образовательное учреждение высшего образования "ВОЕННАЯ АКАДЕМИЯ МАТЕРИАЛЬНО-ТЕХНИЧЕСКОГО ОБЕСПЕЧЕНИЯ имени генерала армии А.В. Хрулева" Collapsible span with a corrugated vertical wall of the main beam and the castle connection of the blocks with large diameter pins
KR20190035117A (en) 2017-09-26 2019-04-03 주식회사 포스코건설 Noise and vibration reduction device of lower through bridge
CN109702366A (en) * 2018-09-28 2019-05-03 江苏中铁山桥重工有限公司 A kind of big sweep rigid torsion opening trough_like girder steel construction method
CN110106772A (en) * 2019-04-16 2019-08-09 河海大学 A kind of highway clod wash U-shaped composite beam bridge and its construction method
KR20200070490A (en) * 2018-12-07 2020-06-18 한국철도기술연구원 Highlevel Structure having Nanocell Type Closed Section
KR20200070491A (en) * 2018-12-07 2020-06-18 한국철도기술연구원 Highlevel Structure having Hybrid Closed Section

Cited By (26)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100811203B1 (en) 2007-01-12 2008-03-07 휘선건설(주) Prestressed composite beam
KR100800393B1 (en) 2007-09-14 2008-02-01 노윤근 Steel synthetic concrete u girder
KR100881921B1 (en) 2008-04-21 2009-02-04 노윤근 Opening trapezoid steel synthetic ugirder construction technique
WO2009131284A1 (en) * 2008-04-21 2009-10-29 Woo Kyoung Construction Co., Ltd. Opening steel composite u girder construction method
KR100948358B1 (en) 2009-07-16 2010-03-22 노윤근 Construction technique of steel box girder bridge and this
WO2011007990A2 (en) * 2009-07-16 2011-01-20 No Yun Keun Steel box girder bridge and method for constructing same
WO2011007990A3 (en) * 2009-07-16 2011-06-03 No Yun Keun Steel box girder bridge and method for constructing same
KR101191647B1 (en) 2010-05-28 2012-10-17 (주)삼현피에프 Constructing method of continuous bridge with complex upper structure
KR101011443B1 (en) 2010-12-06 2011-01-28 (주) 태평양지질 Structure with integrated slab beam bridge and method of manufacturing thereof
KR101251118B1 (en) * 2011-07-08 2013-04-04 주식회사 인터컨스텍 A manufacturing method of a composite steel box girder using prestressed concrete for a positive moment area of a bridge
KR101174098B1 (en) 2011-11-18 2012-08-16 삼표건설 주식회사 Construction method for girder using confined concrete
KR101172442B1 (en) 2011-11-18 2012-08-08 삼표건설 주식회사 Construction method for girder using confined concrete
KR101358877B1 (en) 2012-02-06 2014-02-06 삼표건설 주식회사 Construction method for continuous bridge using confined concrete
CN103321137A (en) * 2013-06-19 2013-09-25 江苏科技大学 Groove-shaped bridge beam
CN103321137B (en) * 2013-06-19 2015-07-08 江苏科技大学 Groove-shaped bridge beam
KR101476290B1 (en) * 2014-05-09 2014-12-24 우경기술주식회사 Steel composite PSC corrugated steel plate U girder
KR20180091582A (en) 2017-02-07 2018-08-16 한국철도기술연구원 Composite through bridge and the construction method thereof
KR20190035117A (en) 2017-09-26 2019-04-03 주식회사 포스코건설 Noise and vibration reduction device of lower through bridge
RU182810U1 (en) * 2018-04-20 2018-09-04 Федеральное государственное казенное военное образовательное учреждение высшего образования "ВОЕННАЯ АКАДЕМИЯ МАТЕРИАЛЬНО-ТЕХНИЧЕСКОГО ОБЕСПЕЧЕНИЯ имени генерала армии А.В. Хрулева" Collapsible span with a corrugated vertical wall of the main beam and the castle connection of the blocks with large diameter pins
CN109702366A (en) * 2018-09-28 2019-05-03 江苏中铁山桥重工有限公司 A kind of big sweep rigid torsion opening trough_like girder steel construction method
CN109702366B (en) * 2018-09-28 2021-01-01 江苏中铁山桥重工有限公司 Manufacturing method of large-curve-radius rigid torsional open-slot steel beam
KR20200070490A (en) * 2018-12-07 2020-06-18 한국철도기술연구원 Highlevel Structure having Nanocell Type Closed Section
KR20200070491A (en) * 2018-12-07 2020-06-18 한국철도기술연구원 Highlevel Structure having Hybrid Closed Section
KR102194475B1 (en) * 2018-12-07 2020-12-24 한국철도기술연구원 Viaduct structure with nanostructural closed sections
KR102194476B1 (en) * 2018-12-07 2020-12-24 한국철도기술연구원 Viaduct structure with hybrid composite sections
CN110106772A (en) * 2019-04-16 2019-08-09 河海大学 A kind of highway clod wash U-shaped composite beam bridge and its construction method

Similar Documents

Publication Publication Date Title
KR100665876B1 (en) The prestressed opening trapezoid waveform still girder construction method of having installed concrete caisson in the upper flange
KR100881921B1 (en) Opening trapezoid steel synthetic ugirder construction technique
KR100836079B1 (en) Structure of precast half slab-girder unit and method constructing the slab of a bridge with it
KR101107826B1 (en) Slab-type box girder made by precast concrete and method constructing the bridge therewith
KR101064731B1 (en) Steel-concrete composite girder and constructing method thereof
KR101045929B1 (en) Pro-environment prestressed long span light-weight precast concrete panel and this construction technique
KR100952623B1 (en) Bridge having deck slab concrete structure on plural beams, constructing method thereof and precast partial-depth deck slab concrete structure used in constructing same
KR100704055B1 (en) continuous steel bridge having precast concrete slab and construction method thereof
KR20080103678A (en) Method for composite girder and bridge construction method composite girder
KR102396444B1 (en) Composite structure of bridge deck and open box girder
KR100343960B1 (en) Steel concrete structure
KR100984249B1 (en) Bridge construction method using strength connector detail and composite curing pannel
KR100543745B1 (en) Manufacturing method for steel-concrete composite girder using delayed composite effects
KR100679570B1 (en) Precast cantilever deck, bridge deck having such precast cantilever deck, and constructing method of such bridge deck
KR100690395B1 (en) Continuous Beam Construction Method of Prestressed Concrete Beam
KR101067717B1 (en) Process for producing prestressed concrete girder and concrete girder structure
KR20080111973A (en) Prestressed steel composite beam and a manufacturing method thereof
KR20070001410A (en) Mounting structure of steel cross-beam in multi-girder concrete bridge and its construction method
KR100897060B1 (en) The continuous bridge structure including a prestressing plate and it's building method
KR100984247B1 (en) Bridge construction method using strength connector detail joined with rebar of upper flange concrete
KR100989153B1 (en) Psc girder connection structure with strength connector detail for substitution of rebar placement in deck and bridge construction method using the same
KR101038714B1 (en) Bridge and its construction method using tide arch hybrid girders having precast slabs
KR100696646B1 (en) External prestressing method of ps concrete composite girder bridge by tendon anchored/supported to prefabricated cross beam
KR100984248B1 (en) Bridge construction method using strength connector detail for curing pannel of upper strength reinforcing block
KR101912422B1 (en) Composite beam fabricating method with pre-load process and composite beam using the same

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130103

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20140103

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20150105

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20151016

Year of fee payment: 10

LAPS Lapse due to unpaid annual fee