KR100620746B1 - Constructing Method for Pipe Supporting Concrete Structure - Google Patents

Constructing Method for Pipe Supporting Concrete Structure Download PDF

Info

Publication number
KR100620746B1
KR100620746B1 KR1020040099965A KR20040099965A KR100620746B1 KR 100620746 B1 KR100620746 B1 KR 100620746B1 KR 1020040099965 A KR1020040099965 A KR 1020040099965A KR 20040099965 A KR20040099965 A KR 20040099965A KR 100620746 B1 KR100620746 B1 KR 100620746B1
Authority
KR
South Korea
Prior art keywords
concrete
concrete structure
foundation
plate
pipe support
Prior art date
Application number
KR1020040099965A
Other languages
Korean (ko)
Other versions
KR20060061094A (en
Inventor
민형주
Original Assignee
두산중공업 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 두산중공업 주식회사 filed Critical 두산중공업 주식회사
Priority to KR1020040099965A priority Critical patent/KR100620746B1/en
Publication of KR20060061094A publication Critical patent/KR20060061094A/en
Application granted granted Critical
Publication of KR100620746B1 publication Critical patent/KR100620746B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/46Foundations for supply conduits or other canals
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/028Laying or reclaiming pipes on land, e.g. above the ground in the ground
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Sewage (AREA)

Abstract

본 발명은 파이프 지지용 콘크리트 구조물 시공 방법에 관한 것으로서, 더욱 상세하게는, 매입 플레이트와 페데스탈을 사전에 일체화한 프리캐스트 콘크리트를 기초부 타설시 일체화함으로써 시공 현장에서의 공정을 단순화 하고 그라우팅 재료의 낭비가 없는 파이프 지지용 콘크리트 구조물 시공 방법에 관한 것이다. The present invention relates to a method for constructing a concrete structure for pipe support, and more particularly, to simplify the process at the construction site and to waste the grouting material by integrating the precast concrete, in which the embedding plate and the pedestal are integrated in advance. The present invention relates to a method for constructing a concrete structure for pipe support without pipes.

본 발명에서는, 매입 플레이트의 앵커들이 상부를 향하게 하고, 그 위쪽으로 페데스탈부에 해당하는 철근을 배근하여 콘크리트를 타설함으로써 매입 플레이트와 페데스탈부가 일체화된 프리캐스트 복합체를 사전에 제작하는 단계; 상기 사전 제작된 프리캐스트 복합체를, 그의 매입 플레이트가 상부를 향하게 한 후 시공 현장의 기초부 배근에 설치하여 기초부에 콘크리트를 타설함으로써 프리캐스트 복합체를 기초부와 일체화 하는 단계; 및 상기 프리캐스트 복합체의 매입 플레이트 상면에 파이프 지지용 새들을 설치하는 단계를 포함하는 파이프 지지용 콘크리트 구조물 시공 방법이 제공된다. In the present invention, the anchoring of the buried plate to the upper side, the reinforcing bars corresponding to the pedestal portion to the upper cast the concrete to prepare a precast composite integrating the buried plate and the pedestal portion; Integrating the precast composite with the foundation by placing the prefabricated precast composite on top of the construction site with its embedded plate facing upwards and placing concrete on the foundation; And it provides a pipe support concrete structure construction method comprising the step of installing the pipe support saddle on the upper surface of the embedded plate of the precast composite.

파이프, 지지, 콘크리트, 구조물, 시공, 담수화 플랜트, 발전소Pipe, support, concrete, structure, construction, desalination plant, power plant

Description

파이프 지지용 콘크리트 구조물 시공 방법{Constructing Method for Pipe Supporting Concrete Structure} Constructing Method for Pipe Supporting Concrete Structure             

도 1은 종래의 일반적인 파이프 지지용 콘크리트 구조물의 구조를 보여주는 개략도이다. 1 is a schematic view showing the structure of a conventional concrete pipe support concrete structure.

도 2a 및 도 2b는 종래의 파이프 지지용 콘크리트 구조물의 시공 순서를 보여주는 도면이다. Figure 2a and 2b is a view showing the construction sequence of a conventional concrete structure for supporting pipes.

도 3a 내지 도 3c는 본 발명에 따른 파이프 지지용 콘크리트 구조물의 시공 순서를 보여주는 도면이다. Figure 3a to 3c is a view showing the construction sequence of the pipe support concrete structure according to the present invention.

도 4는 본 발명에 따라 파이프 지지용 콘크리트 구조물의 시공이 완료된 상태를 보여주는 도면이다. 4 is a view showing a state in which the construction of the concrete structure for pipe support according to the present invention is completed.

<도면의 주요부분에 대한 부호의 설명> <Description of the symbols for the main parts of the drawings>

100 : 프리캐스트 복합체 110 : 매입 플레이트 100: precast composite 110: embedded plate

112 : 앵커 120 : 페데스탈부 112: anchor 120: pedestal

121 : 내부철근 122 : 연결용 철근 121: internal reinforcement 122: connection reinforcement

200 : 기초부 210 : 기초철근 200: foundation 210: foundation rebar

본 발명은, 파이프 지지용 콘크리트 구조물 시공 방법에 관한 것으로서, 더욱 상세하게는, 매입 플레이트와 페데스탈을 사전에 일체화한 프리캐스트 콘크리트를 기초부 타설시 일체화함으로써 시공 현장에서의 공정을 단순화 하고 그라우팅 재료의 낭비가 없는 파이프 지지용 콘크리트 구조물 시공 방법에 관한 것이다. The present invention relates to a method for constructing a concrete structure for pipe support, and more particularly, to simplify the process in the construction site by integrating the precast concrete, in which the embedding plate and the pedestal have been previously integrated, at the time of foundation laying, The present invention relates to a method for constructing a concrete structure for supporting pipes without waste.

담수화 플랜트나 발전소(보일러) 플랜트 등에는 직경이 1.2m나 되는 대구경의 파이프들이 배관되는 예가 흔히 있다. In the desalination plant or power plant (boiler) plant, a large diameter pipe of 1.2 m in diameter is common.

예를들어, 담수화 플랜트에서 브라인 순환 펌프(Brine Recirculration Pump)의 인입측 파이프나 토출측 파이프 등이 그것인데, 이러한 파이프 들은 진동이나 처짐에 대비하여 파이프의 아래부분을 콘크리트 구조물로써 지지하고 있다. In desalination plants, for example, the inlet or outlet pipes of the Brine Recirculration Pump, which support the lower part of the pipe as a concrete structure in case of vibration or sag.

첨부도면 도 1에는 종래의 파이프 지지용 콘크리트 구조물을 보여주는 것으로서, 철근 콘크리트로 이루어지는 기초부(10) 위에 철근 콘크리트로 이루어지는 페데스탈부(20)가 타설되어 있고, 상기 페데스탈부(20) 상면에는 매입 플레이트(30)가 설치되며, 상기 매입 플레이트(30) 위에 파이프(2)를 지지하는 새들(40)이 설치되는 구조로 이루어져 있다. 1 shows a conventional concrete structure for supporting pipes, a pedestal portion 20 made of reinforced concrete is placed on a foundation 10 made of reinforced concrete, and an upper plate of the pedestal portion 20 is embedded. 30 is installed, and the saddle 40 for supporting the pipe (2) is installed on the embedding plate (30).

이와 같은 파이프 지지용 콘크리트 구조물에 대한 종래의 시공 순서는 도 2a및 도 2b에 도시되어 있다. The conventional construction sequence for such a pipe support concrete structure is shown in Figures 2a and 2b.

즉, 종래에는 도 2a에 도시된 것과 같이, 기초부(10)에 대한 철근(12)을 배근한 다음, 콘크리트를 타설하여 기초부(10)를 완성하고, 상기 기초부(10) 위에 페데스탈부(20)에 해당하는 철근(22)을 배근한 다음 콘크리트를 타설하여 일체화 한다. That is, in the related art, as shown in FIG. 2A, the reinforcing bars 12 are disposed on the base part 10, and then the concrete is poured to complete the base part 10, and the pedestal part is placed on the base part 10. After reinforcing the reinforcing bar 22 corresponding to (20), the concrete is poured and integrated.

그런 다음, 도 2b에 도시된 것과 같이, 페데스탈부(20)의 상면에 오목하게 형성된 매입홈(24)에 매입 플레이트(30)의 앵커(32)들을 삽입시킨 다음 페데스탈부(20)와 매입 플레이트(30) 사이의 공간에 그라우팅 재료(50)를 채워 일체화 하였다. Then, as shown in FIG. 2B, the anchors 32 of the embedding plate 30 are inserted into the recess groove 24 formed concave on the upper surface of the pedestal portion 20, and then the pedestal portion 20 and the embedding plate are inserted. The grouting material 50 was filled in the space between the 30 to integrate.

이와 같이 종래에는, 기초부(10)를 시공하고, 거기에 페데스탈부(20)를 시공하며, 거기에 매입 플레이트(30)를 설치하는 3단계의 공정을 수행하여야 하였으므로, 공사 기간이 지연되는 한편, 특히 매입 플레이트(30) 바닥과 페데스탈부(20) 상면 사이의 공간(Gap) 및 매입홈(24)에 그라우팅 재료(50)를 채워야만 함으로써, 시공이 복잡하고 그라우팅 재료가 낭비되는 폐단이 있었다. As such, in the related art, since the three-step process of constructing the foundation part 10, constructing the pedestal part 20, and installing the embedding plate 30 therein has to be performed, the construction period is delayed. In particular, the gap between the bottom of the buried plate 30 and the upper surface of the pedestal 20 and the filling groove 24 must be filled with the grouting material 50, thereby resulting in a complicated construction and waste of grouting material. .

본 발명은, 위와 같은 종래의 여러 가지 단점과 한계를 극복하기 위하여 개발된 것으로서, 본 발명의 목적은 시공 현장에서의 공정을 단순화 하고 그라우팅 재료의 낭비가 없도록 하는데 있다.
The present invention has been developed to overcome the various disadvantages and limitations of the prior art as described above, the object of the present invention is to simplify the process in the construction site and to avoid the waste of grouting material.

본 발명은, 위와 같은 종래의 현장 타설 파이프 지지용 콘크리트 구조물 시공 방법이 가지고 있는 여러 가지 단점과 한계를 극복하기 위하여 개발된 것으로서, 본 발명에서는 매입 플레이트와 페데스탈부를 사전에 별도로 일체화하여 제작한 프리캐스트 구조물을 마련하고, 이를 시공 현장의 기초부 타설시 일체화 하는 파이프 지지용 콘크리트 구조물 시공 방법이 제공된다. The present invention was developed in order to overcome various disadvantages and limitations of the above-described conventional method for constructing concrete structures for cast-in-place concrete pipes, and in the present invention, the precast plate and pedestal unit are separately pre-integrated and manufactured. There is provided a method of constructing a concrete structure for pipe support, which provides a structure and integrates it when placing the foundation part of a construction site.

구체적으로 본 발명에 따른 파이프 지지용 콘크리트 구조물 시공 방법은, 매입 플레이트의 앵커들이 상부를 향하게 하고, 그 위쪽으로 페데스탈부에 해당하는 철근을 배근하여 콘크리트를 타설함으로써 매입 플레이트와 페데스탈부가 일체화된 프리캐스트 복합체를 사전에 제작하는 단계; 상기 사전 제작된 프리캐스트 복합체를, 그의 매입 플레이트가 상부를 향하게 한 후 시공 현장의 기초부 배근에 설치하여 기초부에 콘크리트를 타설함으로써 프리캐스트 복합체를 기초부와 일체화 하는 단계; 및 상기 프리캐스트 복합체의 매입 플레이트 상면에 파이프 지지용 새들을 설치하는 단계를 포함하는 것을 특징으로 한다. Specifically, the method for constructing a concrete structure for pipe support according to the present invention is to precast the buried plate and the pedestal part by placing the anchors of the buried plate facing upward and reinforcing the reinforcing bars corresponding to the pedestal part. Preparing the composite in advance; Integrating the precast composite with the foundation by placing the prefabricated precast composite on top of the construction site with its embedded plate facing upwards and placing concrete on the foundation; And installing a pipe support saddle on the upper surface of the embedded plate of the precast composite.

이하, 첨부된 예시도면을 참조하여 본 발명의 바람직한 실시예를 상세하게 설명한다. Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings.

첨부도면 도 3a 내지 도 3c에는 본 발명에 따른 파이프 지지용 콘크리트 구조물의 시공 순서를 보여주는 도면이 도시되어 있다. 3a to 3c are drawings showing the construction sequence of the pipe support concrete structure according to the present invention.

도 3a에 도시된 것과 같이, 사전에 준비된 거푸집(4) 내에 매입 플레이트(110)의 앵커(112)들이 상부를 향하게 하여 안착시킨 다음, 그 위쪽으로 페데스탈 부(120)를 콘크리트 타설하여 매입 플레이트(110)와 페데스탈부(120)가 일체화된 프리캐스트 복합체(100)를 형성한다. As shown in FIG. 3A, the anchors 112 of the embedding plate 110 are seated upwards in the previously prepared formwork 4, and then the concrete is poured into the embedded pedestal 120. 110 and the pedestal portion 120 forms an integrated precast composite 100.

도 3a에서는 페데스탈부(120)를 이루는 철근이 배근된 상태는 생략하였으나, 콘크리트 타설에 앞서 상기 매입 플레이트(110) 위에 페데스탈부(120)를 이루는 철근을 배근하는 것은 당연하다. In FIG. 3A, the reinforcing bars forming the pedestal part 120 are omitted, but it is natural to reinforce the reinforcing bars forming the pedestal part 120 on the embedding plate 110 before the concrete is placed.

그리고, 시공 현장에는 먼저, 도 3b에 도시된 것과 같이, 기초부(200)를 이루는 기초 철근(210)을 배근하여 놓는다. Then, at the construction site, as shown in FIG. 3B, the foundation reinforcing bars 210 forming the foundation 200 are placed.

그리고, 앞서 사전에 제작된 프리캐스트 복합체(100)를 기초부(200)에 배그된 기초 철근(210) 위에 연결 설치한 다음, 기초부(200)에 콘크리트를 타설하여 상기 프리캐스트 복합체(100)를 기초부(200)와 일체화한다. In addition, the precast composite 100 previously prepared is connected to and installed on the foundation reinforcement 210 bagged on the foundation 200, and then cast concrete on the foundation 200 to precast the composite 100. It is integrated with the base portion 200.

따라서, 시공 현장에서 기초부를 시공하고, 거기에 페데스탈부를 시공하며, 거기에 다시 매입 플레이트를 설치하던 종래의 3단계의 공정이, 프리캐스트 복합체(100)를 기초부(200)에 일체화 하는 2단계의 공정으로 줄어든다. Therefore, the conventional three-step process of constructing the foundation part at the construction site, constructing the pedestal part therein, and installing the embedding plate there again is a two-step process of integrating the precast composite 100 into the foundation part 200. Is reduced to the process of.

또한, 도 3c에 도시된 것과 같이, 매입 플레이트 바닥과 페데스탈부 상면 사이의 공간 및 매입홈에 그라우팅 재료를 채워야만 하였던 종래의 공정이 삭제되는 것이다. In addition, as shown in FIG. 3C, the conventional process, which had to fill the grouting material in the recess and the space between the buried plate bottom and the top of the pedestal, is eliminated.

여기서, 상기 프리캐스트 복합체(100)와 기초 철근(210)과의 연결방법은, 도 3b에 도시된 것과 같이, 프리캐스트 복합체(100)의 내부철근(121)들과 연결된 연결용 철근(122)을 외부로 노출시켜, 이를 기초 철근(210)에 연결시키는 통상적인 방법을 사용할 수도 있다. Here, the connection method of the precast composite 100 and the base reinforcement 210, as shown in Figure 3b, connecting reinforcing bars 122 connected to the internal reinforcement 121 of the precast composite 100 By exposing to the outside and connecting it to the base reinforcement 210 may be used.

이와 같이 하여 일정 기간 동안 양생하면, 도 4에 도시된 것과 같이, 상면에 매입 플레이트(110)가 일체로 구비된 프리캐스트 복합체(100)가 기초부(200)에 일체로 설치된 파이프 지지용 콘크리트 구조물의 시공이 완료된다. In this way, if the curing for a certain period, as shown in Figure 4, the precast composite 100 having a buried plate 110 is integrally provided on the upper surface of the pipe support concrete structure is integrally installed on the base 200 Construction is completed.

따라서, 상기 매입 플레이트(110)의 상면에 전술한 새들을 안착시켜 파이프를 지지할 수 있게 된다. Therefore, it is possible to support the pipe by seating the above-described saddle on the upper surface of the embedded plate (110).

위와 같은 본 발명에 따르면, 종래에 시공 현장에서 기초부를 시공하고, 거기에 페데스탈부를 시공하며, 거기에 다시 매입 플레이트를 설치하던 3단계의 공정이, 사전에 제작된 프리캐스트 복합체를 기초부에 일체화 하는 2단계의 단순한 공정으로 줄어듬으로써, 공정을 단순화 하여 공사 기간을 단축할 수 있다. According to the present invention as described above, the three-step process of conventionally constructing the foundation part at the construction site, constructing the pedestal part therein, and installing the embedding plate therein, integrates a precast composite prepared beforehand into the foundation part. By reducing to a simple two-step process, the process can be simplified to shorten the construction period.

또한, 매입 플레이트가 사전에 페테스탈부에 일체로 제작되므로 매입 플레이트 바닥과 페데스탈부 상면 사이에 공간을 형성할 필요도, 매입 플레이트의 앵커를 정착하기 위한 매입홈도 필요치 않고, 그에 따라 상술한 공간이나 매입홈에 그라우팅 재료를 채울 필요도 없으므로, 그라우팅 재료의 낭비도 방지할 수 있게 된다. In addition, since the embedding plate is made integrally with the pedestal part in advance, there is no need to form a space between the embedding plate bottom and the pedestal upper surface, and there is no need for an embedding groove for fixing the anchor of the embedding plate. Since the grouting material does not need to be filled in the recess groove, the waste of the grouting material can be prevented.

Claims (1)

파이프의 하단을 새들로 지지하는 경우, 상기 새들을 안착시키기 위한 지지용 콘크리트 구조물을 시공하는 방법에 있어서, In the case of supporting the bottom of the pipe with a saddle, in the method for constructing a support concrete structure for seating the saddle, 매입 플레이트의 앵커들이 상부를 향하게 하고, 그 위쪽으로 페데스탈부에 해당하는 철근을 배근하여 콘크리트를 타설함으로써 매입 플레이트와 페데스탈부가 일체화된 프리캐스트 복합체를 사전에 제작하는 단계; Pre-fabricating the precast composite in which the embedding plate and the pedestal portion are integrated by placing the anchors of the embedding plate upward and reinforcing the concrete corresponding to the pedestal portion upward; 상기 사전 제작된 프리캐스트 복합체를, 그의 매입 플레이트가 상부를 향하게 한 후 시공 현장의 기초부 배근에 설치하여 기초부에 콘크리트를 타설함으로써 프리캐스트 복합체를 기초부와 일체화 하는 단계; 및 Integrating the precast composite with the foundation by placing the prefabricated precast composite on top of the construction site with its embedded plate facing upwards and placing concrete on the foundation; And 상기 프리캐스트 복합체의 매입 플레이트 상면에 파이프 지지용 새들을 설치하는 단계를 포함하는 것을 특징으로 하는 파이프 지지용 콘크리트 구조물 시공 방법. The pipe support concrete structure construction method comprising the step of installing a pipe support saddle on the upper surface of the embedded plate of the precast composite.
KR1020040099965A 2004-12-01 2004-12-01 Constructing Method for Pipe Supporting Concrete Structure KR100620746B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020040099965A KR100620746B1 (en) 2004-12-01 2004-12-01 Constructing Method for Pipe Supporting Concrete Structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020040099965A KR100620746B1 (en) 2004-12-01 2004-12-01 Constructing Method for Pipe Supporting Concrete Structure

Publications (2)

Publication Number Publication Date
KR20060061094A KR20060061094A (en) 2006-06-07
KR100620746B1 true KR100620746B1 (en) 2006-09-12

Family

ID=37157685

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020040099965A KR100620746B1 (en) 2004-12-01 2004-12-01 Constructing Method for Pipe Supporting Concrete Structure

Country Status (1)

Country Link
KR (1) KR100620746B1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102679040B (en) * 2012-05-15 2014-12-10 上海交通大学 Construction method for preventing reinforced concrete pipe joint from being damaged and leaking slurry in pipe-jacking construction

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5231203U (en) 1975-08-27 1977-03-04
JPS5430708U (en) 1977-08-03 1979-02-28
JPS61151328A (en) 1984-12-22 1986-07-10 Hitachi Plant Eng & Constr Co Ltd Installation structure for machinery
JPS6268928A (en) 1985-09-20 1987-03-30 Kajima Corp Construction for foundation for setting machine
JPH0583127U (en) * 1992-04-10 1993-11-09 日本碍子株式会社 Composite fireproof panel
KR0140327B1 (en) * 1994-12-28 1998-06-15 김만제 Method for manufacturing high tenacity metal board cement composite panel
JP2001329545A (en) 2000-05-22 2001-11-30 Yamakawa Kensetsu Kk Bridge pier foundation construction method and floor slab for bridge pier

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5231203U (en) 1975-08-27 1977-03-04
JPS5430708U (en) 1977-08-03 1979-02-28
JPS61151328A (en) 1984-12-22 1986-07-10 Hitachi Plant Eng & Constr Co Ltd Installation structure for machinery
JPS6268928A (en) 1985-09-20 1987-03-30 Kajima Corp Construction for foundation for setting machine
JPH0583127U (en) * 1992-04-10 1993-11-09 日本碍子株式会社 Composite fireproof panel
KR0140327B1 (en) * 1994-12-28 1998-06-15 김만제 Method for manufacturing high tenacity metal board cement composite panel
JP2001329545A (en) 2000-05-22 2001-11-30 Yamakawa Kensetsu Kk Bridge pier foundation construction method and floor slab for bridge pier

Also Published As

Publication number Publication date
KR20060061094A (en) 2006-06-07

Similar Documents

Publication Publication Date Title
KR100662811B1 (en) Non-synthetic complex steel pipe columm having tie ends for filling a steel soncrete and construction method thereof
KR20140047118A (en) Foundation system for bridges
US9695558B2 (en) Foundation system for bridges and other structures
CN105155724A (en) Construction method of structural column for simultaneous construction with frame-structured filled wall
KR20070111000A (en) Fabrication-type slab bridge constructed by supporting h-girder to connection member inserted on matrix pile column and construction method thereof
KR20110038443A (en) Connecting method and connecting structure between footing and prestressed precast concrete pile
KR102197106B1 (en) Slab unit implanted with means for pressing pile and the method for carrying out the construction of the steel column using it
KR100665679B1 (en) Combined retaining wall and the making method
KR20090118722A (en) Precast foundation and pile connection structure between precast foundation and pile
KR100620746B1 (en) Constructing Method for Pipe Supporting Concrete Structure
JP2019100087A (en) Pile head isolation structure and construction method thereof
JP2004100157A (en) Retaining wall structure and its construction method
JP5197453B2 (en) Building foundations and foundation construction methods
JPS6313197Y2 (en)
JP2004124458A (en) Construction method for precast concrete ring in pile head part
JP2515227B2 (en) Installation method of cast-in-place concrete foundation and precast concrete wall slab
JP5290714B2 (en) PRECAST CONCRETE MEMBER FOR WAVE RETURN PART OF DAM WALL WALL
KR100722198B1 (en) Strut system of temporary retaining wall and subgrade external wall construction method utilizing the same
JPH1096210A (en) Method of executing enlargement of bridge pier
KR200428941Y1 (en) Strut system of temporary retaining wall
JPH0657768A (en) Retaining wall structure and working method thereof
KR102616234B1 (en) Connection method of concrete filled tube bridge column and reinforced concrete footing
JP5000771B2 (en) Septic tank installation structure
KR102527148B1 (en) Ground foundation structure and its construction method
KR102570497B1 (en) PC abutment wall and concrete foundation hinge joining construction method and structure

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20110802

Year of fee payment: 6

LAPS Lapse due to unpaid annual fee