KR100488130B1 - Precast concrete counterforts retaining wall - Google Patents

Precast concrete counterforts retaining wall Download PDF

Info

Publication number
KR100488130B1
KR100488130B1 KR10-2002-0047334A KR20020047334A KR100488130B1 KR 100488130 B1 KR100488130 B1 KR 100488130B1 KR 20020047334 A KR20020047334 A KR 20020047334A KR 100488130 B1 KR100488130 B1 KR 100488130B1
Authority
KR
South Korea
Prior art keywords
retaining wall
wall
prefabricated
installation
space
Prior art date
Application number
KR10-2002-0047334A
Other languages
Korean (ko)
Other versions
KR20040014707A (en
Inventor
정석태
우혁근
Original Assignee
진성토건 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 진성토건 주식회사 filed Critical 진성토건 주식회사
Priority to KR10-2002-0047334A priority Critical patent/KR100488130B1/en
Publication of KR20040014707A publication Critical patent/KR20040014707A/en
Application granted granted Critical
Publication of KR100488130B1 publication Critical patent/KR100488130B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/205Securing of slopes or inclines with modular blocks, e.g. pre-fabricated
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Abstract

본 발명은 산간 도로 등의 가장 자리에 설치되어 산비탈 등지에서 흘러내리는 토사가 도로를 침범하는 것을 방지하기 위하여 별도의 장소에서 미리 제작된 옹벽을 작업현장에서 단순 조립하여 설치하는 조립식 옹벽에 있어서, 옹벽(10)의 벽체(11) 하단 양측과, 벽체(11)의 배면에 하향 경사지게 설치되는 뒷부벽(13)의 하단에 다리부(12)(14)를 형성하여 옹벽(10)의 하단부에 공간부(15)가 형성되며, 일렬상으로 상기 옹벽(10)을 위치시킬때 다리부(12) 사이에 소정의 공간이 형성되도록 상기 옹벽(10)의 다리부(12)의 가장자리에 단턱부(12a)를 형성시킨 조립식 옹벽에 관한 것이다. 본 발명은 조립식 옹벽의 벽체와 뒷부벽의 하단에 다리부를 형성하여 옹벽의 하단부에 공간부를 형성하여 옹벽 하부에 철근부의 설치가 용이하도록 하므로서, 옹벽 설치에 따른 작업성을 향상시킬 수 있게 된다. 또한, 옹벽 벽체의 뒷부벽 상단에는 일정면적이 형성되도록 접촉면을 형성하므로서, 옹벽의 설치 후에 옹벽에 가로등, 방호벽, 낙석방지책과 같은 기타 도로 제반시설의 설치를 쉽고 용이하게 할 수 있게 된다.The present invention is a prefabricated retaining wall installed in the prefabricated retaining wall in a separate site in order to prevent the earth and sand flowing down from the slope of the mountain slope, etc. to invade the road, retaining wall in the prefabricated retaining wall Legs 12 and 14 are formed at both lower ends of the wall 11 of the wall 10 and at the lower end of the rear wall 13 which is inclined downward on the rear surface of the wall 11 to form a space at the lower end of the retaining wall 10. A portion 15 is formed, and when the retaining wall 10 is positioned in a line, a stepped portion is formed at an edge of the leg portion 12 of the retaining wall 10 so that a predetermined space is formed between the leg portions 12. A prefabricated retaining wall in which 12a) is formed. The present invention forms a leg portion at the lower end of the wall and the rear wall of the prefabricated retaining wall to form a space portion at the lower end of the retaining wall to facilitate the installation of the reinforcing bar in the lower portion of the retaining wall, thereby improving workability according to the retaining wall installation. In addition, by forming a contact surface to form a predetermined area at the top of the rear wall of the retaining wall wall, it is possible to easily and easily install other road facilities such as street lights, protective walls, rockfall prevention measures on the retaining wall after installation of the retaining wall.

Description

조립식 옹벽{Precast concrete counterforts retaining wall}Precast Concrete Counterforts Retaining Wall

본 발명은 도로 주변에 설치되는 옹벽을 별도로 준비한 후 이를 설치를 필요로 하는 도로로 이동시켜 설치하는 조립식 옹벽에 관한 것으로, 더욱 상세하게는 조립식 옹벽의 하단에 다리부를 형성하여 옹벽 하부에 철근의 설치를 용이하게 하므로서, 옹벽 설치에 따른 작업성을 향상토록 함은 물론, 옹벽의 후벽부 상단에는 일정면적이 형성되도록 접촉면을 형성하여 옹벽의 설치 후에 가로등과 같은 기타 설비를 설치할 수 있도록 한 조립식 옹벽에 관한 것이다.The present invention relates to a prefabricated retaining wall is prepared by separately preparing the retaining wall to be installed around the road to move to the road that needs to be installed, and more specifically, to form a leg at the bottom of the prefabricated retaining wall to install the reinforcing bar in the lower retaining wall It is easy to improve the workability of the retaining wall installation, as well as to form a contact surface to form a certain area at the top of the rear wall portion of the retaining wall to provide a prefabricated retaining wall to install other equipment such as street lights after installing the retaining wall will be.

일반적으로, 도로 옹벽이라 함은 산간 도로 등의 가장 자리에 설치되어 산비탈 등지에서 지형으로부터 흘러내리는 토사가 도로를 침범 및 붕괴를 방지하는 데 사용하는 것으로, 지금까지는 콘크리트 구조물을 시공하듯이 기초 시공후 그 위에 합판거푸집을 설치하여 높이에 따라 단계적으로 벽체를 현장에서 타설하여 시공하는 현장타설공법이 사용되었다.In general, road retaining walls are used to prevent invasion and collapse of roads that are installed on the edges of mountain roads and flow down from the terrain on mountain slopes. On-site casting method was used to install plywood formwork and to install the wall in stage according to the height.

하지만, 이와 같은 현장타설공법은 작업현장에서 설치하기 때문에 옹벽을 설치하고 콘크리트가 경화하는 동안 많은 시간이 경과해야 만이 옹벽의 역할을 수행할 수 있게 됨은 물론, 거푸집의 설치 및 해체, 철근조립 등에 많은 시간이 소요되게 되었다. 이 때문에 최근에는 미리 제작장 또는 공장에서 제작하여 양생이 완료된 옹벽을 작업현장으로 이동시킨 다음 현장에서 단순 조립하여 설치하는 조립식 옹벽이 사용되고 있다.However, since the site casting method is installed at the work site, it is only necessary to have a long time during the installation of the retaining wall and the concrete hardening, so that the retaining wall can play the role of the retaining wall. It took time. For this reason, recently, a prefabricated retaining wall has been used to move the retaining wall, which has been cured in advance in a manufacturing workshop or a factory, to a work site, and then simply assembled and installed at the site.

그러나, 이러한 용도로 사용되는 종래의 조립식 옹벽에 의하면, 옹벽 벽체의 하단부가 도 1에 도시된 바와 같이 민자 즉, 수평면으로 형성되므로서, 조립식 옹벽을 설치하기 위한 기초공사인 철근망의 기초부 공사가 어려웠고, 이에 따라 작업성이 저하되는 문제점이 발생하였으며, 철근망의 기초부 공사 후에 인양장비를 통해 옹벽(100)을 조립, 설치한다 하더라도 수평을 유지하기가 매우 어려운 문제점이 발생하였다.However, according to the conventional prefabricated retaining wall used for this purpose, since the lower end portion of the retaining wall wall is formed in a flat surface, that is, a horizontal plane, as shown in Figure 1, the foundation construction of the reinforcing steel network, which is the foundation for installing the prefabricated retaining wall It was difficult, and thus workability was deteriorated, and even when the retaining wall 100 was assembled and installed through lifting equipment after the foundation of the reinforcing bar network, it was very difficult to maintain the level.

또한, 옹벽(100)을 지지, 고정하여 안정성을 확보하기 위한 목적으로 옹벽(100)의 벽체(111) 배면에 설치되는 뒷부벽(113)이 벽체(111)의 상부에서 하방으로 하향경사지게 설치되면서 뒷부벽(113)의 상부에 일정면적을 갖는 접촉면이 없게 형성되므로서, 조립식 옹벽(100)을 설치한 후 도로에 필요한 가로등, 이정표, 방음벽, 낙석방지책 등의 제반시설 등의 설치가 매우 불편하였으며, 이로 인해 상기와 같은 도로 제반시설 등을 도로 일측에 돌출되게 설치하게 됨에 따라 안전사고의 위험도 뒤따르게 되었다.In addition, the rear wall 113 installed on the rear surface of the wall 111 of the retaining wall 100 is installed to be inclined downward from the top of the wall 111 to support and fix the retaining wall 100 to secure stability. Since there is no contact surface having a certain area on the upper part of the rear wall 113, after installing the prefabricated retaining wall 100, it was very inconvenient to install various facilities such as streetlights, milestones, soundproof walls, and rockfall prevention measures required for the road. As a result, as the above-mentioned road facilities are protruded on one side of the road, the risk of safety accidents is also followed.

본 발명은 상기와 같은 종래의 문제점을 해결하기 위해 안출된 것으로서, 본 발명의 주된 목적으로는 조립식 옹벽의 하단에 다리부를 형성하여 옹벽 하부에 철근의 설치를 용이하게 함으로서, 옹벽 설치에 따른 작업성을 향상시킬 수 있도록 한 조립식 옹벽을 제공하는데 있다.The present invention has been made to solve the conventional problems as described above, the main object of the present invention is to form a leg at the bottom of the prefabricated retaining wall to facilitate the installation of reinforcing bars in the bottom of the retaining wall, workability according to the retaining wall installation To provide a prefabricated retaining wall that can be improved.

본 발명의 다른 목적으로는 조립식 옹벽의 후벽부 상단에 일정면적이 형성되도록 접촉면을 형성시킴으로서, 옹벽의 설치 후에 옹벽에 가로등과 같은 기타 설비를 설치할 수 있도록 한 조립식 옹벽을 제공하는데 있다.Another object of the present invention is to provide a prefabricated retaining wall that allows the installation of the other retaining wall, such as a street lamp after the installation of the retaining wall by forming a contact surface to form a predetermined area on the top of the rear wall portion of the prefabricated retaining wall.

상기 목적을 달성하기 위한 본 발명은, 산간 도로 등의 가장 자리에 설치되어 산비탈 등지에서 흘러내리는 토사가 도로를 침범하는 것을 방지하기 위하여 별도의 장소에서 미리 제작된 옹벽을 작업현장에서 단순 조립하여 설치하는 조립식 옹벽에 있어서, 옹벽의 벽체 하단 양측과, 벽체의 배면에 하향 경사지게 설치되는 뒷부벽의 하단에 다리부를 형성하여 옹벽의 하단부에 공간부가 형성되며, 일렬상으로 상기 옹벽을 위치시킬때 다리부 사이에 소정의 공간이 형성되도록 상기 옹벽의 다리부의 가장자리에 단턱부를 형성시킨 것으로 이루어진다.The present invention for achieving the above object is installed on the edge of the mountain road, such as to prevent the earth and sand flowing down the mountain slope invade the road, the pre-fabricated retaining wall in a separate place to install simply installed in the work site In the prefabricated retaining wall, a leg portion is formed at both ends of the lower end of the wall of the retaining wall and at the lower end of the rear wall which is inclined downward on the rear surface of the retaining wall to form a space at the lower end of the retaining wall, and when placing the retaining wall in a line The stepped portion is formed at the edge of the leg portion of the retaining wall so that a predetermined space is formed therebetween.

즉, 조립식 옹벽의 벽체와 뒷부벽의 하단에 다리부를 형성하여 옹벽의 하단에 공간부를 형성하므로서, 옹벽 하부에 기초 철근부의 설치를 용이하게 할 수 있게 된다. 따라서, 옹벽 설치에 따른 작업성을 향상시킬 수 있게 된다.That is, by forming leg portions at the lower end of the wall of the prefabricated retaining wall and the rear part wall to form a space portion at the lower end of the retaining wall, it is possible to facilitate the installation of the base reinforcing part under the retaining wall. Therefore, the workability by installing the retaining wall can be improved.

또한, 옹벽 벽체의 뒷부벽 상단에는 일정면적이 형성되도록 접촉면을 형성하므로서, 옹벽의 설치 후에 옹벽에 가로등과 같은 기타 설비를 쉽고 용이하게 설치할 수 있게 된다.In addition, by forming a contact surface to form a predetermined area on the top of the rear wall of the retaining wall wall, it is possible to easily and easily install other equipment such as a street lamp on the retaining wall after installation of the retaining wall.

이하, 첨부한 도면에 의거하여 본 발명의 바람직한 실시예를 상세히 설명하면 다음과 같다.Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 2는 본 발명에 따른 조립식 옹벽을 보인 사시도이고, 도 3a는 본 발명에 따른 조립식 옹벽을 설치를 보인 사시도이며, 도 3b는 본 발명에 따른 조립식 옹벽의 설치 후를 보인 사시도이고, 도 4는 본 발명에 따른 조립식 옹벽이 설치된 상태의 설치 상태도이며, 도 5는 본 발명에 따른 일실시예의 옹벽을 도시한 측면도이다.Figure 2 is a perspective view showing a prefabricated retaining wall according to the present invention, Figure 3a is a perspective view showing the installation of a prefabricated retaining wall according to the invention, Figure 3b is a perspective view showing the after installation of a prefabricated retaining wall according to the invention, Figure 4 5 is a side view showing the retaining wall of the embodiment according to the present invention.

본 발명에 따른 조립식 옹벽은 도 2 내지 도 4에 나타낸 바와 같이, 산간 도로 등의 가장 자리에 설치되어 산비탈 등지에서 흘러내리는 토사가 도로를 침범하는 것을 방지하기 위한 조립식 옹벽을 작업현장이 아닌 별도의 장소에서 미리 제작토록 한다.2 to 4, the prefabricated retaining wall according to the present invention is installed on the edge of a mountain road, etc., and the prefabricated retaining wall for preventing the soil from invading the road flowing down the mountain slopes, etc. Make it in advance in place.

이때, 옹벽 벽체(11)의 하단 양측과 벽체(11)의 배면에 설치되는 뒷부벽(13)의 하단에 각각 다리부(12)(14)를 형성하여 옹벽(10)의 하단부에 공간부(15)가 형성되도록 한다.At this time, leg portions 12 and 14 are formed at both lower ends of the retaining wall wall 11 and at the lower end of the rear wall 13 installed on the rear surface of the wall 11, respectively. 15) is formed.

또, 옹벽(10) 벽체(11)의 뒷부벽(13)의 상단에는 낙석방지책 또는 방호벽, 가로등과 같은 도로 제반시설 등을 설치할 수 있도록 일정면적을 갖는 접촉면(17)을 형성시켜 이루어진다.Further, a contact surface 17 having a predetermined area is formed on the upper end of the rear wall 13 of the retaining wall 10 wall 11 so as to install a roadfall facility such as a rockfall prevention barrier or a protective wall or a street lamp.

또한, 상기 옹벽(10) 벽체(11)의 뒷부벽(13)의 상단에 마련되는 접촉면(17)에는 시공범위에 따라 첨부된 도 5에서 도시된 바와 같이, 교량지지대(19)를 옹벽의 벽체(11)상에 안착 지지할 수 있도록 보조 받침부(13-1)를 형성할 수도 있다.In addition, as shown in FIG. 5 attached to the contact surface 17 provided at the upper end of the rear wall 13 of the retaining wall 10, the wall 11, the bridge support 19, the wall of the retaining wall The auxiliary support part 13-1 may be formed so that seating support may be carried out on (11).

상기 보조 받침부(13-1)는 뒷부벽(13)의 접촉면(17)으로부터 거푸집(도면에서 생략함)을 설치한 다음 현장에서 콘크리트물을 타설하여 양생 처리된다. The auxiliary supporting portion 13-1 is installed from the contact surface 17 of the rear wall 13, the formwork (not shown in the figure) and then cast concrete in the field is cured.

도면 중 미설명 부호 20은 철근망을 조립한 기초 철근부를 나타낸다.In the figure, reference numeral 20 denotes a basic reinforcing bar portion assembled with a reinforcing bar network.

이와 같은 구성의 본 발명에 따른 조립식 옹벽의 설치는 먼저, 제작장 또는 공장 등의 별도의 장소에서 바닥 및 강재 거푸집을 이용하여 배수공(도시하지 않음)이 형성된 조립식 옹벽(10)을 제작하여 양생을 완료한다.Installation of the prefabricated retaining wall according to the present invention having such a configuration, first, by using a floor and steel formwork in a separate place, such as a manufacturing site or factory to produce a prefabricated retaining wall (10) formed with a drainage hole (not shown) To complete.

이때, 벽체(11)는 현장 운송, 도로에서의 이동, 작업성 및 안정성을 고려하여 폭은 2.4m내외로 하고, 높이는 최대 8m까지가 되도록 제작한다. 또한, 상기 다리부(12)(14)의 길이는 옹벽의 높이와 배면의 경사도를 고려하여 구한 토압의 크기에 따라 옹벽 저판의 두께를 결정한 후 구할 수 있는데, 통상 기초 두께에서 프리캐스트 옹벽의 벽체가 기초에 묻히는 매입 깊이 8cm를 고려할 때 40∼100cm가 적당하다.At this time, the wall 11 is manufactured in such a way that the width is about 2.4m and the height is up to 8m in consideration of on-site transportation, movement on the road, workability and stability. In addition, the length of the legs 12, 14 can be obtained after determining the thickness of the retaining wall bottom plate according to the magnitude of the earth pressure determined in consideration of the height of the retaining wall and the inclination of the back surface, which is usually the thickness of the precast retaining wall at the foundation thickness. Considering the depth of embedding 8cm buried in the foundation, 40-100cm is suitable.

상기 공간부(15)의 폭 역시 옹벽이 설치되는 지형의 설계조건을 고려하여 계산된 뒤 부벽의 경사도 및 강재 거푸집의 활용성을 함께 고려하여 결정한 후 구할 수 있는데, 통상 옹벽 벽체의 높이가 5m 이하인 경우, 공간부(15)의 폭은 419mm에서 800mm가 되며, 5m에서 8m의 벽체 높이에서는 최소 800mm에서 1400mm 까지 변할 수 있다.The width of the space 15 may also be calculated after considering the design conditions of the terrain on which the retaining wall is installed, and then considering the slope of the subwall and the utility of the steel formwork, and the height of the retaining wall is usually 5 m or less. In this case, the width of the space portion 15 is 419mm to 800mm, it can vary from at least 800mm to 1400mm at the wall height of 5m to 8m.

또한, 도 2를 참조하면, 상기 옹벽(10)의 다리부(12)의 가장자리에는 50mm폭의 단턱부(12a)를 형성하여 일렬상으로 옹벽(10)이 위치할때에 있어 공간을 갖도록 하며, 이 단턱부(12a) 형성에 따른 공간은 철근부(20)를 통한 옹벽을 바닥면으로부터 고정하도록 하는데 있어, 상기 공간부(15)를 포함하는 단턱부(12a)에는 양생 콘크리트의 유입으로 옹벽의 구조체를 견고하게 위치시킬 수 있게 된다.In addition, referring to FIG. 2, a stepped portion 12a having a width of 50 mm is formed at the edge of the leg portion 12 of the retaining wall 10 to have a space when the retaining wall 10 is positioned in a line. In order to fix the retaining wall through the reinforcing part 20 from the bottom surface, the space according to the formation of the stepped part 12a is provided in the stepped part 12a including the space part 15 by the inflow of the curing concrete. It is possible to firmly position the structure of.

한편, 조립식 옹벽(10)이 설치될 현장에서는 기초 터파기 후 조립식 옹벽(10)이 설치되는 바닥에 철근망을 조립하여 기초공사를 행하도록 한다.On the other hand, in the site where the prefabricated retaining wall 10 is to be installed, after the foundation trench, the reinforcing steel bar is assembled on the floor on which the prefabricated retaining wall 10 is installed to perform the foundation work.

이어, 별도의 장소에서 미리 제작되어 양생이 완료된 옹벽(10)을 기초공사가 완료된 작업현장으로 이동시킨 다음 현장에서 인양장비를 이용하여 철근망이 조립된 기초 철근부(20)의 상부에서 조립하여 설치한 다음, 기초 철근부(20)의 상부에 기초부 콘크리트를 타설 시공하여 옹벽(10)과 기초 철근부(20)를 일체화시키도록 한다. 이 경우, 옹벽(10)의 뒤부벽(13)과 연결되는 가로 방향의 철근(도시하지 않음)을 설치하여 좀 더 견고히 결합시킬 수 있다.Subsequently, the retaining wall 10, which has been preliminarily manufactured and cured in a separate place, is moved to the work site where the foundation work is completed, and then assembled on the upper part of the reinforcing bar 20 where the reinforcing bar network is assembled by using lifting equipment at the site. After installation, the foundation concrete is poured on top of the foundation reinforcing portion 20 to integrate the retaining wall 10 and the foundation reinforcing portion 20. In this case, by installing a horizontal reinforcing bar (not shown) connected to the rear wall 13 of the retaining wall 10 can be more firmly coupled.

도 3a 및 3b를 참조하면, 본 발명에 따라 철근망으로 된 기초 철근부(20)의 상부에 옹벽(10)을 설치하게 되면, 옹벽(10)의 벽체(11) 하단부에 형성된 다리부(12)와 뒷부벽(13)의 하단부에 형성된 다리부(14)사이의 공간부(15)로 기초 철근부(20)를 위치할 수 있게 되어 철근조립작업의 작업능률은 물론, 옹벽(10)설치의 작업성을 향상시킬 수 있게 됨은 물론, 옹벽(10)의 기초 구성이 튼튼하게 할 수 있게 된다.3A and 3B, when the retaining wall 10 is installed on the upper part of the basic reinforcing bar 20 made of reinforcing steel bars according to the present invention, the leg 12 formed at the lower end of the wall 11 of the retaining wall 10 is provided. It is possible to position the base reinforcing bar 20 by the space portion 15 between the leg portion 14 formed in the lower end of the rear wall 13), as well as the work efficiency of the reinforcing bar assembly work, the retaining wall 10 installation Not only can the workability be improved, but the foundation structure of the retaining wall 10 can be strengthened.

상기 작업으로 옹벽(10)을 기초공사가 완료된 기초 철근부(20) 상부에 설치할 때, 설치되는 각 옹벽(10)사이의 이음부에는 옹벽(10)의 벽체(11)가 계절에 따라 팽창 및 수축됨을 감안하여 약간의 공극을 형성시킨 다음, 이음부에 접합제 등을 도포하여 접합시킬 수 있다. 또한, 각 옹벽(10)사이를 연결하는 연결부위에는 경첩(도시하지 않음)을 설치하여 각 옹벽(10)을 연결토록 함으로서, 옹벽(10)의 전, 후면에서 작용하는 힘에 적절히 신축적으로 대응할 수 있도록 한다.When the retaining wall 10 is installed in the upper part of the foundation reinforcing bar 20 where the foundation work is completed by the above work, the wall 11 of the retaining wall 10 expands and expands according to the season at the joint between each retaining wall 10 to be installed. In view of shrinkage, some voids can be formed, and then a joint or the like can be applied to the joint. In addition, by installing a hinge (not shown) at the connecting portion connecting each retaining wall 10 to connect each retaining wall 10, it is appropriately stretched to the force acting on the front and rear of the retaining wall 10. Be prepared to respond.

이어, 옹벽(10)의 배면 즉, 옹벽(10)과 절개지의 사이를 뒷채움하여 공사를 마무리한다.Subsequently, the back surface of the retaining wall 10, that is, between the retaining wall 10 and the cutout, is back filled to complete the construction.

한편, 옹벽(10) 벽체(11)의 뒷부벽(13)의 상단에는 일정면적의 접촉면(17)을 형성함으로서, 옹벽(10)의 설치후 낙석방지책 또는 방호벽, 가로등과 같은 도로 제반시설 등을 설치하고자 할 때, 그 접촉면(17)에 상기 제반시설 등을 설치 후 옹벽(10)의 배면을 뒷채움 함으로서, 상기 도로 제반시설 등을 간편하고 용이하게 설치할 수 있게 된다. 본 발명에 있어서, 상기 접촉면(17)의 최상단에서의 두께는 최소 200mm이고, 폭은 옹벽이 설치되는 지형을 고려하여 계산된 뒤부벽(13)의 면적 및 시공성을 고려할 때 최소폭 250mm가 적당하며, 따라서 최상단에서의 단면적은 500㎠ 이상이 되어 상기 제반시설의 설치가 가능하므로, 해당하는 구간의 뒷부벽의 상측으로는 가로등(도 4 참조), 낙석방지책 지주, 교량지지대(도 5 참조)의 설치가 용이한 잇점이 있다.On the other hand, by forming a contact surface 17 of a predetermined area on the upper end of the rear wall 13 of the retaining wall (10) wall 11, after installation of the retaining wall (10) to prevent falling rocks or road facilities such as protection walls, street lights, etc. When the installation, the back surface of the retaining wall 10 after the installation of the various facilities and the like on the contact surface 17, it is possible to easily and easily install the road infrastructure. In the present invention, the thickness at the top of the contact surface 17 is at least 200 mm, the width is at least 250 mm is appropriate considering the area and workability of the back wall 13 calculated in consideration of the terrain on which the retaining wall is installed. Therefore, the cross-sectional area at the uppermost end is 500 cm 2 or more so that the above facilities can be installed. Therefore, the upper side of the rear wall of the corresponding section includes a street lamp (see FIG. 4), a rockfall prevention pillar, and a bridge support (see FIG. 5). It is easy to install.

이상에서와 같이, 본 발명은 조립식 옹벽의 벽체와 뒷부벽의 하단에 다리부를 형성하여 옹벽의 하단부에 공간부를 형성하여 옹벽 하부에 철근부의 설치가 용이하도록 하므로서, 옹벽 설치에 따른 작업성을 향상시킬 수 있게 된다. As described above, the present invention forms a leg portion at the lower end of the wall and the rear wall of the prefabricated retaining wall to form a space portion at the lower end of the retaining wall to facilitate the installation of the reinforcing portion in the lower retaining wall, thereby improving the workability according to the retaining wall installation It becomes possible.

또한, 옹벽 벽체의 뒷부벽 상단에는 일정면적이 형성되도록 접촉면을 형성하므로서, 옹벽의 설치 후에 옹벽에 가로등, 방호벽, 낙석방지책과 같은 기타 도로 제반시설의 설치를 쉽고 용이하게 할 수 있게 된다.In addition, by forming a contact surface to form a predetermined area at the top of the rear wall of the retaining wall wall, it is possible to easily and easily install other road facilities such as street lights, protective walls, rockfall prevention measures on the retaining wall after installation of the retaining wall.

도 1은 종래 조립식 옹벽을 보인 사시도,1 is a perspective view showing a conventional prefabricated retaining wall,

도 2는 본 발명에 따른 조립식 옹벽을 보인 사시도,2 is a perspective view showing a prefabricated retaining wall according to the present invention,

도 3a는 본 발명에 따른 조립식 옹벽을 설치를 보인 사시도, Figure 3a is a perspective view showing the installation of the prefabricated retaining wall according to the invention,

도 3b는 본 발명에 따른 조립식 옹벽의 설치 후 상태를 보인 사시도,Figure 3b is a perspective view showing a state after installation of the prefabricated retaining wall according to the invention,

도 4는 본 발명에 따른 조립식 옹벽이 설치된 상태의 설치상태도,Figure 4 is an installation state of the prefabricated retaining wall installed state according to the invention,

도 5는 본 발명에 따른 일실시예의 옹벽을 도시한 측면도.Figure 5 is a side view showing a retaining wall of one embodiment according to the present invention.

*도면의 주요부분에 대한 부호의 설명** Description of the symbols for the main parts of the drawings *

10 ; 옹벽 11 ; 벽체10; Retaining wall 11; Wall

12 ; 다리부 13 ; 뒷부벽12; Leg 13; Back wall

14 ; 다리부 15 ; 공간부14; Leg 15; Space

17 ; 접촉면17; Contact surface

Claims (4)

산간 도로 등의 가장 자리에 설치되어 산비탈 등지에서 흘러내리는 토사가 도로를 침범하는 것을 방지하기 위하여 별도의 장소에서 미리 제작된 옹벽을 작업현장에서 단순 조립하여 설치하는 조립식 옹벽에 있어서, In the prefabricated retaining wall, which is installed at the edge of a mountain road and flows from the hill slope to prevent the soil from invading the road, the retaining wall prefabricated in a separate place is simply assembled and installed at the work site. 옹벽(10)의 벽체(11) 하단 양측과, 벽체(11)의 배면에 하향 경사지게 설치되는 뒷부벽(13)의 하단에 다리부(12)(14)를 형성하여 옹벽(10)의 하단부에 공간부(15)가 형성되고, 뒷부벽(13)의 상단에는 일정면적을 갖는 접촉면(17)을 형성하며, 일렬상으로 상기 옹벽(10)을 위치시킬 때 다리부(12) 사이에 소정의 공간이 형성되도록 상기 옹벽(10)의 다리부(12)의 가장자리에 단턱부(12a)를 형성시킨 것을 특징으로 하는 조립식 옹벽.Legs 12 and 14 are formed at both lower ends of the wall 11 of the retaining wall 10 and at the lower end of the rear wall 13 which is inclined downward on the rear surface of the wall 11 to form a lower portion of the retaining wall 10. A space 15 is formed, and a contact surface 17 having a predetermined area is formed at an upper end of the rear wall 13, and when the retaining wall 10 is positioned in a line, a predetermined space is provided between the legs 12. Prefabricated retaining wall, characterized in that the stepped portion (12a) is formed on the edge of the leg portion 12 of the retaining wall (10) to form a space. 삭제delete 제1항에 있어서, 상기 벽체(11)의 폭은 2.4m내외로 하고, 높이는 최대 8m까지이며, 다리부(12)(14)의 길이는 40∼100cm이고, 공간부(15)의 폭은 419∼1400mm 인 것을 특징으로 하는 조립식 옹벽.The width of the wall 11 is about 2.4 m, the height is up to 8 m, the length of the legs 12, 14 is 40-100 cm, and the width of the space 15 is A prefabricated retaining wall, which is 419 to 1400 mm. 제1항에 있어서, 상기 옹벽(10)사이의 이음부는 약간의 공극을 형성시킨 다음, 접합제를 도포하여 접합시키고, 옹벽(10)과 옹벽(10)을 연결하는 연결부위는 경첩을 설치하여 연결시킨 것을 특징으로 하는 조립식 옹벽.According to claim 1, wherein the joints between the retaining wall (10) to form a slight gap, and then by applying a bonding agent, the connecting portion for connecting the retaining wall (10) and the retaining wall (10) by installing a hinge Prefabricated retaining wall, characterized in that connected.
KR10-2002-0047334A 2002-08-10 2002-08-10 Precast concrete counterforts retaining wall KR100488130B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR10-2002-0047334A KR100488130B1 (en) 2002-08-10 2002-08-10 Precast concrete counterforts retaining wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR10-2002-0047334A KR100488130B1 (en) 2002-08-10 2002-08-10 Precast concrete counterforts retaining wall

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR2020020023966U Division KR200297480Y1 (en) 2002-08-10 2002-08-10 Precast concrete counterforts retaining wall

Publications (2)

Publication Number Publication Date
KR20040014707A KR20040014707A (en) 2004-02-18
KR100488130B1 true KR100488130B1 (en) 2005-05-16

Family

ID=37321464

Family Applications (1)

Application Number Title Priority Date Filing Date
KR10-2002-0047334A KR100488130B1 (en) 2002-08-10 2002-08-10 Precast concrete counterforts retaining wall

Country Status (1)

Country Link
KR (1) KR100488130B1 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102066809B1 (en) * 2019-05-15 2020-01-15 최귀자 Retaining wall construction method for not required wall finishing and mold
CN111236302A (en) * 2020-03-09 2020-06-05 上海市城市建设设计研究总院(集团)有限公司 Prefabricated counterfort type retaining wall assembling structure and construction method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6036438U (en) * 1983-08-19 1985-03-13 千葉窯業株式会社 Concrete block for earth retention
JPS62288221A (en) * 1986-06-06 1987-12-15 Koji Kato Retaining wall
JPH0386142U (en) * 1989-12-22 1991-08-30
US5144779A (en) * 1988-05-13 1992-09-08 Societe Civile Des Brevets De Henri Vidal Joining of a concrete element to a support
JPH07207685A (en) * 1994-01-22 1995-08-08 Takaaki Endo Building method for large precast retaining wall
JP2001003376A (en) * 1999-06-18 2001-01-09 Sanyu Create:Kk L-shaped retaining wall block and its execution method
KR200297480Y1 (en) * 2002-08-10 2002-12-12 진성토건 주식회사 Precast concrete counterforts retaining wall

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6036438U (en) * 1983-08-19 1985-03-13 千葉窯業株式会社 Concrete block for earth retention
JPS62288221A (en) * 1986-06-06 1987-12-15 Koji Kato Retaining wall
US5144779A (en) * 1988-05-13 1992-09-08 Societe Civile Des Brevets De Henri Vidal Joining of a concrete element to a support
JPH0386142U (en) * 1989-12-22 1991-08-30
JPH07207685A (en) * 1994-01-22 1995-08-08 Takaaki Endo Building method for large precast retaining wall
JP2001003376A (en) * 1999-06-18 2001-01-09 Sanyu Create:Kk L-shaped retaining wall block and its execution method
KR200297480Y1 (en) * 2002-08-10 2002-12-12 진성토건 주식회사 Precast concrete counterforts retaining wall

Also Published As

Publication number Publication date
KR20040014707A (en) 2004-02-18

Similar Documents

Publication Publication Date Title
KR101726725B1 (en) Construction method for a sidewalk enlargement installation
US7614830B1 (en) Pre-cast retaining wall system and method
US20100272509A1 (en) Traffic barrier section
KR101701220B1 (en) Road expansion structure and construction method thereof
KR100488130B1 (en) Precast concrete counterforts retaining wall
JP4083334B2 (en) Underground structure having arch roof and method for constructing the same
KR102475707B1 (en) Modular sidewalk block road
KR200297480Y1 (en) Precast concrete counterforts retaining wall
JP6340044B2 (en) Overhang trail construction body and construction method of overhang trail using these
JP6095840B1 (en) Drainage basin, U-shaped side gutter and construction method
KR100981323B1 (en) Pre-cast block and structure using the same
KR200266040Y1 (en) Precast Concrete Base Structure for Soundproof Wall
KR20050100131A (en) Constructing method for securing a sidewalk and enlarging a driveway using concrete retaining wall block and truss type support in a narrow road without a sidewalk
JP4834649B2 (en) Construction structure of embankment structure, retaining wall block for construction of embankment structure and construction method of embankment structure
KR100828181B1 (en) Construction mathod of load using side wall block
JP4282507B2 (en) Lightweight embankment structure and widening method for lighter embankment structure using the same
JPH0718723A (en) Adjustable-slope road side ditch
JP2005194722A (en) Method of laying overhang sidewalk
KR100274747B1 (en) Method for installation of electric pole and supporting device of the same
CN111779487B (en) Construction method of end well of automatic footpath
JP4198560B2 (en) Foundation block for protective fence and construction method of protective fence
KR200354133Y1 (en) Precast concrete block for retaining wall
JP3629684B2 (en) Sound insulation wall foundation block
JP2000297403A (en) Passage and construction method therefor
JPH0734471A (en) Suspended wall type retaining wall construction method in lightweight filling construction method

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20130418

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20140428

Year of fee payment: 10

LAPS Lapse due to unpaid annual fee