KR100451960B1 - The method for set-up the guardrail and a set-up device for guardrail - Google Patents

The method for set-up the guardrail and a set-up device for guardrail Download PDF

Info

Publication number
KR100451960B1
KR100451960B1 KR1020040027389A KR20040027389A KR100451960B1 KR 100451960 B1 KR100451960 B1 KR 100451960B1 KR 1020040027389 A KR1020040027389 A KR 1020040027389A KR 20040027389 A KR20040027389 A KR 20040027389A KR 100451960 B1 KR100451960 B1 KR 100451960B1
Authority
KR
South Korea
Prior art keywords
support
support means
formwork
installation
foundation structure
Prior art date
Application number
KR1020040027389A
Other languages
Korean (ko)
Inventor
이상우
Original Assignee
주식회사 누리플랜
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 누리플랜 filed Critical 주식회사 누리플랜
Priority to KR1020040027389A priority Critical patent/KR100451960B1/en
Application granted granted Critical
Publication of KR100451960B1 publication Critical patent/KR100451960B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01FADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
    • E01F15/00Safety arrangements for slowing, redirecting or stopping errant vehicles, e.g. guard posts or bollards; Arrangements for reducing damage to roadside structures due to vehicular impact
    • E01F15/02Continuous barriers extending along roads or between traffic lanes
    • E01F15/04Continuous barriers extending along roads or between traffic lanes essentially made of longitudinal beams or rigid strips supported above ground at spaced points
    • E01F15/0476Foundations
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01FADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
    • E01F15/00Safety arrangements for slowing, redirecting or stopping errant vehicles, e.g. guard posts or bollards; Arrangements for reducing damage to roadside structures due to vehicular impact
    • E01F15/02Continuous barriers extending along roads or between traffic lanes
    • E01F15/04Continuous barriers extending along roads or between traffic lanes essentially made of longitudinal beams or rigid strips supported above ground at spaced points
    • E01F15/0484Installing; Repairing; Adjusting

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

PURPOSE: An installation method of a handrail and a device thereof are provided to fix the position of the supporting unit firmly, and to mount the handrail accurately by temporarily assembling the support member at both sides of the supporting unit and placing the supporting unit and the supporting member in the form. CONSTITUTION: A supporting unit(30) is embedded in a foundation structure(20), and the laying position of the supporting unit is indicated in the surface of the supporting unit. A supporting member is temporarily combined with both sides of the supporting unit by a bolt and a nut. The supporting unit is placed at the position in which a support(50) is arranged after temporarily assembling the supporting member with the supporting unit. The position of the supporting unit is fastened, and concrete is poured and cured. The supporting member is disassembled from the supporting unit after removing a form. The support is inserted to the supporting unit after disassembling the supporting member, and combined with the supporting unit.

Description

난간의 설치방법 및 설치장치{The method for set-up the guardrail and a set-up device for guardrail}Railing installation method and installation device {The method for set-up the guardrail and a set-up device for guardrail}

본 발명은 도로변 혹은 인도변등에 설치되는 난간에 관한 것으로, 특히 콘크리트를 타설하기전에 지주를 지지하는 지지수단을 용이하고도 견고하게 설치하여서 신속하고도 보다 용이하게 난간을 설치할 수 있고 외관을 보다 미려하게 설치할 수 있는 난간의 설치방법 및 설치장치에 관한 것이다.The present invention relates to railings installed on roadsides or sidewalks, and in particular, it is possible to install railings quickly and more easily by easily and firmly installing support means for supporting pillars before placing concrete. It relates to a railing installation method and an installation apparatus that can be installed easily.

일반적으로, 도로변 혹은 인도변등에 설치되는 난간은 공개특허 2004-0011572호의 교량의 성능개선 및 보수 보강공법의 명세서의 도 5 및 도 10에 도시된 바와 같이 설치되게 된다.In general, handrails installed on roadsides or sidewalks will be installed as shown in FIGS. 5 and 10 of the specification of the performance improvement and repair reinforcement method of the bridge of Publication No. 2004-0011572.

즉, 종래의 난간은 본 발명 명세서의 도 1 및 도 2에 도시된 바와 같이 설치되게 된다.That is, the conventional railing is to be installed as shown in Figures 1 and 2 of the present specification.

이를 좀더 상세하게 설명하면, 종래의 난간을 설치하고자 할 경우 우선 거푸집을 설치하는 거푸집 설치스텝과, 상기 거푸집 설치스텝에서 설치된 거푸집의 내측에 수절목을 설치하는 수절목설치스텝과, 상기 수절목설치스텝에서 수절목을 설치한 후 앙카박스를 설치하는 앙카박스설치스텝과, 상기 앙카박스설치스텝에서 앙카(311)를 설치한 후 콘크리트를 타설하는 콘크리크타설스텝과, 상기 콘크리트타설스텝에서 콘크리트를 타설한 후 콘크리트를 양생시키는 콘크리트양생스텝과, 상기 콘크리트양생스텝에서 콘크리트를 양생시킨 후 거푸집 및 수절목을 제거시키는 부속품제거스텝과, 상기 부속품제거스텝에서 거푸집 및 수절목을 제거시킨 후 콘크리트의 상면으로부터 돌출된 앙카박스의 앙카(311)에 베이스플레이트(350)가 형성된 지주(310)를 설치하는 지주설치스텝과, 상기 지주설치스텝에서 설치된 지주(310)와 지주(310)사이에 난간대(320)을 설치한 난간대설치스텝으로 이루어져 난간을 설치하게 된다.In more detail, if you want to install the conventional railing, the formwork installation step for installing the formwork first, the tree-planting installation step for installing the treewood inside the formwork installed in the formwork installation step, and the tree-plant installation An anchor box installation step for installing an anchor box after installing a cut tree at the step, a concrete placing step for placing concrete after installing an anchor 311 at the anchor box installation step, and concrete at the concrete pouring step Concrete curing step for curing concrete after pouring, Accessory removal step for removing formwork and trees after curing concrete in the concrete curing step, and Top surface of concrete after removing formwork and tree cutting in the accessory removal step The support plate 310 is formed on the anchor plate 311 of the anchor box protruding from the base plate 350 is installed. Is made up of railing installation step installing the railing (320) is installed between the installation in the holding step, the holding step holding installation (310) and holding (310) is to install a railing.

이와 같은 종래의 난간의 설치방법에 의하면, 상기 앙카박스설치스텝에서 앙카박스를 설치할 경우 앙카박스의 수평 및 수직도를 정밀하게 조정하여서 앙카박스를 설치하여야 하므로서 설치시간이 과다하게 소요된다.According to the conventional installation method of the railing, when the anchor box is installed in the anchor box installation step, the installation time is excessively required because the anchor box must be installed by precisely adjusting the horizontal and vertical degrees of the anchor box.

또, 상기 지주설치스텝에서 상기 지주(310)를 설치할 경우 상기 앙카박스의 앙카볼트(311)와 상기 지주(310)의 베이스플레이트(320)의 구멍을 일치시킨 후 상기 앙카볼트에 너트를 조이게 되며, 이때 상기 지주(310)의 수평 및 수직도를 유지시키기 위해서 베이스플레이트(320)의 하부에 철심들을 고여야 하므로서 상기 지주설치스텝에서 과다한 설치시간이 소요되게 된다.In addition, when the support 310 is installed in the support installation step, the anchor bolt 311 of the anchor box and the hole of the base plate 320 of the support 310 are matched, and then the nut is tightened to the anchor bolt. At this time, since the cores are to be held in the lower portion of the base plate 320 to maintain the horizontal and vertical degrees of the support 310, excessive installation time is required in the support installation step.

또한, 상기 지주설치스텝에서 설치되는 상기 지주(310)에는 베이스플레이트(350)가 리브(351)를 매개로 용접된 후 상기 앙카(311)와 조립되므로서 상기 베이스플레이트(350)와 리브(351)가 기초구조물의 표면으로 노출되므로서 그 외관이 미려하지 못하다는 문제점이 있었다.In addition, the base plate 350 is welded through the rib 351 to the support 310 installed in the support installation step, and then assembled with the anchor 311, so that the base plate 350 and the rib 351 are assembled. ) Is exposed to the surface of the foundation structure has a problem that the appearance is not beautiful.

즉, 종래의 난간의 설치방법에 의하면, 지주의 하부에는 베이스플레이트가 리브를 매개로 조립되어서 앙카에 의해 설치되므로서 설치가 난이한 것은 물론이고 설치시간이 과다하게 소요되며 그 외관이 미려하지 못하다는 등의 여러 가지 문제점들이 있었다.That is, according to the conventional installation method of the railing, since the base plate is assembled by the rib under the support of the base, it is not only difficult to install, but also requires excessive installation time and its appearance is not beautiful. There were a number of problems.

본 발명은 상술한 여러 가지 문제점을 감안해서 이루어진 것으로, 본 발명의 목적은 지주의 하부에 베이스플레이트가 소요됨이 없고 지주를 지지하는 지지수단을 보다 신속하고도 견고하게 정위치시킬 수 있도록 하여 난간의 설치시간을 최소화시키며 종래와 같이 베이스플레이트등의 부재가 외부로 노출됨이 없어 외관을 보다 미려하게 할 수 있는 난간의 설치방법 및 설치장치를 제공하는 데 있다.The present invention has been made in view of the above-mentioned various problems, and an object of the present invention is that the base plate is not required in the lower part of the support, and the support means for supporting the support can be more quickly and firmly positioned so that the railing Minimizing the installation time, and there is no member such as the base plate is exposed to the outside to provide an installation method and installation device that can make the appearance more beautiful.

도 1은 종래예에 적용되는 난간이 설치된 상태를 도시한 단면도.1 is a cross-sectional view showing a state in which a railing applied to a conventional example is installed.

도 2는 종래예에 적용되는 난간이 설치된 상태를 도시한 사시도.2 is a perspective view showing a state in which a railing applied to a conventional example is installed.

도 3은 본 발명에 적용되는 난간이 설치된 상태를 도시한 상태도.Figure 3 is a state diagram showing a state in which the railings applied to the present invention installed.

도 4는 본 발명에 적용되는 난간의 주요부품을 분해하여서 도시한 분해사시도.Figure 4 is an exploded perspective view showing an exploded main parts of the railings applied to the present invention.

도 5는 본 발명에 적용되는 난간의 설치공정을 개략적으로 도시한 공정도.Figure 5 is a process diagram schematically showing the installation process of the balustrade applied to the present invention.

도 6은 본 발명에 적용되는 난간이 가드레일에 적용된 상태를 도시한 상태도.Figure 6 is a state diagram showing a state that the railing applied to the present invention is applied to the guardrail.

*도면의 주요부분에 대한 부호의 설명** Description of the symbols for the main parts of the drawings *

10...거푸집 11...수절목10 ... die 11 ... trees

20...기초구조물 30...지지수단20 ... foundation 30 ... supporting means

31...체결구멍 32...관통공31 ... tightening hole 32 ... through hole

40...서포트부재 41...접촉부40.Support member 41 ... Contact

42...지지부 50...지주42 Support 50 Support

51...난간대51.Handrail

이와 같은 목적을 달성하기 위하여 본 발명에 의한 난간의 설치방법은, 좌우의 상부폭이 L인 기초구조물을 형성시킬 수 있도록 거푸집을 설치하는 거푸집설치스텝과; 상기 거푸집설치스텝에서 설치된 상기 거푸집의 내면에 상기 기초구조물의 높이가 H로 형성되도록 함과 동시에 상기 기초구조물의 상부모서리가 면취되도록 수절목을 상기 거푸집의 내면에 설치하는 수절목설치스텝과; 상기 수절목설치스텝에서 상기 수절목을 설치한 후 콘크리트를 타설하여 상기 기초구조물을 성형시키는 기초구조물성형스텝과; 상기 기초구조물성형스텝에서 성형된 상기 기초구조물에 지주를 설치하는 지주설치스텝과; 상기 지주설치스텝에서 설치된 지주와 지주의 사이에 난간대를 설치하는 난간대설치스텝으로 이루어져 난간을 설치하는 난간의 설치방법에 있어서; 상기 기초구조물에 매설되는 지지수단의 표면에 상기 지지수단이 매설되는 위치를 마킹하는 지지수단마킹스텝과; 상기 지지수단마킹스텝에서 매설되는 위치가 마킹된 상기 지지수단의 양측에 서포트부재를 볼트 및 너트로서 가조립시키는 가조립스텝과; 상기 가조립스텝에서 상기 지지수단의 양측면에 상기 서포트부재를 가조립시킨 후에는 상기 지주가 놓여질 위치에 상기 지지수단을 위치시키는 지지수단고정스텝과; 상기 지지수단고정스텝에서 상기 지지수단을 위치고정시킨 후 콘크리트를 타설 및 양생시키고 상기 거푸집 및 상기 수절목을 제거시킨 후 상기 지지수단에 가조립된 상기 서포트부재를 상기 지지수단으로부터 분해시키는 서포트부재분해스텝과; 상기 서포트부재분해스텝에서 상기 서포트부재를 분해시킨 후 상기 지지수단에 상기 지주를 삽입하여 상기 지주를 상기 지지수단에 조립하는 지주조립스텝으로 이루어진 것을 특징으로 한다.In order to achieve the above object, the installation method of the handrail according to the present invention includes: a formwork installation step for installing formwork so as to form a foundation structure having an upper and left upper width L; A tree-planting installation step of installing the cut tree on the inner surface of the formwork so that the height of the foundation structure is formed at the inner surface of the formwork installed in the formwork setting step as H, and the upper edge of the foundation structure is chamfered; A basic structure forming step of forming the basic structure by placing concrete after installing the tree in the tree arranging step; A support installation step of installing a support on the foundation structure formed in the foundation structure forming step; A handrail installation method comprising: a handrail installation step of installing a handrail between a supporter and a supporter installed in the support installation step; A supporting means marking step for marking a position at which the supporting means is embedded on a surface of the supporting means embedded in the foundation structure; A provisional assembly step of temporarily assembling the support members as bolts and nuts on both sides of the support means marked at the positions of embedding in the support means marking step; A support means fixing step of positioning the support means at a position where the support is to be placed after temporarily mounting the support members on both sides of the support means in the temporary assembly step; The support member disassembling step of disassembling the support member assembled to the support means after the support means is fixed and the concrete is placed and cured, the mold and the tree are removed, and the support means is disassembled from the support means. and; The support member disassembling step in the support member is characterized in that it consists of a support assembly step for assembling the support post to the support means by inserting the support post to the support means.

또, 상기와 같은 목적을 달성하기 위하여 본 발명에 의한 난간의 설치장치는, 거푸집 및 수절목에 의해 상하의 높이가 H이고 좌우의 상부폭이 L로 형성된 기초구조물과, 상기 기초구조물의 상부에 일정간격으로 설치되는 다수의 지주와, 상기 지주와 상기 지주사이에 연결된 난간대로 이루어진 난간의 설치장치에 있어서; 상기 지주가 삽입되도록 내부가 통공으로 이루어지고, 좌우의 폭이 W1으로 이루어져 상기 기초구조물에 매설되며, 좌우측면에는 장공형상의 체결구멍이 형성된 지지수단과; 상기 지지수단이 상기 거푸집 및 상기 수절목을 설치한 후 콘크리트를 타설하기전에 상기 지지수단이 정위치에서 유동됨이 없도록 상기 지지수단의 양측면에 가조립되어서 상기 지지수단을 가지지()하며, 상기 지지수단의 측면과 면접촉되어서 상기 지지수단에 볼트 및 너트에 의해 가조립되도록 관통공이 형성된 접촉부와, 상기 접촉부와 직각으로 일체적으로 조립되어서 상기 지지수단이 정위치에 유동됨이 없도록 상기 수절목에 지지되며 단부가 상기 거푸집의 내면과 면접촉되는 지지부로 이루어진 서포트부재로 이루어진 것을 특징으로 한다.In addition, in order to achieve the above object, the installation device of the handrail according to the present invention, the base structure formed by the formwork and the cut tree, the height of the upper and lower sides and the upper width of the left and right, L, and a constant on the upper portion of the foundation structure In the guardrail installation device consisting of a plurality of struts installed at intervals, and a handrail between the strut and the strut; Support means formed inside the through hole to insert the support, the width of the left and right is made of W1 and embedded in the basic structure, and the support means having a fastening hole shape formed on the left and right sides thereof; After the supporting means installs the formwork and the cut tree, the supporting means is temporarily assembled to both sides of the supporting means so that the supporting means does not flow in the right place, and thus has the supporting means ( And a contact portion having a through hole formed to be in surface contact with the side surface of the support means to be preassembled by bolts and nuts, and integrally assembled at right angles to the contact portion so that the support means does not flow in position. It is characterized in that the support member is made of a support part which is supported by the tree and the end is in surface contact with the inner surface of the formwork.

이와 같은 본 발명에 의한 난간의 설치방법 및 설치장치에 의하면, 거푸집 및 수절목을 설치하고 지지수단의 양측면에 서포트부재를 가조립시킨 후 지지수단과 서포트부재를 거푸집의 내부에 위치시키면 지지수단이 정위치에 견고하게 위치고정되므로서 보다 신속하게 난간의 지주를 지지하는 지지수단을 설치할 수 있는 것은 물론이고, 보다 미려하게 난간을 설치할 수 있다.According to the installation method and the installation device of the balustrade according to the present invention, the support means is fixed by installing the formwork and the cut tree, temporarily assembling the support members on both sides of the support means, and then placing the support means and the support member inside the formwork. Since the position is firmly fixed to the position, the supporting means for supporting the prop of the railing can be installed more quickly, and the railing can be installed more beautifully.

이하, 본 발명에 적용되는 난간의 설치방법 및 설치장치의 일실시예를 첨부된 도면을 참조하여서 상세하게 설명한다.Hereinafter, with reference to the accompanying drawings an embodiment of a railing installation method and installation apparatus applied to the present invention will be described in detail.

도 3은 본 발명에 적용되는 난간이 설치된 상태를 도시한 상태도이고, 도 4는 본 발명에 적용되는 난간의 주요부품을 분해하여서 도시한 분해사시도이며, 도 5는 본 발명에 적용되는 난간의 설치공정을 개략적으로 도시한 공정도이다.Figure 3 is a state diagram showing a state in which the balustrade applied to the present invention is installed, Figure 4 is an exploded perspective view showing the main parts of the balustrade applied to the present invention, Figure 5 is an installation of the balustrade applied to the present invention A process diagram schematically showing the process.

도 3 내지 도 5에 있어서, 부호 10은 후술하는 좌우의 상부폭이 L인 기초구조물이 형성될 수 있도록 틀을 형성시키는 거푸집이고, 부호 11은 후술하는 상하의 높이가 H인 기초구조물의 모서리부의 균열을 방지하고 외관이 미려하도록 모서리부를 면취시키며 상기 거푸집(10)의 내면에 설치되는 수절목이다.In Figures 3 to 5, reference numeral 10 is a formwork for forming a frame so that the base structure of the left and right upper width to be described later L can be formed, and the reference numeral 11 is a crack of the corner of the base structure of the H and H will be described later To prevent and chamfer the corner portion so that the appearance is beautiful, it is a cut-off wood installed on the inner surface of the formwork (10).

또, 부호 20은 상기 거푸집(10) 및 상기 수절목(11)에 의해서 좌우의 상부폭이 L이고 상하의 높이가 H로 콘크리트에 의해 형성된 기초구조물이다.Reference numeral 20 is a basic structure formed of concrete with the upper and lower widths of the left and right and the upper and lower heights of H by the formwork 10 and the cut tree 11.

또한, 부호 30은 좌우의 폭이 W1으로 이루어지고 후술하는 지주가 삽입되도록 내부가 통공으로 이루어져 상기 기초구조물(20)에 매설되는 지지수단으로서, 좌우측면에는 후술하는 지주가 볼트 및 너트에 의해 견고하게 조립되도록 장공형상의 체결구멍(31)이 형성되어 있다.In addition, reference numeral 30 is a support means that the left and right width is made of W1 and the inside is made of a through hole so that the posts to be described later are inserted, embedded in the foundation structure 20, the posts described later are firmly secured by bolts and nuts. The fastening hole 31 of the long hole shape is formed so that it may be assembled.

또, 상기 지지수단(30)의 하부에는 상기 지지수단(30)의 일부가 콘크리트에 매설된 후 상기 지지수단(30)이 유동됨이 없이 보다 견고하게 상기 지초구조물(20)에 설치되도록 철근등과 같은 보강부재(33)가 삽입되는 관통공(32)이 천공되어 있다.In addition, the lower portion of the support means 30, a part of the support means 30 is embedded in the concrete so that the support means 30 is installed on the foundation structure 20 more firmly without flowing the support means 30, etc. The through hole 32 into which the reinforcing member 33 is inserted is drilled.

또한, 부호 40은 상기 지지수단(30)이 상기 거푸집(10) 및 상기 수절목(11)을 설치한 후 콘크리트를 타설하기전에 상기 지지수단(30)이 정위치에서 유동됨이 없도록 상기 지지수단(30)의 양측면에 가조립되어서 상기 지지수단(30)을 가지지()하는 서포트부재로서, 상기 지지수단(30)의 측면과 면접촉되어서 상기 지지수단(30)에 볼트 및 너트에 의해 가조립되도록 관통공(411)이 형성된 접촉부(41)와, 상기 접촉부(41)와 직각으로 일체적으로 조립되어서 상기 지지수단(30)이 정위치에 유동됨이 없도록 상기 수절목(11)에 지지되며 단부가 상기 거푸집(10)의 내면과 면접촉되는 지지부(42)로 이루어진다.Further, reference numeral 40 denotes the support means such that the support means 30 does not flow in place after the support means 30 installs the formwork 10 and the cut tree 11 and before placing concrete. Provisionally assembled on both sides of the (30) to have the support means 30 ( And a contact portion 41 having a through hole 411 formed to be in surface contact with the side surface of the support means 30 to be assembled to the support means 30 by bolts and nuts, and the contact portion 41. It is integrally assembled at right angles with the support means 30 so as to be supported by the tree 11 so that there is no flow in the right position, and the end portion is made of a support portion 42 which is in surface contact with the inner surface of the formwork 10. .

즉, 상기 서포트부재(40)는 상기 지지수단(30)이 콘크리트가 타설되기 전에 유동됨이 없이 견고하게 정위치에 위치되도록 상기 지지수단(30)의 양측면에 볼트 및 너트에 의해서 가조립되고, 접촉부(41)와 지지부(42)가 직각으로 조립되어서 좌우의 폭(W2)이 상기 기초구조물(20)의 좌우의 상부폭(L)에서 상기 지지수단(30)의 좌우의 폭(W1)을 뺀 길이의 1/2로 형성되어 있다.That is, the support member 40 is assembled by bolts and nuts on both sides of the support means 30 so that the support means 30 is firmly positioned in place without flowing before the concrete is poured. 41 and the support portion 42 are assembled at right angles so that the left and right width W2 is obtained by subtracting the right and left width W1 of the support means 30 from the left and right upper width L of the foundation structure 20. It is formed by 1/2 of the length.

이를 좀더 상세하게 설명하면, 상기 서포트부재(40)의 좌우의 폭(W2)은 상기기초구조물(20)의 좌우의 폭(L)에서 상기 지지수단(30)의 좌우의 폭(W1)을 뺀 길이의 1/2인 (L-W1)/2로 형성되므로서, 상기 지지수단(30)의 양측에 상기 서포트부재(40)를 가조립시킨 후 상기 지지수단(30)과 상기 서포트부재(40)를 상기 거푸집(10)의 내부에 위치시키면 상기 서포트부재(40)의 단부가 상기 수절목(11)에 지지됨과 동시에 상기 거푸집(10)의 내면과 면접촉되어서 유동됨이 없이 정위치로 고정되게 된다.In more detail, the left and right width W2 of the support member 40 is obtained by subtracting the left and right width W1 of the support means 30 from the left and right width L of the foundation structure 20. Since it is formed of (L-W1) / 2 which is 1/2 of the length, the support member 40 is temporarily assembled on both sides of the support means 30, and then the support means 30 and the support member 40 are assembled. When the inside of the formwork 10 is positioned so that the end of the support member 40 is supported by the cut tree 11 and in contact with the inner surface of the formwork 10 to be fixed in place without flow. do.

한편, 부호 50은 상기 지지수단(30)에 삽입되어 볼트 및 너트에 의해 상기 지지수단(30)과 조립되는 난간의 지주이고, 부호 51은 상기 지주(50)와 상기 지주(50)사이에 조립되는 난간대이다.On the other hand, reference numeral 50 is a post of the handrail inserted into the support means 30 and assembled with the support means 30 by bolts and nuts, and reference numeral 51 is assembled between the support 50 and the support 50. Become a railing.

도 3 내지 도 5에 있어서 인도변에 설치되는 난간을 도시하고 설명하였으나, 본 발명은 도 6에 도시된 바와 같은 가드레일 혹은 방호책에도 적용되는 것은 물론이다.3 to 5 illustrate and explain the handrail installed in the sidewalk, the present invention is, of course, also applied to the guardrail or a protective measure as shown in FIG.

다음은, 상기와 같이 구성된 부품으로 난간을 설치하는 난간의 설치방법 및 그 작용효과를 설명한다.Next, a method of installing a railing for installing a railing with the components configured as described above and an effect thereof will be described.

우선, 높이가 H이고 좌우의 상부폭이 L인 상기 기초구조물(20)을 형성시킬 수 있도록 상기 거푸집(10)으로 좌우의 상부폭이 L이 되도록 상기 거푸집(10)을 설치한다.First, the formwork 10 is installed such that the formwork 10 has an upper width of left and right as the formwork 10 so as to form the foundation structure 20 having a height of H and an upper width of left and right.

또, 상기 거푸집(10)을 설치한 후에는 상기 기초구조물(20)의 높이가 H로 형성되도록 함과 동시에 상기 기초구조물(20)의 상부모서리가 면취되도록 상기 수절목(11)을 상기 거푸집(10)의 내면에 설치한다.In addition, after the formwork 10 is installed, the height of the foundation 20 is formed to be H, and at the same time the cutoff tree 11 is formed so that the upper edge of the foundation 20 is chamfered. 10) to be installed on the inner surface.

또한, 상기 수절목(11)을 상기 거푸집(10)의 내면에 설치할 경우 수평계등과같은 측정수단으로 상기 수절목(11)이 수평이 유지되도록 설치한다.In addition, when the cut tree 11 is installed on the inner surface of the formwork 10, the cut tree 11 is installed to maintain the horizontal level by measuring means such as a level gauge.

또, 상기 거푸집(10)의 내면에 상기 수절목(11)이 수평을 유지되도록 설치한 후에는 상기 지지수단(30)이 상기 기초구조물(20)에 매설될 위치를 마킹한다.In addition, after the cut tree 11 is installed on the inner surface of the formwork 10 to be horizontal, the support means 30 marks the position to be embedded in the foundation structure (20).

또한, 상기 지지수단(30)이 상기 기초구조물(20)에 매설될 위치가 마킹된 후에는 상기 지지수단(30)의 양측에 상기 서포트부재(40)를 볼트 및 너트로서 가조립시킨다.In addition, after the position at which the supporting means 30 is embedded in the foundation 20 is marked, the support members 40 are temporarily assembled on both sides of the supporting means 30 as bolts and nuts.

이때, 상기 서포트부재(40)의 지지부(42)의 하면은 상기 지지수단(30)의 마킹선과 일치되도록 상기 서포트부재(40)를 상기 지지수단(30)의 양측면에 조립시키면 상기 서포트부재(40)와 상기 지지수단(30)의 좌우의 폭은 상기 거푸집(10)의 좌우의 폭(L)과 동일한 폭으로 된다.In this case, when the support member 40 is assembled to both side surfaces of the support means 30 so that the bottom surface of the support part 42 of the support member 40 is aligned with the marking line of the support means 30, the support member 40 is supported. ) And the right and left widths of the support means 30 are equal to the width L of the left and right sides of the formwork 10.

또, 상기 지지수단(30)의 양측면에 상기 서포트부재(40)를 가조립시킨 후에는 상기 거푸집(10)의 상기 지주(50)가 놓여질 위치에 상기 지지수단(30)을 위치시키면 상기 서포트부재(40)의 지지부(42)의 단부가 상기 수절목(11)에 지지됨과 동시에 상기 지지부(42)의 단부가 상기 거푸집(10)의 내면에 면접촉되어서 상기 지지수단(30)은 유동됨이 없이 정위치에 고정되게 된다.In addition, after temporarily assembling the support member 40 on both sides of the support means 30, if the support means 30 is positioned at the position where the support 50 of the formwork 10 is to be placed, the support member ( The end of the support 42 of the 40 is supported by the tree 11, and the end of the support 42 is in surface contact with the inner surface of the form 10 so that the support means 30 does not flow. It will be fixed in place.

또한, 상기 지지수단(30)을 상기 거푸집(10)에 위치시키기 전에 상기 지지수단(30)의 하부에 형성된 상기 관통공(32)에 철근등과 같은 재질의 보강부재(33)를 삽입하여 상기 지지수단(30)이 콘크리트에 타설된 후 보다 견고하게 상기 지지수단(30)이 고정되도록 하는 것이 바람직하다.In addition, the reinforcing member 33 made of a material such as reinforcing bar is inserted into the through hole 32 formed in the lower portion of the supporting means 30 before placing the supporting means 30 in the formwork 10. It is preferable that the support means 30 is more firmly fixed after the support means 30 is poured into concrete.

또, 상기 지지수단(30)을 상기 거푸집(10)의 정위치에 고정시킨 후에는 상기기초구조물(20)의 좌우의 상부폭이 L이고 상하의 높이가 H가 되도록 콘크리트를 타설한다.In addition, after fixing the support means 30 in the correct position of the formwork 10, the concrete is poured so that the upper and left upper width of the base structure 20 is L and the upper and lower heights are H.

또한, 콘크리트를 타설하여 상기 기초구조물(20)이 양생된 후에는 상기 거푸집(10) 및 상기 수절목(11)을 상기 기초구조물(20)로부터 분리시키고, 상기 지지수단(30)의 양측면에 가조립된 상기 서포트부재(40)를 제거시킨다.In addition, after the foundation 20 is cured by pouring concrete, the formwork 10 and the cut tree 11 are separated from the foundation 20 and temporarily assembled on both sides of the supporting means 30. Remove the support member 40.

한편, 상기 지지수단(30)의 양측면에 가조립된 상기 서포트부재(40)를 제거시키면 상기 지지수단(30)은 상기 기초구조물(20)에 견고하게 매설된 상태로 된다.On the other hand, when the support member 40 temporarily assembled on both sides of the support means 30 is removed, the support means 30 is firmly embedded in the foundation structure 20.

또, 상기 지지수단(30)이 상기 기초구조물(20)에 견고하게 매설된 후에는 상기 지주(50)를 상기 지지수단(30)에 삽입하여 볼트 및 너트로서 상기 지주(50)를 상기 지지수단(30)에 견고하게 조립시킨다.In addition, after the support means 30 is firmly embedded in the foundation 20, the support 50 is inserted into the support means 30 to support the support 50 as bolts and nuts. Assemble firmly to (30).

이때, 상기 지지수단(30)의 양측면에는 장공형상의 체결구멍(31)이 형성되므로서 상기 지주(50)의 높낮이를 별도의 부재를 사용함이 없이 용이하게 조절하여 보다 견고하고도 신속하게 상기 지주(50)를 상기 지지수단(30)에 조립시킬 수 있다.At this time, since both sides of the support means 30 are formed with a fastening hole 31 having a long hole shape, the height and height of the support 50 can be easily adjusted without using a separate member so that the support can be firmly and quickly. 50 may be assembled to the support means 30.

또, 상기 지지수단(30)에 상기 지주(50)를 조립시킨 후에는 상기 지주(50)와 상기 지주(50)의 사이에 난간대(51)를 조립하면 난간의 설치가 완료되게 되는 것이다.In addition, after assembling the support 50 to the support means 30, if the handrail 51 is assembled between the support 50 and the support 50, the installation of the handrail is completed.

즉, 본 발명에 의한 난간의 설치방법 및 설치장치에 의하면, 거푸집 및 수절목을 설치하고 지지수단의 양측면에 서포트부재를 가조립시킨 후 지지수단과 서포트부재를 거푸집의 내부에 위치시키면 지지수단이 정위치에 견고하게 위치고정되므로서 앙카박스를 설치함이 없이 보다 신속하게 난간의 지주를 지지하는 지지수단을 설치할 수 있는 것은 물론이고, 기초구조물의 상부에는 종래와 같은 베이스플레이트가 소요됨이 없어 보다 미려하게 난간을 설치할 수 있다는 매우 뛰어난 효과가 있다.That is, according to the installation method and the installation device of the handrail according to the present invention, after the formwork and the cutting tree are installed and the support members are temporarily assembled on both sides of the support means, the support means and the support member are positioned inside the formwork, and the support means is fixed. It is firmly fixed in the position, so that it is possible to install the supporting means for supporting the prop of the railing more quickly without installing the anchor box, and the upper part of the basic structure does not require the same base plate as in the prior art. This makes it very easy to install railings.

앞에서 설명한 바와 같이 본 발명에 의한 난간의 설치방법 및 설치장치에 의하면, 거푸집 및 수절목을 설치하고 지지수단의 양측면에 서포트부재를 가조립시킨 후 지지수단과 서포트부재를 거푸집의 내부에 위치시키면 지지수단이 정위치에 견고하게 위치고정되므로서 보다 신속하게 난간의 지주를 지지하는 지지수단을 설치할 수 있는 것은 물론이고, 보다 미려하게 난간을 설치할 수 있다는 매우 뛰어난 효과가 있다.As described above, according to the railing installation method and installation apparatus according to the present invention, after the formwork and the cutting tree are installed and the support members are temporarily assembled on both sides of the support means, the support means and the support member are positioned within the formwork for the support means. Since it is firmly fixed in this position, it is possible to install the supporting means for supporting the props of the railings more quickly, and there is a very excellent effect of installing the railings more beautifully.

Claims (5)

좌우의 상부폭이 L인 기초구조물(20)을 형성시킬 수 있도록 거푸집(10)을 설치하는 거푸집설치스텝과; 상기 거푸집설치스텝에서 설치된 상기 거푸집(10)의 내면에 상기 기초구조물(20)의 높이가 H로 형성되도록 함과 동시에 상기 기초구조물(20)의 상부모서리가 면취되도록 수절목(11)을 상기 거푸집(10)의 내면에 설치하는 수절목설치스텝과; 상기 수절목설치스텝에서 상기 수절목(11)을 설치한 후 콘크리트를 타설하여 상기 기초구조물(20)을 성형시키는 기초구조물성형스텝과; 상기 기초구조물성형스텝에서 성형된 상기 기초구조물(20)에 지주(50)를 설치하는 지주설치스텝과; 상기 지주설치스텝에서 설치된 지주(50)와 지주(50)의 사이에 난간대(51)를 설치하는 난간대설치스텝으로 이루어져 난간을 설치하는 난간의 설치방법에 있어서;A formwork installation step of installing the formwork 10 so as to form the foundation structure 20 having an upper width at the left and right sides thereof; The formwork tree 11 is formed so that the height of the foundation structure 20 is formed at the inner surface of the formwork 10 installed in the formwork installation step H and the upper edge of the foundation structure 20 is chamfered. A cut wood installation step for installing on the inner surface of (10); A basic structure forming step of forming the foundation structure 20 by installing concrete after installing the tree 11 at the tree cutting step; A support installation step of installing a support (50) on the foundation structure (20) formed in the foundation structure forming step; In the handrail installation method comprising a handrail installation step for installing a handrail 51 between the support post 50 and the support post 50 installed in the support installation step; 상기 기초구조물(20)에 매설되는 지지수단(30)의 표면에 상기 지지수단(30)이 매설되는 위치를 마킹하는 지지수단마킹스텝과;A supporting means marking step for marking a position at which the supporting means 30 is embedded on a surface of the supporting means 30 embedded in the foundation structure 20; 상기 지지수단마킹스텝에서 매설되는 위치가 마킹된 상기 지지수단(30)의 양측에 서포트부재(40)를 볼트 및 너트로서 가조립시키는 가조립스텝과;A provisional assembly step of temporarily assembling the support members 40 as bolts and nuts on both sides of the support means 30 in which the positions to be embedded in the support means marking step are marked; 상기 가조립스텝에서 상기 지지수단(30)의 양측면에 상기 서포트부재(40)를 가조립시킨 후에는 상기 지주(50)가 놓여질 위치에 상기 지지수단(30)을 위치시키는 지지수단고정스텝과;A support means fixing step of positioning the support means (30) at a position where the support (50) is to be placed after temporarily mounting the support member (40) on both sides of the support means (30) in the provisional assembly step; 상기 지지수단고정스텝에서 상기 지지수단(30)을 위치고정시킨 후 콘크리트를 타설 및 양생시키고 상기 거푸집(10) 및 상기 수절목(11)을 제거시킨 후 상기 지지수단(30)에 가조립된 상기 서포트부재(40)를 상기 지지수단(30)으로부터 분해시키는 서포트부재분해스텝과;After fixing the position of the support means 30 in the support means fixing step, the concrete is poured and cured, the form 10 and the cut tree 11 is removed and the support is assembled to the support means 30 A support member disassembling step of disassembling the member 40 from the support means 30; 상기 서포트부재분해스텝에서 상기 서포트부재(40)를 분해시킨 후 상기 지지수단(30)에 상기 지주(50)를 삽입하여 상기 지주(50)를 상기 지지수단(30)에 조립하는 지주조립스텝으로 이루어진 것을 특징으로 난간의 설치방법.In the support member disassembly step, the support member 40 is disassembled, and then the support member 30 is inserted into the support member 30, and then the support member 30 is assembled into the support member 30. Installation method of the railings, characterized in that made. 제 1항에 있어서,The method of claim 1, 상기 지지수단고정스텝에서 상기 지지수단(30)을 상기 거푸집(10)에 위치시키기 전에 상기 지지수단(30)의 하부에 형성된 상기 관통공(32)에 철근등과 같은 재질의 보강부재(33)를 삽입하는 보강부재삽입스텝이 추가되는 것을 특징으로 하는 난간의 설치방법.Reinforcing member 33 made of a material such as reinforcing bar in the through hole 32 formed in the lower portion of the support means 30 before placing the support means 30 in the formwork 10 in the support means fixing step Installation method of the handrail, characterized in that the step of inserting the reinforcing member insertion step is added. 거푸집(10) 및 수절목(11)에 의해 상하의 높이가 H이고 좌우의 상부폭이 L로 형성된 기초구조물(20)과, 상기 기초구조물(20)의 상부에 일정간격으로 설치되는 다수의 지주(50)와, 상기 지주(50)와 상기 지주(50)사이에 연결된 난간대(51)로 이루어져 지주(50)를 지지하는 난간의 설치장치에 있어서;The base structure 20 formed by the formwork 10 and the cut tree 11 with the height of the upper and lower sides of H and the upper width of the left and right sides of L, and a plurality of struts installed at regular intervals on the upper portion of the foundation structure 20 In the installation device for supporting railings consisting of 50, and the handrail (51) connected between the support (50) and the support (50); 상기 지주(50)가 삽입되도록 내부가 통공으로 이루어지고, 좌우의 폭이 W1으로 이루어져 상기 기초구조물(20)에 매설되며, 좌우측면에는 장공형상의 체결구멍(31)이 형성된 지지수단(30)과;The support 50 is formed inside the through hole so that the support 50 is inserted, and the width of the left and right is made of W1 and embedded in the foundation structure 20, and the fastening hole 31 having a long hole shape is formed at the left and right sides thereof. and; 상기 지지수단(30)이 상기 거푸집(10) 및 상기 수절목(11)을 설치한 후 콘크리트를 타설하기전에 상기 지지수단(30)이 정위치에서 유동됨이 없도록 상기 지지수단(30)의 양측면에 가조립되어서 상기 지지수단(30)을 가지지()하며, 상기 지지수단(30)의 측면과 면접촉되어서 상기 지지수단(30)에 볼트 및 너트에 의해 가조립되도록 관통공(411)이 형성된 접촉부(41)와, 상기 접촉부(41)와 직각으로 일체적으로 조립되어서 상기 지지수단(30)이 정위치에 유동됨이 없도록 상기 수절목(11)에 지지되며 단부가 상기 거푸집(10)의 내면과 면접촉되는 지지부(42)로 이루어진 서포트부재(40)로 이루어진 것을 특징으로 하는 난간의 설치장치.Both side surfaces of the support means 30 so that the support means 30 does not flow in place after the support means 30 installs the formwork 10 and the cut tree 11 before placing the concrete. Is assembled to have the support means 30 ( And a contact portion 41 having a through hole 411 formed to be in surface contact with the side surface of the support means 30 so as to be assembled to the support means 30 by bolts and nuts, and at a right angle with the contact portion 41. It is integrally assembled so that the support means 30 is supported by the tree 11 so that the flow does not flow in place, the support member consisting of a support portion 42 which is in surface contact with the inner surface of the die 10 ( Balustrade installation device, characterized in that consisting of 40). 제 3항에 있어서,The method of claim 3, wherein 상기 서포트부재(40)의 좌우의 폭(W2)은,Left and right width W2 of the support member 40, 상기 지지수단(30)의 양측에 상기 서포트부재(40)를 가조립시킨 후 상기 지지수단(30)과 상기 서포트부재(40)를 상기 거푸집(10)의 내부에 위치시키면 상기 서포트부재(40)의 단부가 상기 수절목(11)에 지지됨과 동시에 상기 거푸집(10)의 내면과 면접촉되어서 유동됨이 없이 정위치로 고정되도록 상기 기초구조물(20)의 좌우의 폭(L)에서 상기 지지수단(30)의 좌우의 폭(W1)을 뺀 길이의 1/2인 (L-W1)/2로 형성되는 것을 특징으로 하는 난간의 설치장치.Temporarily assembling the support member 40 on both sides of the support means 30 and then placing the support means 30 and the support member 40 in the form 10 of the support member 40 The support means at the left and right widths (L) of the foundation structure 20 so that the end is supported by the tree (11) and at the same time in contact with the inner surface of the formwork 10 and fixed in place without flow. A handrail mounting apparatus, characterized in that formed by (L-W1) / 2 which is 1/2 of the length minus the width (W1) of the left and right of 30). 제 3항에 있어서,The method of claim 3, wherein 상기 지지수단(30)의 하부에는 상기 지지수단(30)이 콘크리트에 매설된 후 상기 지지수단(30)이 유동됨이 없이 보다 견고하게 상기 기초구조물(20)에 설치되도록 철근등과 같은 보강부재(33)가 삽입되는 관통공(32)이 천공되어 있는 것을 특징으로 하는 난간의 설치장치.A reinforcing member such as a reinforcing bar is installed at the lower portion of the support means 30 so that the support means 30 is embedded in the concrete, and thus, the support means 30 is firmly installed in the foundation structure 20 without flowing. A handrail installation apparatus, characterized in that the through hole 32 into which the 33 is inserted is drilled.
KR1020040027389A 2004-04-21 2004-04-21 The method for set-up the guardrail and a set-up device for guardrail KR100451960B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020040027389A KR100451960B1 (en) 2004-04-21 2004-04-21 The method for set-up the guardrail and a set-up device for guardrail

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020040027389A KR100451960B1 (en) 2004-04-21 2004-04-21 The method for set-up the guardrail and a set-up device for guardrail

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR20-2004-0011018U Division KR200357073Y1 (en) 2004-04-21 2004-04-21 The Supporting device for a guardrail

Publications (1)

Publication Number Publication Date
KR100451960B1 true KR100451960B1 (en) 2004-10-12

Family

ID=37366998

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020040027389A KR100451960B1 (en) 2004-04-21 2004-04-21 The method for set-up the guardrail and a set-up device for guardrail

Country Status (1)

Country Link
KR (1) KR100451960B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100739535B1 (en) * 2006-03-09 2007-07-16 금창준 Structure foundation using pile

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100739535B1 (en) * 2006-03-09 2007-07-16 금창준 Structure foundation using pile

Similar Documents

Publication Publication Date Title
US8844224B2 (en) Utility dowel bracket
KR100873266B1 (en) Prefabricated pillar structure
EA025860B1 (en) Prefabricated mold for construction of concrete pavement
KR20200046412A (en) Landfill facility for bridge inspection structure and construction method
US8496398B2 (en) Rebar sleeve unit
KR101027016B1 (en) Construction Method of Support Plate for Grating
KR100451960B1 (en) The method for set-up the guardrail and a set-up device for guardrail
KR200357073Y1 (en) The Supporting device for a guardrail
KR20040019501A (en) divided supporter structure for supporting a mould for forming a concrete united wall and method of forming a concrete united wall using the divided supporter structure
KR100863003B1 (en) Handrail installing structure and construction method
JP3019766B2 (en) Method of constructing formwork for concrete structures
KR20110035576A (en) Fixer for thermal insulation material
JPH01278620A (en) Installation method for anchor bolt and anchor bolt supporting device used therefor
KR100715695B1 (en) Slab formwork for PC beam bridge
JP5749624B2 (en) Anchor construction method
JP3740232B2 (en) Anchor bolt mounting bracket
JP2000038727A (en) Foundation concrete and execution therefor
CN214302952U (en) Embedded screw rod positioner of assembled stair
JP7288390B2 (en) Foundation construction method and foundation
KR20070017085A (en) A Aluminum Handrail
KR100458945B1 (en) temporary bracket for construction of precast concrete beam bridge and the installation method using the same
KR200322141Y1 (en) Temporary apparatus support structure for pier of bridge
KR0172034B1 (en) Device for supporting an anchor bolt
JP2008150820A (en) Wall concrete, and manufacturing method and construction method therefor
JPH06136768A (en) Construction method for concrete permanent form

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20120830

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20130903

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20140902

Year of fee payment: 11

LAPS Lapse due to unpaid annual fee