KR100863003B1 - Handrail installing structure and construction method - Google Patents

Handrail installing structure and construction method Download PDF

Info

Publication number
KR100863003B1
KR100863003B1 KR1020080040836A KR20080040836A KR100863003B1 KR 100863003 B1 KR100863003 B1 KR 100863003B1 KR 1020080040836 A KR1020080040836 A KR 1020080040836A KR 20080040836 A KR20080040836 A KR 20080040836A KR 100863003 B1 KR100863003 B1 KR 100863003B1
Authority
KR
South Korea
Prior art keywords
handrail
base plate
fixture
boundary stone
fixing
Prior art date
Application number
KR1020080040836A
Other languages
Korean (ko)
Inventor
강도묵
박현철
Original Assignee
(주)경동기술공사
주식회사 로드맥스 엔지니어링
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)경동기술공사, 주식회사 로드맥스 엔지니어링 filed Critical (주)경동기술공사
Priority to KR1020080040836A priority Critical patent/KR100863003B1/en
Application granted granted Critical
Publication of KR100863003B1 publication Critical patent/KR100863003B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F11/00Stairways, ramps, or like structures; Balustrades; Handrails
    • E04F11/18Balustrades; Handrails
    • E04F11/181Balustrades
    • E04F11/1812Details of anchoring to the wall or floor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Steps, Ramps, And Handrails (AREA)

Abstract

A structure for installing a handrail and a construction method thereof are provided to save the maintenance cost for a handrail by preventing the handrail from being separated from a boundary stone. A structure for installing a handrail comprises a fixing device and a handrail(10). The fixing device is buried in the corner of a boundary stone to share the upper and side surfaces of the boundary stone. A fixing unit(13) is formed at the corner of the lower portion of the handrail and is fixed to the fixing device. The fixing unit includes horizontal and vertical units(11,12). The fixing device includes a base plate and a fixing member(30) having a block shape. The base plate includes horizontal and vertical units(21,22) coupled with the handrail. The fixing member is coupled with the vertical unit of the base plate by using a coupling member(15) in a state in which the fixing unit of the handrail is mounted.

Description

난간 설치 구조 및 시공 방법{Handrail installing structure and construction method}Handrail installing structure and construction method

본 발명은 난간에 관한 것으로서, 더욱 상세하게는 난간을 경계석의 모서리부에 설치하여 경계석의 상면과 측면을 지지기반으로 경계석에 견고하게 지지되도록 하며 난간의 설치 작업을 단순화할 수 있는 난간 설치 구조 및 시공 방법에 관한 것이다.The present invention relates to a railing, and more particularly, to install a railing at a corner of a boundary stone so that the upper and side surfaces of the boundary stone are firmly supported by the boundary stone, and a railing installation structure capable of simplifying the installation work of the railing and It is about a construction method.

일반적으로, 도로의 가장자리 또는 건물의 일측에는 사람들의 동선에 제약을 가하기 위하여 난간을 설치한다.Generally, railings are installed on the edge of a road or on one side of a building to restrict people's traffic.

종래 난간 설치구조는 콘크리트를 타설하기 전에 비계용 강관이 끼워지는 직경의 철근이나 파이프를 매설하여 콘크리트 경화후 일정부분이 외부로 노출되게 하였다. 이렇게 노출된 철근이나 파이프에 강관비계를 끼워서 난간을 시공하였다.In the conventional railing installation structure, before reinforcing concrete, certain parts are exposed to the outside after the concrete is hardened by embedding steel reinforcing bars or pipes into which steel pipes for scaffolding are fitted. Railings were constructed by inserting steel pipe scaffolding into the exposed rebar or pipe.

하지만, 이렇게 설치된 난간은 설치 후 강관과 그가 끼워지는 철근이나 파이프와의 유격 때문에 난간이 흔들거려 작업자가 위험할 뿐만 아니라, 유지보수에도 어려움이 있었다. 또한, 난간 해체 후에는 콘크리트를 돌출한 철근이나 파이프의 노출부분을 절단해야 하는 번거로움이 있고, 나아가 이러한 돌출된 노출부분 때문에 바닥 마감 시공 상에 불편함이 따르고 시공불량을 가져오는 등의 문제가 있었다.However, the railings installed in this way were not only dangerous to the worker, but also difficult to maintain due to shaking of the railings due to the clearance between the steel pipe and the reinforcing bars or pipes to which they were fitted. In addition, after the dismantling of the railing, it is cumbersome to cut the exposed part of the reinforcing bar or pipe that protrudes the concrete, and furthermore, such a protruding exposed part causes inconvenience in the floor finishing work and brings about poor construction. there was.

이러한 문제를 극복하기 위한 다른 종래 기술로, 난간은 콘크리트 슬래브에 장착할 수 있도록 압착핸들이 마련되어 있으며, 이 하단에 구비된 압착핸들을 회전시켜서 슬래브에 고정하게 된다. 이 압착핸들에는 수직봉들과 수평봉들이 연결되어 난간을 이루고 있으며, 이 압착핸들을 난간대의 적어도 좌우에 구비하여 슬래브에 난간을 고정하게 된다. In another conventional technique for overcoming this problem, the handrail is provided with a crimping handle to be mounted on the concrete slab, it is fixed to the slab by rotating the crimp handle provided on the bottom. The pressing rods are connected with vertical rods and horizontal rods to form a railing, and the pressing handles are provided on at least the left and right sides of the railing to fix the railing to the slab.

이러한 장착형 난간은 제조비가 많이 소요되어 제품단가가 비싸며, 압착력 만으로 콘크리트구조물에 고정되므로 안전성이 취약할 뿐만 아니라, 일체형으로 제작되므로 부피가 크고 무거워 이동운반 및 보관이 불편한 단점을 지니고 있다.These mounting railings are expensive to manufacture due to the high production cost, and because they are fixed to the concrete structure only by the pressing force, not only the safety is weak, but also because they are made in one piece, they are bulky and heavy, which makes them difficult to transport and store.

본 발명은 상기와 같은 문제점을 해결하기 위한 것으로, 난간을 경계석의 모서리부에 설치하여 경계석의 상면과 측면을 지지기반으로 경계석에 견고하게 지지되도록 하며 난간의 설치 작업을 단순화할 수 있는 난간 설치 구조 및 시공 방법을 제공하는데 그 목적이 있다.The present invention is to solve the above problems, the railing is installed on the corner of the boundary stone to support the top and side of the boundary stone firmly supported by the boundary stone and railing installation structure that can simplify the installation work of the railing And a construction method.

전술한 바와 같은 목적을 달성하기 위한 본 발명에 의한 난간 설치 구조는, 경계석의 모서리부에는 상기 경계석의 상면과 측면을 공유하도록 고정수단이 매설되며, 난간의 저부에는 수평부와 수직부로 이루어진 고정부가 형성되어, 이 고정부가 상기 고정수단에 고정되고, 상기 고정수단은, 상기 난간이 체결되는 수평부와 수직부로 이루어진 베이스 플레이트와; 블록 형태이며 상기 베이스 플레이트의 수직부에 체결됨과 아울러 측면에 상기 난간이 체결구를 통해 체결되는 고정구로 구성된 것을 특징으로 한다.In the handrail installation structure according to the present invention for achieving the object as described above, the fixing means is embedded in the corner portion of the boundary stone to share the upper surface and the side surface of the boundary stone, the fixing portion consisting of a horizontal portion and a vertical portion at the bottom of the railing And a fixing part fixed to the fixing means, the fixing means comprising: a base plate comprising a horizontal part and a vertical part to which the handrail is fastened; It is a block form and is fastened to the vertical portion of the base plate, characterized in that consisting of a fastener is fastened through the fastener on the side.

본 발명에 의한 난간 설치 구조 및 시공 방법에 의하면, 난간이 경계석의 상면과 측면 2곳에 지지되어 방향에 상관없이 종방향과 횡방향으로부터 가해지는 외력에 대한 버팀력을 확보함으로써 난간이 경계석으로부터 이탈되지 않도록 견고하게 지지되므로 난간의 유지비용을 절감할 수 있다.According to the railing installation structure and construction method according to the present invention, the railing is supported on the upper surface and the two sides of the boundary stone so that the railing is not separated from the boundary stone by securing the support force against external force applied from the longitudinal direction and the transverse direction regardless of the direction. It is firmly supported so that the cost of railing maintenance can be reduced.

그리고, 난간이 경계석에 직접 설치되지 않고 경계석에 매설된 베이스 플레이트와 고정구를 통해 설치되어 난간의 설치시 경계석의 파손을 막을 수 있다.And, the railing is not installed directly on the boundary stone, but is installed through the base plate and the fixture embedded in the boundary stone can prevent breakage of the boundary stone when installing the railing.

도 1과 도 2에서 보이는 것처럼, 본 발명에 의한 난간 설치구조는 다음과 같다.As shown in Figure 1 and Figure 2, the railing installation structure according to the present invention is as follows.

난간(10)은 경계석(1)의 상면과 측면 2곳에서 결합이 이루어져 외력에 대항하는 큰 버팀력을 발휘한다. Handrail 10 is coupled to the upper surface and two sides of the boundary stone (1) to exert a large support force against the external force.

난간(10)의 저부에는 경계석(1)의 상면과 측면에 각각 지지될 수 있도록 수평부(11)와 수직부(12)를 갖는 고정부(13)가 형성된다.A bottom portion of the handrail 10 is formed with a fixing portion 13 having a horizontal portion 11 and a vertical portion 12 so as to be supported on the top and side surfaces of the boundary stone 1, respectively.

난간(10)의 설치를 위하여 베이스플레이트(20) 및 고정구(30)가 사용된다.The base plate 20 and the fixture 30 are used for the installation of the handrail 10.

도 2와 도 3에서처럼, 베이스 플레이트(20)와 고정구(30)는 한 셋트로 구성되며, 경계석(1)의 길이방향을 따라 다수개가 일정 간격을 두고 경계석(1) 내부에 매설되어 고정된다.As shown in Figure 2 and 3, the base plate 20 and the fixture 30 is composed of one set, a plurality of fixed along the longitudinal direction of the boundary stone (1) embedded in the boundary stone (1) is fixed.

베이스 플레이트(20)는 경계석(1)의 상면에 배치되며 난간(10)의 수평부(11)가 안착 고정되는 상부 수평부(21) 및 수평부(21)의 일측 단부에서 하부를 향해 연장되어 경계석(1)의 측면에 배치되는 수직부(22)로 이루어진다.The base plate 20 is disposed on the upper surface of the boundary stone 1 and extends downward from one end of the horizontal portion 21 and the horizontal portion 21 on which the horizontal portion 11 of the handrail 10 is seated and fixed. It consists of the vertical part 22 arrange | positioned at the side of the boundary stone 1.

베이스 플레이트(20)는 경계석(1)의 콘크리트 타설시 거푸집(미도시)에 의해 지지되어 콘크리트에 매설되며, 매설된 상태에서 난간(10)이 설치된다. 이를 위하여 베이스 플레이트(20)의 수평부(21)의 저부에는 난간(10)과의 결합을 위한 보스(23)가 형성된다. The base plate 20 is supported by formwork (not shown) when the concrete is placed in the boundary stone 1 is embedded in the concrete, the railing 10 is installed in the embedded state. To this end, a boss 23 for coupling with the handrail 10 is formed at the bottom of the horizontal portion 21 of the base plate 20.

즉, 난간(10)의 수평부(11)가 베이스 플레이트(20)의 수평부(21)에 안착된 상태에서 체결구(24)가 난간(10)의 수평부(11)와 베이스 플레이트(20)의 보스(23)에 체결됨으로써 고정이 이루어진다.That is, the fastener 24 is the horizontal portion 11 of the handrail 10 and the base plate 20 while the horizontal portion 11 of the handrail 10 is seated on the horizontal portion 21 of the base plate 20. The fastening is performed by being fastened to the boss 23.

베이스 플레이트(20)는 경계석(1)에 대해 견고하게 고정되도록 매설핀(25)이 체결된다. 매설핀(25)은 볼트(25a)와 너트(25b)로 이루어지며, 보스(23)의 하단부 에 볼트(25a)의 머리가 끼워진 후 너트(25b)가 조여짐으로써 보스(23)에 고정되고, 콘크리트와의 마찰력에 의해 베이스 플레이트(20)를 지지한다.The base plate 20 is fastened to the buried pin 25 to be firmly fixed to the boundary stone (1). The buried pin 25 is composed of a bolt 25a and a nut 25b, and is fixed to the boss 23 by tightening the nut 25b after the head of the bolt 25a is fitted to the lower end of the boss 23. The base plate 20 is supported by friction with concrete.

베이스 플레이트(20)는 고정구(30)와 함께 조립되며, 이 조립 구조는 고정구(30)의 설명시 명확해질 것이다.The base plate 20 is assembled with the fixture 30, and this assembly structure will be apparent in the description of the fixture 30.

고정구(30)는 베이스 플레이트(20)와 하나 이상의 체결구(26)를 통해 결합되어 경계석(1)의 콘크리트 타설 이전에 거푸집에 의해 지지되며, 난간(10)이 고정된다. 체결구(26)는 경계석(1)에 매설되는 것으로 베이스 플레이트(20)가 경계석(1)에서 이탈되지 않도록 한다.The fixture 30 is coupled through the base plate 20 and one or more fasteners 26 to be supported by the formwork before concrete placing of the boundary stone 1, and the handrail 10 is fixed. The fastener 26 is embedded in the boundary stone 1 to prevent the base plate 20 from being separated from the boundary stone 1.

고정구(30)는 경계석(1)의 모서리부 즉 난간(10)의 고정부(13)의 모서리부(수평부(11)와 수직부(12)의 사이)에 배치되어 즉 난간(10)의 2면을 지지한다.The fastener 30 is arranged at the corner of the boundary stone 1, that is, at the corner of the fixing part 13 of the handrail 10 (between the horizontal part 11 and the vertical part 12), that is, of the handrail 10. Support two sides.

고정구(30)에 대한 난간(10)의 설치 구조는 다음과 같다.The installation structure of the handrail 10 for the fixture 30 is as follows.

난간(10)은 하나 이상의 체결구(15)를 통해 고정구(30)에 설치됨과 아울러 끼움식으로 조립된다. Handrail 10 is installed on the fixture 30 through one or more fasteners 15 and is assembled by fitting.

고정구(30)는 육면체의 블록형태일 수 있으며, 내부에는 일측(도로측)을 향해 개방된 삽입홈(31)이 구비되며, 삽입홈(31)의 좌우 양측에는 각각 보스(32)가 형성된다. 보스(32)에는 베이스 플레이트(20)를 고정하는 체결구(26)와 난간(10)을 고정하는 체결구(15)가 서로 반대측에서 각각 체결됨으로써 고정구(30)의 전체적인 구조를 단순화한다.Fixture 30 may be in the form of a block of hexahedron, the inside is provided with an insertion groove 31 open toward one side (road side), the boss 32 is formed on each of the left and right sides of the insertion groove 31, respectively. . The boss 32 has a fastener 26 fixing the base plate 20 and a fastener 15 fixing the handrail 10, respectively, on the opposite side, thereby simplifying the overall structure of the fastener 30.

난간(10)의 고정구(13)에는 삽입구(14)가 돌출 형성되며, 수직부(12)에는 보스(32)와 연통하는 통공이 형성된다.The insertion hole 14 protrudes and is formed in the fixture 13 of the handrail 10, The vertical part 12 is formed with the through-hole communicating with the boss 32.

즉, 난간(10)이 체결구(15)를 통해 고정됨과 아울러 삽입구(14)가 고정구(30)의 삽입홈(31)에 끼워져 난간(10)을 지지함에 따라 난간(10)과 고정구(30)를 견고하게 결속할 수 있다.That is, as the handrail 10 is fixed through the fastener 15 and the insertion hole 14 is inserted into the insertion groove 31 of the fastener 30 to support the handrail 10, the handrail 10 and the fixture 30 ) Can be solidly bound.

삽입홈(31)은 난간(10)의 설치시에만 개방되어야 하고 콘크리트 타설시에는 콘크리트가 유입되지 않아야 할 것이므로 경계석(1)의 콘크리트 타설시에는 스티로폼 등의 채움재가 끼워져 메워질 수 있다. 상기 스티로폼은 삽입홈(31)을 막으면서 난간(10)의 설치시 제거될 수 있는 채움재를 대표하는 것이라 할 수 있다.Insertion groove 31 should be opened only when the railing 10 is installed and the concrete should not be introduced during the concrete placing, so when the concrete of the boundary stone (1) can be filled with filling material such as styrofoam. The styrofoam can be said to represent the filling material that can be removed during installation of the handrail 10 while blocking the insertion groove (31).

본 발명에 의한 난간 설치 방법은 다음과 같다.Railing installation method according to the present invention is as follows.

(S10) 거푸집 설치.(S10) formwork installation.

경계석(1)의 시공을 위하여 설계에 맞춰 거푸집을 설치한다. Formwork is installed in accordance with the design for the construction of the boundary stone (1).

이때, 베이스 플레이트(20)와 고정구(30)를 상기 거푸집에 지지한다. 베이스 플레이트(20)와 고정구(30)는 체결구(26)를 통해 조립된 상태이며, 베이스 플레이트(20)에는 매설핀(25)이 체결되어 있고, 고정구(30)의 삽입홈(31)에는 스티로폼이 끼워져 콘크리트가 유입되지 않도록 되어 있다.At this time, the base plate 20 and the fixture 30 is supported on the formwork. The base plate 20 and the fixture 30 are assembled through the fastener 26, and the buried pin 25 is fastened to the base plate 20, and the insertion groove 31 of the fixture 30 is fixed to the base plate 20. Styrofoam is inserted to prevent concrete from entering.

(S20) 콘크리트 타설.(S20) concrete pouring.

상기 거푸집 안쪽에 콘크리트를 타설 양생하여 경계석(1)을 시공한다.The cured concrete is poured into the formwork to construct the boundary stone (1).

콘크리트가 타설되면 매설핀(25)과 체결구(26)에 의해 베이스 플레이트(20)와 고정구(30) 조립체가 경계석(1)에 견고하게 매설된다. 콘크리트의 타설시 고정구(30)의 삽입홈(31)에는 스티로폼이 삽입되어 있기 때문에 콘크리트가 유입되지 않는다.When the concrete is poured, the base plate 20 and the fixture 30 assembly are firmly embedded in the boundary stone 1 by the embedding pin 25 and the fastener 26. Concrete is not introduced because the styrofoam is inserted into the insertion groove 31 of the fixture 30 when the concrete is poured.

(S30) 거푸집 탈형.(S30) formwork demoulding.

콘크리트의 양생이 완료되면 상기 거푸집을 탈형하며, 상기 거푸집의 탈형시 베이스 플레이트(20)와 고정구(30)는 경계석(1)에 남게 된다. 상기 거푸집의 탈형이 완료되면 고정구(30)의 삽입홈(31)에 끼워진 스티로폼을 빼내어 삽입홈(31)을 개방한다.When curing of the concrete is completed, the mold is demolded, and the base plate 20 and the fixture 30 remain in the boundary stone 1 when demolding the formwork. When the mold is demolded, the styrofoam inserted into the insertion groove 31 of the fixture 30 is removed to open the insertion groove 31.

(S40) 난간 설치.(S40) railing installation.

난간(10)의 고정부(13)를 경계석(1)의 모서리 즉 베이스 플레이트(20)와 고정구(30)에 맞춰 배열한 후, 난간(10)의 삽입구(14)를 고정구(30)의 삽입홈(31)에 삽입한다. 이렇게 되면 난간(10)은 고정부(13)의 수평부(11)가 베이스 플레이트(20)의 상면에 안착되며 수직부(12)가 고정구(30)의 측면에 지지된 상태를 유지한다.After arranging the fixing part 13 of the handrail 10 to the corner of the boundary stone 1, that is, the base plate 20 and the fixing device 30, the insertion opening 14 of the handrail 10 is inserted into the fixing device 30. Insert into the groove (31). In this case, the railing 10 maintains a state in which the horizontal portion 11 of the fixing portion 13 is seated on the upper surface of the base plate 20, and the vertical portion 12 is supported on the side surface of the fixing tool 30.

이어서, 체결구(24,15)를 통해 난간(10)의 고정부(13)의 수평부(11)와 수직부(12)를 베이스 플레이트(20)의 수평부(21)와 고정구(30)에 각각 고정한다. 이로써, 난간(10)의 설치가 완료된다.Subsequently, the horizontal portion 11 and the vertical portion 12 of the fixing portion 13 of the handrail 10 are fastened to the horizontal portion 21 and the fixing portion 30 of the base plate 20 through the fasteners 24 and 15. To each. This completes the installation of the handrail 10.

이와 같은 방법에 의해 설치된 난간(10)은 경계석(1)의 모서리부인 상면과 측면에 지지되어 종방향 및 횡방향의 외력에 대한 버팀력이 확보되므로 어느 방향에서 외력이 가해지더라도 경계석(1)에 견고하게 지지될 수 있다.The handrail 10 installed by the above method is supported on the upper and side surfaces, which are the edges of the boundary stone 1, so that the supporting force for the external force in the longitudinal and transverse directions is secured, so that no matter in which direction the external force is applied to the boundary stone 1 It can be firmly supported.

그리고, 베이스 플레이트(20)와 고정구(30)가 경계석(1)의 콘크리트 타설시 매설되어 체결구(24,15)를 체결하는 작업에 의해서 난간(10)을 설치할 수 있으므로 난간(10)의 설치 작업이 매우 용이하다.In addition, since the base plate 20 and the fixture 30 are embedded in the concrete placing of the boundary stone 1, the handrail 10 can be installed by the fastening fasteners 24 and 15, so that the handrail 10 is installed. The operation is very easy.

도 1은 본 발명에 의한 난간 설치 구조를 보인 측단면도.1 is a side cross-sectional view showing a railing installation structure according to the present invention.

도 2는 본 발명에 의한 난간 설치 구조를 보인 사시도.Figure 2 is a perspective view showing a railing installation structure according to the present invention.

도 3은 본 발명에 의한 난간 설치 구조에 적용된 난간과 베이스 플레이트 및 고정구의 분해 사시도.3 is an exploded perspective view of a handrail and a base plate and a fixture applied to a handrail mounting structure according to the present invention.

< 도면의 주요 부분에 대한 부호 설명><Description of Signs for Main Parts of Drawings>

1 : 경계석, 10 : 난간1: boundary stone, 10: handrail

13 : 고정부, 20 : 베이스 플레이트13: fixed part, 20: base plate

30 : 고정구,30: fixture,

Claims (4)

경계석(1)의 모서리부에는 상기 경계석의 상면과 측면을 공유하도록 고정수단이 매설되며,At the corners of the boundary stone 1, fixing means are embedded so as to share the upper surface and the side surface of the boundary stone, 난간(10)의 저부 모서리부에는 수평부(11)와 수직부(12)로 이루어진 고정부(13)가 형성되어 이 고정부가 상기 고정수단에 고정되고,A bottom portion of the handrail 10 is formed with a fixing portion 13 consisting of a horizontal portion 11 and a vertical portion 12, the fixing portion is fixed to the fixing means, 상기 고정수단은,The fixing means, 상기 난간이 체결되는 수평부(21)와 수직부(22)로 이루어진 베이스 플레이트(20)와;A base plate 20 comprising a horizontal portion 21 and a vertical portion 22 to which the handrail is fastened; 블록 형태이며 상기 베이스 플레이트의 수직부에 체결됨과 아울러 상기 난간의 고정부가 안착된 상태에서 체결구(15)를 통해 체결되는 고정구(30)로 이루어진 것을 특징으로 하는 난간 설치 구조.Handrail installation structure characterized in that the block is made of a fastener (30) is fastened through the fastener (15) in the state in which the fixing portion of the handrail and fastened to the vertical portion of the base plate. 청구항 1에 있어서, 상기 고정구에는 일측을 향해 개방된 삽입홈(31)이 형성되며, 상기 난간의 고정부에는 상기 삽입홈에 끼워지는 삽입구(14)가 돌출 형성되어, 상기 난간이 상기 삽입구를 통해 상기 고정구에 끼워 고정되는 것을 특징으로 하는 난간 설치 구조.The method of claim 1, wherein the fixing tool is formed with an insertion groove 31 which is open toward one side, the fixing portion of the handrail is inserted into the insertion hole 14 is inserted into the insertion groove is formed, the handrail through the insertion hole Handrail installation structure, characterized in that fixed to the fixture. 경계석의 형태에 따라 거푸집을 설치하고, 수평부(21)와 수직부(22)로 이루어진 베이스 플레이트(20) 및 삽입홈(31)을 갖는 고정구(30)를 결합하여 상기 거푸집의 모서리부에 길이방향을 따라 일정 간격을 두고 다수개를 설치하는 제1단계와;The formwork is installed according to the shape of the boundary stone, and the base plate 20 consisting of the horizontal portion 21 and the vertical portion 22 and the fixture 30 having the insertion groove 31 are coupled to each other so that the edge portion of the formwork has a length. A first step of installing a plurality at regular intervals along the direction; 상기 거푸집 내부에 콘크리트를 타설하는 제2단계와;A second step of pouring concrete into the formwork; 상기 콘크리트의 양생 후 상기 거푸집만을 탈형하여 콘크리트 양생된 경계석(1)에 상기 베이스 플레이트와 고정구를 매설하는 제3단계와; 그리고,A third step of embedding the base plate and the fixture in the cured boundary stone (1) by demolding only the formwork after curing of the concrete; And, 하단부에 고정부(13)가 형성된 난간(10)을 상기 고정구 앞에 배치하고 상기 고정부(13)를 상기 베이스 플레이트와 고정구에 맞춰 결속하는 제4단계로 이루어진 것을 특징으로 하는 난간 시공 방법.A handrail construction method comprising a fourth step of placing a handrail (10) having a fixed portion (13) formed at a lower end in front of the fixture, and binding the fixing portion (13) to the base plate and the fixture. 청구항 3에 있어서, 상기 제1단계에서는 상기 고정구의 삽입홈에 채움재를 끼워 상기 제2단계에서 콘크리트를 타설하고, 상기 제4단계에서는 상기 채움재를 상기 고정구에서 제거한 후 상기 난간의 고정부에 형성된 삽입구를 상기 고정구에 형성된 삽입홈에 끼워 결속하는 것을 특징으로 하는 난간 시공 방법.4. The insert of claim 3, wherein in the first step, the filler is inserted into the insertion groove of the fixture, and the concrete is poured in the second step, and in the fourth step, the filler is formed in the fixing part of the railing after removing the filler from the fixture. Handrail construction method characterized in that the binding to the insertion groove formed in the fixture.
KR1020080040836A 2008-04-30 2008-04-30 Handrail installing structure and construction method KR100863003B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020080040836A KR100863003B1 (en) 2008-04-30 2008-04-30 Handrail installing structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020080040836A KR100863003B1 (en) 2008-04-30 2008-04-30 Handrail installing structure and construction method

Publications (1)

Publication Number Publication Date
KR100863003B1 true KR100863003B1 (en) 2008-10-13

Family

ID=40153204

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020080040836A KR100863003B1 (en) 2008-04-30 2008-04-30 Handrail installing structure and construction method

Country Status (1)

Country Link
KR (1) KR100863003B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101153876B1 (en) * 2009-11-20 2012-06-18 김명근 With the wall body together construction work of supporter for establishing railings construction method thereof and the supporter for establishing railings
CN103821380A (en) * 2014-02-25 2014-05-28 中天建设集团有限公司 Construction method for installing steel railing on site through positioning fixture

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09170358A (en) * 1995-12-20 1997-06-30 Tokiko Yuki Kk Fire fence
KR19990015518U (en) * 1997-10-17 1999-05-15 윤종용 Support device for road hazard warning lights
KR20050055637A (en) * 2005-03-25 2005-06-13 (주)우리에스티에스 Construct method of balcony parapet
KR100613414B1 (en) 2004-07-09 2006-08-17 주식회사 에이브이티 Structure for fixing base-plate on a central separating stand of a bridge
JP2007063834A (en) 2005-08-31 2007-03-15 Sekisui Jushi Co Ltd Guard fence support and guard fence

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09170358A (en) * 1995-12-20 1997-06-30 Tokiko Yuki Kk Fire fence
KR19990015518U (en) * 1997-10-17 1999-05-15 윤종용 Support device for road hazard warning lights
KR100613414B1 (en) 2004-07-09 2006-08-17 주식회사 에이브이티 Structure for fixing base-plate on a central separating stand of a bridge
KR20050055637A (en) * 2005-03-25 2005-06-13 (주)우리에스티에스 Construct method of balcony parapet
JP2007063834A (en) 2005-08-31 2007-03-15 Sekisui Jushi Co Ltd Guard fence support and guard fence

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101153876B1 (en) * 2009-11-20 2012-06-18 김명근 With the wall body together construction work of supporter for establishing railings construction method thereof and the supporter for establishing railings
CN103821380A (en) * 2014-02-25 2014-05-28 中天建设集团有限公司 Construction method for installing steel railing on site through positioning fixture

Similar Documents

Publication Publication Date Title
KR101765762B1 (en) Cantilever part for bridge and constructing method thereof
KR100819833B1 (en) Apparatus and method for building slab of a concrete build
KR101237333B1 (en) Spacer for stripping deck
KR101237330B1 (en) Spacer for stripping deck
JP2010150871A (en) Decorative plate attaching method for thermal insulation material doubling as form and latching member for outer wall
KR100863003B1 (en) Handrail installing structure and construction method
KR20070027432A (en) A fastener for fixing a reinforcing bar assembly, a mold panel, and a ceiling panel by fixing pin
KR20090085204A (en) A precast deck slab of a bridge
KR101278686B1 (en) Device for support slab formwork and its using the same slab construction method
US20160060885A1 (en) Support bracket and method for temporary guard railing
KR101282243B1 (en) A construction method using the column cap for permanent beam form
KR200477823Y1 (en) Filler form for concrete building and connecting structure using the same
KR100612938B1 (en) A construction system of the wall/dome and the the method thereof it
KR200281867Y1 (en) An iron reinforcing bar prop
KR101322581B1 (en) Spacer for fastening Reinforcement Bar and Hanger Bolt
KR101157588B1 (en) Slab form bracket and method for constructing slab of an iron architect using thereof
JP2007217871A (en) Dry foundation and its construction method
KR200234872Y1 (en) An iron reinforcing bar prop
KR100737995B1 (en) Insert for ceiling finish panel installation
KR101182201B1 (en) Assembly form for boundary stone
KR20160043501A (en) A sump or elevator pit under structure
KR200457690Y1 (en) Block for the ground reinforcement structure
KR100785312B1 (en) Mounting structure for steel-frame stair
KR101046020B1 (en) Formwork wedge joining structure for easy demoulding and reassembly
KR101615270B1 (en) Form and integrated with concrete and method for constructing thereof

Legal Events

Date Code Title Description
A201 Request for examination
N231 Notification of change of applicant
N231 Notification of change of applicant
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20120928

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20131002

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20140926

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20151007

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20161007

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20171011

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20181008

Year of fee payment: 11