KR100402436B1 - The method for carrying out of underground structure object using a fiberglass reinforced plastics and a hydraulic jack - Google Patents

The method for carrying out of underground structure object using a fiberglass reinforced plastics and a hydraulic jack Download PDF

Info

Publication number
KR100402436B1
KR100402436B1 KR10-2001-0028318A KR20010028318A KR100402436B1 KR 100402436 B1 KR100402436 B1 KR 100402436B1 KR 20010028318 A KR20010028318 A KR 20010028318A KR 100402436 B1 KR100402436 B1 KR 100402436B1
Authority
KR
South Korea
Prior art keywords
hydraulic jack
composite member
panel
underground structure
vertical
Prior art date
Application number
KR10-2001-0028318A
Other languages
Korean (ko)
Other versions
KR20020089689A (en
Inventor
최성욱
Original Assignee
주식회사유신코퍼레이션
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사유신코퍼레이션 filed Critical 주식회사유신코퍼레이션
Priority to KR10-2001-0028318A priority Critical patent/KR100402436B1/en
Publication of KR20020089689A publication Critical patent/KR20020089689A/en
Application granted granted Critical
Publication of KR100402436B1 publication Critical patent/KR100402436B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B9/00Water-power plants; Layout, construction or equipment, methods of, or apparatus for, making same
    • E02B9/02Water-ways
    • E02B9/06Pressure galleries or pressure conduits; Galleries specially adapted to house pressure conduits; Means specially adapted for use therewith, e.g. housings, valves, gates
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/34Horizontally-travelling moulds for making walls blockwise or section-wise
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mechanical Engineering (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Paleontology (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

본 발명은 복합부재 특수판넬과 유압 잭을 이용한 지하구조물의 시공법에 관한 것으로서, 더욱 상세하게는 지하 구조물을 제작하는 경우 작업자들이 편리하고 안전하게 사용할 수 있도록 복합부재 판넬과 유압 잭을 이용하는 시공방법을 제공하여 지하구조물에 대한 설치 및 해체가 용이하고 녹 발생이 전혀 없으며, 또한 복합부재 판넬을 이용한 거푸집을 사용하는 관계로 공사비 절감과 하자 작업을 최대한 줄일 수 있는 구조를 가지는 복합부재 판넬과 유압 잭을 이용한 지하 구조물 시공법에 관한 것이다.The present invention relates to a construction method for underground structures using a composite member special panel and a hydraulic jack, and more particularly, to provide a construction method using a composite member panel and a hydraulic jack so that workers can conveniently and safely use the underground structure. Therefore, it is easy to install and dismantle the underground structure, and there is no rust. Also, it uses the formwork using the composite member panel, and the composite member panel and the hydraulic jack have the structure that can reduce the construction cost and minimize the defect work. It is about underground construction method.

본 발명은, 지하에 설치되어 공동구, 전선구 및 하수도로 이용되는 지하 구조물의 시공법에 있어서, 기초 콘크리트를 타설하고 그 상부에 거푸집 조정장치를 설치하되, 상기의 거푸집 조정장치는 하부 높이조정 유압 잭을 기초 콘크리트에 밀착시키고, 상기의 거푸집 조정장치는 조정 판넬을 작동하여 수평부 유압 잭, 수직부 유압 잭 및 사선부 유압 잭을 지하 구조물의 내측 너비 및 높이로 고정시키며, 상기의 거푸집 조정장치에는 일체로 결합되어 있는 수직 내부 보강재, 복합부재 사각 보강재 및 내측 복합부재 판넬을 수평부 유압 잭, 수직부 유압 잭 및 사선부 유압 잭의 그 끝단에 밀착시키고, 상기의 수직 내부 보강재와 내측 복합부재 판넬에는 직하부에 하부받침 고정틀을 설치하여 수직 내부 보강재와 내측 복합부재 판넬을 지지시키며, 상기의 내측 복합부재 판넬의 측면에 철근을 배근한 뒤 지하 구조물의 두께만큼 외측 복합부재 판넬을 이격하여 설치한 뒤 콘크리트를 타설하여 지하 구조물을 시공하고 자동으로 탈형하는 것을 특징으로 하는 복합부재 판넬과 유압 잭을 이용한 지하 구조물 시공법을 제공한다.The present invention, in the construction method of the underground structure is installed in the basement used in the cavity, electric wire and sewer, the foundation concrete is installed and the formwork adjusting device is installed on the upper part, the formwork adjusting device is a lower height adjustment hydraulic jack In close contact with the foundation concrete, the formwork adjusting device operates the adjusting panel to fix the horizontal hydraulic jack, the vertical hydraulic jack and the diagonal hydraulic jack to the inner width and height of the underground structure, and is integrated with the formwork adjusting device. The vertical inner stiffener, the composite member square stiffener and the inner composite panel, which are joined together, are brought into close contact with the ends of the horizontal hydraulic jack, the vertical hydraulic jack and the diagonal hydraulic jack. The lower support fixing frame is installed directly below to support the vertical inner reinforcement and the inner composite member panel. Reinforce the reinforcing bar on the side of the inner composite member panel and install the outer composite member panel as the thickness of the underground structure and install the underground structure by placing concrete and demoulding automatically. Provide underground construction method using

Description

복합부재 판넬과 유압 잭을 이용한 지하 구조물 시공법{The method for carrying out of underground structure object using a fiberglass reinforced plastics and a hydraulic jack}The method for carrying out of underground structure object using a fiberglass reinforced plastics and a hydraulic jack}

본 발명은 복합부재 특수판넬과 유압 잭을 이용한 지하구조물의 시공법에 관한 것으로서, 더욱 상세하게는 지하 구조물을 제작하는 경우 작업자들이 편리하고 안전하게 사용할 수 있도록 복합부재 판넬과 유압 잭을 이용하는 시공방법을 제공하여 지하구조물에 대한 설치 및 해체가 용이하고 녹 발생이 전혀 없으며, 또한 복합부재 판넬을 이용한 거푸집을 사용하는 관계로 공사비 절감과 하자 작업을 최대한 줄일 수 있는 구조를 가지는 복합부재 판넬과 유압 잭을 이용한 지하 구조물 시공법에 관한 것이다.The present invention relates to a construction method for underground structures using a composite member special panel and a hydraulic jack, and more particularly, to provide a construction method using a composite member panel and a hydraulic jack so that workers can conveniently and safely use the underground structure. Therefore, it is easy to install and dismantle the underground structure, and there is no rust. Also, it uses the formwork using the composite member panel, and the composite member panel and the hydraulic jack have the structure that can reduce the construction cost and minimize the defect work. It is about underground construction method.

일반적으로 지하 구조물의 시공법은 목재 또는 철재를 이용하여 지하 구조물의 내부에서 인력으로 설치 또는 해체를 하여 작업하게 된다.In general, the construction method of underground structures is to work by installing or dismantling in the interior of underground structures using wood or steel.

도 1은 일반적인 지하 구조물을 제작하는 시공법을 개략적으로 나타내는 도면으로서, 기초 콘크리트(20)를 타설한 후 상기의 기초 콘크리트(20)의 상부에 합판 거푸집(22)을 설치한다.1 is a view schematically showing a construction method for manufacturing a general underground structure, after the foundation concrete 20 is placed, the plywood formwork 22 is installed on the upper portion of the foundation concrete 20.

상기의 합판 거푸집(22)은 내측과 외측으로 각각 설치되고 상부가 오픈되는구조로 형성되는데, 상기의 합판 거푸집(22)중 내측은 동바리(24)를 설치하여 지지하고 외측도 역시 지지 구조물(일반적인 기술사항이라 도면상 미도시)을 이용하여 지지하게 된다.The plywood formwork 22 is formed in a structure that is installed in the inner and outer sides, respectively, the top is open, the inner side of the plywood formwork 22 is installed by the support bar 24 and the outside is also a support structure (general It is supported by the technical matters (not shown in the drawings).

즉, 상기의 내측 합판 거푸집(22)의 설치가 완료되면 그 사이에 철근을 가공조립한 후 외측 합판 거푸집을 설치하고 콘크리트를 타설하여 지하 구조물(26)을 시공한다.That is, when the installation of the inner plywood formwork 22 is completed, the steel bars are processed and assembled thereafter, the outer plywood formwork is installed, and the concrete is poured to construct the underground structure 26.

상술한 구조로 지하 구조물을 시공하는 경우에는 동바리 및 내,외측 합판 거푸집을 설치하고 해체하는 작업의 번거로움이 있었고, 상기의 작업을 시행하는데 인건비가 과다하게 투입되는 문제점을 가졌다.In the case of constructing the underground structure with the above-described structure, there was the trouble of installing and dismantling the copper bar and the inner and outer plywood formwork, and the labor cost was excessively put into practice to perform the above work.

또한, 상기의 동바리 및 내,외측 합판 거푸집에 대한 철거 작업이 번거로운 관계로 공사기간이 장기간 소요되며, 특히 지하 구조물을 제작하는데 목재를 사용하는 경우 소모자재가 많이 발생되는 문제점을 가졌다.In addition, since the demolition work for the copper bar and the inner and outer plywood formwork is cumbersome, the construction takes a long time, in particular, when using wood to manufacture the underground structure had a problem that a lot of consumable materials are generated.

또한, 상기의 완성된 지하 구조물은 내,외측 합판 거푸집과 밀착되었던 콘크리트 표면이 거칠게 형성되어 지하 구조물의 완성 제품에 대한 품질이 저하되는 문제점을 가졌다.In addition, the finished underground structure has a problem that the concrete surface that is in close contact with the inner and outer plywood formwork is formed rough, the quality of the finished product of the underground structure is degraded.

본 발명은 상술한 문제점을 해결하기 위하여 안출된 것으로서, 본 발명은, 지하 구조물을 제작하는 경우 작업자들이 편리하고 안전하게 사용할 수 있도록 복합부재 판넬과 유압 잭을 이용한 거푸집 시스템을 구성하여 지하 구조물에 대한 설치 및 해체 작업이 용이하고, 상기의 지하 구조물에 대한 높이 조정과 폭 조정을할 수 있도록 거푸집 조정장치를 구성한 복합부재 판넬과 유압 잭을 이용한 지하 구조물 거푸집 시공법을 제공하는 것을 그 목적으로 한다.The present invention has been made in order to solve the above problems, the present invention, when manufacturing the underground structure to form a system using a composite member panel and a hydraulic jack so that workers can use conveniently and safely installed on the underground structure And it is an object of the present invention to provide a method of constructing the underground structure using a composite member panel and a hydraulic jack constituting the formwork adjusting device to facilitate the dismantling operation, the height adjustment and the width adjustment for the above-mentioned underground structure.

본 발명은 상술한 목적을 달성하기 위하여 안출된 것으로서, 본 발명은, 지하에 설치되어 공동구, 전선구 및 하수도로 이용되는 지하 구조물의 시공법에 있어서, 기초 콘크리트를 타설하고 그 상부에 거푸집 조정장치를 설치하되, 상기의 거푸집 조정장치는 하부 높이조정 유압 잭을 기초 콘크리트에 밀착시키고, 상기의 거푸집 조정장치는 조정 판넬을 작동하여 수평부 유압 잭, 수직부 유압 잭 및 사선부 유압 잭을 지하 구조물의 내측 너비 및 높이로 고정시키며, 상기의 거푸집 조정장치에는 일체로 결합되어 있는 수직 내부 보강재, 복합부재 사각 보강재 및 내측 복합부재 판넬을 수평부 유압 잭, 수직부 유압 잭 및 사선부 유압 잭의 그 끝단에 밀착시키고, 상기의 수직 내부 보강재와 내측 복합부재 판넬에는 직하부에 하부받침 고정틀을 설치하여 수직 내부 보강재와 내측 복합부재 판넬을 지지시키며, 상기의 내측 복합부재 판넬의 측면에 철근을 배근한 뒤 지하 구조물의 두께만큼 외측 복합부재 판넬을 이격하여 설치한 뒤 콘크리트를 타설하여 지하 구조물을 시공하고 자동으로 탈형하는 것을 특징으로 하는 복합부재 판넬과 유압 잭을 이용한 지하 구조물 시공법을 제공한다.The present invention has been made in order to achieve the above object, the present invention, in the construction method of the underground structure installed in the basement is used in the cavity, electric wire and sewer, the base concrete is poured and the formwork adjusting device is installed thereon However, the formwork adjuster is in close contact with the lower height-adjusting hydraulic jack to the foundation concrete, the formwork adjuster operates the adjustment panel to move the horizontal hydraulic jack, vertical hydraulic jack and oblique hydraulic jack to the inside of the underground structure Fixed in width and height, and the formwork adjusting device includes a vertical internal reinforcement, a composite member square reinforcement, and an inner composite member panel integrated at the ends of the horizontal hydraulic jack, the vertical hydraulic jack and the diagonal hydraulic jack. In close contact with the vertical internal reinforcement and the inner composite member panel, Supports the inner inner reinforcement and the inner composite panel, reinforces the side of the inner composite member panel, installs the outer composite member panel as the thickness of the underground structure and installs the underground structure by pouring concrete. It provides a method of underground structure construction using a composite member panel and a hydraulic jack characterized in that the demoulding automatically.

도 1은 일반적인 지하 구조물을 제작하는 시공법을 개략적으로 나타내는 도면.1 is a view schematically showing a construction method for manufacturing a general underground structure.

도 2는 본 발명의 지하 구조물을 제작하는 시공법을 개략적으로 나타내는 도면.2 is a view schematically showing a construction method for manufacturing the underground structure of the present invention.

도 3은 본 발명의 지하 구조물을 제작하는 시공법의 조립 개념도.3 is an assembly conceptual view of the construction method for manufacturing the underground structure of the present invention.

도 4는 본 발명의 지하 구조물을 제작하는 시공법의 분해 상태도.Figure 4 is an exploded state diagram of the construction method for manufacturing the underground structure of the present invention.

도 5는 본 발명의 지하 구조물을 제작하는 시공 순서도.5 is a construction flowchart of manufacturing the underground structure of the present invention.

< 도면의 주요 부분에 대한 부호의 간단한 설명 ><Brief description of symbols for the main parts of the drawings>

50 : 기초 콘크리트 52 : 거푸집 조정장치50: foundation concrete 52: formwork adjusting device

54 : 몸체 56 : 강관 파이프 조정틀54 body 56 steel pipe adjustment frame

58 : 이동식 바퀴 60 : 하부 높이조정 유압 잭58: movable wheel 60: lower height adjustment hydraulic jack

62 : 수평부 유압 잭 64 : 잭 고정판62: horizontal hydraulic jack 64: jack fixing plate

66 : 수직부 유압 잭 68 : 조정 베어링 받침판66: vertical hydraulic jack 68: adjustment bearing support plate

70 : 사선부 유압 잭 72 : 현치부 받침판70: diagonal hydraulic jack 72: the port portion support plate

74 : 수직 내부 보강재 76 : 복합부재 사각 보강재74: vertical internal reinforcement 76: composite member square reinforcement

78 : 내측 복합부재 판넬 80 : 외측 복합부재 판넬78: inner composite member panel 80: outer composite member panel

82 : 하부받침 고정틀 84 : 철근82: lower support fixing frame 84: reinforcing bars

86 : 지하 구조물86: underground structure

이하, 첨부 도면을 참조하여 본 발명의 구성과 작동 상태를 상세하게 설명한다.Hereinafter, with reference to the accompanying drawings will be described in detail the configuration and operation of the present invention.

도 2는 본 발명의 지하 구조물을 제작하는 시공법을 개략적으로 나타내는 도면이다.2 is a view schematically showing a construction method for manufacturing the underground structure of the present invention.

도 2에서 알 수 있는 바와 같이, 기초 콘크리트(50)를 타설한 후 상기의 기초 콘크리트(50)에는 그 상부에 거푸집 조정장치(52)가 설치되는데, 상기의 거푸집 조정장치(52)에는 내측 복합부재 판넬(78)을 결합시키고, 상기의 내측 복합부재 판넬(78)의 설치가 완료되면 그 일측에 철근을 가공조립한 후 외측 복합부재 판넬을 설치하고 상기의 내측 복합부재 판넬(78)과 외측 복합부재 판넬의 사이에 콘크리트를 타설하여 지하 구조물(86)을 시공한다.As can be seen in Figure 2, after pouring the foundation concrete 50, the formwork adjusting device 52 is installed in the upper part of the base concrete 50, the formwork adjusting device 52, the inner composite When the member panel 78 is coupled and the installation of the inner composite member panel 78 is completed, processing and assembling rebar on one side thereof, and then installing the outer composite member panel and the inner composite member panel 78 and the outer side Concrete is poured between the composite member panels to construct the underground structure 86.

이때 상기의 거푸집 조정장치(52)에는 수평, 수직 및 사선 방향으로 유압 잭이 형성된 관계로 내측 복합부재 판넬(78)을 지지한 상태에서 지하 구조물(86)을 제작할 수 있게 된다.At this time, in the formwork adjusting device 52, the underground structure 86 can be manufactured in a state in which the hydraulic jack is formed in the horizontal, vertical and oblique directions while supporting the inner composite member panel 78.

도 3은 본 발명의 지하 구조물을 제작하는 시공방법의 조립 개념도이다.3 is an assembly conceptual view of a construction method for manufacturing the underground structure of the present invention.

도 3에서 알 수 있는 바와 같이, 상기의 거푸집 조정장치(52)는 기초 콘크리트(50)가 타설된 그 상부에 설치되는데, 이때 상기의 거푸집 조정장치(52)에는 수평 및 수직 유압 잭의 그 끝단에 수직 내부 보강재(74)를 결합하게 된다.As can be seen in Figure 3, the formwork adjusting device 52 is installed on top of the base concrete 50 is poured, wherein the formwork adjusting device 52 is the end of the horizontal and vertical hydraulic jack The vertical inner stiffener 74 is coupled to.

상기의 수직 내부 보강재(74)에는 그 외측면에 내측 복합부재 판넬(78)이 밀착되고, 그 내측 복합부재 판넬(78)에는 콘크리트가 타설되어 지하 구조물(86)을 제작하게 된다. 도면상 외측 복합부재 판넬은 생략한 상태로 지하 구조물(86)을 제작하는 상태를 설명하였다.The inner composite member panel 78 is in close contact with the vertical inner reinforcement 74, the concrete is poured into the inner composite member panel 78 to produce the underground structure 86. The outer composite member panel in the drawings has been described a state of manufacturing the underground structure 86 in the omitted state.

도 4는 본 발명의 지하 구조물을 제작하는 시공방법의 분해 상태도로서, 상기의 거푸집 조정장치(52)는 크게, 몸체(54), 조정 판넬(도면상 미도시), 강관 파이프 조정틀(56), 이동식 바퀴(58), 하부 높이조정 유압 잭(60), 수평부 유압 잭(62), 수직부 유압 잭(66), 사선부 유압 잭(70), 수직 내부 보강재(74), 복합부재 사각 보강재(76), 내측 복합부재 판넬(78) 및 하부받침 고정틀(82)이 일체로 구성되고, 상기의 내측 복합부재 판넬(78)과 콘크리트 벽체의 두께만큼 일정한 거리를 유지하며 외측에 설치되는 외부 복합부재 판넬(80)로 구성된다.4 is an exploded state view of the construction method for manufacturing the underground structure of the present invention, the formwork adjusting device 52 is large, the body 54, the adjustment panel (not shown in the figure), steel pipe pipe adjusting frame 56 , Movable wheel 58, lower height adjustable hydraulic jack 60, horizontal hydraulic jack 62, vertical hydraulic jack 66, diagonal hydraulic jack 70, vertical internal reinforcement 74, composite member square The reinforcing member 76, the inner composite member panel 78 and the lower support fixing frame 82 is integrally formed, the outer composite member panel 78 and the outer which is installed on the outside while maintaining a constant distance as the thickness of the concrete wall It consists of a composite member panel (80).

상기의 거푸집 조정장치(52)는 몸체(54)에 조정 판넬(상기의 거푸집 조정장치(52)를 작동시키는 콘트롤 상자임; 도면상 미도시)과 강관 파이프 조정틀(56)이 형성되고, 상기의 몸체(54)에는 그 하부에 하부 높이조정 유압잭(60)이 형성되어 기초 콘크리트와 밀착지지되며, 상기의 강관 파이프 조정틀(56)에는 하부에 이동식 바퀴(58)가 설치된다.The formwork adjusting device 52 is an adjustment panel (control box for operating the formwork adjusting device 52 described above) and a steel pipe adjusting frame 56 are formed on the body 54, The body 54 of the lower height adjustment hydraulic jack 60 is formed in the lower portion is supported in close contact with the foundation concrete, the steel pipe pipe adjustment frame 56 is provided with a movable wheel 58 in the lower portion.

상기의 거푸집 조정장치(52)는 강관 파이프 조정틀(56)의 양측 수평면에 수평부 유압 잭(62)이 결합되고, 상기의 강관 파이프 조정틀(56)의 중앙부에 수직부 유압 잭(66)이 결합되며, 상기의 거푸집 조정장치(52)는 몸체(54)에 사선 방향으로 사선부 유압 잭(70)이 결합된다.In the formwork adjusting device 52, the horizontal hydraulic jack 62 is coupled to both horizontal surfaces of the steel pipe adjusting frame 56, and the vertical hydraulic jack 66 is located at the center of the steel pipe adjusting frame 56. It is coupled, the formwork adjusting device 52 is a diagonal hydraulic jack 70 is coupled to the body 54 in an oblique direction.

상기의 수평부 유압 잭(62)에는 그 끝단에 잭 고정판(64)이 설치되어 수직 내부 보강재와 밀착되며, 상기의 사선부 유압 잭(70)에는 그 끝단에 현치부 받침판(72)이 설치되어 수직 내부 보강재의 굴곡(winding part)된 부분에 밀착되며, 상기의 수직부 유압 잭(66)에는 그 끝단에 조정 베어링 받침판(68)이 설치되어 수직 내부 보강재와 밀착된다.The horizontal hydraulic jack 62 is provided with a jack fixing plate 64 at its end to be in close contact with the vertical internal reinforcement, and the diagonal hydraulic jack 70 is provided with a support base plate 72 at its end. It is in close contact with the winding (winding part) of the vertical internal reinforcement, the vertical hydraulic jack 66 is provided with an adjustment bearing support plate 68 at its end is in close contact with the vertical internal reinforcement.

즉, 상기의 수평부 유압 잭(62), 수직부 유압 잭(66) 및 사선부 유압 잭(70)의 각 끝단에 설치된 각 부재에는 수직 내부 보강재(74)가 밀착된다.That is, the vertical internal reinforcement 74 is in close contact with each member provided at each end of the horizontal hydraulic jack 62, the vertical hydraulic jack 66, and the diagonal hydraulic jack 70.

상기의 수직 내부 보강재(74)에는 그 외측면에 수직 내부 보강재와 90° 각도를 이루며 복합부재 사각 보강재(76)가 밀착되고, 상기의 복합부재 사각 보강재(76)에는 그 외측면에 내측 복합부재 판넬(78)이 밀착된다.The vertical inner stiffener 74 has a 90 ° angle with the vertical inner stiffener on its outer side, and the composite member square stiffener 76 is in close contact, and the composite member square stiffener 76 has an inner composite member on its outer side. The panel 78 is in close contact.

상기의 수직 내부 보강재(74), 복합부재 사각 보강재(76)와 내측 복합부재 판넬(78)은 볼팅되거나 리벳팅되는 구조로 고정되는데, 이때 상기의 내측 복합부재 판넬(78)에 홈이 형성되어 있어 리벳팅 작업을 진행하여도 내측 복합부재 판넬(78)과 리벳팅면이 평면을 이루도록 구성된다.The vertical inner reinforcement 74, the composite member square reinforcement 76 and the inner composite member panel 78 is fixed in a structure that is bolted or riveted, wherein a groove is formed in the inner composite member panel 78 There is also a riveting operation to the inner composite member panel 78 and the riveting surface is configured to form a plane.

상기의 수직 내부 보강재(74)와 복합부재 사각 보강재(76)는 복합부재인 섬유강화플라스틱(FRP)을 재질로 하여 제작되는 한편, 상기의 수직 내부 보강재(74)와 복합부재 사각 보강재(76)는 사각 단면 구조로 형성된 파이프를 사용한다.The vertical inner stiffener 74 and the composite member square stiffener 76 is made of a fiber-reinforced plastic (FRP) as a composite material, while the vertical inner stiffener 74 and the composite member square stiffener 76 Uses a pipe formed in a rectangular cross-sectional structure.

상기의 내측 복합부재 판넬(78)은 2개가 1조를 이루어 사용되는데, 상기의 내측 복합부재 판넬(78)은 대략적으로 "ㄱ"자 형상으로 형성되고 그 재질은 섬유강화 플라스틱을 사용하여 제작된다.The inner composite member panel 78 is used in a pair of two, the inner composite member panel 78 is formed in a substantially "b" shape and the material is made of fiber-reinforced plastic. .

즉, 상기의 수직 내부 보강재(74)와 내측 복합부재 판넬(78)은 같은 형태로 설치되고, 상기의 수직 내부 보강재(74)와 밀착되는 복합부재 사각 보강재(76)는 수직 내부 보강재(74)와 외측면에 90° 각도를 이루며 밀착고정된다.That is, the vertical inner stiffener 74 and the inner composite member panel 78 are installed in the same shape, the composite member square stiffener 76 in close contact with the vertical inner stiffener 74 is a vertical inner stiffener (74) It is fixed at a 90 ° angle to the outer surface.

상기의 거푸집 조정장치(52)는 수직 내부 보강재(74)와 내측 복합부재 판넬(78)의 그 양끝단을 하부받침 고정틀(82)로 고정시키는데, 이때 상기의 내측 복합부재 판넬(78)과 하부받침 고정틀(82)은 고정볼트로 체결된다.The formwork adjusting device 52 secures both ends of the vertical inner reinforcement 74 and the inner composite member panel 78 with the lower support fixing frame 82, wherein the inner composite member panel 78 and the lower portion thereof. The supporting frame 82 is fastened with fixing bolts.

상기의 거푸집 조정장치(52)는 내측 복합부재 판넬(78)이 고정된 상태에서 일정한 간격을 유지하며 외측 복합부재 특수틀(80)이 설치되는데, 상기의 내측 복합부재 판넬(78)과 외측 복합부재 판넬(80)이 설치된 그 사이에는 철근을 배근하고 콘크리트를 타설하게 된다.The formwork adjusting device 52 maintains a constant interval in the state in which the inner composite member panel 78 is fixed and the outer composite member special frame 80 is installed, and the inner composite member panel 78 and the outer composite The member panel 80 is installed between the reinforcing bars and placing concrete.

상기의 내측 복합부재 판넬(78)과 외측 복합부재 판넬(80)은 제작이 어려우나 시공이 간단하고 설치 및 해체가 용이하여 지하 구조물(86)을 제작하는데 소요되는 공기를 단축시킬 수 있게 된다.The inner composite member panel 78 and the outer composite member panel 80 is difficult to manufacture, but the construction is simple and easy to install and dismantle, it is possible to shorten the air required to manufacture the underground structure 86.

도 5는 본 발명의 지하 구조물을 제작하는 시공 순서도이다.5 is a construction flowchart of manufacturing the underground structure of the present invention.

첫째로, 지하 구조물을 제작하기위해 기초 콘크리트(50)를 타설하고 상기의 기초 콘크리트(50)의 상부에 거푸집 조정장치(52)를 설치한다.First, in order to manufacture the underground structure, the foundation concrete 50 is poured and the formwork adjusting device 52 is installed on the upper portion of the foundation concrete 50.

즉, 상기의 기초 콘크리트(50)에는 그 직상부에 거푸집 조정장치(52)를 설치하게 되는데, 상기의 거푸집 조정장치(52)는 하부 높이조정 유압 잭(60)을 이용하여 기초 콘크리트(50)의 상부에 고정한 뒤 수평부 유압 잭(62), 수직부 유압 잭(66) 및 사선부 유압 잭(70)을 제작하고자 하는 지하 구조물의 크기로 조정하고, 상기의 수평부 유압 잭(62), 수직부 유압 잭(66) 및 사선부 유압 잭(70)에는 그 끝단에 설치된 각 부재에 수직 내부 보강재(74), 복합부재 사각 보강재(76), 내측 복합부재 판넬(78)을 일체로 고정하게 된다.That is, the formwork adjusting device 52 is installed on the base concrete 50 directly above the formwork adjusting device 52, the formwork adjusting device 52 is the foundation concrete 50 by using the lower height adjustment hydraulic jack 60 After fixing the upper portion of the horizontal hydraulic jack 62, vertical hydraulic jack 66 and oblique hydraulic jack 70 to adjust the size of the underground structure to be made, the horizontal hydraulic jack 62, The vertical hydraulic jack 66 and the diagonal hydraulic jack 70 integrally fix the vertical internal reinforcement 74, the composite member square reinforcement 76, and the inner composite member panel 78 to each member installed at the ends thereof. do.

둘째로, 상기의 수직 내부 보강재(74)와 내측 복합부재 판넬(78)에는 그 직하부에 하부받침 고정틀(82)을 설치하여 고정하며, 상기의 내측 복합부재 판넬(78)과 일정한 거리를 유지하도록 외측 복합부재 판넬(80)을 기초 콘크리트(50)의 상부에 설치한다.Second, the vertical inner reinforcement 74 and the inner composite member panel 78 is installed and fixed to the lower support fixing frame 82 directly below it, and maintain a constant distance from the inner composite member panel 78 The outer composite member panel 80 is installed on the top of the base concrete 50 so as to.

즉, 상기의 내측 복합부재 판넬(78)과 외측 복합부재 판넬(80)에는 그 사이에 콘크리트를 타설할 수 있도록 콘크리트 두께만큼 일정한 거리를 유지하게 되는 것이다.That is, the inner composite member panel 78 and the outer composite member panel 80 is to maintain a certain distance by the thickness of the concrete so that the concrete can be placed therebetween.

셋째로, 상기의 내측 복합부재 판넬(78)과 외측 복합부재 판넬(80)에는 그 사이에 철근을 배근하고 콘크리트를 타설한 후 양생한다.Third, the inner composite member panel 78 and the outer composite member panel (80) is cured after reinforcing the reinforcement between them and poured concrete.

즉, 상기의 콘크리트 구조물인 지하 구조물은 스팀 양생이나 일반 양생을 실시하게 된다.That is, the underground structure, which is the concrete structure, performs steam curing or general curing.

넷째로, 상기의 지하 구조물에 대한 양생이 완료되면, 상기의 외측 복합부재 판넬(80)을 해체하고 상기의 거푸집 조정장치(52)의 수평부 유압 잭(62), 수직부 유압 잭(66) 및 사선부 유압 잭(70)을 내측으로 축소하여 지하 구조물(86)과 내측 복합부재 판넬(78)을 이탈시키며, 상기의 작업 후 바로 하부 높이조정 유압 잭(60)을 상부로 들어올려 기초 콘크리트(50)와 이격되게 한다.Fourth, when the curing of the underground structure is completed, the outer composite member panel 80 is dismantled and the horizontal hydraulic jack 62, vertical hydraulic jack 66 of the formwork adjusting device 52 And the diagonal hydraulic jack 70 is reduced inward to separate the underground structure 86 and the inner composite member panel 78, and immediately after the above operation, lifts the lower height-adjusting hydraulic jack 60 to the upper part of the base concrete. Spaced apart from (50).

다섯째로, 상기의 거푸집 조정장치(52)를 지하 구조물(50)의 내측에서 이동시켜 완전히 탈형한다.Fifth, the formwork adjusting device 52 is moved from the inside of the underground structure 50 to demould completely.

여섯째로, 상기의 거푸집 조정장치를 지하 구조물에서 탈형을 하면 지하 구조물(50)에 대한 시공이 완료된다.Sixth, when the mold adjusting device is demoulded from the underground structure, construction of the underground structure 50 is completed.

상술한 구성에 따른 지하 구조물(50)과 거푸집 조정장치(52)에 대한 제작 상태와 시공 순서를 설명한다.The manufacturing state and construction procedure for the underground structure 50 and the formwork adjusting device 52 according to the above-described configuration will be described.

상기의 지하 구조물(50)의 시공 순서를 설명하면, 기초 콘크리트(50)를 타설한 후 그 상부에 거푸집 조정장치(52)를 설치하고, 이때 상기의 거푸집 조정장치(52)는 하부 높이조정 유압 잭(60)을 기초 콘크리트(50)에 밀착되도록 고정하며, 또한 상기의 거푸집 조정장치(52)의 조정 판넬을 작동하여 수평부 유압 잭(62)의 길이를 제작하고자 하는 지하 구조물의 내측 너비로 고정하고 상기의 거푸집 조정장치(52)의 수직부 유압 잭(66)과 사선부 유압 잭(70)을 제작하고자 하는 지하 구조물의 내측 높이로 고정하며, 그로인해 상기의 거푸집 조정장치(52)는 일체로 결합되어 있는 수직 내부 보강재(74), 복합부재 사각 보강재(76) 및 내측 복합부재 판넬(78)을 지지할 수 있게 되고, 이때 상기의 수직 내부 보강재(74)와 내측 복합부재 판넬(78)에는 직하부에 하부받침 고정틀(82)을 설치하여 수직 내부 보강재(74)와 내측 복합부재 판넬(78)을 지지하게 된다.Referring to the construction procedure of the above-described underground structure 50, after the foundation concrete 50 is poured, the formwork adjusting device 52 is installed on the upper part, wherein the formwork adjusting device 52 is the lower height adjustment hydraulic pressure The jack 60 is fixed in close contact with the foundation concrete 50, and the control panel of the formwork adjusting device 52 is operated to the inner width of the underground structure to produce the length of the horizontal hydraulic jack 62. Fixing and fixing the vertical hydraulic jack 66 and the oblique hydraulic jack 70 of the formwork adjusting device 52 to the inner height of the underground structure to be manufactured, whereby the formwork adjusting device 52 is The vertical inner reinforcement 74, the composite member square reinforcement 76 and the inner composite member panel 78 can be supported integrally, wherein the vertical inner reinforcement 74 and the inner composite panel (78) ) Is directly below the lower support frame (82 ) To support the vertical inner reinforcement 74 and the inner composite panel (78).

또한, 상기의 작업이 완료되면 내측 복합부재 판넬(78)의 측면에 철근(84)을 배근한 뒤 지하 구조물(50)의 두께만큼 외측 복합부재 판넬(80)을 이격하여 설치한 뒤 콘크리트를 타설하여 지하 구조물(50)을 제작한다.In addition, when the above operation is completed, the reinforcing bar 84 is disposed on the side of the inner composite member panel 78 and the concrete is poured after installing the outer composite member panel 80 spaced apart by the thickness of the underground structure 50. To fabricate the underground structure (50).

상기의 콘크리트를 양생시 스팀 양생인 때에는 7일간 거푸집을 해체하지 않고 일반 양생인 때에는 15일간 거푸집을 해체하지 않으며, 콘크리트에 대한 양생이 완료되면 외측 복합부재 판넬(80)을 해체하고 하부 높이조정 유압 잭(60)을 기초 콘크리트(50)에서 상부로 들어올리며, 상기의 거푸집 조정장치(52)의 수평부 유압 잭(62), 수직부 유압 잭(66) 및 사선부 유압 잭(70)을 몸체(54)의 방향으로 이동시켜 내측 복합부재 판넬(78)을 지하 구조물(50)과 탈형하며, 상기의 작업후에 거푸집 조정장치(52)를 지하 구조물(50)의 내측에서 이동시키게 되면 지하 구조물(50)에 대한 시공이 완료된다.When curing the concrete, the steam curing is not dismantled formwork for 7 days, the general curing does not dismantle the form for 15 days, when curing of concrete is completed dismantle the outer composite member panel 80 and the lower height adjustment hydraulic The jack 60 is lifted upward from the foundation concrete 50, and the horizontal hydraulic jack 62, the vertical hydraulic jack 66, and the diagonal hydraulic jack 70 of the formwork adjusting device 52 are the body. The inner composite member panel 78 is demolished with the underground structure 50 by moving in the direction of 54, and after moving the formwork adjusting device 52 from the inside of the underground structure 50 after the above operation, the underground structure ( Construction for 50) is completed.

상기의 거푸집 조정장치(52)를 제작하는 순서는, 먼저 몸체(54)와 강관 파이프 조정틀(56)을 제작하고 이동식 바퀴(58)를 제작하며, 또한 상기의 몸체(54)의 하부에 결합되는 하부 높이조정 유압 잭(60)을 제작하고, 상기의 강관 파이프 조정틀(56)에 수평으로 결합되는 수평부 유압 잭(62)과 잭 고정판(64)을 제작하고, 또한 상기의 강관 파이프 조정틀(56)에 수직으로 결합되는 수직부 유압 잭(66)과 조정 베어링 받침판(68)을 제작하며, 또한 상기의 강관 파이프 조정틀(56)에 사선으로 결합되는 사선부 유압 잭(70)과 현치부 받침틀(72)을 제작하고, 또한 상기의 수평부 유압 잭(62), 수직부 유압 잭(66) 및 사선부 유압 잭(70)의 그 끝단에 각자 결합되는 부재에 밀착되는 수직 내부 보강재(74)를 제작하고 상기의 수직 내부 보강재(74)에 90° 각도로 밀착되는 복합부재 사각 보강재(76)를 제작하며, 또한 상기의 복합부재 사각 보강재(76)의 외측에 밀착되는 내측 복합부재 판넬(78)을 제작하고 상기 내측 복합부재 판넬(78)의 하부를 지지하는 하부 받침 고정틀(82)을 제작하며, 마지막으로 외측 복합부재 판넬(80)을 제작하게 된다.In order to manufacture the formwork adjusting device 52, first, the body 54 and the steel pipe adjustment frame 56 is manufactured, and the movable wheel 58 is manufactured, and also coupled to the lower portion of the body 54. The lower height adjustment hydraulic jack 60 is produced, the horizontal hydraulic jack 62 and the jack fixing plate 64 are horizontally coupled to the steel pipe pipe adjusting frame 56, and the steel pipe pipe adjustment described above. The vertical hydraulic jack 66 and the adjusting bearing support plate 68 are vertically coupled to the frame 56, and the diagonal hydraulic jack 70 is diagonally coupled to the steel pipe adjusting frame 56. Vertical internal reinforcement which manufactures the suspension support frame 72 and is in close contact with the members respectively coupled to the ends of the horizontal hydraulic jack 62, the vertical hydraulic jack 66 and the oblique hydraulic jack 70. (74) composite member square close to the vertical internal reinforcement (74) at a 90 ° angle The lower support fixing frame for manufacturing the steel material 76, and also to produce the inner composite member panel 78 in close contact with the outer side of the composite member square reinforcement 76 and to support the lower portion of the inner composite member panel 78 ( 82), and finally, the outer composite panel 80 is manufactured.

즉, 상기의 지하 구조물(50)은 거푸집 고정장치(52)에 의해 안전한 지하 구조물(50)을 시공할 수 있게 된다.That is, the basement structure 50 is able to construct a safe underground structure 50 by the formwork fixing device (52).

상술한 본 발명의 구성과 작동 상태에 따른 효과를 설명한다.Effects of the configuration and operation of the present invention described above will be described.

본 발명의 복합부재 판넬과 유압 잭을 이용한 지하 구조물 시공법은 종래와 다르게 거푸집을 복합부재인 섬유강화플라스틱(FRP)을 재질로 하여 제작하는 관계로 무게가 가볍고 설치 및 해체가 용이하며, 또한 상기의 지하 구조물을 시공시 거푸집 조정장치를 조정하여 자동으로 탈형하는 방식으로 거푸집 조정장치에 대한 조정이 용이할뿐 아니라 시공후 거푸집 조정장치에 대한 이동이 편리하여 작업의 효율성과 자동화를 얻을 수 있게 된다.Underground structure construction method using the composite member panel and the hydraulic jack of the present invention, unlike the prior art fabrication of the composite member made of fiber-reinforced plastic (FRP) as a material is light in weight, easy to install and dismantle, and also It is easy to adjust the formwork adjusting device by adjusting the formwork adjusting device automatically when constructing the underground structure, and it is easy to move the formwork adjusting device after construction to get the efficiency and automation of work.

또한, 상기의 지하 구조물 시공법은 거푸집을 유압 잭을 이용하는 장치로 제작한 관계로 자동 설치 및 자동 해체가 용이하게 구성됨과 동시에 그로인해 지하 구조물을 제작하는데 소요되는 공사비를 최대한 절감시킬 수 있고 완성된 지하 구조물을 하자가 없는 제품으로 제작할 수 있게 된다.In addition, the above-mentioned underground structure construction method is easy to automatically install and dismantle because the formwork is made of a device using a hydraulic jack, and at the same time it can reduce the construction cost required to manufacture the underground structure to the maximum, and the completed underground The structure can be manufactured as a defect-free product.

또한, 상기의 시공법에 의해 제작된 지하 구조물은 복합부재를 사용하는 관계로 강재 거푸집에 비하여 녹 발생이 전혀 없고 사용후 관리가 편리하며, 또한 목재 거푸집에 비하여 파손의 정도가 약하여 오랜 기간 사용할 수 있는 효과를 가진다.In addition, the underground structure manufactured by the above construction method has no rust generation, and is easy to manage after use, because it uses a composite member, and it is easy to manage after use. Has an effect.

또한, 상기의 지하 구조물 시공법은 강재 거푸집과 목재 거푸집을 이용하는 경우에 비하여 콘크리트를 타설후 탈형이 깨끗하게 이루어지는 관계로 복합부재 판넬에 박리제를 바르지 않고 사용할 수 있는 효과를 가진다.In addition, the construction method of the underground structure has an effect that can be used without applying a release agent to the composite member panel since the demoulding is clean after pouring concrete compared to the case of using steel formwork and wood formwork.

Claims (2)

지하에 설치되어 공동구, 전선구 및 하수도로 이용되는 지하 구조물의 시공법에 있어서, 기초 콘크리트(50)를 타설하고 그 상부에 거푸집 조정장치(52)를 설치하되, 상기의 거푸집 조정장치(52)는 하부 높이조정 유압 잭(60)을 기초 콘크리트(50)에 밀착시키고, 상기의 거푸집 조정장치(52)는 조정 판넬을 작동하여 수평부 유압 잭(62), 수직부 유압 잭(66) 및 사선부 유압 잭(70)을 지하 구조물의 내측 너비 및 높이로 고정시키며, 상기의 거푸집 조정장치(52)에는 일체로 결합되어 있는 수직 내부 보강재(74), 복합부재 사각 보강재(76) 및 내측 복합부재 판넬(78)을 수평부 유압 잭(62), 수직부 유압 잭(66) 및 사선부 유압 잭(70)의 그 끝단에 밀착시키고, 상기의 수직 내부 보강재(74)와 내측 복합부재 판넬(78)에는 직하부에 하부받침 고정틀(82)을 설치하여 수직 내부 보강재(74)와 내측 복합부재 판넬(78)을 지지시키며, 상기의 내측 복합부재 판넬(78)의 측면에 철근(84)을 배근한 뒤 지하 구조물(50)의 두께만큼 외측 복합부재 판넬(80)을 이격하여 설치한 뒤 콘크리트를 타설하여 지하 구조물(50)을 시공하고 자동으로 탈형하는 것을 특징으로 하는 복합부재 판넬과 유압 잭을 이용한 지하 구조물 시공법.In the construction method of the underground structure installed in the basement used in the cavity, electric wire and sewer, the foundation concrete 50 is poured and the formwork adjusting device 52 is installed on the upper part, but the formwork adjusting device 52 is the lower part. The height adjusting hydraulic jack 60 is brought into close contact with the foundation concrete 50, and the formwork adjusting device 52 operates the adjusting panel to operate the horizontal hydraulic jack 62, the vertical hydraulic jack 66 and the diagonal hydraulic. The jack 70 is fixed to the inner width and height of the underground structure, the formwork adjusting device 52 of the vertical internal reinforcement 74, composite member square reinforcement 76 and the inner composite panel ( 78) in close contact with the ends of the horizontal hydraulic jack 62, vertical hydraulic jack 66 and oblique hydraulic jack 70, the vertical inner reinforcement 74 and the inner composite member panel (78). Vertical internal reinforcement by installing lower support fixing frame 82 directly under Supporting the 74 and the inner composite panel (78), the reinforcing bars 84 to the side of the inner composite panel (78) and then the outer composite panel (80) by the thickness of the underground structure 50 After installing the spaced apart concrete to construct the underground structure 50, and underground structure construction method using a composite member panel and a hydraulic jack characterized in that the demoulding automatically. 제 1 항에 있어서, 상기의 거푸집 조정장치(52)는, 몸체(54)에 조정 판넬과 강관 파이프 조정틀(56)이 형성되고, 상기의 몸체(54)에는 그 하부에 하부 높이조정 유압잭(60)이 형성되며, 상기의 강관 파이프 조정틀(56)에는 하부에 이동식 바퀴(58)가 설치되고, 상기의 강관 파이프 조정틀(56)의 양측 수평면에 수평부 유압 잭(62)이 결합되며, 상기의 강관 파이프 조정틀(56)의 중앙부에 수직부 유압 잭(66)이 결합되고, 상기의 거푸집 조정장치(52)는 몸체(54)에 사선 방향으로 사선부 유압 잭(70)이 결합되며, 상기의 수평부 유압 잭(62)에는 그 끝단에 잭 고정판(64)이 설치되고 상기의 사선부 유압 잭(70)에는 그 끝단에 현치부 받침판(72)이 설치되며, 상기의 수직부 유압 잭(66)에는 그 끝단에 조정 베어링 받침판(68)이 설치되고, 상기의 수평부 유압 잭(62), 수직부 유압 잭(66) 및 사선부 유압 잭(70)의 각 끝단에 설치된 각 부재에는 수직 내부 보강재(74)가 밀착되며, 상기의 수직 내부 보강재(74)에는 그 외측면에 수직 내부 보강재와 90° 각도를 이루며 복합부재 사각 보강재(76)가 밀착되고, 상기의 복합부재 사각 보강재(76)에는 그 외측면에 내측 복합부재 판넬(78)이 밀착되며, 상기의 수직 내부 보강재(74), 복합부재 사각 보강재(76)와 내측 복합부재 판넬(78)은 리벳팅되고, 상기의 내측 복합부재 판넬(78)은 "ㄱ"자 형상으로 형성된 2개가 1조를 이루며, 상기의 수직 내부 보강재(74)와 내측 복합부재 판넬(78)는 그 양끝단을 하부받침 고정틀(82)로 고정되고 상기의 내측 복합부재 판넬(78)과 하부받침 고정틀(82)은 고정볼트로 체결되며, 상기의 내측 복합부재 판넬(78)에는 지하 구조물의 두께만큼 간격을 유지하며 외측 복합부재 특수틀(80)이 설치되는 구성인 것을 특징으로 하는 복합부재 판넬과 유압 잭을 이용한 지하 구조물 시공법.According to claim 1, wherein the formwork adjusting device 52, the adjustment panel and the steel pipe adjusting frame 56 is formed in the body 54, the lower height adjustment hydraulic jack (below) in the body 54 60 is formed, the steel pipe pipe adjusting frame 56 is provided with a movable wheel 58 at the bottom, the horizontal hydraulic jack 62 is coupled to both horizontal surfaces of the steel pipe pipe adjusting frame 56 above. , Vertical hydraulic jack 66 is coupled to the central portion of the steel pipe adjustment frame 56, the die adjusting device 52 is a diagonal hydraulic jack 70 is coupled to the body 54 in an oblique direction. The horizontal hydraulic jack 62 is provided with a jack fixing plate 64 at its end and the oblique hydraulic jack 70 is provided with a support base plate 72 at its end, and the vertical portion. The hydraulic jack 66 is provided with an adjustment bearing support plate 68 at the end thereof, and the horizontal hydraulic jack 62 and the vertical hydraulic jack 66 are provided. And a vertical internal reinforcement 74 is in close contact with each member installed at each end of the diagonal hydraulic jack 70, and the vertical internal reinforcement 74 forms a 90 ° angle with the vertical internal reinforcement at its outer surface. Square reinforcing member 76 is in close contact, the composite member rectangular reinforcing member 76 is in close contact with the inner composite member panel 78 on its outer surface, the vertical inner reinforcing member 74, the composite member rectangular reinforcing member 76 And the inner composite member panel 78 is riveted, the inner composite member panel 78 is formed of a pair of two formed in the "b" shape, the vertical inner stiffener 74 and the inner composite member panel 78 is fixed to both ends of the lower support frame 82, the inner composite member panel 78 and the lower support frame 82 is fastened with a fixing bolt, the inner composite member panel 78 Spaced by the thickness of the underground structure, the outer composite member special frame ( 80) is an underground structure construction method using a composite member panel and a hydraulic jack, characterized in that the configuration is installed.
KR10-2001-0028318A 2001-05-23 2001-05-23 The method for carrying out of underground structure object using a fiberglass reinforced plastics and a hydraulic jack KR100402436B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR10-2001-0028318A KR100402436B1 (en) 2001-05-23 2001-05-23 The method for carrying out of underground structure object using a fiberglass reinforced plastics and a hydraulic jack

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR10-2001-0028318A KR100402436B1 (en) 2001-05-23 2001-05-23 The method for carrying out of underground structure object using a fiberglass reinforced plastics and a hydraulic jack

Publications (2)

Publication Number Publication Date
KR20020089689A KR20020089689A (en) 2002-11-30
KR100402436B1 true KR100402436B1 (en) 2003-10-22

Family

ID=27706082

Family Applications (1)

Application Number Title Priority Date Filing Date
KR10-2001-0028318A KR100402436B1 (en) 2001-05-23 2001-05-23 The method for carrying out of underground structure object using a fiberglass reinforced plastics and a hydraulic jack

Country Status (1)

Country Link
KR (1) KR100402436B1 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040020279A (en) * 2002-08-30 2004-03-09 평산에스아이 주식회사 Mending method of concret underdrain using corrugated matter plate and structure thereof
KR100898812B1 (en) 2008-08-28 2009-05-22 주식회사 하이드로코리아 Atch tunnel structure construction method
CN110080299A (en) * 2019-05-10 2019-08-02 成都建工路桥建设有限公司 A kind of shallow embedding mountain tunnel open-cut engineering method

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103590379B (en) * 2013-11-25 2016-02-03 中国能源建设集团广东省电力设计研究院有限公司 The easy mounted-dismounted type tunnel mouth baffle device for water of electric power plant circulating water system and construction method thereof
CN106988339B (en) * 2017-03-23 2018-11-27 海门市帕源路桥建设有限公司 Sandy gravel stratum piping lane construction technology
CN107905254B (en) * 2017-11-16 2020-02-18 中铁四局集团有限公司 Construction method of comprehensive pipe gallery formwork supporting integrated hydraulic internal formwork trolley
CN111749270B (en) * 2020-05-25 2022-04-15 中铁隧道集团二处有限公司 Concrete pipe gallery internal mold positioning and demolding method
CN111749269A (en) * 2020-05-25 2020-10-09 中铁隧道集团二处有限公司 Method for carrying out pipe gallery lining construction by combining inner formwork with lifting trolley
CN111593763B (en) * 2020-06-01 2021-07-30 武汉雅思达科技有限公司 Fixing device for mounting underground pipe gallery and using method thereof
CN113431086B (en) * 2021-06-25 2022-08-19 中交路桥建设有限公司 Method for improving installation elevation precision of prefabricated pipe gallery
CN113846693B (en) * 2021-10-27 2023-02-28 中国十九冶集团有限公司 Construction method for pouring underground concrete comprehensive pipe gallery
CN113818483B (en) * 2021-10-27 2023-03-14 中国十九冶集团有限公司 A template system for utility tunnel concrete placement

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20040020279A (en) * 2002-08-30 2004-03-09 평산에스아이 주식회사 Mending method of concret underdrain using corrugated matter plate and structure thereof
KR100898812B1 (en) 2008-08-28 2009-05-22 주식회사 하이드로코리아 Atch tunnel structure construction method
CN110080299A (en) * 2019-05-10 2019-08-02 成都建工路桥建设有限公司 A kind of shallow embedding mountain tunnel open-cut engineering method

Also Published As

Publication number Publication date
KR20020089689A (en) 2002-11-30

Similar Documents

Publication Publication Date Title
KR100402436B1 (en) The method for carrying out of underground structure object using a fiberglass reinforced plastics and a hydraulic jack
KR101645462B1 (en) Precast crossing beam manufacturing method for bridge and precast crossing beam construction method for bridge
US20070276526A1 (en) Construction element form and method of fabricating same
KR101165563B1 (en) Variable steel formwork for precast concrete
KR101206517B1 (en) Mould system for manufacturing non-uniform precast concrete floor slab
CN112359962A (en) Method for manufacturing quick detachable and re-built assembled building unit
CN215907389U (en) A template structure for clear water concrete construction
CN114193611A (en) Construction forming method of assembly type bridge deck prefabricated member
KR100448221B1 (en) Movable Steel Form for Constructing Culvert and Continuous Constructing Method of Culvert Using the Same
CN209832015U (en) Dedicated superposed beam design mould subassembly
CN107060173B (en) Early demoulding construction method in clear-water concrete wafer board structure hole
CN112223496A (en) Simple mould for assembling building unit
CN112523243B (en) Caisson template
KR20220100474A (en) Slab constructing method for bridge
CN220433734U (en) A template system for construction of underground space concrete structure
CN111042549A (en) Method for building aluminum frame plastic formwork room
CN110185254A (en) A kind of Combined aluminum alloy template system and its application method
CN114351943B (en) Shaped steel mould large-section stiff fair-faced concrete column structure and construction method
CN114161550B (en) Prefabricated small box girder integral walking type template system
KR200184988Y1 (en) Establishment structure forming system using kicker block
KR20180049533A (en) Manufacturing method of precast P.S composite girder using support devices with ability of height adjustment
CN2061580U (en) Shuttering device for lifting removal form of box-type building member
CN111877749B (en) Integral lifting type elevator shaft template and elevator shaft template supporting method
CN217434607U (en) Assembling die of usefulness is pour to prefabricated post
CN109591163B (en) Prefabricated house unit mould and manufacturing method

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20110930

Year of fee payment: 9

LAPS Lapse due to unpaid annual fee