JPS6332164Y2 - - Google Patents

Info

Publication number
JPS6332164Y2
JPS6332164Y2 JP1983052564U JP5256483U JPS6332164Y2 JP S6332164 Y2 JPS6332164 Y2 JP S6332164Y2 JP 1983052564 U JP1983052564 U JP 1983052564U JP 5256483 U JP5256483 U JP 5256483U JP S6332164 Y2 JPS6332164 Y2 JP S6332164Y2
Authority
JP
Japan
Prior art keywords
foundation block
block
concrete
leg
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP1983052564U
Other languages
Japanese (ja)
Other versions
JPS59160603U (en
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed filed Critical
Priority to JP5256483U priority Critical patent/JPS59160603U/en
Publication of JPS59160603U publication Critical patent/JPS59160603U/en
Application granted granted Critical
Publication of JPS6332164Y2 publication Critical patent/JPS6332164Y2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Road Paving Structures (AREA)

Description

【考案の詳細な説明】 この考案は、例えば高架歩道の縁部に敷設する
コンクリート製の張出歩道ブロツクに関する。
[Detailed Description of the Invention] This invention relates to an overhanging walkway block made of concrete that is laid, for example, at the edge of an elevated walkway.

従来、用水路が縁を流れたり、田の中に通され
た道路の縁部に歩道を造成するのには用水路や田
の埋め立を行わなければならなかつた、しかし、
このような構造の歩道は、用水路や田を埋め立て
て造成を行うものであるため、手間と費用が多く
かかり、しかも用水路等が無用のものになる。
Traditionally, in order to create a sidewalk along the edge of a road that runs through an irrigation canal or into a rice field, it was necessary to fill in the irrigation canal or the rice field.
Since sidewalks with such a structure are created by reclaiming irrigation canals and rice fields, they require a lot of effort and expense, and moreover, the irrigation canals and the like become useless.

用水路、田等を埋め立てずに周囲より高く形成
された高架道路(車道)の縁部に歩道を張り出し
て造成する方法としては、従来、例えば第1図に
示す構造のものがある。先ず、現場において生コ
ンクリートを打設して形成される基礎ブロツクA
と、該基礎ブロツクAの上面に載置、固定される
コンクリート製の張出桟材Bと該張出桟材Bを前
記基礎ブロツクAの上面に載置、固定するために
前記基礎ブロツクAの上面に植設されたアンカ
ー・ボルトC,Dとから形成される。
BACKGROUND OF THE INVENTION Conventionally, there is a method of constructing a sidewalk by overhanging the edge of an elevated road (roadway) that is higher than the surrounding area without reclaiming irrigation canals, rice fields, etc., for example, there is a structure shown in FIG. First, foundation block A is formed by pouring fresh concrete on site.
and a concrete projecting beam B to be placed and fixed on the top surface of the foundation block A. It is formed from anchor bolts C and D planted on the top surface.

そして歩道Eを造成する場合を第2図とともに
次に述べる。
The case of creating sidewalk E will be described below with reference to Figure 2.

先ず、車道Fの縁部の土を掘削して断面略L字
状の掘削部Gを形成する。次にこの掘削部Gに生
コンクリートを打設してベース・コンクリートH
を形成する。その後、ベース・コンクリートHの
上に型枠J1,J2を対向して配置し、この型枠J1
J2内に主筋Kを数本、連続して配筋し、さらにこ
の数本の主筋Kに直交して配力筋Lを略等間毎に
配列して配筋作業を行う。その後、張出桟材Bを
固定するためのアンカー・ボルトC,Dを計測し
て植設してから、型枠J1,J2の間に生コンクリー
トNを連続して打設、固化させることにより、養
生後、連続した基礎ブロツクAを形成していた。
それから、張出桟材Bの基部bに予め設けた数個
のボルト挿通孔O,P内に基礎ブロツクAに位置
めした後の前記アンカー・ボルトC,Dを挿通し
該ボルト挿通孔O,P内にモルタルQを打設、固
化する。そして、このアンカー・ボルトC,Dに
座金を介してナツトを螺合させることにより基礎
ブロツクAの上面に張出桟材Bを固定する。さら
に張出桟材Bの一側の表面部と、掘削部Gに埋め
戻した土とにアスフアルトR,Zを舗装して歩道
Eを造成する。
First, the soil at the edge of the roadway F is excavated to form an excavated portion G having a substantially L-shaped cross section. Next, pour ready-mixed concrete into this excavated portion G to create base concrete H.
form. Thereafter, the formwork J 1 and J 2 are placed facing each other on the base concrete H, and the formwork J 1 ,
Reinforcement work is performed by arranging several main reinforcements K in succession within J2 , and then arranging distribution reinforcements L at approximately equal intervals perpendicular to these several main reinforcements K. After that, anchor bolts C and D for fixing the overhanging beam B are measured and installed, and fresh concrete N is continuously poured and hardened between formworks J 1 and J 2 . As a result, a continuous basic block A was formed after curing.
Then, the anchor bolts C and D, which have been positioned on the foundation block A, are inserted into several bolt insertion holes O and P previously provided in the base b of the overhanging beam B, and the bolts C and D are inserted into the bolt insertion holes O and P, respectively. Place mortar Q inside P and harden it. Then, the overhanging beam B is fixed to the upper surface of the foundation block A by screwing nuts onto the anchor bolts C and D through washers. Furthermore, a sidewalk E is created by paving the surface of one side of the overhanging beam B and the soil backfilled in the excavated portion G with asphalt R and Z.

しかし上記従来品は、基礎ブロツクAを形成す
るのに現場で組立てた型枠J1,J2内に生コンクリ
ートNを打設し、再び型枠J1,J2を取外さなけれ
ばならないので手間と費用とがかかる。また連続
して基礎ブロツクAを構造的に補強するために主
筋Kおよび之に直交して配置される配力筋Lとの
夫々の敷設位置を計測して敷設しなければならな
いので配筋作業に手間がかかつていた。同様に、
アンカー・ボルトC,Dの取付位置出しも継続し
てから行わなければならないので手間がかかる。
However, in the conventional product described above, in order to form the foundation block A, it is necessary to pour fresh concrete N into the formworks J 1 and J 2 assembled on site, and then remove the formworks J 1 and J 2 again. It takes time and money. In addition, in order to continuously reinforce the foundation block A structurally, it is necessary to measure and lay the respective installation positions of the main reinforcement K and the distribution reinforcement L placed perpendicularly to the main reinforcement K, so it is necessary to install reinforcement It was time consuming. Similarly,
The installation position of the anchor bolts C and D has to be determined continuously, which is time-consuming.

さらには、連続してしかも均一にコンクリート
打ちを行わなければならないので手間がかかつて
いた。このように上記従来品は、歩道Eを造成す
るのに工期が長くなる欠点があつた。従つて、交
通量が多い場所でも迅速に工事が行えなかつた。
Furthermore, it was time-consuming because concrete had to be poured continuously and uniformly. As described above, the conventional product described above has the disadvantage that it takes a long time to construct the sidewalk E. Therefore, construction work could not be carried out quickly even in areas with heavy traffic.

また、基礎ブロツクA内でアンカー・ボルト
C,Dの取付位置がばらつきを生ずるため、張出
桟材B相互の間隔が手元と数百m先に置かれたも
のとでは内側(車道側)と外側(歩道側)とで不
揃になり、車道に沿つて正確に歩道の造成を行う
ことはできなかつた。特にカーブに沿そつて歩道
Eを造成する場合に型枠J1,J2の敷設と、アンカ
ー・ボルトC,D、主筋K、配力筋L等の敷設と
位置決め作業が難かしかつた。
In addition, because the installation positions of anchor bolts C and D vary within foundation block A, the distance between projecting beams B may differ between the one placed at hand and the one placed several hundred meters away from the inside (roadside side). The outside (sidewalk side) was uneven, and it was not possible to create a sidewalk accurately along the road. Particularly when constructing sidewalk E along a curve, it was difficult to lay formwork J 1 and J 2 , and to lay and position anchor bolts C, D, main reinforcement K, distribution reinforcement L, etc. .

また基礎ブロツクA、張出桟材Bがコンクリー
ト製で重量が重くなり、基礎ブロツクAに対して
張出桟材Bが外側に張出すことによつて基礎ブロ
ツクAの上部一側に張出桟材Bの荷重がかかつて
不安定な恰好になるうえ、基礎ブロツクAは掘削
部Gに固定されない構造であるから水分を多く含
んで地盤が緩んだり、または土圧、自動車の振
動、地震等の外力が加わつたり、打設、固化され
る生コンクリートが膨張する等の内部応力が加わ
ると基礎ブロツクA、および張出桟材Bがすべり
を生じて傾く等の構造的に弱い欠点があつた。
In addition, since foundation block A and overhanging block B are made of concrete, they are heavy, and as overhanging block B protrudes outward from foundation block A, the overhanging block is placed on one side of the upper part of foundation block A. The load on material B becomes unstable, and since the foundation block A is not fixed to the excavated part G, the ground may become loose due to high moisture content, or may be affected by earth pressure, vibrations from automobiles, earthquakes, etc. There were structural weaknesses such as foundation block A and overhanging beam B slipping and leaning when external force is applied or internal stress is applied such as expansion of fresh concrete that is poured and hardened. .

本考案は上述の如き点に鑑みてなされたもので
あり、その目的とするところは、基礎ブロツク自
体をラーメン構造に形成して構造堅牢になし、ま
た基礎ブロツクに対する主筋の配筋作業が対向す
る脚材部間において所定位置に迅速且つ確実に行
え、しかも特別な型枠を要せずに対向する脚材部
と該脚材部間を結合する連結部材とにより囲まれ
掘削部に略全域が開口された基礎ブロツクの空間
部内に生コンクリートを打設、固化することによ
り、生コンクリートの掘削部に対する接地面積を
増大して基礎ブロツクを土圧、自動車の振動等の
外力を受けたり生コンクリートが養生、固化する
時に膨張する等の内部応力に対してすべりを生ず
ることなく強固に基礎ブロツクを掘削部に固定で
きるとともに脚材部間に必要に応じて打設後の生
コンクリートに含まれる余分な水分や車道面に溜
まる雨等の余分な水分を路肩に排水するようにし
て基礎ブロツクが水による侵食を受けたり、ひび
割れるのを防止するとともに掘削部の地盤が余分
な水分を含んで弛むのを防止して保守、管理を良
好になし、さらにはアンカー・ボルトを植設する
手間と、之に要する位置決め作業と、基礎ブロツ
クに対する張出桟部の取付作業が省略化されて狭
い場所において広い所望幅の造成が直線および曲
線を問わず自由に行える張出歩道ブロツクを提供
するのにある。
The present invention was developed in view of the above points, and its purpose is to form the foundation block itself into a rigid frame structure to make the structure robust, and to make the reinforcement work of the main reinforcement opposite to the foundation block. It can be quickly and reliably moved to a predetermined position between the leg parts, and does not require a special formwork, and is surrounded by the opposing leg parts and the connecting member that connects the leg parts, so that almost the entire area is covered in the excavation part. By pouring fresh concrete into the opened space of the foundation block and hardening it, the ground contact area of the fresh concrete with the excavated area is increased, and the foundation block is not exposed to external forces such as earth pressure and vibrations from automobiles, and the fresh concrete is The foundation block can be firmly fixed to the excavated part without slipping due to internal stresses such as expansion during curing and solidification, and if necessary, excess material contained in the ready-mixed concrete after pouring can be removed between the leg parts. By draining water and excess moisture such as rain that accumulates on the roadway surface to the road shoulder, it prevents the foundation blocks from being eroded by water and cracking, and also prevents the ground at the excavated area from loosening due to excess moisture. In addition, the trouble of installing anchor bolts, the positioning work required for this, and the work of attaching the projecting crosspiece to the foundation block are omitted, making it suitable for use in narrow spaces. To provide an overhanging sidewalk block whose width can be freely constructed regardless of whether it is straight or curved.

以下本考案の一実施例を第3図乃至第8図に従
つて説明する。
An embodiment of the present invention will be described below with reference to FIGS. 3 to 8.

1は例えばその縁部に用水路が流れたり、田の
中に通される等、高架に造成された車道、2はこ
の車道1の縁部の高架な位置に造成されるべき歩
道である。3は歩道2を造成する際に車道1の縁
部の土を掘削して形成される断面略L字状の掘削
部である。4はコンクリート製の基礎ブロツク
で、この基礎ブロツク4は対向した脚材部5,6
間と、該脚材部5,6間を結合する2本の連結部
材7,7とにより全体がラーメン構造を呈して対
向する脚材部5,6と連結部材7,7とにより囲
まれて掘削部3に略全域にわたつて開口する開口
部を下面に有した捨型枠としての空間部4aと、
さらに該基礎ブロツク4の上部外側に張出された
表板部9とから形成される。
Reference numeral 1 designates an elevated roadway with an irrigation canal flowing along its edge or a path through a rice field, and reference numeral 2 designates a sidewalk to be constructed at an elevated position on the edge of the roadway 1. Reference numeral 3 denotes an excavated portion having a substantially L-shaped cross section, which is formed by excavating the soil at the edge of the roadway 1 when constructing the sidewalk 2. 4 is a concrete foundation block, and this foundation block 4 has opposed leg parts 5 and 6.
and the two connecting members 7, 7 that connect the leg parts 5, 6, the whole exhibits a rigid frame structure, and is surrounded by the opposing leg parts 5, 6 and the connecting members 7, 7. a space portion 4a serving as a waste formwork having an opening on the lower surface that opens over substantially the entire area of the excavation portion 3;
Furthermore, it is formed from a top plate part 9 extending outward from the upper part of the foundation block 4.

7aはこの連結部材7,7の対向位置に数段、
数列に設けられた挿入孔で、この挿入孔7aは相
互に軸長方向において一致して主筋8が挿入され
る。この挿入孔7aの個数は図面に示すものに限
られず複数個である。また前記脚材部5,6のう
ち控側(車道側)の脚材部5は他方の脚材部6よ
りも肉厚で重量が増大することにより傾倒するこ
となく安定化している。9は表板部で、この表板
部9は前記基礎ブロツク4の上部外側に張出され
た2本の張出桟材部9A,9Aの上面に直角的に
形成される。またこの表板部9の長手方向の端縁
には基礎ブロツク4相互が接続された時に第8図
に示すように断面略三角形に衝合自在となるよう
な下向きの斜面部9Bに形成されている。10は
地覆で、この地覆10は前記表板部9の外縁、上
面にモルタルおよびアンカー・ボルト等を用いて
接着、固化される。またこの地覆10は通常はコ
ンクリートで形成されるが、図面には示さないが
その内部を必要に応じて空胴化させて軽量にす
る。9Cは前記表板部9の上面、外縁に設けた位
置決め用の突条で、この突条9Cに前記地覆10
の下面に設けた凹部10Aが嵌合されることによ
り表板部9に対する地覆10の取付の位置決めが
行われる。6A,9Dは前記表板部9、および路
肩に面して前記脚材部6に適宜数個、設けられた
ノツク・アウト式(薄肉の凹欠部となしていて使
用時に必要に応じて打抜くもの)の水抜孔であ
り、このうち水抜孔6Aは脚材部5,6間に打
設、固化される後記生コンクリート18を打設後
に、生コンクリート18に含まれる余分な水分や
車道1の上面に溜まる余分な水分を路肩に排水す
るものである。11は2本の前記連結部材7,7
と前記脚材部5との上面にかけて形成された段差
である。10Bは前記地覆10に設けられた取付
穴で、この取付穴10Bはその内部に支柱12の
下端を挿入してコンクリートを充填、固化するこ
とによりガイド棚13を立設する。14はガイド
レール、15はその支柱である。
7a has several stages at opposing positions of the connecting members 7, 7,
The insertion holes 7a are provided in several rows, and the main reinforcing bars 8 are inserted into the insertion holes 7a, which coincide with each other in the axial direction. The number of insertion holes 7a is not limited to those shown in the drawings, but is plural. Further, among the leg parts 5 and 6, the leg part 5 on the rear side (roadway side) is thicker and heavier than the other leg part 6, so that it is stabilized without being tilted. Reference numeral 9 denotes a top plate portion, and this top plate portion 9 is formed perpendicularly to the upper surfaces of two projecting beam portions 9A, 9A projecting to the outside of the upper portion of the foundation block 4. Further, the longitudinal edge of this top plate part 9 is formed with a downward slope part 9B which can freely collide with a substantially triangular cross section as shown in FIG. 8 when the foundation blocks 4 are connected to each other. There is. Reference numeral 10 denotes a ground covering, and this ground covering 10 is adhered and solidified to the outer edge and upper surface of the top plate portion 9 using mortar, anchor bolts, and the like. Further, although this ground cover 10 is usually formed of concrete, the inside thereof may be hollowed out as necessary to make it lightweight, although it is not shown in the drawings. Reference numeral 9C denotes a positioning protrusion provided on the outer edge of the top surface of the top plate portion 9, and the ground cover 10 is attached to this protrusion 9C.
By fitting into the recessed portion 10A provided on the lower surface of the base plate 1, the mounting position of the ground cover 10 to the top plate portion 9 is determined. Numerals 6A and 9D are knock-out type (thin-walled recesses) provided on the top plate portion 9 and the leg portion 6 facing the road shoulder. Among these, the drain hole 6A is a drainage hole for removing excess water contained in the fresh concrete 18 and the roadway 1 after pouring the fresh concrete 18 that is poured and hardened between the leg parts 5 and 6. This is to drain excess moisture that accumulates on the top surface of the road to the roadside. 11 is the two connecting members 7, 7
This is a step formed over the upper surface of the leg portion 5 and the leg portion 5. Reference numeral 10B denotes a mounting hole provided in the ground cover 10, into which the guide shelf 13 is erected by inserting the lower end of the support column 12 and filling and solidifying concrete. 14 is a guide rail, and 15 is a support thereof.

本考案の一実施例は上述のような構成からな
り、歩道2を造成するのには、先ず車道1の縁部
に断面略L字状の掘削部3を形成する。次に掘削
部3にベースコンクリート16を打設して車道1
に沿つて多数の基礎ブロツク4を並設する。この
場合、基礎ブロツク4の控側(車道側)の脚材部
5は他方(歩道側)の脚材部6よりも肉厚で重い
から、基礎ブロツク4の上部一側に設けた表板部
9および張出桟部9A,9Aの重量がかかつても
不安定になつて掘削部3から基礎ブロツク4が転
げ落ちることはない。また隣接する基礎ブロツク
4の表板部9の長手方向の端縁に形成された斜面
部9Bは下向きに形成されて基礎ブロツク4相互
が接続された際に第8図に示すように断面略三角
形を呈するように衝合自在に形成されたモルタル
M、コンクリート等の接合剤との接触面積が大き
くなつて流れ落ちないようにして形成されている
ため、カーブに沿つて並設した表板部9が外側に
おいて開いてもモルタルMが漏れ落ちることがな
い。その後、対向した脚材部5,6間の連結部材
7,7に数段、数列に穿設した複数個の挿入孔7
a内に主筋8を夫々、挿入することによつて並設
した基礎ブロツク4の脚材部5,6間に数本の主
筋8を配筋する。この場合、並配した基礎ブロツ
ク4の連結部材7,7には数段、数列に挿入孔7
aが設けられているから主筋8は自然に位置決め
されて対向した脚材部5,6間の所定位置に配筋
される。そして、並設した各基礎ブロツク4の脚
材部5,6間に生コンクリート18を連続して打
設すると生コンクリート18は対向する脚材部
5,6と該脚材部5,6を結合した連結した連結
部材7,7とによつて囲まれ下面が略全域に亘つ
て開口されて掘削部3に対する接地面積が大きな
空間部4a内を通じて掘削部3に注入されること
により掘削部3に基礎ブロツク4を強固に固定さ
せる。従つて基礎ブロツク4は土圧を受けたり、
自動車の走行時の振動、地震等の外力を受けた
り、また生コンクリート18が養生、固化する時
に膨張する等の内部応力を受けた場合に、掘削部
3にすべりを生ずることなく強固に固定できる。
しかも主筋8の筋作業は、基礎ブロツク4の脚材
部5,6を結合する連結部材7,7の対向位置に
穿設された複数の挿入孔7a内に挿入されて容易
に位置決めされて脚材部5,6間を結合する連結
部材7,7に支持されて脚材部5,6間に規則正
しく配筋されるとともに之に直交した連結部材
7,7が対向する脚材部5,6間を結合してラー
メン構造を呈することにより、生コンクリート1
8が打設、固化されるから基礎ブロツク4は連続
した状態で強固に接続される。それから掘削部3
を土19で埋め戻し、そして表板部9の外縁、上
面に沿つてモルタル、コンクリート等を用いて地
覆10を固定する。この場合、表板部9の上面、
外縁には突条9Cが形成されているから、この突
条9Cが地覆10の下面に設けた凹部10A内に
嵌合されることにより表板部9に地覆10は固定
される。また掘削部3中に含まれる水分の量が多
く含まれて緩い地盤であつたり、車道1上に雨水
等の水が溜り易かつたり、対向する脚材部5,6
間に打設、固化される生コンクリート18の水分
の含有量が必要量以上に多い場合には、必要に応
じて薄肉部を打抜くことによりノツク・アウト式
の数個の水抜孔6Aを形成することによつて、こ
の水抜孔6Aから車道1の上面に溜る水分や脚材
部5,6間に打設、固化される生コンクリート1
8中の水分を抜く。この結果、基礎ブロツク4が
水によつて侵食されるのを防止したり、ひび割れ
が促進されるのを防止するとともに車道1に溜る
雨水等の水分を路肩に流すことによつて掘削部3
に必要以上の水分が含まれて地盤が緩むのを防止
する。
One embodiment of the present invention has the above-mentioned configuration, and in order to create the sidewalk 2, first an excavation portion 3 having a substantially L-shaped cross section is formed at the edge of the roadway 1. Next, base concrete 16 is poured into the excavated portion 3 and the roadway 1 is
A large number of foundation blocks 4 are arranged in parallel along the road. In this case, since the leg part 5 on the rear side (roadway side) of the foundation block 4 is thicker and heavier than the leg part 6 on the other side (sidewalk side), the top plate part provided on one side of the upper part of the foundation block 4 9 and the overhanging crosspieces 9A, 9A will not become unstable and the foundation block 4 will not fall down from the excavation part 3. Further, the slope portion 9B formed at the longitudinal edge of the top plate portion 9 of the adjacent foundation block 4 is formed downward, so that when the foundation blocks 4 are connected to each other, the cross section becomes approximately triangular as shown in FIG. The mortar M is formed so that it can collide freely so that the contact area with the bonding agent such as concrete is increased and the surface plate portions 9 arranged in parallel along the curve are formed so that they do not flow off. Even if it is opened on the outside, the mortar M will not leak out. After that, a plurality of insertion holes 7 are drilled in several stages and rows in the connecting members 7, 7 between the opposing leg parts 5, 6.
Several main reinforcements 8 are arranged between the leg portions 5 and 6 of the foundation blocks 4 arranged in parallel by inserting the main reinforcements 8 into the sections a. In this case, the connecting members 7, 7 of the foundation blocks 4 arranged in parallel have insertion holes 7 in several stages and rows.
Since the main reinforcing bars 8 are provided, the main reinforcing bars 8 are naturally positioned and placed at predetermined positions between the opposing leg parts 5 and 6. Then, when fresh concrete 18 is poured continuously between the leg parts 5 and 6 of each foundation block 4 installed in parallel, the ready-mixed concrete 18 connects the opposing leg parts 5 and 6 to the leg parts 5 and 6. The water is injected into the excavated part 3 through the space 4a, which is surrounded by the connected connecting members 7, 7, whose lower surface is opened over almost the entire area, and has a large ground contact area with the excavated part 3. The foundation block 4 is firmly fixed. Therefore, the foundation block 4 is subjected to earth pressure,
It can be firmly fixed to the excavated part 3 without slipping when subjected to external forces such as vibrations and earthquakes when a car is running, or when subjected to internal stress such as expansion of fresh concrete 18 when curing and solidifying. .
Moreover, the main reinforcement 8 can be easily positioned by being inserted into a plurality of insertion holes 7a bored at opposing positions of the connecting members 7, 7 that connect the leg parts 5, 6 of the foundation block 4. The leg parts 5, 6 are supported by the connecting members 7, 7 that connect the material parts 5, 6, and are reinforced regularly between the leg parts 5, 6, and the connecting members 7, 7 orthogonal thereto face each other. By connecting the spaces and creating a rigid frame structure, ready-mixed concrete 1
8 is poured and solidified, so that the foundation blocks 4 are firmly connected in a continuous state. Then excavation part 3
is backfilled with soil 19, and a ground cover 10 is fixed along the outer edge and upper surface of the top plate portion 9 using mortar, concrete, or the like. In this case, the upper surface of the top plate portion 9,
Since the ridge 9C is formed on the outer edge, the ridge 9C is fitted into the recess 10A provided on the lower surface of the ground cover 10, thereby fixing the ground cover 10 to the top plate portion 9. In addition, the ground may be loose due to a large amount of water contained in the excavated portion 3, or water such as rainwater may easily accumulate on the roadway 1, or the opposing leg portions 5 and 6
If the moisture content of the fresh concrete 18 that is poured and hardened during the process is higher than the required amount, several knock-out type drainage holes 6A are formed by punching out the thin walled parts as necessary. By doing so, moisture that collects on the upper surface of the roadway 1 through this drainage hole 6A and the fresh concrete 1 that is poured and hardened between the leg parts 5 and 6 are removed.
8 Remove the moisture. As a result, the foundation block 4 is prevented from being eroded by water, cracks are prevented from being accelerated, and moisture such as rainwater accumulated on the roadway 1 is drained to the road shoulder, thereby preventing the excavated portion 3 from being eroded by water.
Prevent the soil from loosening due to excessive moisture content.

また歩道2上に溜る水も、水抜孔9Dを打抜く
ことによつて水抜きが行える。
Also, water that accumulates on the sidewalk 2 can be drained by punching out the drain holes 9D.

その後、歩道2と車道1とに段差がある、いわ
ゆるマウンド・アツプ式の場合には地覆10から
一定距離、離れた位置に縁石191を並設し、そ
の後、表板部9の上面から縁石191までアスフ
アルト20を舗装し、そして地覆10の取付穴1
0B内にガイド棚13の支柱12の下端を挿入後
に生コンクリートを充填、固化することにより支
柱12を立設してガイド棚13を形成して歩道2
を造成する。また、車道1側の埋め戻した土19
の上面にアスフアルト21を舗装して車道1を造
成する。(第6図参照)。
After that, in the case of a so-called mound up type where there is a step between the sidewalk 2 and the roadway 1, curb stones 191 are installed in parallel at a certain distance from the ground cover 10, and then Pave asphalt 20 up to the curb 19 1 , and install the mounting hole 1 of the ground covering 10.
After inserting the lower end of the pillar 12 of the guide shelf 13 into 0B, the pillar 12 is erected by filling fresh concrete and solidifying it to form the guide shelf 13, and the sidewalk 2
Create. In addition, the backfilled soil 19 on the road 1 side
Pave asphalt 21 on the top surface to create roadway 1. (See Figure 6).

また歩道2と車道1とがフラツトないわゆるフ
ラツト式の歩道2を造成する場合には、前述の生
コンクリート18を打設する際に地覆10から一
定距離、離れた位置に支柱15の下端を挿入して
立設することにより車道1側のガイド棚14を形
成し、そして地覆10の取付穴10B内にガイド
棚13の支柱12の下端を挿入して生コンクリー
トを充填することにより歩道1側のガイド棚13
を形成する。その後、表面板9の上面から埋め戻
した土19の上面にアスフアルト20を舗装する
ことにより歩道2と車道1とを造成する。
Furthermore, when constructing a so-called flat type sidewalk 2 in which the sidewalk 2 and the roadway 1 are flat, the lower ends of the supports 15 are placed a certain distance away from the ground cover 10 when pouring the fresh concrete 18 mentioned above. The guide shelf 14 on the roadway 1 side is formed by inserting and erecting it, and the lower end of the support column 12 of the guide shelf 13 is inserted into the mounting hole 10B of the ground covering 10 and filled with ready-mixed concrete, thereby forming the sidewalk 1. Side guide shelf 13
form. Thereafter, a sidewalk 2 and a roadway 1 are created by paving asphalt 20 on the top surface of the soil 19 that has been backfilled from the top surface of the surface board 9.

なお上記実施例の基礎ブロツク4では脚材部6
の上方、外側に表板部9を一体に形成しているけ
れども、脚材部6の外側に張出桟部9A,9Aを
数本、設けていれば表板部9を基礎ブロツク4と
別体に設けることにより張出桟部9A,9Aの上
面に表板部9を固定するものであつてもよい。
In addition, in the basic block 4 of the above embodiment, the leg portion 6
Although the top plate part 9 is integrally formed on the upper and outer side, if several projecting crosspieces 9A, 9A are provided on the outside of the leg part 6, the top plate part 9 can be separated from the foundation block 4. The top plate portion 9 may be fixed to the upper surface of the projecting crosspiece portions 9A, 9A by being provided on the body.

第9図および第10図は本考案の他の実施例を
示したものであり、この実施例においては対向し
た脚材部5,6間に連結した連結部材7,7を脚
材部5,6の側面と平行に形成したことにより隣
接する基礎ブロツク4相互の連結部材7,7を接
触するようにして基礎ブロツク4相互の位置決め
作業を容易に行い前記連結部材7,7の対向位置
に設けた数個の挿入孔7a内に主筋8を挿入する
ことにより主筋8を自然に捨型枠としての脚材部
5,6間に正確に位置決めして配筋作業を能率良
く行う点は前記実施例と同様であるが、この実施
例においては連結部材7に設けられた挿入孔7a
内に必要本数の主筋8を挿入して脚材部5,6間
に配筋を行うほか、この挿入孔7aを利用してボ
ルトナツト30を用いて隣接する基礎ブロツク4
相互を連続的に堅牢に結合するようにした点が前
記第1実施例と異なる。
9 and 10 show another embodiment of the present invention. In this embodiment, the connecting members 7, 7 connected between the opposing leg parts 5, 6 are connected to the leg parts 5, 6. By forming the connecting members 7, 7 of the adjacent foundation blocks 4 in parallel with the side surfaces of the connecting members 6, the connecting members 7, 7 of the adjacent foundation blocks 4 are brought into contact with each other, thereby facilitating the mutual positioning of the foundation blocks 4. By inserting the main reinforcing bars 8 into the several insertion holes 7a, the main reinforcing bars 8 are automatically positioned accurately between the leg parts 5 and 6 serving as a waste form frame, and the reinforcement work can be carried out efficiently. Although similar to the example, in this example, the insertion hole 7a provided in the connecting member 7
In addition to inserting the required number of main reinforcements 8 into the base block 4 and arranging reinforcement between the leg parts 5 and 6, the insertion holes 7a are used to connect the adjacent foundation blocks 4 with bolts and nuts 30.
This embodiment differs from the first embodiment in that they are continuously and firmly connected to each other.

上述のように本考案は、対向する脚材部間を連
結部材を用いて結合することによつて基礎ブロツ
クをラーメン構造に形成したので基礎ブロツク自
体、構造堅牢にでき、また前記連結部材の対向位
置に挿入孔を設けたことにより、この挿入孔内に
主筋を挿入するだけの簡単な取扱いで基礎ブロツ
クの対向する脚材部間への主筋の配筋作業が所定
位置に迅速且つ確実に行え、しかも特別な型枠を
要せずに基礎ブロツクの対向する脚材部間の空間
部内に生コンクリートを連続して打設、固化させ
て養生後に型枠を取外すこともなく生コンクリー
トの掘削部に対する接地面積を増大して車道の縁
部に形成した掘削部にその外側に張出桟部を有す
る基礎ブロツクを強固に固定でき、自動車の振動
等の外力を受けたり、生コンクリートが養生、固
化する時に膨張する等の内部応力に対してすべり
を生ずることなく歩道を造成できる。
As mentioned above, in the present invention, the foundation block is formed into a rigid frame structure by connecting the opposing leg parts using the connection member, so that the foundation block itself can be structurally robust, and the By providing an insertion hole in the position, the main reinforcement can be placed in the specified position quickly and reliably by simply inserting the main reinforcement into the insertion hole. Moreover, fresh concrete is poured continuously into the space between the opposing leg parts of the foundation block without the need for special formwork, and the fresh concrete is poured into the excavated area without removing the formwork after curing. By increasing the ground contact area for the concrete, it is possible to firmly fix the foundation block with the protruding crosspiece on the outside to the excavated part formed at the edge of the roadway, and it will not be exposed to external forces such as vibrations from automobiles, and the fresh concrete will not cure or solidify. It is possible to create a sidewalk without causing slippage due to internal stress such as expansion when moving.

また張出側の脚材部には水抜孔が設けられてい
るので、脚材部間に打設後に含まれる生コンクリ
ートに必要以上の余分な水分が含まれたり、車道
面に雨等の余分な水が溜つた場合には路肩に排水
することによつて基礎ブロツクが水による侵食を
受けて短命になつたり、しかもひび割れを防止で
きるとともに掘削部が余分な水分を含んで緩むの
を防止できるため、保守、管理が良好になる。
In addition, since drainage holes are provided in the leg parts on the overhanging side, there is a risk that the ready-mixed concrete contained between the leg parts after pouring will contain more water than necessary, or that excess water from rain etc. will get on the roadway surface. When water accumulates, draining it to the roadside prevents the foundation block from being eroded by water and shortening its lifespan, and also prevents cracks and prevents the excavated part from loosening due to excess moisture. Therefore, maintenance and management will be better.

また前述のように基礎ブロツクの上面に張出桟
部がそれぞれ形成されているから、高架な車道に
沿つて基礎ブロツクを並設するだけで手元と先方
の張出桟部相互の間〓が内側と外側では一様にな
り、直線および曲線を問わず車道に沿つて狭い場
所においても広い所望幅の歩道の造成が正確にで
きる。
In addition, as mentioned above, since the overhanging crosspieces are formed on the top surface of each foundation block, simply by arranging the foundation blocks side by side along the elevated roadway, the distance between the protruding crosspieces at hand and the other side can be moved inside. This makes it possible to accurately construct a wide sidewalk of a desired width even in a narrow place along a roadway, regardless of whether it is straight or curved.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は従来の張出歩道ブロツクの敷設状態を
示した断面図、第2図は同じく斜面図、第3図は
本考案の張出歩道ブロツクの一実施例を示した斜
面図、第4図は同じく本実施例を構成する基礎ブ
ロツクの斜面図、第5図は同じく地覆を表板部に
固定する状態の斜面図、第6図はマウンド・アツ
プ式の敷設状態を示した断面図、第7図は他の使
用例におけるフラツト式の敷設状態を示した断面
図、第8図は隣接する表板部相互の衝合をモルタ
ルで行つた状態の断面図、第9図は本考案の張出
歩道ブロツクの他の実施例を示した斜面図、第1
0図は同じく平面図である。 4…基礎ブロツク、5,6…脚材部、7…連結
部材、7a…挿入孔、8…主筋、9…表板部。
Fig. 1 is a sectional view showing the installation state of a conventional overhanging walkway block, Fig. 2 is a slope view of the same, Fig. 3 is a slope view showing an embodiment of the overhanging walkway block of the present invention, and Fig. 4 The figure is a slope view of the foundation block that constitutes this embodiment, Figure 5 is a slope view of the ground cover being fixed to the top plate, and Figure 6 is a cross-sectional view showing the mound-up type installation. , Fig. 7 is a cross-sectional view showing a flat type installation state in another usage example, Fig. 8 is a cross-sectional view of a state in which adjacent top plate parts are butted with mortar, and Fig. 9 is a cross-sectional view showing a state in which the flat type is laid in another usage example. Slope view showing another example of the overhanging walkway block, 1st
Figure 0 is also a plan view. 4... Foundation block, 5, 6... Leg portion, 7... Connecting member, 7a... Insertion hole, 8... Main reinforcement, 9... Top plate part.

Claims (1)

【実用新案登録請求の範囲】[Scope of utility model registration request] 基礎ブロツクの上部外側に張出桟部が延出され
表板部が上面に形成されたコンクリート製の張出
歩道ブロツクにして、対向される脚材部;該脚材
部を結合する対向した連結部材;前記脚材部およ
び前記連結部材によつて囲まれ生コンクリートを
連続して打設可能に掘削部に略全域が開口する空
間部とから形成される基礎ブロツクと、前記脚材
部間に主筋が挿入自在に前記連結部材の対向位置
に設けられた挿入孔と、張出側の前記脚材部に前
記空間部と連通して路肩に臨むように設けられた
水抜孔とから成る張出歩道ブロツク。
An overhanging walkway block made of concrete with an overhanging crosspiece extending outside the upper part of the foundation block and a top plate formed on the upper surface, and opposed leg parts; opposing connections connecting the leg parts. member; a foundation block formed from a space surrounded by the leg part and the connecting member and having substantially the entire area open to the excavation part so that ready-mixed concrete can be poured continuously; An overhang consisting of an insertion hole provided at a position opposite to the connecting member so that the main reinforcement can be inserted freely, and a drain hole provided in the leg portion on the overhang side so as to communicate with the space and face the road shoulder. Sidewalk block.
JP5256483U 1983-04-11 1983-04-11 overhang sidewalk block Granted JPS59160603U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5256483U JPS59160603U (en) 1983-04-11 1983-04-11 overhang sidewalk block

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5256483U JPS59160603U (en) 1983-04-11 1983-04-11 overhang sidewalk block

Publications (2)

Publication Number Publication Date
JPS59160603U JPS59160603U (en) 1984-10-27
JPS6332164Y2 true JPS6332164Y2 (en) 1988-08-29

Family

ID=30182909

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5256483U Granted JPS59160603U (en) 1983-04-11 1983-04-11 overhang sidewalk block

Country Status (1)

Country Link
JP (1) JPS59160603U (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007032207A (en) * 2005-07-29 2007-02-08 Tokukon Kk Method for constructing overhang walkway

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5252250U (en) * 1975-10-14 1977-04-14

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4735206U (en) * 1971-05-10 1972-12-19

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5252250U (en) * 1975-10-14 1977-04-14

Also Published As

Publication number Publication date
JPS59160603U (en) 1984-10-27

Similar Documents

Publication Publication Date Title
KR101726725B1 (en) Construction method for a sidewalk enlargement installation
JP3519378B2 (en) Retaining wall structure and members for retaining wall construction in the observer passage in the tunnel
JPS6332164Y2 (en)
CN116463993A (en) Quickly assembled square framework slope protection structure and construction method
JP3065931B2 (en) Expansion joint support for steel road bridge and construction method of expansion joint for steel road bridge
JP6931876B2 (en) How to build a permeable wall for slope reinforcement
JPH0258606A (en) Repair of median strip and fender block used therefor
KR19990073084A (en) Formwork method using no prop for the floor concrete of the bridge
KR100609825B1 (en) Preflexed rigid- frame bridge installed using prestressed upper structure and constructing method thereof
JP3856791B2 (en) How to lay an overhanging sidewalk
KR102120849B1 (en) Installation structure and method of precast concrete culvert
KR100964721B1 (en) Block for road extension
JPS6250601B2 (en)
JPS6319642B2 (en)
KR20050089576A (en) Precast concrete block for retaining wall and construction method using the same
JP2536376B2 (en) Foundation structure of shed for road protection
JPS6340484Y2 (en)
KR100400676B1 (en) Method constructing gutler and struc ture thereof
JPS6312161Y2 (en)
JPS6315402B2 (en)
KR102174082B1 (en) Construction method of slope drainage ditch
CN214362568U (en) Ballastless track structure
KR200354133Y1 (en) Precast concrete block for retaining wall
CN220099797U (en) Square skeleton slope protection structure is assembled fast
CN108487073B (en) Construction method for integrally pouring cast-in-place beam on sand box foundation