JPS6322916A - Construction of continuous underground wall in artificial islet - Google Patents

Construction of continuous underground wall in artificial islet

Info

Publication number
JPS6322916A
JPS6322916A JP16474086A JP16474086A JPS6322916A JP S6322916 A JPS6322916 A JP S6322916A JP 16474086 A JP16474086 A JP 16474086A JP 16474086 A JP16474086 A JP 16474086A JP S6322916 A JPS6322916 A JP S6322916A
Authority
JP
Japan
Prior art keywords
tie rod
construction
wall
sheet piles
underground wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP16474086A
Other languages
Japanese (ja)
Other versions
JPH0366452B2 (en
Inventor
Masaya Hirai
平井 正哉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ohbayashi Gumi Ltd
Obayashi Corp
Original Assignee
Ohbayashi Gumi Ltd
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ohbayashi Gumi Ltd, Obayashi Corp filed Critical Ohbayashi Gumi Ltd
Priority to JP16474086A priority Critical patent/JPS6322916A/en
Publication of JPS6322916A publication Critical patent/JPS6322916A/en
Publication of JPH0366452B2 publication Critical patent/JPH0366452B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PURPOSE:To maintain reinforcing effects by tie rods by method in which tie rods inserted into guide wall on the top end of an excavated trench and the sheath pipe of sheet pile are temporarily pulled out, underground walls are constructed, and the sheet piles are connected. CONSTITUTION:A tie rod 9 is thrust through sheet piles 1 and sheath pipes 6 and 7 pierced the lower part of a guide wall 5 and the sheet piles 1 set in an artificial islet 3 partitioned by the steel tubular sheet piles 1. The tie rod 9 is fixed with nuts 9a, and the tie rod 9 in the preceding construction section is pulled out. The preceding trench 11 is excavated while filling it with mud water under the guidance of the wall 5, a reinforcing bar cage is set in the trench 11, and concrete is placed. The tie rod 9 is again set to construct the preceding panel 12, and by repeating the same processes, the following panels are connected to the panel 12. An underground continuous wall can thus be constructed in the minimum area of the islet.

Description

【発明の詳細な説明】 (産業上の利用分野) この発明は、人工島における連続地中壁の施工方法に関
する。
DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a method of constructing a continuous underground wall on an artificial island.

(従来の技術) 連続地中壁の水中施工は、一般に鋼管矢板等を用いた締
切り内に土砂を投入して人工島を築島した後、その内部
に掘削形成された掘削溝内に対する鉄筋組の建込みと、
コンクリートを打設する作業の繰返しによって行われる
(Conventional technology) Underwater construction of continuous underground walls generally involves constructing an artificial island by pouring earth and sand into a cofferdam using steel pipe sheet piles, etc., and then installing reinforcing bars in an excavated trench inside the island. The construction and
This is done by repeating the process of placing concrete.

(発明が解決しようとする問題点) 人工島は内部の土圧や、静水圧のほか波、水流などの動
圧を頻繁に受けるため、矢板間をタイロッドで連結して
補強する必要がある。
(Problems to be solved by the invention) Since artificial islands are frequently subjected to internal earth pressure, hydrostatic pressure, and dynamic pressure such as waves and water currents, it is necessary to connect and reinforce the sheet piles with tie rods.

したがって、掘削溝の掘削時や、鉄筋組の建込み時にこ
れらのタイロッドが障害になる。
Therefore, these tie rods become an obstacle when excavating an excavation trench or erecting reinforcing bars.

つまり、締切工が地中壁の構築方向に沿って形成される
ので、タイロッドは必然的に掘削溝の上部に直交するか
らである。
In other words, since the cofferdam is formed along the construction direction of the underground wall, the tie rod is necessarily perpendicular to the top of the excavated trench.

なお、比較的大面積の人工島では、二重締め切りをする
ことで、タイロッドによる障害をなくすことができる。
In addition, for artificial islands with relatively large areas, obstructions caused by tie rods can be eliminated by double closing.

しかし、二重締め切りは、工費が高価であり、しかも大
深度、大面積工事に限られる。
However, double closing is expensive and is limited to deep-depth, large-area construction.

また、地中壁の構築位置のタイロッドを切除したのでは
補強効果がまったくなくなる。
Furthermore, if the tie rods at the construction location of the underground wall are removed, the reinforcing effect will be completely lost.

この発明は、以上の問題を解決するもので、地中壁と交
差するタイロッドを切除することなく、地中壁を構築す
ることを目的とする。
This invention solves the above problems, and aims to construct an underground wall without removing the tie rods that intersect with the underground wall.

(問題点を解決するための手段) 前記目的を解決するため、この発明では、一重締切工で
水域を区画し、該締切工内に土砂を投入して人工島を構
築し、かつ該締切工間をタイロッドによって連結して人
工島を補強し、次いで、該人工島内に掘削溝を形成し、
該掘削溝内にコンクリートを打設して連続地中壁を構築
する施工方法において、前記掘削溝の天端に形成される
ガイドウオールと締切工のタイロッド挿入位置とに同一
直線上に並ぶシース管をあらかじめ設け、前記地中壁の
施工時に一時的にタイロッドをシース管から抜き、施工
侵、再度シース管を通じてタイロッドを締切工間に連結
することを特徴とする。
(Means for Solving the Problems) In order to solve the above object, the present invention divides a water area with a single cofferdam, constructs an artificial island by pouring earth and sand into the cofferdam, and reinforcing the artificial island by connecting them with tie rods, and then forming an excavation groove in the artificial island,
In the construction method of constructing a continuous underground wall by pouring concrete into the excavated trench, a sheath pipe aligned on the same straight line as a guide wall formed at the top of the excavated trench and a tie rod insertion position of the cofferdam. is provided in advance, and during construction of the underground wall, the tie rod is temporarily removed from the sheath pipe, and after construction, the tie rod is connected again through the sheath pipe between the cofferdams.

(作 用) 上記構成の施工方法によれば、地中壁の一工区ごとに該
当するタイロッドをいったん引き抜き、施工が終了した
後、再装填すればよいので、タイロッドによる補強効果
を失うことなく施工ができる。
(Function) According to the construction method with the above configuration, it is only necessary to pull out the corresponding tie rod for each section of the underground wall and reload it after the construction is completed, so the construction can be carried out without losing the reinforcing effect of the tie rod. Can be done.

(実施例) 以下、この発明の一実施例を図面を用いて詳細に説明す
る。
(Example) Hereinafter, an example of the present invention will be described in detail using the drawings.

第1図(a)〜(f)はこの発明の施工方法を示す平面
図、第2図(a)〜(f)は同所面図である。
FIGS. 1(a) to (f) are plan views showing the construction method of the present invention, and FIGS. 2(a) to (f) are plan views of the same location.

図(a)において、1は海底面に打ち込まれた一対の鋼
管矢板であり、この鋼管矢板1によって海域Eを締め切
り、図(b)の如くその内部に自硬体安定液、ソイルセ
メント、或いは貧配合モルタルなどの中詰土砂2を投入
することによって前記鋼管矢板1に作用する土圧を低減
した状態で、人工島3の築島を完成する。
In Figure (a), numeral 1 is a pair of steel pipe sheet piles driven into the seabed. The steel pipe sheet piles 1 close off the sea area E, and as shown in Figure (b), there is a self-hardening stabilizer, soil cement, or The construction of the artificial island 3 is completed in a state where the earth pressure acting on the steel pipe sheet pile 1 is reduced by introducing filling soil 2 such as poorly mixed mortar.

この人工島3は、得ようとする連続地中壁の構築方向に
沿って細長状に形成されるものであり、その−側部には
作業台4が構築されている。
This artificial island 3 is formed into an elongated shape along the construction direction of the continuous underground wall to be obtained, and a workbench 4 is constructed on the negative side thereof.

築島完成後、同図(C)に示す如く、矢板1の内側にお
いて中詰土砂2の上面には後述の掘削溝の天端を縁取る
一対のガイドウオール5が対向して敷設される。
After the construction of the island is completed, a pair of guide walls 5, which will be described later, border the top of the excavated trench, are laid facing each other on the upper surface of the filling earth and sand 2 inside the sheet pile 1, as shown in FIG. 1C.

第3図に拡大して示すように、ガイドウオール5の下部
には適宜間隔で長手方向と直交するシース管6があらか
じめ埋設されている。また、矢板1にも前記シース管6
と同一ピッチでシース管7が内外を貫通して配置されて
いる。そして、ガイドウオール5を設置するにあたって
は、各シース管6.7が同一直線上に並ぶように配列さ
れる。
As shown in an enlarged view in FIG. 3, sheath tubes 6 are embedded in advance in the lower part of the guide wall 5 at appropriate intervals and perpendicular to the longitudinal direction. Also, the sheath pipe 6 is also included in the sheet pile 1.
The sheath tubes 7 are arranged penetrating the inside and outside at the same pitch. When installing the guide wall 5, the sheath tubes 6.7 are arranged on the same straight line.

その後、第1.2図(d)に示すようにガイドウオール
5の外側部に復起し8を配置し、次いで矢板1.ガイド
ウオール5のシース管6,7を通じて矢板1管にタイロ
ッド9を挿通し、ナツト9aにより固定する(第3図参
照)。これによって人工島3は十分に補強される。
Thereafter, as shown in FIG. 1.2(d), the sheet piles 8 are placed on the outside of the guide wall 5, and then the sheet piles 1. A tie rod 9 is inserted into the sheet pile 1 through the sheath tubes 6 and 7 of the guide wall 5, and fixed with a nut 9a (see FIG. 3). The artificial island 3 is thereby sufficiently reinforced.

以上の準備作業後連続地中壁の構築作業が行われる。After the above preparatory work, the continuous underground wall construction work will be carried out.

この作業順序としては、先ず第1.2図(e)に示すよ
うに、先′行工区Aの位置決めをし、その工区Aに直交
するタイロッド9を川床く。その後ガイドウオール5を
ガイドとして泥水10を満しつつ先行の掘削溝11を掘
削し、鉄筋量の建込みと、コンクリート打設作業を行な
うことにより、同図(f)に示すように先行の地中連続
壁すなわち先行パネル12を完成する。
In this work order, first, as shown in Fig. 1.2(e), the preceding work section A is positioned, and the tie rod 9 perpendicular to the work section A is moved to the riverbed. After that, using the guide wall 5 as a guide, the preceding excavation trench 11 is excavated while filling with muddy water 10, and the amount of reinforcing bars is erected and concrete is placed.As shown in FIG. The intermediate continuous wall or preceding panel 12 is completed.

以上の一連の作業は作業構築台4上に設けた掘削機、ク
レーン、コンクリート打設機械等によって行われる。
The above-mentioned series of operations are performed by an excavator, a crane, a concrete pouring machine, etc. installed on the work construction table 4.

先行パネル12の施工完了後、いったん川床いたタイロ
ッド9は再び装填される。これにより、先行工区Aの脆
弱性は解消される。
After the construction of the preceding panel 12 is completed, the tie rod 9 that has been left in the riverbed is loaded again. This eliminates the vulnerability of the preceding construction section A.

次に同図(f)に示すように先行工区Aに隣接して後行
工区Bの施工を行なうのであるが、該工区Bも前記先行
1区Aと同じくタイロッド9の用法、掘削溝11の掘削
、鉄筋量の建込みおよびコンクリート打設を行い、先行
パネル12に後行パネル14が打ち継がれる。後行パネ
ル14の施工完了後、タイロッド9を再び装填する。
Next, as shown in Figure (f), the construction of the succeeding work area B is carried out adjacent to the preceding work area A, but this work area B also uses the same tie rod 9 and excavated groove 11 as the preceding work area A. Excavation, erection of reinforcing bars, and concrete placement are performed, and the trailing panel 14 is succeeded to the leading panel 12. After completing the construction of the trailing panel 14, the tie rod 9 is loaded again.

以下、次々と同様のサイクルで作業を繰返すことによっ
て、連続地中壁の施工を完了するのである。
After that, the construction of the continuous underground wall is completed by repeating the work one after another in the same cycle.

(発明の効果) 以上実施例で説明したように、この発明の施工方法によ
れば、−工区ごとに該当するタイロッドを引き抜き、施
工終了後再び装填すればよいので、タイロッドによる人
工島の補強効果が損われることがない。また、地中連続
壁の構築にあたっては、最小限度の築島面積、締切間隔
でよく、施工費用も安価となる。
(Effects of the Invention) As explained in the embodiments above, according to the construction method of the present invention, the tie rods can be used to reinforce the artificial island by pulling out the tie rods for each construction section and reloading them after the completion of construction. will not be damaged. In addition, when constructing an underground continuous wall, only the minimum construction area and cut-off intervals are required, and the construction cost is also low.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図(a)〜(f)はこの発明の施工方法を示す平面
図、第2図(a)〜(f)は同断面図、第3図はシース
管に対するタイロッドの結合状態の詳細を示す拡大断面
図である。 1・・・・・・鋼管矢板    2・・・・・・中詰土
砂3・・・・・・人工島     5・・・・・・ガイ
ドウオール6.7・・・シース管   9・・・・・・
タイロッド12・・・先行パネル(地中壁) 14・・・後行パネル(地中壁) 特許出願人      株式会社 大 林 組代 理 
人      弁理士 −色 健 軸周       
 弁理士 松 本 雅 和事1図 (a) 第1図 (C) (d) 第1図 (e) (f) 第2図 (a) 第2図 (b) 第2図 (C) 第2図 (d) 第2図 (e)
Figures 1 (a) to (f) are plan views showing the construction method of the present invention, Figures 2 (a) to (f) are sectional views of the same, and Figure 3 shows details of the state of connection of the tie rod to the sheath pipe. FIG. 1...Steel pipe sheet pile 2...Filled earth and sand 3...Artificial island 5...Guide wall 6.7...Sheath pipe 9...・・・
Tie rod 12... Leading panel (underground wall) 14... Trailing panel (underground wall) Patent applicant Obayashi Corporation Agent
Person Patent Attorney - Color Ken Shaft Circumference
Patent Attorney Masaru Matsumoto Kazuko Figure 1 (a) Figure 1 (C) (d) Figure 1 (e) (f) Figure 2 (a) Figure 2 (b) Figure 2 (C) 2 Figure (d) Figure 2 (e)

Claims (1)

【特許請求の範囲】[Claims] (1)一重締切工で水域を区画し、該締切工内に土砂を
投入して人工島を構築し、かつ該締切工間をタイロッド
によつて連結して人工島を補強し、次いで、該人工島内
に掘削溝を形成し、該掘削溝内にコンクリートを打設し
て連続地中壁を構築する施工方法において、前記掘削溝
の天端に形成されるガイドウォールと締切工のタイロッ
ド挿入位置とに同一直線上に並ぶシース管をあらかじめ
設け、前記地中壁の施工時に一時的にタイロッドをシー
ス管から抜き、施工後、再度シース管を通じてタイロッ
ドを締切工間に連結することを特徴とする人工島におけ
る連続地中壁の施工方法。
(1) Divide the water area with a single cofferdam, construct an artificial island by pouring earth and sand into the cofferdam, connect the coffers with tie rods to reinforce the artificial island, and then In a construction method in which an excavated groove is formed in an artificial island and concrete is poured into the excavated groove to construct a continuous underground wall, the guide wall formed at the top of the excavated groove and the tie rod insertion position of the cofferdam. A sheath pipe arranged in the same straight line is provided in advance in the underground wall, the tie rod is temporarily removed from the sheath pipe during construction of the underground wall, and after construction, the tie rod is connected again through the sheath pipe between the cofferdams. Construction method for continuous underground walls on artificial islands.
JP16474086A 1986-07-15 1986-07-15 Construction of continuous underground wall in artificial islet Granted JPS6322916A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16474086A JPS6322916A (en) 1986-07-15 1986-07-15 Construction of continuous underground wall in artificial islet

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16474086A JPS6322916A (en) 1986-07-15 1986-07-15 Construction of continuous underground wall in artificial islet

Publications (2)

Publication Number Publication Date
JPS6322916A true JPS6322916A (en) 1988-01-30
JPH0366452B2 JPH0366452B2 (en) 1991-10-17

Family

ID=15799004

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16474086A Granted JPS6322916A (en) 1986-07-15 1986-07-15 Construction of continuous underground wall in artificial islet

Country Status (1)

Country Link
JP (1) JPS6322916A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112962580A (en) * 2021-03-08 2021-06-15 中国建筑一局(集团)有限公司 Underground continuous wall refined roundness connection structure and construction method thereof
CN112962579A (en) * 2021-03-08 2021-06-15 中国建筑一局(集团)有限公司 Construction method of underground continuous wall of coastal push-filling area
CN113089645A (en) * 2021-04-22 2021-07-09 安徽水安建设集团股份有限公司 Slotted hole structure system for reinforcing concrete impervious wall by penetrating silt layer and construction method
CN114263168A (en) * 2022-01-10 2022-04-01 北京市政建设集团有限责任公司 Construction method of rock-socketed diaphragm wall of stratum water-stopping enclosure structure

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112962580A (en) * 2021-03-08 2021-06-15 中国建筑一局(集团)有限公司 Underground continuous wall refined roundness connection structure and construction method thereof
CN112962579A (en) * 2021-03-08 2021-06-15 中国建筑一局(集团)有限公司 Construction method of underground continuous wall of coastal push-filling area
CN112962580B (en) * 2021-03-08 2023-01-20 中国建筑一局(集团)有限公司 Underground continuous wall refined roundness connection structure and construction method thereof
CN113089645A (en) * 2021-04-22 2021-07-09 安徽水安建设集团股份有限公司 Slotted hole structure system for reinforcing concrete impervious wall by penetrating silt layer and construction method
CN113089645B (en) * 2021-04-22 2022-11-22 安徽水安建设集团股份有限公司 Slotted hole structure system for reinforcing concrete impervious wall by penetrating silt layer and construction method
CN114263168A (en) * 2022-01-10 2022-04-01 北京市政建设集团有限责任公司 Construction method of rock-socketed diaphragm wall of stratum water-stopping enclosure structure

Also Published As

Publication number Publication date
JPH0366452B2 (en) 1991-10-17

Similar Documents

Publication Publication Date Title
CN106400820A (en) Cofferdam formed by latched steel tube and concrete combined piles and construction method
JPS6322916A (en) Construction of continuous underground wall in artificial islet
JP3135188B2 (en) Construction method of underground cavity
JPS63280153A (en) Underground inverted lining method
CN115387364B (en) Deep water rock-embedded combined light cofferdam construction method
JPS6322917A (en) Construction of underground continuous wall in arrificial islet
JPH073777A (en) Method for constructing self-supporting land slide protection wall
JP3082053B2 (en) Large-scale, deep steel continuous basement wall and method of constructing the same
JPH0468407B2 (en)
JPS6018769B2 (en) Construction method of underground structure
JP2565452B2 (en) Construction method of self-supporting retaining wall
JPS61221413A (en) Skew pile driving work
JPS61186623A (en) Method of building foundation of building
JPS601451B2 (en) Water stop mountain stop wall construction method using Benoto pile excavator
JPS5853321Y2 (en) Element for mountain retainer
JPH05125891A (en) Large bore underground wall and its constructing method, and pipe burying excavator
JP2828786B2 (en) Casing shaft
JP2002088777A (en) Method for connecting jacket structure to pile, and pipe expanding apparatus for use in the method
JPH0266220A (en) Prevention method of damage at cross-section in concrete part of cast-in-place pile
JPS61191725A (en) Stress material drawing work
JPH0430491B2 (en)
JPH0428044B2 (en)
JPH06240659A (en) Waterproof wall device
JPH07150551A (en) Steel frame for continuous underground wall and method for constructing wall and its segment
JPH0259889B2 (en)