JPS63184693A - Method of protection construction of existing tunnel - Google Patents

Method of protection construction of existing tunnel

Info

Publication number
JPS63184693A
JPS63184693A JP1392187A JP1392187A JPS63184693A JP S63184693 A JPS63184693 A JP S63184693A JP 1392187 A JP1392187 A JP 1392187A JP 1392187 A JP1392187 A JP 1392187A JP S63184693 A JPS63184693 A JP S63184693A
Authority
JP
Japan
Prior art keywords
existing tunnel
shaft
tunnel
excavated
existing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP1392187A
Other languages
Japanese (ja)
Other versions
JPH0416598B2 (en
Inventor
松村 米紘
猪野 宣長
清 宮
栗原 雄二
好信 居相
文行 横溝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ohbayashi Gumi Ltd
Obayashi Corp
Original Assignee
Ohbayashi Gumi Ltd
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ohbayashi Gumi Ltd, Obayashi Corp filed Critical Ohbayashi Gumi Ltd
Priority to JP1392187A priority Critical patent/JPS63184693A/en
Publication of JPS63184693A publication Critical patent/JPS63184693A/en
Publication of JPH0416598B2 publication Critical patent/JPH0416598B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 (産業上の利用分野) この発明は、例えば市街地などにおける地下1−ンネル
の老朽化に伴ない、トンネルの使用に支障を与えること
なくこれを外部より補強するための既存トンネルの防護
工法に関する。
[Detailed Description of the Invention] (Industrial Application Field) This invention provides a method for reinforcing underground tunnels from the outside without hindering the use of the tunnels, for example, as underground tunnels in urban areas become obsolete. Regarding protection construction methods for existing tunnels.

(従来の技術) 地下トンネルの老朽化に伴ない、このトンネルを壊さず
にそのままの状態で使用し、しかもトンネルの補強工事
を行うための工法として、最も簡単には第7図に示すよ
うに、既存トンネル1の両側N+を地下連続壁2で囲い
、その状態で既存トンネル1の上部を開削し、コンクリ
−;・頂版3を架設し、既存トンネル1を包囲すること
である。
(Prior art) As underground tunnels become older, the simplest construction method to use them as they are without destroying them and to carry out tunnel reinforcement work is as shown in Figure 7. , both sides N+ of the existing tunnel 1 are surrounded by underground continuous walls 2, and in this state, the upper part of the existing tunnel 1 is excavated, a concrete top plate 3 is erected, and the existing tunnel 1 is surrounded.

(発明が解決しようとする問題点) しかし、市街地などでこの工事を行うためには、地上部
における既存建物との関係や、既存トンネル1の上部の
地中内に配置されているガス管や上下水道管、電話ケー
ブルの埋設管など種々の地下埋設物を考慮しなければな
らない。特に繁華街において老朽化が進んでいる地下鉄
のトンネルなどではその上部の裡設物が錯雑に配置され
、どの位置にあるかも解らないし、既存建物がトンネル
上部の地表面に位置している場合もあり、したがって、
実質的にはこの種の工法は採用範囲が非常に限定される
(Problem to be solved by the invention) However, in order to carry out this construction in urban areas, etc., it is necessary to consider the relationship between the above-ground part and existing buildings, the gas pipes placed underground above the existing tunnel 1, etc. Various underground structures such as water and sewage pipes and telephone cable pipes must be considered. Particularly in the case of aging subway tunnels in downtown areas, the facilities above are arranged in a complicated manner, making it difficult to know where they are located, and in some cases, existing buildings are located on the ground surface above the tunnel. Yes, therefore,
Practically speaking, this type of construction method has a very limited range of application.

また、この種の防護工事に替で既存トンネル1を壊して
新たなトンネルを構築する場合にも営業用の線路を迂回
させるための代替地を予め確保しなければならないため
、代替地の余裕がない状態では建苔え工事もままになら
ないものとなっていた。
In addition, if the existing tunnel 1 is to be demolished and a new tunnel constructed instead of this type of protection work, an alternative site must be secured in advance to detour the commercial track, so there is not enough room for an alternative site. Without it, the moss construction work would not be possible.

この発明は以上の実状に鑑みなされたものであり、既存
トンネルを壊さずに仕上がり状態では前記第7図に示す
のとほぼ同等の防護構造となるようにすることを目的と
する。
This invention has been made in view of the above-mentioned circumstances, and it is an object of the present invention to provide a protective structure almost equivalent to that shown in FIG. 7 in the finished state without destroying the existing tunnel.

(問題点を解決するための手段) 前記目的を達成するため、この発明は、既存トンネルの
両側部に発進導坑を掘削し、該発進導坑を始点としてト
ンネル工法によって所定の区間に既存トンネルの両側面
に沿う一対の導坑を掘削し、次いで推進工法により各導
坑の一方から他方に向けて既存I・ンネルの少くとも頂
部に沿う中空状の函体を順次密接状態に並列配置し、前
記導坑と前記函体部とを相互に連通させた状態でこれら
の内部にコンクリートを打設して、既存トンネルの両側
部と頂部をコンクリート防護壁および頂版によって包囲
したことを特徴とする。
(Means for Solving the Problems) In order to achieve the above object, the present invention involves excavating a starting shaft on both sides of an existing tunnel, and using a tunnel construction method to extend the existing tunnel in a predetermined section using the starting shaft as a starting point. A pair of shafts are excavated along both sides of the tunnel, and then hollow boxes are successively arranged closely parallel to each other along at least the top of the existing I-channel from one side of each shaft to the other using the propulsion method. , characterized in that concrete is cast inside the shaft and the box part in a state where they communicate with each other, and both sides and the top of the existing tunnel are surrounded by concrete protective walls and a top slab. do.

(作 用) 防護しようとする区間に最も近い位置であって、既存の
建物や、埋設物に影響されない小面積の土地をえらんで
ここに発進導坑を掘削すれば、その後はトンネル上部の
既存埋設物に影響や干渉されることなく既存トンネルの
両側部に沿って導坑を掘削でき、完成状態は地下連続壁
と少くとも頂版で既存トンネルを囲った場合と構造的に
全く同一状態となる。
(Function) If you select a small area of land that is closest to the section to be protected and will not be affected by existing buildings or buried objects, and excavate the starting shaft there, the A shaft can be excavated along both sides of the existing tunnel without being affected or interfered with by buried objects, and the completed state will be structurally exactly the same as when the existing tunnel was surrounded by an underground continuous wall and at least a top plate. Become.

(実 施 例) 以下、この発明の一実施例を図面を用いて詳細に説明す
る。
(Example) Hereinafter, an example of the present invention will be described in detail using the drawings.

第1図〜第6図はこの発1ullの一実施例を示してい
る。
FIGS. 1 to 6 show an embodiment of this 1ull.

図において、10は市街地における老朽化した既存トン
ネルを示し、実施例ではこの既存トンネル10の外周の
所定区間を防護工事する場合を説明している。
In the figure, reference numeral 10 indicates a dilapidated existing tunnel in an urban area, and in the embodiment, a case where a predetermined section of the outer periphery of this existing tunnel 10 is protected is explained.

まず、既存トンネル10の両側部に、一対の発進導坑1
2を掘削する。発進導坑12は、既存トンネル10内の
地下鉄軌道の側方に発進導坑12を掘削する余地があれ
ばその部分に発3t!!竪坑12を設ければよいが、発
進導坑12は必ずしも既存トンネル10内に設ける必要
はなく、地上に掘削可能な場所があれば、そこを選択す
ることもできる。
First, a pair of starting shafts 1 are installed on both sides of the existing tunnel 10.
Drill 2. If there is room to excavate the starting shaft 12 on the side of the subway track within the existing tunnel 10, the starting shaft 12 will be located in that part! ! Although it is sufficient to provide the shaft 12, the starting shaft 12 does not necessarily need to be provided in the existing tunnel 10, and if there is a place on the ground where it can be excavated, it can be selected there.

各発進導坑12−が所定深度まで構築されると、導坑1
2からはそれぞれトンネル工法によって導坑14a、1
4b、14cが三段積み重ねた状態で既存トンネル10
の両側部に沿って掘削される。
When each starting shaft 12- is constructed to a predetermined depth, the shaft 1
From 2 to 2, guide shafts 14a and 1 are constructed using tunnel construction methods, respectively.
Existing tunnel 10 with 4b and 14c stacked in three stages
excavated along both sides of the

導坑148〜14Cは既存トンネル10の高さに応じて
掘削作業が可能な幅および高さに設定され、またその掘
削方法としては手掘り方式やロックボルト工法を併用す
る機械方式などが採用される。
The guide shafts 148 to 14C are set to a width and height that allows excavation work according to the height of the existing tunnel 10, and the excavation method is a manual method or a mechanical method using a rock bolt method. Ru.

各導坑14a〜14Cの断面形状は、この実施例では矩
形状であって、ト1形鋼を矩形状に組み合わせた支保工
16を掘削方向に沿って適宜間隔に配列しである。
In this embodiment, the cross-sectional shape of each of the guide shafts 14a to 14C is rectangular, and shoring structures 16 made of rectangular steel sections are arranged at appropriate intervals along the excavation direction.

各導坑148〜14Gの一側部は既存トンネル10の側
壁に面しているので、少くとも上部および他側部は吹き
付はコンクリートによって掘削壁面を補強する。
Since one side of each shaft 148 to 14G faces the side wall of the existing tunnel 10, the excavated wall surface is reinforced with sprayed concrete at least on the upper part and the other side.

最下段の導坑14aの掘削後、導坑14aの下方には場
所打ち杭工法によって補強杭18が掘削方向に沿って適
宜間隔に造成され、防護壁体の鉛直支持力および側部土
圧の水平支持力を補強する。
After excavating the lowermost guide shaft 14a, reinforcing piles 18 are constructed below the guide shaft 14a at appropriate intervals along the excavation direction using the cast-in-place pile construction method to reduce the vertical bearing capacity of the protective wall and the lateral earth pressure. Reinforce horizontal support capacity.

次いでこの導坑14aの内部には、既存トンネル10の
側面から若干間隔をあけて、後述する推進工法で構築さ
れる構造形状・荷重等によって生じる断面力によって決
定された壁厚を備えた下段防護壁19aが、型枠を導坑
14aに沿って設置して、鉄筋を組立てた後、コンクリ
ートを打設して形成される。
Next, inside this tunnel 14a, a lower level protection is installed at a slight distance from the side of the existing tunnel 10, with a wall thickness determined by the cross-sectional force generated by the structural shape, load, etc. constructed by the propulsion method described later. The wall 19a is formed by installing a formwork along the shaft 14a, assembling reinforcing bars, and then pouring concrete.

そして、下段防饅壁19aが構築されると型枠を撤去し
て、防1!119aと導坑14aとの間に気泡コンクリ
ート等が充填される。
Then, when the lower banishing wall 19a is constructed, the formwork is removed and aerated concrete or the like is filled between the first banishing wall 119a and the guide shaft 14a.

充填が終了すると、第2段目の導坑14bが掘削され、
掘削後に下段防護壁19aの上端に中段防護壁19bを
構築して、前記と同様に気泡コンクリート等が充填され
る。
When filling is completed, the second stage shaft 14b is excavated,
After excavation, a middle protection wall 19b is constructed at the upper end of the lower protection wall 19a, and filled with aerated concrete or the like in the same manner as described above.

次いで最上段の導坑14cが掘削される。この導坑14
cの高さは既存トンネル10の上部より突出しており、
導坑14cの完成後は上部突出部分の側面に既存トンネ
ル10の上部長手方向に直交して既存トンネル10を挟
む一方の導坑14cから他方の導坑14Cに向けて推進
工法によって中空函体30の配置作業が行なわれる。
Next, the uppermost shaft 14c is excavated. This shaft 14
The height of c protrudes from the top of the existing tunnel 10,
After completion of the guide shaft 14c, a hollow box is installed on the side surface of the upper protruding part, perpendicular to the upper longitudinal direction of the existing tunnel 10, from one guide shaft 14c to the other guide shaft 14C sandwiching the existing tunnel 10. 30 placement operations are performed.

中空函体30の推進に先立って、発進側め一方の導坑1
4c内には、掘削土砂の運搬軌条20゜中空函体30の
運搬軌条24が敷設される。
Prior to propulsion of the hollow box 30, the guide shaft 1 on the starting side
A transport rail 24 for the hollow box 30 with a 20° transport rail for excavated earth and sand is laid in the inside 4c.

上記運搬軌条24上には中空函体30を運搬する台車2
6と、この台車26から受承した中空函体30を推進位
置にセットする発進台車27が配置される。
On the transport rail 24 is a trolley 2 for transporting the hollow box 30.
6, and a starting truck 27 that sets the hollow box 30 received from the truck 26 to the propulsion position.

そして、掘削土砂の運搬軌条20上には、推進ジヤツキ
22の設置用台車32を配置し、これを掘削土砂の搬送
台車34の最前部に接続し、バッテリ機関車36で牽引
するようにする。また、導坑14Cの天井面にはホイス
トクレーン38の案内軌条40を固定し、前記台車32
に一端を接続し、伯端を搬送台車34上に位置するベル
トコンベア42を吊り下げるホイストクレーン44を設
けておく。さらに、前記中空函体30用の台車26もバ
ッテリ台車36に接続し、これに牽引されて移動できる
ようにしておく。
A cart 32 for installing the propulsion jack 22 is arranged on the excavated earth and sand transportation rail 20, connected to the frontmost part of the excavated earth and sand transport truck 34, and pulled by a battery locomotive 36. Further, a guide rail 40 of a hoist crane 38 is fixed to the ceiling surface of the guide shaft 14C, and the guide rail 40 of the hoist crane 38 is fixed to
A hoist crane 44 is provided, which connects one end to the belt conveyor 42 and suspends the belt conveyor 42 located on the conveyor truck 34 at the lower end thereof. Furthermore, the cart 26 for the hollow box 30 is also connected to the battery cart 36 so that it can be moved by being towed by this.

以上の準備作業後、発進側の導坑14C1,:おける防
護工区の最先端位置に推進ジヤツキ22を固定し、この
推進ジヤツキ22の加圧力によって、運搬台車26を経
て推進台車27に移しかえた先端に刃口30aを設けた
矩形状の中空函体30を既存トンネル10の頂部上に直
交して圧入しつつその内部の土砂を掘削し、掘削された
土砂をベルトコンベア42を介して搬送台車34側に排
出する。
After the above preparation work, the propulsion jack 22 was fixed at the most extreme position of the protected area in the starting side shaft 14C1, and by the pressing force of this propulsion jack 22, it was transferred to the propulsion truck 27 via the transport truck 26. A rectangular hollow box 30 with a cutting edge 30a at the tip is press-fitted orthogonally onto the top of the existing tunnel 10 while excavating the earth and sand inside it, and the excavated earth and sand is conveyed via a belt conveyor 42 to a transport vehicle. Discharge to the 34 side.

最初の中空函体30の圧入完了後は、これの後端部を鋼
製のカラーで接合した状態で、次の中空函体30を継ぎ
足しつつ推進ジヤツキ22で圧入および人力による土砂
の掘削作業を繰り返す。以上の作業により、最先端部の
中空函体30は他方の導坑14Cに到達する。その後は
この中空函体30の刃口30aを取り外し、これを一方
の導坑14C側に搬送し、次の推進作業用に繰り返し使
用する。
After the first hollow box 30 is press-fitted, the rear end of the hollow box 30 is joined with a steel collar, and the next hollow box 30 is added, press-fitted using the propulsion jack 22, and earth and sand excavated manually. repeat. Through the above operations, the hollow box 30 at the leading end reaches the other guide shaft 14C. Thereafter, the cutting edge 30a of this hollow box 30 is removed, and it is transported to one of the guide shafts 14C and used repeatedly for the next propulsion operation.

最初の工区に使われる中空函体30は、いずれも四方を
側板で囲んだ矩形状をなす鋼管であって、従来の推進工
法と変わりがない構造のものが用いられる。
The hollow boxes 30 used in the first section are all rectangular steel pipes surrounded by side plates on all sides, and have the same structure as the conventional propulsion method.

次にこの工区に隣接する工区を推進するための中空函体
は先頭のものに刃口30aを装着することは同じである
が、中空函体自体は特殊形状となっている。
Next, the hollow box for propelling the work section adjacent to this section is the same as the first one with a cutting edge 30a attached, but the hollow box itself has a special shape.

すなわち、第5図(a)〜(d)に示すように、この中
空函体50は天板50a、及び底板50bは前記と同様
の鋼板製であるが、−側部が開口したコ字形断面をなし
、伯側部はラスなどの金網板50cから構成されている
。また、両側部の上下にはアングル板52で補強されて
いるとともに、各アングル板52の側面には互いに逆向
の鉤形フック部54が側面突出状態で一体化され、隣り
合う工区の各中空函体50同士が駒形に係合しあった状
態で接合されるようになっており、隣接工区の中空函体
50同士が繋がれた状態で密接配置できるようにしであ
る。
That is, as shown in FIGS. 5(a) to 5(d), this hollow box 50 has a top plate 50a and a bottom plate 50b made of steel plates similar to those described above, but has a U-shaped cross section with an open side. The side portion is made of a wire mesh plate 50c such as lath. In addition, the upper and lower sides of both sides are reinforced with angle plates 52, and the sides of each angle plate 52 are integrated with hook-shaped hook portions 54 that are oriented in opposite directions and protrude from the side. The bodies 50 are joined in a state in which they are engaged with each other in a piece-like manner, so that the hollow boxes 50 in adjacent construction sections can be closely arranged in a connected state.

なお、フック部54の係合面内部にコーキング材56を
充填することによって、各中空函体50同士の接合面は
完全にシールされ、水密状態を保つことができる。また
フック部54の係合だけでは結合が弱いので、前記と同
様に一推進作業完了ごとに先後行の中空函体5oのアン
グル板52同士をボルトBによって結合すれば各中空函
体50同士は縦横に結合し、強固な結合となる。
Note that by filling the inside of the engagement surface of the hook portion 54 with the caulking material 56, the joint surfaces of the hollow boxes 50 are completely sealed, and a watertight state can be maintained. Further, since the connection is weak only by the engagement of the hook portions 54, if the angle plates 52 of the preceding and following hollow boxes 5o are connected with each other with bolts B each time one propulsion operation is completed, each hollow box 50 can be connected to each other as described above. It joins vertically and horizontally to form a strong bond.

以上の推進作業は最初の工区と全く同様の作業で行われ
る。
The above promotion work will be carried out in exactly the same way as in the first section.

以下同様の手順を繰り返しつつ防護工区全体に中空函体
50を配置すれば、各先行工区に隣接する後行工区は互
いに金網板50Cを通じて横に連通した状態で縦横マト
リックス状に接合され、平板状の一つの空間を各中空函
体50で囲われた状態に形成する。
By repeating the same procedure and arranging the hollow boxes 50 throughout the protection work area, the subsequent work areas adjacent to each preceding work area will be joined in a vertical and horizontal matrix shape with horizontal communication through the wire mesh plate 50C, and will form a flat plate. One space is surrounded by each hollow box 50.

なお、最終工区では一番最初の工区と同様の中空函体3
0の群を用いて、推進作業を行い、防護工区と非防護区
域とを完全に隔離する。
In addition, in the final section, a hollow box 3 similar to the first section is used.
0 group is used to perform the propulsion work and completely isolate the protected area from the non-protected area.

以上のように推進作業が終了し、中空函体30゜50の
部分と導坑140.14Gとが連通した後は、各機材を
撤去し、既存トンネル10の天井面」二部に形成された
空間内部に縦横にWANを配筋し、コンクリートを打設
して頂板62を構築する。
After the propulsion work was completed as described above and the 30°50 section of the hollow box was connected to the guide shaft 140.14G, each piece of equipment was removed and a tunnel was formed on the ceiling surface of the existing tunnel 10. WAN reinforcement is arranged vertically and horizontally inside the space, concrete is poured, and the top plate 62 is constructed.

そして、頂板62が構築されると、導坑14C914C
内に第2段目の導坑14b、14b内に形成された中段
防護壁19b、19bと、頂板62の両端とを連結する
L字形の上段防護壁19cを鉄筋コンクリートで構築し
た後、導坑14c、14C内の空隙に気泡コンクリート
を充填して、既存トンネル10の両側面および頂部を鉄
筋コンクリート製の防護壁60と頂板62とで囲んで工
事を終了する。
Then, when the top plate 62 is constructed, the guide shaft 14C914C
After constructing an L-shaped upper protection wall 19c with reinforced concrete that connects the middle protection walls 19b, 19b formed inside the second stage guide shaft 14b and both ends of the top plate 62, the guide shaft 14c , 14C is filled with aerated concrete, both sides and the top of the existing tunnel 10 are surrounded by a protective wall 60 and a top plate 62 made of reinforced concrete, and the construction is completed.

なお、この実施例では既存トンネル10の両側部に形成
される導坑12a〜12cを三段重ね状態に形成したが
、既存トンネル10の高さや、作業性を考慮して一段で
あってもいいし、それ以上あってもよい。
In addition, in this embodiment, the guide shafts 12a to 12c formed on both sides of the existing tunnel 10 are formed in a three-tier stacked state, but they may be formed in one layer considering the height of the existing tunnel 10 and workability. However, there may be more.

また、この実施例では既存トンネル10の上部にのみ防
護用の頂板62を設けたが、既存トンネル10の底面側
にも防護版を設けるようにしても良い。この場合には、
最下段の導坑の側面を推進工法によって中空函体30.
50を押し込んで、他端側に貫通させる。しかし、この
場合には既存1ヘンネル10の重1を支える必要があり
、前記実施例のように広範囲を一つの空間とすることは
出来ない場合もあるので、その場合には何か所かに分断
した状態で推進作業を行い、コンクリートを打設した後
次の工区の推進作業を繰り返すようにすればよい。
Further, in this embodiment, the protective top plate 62 is provided only on the top of the existing tunnel 10, but a protective plate may also be provided on the bottom side of the existing tunnel 10. In this case,
A hollow box 30.
50 to penetrate the other end. However, in this case, it is necessary to support the weight 1 of the existing 1 Hennel 10, and there are cases where it is not possible to make a wide area into one space as in the above embodiment, so in that case, it is necessary to support the weight 1 of the existing 1 Hennel 10. It is sufficient to carry out the propulsion work in a divided state, and repeat the propulsion work for the next section after concrete is poured.

さらに、上記実施例で示した断面口字形の中空函体50
の一側開口は、着脱可能な鋼板で構成してJ3き、設置
後にこれを除去するようにしてもよい。
Furthermore, the hollow box 50 with an opening-shaped cross section shown in the above embodiment
The opening on one side may be made of a removable steel plate and removed after installation.

さらにまた、他方の金網板50cは、適宜個所に孔部を
穿設して孔あき板であってもよく、また、防護壁60は
、各導坑14a〜14C内に配筋を施してコンクリート
な打設して、その断面積全体を防護壁60とすることも
できる。
Furthermore, the other wire mesh plate 50c may be a perforated plate with holes drilled at appropriate locations, and the protective wall 60 may be made of concrete by placing reinforcement in each of the shafts 14a to 14C. It is also possible to use the entire cross-sectional area as the protective wall 60 by pouring it.

(効 果) 以上実施例によって詳細に説明したように、この発明の
既存トンネルの防護工法にあっては、少なくとも地表面
に露出する部分が一対の発進導坑のみであって、他の大
多数の作業部分は地中であるため、工事に必要な地表面
積を最小限に止どめることができ、既存トンネル上部の
地下埋設物や、既存建物の基礎に干渉されることなく作
業を進捗できる。
(Effects) As explained in detail using the embodiments above, in the existing tunnel protection method of the present invention, at least the part exposed to the ground surface is only the pair of starting shafts, and most of the other parts are exposed to the ground surface. Since the work part is underground, the ground surface area required for construction can be kept to a minimum, allowing work to proceed without interference from underground objects above the existing tunnel or the foundations of existing buildings. can.

したがって、この発明工法では、特に市街地などで老朽
化したトンネルの防護補強工事に好適であり、最少の工
費で施工できる。
Therefore, the construction method of this invention is particularly suitable for the protection and reinforcement work of dilapidated tunnels in urban areas, and can be performed at minimum construction cost.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図はこの発明工法を示す平断面図、第2図は同側断
面図、第3図は同正断面図、第4図は推進工程を示す正
断面図、第5図(a)は推進工法に用いる中空函体を示
す斜視図、同(b)は断面図、同(C)は燐工区同士の
中空函体の結合状態を示す部分断面図、同(d)は同結
合状態の部分平面図、第6図は防護構造の完成状態を示
す正断面図、第7図は一般の地下連続壁工法によって既
存トンネルの防護を行う場合を示す正断面図であ)。 10・・・既存トンネル 12・・・発進導坑14a−
c・・・導坑  18・・・補強杭28・・・推進ジヤ
ツキ 30・・・中空函体50・・・中空函体   6
0・・・防護壁62・・・頂板(防護版)
Figure 1 is a plan sectional view showing this invention method, Figure 2 is a side sectional view, Figure 3 is a front sectional view, Figure 4 is a front sectional view showing the propulsion process, and Figure 5 (a) is A perspective view showing a hollow box used in the propulsion method, (b) is a cross-sectional view, (c) is a partial cross-sectional view showing the state in which the hollow boxes are connected to each other in phosphor work sections, and (d) is a partial cross-sectional view showing the state in which the hollow boxes are connected to each other. 6 is a front sectional view showing the completed state of the protection structure, and FIG. 7 is a front sectional view showing the case where an existing tunnel is protected by a general underground continuous wall construction method. 10... Existing tunnel 12... Starting shaft 14a-
c... Guide shaft 18... Reinforcement pile 28... Propulsion jack 30... Hollow box 50... Hollow box 6
0... Protective wall 62... Top plate (protective plate)

Claims (2)

【特許請求の範囲】[Claims] (1)既存トンネルの両側部に発進竪坑を掘削し、該発
進竪坑を始点としてトンネル工法によって所定の区間に
既存トンネルの両側面に沿う一対の導坑を掘削し、次い
で推進工法により各導坑の一方から他方に向けて既存ト
ンネルの少くとも頂部に沿う中空状の函体を順次密接状
態に並列配置し、前記導坑と前記函体部とを相互に連通
させた状態でこれらの内部にコンクリートを打設して、
既存トンネルの両側部と頂部をコンクリート防護壁およ
び頂版によつて包囲することを特徴とする既存トンネル
の防護工法。
(1) A starting shaft is excavated on both sides of the existing tunnel, and a pair of guide shafts are excavated along both sides of the existing tunnel in a predetermined section using the tunnel method using the starting shaft as the starting point, and then each guide shaft is excavated using the propulsion method. hollow boxes along at least the top of the existing tunnel from one side to the other side are arranged in close parallel order, and the shaft and the box part are in communication with each other, and pour concrete,
A protection construction method for an existing tunnel characterized by surrounding both sides and the top of the existing tunnel with concrete protective walls and a top slab.
(2)前記各導坑の下方に場所打ち杭工法により順次補
強杭を構築することを特徴とする特許請求の範囲第1項
に記載の既存トンネルの防護工法。
(2) The method for protecting an existing tunnel according to claim 1, characterized in that reinforcing piles are sequentially constructed below each of the shafts by a cast-in-place pile method.
JP1392187A 1987-01-26 1987-01-26 Method of protection construction of existing tunnel Granted JPS63184693A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1392187A JPS63184693A (en) 1987-01-26 1987-01-26 Method of protection construction of existing tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1392187A JPS63184693A (en) 1987-01-26 1987-01-26 Method of protection construction of existing tunnel

Publications (2)

Publication Number Publication Date
JPS63184693A true JPS63184693A (en) 1988-07-30
JPH0416598B2 JPH0416598B2 (en) 1992-03-24

Family

ID=11846639

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1392187A Granted JPS63184693A (en) 1987-01-26 1987-01-26 Method of protection construction of existing tunnel

Country Status (1)

Country Link
JP (1) JPS63184693A (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4919637A (en) * 1972-06-14 1974-02-21
JPS59195996A (en) * 1983-04-20 1984-11-07 日本国有鉄道 Tunnel constructing method
JPS6195199A (en) * 1984-10-16 1986-05-13 財団法人鉄道総合技術研究所 Traverse structure under road foundation

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4919637A (en) * 1972-06-14 1974-02-21
JPS59195996A (en) * 1983-04-20 1984-11-07 日本国有鉄道 Tunnel constructing method
JPS6195199A (en) * 1984-10-16 1986-05-13 財団法人鉄道総合技術研究所 Traverse structure under road foundation

Also Published As

Publication number Publication date
JPH0416598B2 (en) 1992-03-24

Similar Documents

Publication Publication Date Title
US4405260A (en) Method of constructing underpass across railway and highway without affecting normal traffic thereof
KR100289256B1 (en) Tunnel construction method in shallow toffee area
JP2000352296A (en) Method o constructing passage just under underground structure
JP2000291398A (en) Underground structure and construction method therefor
JPS63184693A (en) Method of protection construction of existing tunnel
JP2656892B2 (en) Underground structure construction method and continuous underground wall construction method
JPH0415878B2 (en)
JPH07331997A (en) Constructing method of rock cavern
JPH0721196B2 (en) Reverse construction method of underground structure
JPH07139300A (en) Method for constructing underground construction
JP3511145B2 (en) How to build underground structures
JPS63184695A (en) Method of creation construction of underground concrete block
JPH0355640B2 (en)
JP6967123B1 (en) How to build a box-shaped roof stand
JP3348052B2 (en) Open shield machine
JP2004132124A (en) Pneumatic caisson and pneumatic caisson constructing method
JPS6062327A (en) Construction of underwater continuous wall
JPS63201295A (en) Method of protective construction of existing tunnel
JP3406370B2 (en) Horizontal shaft construction method
JPS6024249B2 (en) How to build a basement
JPS5921831A (en) Reverse placement work
JP2002339691A (en) Earth retaining equipment and open-cut construction method using this equipment
JPH054490B2 (en)
JPH0475994B2 (en)
JP2005213798A (en) Method for constructing retaining wall