JPS6311737A - Method for bonding steel pipe/concrete pillar - Google Patents
Method for bonding steel pipe/concrete pillarInfo
- Publication number
- JPS6311737A JPS6311737A JP15514186A JP15514186A JPS6311737A JP S6311737 A JPS6311737 A JP S6311737A JP 15514186 A JP15514186 A JP 15514186A JP 15514186 A JP15514186 A JP 15514186A JP S6311737 A JPS6311737 A JP S6311737A
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- steel pipe
- column
- joint
- columns
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 229910000831 Steel Inorganic materials 0.000 title claims description 38
- 239000010959 steel Substances 0.000 title claims description 38
- 238000000034 method Methods 0.000 title claims description 10
- 230000003014 reinforcing effect Effects 0.000 claims description 17
- 238000003466 welding Methods 0.000 description 5
- 230000005540 biological transmission Effects 0.000 description 2
- 238000010276 construction Methods 0.000 description 2
- 238000007796 conventional method Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 238000002347 injection Methods 0.000 description 2
- 239000007924 injection Substances 0.000 description 2
- 239000002184 metal Substances 0.000 description 2
- 230000015572 biosynthetic process Effects 0.000 description 1
- 230000015556 catabolic process Effects 0.000 description 1
- 239000003795 chemical substances by application Substances 0.000 description 1
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000006731 degradation reaction Methods 0.000 description 1
- 238000005553 drilling Methods 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
Landscapes
- Rod-Shaped Construction Members (AREA)
- Joining Of Building Structures In Genera (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
〔産業上の利用分野〕
本発明は鋼管コンクリート柱の接合方法の改良に関する
ものである。DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to an improvement in a method for joining steel pipe concrete columns.
(従来の技術)
第6図、第7図は従来性なわれている鋼管コンクリート
柱の接合方法を示すもので、(a)は断面図、(b)は
正面図である。図に示すように、上下の鋼管コンクリー
ト柱(1)の接合部分は、コンクリートを充填せずにお
き、第6図の場合はこのtI4管部分を目板(りを介し
、高張力ボルト(3)により連結した後、コンクリート
(4)を注入して接合するもので、第7図の場合はこの
鋼管部分を裏当て金(7)を用いた現場突合せ溶接(6
)で連結した後、コンクリート(4)を注入して接合す
るものである。なお(5)は鋼管コンクリート柱(1)
の工場打設コンクリートである。(Prior Art) Figures 6 and 7 show a conventional method of joining steel pipe concrete columns, with (a) being a sectional view and (b) being a front view. As shown in the figure, the joint between the upper and lower steel pipe concrete columns (1) is left unfilled with concrete, and in the case of Fig. ), and then concrete (4) is poured into the joint. In the case of Fig. 7, this steel pipe section is welded on-site using a backing metal (7) (6).
), and then concrete (4) is poured into the joint. Note that (5) is a steel pipe concrete column (1)
This is factory-cast concrete.
ところで上記従来の接合方法においては、次に述べるよ
うな問題点がある。However, the conventional bonding method described above has the following problems.
■ 接合部ではコンクリートか不連結となり、鋼管(1
)とコンクリート(4)との付着力が殆んどないので、
接合部のコンクリートを介した。応力伝達ができない。■ At the joint, concrete or unconnected, steel pipe (1
) and concrete (4) have almost no adhesion, so
Through the concrete of the joint. Stress transmission is not possible.
■ 充分な接合耐力を得るためには高張力ボルト(3)
の本数が多くなる。■ High tensile strength bolts (3) are required to obtain sufficient joint strength.
The number of books will increase.
■ 現場突合せ溶接(6)は、角形鋼管コーナ一部の裏
当て金(7)の加工に手間がかかるとともに、信頼性が
低く溶接欠陥が生じ易い。又、鋼管の板、厚か異なる場
合は溶接が困難となる。■ On-site butt welding (6) requires time and effort to process the backing metal (7) at a part of the corner of the square steel pipe, has low reliability, and is prone to welding defects. Also, welding becomes difficult when the steel pipe plates have different thicknesses.
■ 接合部にコンクリート(4)を現場で注入する際、
空気が抜けされず空気溜りが生じて圧縮力を充分に負担
できない可能性がある。■ When pouring concrete (4) into the joint on site,
There is a possibility that the air will not be released and an air pocket will be formed, which may not be able to fully bear the compression force.
本発明は従来の柱の接合方法の上記問題点を解消するた
めになされたもので、強度の信頼性の高い、接合方法を
提供しようとするものである。The present invention was made in order to solve the above-mentioned problems of the conventional column joining method, and it is an object of the present invention to provide a joining method with high strength and reliability.
(問題点を解決するための手段)
上記目的を達成するため、柱にはコンクリートを充填す
る内面突起付角形鋼管を使用し、上部柱の工場打設コン
クリート下面に傾斜を設け、該傾斜の上端部の鋼管に空
気抜き孔を穿設する。ついて接合部に複数個の異形鉄筋
を柱長手方向に配筋し、目板を介して上下柱を高張力ボ
ルトで連結した後、接合部内にコンクリートを注入充填
する。(Means for solving the problem) In order to achieve the above purpose, square steel pipes with internal protrusions filled with concrete are used for the columns, and the lower surface of the factory-cast concrete of the upper column is sloped, and the upper end of the slope is Drill an air vent hole in the steel pipe. Then, a plurality of deformed reinforcing bars are arranged in the longitudinal direction of the columns at the joint, and after connecting the upper and lower columns with high-tensile bolts via battens, concrete is injected into the joint.
(作用)
鋼管柱の内面に突起を備えているので、この突起を介し
て鋼管と充填コンクリート間に機械的な応力伝達が可能
となり、高張力ボルトによる摩擦接合との併用と併せ、
接合部の強度の信顆・性か大幅に向上する。接合部に異
形鉄筋を配筋することにより、高張力ボルトの本数を減
らすことが可能となり、更に、鉄筋二ボルト数の調整に
より最適な継手強度の設計が可能となる。又、上部柱の
工場打設コンクリートの下面に傾斜を設けたので、コン
クリートの現場注入時空気抜きが完全に行なわれ、空気
溜りの介在による接合部の強度低下が防止できる。(Function) Since the inner surface of the steel pipe column is equipped with projections, it is possible to mechanically transmit stress between the steel pipe and the filled concrete through this projection, and in combination with friction bonding using high-tensile bolts,
Significantly improves the strength and strength of joints. By arranging deformed reinforcing bars at the joint, it is possible to reduce the number of high-tensile bolts, and furthermore, by adjusting the number of reinforcing bars, it is possible to design the optimal joint strength. Furthermore, since the lower surface of the factory-cast concrete of the upper column is sloped, air can be completely vented during on-site pouring of concrete, and a decrease in strength of the joint due to air pockets can be prevented.
(発明の実施例)
第1図は本発明の一実施例を示す鋼管コンクリート柱の
接合方法の(a)は側面断面図、(b)は平面断面図、
(c)は側面図で、図中(2)、 (3)は従来装置と
同一部品、(11)は鋼管コンクリート柱、Oのはその
内面突起、03はその工場打設のニークリート、α4)
は上部柱のコンクリート下面、(15)は異形鉄筋、(
I6)はコンクリート、α7)はコンクリート!主人口
、叫は空気抜き孔である。(Embodiment of the Invention) Fig. 1 shows an embodiment of the present invention, showing a method for joining steel pipe concrete columns, (a) is a side sectional view, (b) is a plan sectional view,
(c) is a side view, in which (2) and (3) are the same parts as the conventional device, (11) is a steel pipe concrete column, O is its inner protrusion, 03 is the factory-cast concrete, α4)
is the concrete bottom surface of the upper column, (15) is the deformed reinforcing bar, (
I6) is concrete, α7) is concrete! The main population, the scream, is the air vent hole.
図に示すように、柱にはコンクリートを充填した内面に
突起αつを有する角形鋼管(11)を使用し、この柱の
接合に当っては上部柱の工場打設コンクリート03の下
部α4)に傾斜をつけ、その傾斜の上端部の鋼管に空気
抜き孔を穿設し、上下の柱の接合部に複数個の異形鉄筋
(L19を配設し、目板(2)を介し、高張力ボルト(
3)で上下柱を連結した後、コンクリート注入孔(17
)よりコンクリート(16)を注入する。As shown in the figure, a square steel pipe (11) filled with concrete and having two protrusions on the inner surface is used for the column, and when joining this column, the lower part α4) of the factory-cast concrete 03 of the upper column is used. An air vent hole was drilled in the steel pipe at the upper end of the slope, and multiple deformed reinforcing bars (L19) were installed at the joints of the upper and lower columns, and high-tensile bolts (L19) were installed through the battens (2).
After connecting the upper and lower columns in step 3), connect the concrete injection hole (17
) Pour concrete (16).
鋼管コンクリート柱の接合を上記のように行なうので、
接合部におけるコンクリートは、鋼管内面の突起α乃に
より、一体化するとともに、柱長手方向に鉄筋[15)
を配筋し、さらに鋼管部分の高張力ボルトによる連結も
あって、接合部の強度、信頼性は従来方法に比へ大幅に
向上する。又上部柱の工場打設コンクリートの下面α4
)に傾斜をつけ、その傾斜の上端部の鋼管に空気抜き孔
(18)を穿設したので、コンクリート注入時、内部の
脱気が完全となり空気溜りの発生が抑えられ、空気溜り
によるコンクリートの強度低下は防止される。Since the steel pipe concrete columns are joined as described above,
The concrete at the joint is integrated by the protrusion α on the inner surface of the steel pipe, and the reinforcing bars [15] extend in the longitudinal direction of the column.
By arranging reinforcement and connecting the steel pipe sections with high-tensile bolts, the strength and reliability of the joint are significantly improved compared to conventional methods. Also, the lower surface of the factory-cast concrete of the upper column α4
) is sloped, and an air vent hole (18) is drilled in the steel pipe at the upper end of the slope, so when concrete is poured, the internal air is completely removed, preventing the formation of air pockets, and increasing the strength of the concrete due to air pockets. Degradation is prevented.
第2図は他の実施例を示す接合部の断面図で、下部柱(
1)のコンクリートαつを工場で打設する際、接合部に
配筋する鉄筋(1ツを、同時に配筋しておく方法を示す
ものである。予め配筋するので、その分現場工事が減少
し、現場工事の工期及びコストが低減する。Figure 2 is a sectional view of the joint showing another embodiment, and shows the lower column (
This shows a method of placing reinforcing bars (one reinforcing bar) at the joint at the same time when pouring concrete α in 1) at a factory.Since the reinforcing bars are placed in advance, the on-site work is reduced accordingly. This reduces the construction period and cost of on-site construction.
第3図、第4図及び第5図は、鉄筋の形を異にする他の
実施例を示す(a)は平面断面図、(b)は側面断面図
である。3, 4, and 5 show other embodiments in which reinforcing bars have different shapes. (a) is a plan sectional view, and (b) is a side sectional view.
図にみるように、鉄筋の形が夫々異なっており、第3図
はヘッド付丸鋼、第4図は突起付山形鋼、第5図は外面
突起付鋼管を夫々の鉄筋の代りに用いた例を示している
。As shown in the figures, the shapes of the reinforcing bars are different. Figure 3 uses a round bar with a head, Figure 4 uses an angle bar with a protrusion, and Figure 5 uses a steel pipe with an external protrusion instead of each reinforcing bar. An example is shown.
なお、本実施例においては鋼管内面に突起を設けたが、
突起の代りにスタッドジベル等を固着してもよい。Note that in this example, a protrusion was provided on the inner surface of the steel pipe, but
A stud dowel or the like may be fixed instead of the protrusion.
また、接合部の発生応力か小さい場合には、高張力ボル
トによる連結を省略することも可能である。Furthermore, if the stress generated at the joint is small, it is possible to omit the connection using high-tensile bolts.
(発明の効果)
本発明は、コンクリートを充填した内面突起付鋼管の柱
を接合する場合、接合部に村長手方向に鉄筋を配筋し、
上部柱の工場打設コンクリート下面に傾斜をつけ、鋼管
に空気抜き孔を穿設して接合部にコンクリートを注入し
たので、次に述べるような優れた効果をあげることがで
きた。(Effect of the invention) When joining columns of steel pipes with internal projections filled with concrete, the present invention arranges reinforcing bars in the longitudinal direction of the joint,
By sloping the lower surface of the factory-cast concrete for the upper column, drilling air vents in the steel pipes, and injecting concrete into the joints, we were able to achieve the excellent effects described below.
■ 現場溶接を必要とせず、内面突起付き鋼管、異形鉄
筋によるコンクリートの接合と高張力ボルト摩擦接合に
よる鋼管の接合との併用により、信頼性及び自由度の高
い接合部の設計が可能となる。■Without the need for on-site welding, it is possible to design joints with high reliability and flexibility by combining concrete joints using steel pipes with internal protrusions, deformed reinforcing bars, and steel pipe joints using high-tensile bolt friction welding.
■ 内面突起付鋼管の使用により、コンクリート間に機
械的応力伝達が可能となり、異形鉄筋の配筋によって高
張力ボルトの使用個数を大幅に減少させることができる
。■ The use of steel pipes with internal protrusions enables mechanical stress transmission between concrete, and the use of deformed reinforcing bars can significantly reduce the number of high-tensile bolts used.
■ 注入コンクリートの空気抜きが容易で接合部の信頼
性か向上する。■ It is easy to vent air from poured concrete, improving the reliability of joints.
■ 上下柱の鋼管板厚か異なっていても接合が可能であ
る。■ It is possible to join even if the steel pipe plate thicknesses of the upper and lower columns are different.
第1図は本発明の一実施例である鋼管コンクリート柱の
接合方法を示す(a)は側面断面図、(b)は平面断面
図、(C)は正面区、第2図は他の実施例の側面断面図
、第3図〜第5図はさらに他の実施例を示す(a)は平
面断面図、(b)は4fil団断面図、第6図、第7図
は従来の鋼管コンクリート柱の接合部の(a)は側面断
面図、(b)は側面図である。
図中(lυは鋼管コンクリート柱、Ozはその内面突起
、03は柱の工場打設のコンクリート、α4)は上部柱
の工場打設コンクリートの下面、(15)は鉄筋、(+
6)は接合部のコンクリート、(17)はコンクリート
注入孔、(18)は空気抜き孔である。
代理人 弁理士 佐 藤 正 年
第7図
(Q) (b)Figure 1 shows a method for joining steel pipe concrete columns according to an embodiment of the present invention. (a) is a side sectional view, (b) is a plan sectional view, (C) is a front view, and Figure 2 is another embodiment. The side sectional view of the example, and FIGS. 3 to 5 show still other embodiments. (a) is a plan sectional view, (b) is a 4fil group sectional view, and FIGS. 6 and 7 are conventional steel pipe concrete. (a) is a side cross-sectional view, and (b) is a side view of the joint portion of the pillars. In the figure (lυ is a steel pipe concrete column, Oz is its inner protrusion, 03 is the factory-cast concrete of the column, α4) is the bottom surface of the factory-cast concrete of the upper column, (15) is the reinforcing bar, (+
6) is the concrete at the joint, (17) is the concrete injection hole, and (18) is the air vent hole. Agent Patent Attorney Tadashi Sato Figure 7 (Q) (b)
Claims (1)
トを充填した内面突起付角形鋼管を使用し、上部柱の工
場打設コンクリートの下面に傾斜を設け、該傾斜面の上
端部の鋼管に空気抜き孔を穿設し、柱の接合部に複数個
の異型鉄筋を柱の長手方向に配筋して、上下柱の鋼管部
を目板を介し高張力ボルトで連結後、接合部鋼管内にコ
ンクリートを充填して接合部を構成したことを特徴とす
る鋼管コンクリート柱の接合方法。When joining steel pipes and concrete columns, square steel tubes with internal protrusions filled with concrete are used for the columns, the lower surface of the factory-cast concrete of the upper column is sloped, and air vent holes are drilled in the steel tube at the upper end of the slope. After installing multiple deformed reinforcing bars in the column longitudinal direction at the column joints and connecting the steel pipes of the upper and lower columns with high-tensile bolts through battens, concrete is filled into the steel pipes at the joints. A method for joining a steel pipe concrete column, characterized in that the joint is configured by
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP15514186A JPS6311737A (en) | 1986-07-03 | 1986-07-03 | Method for bonding steel pipe/concrete pillar |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP15514186A JPS6311737A (en) | 1986-07-03 | 1986-07-03 | Method for bonding steel pipe/concrete pillar |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS6311737A true JPS6311737A (en) | 1988-01-19 |
Family
ID=15599440
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP15514186A Pending JPS6311737A (en) | 1986-07-03 | 1986-07-03 | Method for bonding steel pipe/concrete pillar |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS6311737A (en) |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS62288236A (en) * | 1986-06-09 | 1987-12-15 | 日本鋼管株式会社 | Connection of steel pipe concrete pillar |
-
1986
- 1986-07-03 JP JP15514186A patent/JPS6311737A/en active Pending
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS62288236A (en) * | 1986-06-09 | 1987-12-15 | 日本鋼管株式会社 | Connection of steel pipe concrete pillar |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP3978642B2 (en) | Combined pile and girder structure | |
JP4233106B2 (en) | Seismic reinforcement method for existing pillars | |
JPS6047140A (en) | Steel plate concrete structure | |
JPS6311737A (en) | Method for bonding steel pipe/concrete pillar | |
JP3802996B2 (en) | Construction method of flat slabs using steel pipe concrete columns | |
JP4233105B2 (en) | Seismic reinforcement method for existing pillars | |
JPH0610420A (en) | Method for connecting precast concrete member | |
JP3776330B2 (en) | Seismic walls of existing buildings and construction methods | |
JP3851563B2 (en) | Frame reinforcement structure and its construction method | |
JP3826348B2 (en) | Construction method of composite wall with mountain retaining core and underground outer wall | |
JPS62288236A (en) | Connection of steel pipe concrete pillar | |
JPS61179947A (en) | Steel pipe concrete composite pillar | |
JP2545626Y2 (en) | PC beam | |
JP3829081B2 (en) | Reinforcement method for reinforced concrete columns | |
JPS5965149A (en) | Joint structure of iron wire | |
JPS6367347A (en) | Method for connecting precast concrete pillar | |
JPS62264235A (en) | Square steel pipe concrete pillar | |
JP2001262707A (en) | Junction structure for reinforced concrete column and steel beam | |
JP3218377B2 (en) | Beam joint structure | |
JPS6332030A (en) | Method for bonding pillar | |
JPH019852Y2 (en) | ||
JPH0248539Y2 (en) | ||
JP3639544B2 (en) | Frame reinforcement structure | |
JPS62264236A (en) | Square steel pipe concrete pillar | |
JPS61126248A (en) | Pc pillar and its production |