JPS62280491A - Method of pre-fabricated perforated pipe propulsion construction - Google Patents

Method of pre-fabricated perforated pipe propulsion construction

Info

Publication number
JPS62280491A
JPS62280491A JP12323986A JP12323986A JPS62280491A JP S62280491 A JPS62280491 A JP S62280491A JP 12323986 A JP12323986 A JP 12323986A JP 12323986 A JP12323986 A JP 12323986A JP S62280491 A JPS62280491 A JP S62280491A
Authority
JP
Japan
Prior art keywords
prefabricated
pipe
prefabricated pipe
soil
holes
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP12323986A
Other languages
Japanese (ja)
Inventor
阿部 秀人
秀一 田中
光男 原田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kandenko Co Ltd
Tokyo Electric Power Co Holdings Inc
Original Assignee
Tokyo Electric Power Co Inc
Kandenko Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tokyo Electric Power Co Inc, Kandenko Co Ltd filed Critical Tokyo Electric Power Co Inc
Priority to JP12323986A priority Critical patent/JPS62280491A/en
Publication of JPS62280491A publication Critical patent/JPS62280491A/en
Pending legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 3、発明の詳細な説明 (産業上の利用分野) この発明はケーブル保蔵用の管路を地中に形成せしめる
プレハブ多孔管推進工法に関するものである。
[Detailed Description of the Invention] 3. Detailed Description of the Invention (Field of Industrial Application) This invention relates to a prefabricated perforated pipe propagation method for forming a cable storage conduit underground.

(従来の技術) 従来ケーブル保蔵用管を地中に形成するには、先端にカ
ッター等を有する掘進機のあとに推進管を配し、これを
後方からジヤツキ等の押圧装置で押して推進せしめ、土
中に推進管を埋設し、この埋設した推進管の中に必要数
の小径のケーブル保蔵用管を挿入し、さらにその後、推
進管とケーブル保蔵用管との隙間に適宜の充填材を裏込
めしていた。
(Prior art) Conventionally, in order to form a cable storage pipe underground, a propulsion pipe is placed behind an excavator having a cutter or the like at the tip, and the pipe is pushed from behind with a pushing device such as a jack to propel it. A propulsion pipe is buried in the soil, a required number of small diameter cable storage pipes are inserted into the buried propulsion pipe, and then the gap between the propulsion pipe and the cable storage pipe is lined with an appropriate filler. I was putting a lot of effort into it.

あるいは、ケーブル保蔵用管路を形成しようとする箇所
に、予め掘削機と、削土の移送手段たるスクリューコン
ベア等を内蔵した誘導管とを到達立坑まで貫通させて、
削土の排出が完了した後、所定数のケーブル保蔵用管路
を自体に貫設した多孔管路単体を順次押し込んでいくも
のが提案されている。
Alternatively, an excavator and a guiding pipe equipped with a screw conveyor, which is a means of transporting the excavated soil, are passed through the area where the cable storage conduit is to be formed up to the reaching shaft.
It has been proposed that after the excavation of soil is completed, a single porous conduit having a predetermined number of cable storage conduits inserted therein is successively pushed into the conduit.

(発明が解決しようとする問題点) しかしながら前者の工法によれば、推進管の埋設、次に
ケーブル保蔵用管の挿入、そして最後に充填材の注入、
固化という作業手順を踏まえなければ、ケーブル保蔵用
の管路を地中に形成させることができず、そのためまず
各作業に相応する設備機器が必要であり、またさらに各
個の作業に伴う手間、作業移行のための準備等もあって
、結果的に作業に要する労力、時間、費用は多大なもの
があった。
(Problem to be solved by the invention) However, according to the former construction method, the propulsion pipe is buried, then the cable storage pipe is inserted, and finally the filler is injected.
Unless the work procedure of solidification is taken into account, conduits for cable storage cannot be formed underground. Therefore, equipment suitable for each work is first required, and in addition, the labor and work associated with each work is required. Due to preparations for the transition, the effort, time, and expense required for the work was enormous.

一方、後者の工法によれば、結果的に二度手間であって
時間がかかり、また掘削機、多孔管路単体の他に移送手
段を内蔵した誘導管を発進側立坑から到達側立坑に至る
までの長さの分だけ用意しなければならない。
On the other hand, the latter method results in double work and time, and in addition to the excavator and perforated pipe, a guide pipe with built-in transport means is connected from the starting shaft to the destination shaft. You must prepare enough for the length up to.

(問題点を解決するための手段) この考案はかかる点に鑑みてなされたものであり、ケー
ブル保蔵用管路を構成する貫通孔を自体の軸方向に設け
たプレハブ管を掘進機の後端に配してこれを直接、未掘
削の土中に推進工法によって押し込み、掘削土砂はプレ
ハブ管にある貫通孔を通して直接後方へ排出する工法を
提供して問題の解決を図るものである。
(Means for solving the problem) This idea was made in view of the above points, and a prefabricated pipe with a through hole forming a cable storage conduit in the axial direction is installed at the rear end of the excavator. This problem is solved by providing a construction method in which the excavated soil is directly pushed into unexcavated soil using a propulsion method, and the excavated soil is discharged directly backward through a through hole in the prefabricated pipe.

而してこの発明の具体的構成について言えば、ケーブル
保蔵用管路を構成する貫通孔を自体の軸方向に適宜敷設
けたプレハブ管を、カッターなどの掘削装置並びに掘削
土排出手段を備えた掘進機の後端に配して、これらを立
坑の発進側内側面から未だ掘削していない土中に入れ、
プレハブ管の後端を押圧装置により押し、掘削土をプレ
ハブ管の貫通孔を通じて後方へ排出させる。そして一定
長推進させる毎に他のプレハブ管を、押し込んだプレハ
ブ管の後端から継ぎ足し各プレハブ管の貫通孔を各々合
致させながら、適宜手段、例えばボルトによる固着やプ
レハブ管に別途貫通孔を穿設してこれにPC鋼線等を挿
通させる等によって各プレハブ管相互を係止せしめ、順
次最後部のプレハブ管を押して掘削土をプレハブ管の貫
通孔から排出させながら推進させて、各プレハブ管を土
中に残置させるものである。
As for the specific configuration of the present invention, a prefabricated pipe having through-holes configuring the cable storage conduit appropriately laid in its axial direction can be excavated using an excavating device such as a cutter and an excavated soil discharge means. Place them at the rear end of the machine and insert them into the soil that has not yet been excavated from the inside surface of the starting side of the shaft.
The rear end of the prefabricated pipe is pushed by a pressing device, and the excavated soil is discharged rearward through the through hole of the prefabricated pipe. Then, each time the prefabricated tube is propelled a certain length, another prefabricated tube is added from the rear end of the pushed prefabricated tube, and while the through holes of each prefabricated tube are aligned with each other, appropriate means such as fixation with bolts or separate through holes are drilled in the prefabricated tube. The prefabricated pipes are locked to each other by inserting a PC steel wire or the like through the prefabricated pipes, and the last prefabricated pipe is sequentially pushed to discharge the excavated soil from the through hole of the prefabricated pipe. is left in the soil.

(作 用) 推進中に生じる削土は、掘進機から、ケーブル保蔵用管
路を構成する各プレハブ管の貫通孔から排出されるので
、各貫通孔は推進中には土砂排出の経路となり、施工が
完了した後はケーブル保蔵用管路となる。もちろんこの
貫通孔に適宜のパイプを通してもよい。
(Function) The excavated earth generated during propulsion is discharged from the excavator through the through holes of each prefabricated pipe that constitutes the cable storage conduit, so each through hole serves as a path for earth and sand discharge during propulsion. After construction is complete, it will be used as a cable storage conduit. Of course, an appropriate pipe may be passed through this through hole.

また各プレハブ管は適宜手段によって相互に係止されて
いるから、推進中にズしたり、外れたりすることはない
Furthermore, since the prefabricated tubes are mutually locked by appropriate means, they will not shift or come off during propulsion.

(実施例) 以下、この考案の実施例を図について説明する。(Example) Hereinafter, embodiments of this invention will be described with reference to the drawings.

第1図、第2図は本実施例に使用するプレハブ管1につ
いての図であり、各図から明らかなようにプレハブ管1
は略円柱形状であり、その端面−側には各角部が丸みを
おびた略長方形の凸部1aを有し、他側にはこの凸部1
aに合致する凹部1bを設けである。
Figures 1 and 2 are diagrams of the prefabricated pipe 1 used in this embodiment, and as is clear from each figure, the prefabricated pipe 1
has a substantially cylindrical shape, and has a substantially rectangular convex portion 1a with rounded corners on its end face side, and this convex portion 1a on the other side.
A recessed portion 1b is provided that matches the shape of the recessed portion 1b.

本実施例におけるケーブル保蔵用管路を構成する貫通孔
は、この凸部1a、凹部1bを結ぶ範囲内で計6ケ所の
円形の貫通孔2.3.4.5.6.7がプレハブ管lの
軸方向に穿設しである。またこれとは別に、後述する管
相互のズレを防止するだめの係止手段に供する貫通型の
連結孔8.9.10.11がやはりプレハブ管1の軸方
向に穿設しである。また凸部1aの側面外周にはシール
材12を被覆させである。
The through holes constituting the cable storage conduit in this embodiment are a total of six circular through holes 2.3.4.5.6.7 within the range connecting the convex portion 1a and the concave portion 1b. It is perforated in the axial direction of l. Separately from this, a through-type connecting hole 8.9.10.11 is also bored in the axial direction of the prefabricated pipe 1 and serves as a locking means for preventing mutual displacement of the pipes, which will be described later. Further, the outer periphery of the side surface of the convex portion 1a is coated with a sealing material 12.

次に実施例に係る施工方法について第3図以下について
説明する。第3図は施工が途中まで進んだ状態を示して
おり、とは先頭にカッターηを備えた掘進機であり、掘
進機21の後端には、既に推進させたプレハブ管るが位
置しており、さらにその後には、次に継ぎ足して推進さ
せたプレハブ管あがある。
Next, the construction method according to the embodiment will be explained with reference to FIG. 3 and subsequent figures. Figure 3 shows a state in which construction has progressed halfway, and is an excavator equipped with a cutter η at the front, and a prefabricated pipe that has already been propelled is located at the rear end of the excavator 21. After that, there is a prefabricated pipe that was then added and propelled.

本実施例における掘進機21は、内部後方に隔壁5を設
け、この隔壁5と後端面あとの間に駆動装置Mを設け、
この駆動装置γによってカッターn及び削土の移送手段
たるスクリューコンベアあを回転させるものである。掘
進機21内の方向修正第四後方で、スクリューコンベア
四の下方に位置する室には削土排出手段たる土砂圧送ポ
ンプ加が設置しである。本実施例に使用したこの土砂圧
送ポン7’30は、後方へスライド自在な外側シリンダ
ー30a、及び外側シリンダー30aの内側にある内側
シリンダー30b、内側シリンダーの中に位置するピス
トン30c、及びピストン30cを作動させる油圧ジヤ
ツキ30dかも成り、スクリューコンベアあの末端部周
辺の土砂室31へ向けて外側シリンダー30aがスライ
ドして土砂室内の削土を取り込み、隔壁5の下方に設け
た圧送口32に直結する。圧送口32には圧送用パイプ
あが設けてあり、その後端は掘進機21後端の排出口あ
へ接続されている。
The excavator 21 in this embodiment is provided with a partition wall 5 at the rear of the interior, and a drive device M is provided between the partition wall 5 and the rear end surface.
This drive device γ rotates the cutter n and the screw conveyor A, which is a means for transporting excavated soil. An earth and sand pressure pump serving as excavation and discharge means is installed in a chamber located below the screw conveyor 4 at the rear of the direction adjustment unit 4 in the excavator 21. This earth and sand pump 7'30 used in this example includes an outer cylinder 30a that can freely slide rearward, an inner cylinder 30b located inside the outer cylinder 30a, a piston 30c located inside the inner cylinder, and a piston 30c. A hydraulic jack 30d is activated, and the outer cylinder 30a slides toward the earth and sand chamber 31 around the end of the screw conveyor to take in the excavated soil in the earth and sand chamber, and is directly connected to a pressure feeding port 32 provided below the partition wall 5. The pressure feed port 32 is provided with a pressure feed pipe, and its rear end is connected to a discharge port at the rear end of the excavator 21.

掘進機21の後端は、前出プレハブ管器の凸部211が
嵌まりこむ形状をなし、プレハブ管器の−の貫通孔と排
出口あとは合致している。
The rear end of the excavator 21 has a shape into which the convex portion 211 of the prefabricated pipe is fitted, and the negative through hole of the prefabricated pipe matches the discharge port.

ア、アは夫々PC鋼線であり、プレハブ管お、冴の各々
の連結孔37、羽を貫通しており、また相互に接続され
ているものである。PC鋼線あの掘進機21側端部、す
なわち前方端部は連結孔訂の前方端部周縁に係止させで
ある(なお説明の便宜上、第3図以下に図示する各プレ
ハブ管の貫通孔と連結孔とは、各々の相対的位置関係を
変えて図示している)。また図にはあられれないが、プ
レハブ管相互のズレを防止するPC鋼線は、各プレハブ
管23.24において他に3ケ所貫通させであるもので
ある。
A and A are PC steel wires, which pass through the connecting holes 37 and wings of the prefabricated tubes O and S, respectively, and are connected to each other. The end of the PC steel wire on the side of the excavator 21, that is, the front end, is fixed to the periphery of the front end of the connecting hole. The connecting holes are illustrated with their relative positions changed.) Although not shown in the figure, the PC steel wires that prevent the prefabricated tubes from shifting from each other are passed through three other locations in each prefabricated tube 23 and 24.

而してこの後の作業について言うと、まず継ぎ足そうと
するプレハブ管39の連結孔4oにPC鋼線41を貫通
させ、既に推進させである最後部のプレハブ管翼のPC
鋼線アと接続させる。そのあとプレハブ管39の凸部3
9aをプレハブ管送の凹部24bへと挿入させ、各プレ
ハブ管翼、39の夫々の貫通孔42,43その他を相互
に合致させて、PC’iA線41を他物で緊張させなが
ら、発進側立坑■内に設置しである元押ジヤツキ45の
押し輪46をプレハブ管39の後端にあてがって押圧さ
せる。このようにして推進は第参図のように行われる。
Regarding the subsequent work, first pass the PC steel wire 41 through the connection hole 4o of the prefabricated pipe 39 to be added, and connect the PC of the rearmost prefabricated pipe wing that has already been propelled.
Connect to steel wire A. After that, the convex portion 3 of the prefabricated pipe 39
9a into the recess 24b of the prefabricated pipe feed, and align the through holes 42, 43, etc. of each prefabricated pipe wing 39 with each other, and while tensioning the PC'iA wire 41 with another object, The push ring 46 of the original push jack 45 installed in the shaft (2) is applied to the rear end of the prefabricated pipe 39 to press it. In this way, the propulsion is carried out as shown in Figure 1.

推進している間、カッターnが切削した削土はスクリュ
ーコンベア路によって土砂室31へと移送され、土砂圧
送ポンプ美のピストン30cによって、圧送口翌から圧
送用パイプ関さらに排出口あ、さらに排出口調に合致さ
せであるプレハブ管器の貫通孔47からこの貫通孔47
に合致している他のプレハブ管酢及び39の各貫通孔4
2,43を経由して、発進側立坑44へ排出される。
During the propulsion, the excavated soil cut by the cutter n is transferred to the earth and sand chamber 31 by the screw conveyor path, and is transferred from the pressure feed port to the pressure feed pipe section, and then to the discharge port by the soil pressure pump beauty piston 30c. This through hole 47 is made from the through hole 47 of the prefabricated pipe that matches the tone.
Other prefabricated pipes that match and 39 through holes 4
2 and 43, and is discharged to the starting side shaft 44.

なおこの場合各プレハブ管23.24.39の各貫通孔
47.42.43の内部に予め適宜の排出パイプ、ホー
ス(図外)を挿通させておき、この排出パイプ、ホース
の中で削土の排出、搬送を行えばより良好な排出ができ
る。
In this case, an appropriate discharge pipe and hose (not shown) are inserted into the through holes 47, 42, and 43 of each prefabricated pipe 23, 24, and 39 in advance, and the earth is excavated inside the discharge pipe and hose. Better discharge can be achieved by discharging and transporting.

プレハブ管Iの推進が完了すると、元押ジヤツキ45の
押し輪46を第5図のように引き戻し、以後再び@3図
以下の作業を繰り返していけばよい。
When the propulsion of the prefabricated pipe I is completed, the push ring 46 of the pusher jack 45 is pulled back as shown in FIG. 5, and the operations shown in FIG. 3 and subsequent steps are repeated again.

実施例に係る施工方法は上述の如くであり、本実施例に
おいて使用したプレハブ管は第1図に示中に掘削土など
が、継手部から漏れることはない。
The construction method according to this example is as described above, and the prefabricated pipe used in this example, as shown in FIG. 1, does not leak excavated soil or the like from the joint.

しかも施工完了後はケーブル保蔵用管路となる貫通孔の
気密性も保持される。
Furthermore, after the construction is completed, the airtightness of the through hole, which will serve as the cable storage conduit, will be maintained.

また上記実施例ではpca線を貫通型の連結孔に貫通さ
せることによって各プレハブ管相互のズレ防止に寄与す
るが、このPC鋼線を適宜手段で強く緊張させることに
よって、各プレハブ管相互の連結状態は強固となり、所
謂「しまり」が良くなるものである。熱論これに限らず
、各プレハブ管相互のズレの防止は例えば非貫通形のビ
ン孔をプレハブ管の一端に穿設し、他端にビンを設ける
等の手段によっても構わない。
In addition, in the above embodiment, the PCA wire is passed through the through-type connecting hole, which contributes to preventing the mutual displacement of the prefabricated pipes. The condition becomes stronger and the so-called "tightness" improves. The invention is not limited to this, but prevention of misalignment between the prefabricated tubes may be achieved by, for example, providing a non-penetrating bottle hole at one end of the prefabricated tube and a vial at the other end.

なお、削土排出手段としては圧送ポンプの他に、分離、
接続自在の小径のスクリューコンベアラ、掘進機から各
プレハブ管の貫通孔の中に通すことも提案できる。
In addition to pressure pumps, separation,
It is also possible to propose a small-diameter screw conveyor that can be freely connected, or a tunneling machine that passes through the through holes of each prefabricated pipe.

(発明の効果) この発明によればケーブル保蔵用管路の地中への形成が
、プレハブ管の推進という作業のみで行える。またプレ
ハブ管の貫通孔は、推進中には削土の排出経路となり、
施工完了後はケーブル保蔵用管路を構成し、無駄がなく
極めて合理的である。
(Effects of the Invention) According to the present invention, a cable storage conduit can be formed underground by simply pushing a prefabricated pipe. In addition, the through holes in the prefabricated pipes serve as excavated soil discharge routes during propulsion.
After the construction is completed, it will be constructed as a conduit for storing cables, which is extremely efficient and eliminates waste.

しかも従来この種の工法においてみられたような、まず
はじめに削土排出手段を内蔵した誘導管等を一旦到達側
立坑まで推進させて、貫通させるという作業が不要であ
り、従来工法に比してその作業時間は飛躍的に短縮され
、それとともに労力、手間、使用する諸機器も少なくて
済み、総じて単純な作業によって行える。
Moreover, unlike conventional construction methods of this type, there is no need to first propel a guide pipe with a built-in excavation and discharge means to the destination shaft and then penetrate it, which is superior to conventional construction methods. The work time is dramatically shortened, and at the same time, less labor, effort, and equipment are required, and the work is generally simple.

゛  また作業に要する設備、機材も従来のものを殆ん
どそのまま用いることが出来、無駄がない。
゛ Furthermore, most of the equipment and equipment required for the work can be used as they are, so there is no waste.

しかも新たに使用することになるプレハブ管の構造も極
めて簡易で、その製造も比較的容易であるから、作業コ
ストの低減も実現できるなど、この発明の実用的効果は
高いものである。
Moreover, the structure of the prefabricated pipe to be newly used is extremely simple and its manufacture is relatively easy, so that the work cost can be reduced, and the practical effects of this invention are high.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図、第2図はそれぞれ実施例に使用するプレハブ管
のそれぞれ右側面図、正面図、第3図乃至第5図は実施
例による施工過程を示す側面説明図である。 なお図中、1.23.24.39はプレハブ管、2.3
.4.5.6.7.42.43.47は貫通孔、8.9
.10.11.37、関、栃は連結孔、21は掘進機、
刃は土砂圧送ポンプ、ηはカッター、35.36.41
はP Cf141flis ”は発進側立坑、45は元
押ジヤツキ、46は押し輪である。
FIGS. 1 and 2 are a right side view and a front view, respectively, of a prefabricated pipe used in the example, and FIGS. 3 to 5 are explanatory side views showing the construction process according to the example. In addition, in the figure, 1.23.24.39 are prefabricated pipes, 2.3
.. 4.5.6.7.42.43.47 is a through hole, 8.9
.. 10.11.37, Seki and Tochi are connecting holes, 21 is an excavator,
The blade is a sand pump, η is a cutter, 35.36.41
``PCf141flis'' is the starting side shaft, 45 is the main push jack, and 46 is the push ring.

Claims (1)

【特許請求の範囲】[Claims] ケーブル保蔵用管路を構成する貫通孔を自体の軸方向に
適宜敷設けたプレハブ管を、掘削装置並びに掘削土排出
手段を備えた掘進機の後端に配して、これらを立坑の発
進側内側面から未掘削の土中に入れ、プレハブ管の後端
を押圧装置により押し、掘削土はプレハブ管の貫通孔を
通じて後方へ排出させ、一定長推進させる毎に他のプレ
ハブ管を後方から継ぎ足して相互の貫通孔を各々合致さ
せながらプレハブ管相互を適宜手段で係止せしめ、再び
これを押圧装置で押して、各プレハブ管を推進させて土
中に残置させることを特徴とする、プレハブ多孔管推進
工法。
A prefabricated pipe with appropriate through-holes laid in the axial direction that constitutes the cable storage conduit is placed at the rear end of the excavation equipment and the excavation machine equipped with the means for discharging excavated soil, and these are placed inside the starting side of the shaft. The prefabricated pipe is inserted into unexcavated soil from the side, and the rear end of the prefabricated pipe is pushed by a pushing device, and the excavated soil is discharged backward through the through hole of the prefabricated pipe. Every time it is propelled a certain length, another prefabricated pipe is added from the rear. Prefabricated porous pipe propulsion characterized in that the prefabricated pipes are locked to each other by appropriate means while matching each other's through holes, and then pushed again by a pressing device to propel each prefabricated pipe and leave it in the soil. Construction method.
JP12323986A 1986-05-30 1986-05-30 Method of pre-fabricated perforated pipe propulsion construction Pending JPS62280491A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12323986A JPS62280491A (en) 1986-05-30 1986-05-30 Method of pre-fabricated perforated pipe propulsion construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12323986A JPS62280491A (en) 1986-05-30 1986-05-30 Method of pre-fabricated perforated pipe propulsion construction

Publications (1)

Publication Number Publication Date
JPS62280491A true JPS62280491A (en) 1987-12-05

Family

ID=14855641

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12323986A Pending JPS62280491A (en) 1986-05-30 1986-05-30 Method of pre-fabricated perforated pipe propulsion construction

Country Status (1)

Country Link
JP (1) JPS62280491A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01180590U (en) * 1988-06-08 1989-12-26
JPH0258088U (en) * 1988-10-18 1990-04-26
JPH0510073Y2 (en) * 1987-11-26 1993-03-11
US9975083B2 (en) 2013-05-03 2018-05-22 Fluor Technologies Corporation Systems and methods for multi-celled gas processing

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6155571B2 (en) * 1982-09-21 1986-11-28 Kawasaki Steel Co

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6155571B2 (en) * 1982-09-21 1986-11-28 Kawasaki Steel Co

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0510073Y2 (en) * 1987-11-26 1993-03-11
JPH01180590U (en) * 1988-06-08 1989-12-26
JPH0258088U (en) * 1988-10-18 1990-04-26
US9975083B2 (en) 2013-05-03 2018-05-22 Fluor Technologies Corporation Systems and methods for multi-celled gas processing

Similar Documents

Publication Publication Date Title
JPS62280491A (en) Method of pre-fabricated perforated pipe propulsion construction
JPH04106293A (en) Underground connection method of shield tunnel
JP3170215B2 (en) Pipe burial method
JP2004324256A (en) Shield machine
US3487649A (en) Apparatus for use in the construction of concrete lined tunnels
JP2835388B2 (en) Branch shield method
JP3093437B2 (en) Shield machine
JP4205237B2 (en) Equipment and methods for tunnel construction and pipe laying.
JP3181242B2 (en) Equipment for middle pressing method
JP3579373B2 (en) Branch excavating shield excavator and branch shield excavating method
JP7162501B2 (en) Outer shell shield construction method using shield starting base and circumferential tunnel
JP3780708B2 (en) Parent-child shield machine
JP3088980B2 (en) Branch shield excavation method and shield excavator capable of branch excavation
JPH0345194B2 (en)
JP2586216Y2 (en) Pipe burial equipment
JPH02229396A (en) Separate type shield excavator
JP3681371B2 (en) Shield digging machine capable of branch start and branch shield digging method
JP2835387B2 (en) Branch shield method
JP3519640B2 (en) Primary propulsion pipe and excavation method for small-diameter tunnel excavation
JP2557850Y2 (en) Pipe burial equipment
JP2551085Y2 (en) Pipe burial equipment
JP2975568B2 (en) Shield excavator capable of branch excavation
JPS59134298A (en) Pipe propelling method
JPS60238599A (en) Enlarging shield drilling machine
JPH03267494A (en) Pipe roof method and pipe roof machine