JPS6221989A - Excavation method of shielding excavator - Google Patents

Excavation method of shielding excavator

Info

Publication number
JPS6221989A
JPS6221989A JP60159779A JP15977985A JPS6221989A JP S6221989 A JPS6221989 A JP S6221989A JP 60159779 A JP60159779 A JP 60159779A JP 15977985 A JP15977985 A JP 15977985A JP S6221989 A JPS6221989 A JP S6221989A
Authority
JP
Japan
Prior art keywords
rod
reaction force
reaction
concrete
excavation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP60159779A
Other languages
Japanese (ja)
Inventor
義幸 高橋
栄 中井
角田 康治
古田 敏夫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsui Construction Co Ltd
Original Assignee
Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsui Construction Co Ltd filed Critical Mitsui Construction Co Ltd
Priority to JP60159779A priority Critical patent/JPS6221989A/en
Publication of JPS6221989A publication Critical patent/JPS6221989A/en
Pending legal-status Critical Current

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 (a)、産業上の利用分野 本発明は、覆工を現場打ちのコンクリ−1−で構築する
と共に、当該覆工中にトンネルの掘削方向に埋設された
反力棒て反力を取・りっつ掘進する、シールド掘削機の
掘進方法に関する。
DETAILED DESCRIPTION OF THE INVENTION (a) Industrial Field of Application The present invention is directed to constructing a lining with cast-in-place concrete, and to construct a reaction force buried in the lining in the excavation direction of a tunnel. This article relates to an excavation method using a shield excavator, which uses a bar to remove reaction force and excavate.

(b)、従来の技術 通常、覆工を現場打ちのコンクリートで構築すると、打
設されたコンクリートが所定の強度に達するまで、当該
打設されたコンクリートからシールドを掘削機のt掘進
の際の反力を取ることは出来ない。そこて、覆工中に、
反力を取るための反力棒を、トンネルの庭前方向に埋設
しておき、当該反力棒を介して掘削機の掘進の反力を取
ろうとする提案がなされている。
(b) Conventional technology Usually, when a lining is constructed with cast-in-place concrete, a shield is removed from the poured concrete until the poured concrete reaches a predetermined strength. You can't take the reaction force. Then, during the construction,
A proposal has been made to bury a reaction force rod in front of the tunnel in order to absorb the reaction force, and to use the reaction force rod to absorb the reaction force caused by the excavation of the excavator.

(C)0発明が解決しようとする問題点この方法では、
覆工を構築するために打設されろコンクリートの強度状
態にかかわらず、反力棒により(掘削機の掘進に必要な
反力を、既に構築済みの覆工から取ることが出来るが、
反力棒とシールド[掘削機側の掘進ジヤツキの配置状態
が正確に一致していないと、良好な状態で反力を取るこ
とが出来なくなるので、反力棒の設置に高度の正確さが
要求され、その設置作業に多くの手間と時間を要する不
都合が生じる。
(C)0 Problems that the invention attempts to solve In this method,
Regardless of the strength of the concrete that is cast to construct the lining, the reaction force required for the excavator to dig can be taken from the lining that has already been constructed.
Reaction force rod and shield [If the position of the digging jack on the excavator side does not match exactly, it will not be possible to take the reaction force in good condition, so a high degree of accuracy is required for the installation of the reaction force rod. This causes the inconvenience that the installation work requires a lot of effort and time.

本発明は、前述の欠点を解消すべく、反力棒と掘進用ジ
ヤツキの配置状態が正確に一致していなくとも、良好な
状態で反力を取ることが出来、従って反力棒の設置作業
を手間を掛けること無く短時間で行うことが出来ろシー
ルド掘削機の掘進方法を提供することを目的とするもの
である。
In order to solve the above-mentioned drawbacks, the present invention makes it possible to take the reaction force in a good condition even if the arrangement of the reaction force rod and the excavation jack do not match exactly, so that the installation of the reaction force rod can be carried out easily. The purpose of this invention is to provide a method for excavating with a shield excavator, which can be carried out in a short time without much effort.

(d)1問題点を解決するための手段 即ち、本発明は、掘進用ジヤツキと反力棒が直接当接係
合することから、上記した不都合が生じることに着目し
、反力棒(17a)から掘進用の反力を得る際に、(尿
道用ジヤツキ(7)と反力棒(17a)との間に、ジヤ
ツキ(7)及び反力棒(17a)と共に当接係合し得る
プレスリング(9)を介在させ、当該プレスリング(9
)を介して掘進用の反力を得るようにして構成される。
(d) Means for solving the first problem, that is, the present invention focuses on the fact that the above-mentioned inconvenience occurs because the excavation jack and the reaction rod directly abut and engage, and the reaction rod (17a ) When obtaining a reaction force for digging from the urethral jack (7) and the reaction rod (17a), a press that can be brought into abutting engagement with the jack (7) and the reaction rod (17a) A ring (9) is interposed between the press ring (9) and the press ring (9).
) to obtain the reaction force for digging.

なお、括弧内の番号は、図面における対応する要素を示
す、便宜的なものであり、従って、本記述は図面上の記
載に限定拘束されるものではない。以下のr (el 
、作用」の欄についても同様である。
Note that the numbers in parentheses are for convenience and indicate corresponding elements in the drawings, and therefore, this description is not limited to the descriptions in the drawings. The following r (el
The same applies to the column ``, action''.

(e)0作用 上記した構成により、本発明は、シールド1屈削1(2
)の掘進に際して、プレスリング(9)が、掘進用ジヤ
ツキ(7)及び反力棒(17a)と共に当接係合して、
応力伝達部材としての役割を果たすように作用する。
(e) 0 effect With the above-described configuration, the present invention can provide shield 1 bending 1 (2
), the press ring (9) abuts and engages with the digging jack (7) and the reaction rod (17a),
It acts as a stress transmitting member.

(f)、実施例 − 以下、本発明の実施例を図面に基づき説明する。(f), Example - Embodiments of the present invention will be described below based on the drawings.

第1図は本発明が適用されろトンネルの掘削現場の一例
を示す図、 第2図は第1図の■−■線による断面図、第3図は第1
図のI−1[線による断面図、第4図はテールボイド注
入管部分の詳細を示す拡大図、 第5図は第4図の平面図である。
Figure 1 is a diagram showing an example of a tunnel excavation site to which the present invention is applied, Figure 2 is a sectional view taken along the line ■-■ in Figure 1, and Figure 3 is a
FIG. 4 is an enlarged view showing details of the tail void injection pipe portion, and FIG. 5 is a plan view of FIG. 4.

トンネル1のt庭前現場は、第1図に示すように、円筒
形の外殻3を有するシールド掘削機2が設けら他でおり
、外殻3にはカッタ5が油圧モークロにより回転駆動自
在に支持されている。外殻3の内側には、掘進用ジヤツ
キ7が複数個、断面円形の外殻3に沿った形で配置され
ておす、間通用ジヤツキ7にはラム7aが矢印A、B方
向に突出駆動自在に設けられている。外殻3の後端、即
ち第1図右端部分は、第3図に示すように、所定の厚さ
を有するリング状の内殻11が設けられており、内殻1
1には所定角度ピンチでテールボイド注入装置10が複
数個、外殻3の内周に沿った形で設けられている。
At the site in front of the tunnel 1, as shown in Fig. 1, a shield excavator 2 having a cylindrical outer shell 3 is installed. is supported by Inside the outer shell 3, a plurality of digging jacks 7 are arranged along the outer shell 3, which has a circular cross section.A ram 7a of the intermediate jack 7 can be freely driven to protrude in the directions of arrows A and B. It is set in. As shown in FIG. 3, the rear end of the outer shell 3, that is, the right end portion in FIG. 1, is provided with a ring-shaped inner shell 11 having a predetermined thickness.
1 is provided with a plurality of tail void injection devices 10 along the inner periphery of the outer shell 3 at a predetermined angle.

テールボイド注入装置10は、第4図及び第5図に示す
ように、スライド筒10aを有しており、スライド筒1
0aには注入弁10bが、矢印A、B方向に摺動自在に
設けられている。注入弁10bには駆動シリンダ10c
のピストンロッド]、 Odが接続しており、更に注入
弁10bにはバイパス孔]、 Oe及び注入孔]、 O
fが設けられている。注入孔10fの先端には逆止弁1
0gが設けられており、またスライド筒10aの両側に
はパイプ10b、10iが接続している。
As shown in FIGS. 4 and 5, the tail void injection device 10 has a slide tube 10a.
An injection valve 10b is provided at 0a so as to be slidable in the directions of arrows A and B. The injection valve 10b has a drive cylinder 10c.
piston rod], Od is connected, and the injection valve 10b has a bypass hole], Oe and injection hole], O
f is provided. A check valve 1 is installed at the tip of the injection hole 10f.
0g, and pipes 10b and 10i are connected to both sides of the slide tube 10a.

一方、庭前されたトンネル1中には、トンネル1の1屈
削方向に冶って架台13が構築されており、架台13の
最前方には全体円環状に形成されたプレスリング9がア
ーム13aを介して、矢印A、B方向への移動及びアー
ム13aを中心にした矢印E、F方向への回動をある程
度許容した形で支持されている。プレスリング9には、
第2図に示すように、嵌入溝9bが全周に亙り形成され
ており、その中央部には、アーム13aと接続される接
続棒9aが設けられている。また、架台】3には、型枠
脱着装置15がトンネル1に沿って移動自在に設けられ
ており、型枠脱着装置15にはエレクタ15aが設けら
れている。また、架台13にはトンネル1に沿って、生
コンクリート供給管16が敷設されており、生コンクリ
−1・供給管16の先端にはホース16aを介して吹き
付け、ノズル16bが装着されている。
On the other hand, a pedestal 13 is constructed in the tunnel 1 which has been laid out in front of the garden in one bending direction of the tunnel 1, and at the forefront of the pedestal 13, a press ring 9 formed in an annular shape as a whole is attached to an arm. The arm 13a is supported in a manner that allows movement in the directions of arrows A and B and rotation in the directions of arrows E and F around the arm 13a to some extent. Press ring 9 has
As shown in FIG. 2, a fitting groove 9b is formed around the entire circumference, and a connecting rod 9a connected to the arm 13a is provided at the center thereof. Further, the frame 3 is provided with a formwork attachment/detachment device 15 movable along the tunnel 1, and the formwork removal/detachment device 15 is provided with an erector 15a. Further, a ready-mixed concrete supply pipe 16 is laid along the tunnel 1 on the pedestal 13, and a nozzle 16b is attached to the tip of the ready-mixed concrete 1 supply pipe 16 for spraying through a hose 16a.

また、トンネル1の覆工17は現場打ちコンクリートで
形成されており、覆工17中には、第3図に示すように
、コンクリート製の反力棒17aが所定ピンチで同一円
周上に配置されている。
Furthermore, the lining 17 of the tunnel 1 is made of cast-in-place concrete, and within the lining 17, as shown in FIG. has been done.

反力棒17a1よ、第1図に示すように、単位長さLl
の棒体17cがトンネル1の敷設方向に沿った形で連続
的に接続設置されており、隣接する棒体17c同士の接
続位置CPは、覆工17の現場打ちコンクリートの打ち
継ぎ面17bに対してトンネル1の長さ方向にずれた形
となっている。
The reaction rod 17a1, as shown in FIG. 1, has a unit length Ll.
The rods 17c are connected and installed continuously along the construction direction of the tunnel 1, and the connection position CP of adjacent rods 17c is relative to the pouring surface 17b of the cast-in-place concrete of the lining 17. The shape is shifted in the length direction of the tunnel 1.

シールド掘削機2等は以上のような構成を有するので、
シールド掘削機2によりトンネル1を1屈削する場合に
は、まず、掘進用ジヤツキ7のラム7aを矢印B方向に
突出駆動して、ラム7aの先端をプレスリング9に当接
係合させる。更に、その状態て、ラム7aをB方向に突
出させると、プレスリング9はラム7aの押圧力により
B方向に押され、B方向に移動する。すると、嵌入溝9
b中に、覆工17中に設置された反力棒17aの先端が
嵌入係合する。この状態で、ラム7aを更にB方向に突
出するように駆動すると、シールド1屈削機2は掘進用
ジヤツキ7、プレスリング9を介して反力棒17aから
A方向の反力を受けろ。
Since the shield excavator 2 etc. has the above configuration,
When the shield excavator 2 excavates the tunnel 1 by one bend, the ram 7a of the excavation jack 7 is first driven to protrude in the direction of arrow B, so that the tip of the ram 7a abuts and engages with the press ring 9. Further, in this state, when the ram 7a is projected in the B direction, the press ring 9 is pushed in the B direction by the pressing force of the ram 7a, and moves in the B direction. Then, the insertion groove 9
During b, the tip of the reaction rod 17a installed in the lining 17 is fitted into engagement. In this state, when the ram 7a is further driven to protrude in the B direction, the shield 1 bending machine 2 receives a reaction force in the A direction from the reaction rod 17a via the excavation jack 7 and the press ring 9.

この反力は、反力棒17aが既に構築済みの覆工17に
埋設されていることから、シールドl庭前機2を掘進さ
せるに十分なものである。また、プレスリング9は、ア
ーム13aを中心に矢印EXF方向にある程度揺動する
ので、ラム7aの突出状態や反力棒17aの設置状態が
多少A、B方向に不揃いであっても、適正な状態で反力
を取ることが出来る。また、ラム7aと反力棒17aの
配置状態がトンネル1円周方向ないしは直径方向にずれ
ていても、両者と共に接触するプレスリング9が応力伝
達部材としての役割を果たすので、反力の伝達はプレス
リング9を介して円滑に行うことが出来る。なお、プレ
スリング9の、反力棒17aと当接する嵌入溝9b内や
、ラム7aと当接する部分には、硬質ゴム等の弾性手段
を介在させることが、均等な反力伝達の上で望ましい。
This reaction force is sufficient to cause the shield l garden front machine 2 to dig because the reaction rod 17a is buried in the lining 17 that has already been constructed. In addition, since the press ring 9 swings to some extent in the direction of the arrow EXF around the arm 13a, even if the protruding state of the ram 7a or the installation state of the reaction rod 17a are slightly uneven in the A and B directions, the press ring 9 can be properly adjusted. It is possible to take reaction force in this state. Furthermore, even if the arrangement of the ram 7a and the reaction rod 17a is misaligned in the circumferential direction or diametrical direction of the tunnel 1, the press ring 9 in contact with both acts as a stress transmitting member, so that the reaction force is not transmitted. This can be done smoothly via the press ring 9. In order to evenly transmit the reaction force, it is desirable to interpose elastic means such as hard rubber in the fitting groove 9b of the press ring 9 that comes into contact with the reaction rod 17a and in the part that comes into contact with the ram 7a. .

次に、油圧モータ6を駆動してカッタ5を回転させると
、A方向への反力により、カッタ5と対向する切羽19
部分ばt庭前され、それと共にンールド堀削機2全体が
A方向に移動する形でt尿道する。シールド庭前機2が
入方向に回通すると、それに同期する形でラム7aがB
方向に突出され、反力棒17a側からンールド掘削@z
側に伝達さオコろ反力が常に適正な値に維持され、従っ
て適正な1庭前動作が行われろように調整される。
Next, when the hydraulic motor 6 is driven to rotate the cutter 5, a reaction force in the direction A causes the face 19 facing the cutter 5 to rotate.
A portion of the excavator is removed, and the entire rolled excavator 2 is moved in the A direction at the same time. When the shield Niwamae machine 2 passes in the incoming direction, the ram 7a moves to B in synchronization with it.
It is projected in the direction, and the rolled excavation is performed from the reaction rod 17a side @z
The Okoro reaction force transmitted to the side is always maintained at an appropriate value, and is therefore adjusted so that an appropriate forward motion can be performed.

こうして、一定距離A方向ヘンールド]庭前機2が掘進
したところで、う/、、 7 aをA方向に後退させ、
その状態てプレスリング9をA方向に移動させ、反力棒
leaの最左方のそれまでプレスリング9と当接係合し
ていた棒体17cの先端に、更に新たな棒体17cを接
続すると共に、シールドi庭前機2の掘進の結果生じた
円筒形の、覆工17を構築す・\き空間部分に、鉄筋1
7eをシールド掘削機2の内殻】1に沿った形で配筋す
る。
In this way, when the Niwazen machine 2 has dug a certain distance in the direction A, move the 7a back in the direction A,
In this state, the press ring 9 is moved in the A direction, and a new rod 17c is connected to the tip of the rod 17c on the leftmost side of the reaction rod lea, which was in contact with the press ring 9 until then. At the same time, a cylindrical lining 17 is constructed as a result of the excavation of the shield i garden front machine 2.
7e is arranged along the inner shell of the shield excavator 2.

この状態で、型枠脱着装置15のエレクタ15aでセグ
メント状に分割された型枠20を、配筋された鉄筋17
eの周囲に配置接続して、コンクリート打設空間21を
型枠20と内M11の間に形成する。型枠204よ、所
定のvAL 3で、第3図に示すように、構築すべき覆
工17の内周の曲率に一致した形で円弧状に形成されて
おり、そね等型枠20をトンネルlの円形断面に治って
配置接続することにより、幅L 3で外径がD】の円筒
状の組型枠22が形成されろ。この組型枠22は、覆工
17の構築方向であるA、B方向に連結され、第1図に
示すような、筒状の連結型枠23となる。
In this state, the formwork 20 divided into segments by the erector 15a of the formwork attachment/detachment device 15 is
The concrete casting space 21 is formed between the formwork 20 and the inner M11 by placing and connecting the concrete casting space 21 around the formwork 20 and the inner M11. As shown in FIG. 3, the formwork 204 has a predetermined vAL of 3, and is formed into an arc shape that matches the curvature of the inner circumference of the lining 17 to be constructed. By arranging and connecting them to the circular cross section of the tunnel l, a cylindrical frame 22 with a width L3 and an outer diameter D is formed. The assembled formwork 22 is connected in directions A and B, which are the construction directions of the lining 17, to form a cylindrical connected formwork 23 as shown in FIG.

コンクリート打設空間21が形成されたことろで、生コ
ンクリート供給管16及びホース16aを介して早強コ
ンクリートを吹き付はノズル16bから、コンクリート
打設空間21中に吹き付ける。この作業は、コンクリー
ト打設空間21の、第1図左側、従って切羽側の外部(
こ開放された部位から、既に構築状態にある覆工17の
端面17d(従って、この部位が覆工17の打ち継ぎ面
17bとなる)に向けて早強コンクリートを吹き付ける
形で行われ、端面17dに吹き付けられたコンクリート
は直ちに固まるので、早強コンクリー1−のコンクリ−
1〜打打設量21への打設は、端面17dから早強コン
クリートをA方向に積層してゆく形で行われる。なお、
早強コンクリートは、吹き付は後、直ちに凝固を開始す
るので、吹き付けられたコンクリートが開放状態にある
切羽側から外部に流出してしまうことは無い。
After the concrete placement space 21 is formed, early strength concrete is sprayed into the concrete placement space 21 from the nozzle 16b via the fresh concrete supply pipe 16 and the hose 16a. This work is carried out on the left side of the concrete casting space 21 in Figure 1, that is, on the outside of the face side (
This is done by spraying early-strengthening concrete from the opened area toward the end face 17d of the lining 17 that is already in the constructed state (therefore, this area becomes the pouring surface 17b of the lining 17), and the end face 17d Since the concrete sprayed on the concrete will harden immediately, the concrete with early strength concrete 1-
The pouring from 1 to 21 is performed by laminating early strength concrete in the A direction starting from the end face 17d. In addition,
Since early strength concrete starts solidifying immediately after being sprayed, the sprayed concrete will not flow out from the open face side.

こうして、棒体17c、17cの接続部分をもコンクリ
ートで埋設してしまい、更に覆工17の端面17dから
長さL2に亙り、コンクリートをコンクリート打設空間
21中に吹き付けたところで、再度、掘進用ジヤツキ7
のラム7aを矢印B方向に突出駆動して、ラム7aの先
端をプレスリング9に当接係合させる。すると、既に述
べた要領で、プレスリング9を介して反力棒17aから
A方向の反力を受けるので、カッタ5を回転駆動して、
再度A方向への掘進を開始する。
In this way, the connecting portions of the rods 17c, 17c are also buried in concrete, and concrete is sprayed into the concrete placement space 21 from the end surface 17d of the lining 17 over the length L2, and the concrete is again buried for excavation. Jyatsuki 7
The ram 7a is driven to protrude in the direction of arrow B, so that the tip of the ram 7a abuts and engages the press ring 9. Then, as described above, the reaction force in the direction A is received from the reaction rod 17a via the press ring 9, so the cutter 5 is rotationally driven.
Start digging in direction A again.

なお、シール1z堀削機2がA方向へ、掘進を開始する
と、外殻3及び内殻11もA方向へ移動し、第4図に示
すように、移動する内殻11は、既に凝固状態に到達し
た覆工17部分を、地中に置き去る形で移動する。また
、ンールド堀削機2が移動した後には、外殻3と内殻1
1の厚みに相当する幅L4なるテールボイド25が生じ
るので、各テールボイド注入袋W10の駆動シリンダ1
0Cを駆動して、ピストンロッド10dを、第4図A方
向に後退せさ、注入弁10bをスライド筒10aに沿っ
てA方向に移動させろ。すると、パイプ10hと注入孔
10fが整合するので、パイプ10hを介して注入剤を
テールボイド25に対して注入し、周囲の地山が崩壊す
ることを未然に防止する。なお、テールボイド注入装置
10からの注入祠のテールボイド25への注入が、終了
すると、駆動シリンダ10cによりビス)・ンロッド1
0dがB方向に突出駆動され、注入弁10bもB方向に
移動する。すると、パイプ1. Obとパイプ10iが
バイパス孔10eを介して連通ずるので、パイプ10h
から水等の洗浄液をパイプ101に向けて流し、パイプ
10h内の注入剤を除去清浄化する。
Note that when the seal 1z excavator 2 starts digging in the A direction, the outer shell 3 and the inner shell 11 also move in the A direction, and as shown in FIG. 4, the moving inner shell 11 is already in a solidified state. The 17th section of the lining that has reached this point is moved and left underground. In addition, after the rolled excavator 2 moves, the outer shell 3 and inner shell 1 are
Since a tail void 25 having a width L4 corresponding to the thickness of 1 is generated, the drive cylinder 1 of each tail void injection bag W10
0C to move the piston rod 10d backward in the direction A in FIG. 4, and move the injection valve 10b in the direction A along the slide tube 10a. Then, since the pipe 10h and the injection hole 10f are aligned, the injection agent is injected into the tail void 25 through the pipe 10h, thereby preventing the surrounding ground from collapsing. Note that when the injection from the tail void injection device 10 into the tail void 25 from the injection pit is completed, the drive cylinder 10c causes the screw rod 1 to
0d is driven to protrude in the B direction, and the injection valve 10b also moves in the B direction. Then, pipe 1. Since Ob and the pipe 10i communicate through the bypass hole 10e, the pipe 10h
A cleaning liquid such as water is flowed toward the pipe 101 to remove and clean the injection agent inside the pipe 10h.

こうする内に、連結型枠23の、第1図右方部分のコン
クリートは十分に凝固し、実用強度に達するので、シー
ルド掘削[2が所定路gIA方向に掘進して、再度コン
クリートを打設する際に、図中最右方の組型枠22を連
結型枠23から外し、更に型枠脱着装置15を移動させ
て、当該分離された組型枠22の下にエレクタ15aを
位置決めして、組型枠22を各型枠20に分解する。こ
うして分解された型枠20ば、型枠脱着装置15が入方
向に運搬し、新たに鉄筋17eの設置された部位で、連
結型枠23の、第1図左端の組型枠22に連結する形で
再度組立て、コンク’J−1−打設空間21を形成し、
再使用される。
During this process, the concrete in the right part of the connecting formwork 23 in Figure 1 solidifies sufficiently and reaches practical strength, so shield excavation [2] excavates in the direction of the designated path gIA and concrete is poured again. When doing so, the rightmost set frame 22 in the figure is removed from the connected form frame 23, and the formwork attachment/detachment device 15 is moved to position the erector 15a under the separated set frame 22. , the assembled formwork 22 is disassembled into each formwork 20. The formwork 20b disassembled in this way is transported in the incoming direction by the formwork attachment/detachment device 15, and is connected to the assembled formwork 22 at the left end in FIG. 1 of the connecting formwork 23 at the site where the reinforcing bars 17e are newly installed. Reassemble in the shape and form the conc' J-1 - pouring space 21,
Reused.

(已)1発明の効果 以上、説明したように、本発明によれば、反力棒17a
から掘進用の反力を得る際に、掘進用ジヤツキ7と反力
棒17aとの間に、ジヤツキ7及び反力棒17aと共に
当接係合し得るプレスリング9を介在させるようにした
ので、ラム7a。
(已) 1. Effects of the Invention As explained above, according to the present invention, the reaction rod 17a
When obtaining a reaction force for digging, a press ring 9 is interposed between the digging jack 7 and the reaction rod 17a, so that the press ring 9 can abut and engage with the jack 7 and the reaction rod 17a. Ram 7a.

従ってジヤツキ7と反力棒17aの配置状態が正確に一
致していなくても、両者と共に係合するプレスリング9
が応力伝達部材としての役割を果たすので、反力の伝達
は円滑に行われ、良好な状態で反力を取ることが可能と
なる。また、反力棒17aの設置に高度の正確さが要求
されるようなことが無くなるので、反力棒17aの設置
作業に要する手間と時間を大幅に短縮化することが出来
るっ
Therefore, even if the positions of the jack 7 and the reaction rod 17a do not match exactly, the press ring 9 engages with both.
Since it plays a role as a stress transmitting member, the reaction force is transmitted smoothly, and it becomes possible to take the reaction force in a good condition. Furthermore, since the installation of the reaction force rod 17a does not require a high degree of accuracy, the effort and time required for the installation work of the reaction force rod 17a can be greatly reduced.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明が適用されろトンネルの掘削現場の一例
を示す図、 第2図は第1図の■−■線による断面図、第3図は第1
図のI−I[[線による断面図、第4図はテールボイド
注入管部分の詳細を示す拡大図、 第5図は第4図の平面図である。 2 ・ ノールド掘削機 7 ・・・掘進用ジャνキ 9  プレスリング 17−覆工 17a   反力棒 出願人    三井建設株式会社 代理人  弁理士  相1)伸二 第2図 2シールド・掘屑り琳 ″′−10c 第3図 2長−!訃・搏削層・ 第4図 第5図 )○h
Figure 1 is a diagram showing an example of a tunnel excavation site to which the present invention is applied, Figure 2 is a sectional view taken along the line ■-■ in Figure 1, and Figure 3 is a
4 is an enlarged view showing details of the tail void injection pipe portion, and FIG. 5 is a plan view of FIG. 4. 2. Nord excavator 7... Excavation jack 9 Press ring 17 - Lining 17a Reaction bar Applicant Mitsui Construction Co., Ltd. Agent Patent attorney Phase 1) Shinji Figure 2 2 Shield/Scrap Reel'' ′-10c Fig. 3 2 length -! Grain, scraping layer, Fig. 4 Fig. 5) ○h

Claims (1)

【特許請求の範囲】 シールド掘削機の掘進用ジャッキを覆工内 に埋設された反力棒に押し当て、当該反力棒を介して掘
進用の反力を取りつつ掘進してゆくシールド掘削機の掘
進方法において、 前記反力棒から掘進用の反力を得る際に、 前記掘進用ジャッキと反力棒との間に、前記ジャッキ及
び反力棒と共に当接係合し得るプレスリングを介在させ
、当該プレスリングを介して掘進用の反力を得るように
して構成したシールド掘削機の掘進方法。
[Scope of Claims] A shield excavator that excavates by pressing the excavation jack of the shield excavator against a reaction rod buried in the lining, and taking the reaction force for excavation through the reaction rod. In the digging method, when obtaining a reaction force for digging from the reaction rod, a press ring is interposed between the excavation jack and the reaction rod, which can abut and engage together with the jack and the reaction rod. An excavation method using a shield excavator configured to obtain a reaction force for excavation through the press ring.
JP60159779A 1985-07-19 1985-07-19 Excavation method of shielding excavator Pending JPS6221989A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP60159779A JPS6221989A (en) 1985-07-19 1985-07-19 Excavation method of shielding excavator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP60159779A JPS6221989A (en) 1985-07-19 1985-07-19 Excavation method of shielding excavator

Publications (1)

Publication Number Publication Date
JPS6221989A true JPS6221989A (en) 1987-01-30

Family

ID=15701078

Family Applications (1)

Application Number Title Priority Date Filing Date
JP60159779A Pending JPS6221989A (en) 1985-07-19 1985-07-19 Excavation method of shielding excavator

Country Status (1)

Country Link
JP (1) JPS6221989A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01223298A (en) * 1988-03-03 1989-09-06 Sato Kogyo Co Ltd Construction of tunnel
JPH01223296A (en) * 1988-03-03 1989-09-06 Sato Kogyo Co Ltd Construction of tunnel
JPH01223297A (en) * 1988-03-03 1989-09-06 Sato Kogyo Co Ltd Construction of tunnel
JPH01223299A (en) * 1988-03-03 1989-09-06 Nippon Tetsudo Kensetsu Kodan Construction of tunnel
JPH03187493A (en) * 1989-12-14 1991-08-15 Nippon Tetsudo Kensetsu Kodan Constructing method of tunnel

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01223298A (en) * 1988-03-03 1989-09-06 Sato Kogyo Co Ltd Construction of tunnel
JPH01223296A (en) * 1988-03-03 1989-09-06 Sato Kogyo Co Ltd Construction of tunnel
JPH01223297A (en) * 1988-03-03 1989-09-06 Sato Kogyo Co Ltd Construction of tunnel
JPH01223299A (en) * 1988-03-03 1989-09-06 Nippon Tetsudo Kensetsu Kodan Construction of tunnel
JPH03187493A (en) * 1989-12-14 1991-08-15 Nippon Tetsudo Kensetsu Kodan Constructing method of tunnel

Similar Documents

Publication Publication Date Title
JPS6221989A (en) Excavation method of shielding excavator
JPS6221999A (en) Lining structure in tunnel
JP3753555B2 (en) Small-diameter propulsion machine
JPS6221998A (en) Method of constructing lining in tunnel
JPS6221997A (en) Method of placing concrete in lining
JPS6221990A (en) Shielding excavator
JP3168345B2 (en) Underground joining shield machine and tunnel joining method using it
JPH03132595A (en) Shield machine
JP2766352B2 (en) Shield machine
JPH02132295A (en) Constructing method for tunnel lining work
JPH0519000B2 (en)
JP3153852B2 (en) Tunnel lining equipment
JPH0369438B2 (en)
JP2516582B2 (en) Tunnel construction method
JPS62258093A (en) Method of underground joining construction of shield-tunnel
JP2578609B2 (en) Tunnel excavation method and device
JP3621790B2 (en) Tunnel lining apparatus and method
JPS6221996A (en) Shielding excavator
JP2664867B2 (en) Concrete pipe construction equipment
JP3789572B2 (en) Tunnel digging device and tunnel digging method
JP2526312B2 (en) Shield machine and in-situ lining type shield construction method using the machine
JPH089958B2 (en) Concrete pouring equipment for tunnel lining
JPS62291393A (en) Cutter apparatus of shield excavator
JPS62206198A (en) Method of constructing tunnel lining
JP2808373B2 (en) Shield backfill machine