JPS62189206A - Method for constructing bridge - Google Patents

Method for constructing bridge

Info

Publication number
JPS62189206A
JPS62189206A JP61032203A JP3220386A JPS62189206A JP S62189206 A JPS62189206 A JP S62189206A JP 61032203 A JP61032203 A JP 61032203A JP 3220386 A JP3220386 A JP 3220386A JP S62189206 A JPS62189206 A JP S62189206A
Authority
JP
Japan
Prior art keywords
bridge
pier
bridge body
construction
lower chord
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP61032203A
Other languages
Japanese (ja)
Other versions
JPH0361804B2 (en
Inventor
上前 行孝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MIYACHI IRON WORKS
MIYAJI TEKKOSHO KK
Original Assignee
MIYACHI IRON WORKS
MIYAJI TEKKOSHO KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MIYACHI IRON WORKS, MIYAJI TEKKOSHO KK filed Critical MIYACHI IRON WORKS
Priority to JP61032203A priority Critical patent/JPS62189206A/en
Publication of JPS62189206A publication Critical patent/JPS62189206A/en
Publication of JPH0361804B2 publication Critical patent/JPH0361804B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 〔発明の目的〕 (産業上の利用分野) 本発明は橋の構築方法にかかり、特に大径間でかつ橋脚
と橋台を有し、鋼材を主体とするトラス構造の橋体を有
する橋の構築方法に関する。
[Detailed Description of the Invention] [Objective of the Invention] (Industrial Field of Application) The present invention relates to a method for constructing a bridge, particularly a truss structure having a large span, piers and abutments, and mainly made of steel. This invention relates to a method of constructing a bridge having a bridge body.

(従来の技術) 例えば、第10図に示づような橋、すなわら橋台1.1
間に橋11JI2.2を有し、これら橋台1および橋脚
2聞にわたって上部に沓3.3・・・を介しトラス構造
の橋体4を架設する橋の構築に43いては、従来ケーブ
ル架設工法や張出し工法が一般に採られている。
(Prior art) For example, a bridge as shown in Fig. 10, ie, a bridge abutment 1.1
In the construction of a bridge, which has a bridge 11JI2.2 in between, and a truss structure bridge body 4 is erected over these abutments 1 and 2 piers via shoes 3.3...43, the conventional cable construction method is used. The overhang method is generally used.

なかでも張出し工法は、第11図に示づ°ように橋体4
部分を架設支保工5,5・・・を使用して架設したあと
、橋体4部分な力1クンタにしながらへ区間を経てB区
間に順次張出して架構するようにしている。
Among them, the overhang method is used to construct the bridge body 4 as shown in Figure 11.
After the sections are erected using the construction supports 5, 5, etc., the bridge body is constructed by sequentially extending it to section B through section B while applying a force of 1 kunta to each section of the bridge body.

また張出し工法の別法として第12図に示Jように橋脚
2に架設用の斜文保工6,6を設け、この斜文保工を使
用して橋体4を左右に順次張出し施工するようになされ
−(いる(刊行物、土木施IL法−座3、鋼橋上部構造
施工法、株式会社山尚堂発行参照)。
In addition, as an alternative method to the overhang construction method, as shown in Fig. 12, diagonal reliefs 6, 6 for erection are provided on the piers 2, and using these diagonal reliefs, the bridge body 4 is successively extended from side to side. (Refer to the publication, Civil Engineering IL Method-Za 3, Steel Bridge Superstructure Construction Method, Published by Sanshodo Co., Ltd.)

(発明が解決しようとする問題点) しかるに上記従来の張出し工法によると、支保工をはじ
めとする多大な架設資材や設備が必要となるという大き
な問題点がある。
(Problems to be Solved by the Invention) However, the conventional overhang construction method described above has a major problem in that it requires a large amount of construction materials and equipment including shoring.

上記の工法を採用する理由は、橋台1や橋脚2の上部に
回転または回転と水平移動を可能とした沓3.3・・・
により橋体4が支えられ、この荷重を下部工の橋台1や
橋脚2に伝える構造を採る関係上、カウンタとなるべき
側径間の橋体や斜交保工6.6がないと張出し工法を採
用覆ることができないことによる。
The reason for adopting the above construction method is that the shoes 3.3...
Since the bridge body 4 is supported by the bridge body 4 and the structure is to transmit this load to the abutments 1 and piers 2 of the substructure, the overhang method cannot be used if there is no bridge body or diagonal maintenance 6.6 in the side span that should act as a counter. Due to the fact that the adoption cannot be reversed.

また槽全体の架設を完了した時点において、架設時に入
る初期応力を解放するために橋脚2上の沓3を上下させ
ることが必要となることもあるが、橋体4は巨大である
だけに上記の作業はぎわめで危険であり、かつ困難を極
める作業となる。
Furthermore, when the construction of the entire tank is completed, it may be necessary to raise and lower the shoes 3 on the piers 2 in order to release the initial stress introduced during construction, but since the bridge body 4 is huge, the above The work involved is strenuous, dangerous, and extremely difficult.

特に上記張出し作業における橋体の架設中は、橋体を仮
固定した状態で作業が進められるため、地震や台風等の
異常時の荷重下にa3いては非常に危険な状態におかれ
ることが多いなどの種々の問題点があった。
In particular, during the erection of the bridge body in the above-mentioned overhanging work, the work is carried out with the bridge body temporarily fixed, so the A3 can be placed in an extremely dangerous situation under the load of an abnormality such as an earthquake or typhoon. There were various problems such as:

〔発明の構成〕[Structure of the invention]

(問題点を解決ザるための手段) 上記問題点を解決をはかるため、橋体は鋼Iを主体とす
る部材によるトラス構造とし、橋脚はコンクリート等を
主体とする橋の構築において、トラス構造の橋体を構成
する上弦材、下弦材、斜材の各取合部を橋脚の左右に固
着完結し、橋脚の左右に完結された取合部に橋体の各構
成部材を結合して順次張出し施工し、橋体を橋脚に剛結
一体化することを特徴とするものである。
(Means for solving the problem) In order to solve the above problem, the bridge body is made of a truss structure made of members mainly made of steel, and the piers are made of concrete, etc. The connecting parts of the upper chord, lower chord, and diagonal members that make up the bridge body are fixed and completed on the left and right sides of the pier, and each component of the bridge body is sequentially connected to the joints completed on the left and right sides of the pier. It is characterized by overhanging construction and rigidly integrating the bridge body with the piers.

(実施例) 以下、本発明を第1図乃至第9図に示す実施例を参照し
、第10図乃至第12図と共通する部材には同一符号を
用いて説明する。
(Embodiment) The present invention will be described below with reference to the embodiment shown in FIGS. 1 to 9, using the same reference numerals for the same members as in FIGS. 10 to 12.

第1図および第2図は本発明による構築方法を用いて構
築される橋の全体を示すもので、第1図示の橋は橋体全
部を鋼構造とした場合であり、第2図は橋脚近傍の下弦
材が非常に大ぎい圧宿力を受けることを考慮して、鋼製
下弦材を鉄筋コンクリ−]−7により補強した場合を示
している。
Figures 1 and 2 show the overall structure of a bridge constructed using the construction method according to the present invention. In consideration of the fact that the neighboring lower chord members will receive a very large compression force, the steel lower chord member is reinforced with reinforced concrete ]-7.

本発明においては、コンクリートを主体として横築され
る橋脚2にトラス構造の橋体4の上弦材8、下弦材9、
斜材10を結合するための取合部11.12.13が一
体に固着完結されている。
In the present invention, the upper chord member 8, the lower chord member 9,
Connecting portions 11, 12, and 13 for connecting the diagonal members 10 are integrally fixed.

第3図乃至第5図は上記取合部11.12゜13の設置
構造例を示すものである。
FIGS. 3 to 5 show examples of the installation structure of the above-mentioned connecting portions 11, 12° 13.

第3図示の場合は、鉄骨柱14の上部両側に上弦材取合
部11.11と斜材取合部13.13を、同下部両側に
下弦材取合部12.12をそれぞれ一体に有する取合部
材を橋脚2の構築段階においてその鉄骨柱14部分を橋
脚2内に埋設置るようにして橋脚2と取合部材とを一体
化し、橋脚2の両側面に上弦材取合部11.11、斜材
取合部13.13、下弦材取合部12.12がそれぞれ
突出された形態の橋脚構造とされる。
In the case shown in the third figure, the upper chord connecting part 11.11 and the diagonal connecting part 13.13 are integrally formed on both sides of the upper part of the steel column 14, and the lower chord connecting part 12.12 is integrally formed on both sides of the lower part. During the construction stage of the pier 2, the pier 2 and the connecting member are integrated by embedding the steel column 14 portion within the pier 2, and upper chord connecting portions 11 are formed on both sides of the pier 2. 11, the pier structure is such that diagonal member connecting portions 13.13 and lower chord connecting portions 12.12 are respectively protruded.

第71図示の場合は、橋脚2の施工時に所定の位nにア
ンカボルト15.16を埋設しておぎ、このアンカボル
ト15.16に上弦材取合部11゜11、斜材取合部1
3.13と、下弦材取合部12.12とをそれぞれ結合
することにより、橋脚2の両側面に上弦材取合部11.
11、斜材取合部13,13、および下弦材取合部12
.12がそれぞれ突出された形態の橋脚構造とされる。
In the case shown in Figure 71, anchor bolts 15.16 are buried at predetermined positions n during construction of the pier 2, and the upper chord connecting portions 11° 11 and the diagonal connecting portions 1 are attached to the anchor bolts 15.16.
3.13 and the lower chord connecting portions 12.12, the upper chord connecting portions 11.
11, diagonal member connecting portions 13, 13, and lower chord connecting portion 12
.. 12 is a pier structure with each protruding shape.

さらに第5図示の場合は、上弦材取合部11゜11、斜
材取合部13.13、下弦材取合部12゜12を一体に
有する取合部材を、橋脚2の上端に施工段階において埋
設されたアンカポル1−15に結合して橋脚2と一体に
各取合部が構成されている。
Furthermore, in the case shown in Fig. 5, a connecting member that integrally includes the upper chord connecting part 11. Each connecting portion is integrated with the bridge pier 2 by being connected to the anchor pole 1-15 buried in the bridge.

第6図乃至第9図は、前記第3図示の橋脚2にトラス構
造の橋体4を構築する場合の施工順序を示している。
6 to 9 show the construction order in the case of constructing the bridge body 4 having a truss structure on the bridge pier 2 shown in the third figure.

橋体4の架設手順としては、まず第7図示のように、橋
脚2に一体に形成されている取合部のうち左右の斜材取
合部13.13に斜材10,10の上端を剛結する一方
、左右の下弦材取合部12゜12に下弦材9.9を剛結
し、この下弦材9.9の先端に形成された結合部9A、
9Aに前記斜材10.10の下端を剛結Jる。
The procedure for constructing the bridge body 4 is to first attach the upper ends of the diagonal members 10, 10 to the left and right diagonal member connecting portions 13.13 of the connecting portions integrally formed on the pier 2, as shown in Figure 7. While rigidly connecting, a lower chord member 9.9 is rigidly connected to the left and right lower chord connecting portions 12°12, and a connecting portion 9A formed at the tip of this lower chord member 9.9,
Rigidly connect the lower ends of the diagonal members 10 and 10 to 9A.

ついでこの状態から第8図に示すJ:うに左右の上弦材
取合部11.11に上弦材8.8の一端を剛結し、この
上弦材8.8と下弦材9.9の各先端の結合部8A、8
A、98.98に垂直材16゜16を剛結する。
Next, from this state, one end of the upper chord member 8.8 is rigidly connected to the upper chord member joining parts 11.11 on the left and right sides of J: Urchin shown in Fig. 8, and each tip of the upper chord member 8.8 and the lower chord member 9.9 is connecting parts 8A, 8
A, Rigidly connect the vertical member 16°16 to 98.98.

こうしたのち最初と同様に下弦材8,8の先端の結合部
8B、8Bに斜材10.10を、下弦材9.9の先端に
次の下弦449.9をそれぞれ剛結すると同時に斜材1
0.10と下弦材9.9との先端を剛結するという手順
により順次橋脚2の左右に橋体4が張出され、最終的に
第1図における径間中央部Oで双方の橋脚2.2から張
出された橋体4./Iを結合して橋脚2.2間の架橋を
完了する。
After that, similarly to the beginning, the diagonal members 10.10 are rigidly connected to the connecting parts 8B, 8B at the tips of the lower chord members 8, 8, and the next lower chord 449.9 is rigidly connected to the tips of the lower chord members 9.9.
0.10 and the lower chord members 9.9, the bridge bodies 4 are successively extended to the left and right of the piers 2, and finally both piers 2 are attached at the center of the span O in Fig. 1. .Bridge body extended from 24. /I to complete the bridge between piers 2.2.

また橋脚2.2の反対側に張出される橋体4゜4は橋台
1.1上に結合されC橋脚2,2と橋台1.1間の架橋
を完了する。
Also, the bridge body 4.4 extending on the opposite side of the pier 2.2 is connected to the abutment 1.1 to complete the bridge between the C pier 2, 2 and the abutment 1.1.

なお、第2図示のように、橋脚2の下弦材取合部12.
12に剛結される下弦t149,9を鉄筋コンクリート
7で補強する場合には、ド弦材9,9の剛結後型枠を組
み、鉄筋を配したのちコンクリートを打設して硬化させ
たのち、次の下弦材9の接続作業に入るようにづ゛る。
In addition, as shown in the second figure, the lower chord connecting portion 12 of the pier 2.
When reinforcing the lower chord t149,9 which is rigidly connected to 12 with reinforced concrete 7, after the lower chord members 9,9 are rigidly connected, a formwork is constructed, reinforcing bars are placed, and concrete is poured and hardened. Now we can begin the work of connecting the next lower chord member 9.

こうすることにより、橋脚に近い下弦材9はコンクリー
トとの複合b’4造となり、最も大ぎい圧縮萄重を受(
プる部分の強度を十分に維持させることができる。
By doing this, the lower chord member 9 near the pier becomes a composite b'4 structure with concrete, and receives the greatest compression weight (
It is possible to maintain sufficient strength of the pulling part.

〔発明の効果〕〔Effect of the invention〕

以上説明したように、本発明は、橋体は鋼材を主体とす
る部材によるトラス構造とし、橋脚はコンクリート等を
主体とする橋の構築において、トラス構造の橋体を構成
する上弦材、下弦材、斜材の各取合部を橋脚の左右に固
着完結し、橋脚の左右に完結された取合部に橋体の各構
成部材を結合して順次張出し施工し、橋体を橋脚に剛結
一体化することにより橋を構築するようにしたので、従
来の張出し工法による橋の架設に必要不可欠とされてい
た多大の架設用資材、設備の大幅な削減が可能となり、
得られる経杭的効果はきわめて大きい。
As explained above, the present invention provides a bridge structure in which the bridge body is a truss structure made of members mainly made of steel, and the bridge piers are made mainly of concrete, etc. , each connection part of the diagonal members is fixed and completed on the left and right sides of the pier, and each component of the bridge body is connected to the connection parts completed on the left and right sides of the pier, and the bridge body is stretched out one after another, and the bridge body is rigidly connected to the pier. Since the bridge was constructed by integrating the bridges, it was possible to significantly reduce the amount of construction materials and equipment that were indispensable when constructing bridges using the conventional overhang method.
The benefits obtained are extremely large.

特に橋脚から橋体を張出し施工するとき、従来工法のよ
うに仮固定ではなく完結されでいるので、施工期間中の
地震や台風などによる巽常荷重条件下であってもきわめ
て安全性に優れている。
In particular, when constructing the bridge body by extending it from the piers, it is not temporarily fixed as in conventional construction methods, but is completely fixed, so it is extremely safe even under constant load conditions such as earthquakes and typhoons during the construction period. There is.

また橋体が橋脚と一体化される構築方法であるため、部
分的にトラス構造材を鋼材とコンクリートとによる合成
構造とすることが可能であり、部材の設4時におけるよ
り経列的な設計を行なうことができる。
In addition, since the construction method involves integrating the bridge body with the piers, it is possible to partially construct the truss structure using a composite structure of steel and concrete, which allows for a more longitudinal design when installing members. can be done.

さらに本発明方法によれば、高価な沓を使用する必要が
ないので、構築費の削減をはかることができるなど、従
来の張出し工法に比して種々上れた効果が得られる。
Further, according to the method of the present invention, there is no need to use expensive shoes, so construction costs can be reduced, and various other advantages can be obtained compared to the conventional overhang construction method.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明方法により構築する橋の一例を示ず正面
図、第2図は同他の例を示す正面図、第3図乃至第5図
(A>、<8)は本発明における橋脚の取合部の構造例
を示す部分正面図、第6図乃至第9図は施工順序を示ず
郡1明図、第10tM乃至第12図は従来の張出し工法
を示T説明図である。 1・・・橋台、2・・・橋脚、4・・・橋体、7・・・
鋼とコンクリ−1−の複合部材、8・・・上弦材、9・
・・下弦材、10・・・斜材、11・・・上弦材取合部
、12・・・下弦材取合部、13・・・斜月取合部、1
4・・・鉄骨柱、15゜16・・・アンカボルト。 出願人代理人  佐  藤  −雄 −¥J3図 柄4図 %6図      第7図 5P18図 9Py00図 殆11図 手続補正書 昭和61(「3 月18日 11例の表示 昭和61年 特許願 第32203号 2 発明の名称 橋の構築方法 3 補正をする者 事件との関係  特許出願人 株式会社 宮地鐵工所 4  代  理  人 I JL+ 襲 7 補正のス・j象 明細書の「発明の詳細な説明」ならびに図面。 7 補正の内容 (1)  本願用m門弟1頁下から第2行の「大径間」
を「大径間」と訂正する。 (2)  同上第2頁第7行の「ケーブル架設工法」を
「ベント式架設工法」と訂正する。 (3)  同上同真下から第3行乃至最下行の「(刊行
物土木施工法・・・山海堂発行参照)」を「(刊行物、
鋼道路橋施工便覧、社団法人日本道路協会発行参照)j
と訂正する。 (4)  同上第4真下から第2行の「圧宿力」r圧縮
力」と訂正する。 (5)  図面「第11図」、「第12図」を別紙の通
り補正する。
Fig. 1 is a front view showing an example of a bridge constructed by the method of the present invention, Fig. 2 is a front view showing another example of the bridge, and Figs. 3 to 5 (A>, <8) are A partial front view showing an example of the structure of a connecting part of a bridge pier, Figures 6 to 9 are diagrams of group 1 without showing the construction order, and Figures 10tM to 12 are T explanatory diagrams showing the conventional overhang construction method. . 1... Bridge abutment, 2... Pier, 4... Bridge body, 7...
Composite member of steel and concrete 1-, 8...Top chord material, 9-
...Lower chord member, 10... Diagonal member, 11... Upper chord member connection part, 12... Lower chord member connection part, 13... Diagonal member connection part, 1
4... Steel column, 15°16... Anchor bolt. Applicant's agent Sato - Male - J3 design 4 figures % 6 figures Figure 7 Figure 5P18 Figure 9Py00 Figure Most 11 figures Procedural amendment 1988 (Display of 11 cases on March 18, 1988 Patent application No. 32203 2 Method of building a bridge with the name of the invention 3 Relationship with the case of the person making the amendment Patent applicant Co., Ltd. Miyaji Iron Works 4 Agent I JL+ 7 “Detailed explanation of the invention” in the amended specification and drawings. 7. Contents of the amendment (1) “Large span” in the second line from the bottom of page 1 of the m disciple for the present application.
is corrected to "large span." (2) "Cable erection method" on page 2, line 7 of the above is corrected to "bent type erection method." (3) From the 3rd line to the bottom line from the bottom of the same page, replace “(Publication Civil Engineering Construction Method...Refer to Sankaido Publishing)” with “(Publication,
(See Steel Road Bridge Construction Handbook, published by Japan Road Association)
I am corrected. (4) Corrected "compression force" in the second line from the bottom of No. 4 above as "compression force". (5) The drawings “Figure 11” and “Figure 12” will be corrected as shown in the attached sheet.

Claims (1)

【特許請求の範囲】[Claims] 橋体は鋼材を主体とする部材によるトラス構造とし、橋
脚はコンクリート等を主体とする橋の構築において、ト
ラス構造の橋体を構成する上弦材、下弦材、斜材の各取
合部を橋脚の左右に固着完結し、橋脚の左右に完結され
た取合部に橋体の各構成部材を順次結合して張出す施工
により橋体を橋脚に剛結一体化することを特徴とする橋
の構築方法。
The bridge body is a truss structure made of members mainly made of steel, and the piers are made mainly of concrete. The bridge body is fixed and completed on the left and right sides of the pier, and the bridge body is rigidly integrated with the pier by sequentially connecting and extending each component of the bridge body to the connecting parts that are completed on the left and right sides of the pier. Construction method.
JP61032203A 1986-02-17 1986-02-17 Method for constructing bridge Granted JPS62189206A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP61032203A JPS62189206A (en) 1986-02-17 1986-02-17 Method for constructing bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP61032203A JPS62189206A (en) 1986-02-17 1986-02-17 Method for constructing bridge

Publications (2)

Publication Number Publication Date
JPS62189206A true JPS62189206A (en) 1987-08-19
JPH0361804B2 JPH0361804B2 (en) 1991-09-24

Family

ID=12352347

Family Applications (1)

Application Number Title Priority Date Filing Date
JP61032203A Granted JPS62189206A (en) 1986-02-17 1986-02-17 Method for constructing bridge

Country Status (1)

Country Link
JP (1) JPS62189206A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2022550266A (en) * 2019-09-29 2022-12-01 チャイナ レイルウェイ メジャー ブリッジ エンジニアリング グループ カンパニー リミテッド Method of erecting segment steel girders on pier top short slide girders (Pier-Top Short Slideway Girder)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2022550266A (en) * 2019-09-29 2022-12-01 チャイナ レイルウェイ メジャー ブリッジ エンジニアリング グループ カンパニー リミテッド Method of erecting segment steel girders on pier top short slide girders (Pier-Top Short Slideway Girder)

Also Published As

Publication number Publication date
JPH0361804B2 (en) 1991-09-24

Similar Documents

Publication Publication Date Title
CN106894326B (en) The construction method of assembled pretensioned prestressing corrugated steel web plate composite box girder
CN106906748B (en) Based on the construction method for mixing prestressed assembled corrugated steel web plate composite box girder
CN106758856B (en) The construction method of the pretensioned prestressing corrugated steel web plate composite box girder of precast block
US20030182883A1 (en) Prestressed composite truss girder and construction method of the same
JP3588325B2 (en) Construction method of single span and multi span composite girder bridges
CN106223183A (en) Assembled concrete-filled rectangular steel tube combination truss bridge and construction method
JP3844743B2 (en) Box girder bridge structure and its construction method
JP2734987B2 (en) Existing bridge repair method
JP3737475B2 (en) Box girder bridge structure and construction method
CN206570671U (en) Based on the prestressed assembled corrugated steel web plate composite box girder of mixing
KR100622452B1 (en) Multi-H section steel girder compounded part
CN113863487B (en) Construction process for connecting joints of beam-end steel concrete combined notched beam and primary and secondary beams
JPS62189206A (en) Method for constructing bridge
JP2734986B2 (en) Existing bridge repair method
JP2831934B2 (en) How to build substructure
JP2002275833A (en) Continuing method of simple beam of existing bridge and continuous beam structure
KR102033052B1 (en) Method for constructing truss bridge support with infilled tube using src girder
JPH0492007A (en) Composite pier
Nakai et al. Trends in steel-concrete composite bridges in Japan
KR20090084376A (en) Composite girder used steel-concrete of continuous of prestress bridge and it&#39;s building method
JPH0338245Y2 (en)
JP2522708B2 (en) Reinforcing bar tip assembly beam with formwork and reinforcing bar tip assembly method with formwork
JP3009582B2 (en) Construction method of continuous composite girder bridge between concrete slab and steel girder
JPH0128162B2 (en)
CN211499175U (en) Novel take assembled beam column node that dismouting supported

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees