JPS6131515A - Method of installing hull type caisson - Google Patents

Method of installing hull type caisson

Info

Publication number
JPS6131515A
JPS6131515A JP14964784A JP14964784A JPS6131515A JP S6131515 A JPS6131515 A JP S6131515A JP 14964784 A JP14964784 A JP 14964784A JP 14964784 A JP14964784 A JP 14964784A JP S6131515 A JPS6131515 A JP S6131515A
Authority
JP
Japan
Prior art keywords
caisson
hull
deck
upper concrete
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP14964784A
Other languages
Japanese (ja)
Inventor
Hideaki Hirano
平野 秀昭
Teruo Nohara
野原 輝雄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Heavy Industries Ltd
Original Assignee
Mitsubishi Heavy Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Heavy Industries Ltd filed Critical Mitsubishi Heavy Industries Ltd
Priority to JP14964784A priority Critical patent/JPS6131515A/en
Publication of JPS6131515A publication Critical patent/JPS6131515A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • E02D23/02Caissons able to be floated on water and to be lowered into water in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

PURPOSE:To reduce a cost, by a method wherein, after filling sand, having the same weight as that of upper concrete placed on the deck of a caisson, is charged in a hull type caisson, the caisson is sunk so that the upper concrete is submerged. CONSTITUTION:The inside of a center tank 16 and wing tanks 17 and 18 of a hull type caisson 11 is filled with a filling sand 19 for balance having the same weight as that of upper concrete intended to be placed on a deck 12. Thereafter, upper concrete 20 and breakwater concrete 21 are placed on the deck 12. Sea water is then poured into the caisson 11 through openings 13 of the deck 12 by means of openings 22 of the upper concrete 20 to seat the caisson 11 on rubble- mound 23 so that the upper concrete 20 is submerged down to lower than an average high tide waterline H.W.L. After the filling sand 19 is further charged through the openings 22 and 13 to replace sea water in the caisson 11 with the filling sand, underwater concrete 20a is placed in the openings 22.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は防波、防潮堤、護岸、堤防等の水中構造物の施
工に適用さnる船体ケーソンの据付方法に係るものであ
る。
DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a method for installing a ship's caisson, which is applied to the construction of underwater structures such as breakwaters, seawalls, seawalls, and embankments.

(従来の技術) 第3図は従来の船体ケーソン防波堤の据付工法の実施状
況を示し、船体ケーソン(1)内に海水を注入して同船
体ケーソン(1)を海底地盤上の捨石マウン)’(21
上に沈座させ、次いでデツキ(3)に設けた開孔(4)
から中詰砂(5)を船体(1)内に投入して海水と置換
させ、その後デツキ(3)に上部コンクリート(6)を
打設している。
(Prior art) Figure 3 shows the implementation of the conventional ship caisson breakwater installation method, in which seawater is injected into the ship's caisson (1) and the ship's caisson (1) is mounted on a rubble mound on the seabed. (21
The opening (4) is then made in the deck (3).
Filling sand (5) is poured into the hull (1) to replace seawater, and then upper concrete (6) is placed on the deck (3).

(発明が解決しようとする問題点) 前記従来の工法においては上部コンクリ−)(6)を打
設し易いように、デツキ(6)を平均満潮吃水線H,W
、Lの上に位置させるように捨石マウンl’(2)が構
築されているので、鋼製の船体(1)における平均満潮
吃水線附近に感温部分子−)を生じる同感温部分(四は
腐蝕が早いため、船体ケーソンの耐用年数に問題が生じ
ることとなる。
(Problems to be Solved by the Invention) In the conventional construction method, the deck (6) is placed at the mean high tide water line H, W so that it is easier to place the upper concrete (6).
Since the rubble stone mount l' (2) is constructed so as to be located above the mean high tide water line in the steel hull (1), the temperature sensitive part (4) which produces the temperature sensitive part (-) near the mean high tide water line in the steel hull (1) Since the caissons corrode quickly, problems will arise in the service life of the hull caissons.

この対策として前記感温部分(m)に腐蝕材止用コンク
リート(7)を打設する必要があり、コスト高となって
いた。
As a countermeasure for this, it is necessary to pour corrosion-preventing concrete (7) in the temperature-sensitive portion (m), resulting in high costs.

(問題点を解決するための手段) 本発明はこのような問題点を解決するために提案さ肚た
もので、船体ケーソン内に同ケーソンのデツキ上に打設
される上部コンクリートと同じ重量の中詰砂を投入し、
次いで前記デツキ上に上部コンクリートを打設し、しか
るのち前記上部コンクリート部が水没するように船体ケ
ーソンを沈座させることを特徴とする船体ケーソン据付
方法に係るものである。
(Means for Solving the Problems) The present invention was proposed in order to solve the above problems. Add filling sand,
The method of installing a hull caisson is characterized in that an upper concrete is then placed on the deck, and then the hull caisson is sunk so that the upper concrete portion is submerged in water.

(作用) 本発明においては前記したように、船体ケーソンを沈座
する前に、予め同船体内に、同船体デツキ上に打設さ牡
る上部コンクリートの重量に見合う、バランス用の中詰
砂を投入し、次いで前記デツキ上に上部コンクリートを
打設し、しかるのち船体ケーソンを同上部コンクリート
部分が水没するように沈座させたので、従来のように鋼
製の船体ケーソンに感温部が生じることがなくなる。
(Function) As described above, in the present invention, before the hull caisson is sunk, filling sand for balance is placed in the hull in advance in an amount corresponding to the weight of the upper concrete to be cast on the hull deck. Then, the upper concrete was placed on the deck, and then the hull caisson was sunk so that the upper concrete part was submerged in water, so a temperature-sensitive part was created in the steel hull caisson as in the conventional case. Things will go away.

従って本発明によれば船体ケーソンの感温部の防蝕用コ
ンクリートの打設が不要となり、船体ケーソンの設置コ
ストが低減されるとともに、感温部をなくしたことによ
って船体ケーソンの耐用年限が大幅に増大する。
Therefore, according to the present invention, it is not necessary to pour corrosion-resistant concrete into the temperature-sensing part of the hull caisson, reducing the installation cost of the hull caisson, and by eliminating the temperature-sensing part, the service life of the hull caisson is greatly extended. increase

(実施例) 以下本発明を図示の芙施例について説明する。(Example) The present invention will be described below with reference to the illustrated embodiments.

船体ケーソン(Ll)のデツキαり上に、船体の船首、
船尾方向、右舷、左舷方向に多数の開口(13)を設け
る。
On the deck of the hull caisson (Ll), the bow of the hull,
A large number of openings (13) are provided in the stern direction, starboard direction, and port direction.

(14)は中間フレーム09によって支持された船体ケ
ーソンα1)内の縦隔壁で、同縦隔壁(I(イ)及び前
記中間フレームa暖によってセンタタンク(161及び
ウィングタンク(17+α樽が区画されている。
(14) is a vertical bulkhead in the hull caisson α1 supported by the intermediate frame 09, and the center tank (161) and wing tank (17+α barrels are divided by the vertical bulkhead (I) and the intermediate frame a). There is.

同センタタンク(16)及びウィングタンクαη賭内に
、デツキα2上に打設予定の上部コンクリートの重量に
見合うように、バランス用の中詰砂α鵠を充填する。
Fill the center tank (16) and wing tank αη with filling sand α for balance to match the weight of the upper concrete scheduled to be cast on deck α2.

なお防波コンクリートの重量に見合うバランス川砂(1
9α)は、同防波コンクリートの打設個所とは反対側の
ウィングタンク(I7)内に充填する。
Balance river sand (1
9α) is filled into the wing tank (I7) on the opposite side from where the breakwater concrete is placed.

次いで前記デツキ(12+上に上部コンクリ−) (2
0)及び防波コンクリートaυを打設する。この際デツ
キα2の開口Q3+と同じ個所に開口(ハ)を設ける。
Next, the deck (upper concrete on top of 12+) (2
0) and pour concrete aυ. At this time, an opening (c) is provided at the same location as the opening Q3+ of the deck α2.

なお前記防波コンクリート0υは従来工法では、現地で
の船体ケーソンの沈設時に同ケーソン内にコンクリート
等を投入する必要があるので、その投入口を塞ぐ防波コ
ンクリートen+ま船体ケーソンの沈設後現地で施工し
ていたが、本方法では防波コンクリート0υが船体ケー
ソン沈設前に予め施工されるので、現地施工が省略され
、工費の節減、工期の低減が図られる。
In addition, with the conventional construction method, the breakwater concrete 0υ requires concrete, etc. to be poured into the caisson when the hull caisson is sunk on site. However, with this method, the breakwater concrete 0υ is pre-constructed before the hull caisson is sunk, so on-site construction is omitted, reducing construction costs and construction time.

前記したように事前工事を終了した船体ケーソン01)
を上部コンク’) −) (20+が平均満潮吃水線H
1W、L以下に没するように構築された海底地盤上の捨
石マウンド(支))の海上まで曳航する。
Hull caisson 01) for which preliminary construction has been completed as mentioned above.
The upper conch') -) (20+ is the average high tide water line H
The ship will be towed to the sea to a rubble mound (support) on the seabed built to be submerged below 1W,L.

かくして沈座予定場所に到着した船体ケーソン(11)
内に、上部コンクリート(社)の開口(221を介して
デツキα2)の開口いかも海水を注水して船体ケーソン
01)を捨石マウンド(ハ))上に上部コンクリート(
20)が平均満潮吃水線I(、W、L以下に水没するよ
うに沈座させる。
The hull caisson (11) thus arrived at the planned sinking location.
Inside the upper concrete (Deck α2) opening (through 221), seawater was poured into the upper concrete (Deck α2) and the hull caisson 01) was placed on top of the rubble mound (C)).
20) will be submerged below the mean high tide water line I (, W, L).

次いで海水を注水した前記開口(221(131から中
詰砂σ9)を投入して船体ケーソンI内の海水と置換す
る。
Next, seawater is poured into the opening (221 (from 131 to filling sand σ9)) to replace the seawater in the hull caisson I.

前記中詰砂α9)の投入完了後、上部コンクリート0θ
)の開口(2功に水中コンクリート(20α)を打設し
、かくして船体ケーソン0υを従来のように感温部が生
じることなく捨石マウンド(ハ)上に沈座させるもので
ある。
After the filling sand α9) has been added, the upper concrete 0θ
Underwater concrete (20α) is poured into the opening (2), and the hull caisson 0υ is thus allowed to sit on the rubble mound (c) without creating a temperature-sensitive part as in the past.

(発明の効果) 本発明によれば前記したように船体ケーソンの沈座に先
行して、同ケーソンのデツキ上に打設される上部コンク
リートと同じ1量の中詰砂を投入したのち上部コンクリ
ートを打設し、しかるのち船体ケーソンを前記上部コン
クリート部が水没するように沈座させることによって、
船体ケーソンに感温部が生じることがなく、従って本発
明によれば防蝕用コンクリートの打設が不要となり、船
体ケーソン据付作業の工期を縮減し、工費を節減しうる
ものである。また感温部を除去したことによって船体ケ
ーソンの耐用年限が増大するものである。
(Effects of the Invention) According to the present invention, as described above, prior to the sinking of the hull caisson, the same amount of filling sand as the upper concrete to be cast on the deck of the caisson is poured, and then the upper concrete is poured into the upper concrete. By placing the hull caisson and then sinking the hull caisson so that the upper concrete part is submerged in water,
There is no temperature-sensitive part in the hull caisson, and therefore, according to the present invention, it is not necessary to place corrosion-resistant concrete, and the construction period and construction cost for installing the hull caisson can be reduced. Also, by removing the temperature sensing part, the service life of the hull caisson is increased.

【図面の簡単な説明】[Brief explanation of drawings]

第1図は本発明の方法によって据付けられた船体ケーソ
ンの縦断面図、第2図は同船体ケーソンの沈座前の状態
を示す縦断面図、第3図は従来の船体ケーソンの据付方
法の実施状況を示す縦断面図である。 αυ・・・船体ケーソン、aの・・・デツキ、(13)
両開口、(Igl・・・中詰砂、翰・・・上部コンクリ
ート、@・・・開口復代理人 弁理士 岡 本 重 文 外3名
Fig. 1 is a longitudinal sectional view of a hull caisson installed by the method of the present invention, Fig. 2 is a longitudinal sectional view showing the state of the hull caisson before sinking, and Fig. 3 is a longitudinal sectional view of the hull caisson installed by the method of the present invention. It is a longitudinal cross-sectional view showing the implementation situation. αυ...hull caisson, a...deck, (13)
Both openings, (Igl...filling sand, kiln...upper concrete, @...opening sub-agent Patent attorney Shige Okamoto 3 other people)

Claims (1)

【特許請求の範囲】[Claims] 船体ケーソン内に同ケーソンのデッキ上に打設される上
部コンクリートと同じ重量の中詰砂を投入し、次いで前
記デッキ上に上部コンクリートを打設し、しかるのち前
記上部コンクリート部が水没するように船体ケーソンを
沈座させることを特徴とする船体ケーソン据付方法。
Packing sand of the same weight as the upper concrete to be cast on the deck of the caisson is poured into the hull caisson, and then the upper concrete is poured on the deck, and then the upper concrete part is submerged in water. A hull caisson installation method characterized by sinking the hull caisson.
JP14964784A 1984-07-20 1984-07-20 Method of installing hull type caisson Pending JPS6131515A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14964784A JPS6131515A (en) 1984-07-20 1984-07-20 Method of installing hull type caisson

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14964784A JPS6131515A (en) 1984-07-20 1984-07-20 Method of installing hull type caisson

Publications (1)

Publication Number Publication Date
JPS6131515A true JPS6131515A (en) 1986-02-14

Family

ID=15479793

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14964784A Pending JPS6131515A (en) 1984-07-20 1984-07-20 Method of installing hull type caisson

Country Status (1)

Country Link
JP (1) JPS6131515A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100393946C (en) * 2005-09-16 2008-06-11 刘新勇 Drum structure with wing
KR100856066B1 (en) 2008-03-18 2008-09-03 주식회사 동아지질 Testing device for installing caisson
KR101459666B1 (en) * 2013-12-11 2014-11-12 홍성철 Underwater Structures Prefabricated and Construction Method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5781513A (en) * 1981-09-16 1982-05-21 Penta Ocean Constr Co Ltd Construction of levee with horizontal top end

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5781513A (en) * 1981-09-16 1982-05-21 Penta Ocean Constr Co Ltd Construction of levee with horizontal top end

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100393946C (en) * 2005-09-16 2008-06-11 刘新勇 Drum structure with wing
KR100856066B1 (en) 2008-03-18 2008-09-03 주식회사 동아지질 Testing device for installing caisson
KR101459666B1 (en) * 2013-12-11 2014-11-12 홍성철 Underwater Structures Prefabricated and Construction Method

Similar Documents

Publication Publication Date Title
GB1574784A (en) Method and apparatus for casting tanks in water
JPS6131515A (en) Method of installing hull type caisson
JP2000290936A (en) Method and caisson for constructing bridge pier footing
JP2817466B2 (en) Work box
JPH11140893A (en) Manufacture and launching method for sinking box
JPH1193129A (en) Construction method for superstructure work for landing pier
JPH11117225A (en) Reinforcing method and device for mooring pile of floating pier
JPH0718641A (en) Floating wave killing bank
JP2815492B2 (en) How to build an underwater foundation
JP2000265450A (en) Artificial ground consisting of porous housing and construction method therefor
JP3412100B2 (en) Construction method of tide gate
SU652880A3 (en) Off shore platform for engineering structures
JPS6226371B2 (en)
JPS6340024A (en) Pile-type caisson work
JP2655322B2 (en) Construction method of revetment structure
JPH0444511A (en) Construction of breakwater
JPS622081B2 (en)
JPS628237Y2 (en)
JPS6018776B2 (en) Hull caisson construction method
JPH0415777Y2 (en)
JPS6233836Y2 (en)
JP3294118B2 (en) How to build an environmentally friendly submerged levee
JPH0363604B2 (en)
JPS58160420A (en) Levee body using king post
JPS6040404A (en) Construction of breakwater structure