JPH11117225A - Reinforcing method and device for mooring pile of floating pier - Google Patents

Reinforcing method and device for mooring pile of floating pier

Info

Publication number
JPH11117225A
JPH11117225A JP29320297A JP29320297A JPH11117225A JP H11117225 A JPH11117225 A JP H11117225A JP 29320297 A JP29320297 A JP 29320297A JP 29320297 A JP29320297 A JP 29320297A JP H11117225 A JPH11117225 A JP H11117225A
Authority
JP
Japan
Prior art keywords
mooring
reinforcing
pile
mooring pile
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP29320297A
Other languages
Japanese (ja)
Other versions
JP3852187B2 (en
Inventor
Moriyuki Egami
盛行 江上
Atsushi Arami
敦史 荒見
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
IHI Corp
Original Assignee
IHI Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by IHI Corp filed Critical IHI Corp
Priority to JP29320297A priority Critical patent/JP3852187B2/en
Publication of JPH11117225A publication Critical patent/JPH11117225A/en
Application granted granted Critical
Publication of JP3852187B2 publication Critical patent/JP3852187B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

PROBLEM TO BE SOLVED: To dispense with the welding work at a site in the connection beam for connecting the mooring piles. SOLUTION: A positioning mound 9 is constructed so as to have the same height in the root part projected from the sea bottom 8 of the mooring pile 5 for elevatably supporting the four corners of a floating body 4. A large diameter reinforcing pipe 10 is fitted outside each mooring pile 5 and is placed on the height-adjusting mound 9, and then filling concrete 11 is placed in the inside space and is fixed. The reinforcing pipes 10 being opposite right and left are connected by a connection beam 15 by means of bolts under the sea. The mooring pile 5 positioned above the reinforcing pipe 10 is covered with lining concrete 16.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は漁船や定期船等の係
船岸として用いる浮桟橋の係留杭補強方法及び装置に関
するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method and an apparatus for reinforcing a mooring pile of a floating pier used as a berth of a fishing boat or a liner.

【0002】[0002]

【従来の技術】港内に設置されている浮桟橋は、図9に
その一例の概略を示す如く、岸壁1から海上に上下方向
へ揺動自在に張り出させた連絡橋2の先端に、フラップ
3を介して連絡するように係船岸本体となる浮体4を浮
設配置し、且つ該浮体4の前後左右の四隅を、海底に打
ち込んで立設した鋼管製の係留杭5に、係留装置6を介
して昇降自在に沿わせて、浮体4が潮位の変化に追従し
て上下方向に変位するようにすると共に、浮体4の水平
方向の移動、特に左右方向の移動を係留杭5で拘束でき
るようにしてある。
2. Description of the Related Art As shown schematically in FIG. 9, a floating pier installed in a harbor is provided with a flap at a tip end of a connecting bridge 2 which projects from a quay 1 to the sea so as to swing vertically. A mooring device 6 is mounted on a mooring pile 5 made of a steel pipe which is erected by arranging a floating body 4 serving as a mooring pier main body so as to communicate with the mooring pier 3 at the four front, rear, right and left corners of the floating body 4. The floating body 4 can be displaced in the vertical direction following the change in the tide level, and the horizontal movement of the floating body 4, particularly the horizontal movement, can be restrained by the mooring pile 5. It is like that.

【0003】上記浮桟橋において、各係留杭5に作用す
る浮体4の移動力は、主として、浮体4の玄方向となる
左右方向の移動力であるため、従来では、それぞれ左右
の係留杭5の杭頭部同士を繋ぎビーム7で連結した門型
ラーメン構造を採用している。
In the above-mentioned floating pier, since the moving force of the floating body 4 acting on each mooring pile 5 is mainly a moving force in the left-right direction which is the direction of the floating body 4, conventionally, the moving force of the left and right mooring piles 5 is conventionally used. A portal-type ramen structure in which the heads of the piles are connected to each other by beams 7 is adopted.

【0004】[0004]

【発明が解決しようとする課題】ところが、左右の係留
杭5の杭頭部を繋ぎビーム7で連結して門型ラーメン構
造としてある場合、景観上の問題があるだけでなく、繋
ぎビーム7を現地で高所溶接することになるため、コス
ト高になると共に、現地での溶接により焼けた塗装部分
の再塗装作業が必要となり、しかも、潮位が最高のとき
でも繋ぎビーム7の下を自動車等が通過できる高さとし
なければならないので、係留杭5の高さを高く(海面上
8m位)しなければならず、係留杭に長いものが必要と
なり、更に、繋ぎビーム7は潮風に当ることから錆び易
い、等の問題がある。
However, when the pile heads of the left and right mooring piles 5 are connected by a connecting beam 7 to form a portal-type rigid frame structure, not only there is a problem in the scenery, but also the connecting beam 7 Welding at high places will increase the cost, and will require repainting of the burnt painted parts by welding on site. In addition, even when the tide level is the highest, cars and the like under the connecting beam 7 The height of the mooring pile 5 must be high (approximately 8 m above the sea surface), and a long mooring pile is required. In addition, the connecting beam 7 is exposed to sea breeze. There are problems such as easy rusting.

【0005】そこで、本発明は、景観上の問題を改善で
き、又、繋ぎビームの現地での溶接作業及びそれに付随
した塗装作業を不要とし、且つ係留杭の長さを努めて短
くすることができるような浮桟橋の係留杭補強方法及び
装置を提供しようとするものである。
Therefore, the present invention can solve the problem of landscape, eliminate the need for on-site welding work of the connecting beam and the accompanying painting work, and reduce the length of the mooring pile by shortening it. It is an object of the present invention to provide a method and apparatus for reinforcing a mooring pile of a floating pier.

【0006】[0006]

【課題を解決するための手段】本発明は、上記課題を解
決するために、海底に打ち込んで上端部を海面上へ突出
させて浮体の前後左右両端部の係留装置を沿わせるよう
にしてある前後左右各部の係留杭に、上方より該係留杭
よりも大径とした補強管を嵌めて海水中の所要深さ位置
に位置決めさせた後、各左右の係留杭間で上記海水中で
位置決めした補強管同士を繋ぎビームを介し繋ぎ、上記
補強管と係留杭との間の隙間に中詰コンクリートを注入
し、しかる後、上記補強管より上方の係留杭に、上記浮
体の係留装置を沿わせるようにするガイド面を被覆形成
するようにした浮桟橋の係留杭補強方法とし、又、海底
に打ち込んで上端部を海面上へ突出させて浮体の前後左
右両端部の係留装置を沿わせるようにしてある前後左右
各部の係留杭まわりの海底面上に、所要高さの位置決め
用マウンドを各マウンドの上面が同じ高さとなるように
構築し、且つ該各マウンド上に、各係留杭の外側に嵌め
て二重管構造となるようにした補強管を位置させて、該
補強管と係留杭との間の隙間に中詰コンクリートを詰め
て係留杭と補強管とを一体とすると共に、左右の係留杭
の補強管同士を補強用の繋ぎビームで繋ぎ、更に、上記
各補強管より上方の係留杭の外周を巻きコンクリートで
被覆して、上記係留装置を沿わせるようにした構成を有
する浮桟橋の係留杭補強装置とする。
According to the present invention, in order to solve the above-mentioned problems, the mooring device at the front, rear, left, and right ends of the floating body is driven into the seabed so that the upper end protrudes above the sea surface. After fitting a reinforcing pipe having a diameter larger than that of the mooring pile from above to the mooring piles of the front, rear, left and right parts, and positioning it at a required depth position in seawater, it was positioned in the seawater between the left and right mooring piles. The reinforcing pipes are connected to each other via a connecting beam, and filled concrete is injected into a gap between the reinforcing pipe and the mooring pile. Thereafter, the mooring device of the floating body is moved along the mooring pile above the reinforcing pipe. A mooring pile reinforcement method for a floating pier that covers the guide surface to be formed, and is driven into the seabed so that the upper end protrudes above the sea surface so that the mooring devices at the front, rear, left, and right ends of the floating body are made to follow. The mooring piles of the front, rear, left and right parts On the sea floor, a mound for positioning at a required height is constructed so that the upper surface of each mound has the same height, and on each mound, the mound pile is fitted outside the mooring pile to form a double pipe structure. The reinforcing pipe is located in the space between the reinforcing pipe and the mooring pile, and the gap between the reinforcing pipe and the mooring pile is filled with filling concrete to integrate the mooring pile with the reinforcing pipe. Further, a mooring pile reinforcement device for a floating pier having a configuration in which the outer periphery of the mooring pile above each of the reinforcing pipes is covered with rolled concrete so that the mooring device follows the mooring device.

【0007】左右に位置する係留杭が海水中に沈められ
て浮体と干渉しない深さ位置の繋ぎビームにより連結さ
れて補強されることになるため、現地での溶接作業及び
塗装作業が不要となり、又、繋ぎビームは浮体上の交通
障害とならないことから、係留杭の海面上の高さを低く
できるようになると共に、杭頭部間に繋ぎビームがない
ので景観も改善され、見栄えのよいものとなる。
Since the mooring piles located on the left and right are submerged in seawater and connected and reinforced by a connecting beam at a depth that does not interfere with the floating body, welding work and painting work on site are not required. In addition, since the connecting beam does not become a traffic obstacle on the floating body, the height of the mooring pile on the sea surface can be lowered, and since there is no connecting beam between the pile heads, the landscape is improved and it looks good Becomes

【0008】又、繋ぎビームで予め繋いである2つの補
強管を、各左右の係留杭に上方から嵌めて海水中の所要
深さ位置に位置決めさせるようにすることにより、作業
の合理化を図ることができる。
In addition, the work is rationalized by fitting the two reinforcing pipes previously connected by the connecting beam to the right and left mooring piles from above and positioning them at a required depth position in seawater. Can be.

【0009】更に、海底面に位置決め用のマウンドを構
築して該マウンド上面で補強管の位置決めを行わせるよ
うにしたことに代えて、各係留杭の所要高さ位置より補
強管を吊り下げて位置決めするようにしたり、各係留杭
の海底面より所要高さ位置に位置決め用のフランジを固
定し、該フランジで補強管を受けて位置決めさせるよう
にすることによって、海中作業をより少なくすることが
できるようになる。
Further, instead of constructing a mound for positioning on the sea floor and positioning the reinforcing pipe on the upper surface of the mound, the reinforcing pipe is hung from the required height position of each mooring pile. By performing positioning, or by fixing a positioning flange at a required height from the sea floor of each mooring pile and receiving the reinforcing pipe with the flange and positioning the mooring pile, it is possible to further reduce undersea work. become able to.

【0010】一方、各係留杭の補強管より上方を巻きコ
ンクリートで被覆することに代えて、大径の被覆管で被
覆させ、該被覆管と係留杭との間にコンクリートを詰め
て一体にするようにした構成とすることにより、型枠を
使用せずに済むので、作業をより合理化することができ
るようになる。
[0010] On the other hand, instead of covering the reinforcing pipe of each mooring pile with the concrete wound around it, the mooring pile is covered with a large-diameter cladding pipe, and concrete is packed between the cladding pipe and the mooring pile to be integrated. By adopting such a configuration, it is not necessary to use a mold, so that the work can be further streamlined.

【0011】[0011]

【発明の実施の形態】以下、本発明の実施の形態を図面
を参照して説明する。
Embodiments of the present invention will be described below with reference to the drawings.

【0012】図1乃至図4は本発明の実施の一形態を示
すもので、図9に示したと同様な浮桟橋において、左右
の係留杭5の杭頭部同士を繋ぎビーム7で連結すること
に代えて、左右の係留杭5を海水中で連結して補強した
構成とする。
FIGS. 1 to 4 show one embodiment of the present invention. In a floating pier similar to that shown in FIG. 9, the pile heads of right and left mooring piles 5 are connected to each other by beams 7. Instead, the left and right mooring piles 5 are connected and reinforced in seawater.

【0013】詳述すると、海水中において、海底8から
上方へ突出する各係留杭5まわりの海底面上に、位置決
め用となる所要高さのマウンド9をそれぞれ同一高さレ
ベルとなるように構築し、且つ係留杭5よりも大径で所
要の長さ(高さ)を有する補強管10を、上記位置決め
用のマウンド9上に載置させるように各係留杭5に上方
より嵌装して没水させ、上記マウンド9の上方位置で係
留杭5が補強管10により二重管構造となるようにし、
且つ該補強管10と係留杭5との間の隙間に中詰コンク
リート11を充填して両者を一体構造とし、又、上記左
右に位置する補強管10の間にH型鋼からなる繋ぎビー
ム15を左右方向水平に配置して、該繋ぎビーム15の
両端部を、補強管10の外周に固設されたH型鋼からな
るフランジ12に、添接板13及びボルト14により連
結して、左右に位置する係留杭5を海水中で補強した構
成とし、更に、上記補強管10よりも上方に突出位置す
る係留杭5の外周部を、巻きコンクリート16で被覆
し、該巻きコンクリート16の表面部に係留装置6を沿
わせるようにする。17は補強管10の下端に取り付け
たベースプレートを示す。
More specifically, in seawater, mounds 9 of required height for positioning are constructed on the sea bottom around each mooring pile 5 projecting upward from the sea bottom 8 so as to be at the same height level. The reinforcing pipe 10 having a larger diameter and a required length (height) than the mooring piles 5 is fitted from above to the mooring piles 5 so as to be placed on the positioning mound 9. Submerged, so that the mooring pile 5 has a double pipe structure with the reinforcing pipe 10 at a position above the mound 9,
In addition, a gap between the reinforcing pipe 10 and the mooring pile 5 is filled with filling concrete 11 to form an integral structure, and a connecting beam 15 made of H-shaped steel is provided between the reinforcing pipes 10 located on the left and right sides. The connecting beam 15 is disposed horizontally in the left-right direction, and both ends of the connecting beam 15 are connected to a flange 12 made of H-shaped steel fixed on the outer periphery of the reinforcing pipe 10 by an attachment plate 13 and bolts 14. The mooring pile 5 is reinforced in seawater, and the outer periphery of the mooring pile 5 projecting above the reinforcing pipe 10 is covered with a rolled concrete 16 and moored on the surface of the rolled concrete 16. The device 6 is made to follow. Reference numeral 17 denotes a base plate attached to the lower end of the reinforcing pipe 10.

【0014】なお、上記補強管10及び巻きコンクリー
ト16は、図2及び図4に拡大して示す如く、浮体4の
コーナー部の切り込みと対向する2面部を上下方向に沿
う平坦なガイド面16aとして、巻きコンクリート16
のガイド面16aに上記係留装置6の転動体6aを接触
させるようにしてある。
As shown in FIGS. 2 and 4, the reinforcing pipe 10 and the rolled concrete 16 have two flat portions facing the cuts at the corners of the floating body 4 as flat guide surfaces 16a extending along the vertical direction. , Rolled concrete 16
The rolling element 6a of the mooring device 6 is brought into contact with the guide surface 16a.

【0015】次に、係留杭5を補強する際の具体的手順
の一例を説明する。
Next, an example of a specific procedure for reinforcing the mooring pile 5 will be described.

【0016】先ず、図5に示す如く、海底深く打ち込ん
だ各係留杭5の海底面上の外周に、それぞれ上面が同一
水深レベルとなるように所要高さの位置決め用のマウン
ド9を、たとえば、雑石の積み上げによって構築する。
First, as shown in FIG. 5, a mound 9 for positioning at a required height is provided on the outer periphery of each mooring pile 5 which has been driven deep into the seabed so that the upper surface is at the same water depth level. Build by stacking of miscellaneous stone.

【0017】次に、図2及び図3に示す如く、予め、上
端部外周に繋ぎビーム連結用のフランジ12を溶接する
と共に下端部にベースプレート17を取り付けておいた
補強管10を、図6に示す如く、各係留杭5に上方から
嵌装して落し込んで上記位置決め用のマウンド9上に載
置させて位置決めさせるようにして、係留杭5の海水中
の一部を二重管構造とする。更に、係留杭5と補強管1
0との間の隙間に中詰コンクリート11を水中打設して
固化させることにより、補強管10の位置を固定する。
Next, as shown in FIGS. 2 and 3, a reinforcing pipe 10 in which a flange 12 for beam connection is welded to the outer periphery of an upper end portion and a base plate 17 is attached to a lower end portion in advance is shown in FIG. As shown, each mooring pile 5 is fitted and dropped from above and placed on the positioning mound 9 for positioning, so that part of the mooring pile 5 in seawater has a double pipe structure. I do. Further, the mooring pile 5 and the reinforcing pipe 1
The position of the reinforcing pipe 10 is fixed by casting underfill concrete 11 in water in the gap between 0 and solidification.

【0018】次いで、左右に位置する補強管10のフラ
ンジ12間に、左右方向に延びる繋ぎビーム15を寸法
合わせして配置し、該繋ぎビーム15の両端部を、フラ
ンジ12にそれぞれ添接板13とボルト14を用いて海
中にて連結する。なお、補強管10を繋ぎビーム15で
連結する作業と補強管10内に中詰コンクリート11を
打設する作業は前後逆であってもよい。又、予め、地上
にて、左右の補強管10のフランジ12間に、係留杭5
の左右間隔に合わせて繋ぎビーム15を溶接或いはボル
トにて一体に連結しておき、該繋ぎビーム15で連結し
た状態の左右の補強管10を左右の係留杭5に嵌装させ
るようにしてもよい。
Next, a connecting beam 15 extending in the left-right direction is arranged and arranged between the flanges 12 of the reinforcing pipe 10 located on the left and right sides, and both ends of the connecting beam 15 are attached to the flanges 12 by the attachment plates 13 respectively. And underwater using bolts 14. The operation of connecting the reinforcing pipes 10 by the connecting beams 15 and the operation of placing the filling concrete 11 in the reinforcing pipes 10 may be reversed. In addition, the mooring pile 5 is previously placed between the flanges 12 of the left and right reinforcing pipes 10 on the ground.
The connecting beams 15 are integrally connected to each other by welding or bolts in accordance with the left and right intervals, and the left and right reinforcing pipes 10 connected by the connecting beams 15 may be fitted to the left and right mooring piles 5. Good.

【0019】しかる後、各係留杭5の補強管10よりも
上方に突出位置する部分の外周に、化粧型枠をセット
し、該化粧型枠内に巻きコンクリート16を打設し、養
生後、化粧型枠を取り外すようにすることによって、図
1の如く補強が完了する。
Thereafter, a decorative form is set on the outer periphery of a portion of each mooring pile 5 projecting above the reinforcing pipe 10, and a rolled concrete 16 is poured into the decorative form, and after curing, By removing the decorative form, the reinforcement is completed as shown in FIG.

【0020】本発明では、係留杭5を海水中での所要高
さレベルで補強管10による二重管構造とし、且つ左右
の補強管10を繋ぎビーム15で連結して、海水中で左
右の係留杭5の補強を行うようにしたので、左右の杭頭
間を繋ぎビーム7で連結して門型ラーメン構造とした従
来方式の場合に比して景観を良好にすることができ、
又、現地で繋ぎビーム15を高所溶接する必要がないと
共に、それに付随した塗装作業も不要とすることがで
き、しかも、杭頭間の繋ぎビームを不要としたことか
ら、係留杭5の高さを、潮位を基準として定めることが
できて、従来よりも低く(短く)することができる。更
に、繋ぎビーム15は気中部よりも腐食性の低い海中に
位置することから、防食に対する費用が少なくて済むと
いう利点もある。
In the present invention, the mooring pile 5 has a double pipe structure with reinforcing pipes 10 at a required height level in seawater, and the right and left reinforcing pipes 10 are connected by connecting beams 15 so that the left and right moorings are left and right in seawater. Since the mooring pile 5 is reinforced, the landscape can be improved compared to the case of the conventional system in which the left and right pile heads are connected by the connecting beam 7 to form a portal-type rigid frame structure,
Further, it is not necessary to weld the connecting beam 15 at a high place on site, and it is also possible to eliminate the accompanying painting work. Further, since the connecting beam between the pile heads is not required, the height of the mooring pile 5 can be reduced. Can be determined based on the tide level, and can be lower (shorter) than before. Further, since the connecting beam 15 is located in the sea where corrosiveness is lower than that in the aerial part, there is an advantage that costs for anticorrosion can be reduced.

【0021】又、上記において、係留杭5を被覆させた
巻きコンクリート16は、係留装置6の転動体6aが接
する部分を平坦なガイド面16aとしてあることから、
浮体4が水平方向に移動しても転動体6aの接触係合性
を常に良好に保つことができる。
In the above, the rolled concrete 16 covering the mooring pile 5 has a flat guide surface 16a at the portion where the rolling element 6a of the mooring device 6 comes into contact with.
Even if the floating body 4 moves in the horizontal direction, the contact engagement of the rolling elements 6a can always be kept good.

【0022】次に、図7(イ)(ロ)は本発明の他の実
施の形態を示すもので、上記図1に示したと同様な構成
において、補強管10を所要高さレベルに位置決め定置
させるために、海底8に位置決め用のマウンド9を構築
することに代えて、補強管10を、係留杭5の補強管定
置位置よりも上方部から吊り下げるようにして位置決め
させるようにしたものである。
FIGS. 7 (a) and 7 (b) show another embodiment of the present invention. In a configuration similar to that shown in FIG. 1, the reinforcing tube 10 is positioned and fixed at a required height level. For this purpose, instead of constructing a positioning mound 9 on the seabed 8, the reinforcing pipe 10 is positioned so as to be suspended from an upper portion of the mooring pile 5 from the position where the reinforcing pipe is set. is there.

【0023】すなわち、係留杭5の外周部に小型のフッ
ク18を予め固設しておいて、フック18の外側を通し
て係留杭5に嵌装させた補強管10を、上記フック18
から長さ調整したワイヤロープやチェーン等の索状物1
9を用いて吊り下げた後、中詰コンクリート11、巻き
コンクリート16を同様に順次打設するようにしたもの
である。
That is, a small hook 18 is fixed to the outer periphery of the mooring pile 5 in advance, and the reinforcing pipe 10 fitted to the mooring pile 5 through the outside of the hook 18 is attached to the hook 18.
Objects such as wire ropes and chains whose length has been adjusted from
9, the concrete filling 11 and the wrapping concrete 16 are similarly cast sequentially.

【0024】図7(イ)(ロ)に示すようにしても、現
場での高所溶接作業等を不要とすることができる。
7 (a) and (b), it is possible to eliminate the need for welding at high places on site.

【0025】次いで、図8は本発明の更に他の実施の形
態を示すもので、図1に示したと同様な構成において、
補強管10を所要の高さレベルに位置決め定置させるた
めに、海底8に高さ調整マウンドを構築することに代え
て、予め、補強管10の外周部所要高さ位置に位置決め
用フランジ20を固設しておき、係留杭5を一定量打ち
込むことにより位置決め用フランジ20の海中での高さ
レベルを揃えるようにして、この位置決め用フランジ2
0上に補強管10を載置させるようにしたものである。
Next, FIG. 8 shows still another embodiment of the present invention. In the same configuration as shown in FIG.
In order to position the reinforcing pipe 10 at a required height level, instead of constructing a height adjustment mound on the seabed 8, a positioning flange 20 is fixed in advance at a required height position on the outer peripheral portion of the reinforcing pipe 10. The positioning flanges 20 are set in advance by driving the mooring pile 5 in a fixed amount so that the height levels of the positioning flanges 20 in the sea are made uniform.
The reinforcement tube 10 is placed on the top of the tube.

【0026】図8に示す方式の場合も、現地での溶接作
業及び塗装作業が不要であり、係留杭5の打ち込み深さ
が決まっている場合に特に有利である。
The method shown in FIG. 8 also eliminates the need for on-site welding and painting operations, and is particularly advantageous when the driving depth of the mooring pile 5 is determined.

【0027】なお、本発明は上記実施の形態にのみ限定
されるものではなく、補強管10及び係留杭5を被覆す
る巻きコンクリート16の形状は、係留杭5に単に沿わ
せた円筒形状であっても特に支障はないこと、又、図1
において、各係留杭5の補強管10よりも上方部を巻き
コンクリート16で被覆することに代えて、大径の被覆
管で被覆させ、該被覆管と係留杭5との間にコンクリー
トを詰めて一体化するようにしてもよいこと、その他本
発明の要旨を逸脱しない範囲内で種々変更を加え得るこ
とは勿論である。
The present invention is not limited only to the above embodiment, and the shape of the rolled concrete 16 covering the reinforcing pipe 10 and the mooring pile 5 is a cylindrical shape simply following the mooring pile 5. However, there is no particular problem.
In the above, instead of covering the upper part of each mooring pile 5 above the reinforcing pipe 10 with the wound concrete 16, the mooring pile 5 is covered with a large-diameter cladding pipe, and concrete is packed between the cladding pipe and the mooring pile 5. Needless to say, various changes may be made without departing from the spirit of the present invention.

【0028】[0028]

【発明の効果】以上述べた如く、本発明によれば、次の
如き優れた効果を発揮する。 (1) 海底に打ち込んで上端部を海面上へ突出させて浮体
の前後左右両端部の係留装置を沿わせるようにしてある
前後左右各部の係留杭に、上方より該係留杭よりも大径
とした補強管を嵌めて海水中の所要深さ位置に位置決め
させた後、各左右の係留杭間で上記海水中で位置決めし
た補強管同士を繋ぎビームを介し繋ぎ、上記補強管と係
留杭との間の隙間に中詰コンクリートを注入し、しかる
後、上記補強管より上方の係留杭に、上記浮体の係留装
置を沿わせるようにするガイド面を被覆形成するように
したので、従来の如きラーメン構造に比して景観を改善
できると共に、現地での高所溶接作業及び塗装作業を不
要にでき、又、繋ぎビームを、気中よりも腐食性の低い
海中に位置させたことによって、防食に対する費用の面
でも有利となる。 (2) 繋ぎビームで予め繋いである2つの補強管を、各左
右の係留杭に上方から嵌めて海水中の所要深さ位置に位
置決めさせるようにすることにより、海中での繋ぎビー
ムの連結作業をなくすことができるので、作業の更なる
合理化、能率化を図ることができる。 (3) 海底に打ち込んで上端部を海面上へ突出させて浮体
の前後左右両端部の係留装置を沿わせるようにしてある
前後左右各部の係留杭まわりの海底面上に、所要高さの
位置決め用マウンドを各マウンドの上面が同じ高さとな
るように構築し、且つ該各マウンド上に、各係留杭の外
側に嵌めて二重管構造となるようにした補強管を位置さ
せて、該補強管と係留杭との間の隙間に中詰コンクリー
トを詰めて係留杭と補強管とを一体とすると共に、左右
の係留杭の補強管同士を補強用の繋ぎビームで繋ぎ、更
に、上記各補強管より上方の係留杭の外周を巻きコンク
リートで被覆して、上記係留装置を沿わせるようにした
構成とすることにより、係留杭を確実に補強することが
できるだけでなく浮体上の交通の障害をなくすことがで
きて、係留杭の高さを低くすることができる。 (4) 海底面に位置決め用のマウンドを構築して該マウン
ド上面で補強管の位置決めを行わせるようにしたことに
代えて、各係留杭の所要高さ位置より補強管を吊り下げ
て位置決めするようにしたり、各係留杭の海底面より所
要高さ位置に位置決め用のフランジを固定し、該フラン
ジで補強管を受けて位置決めさせるようにすることによ
って、海中作業を少なくすることができて、より有利と
なる。 (5) 各係留杭の補強管より上方を巻きコンクリートで被
覆することに代えて、大径の被覆管で被覆させ、該被覆
管と係留杭との間にコンクリートを詰めて一体にするよ
うにした構成とすることにより、型枠を使用しなくて済
むので、作業をより合理化することができる。
As described above, according to the present invention, the following excellent effects are exhibited. (1) The mooring piles at each of the front, rear, left, and right parts that are driven into the seabed so that the upper end protrudes above the sea surface so that the mooring devices at the front, rear, left, and right ends of the floating body follow the floating body. After fitting the reinforcing pipes and positioning them at the required depth position in the seawater, the reinforcing pipes positioned in the seawater between the right and left mooring piles are connected via a connecting beam, and the reinforcing pipes and the mooring piles are connected. Filled concrete is injected into the gap between the reinforcing pipes, and thereafter, the guide surface for allowing the mooring device of the floating body to follow the mooring pile is formed on the mooring pile above the reinforcing pipe. In addition to improving the landscape compared to the structure, it eliminates the need for on-site welding at high places and painting, and also places the connecting beam in the sea, which is less corrosive than the air, to prevent corrosion. It is also advantageous in terms of cost. (2) Connecting work of connecting beams in the sea by fitting two reinforcing pipes previously connected by connecting beams to the right and left mooring piles from above and positioning them at the required depth position in seawater Can be eliminated, so that the work can be further streamlined and streamlined. (3) Positioning the required height on the sea floor around the mooring piles in each of the front, rear, left and right parts, which are driven into the seabed so that the upper end protrudes above the sea surface so that the mooring devices at the front, rear, left and right both ends of the floating body are along The mound is constructed so that the upper surface of each mound has the same height, and a reinforcing pipe fitted to the outside of each mooring pile to form a double pipe structure is positioned on each mound, and the reinforcement is performed. Filling the gap between the pipe and the mooring pile with filling concrete, the mooring pile and the reinforcing pipe are integrated, and the reinforcing pipes of the left and right mooring piles are connected with a connecting beam for reinforcement. By covering the outer periphery of the mooring pile above the pipe with rolled concrete and extending along the mooring device, not only can the mooring pile be reliably reinforced, but also obstacles to traffic on the floating body Can be eliminated, the height of the mooring pile Can be lowered. (4) Instead of constructing a mound for positioning on the sea floor and positioning the reinforcing pipe on the upper surface of the mound, suspending and positioning the reinforcing pipe from the required height position of each mooring pile Or by fixing a positioning flange at a required height position from the sea bottom of each mooring pile, and by positioning the flange by receiving a reinforcing pipe, it is possible to reduce undersea work, It is more advantageous. (5) Instead of covering the reinforcement pipe of each mooring pile above the reinforcing pipe with concrete, cover it with a large-diameter cladding pipe and pack concrete between the cladding pipe and the mooring pile to integrate them. With this configuration, it is not necessary to use a formwork, so that the work can be further streamlined.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の浮桟橋の係留杭補強装置の実施の一形
態を示す正面図である。
FIG. 1 is a front view showing an embodiment of a mooring pile reinforcing device for a floating pier according to the present invention.

【図2】図1のA−A方向拡大矢視図である。FIG. 2 is an enlarged view in the direction of arrows AA in FIG. 1;

【図3】図2のB−B方向矢視図である。FIG. 3 is a view taken in the direction of arrows BB in FIG. 2;

【図4】図1のC−C方向拡大矢視図である。4 is an enlarged view in the direction of arrows CC in FIG. 1;

【図5】係留杭の具体的な補強手順を示すもので、係留
杭の根本部に高さ調整マウンドを構築した状態の概要図
である。
FIG. 5 is a schematic diagram showing a specific reinforcing procedure of the mooring pile, and showing a state in which a height adjusting mound is constructed at the root of the mooring pile.

【図6】係留杭の具体的な補強手順を示すもので、左右
の係留杭を繋ぎビームで連結した状態の概要図である。
FIG. 6 is a schematic diagram showing a specific procedure for reinforcing the mooring piles, in a state where left and right mooring piles are connected by connecting beams.

【図7】本発明の他の実施の形態を示すもので、(イ)
は係留杭を二重管構造とした部分の正面図、(ロ)は
(イ)のD−D方向拡大矢視図である。
FIG. 7 shows another embodiment of the present invention.
Is a front view of a portion where the mooring pile has a double-pipe structure, and (b) is an enlarged view in the direction of arrow DD in (a).

【図8】本発明の更に他の実施の形態を示す部分正面図
である。
FIG. 8 is a partial front view showing still another embodiment of the present invention.

【図9】浮桟橋の一例を示す概略図である。FIG. 9 is a schematic view showing an example of a floating pier.

【符号の説明】[Explanation of symbols]

4 浮体 5 係留杭 6 係留装置 8 海底 9 位置決め用のマウンド 10 補強管 11 中詰コンクリート 12 フランジ 14 ボルト 15 繋ぎビーム 16 巻きコンクリート 16a ガイド面 19 索状物 20 位置決め用フランジ Reference Signs List 4 Floating body 5 Mooring pile 6 Mooring device 8 Sea floor 9 Mound for positioning 10 Reinforcement pipe 11 Filling concrete 12 Flange 14 Bolt 15 Connecting beam 16 Rolled concrete 16a Guide surface 19 Wire 20 Positioning flange

Claims (7)

【特許請求の範囲】[Claims] 【請求項1】 海底に打ち込んで上端部を海面上へ突出
させて浮体の前後左右両端部の係留装置を沿わせるよう
にしてある前後左右各部の係留杭に、上方より該係留杭
よりも大径とした補強管を嵌めて海水中の所要深さ位置
に位置決めさせた後、各左右の係留杭間で上記海水中で
位置決めした補強管同士を繋ぎビームを介し繋ぎ、上記
補強管と係留杭との間の隙間に中詰コンクリートを注入
し、しかる後、上記補強管より上方の係留杭に、上記浮
体の係留装置を沿わせるようにするガイド面を被覆形成
することを特徴とする浮桟橋の係留杭補強方法。
1. A mooring pile at each of the front, rear, left, and right portions, which is driven into the seabed so that an upper end portion protrudes above the sea surface so that mooring devices at both front, rear, left, and right ends thereof are larger than the mooring pile from above. After fitting the reinforcing pipe having the diameter and positioning it at the required depth position in the seawater, connecting the reinforcing pipes positioned in the seawater between the left and right mooring piles via connecting beams, the reinforcing pipe and the mooring pile Characterized in that a filling surface is filled with a guide surface for allowing the mooring device of the floating body to follow the mooring pile above the reinforcing pipe. Mooring pile reinforcement method.
【請求項2】 繋ぎビームで予め繋いである2つの補強
管を、各左右の係留杭に上方から嵌めて海水中の所要深
さ位置に位置決めさせるようにする請求項1記載の浮桟
橋の係留杭補強方法。
2. The mooring of a floating pier according to claim 1, wherein the two reinforcing pipes connected in advance by the connecting beam are fitted to the left and right mooring piles from above and positioned at a required depth position in seawater. Pile reinforcement method.
【請求項3】 海底に打ち込んで上端部を海面上へ突出
させて浮体の前後左右両端部の係留装置を沿わせるよう
にしてある前後左右各部の係留杭まわりの海底面上に、
所要高さの位置決め用マウンドを各マウンドの上面が同
じ高さとなるように構築し、且つ該各マウンド上に、各
係留杭の外側に嵌めて二重管構造となるようにした補強
管を位置させて、該補強管と係留杭との間の隙間に中詰
コンクリートを詰めて係留杭と補強管とを一体とすると
共に、左右の係留杭の補強管同士を補強用の繋ぎビーム
で繋ぎ、更に、上記各補強管より上方の係留杭の外周を
巻きコンクリートで被覆して、上記係留装置を沿わせる
ようにした構成を有することを特徴とする浮桟橋の係留
杭補強装置。
3. A mooring pile at each of the front, rear, left, and right ends, which is driven into the seabed so that the upper end protrudes above the sea surface so that the mooring devices at the front, rear, left, and right ends of the floating body follow the seabed.
A positioning mound having a required height is constructed so that the upper surface of each mound has the same height, and a reinforcing pipe which is fitted on the outside of each mooring pile to form a double pipe structure is provided on each mound. Then, while filling the gap between the reinforcing pipe and the mooring pile with filled concrete, the mooring pile and the reinforcing pipe are integrated, and the reinforcing pipes of the left and right mooring piles are connected with a connecting beam for reinforcement, Furthermore, the mooring pile reinforcing device for a floating pier has a configuration in which the outer periphery of the mooring pile above each of the reinforcing pipes is covered with rolled concrete so that the mooring device can follow the mooring pile.
【請求項4】 海底面に位置決め用のマウンドを構築し
て該マウンド上面で補強管の位置決めを行わせるように
したことに代えて、各係留杭の所要高さ位置より補強管
を吊り下げて位置決めするようにした請求項3記載の浮
桟橋の係留杭補強装置。
4. Instead of constructing a mound for positioning on the sea floor and positioning the reinforcing pipe on the upper surface of the mound, the reinforcing pipe is suspended from a required height position of each mooring pile. The mooring pile reinforcing device for a floating pier according to claim 3, wherein the positioning is performed.
【請求項5】 海底面に位置決め用のマウンドを構築し
て該マウンド上面で補強管の位置決めを行わせるように
したことに代えて、各係留杭の海底面より所要高さ位置
に位置決め用のフランジを固定し、該フランジで補強管
を受けて位置決めさせるようにする請求項3記載の浮桟
橋の係留杭補強装置。
5. Instead of constructing a mound for positioning on the sea bottom and positioning the reinforcing pipe on the upper surface of the mound, the positioning mound is located at a required height from the sea bottom of each mooring pile. The mooring pile reinforcing device for a floating pier according to claim 3, wherein the flange is fixed, and the reinforcing pipe is received and positioned by the flange.
【請求項6】 左右の係留杭に嵌装させる各補強管と繋
ぎビームとが予め一体に連結されているものを用いるよ
うにする請求項3、4又は5記載の浮桟橋の係留杭補強
装置。
6. A mooring pile reinforcing device for a floating pier according to claim 3, 4 or 5, wherein the reinforcing pipes to be fitted to the left and right mooring piles and the connecting beam are connected in advance. .
【請求項7】 各係留杭の補強管より上方を巻きコンク
リートで被覆することに代えて、大径の被覆管で被覆さ
せ、該被覆管と係留杭との間にコンクリートを詰めて一
体にするようにした請求項3、4、5又は6記載の浮桟
橋の係留杭補強装置。
7. In place of covering the reinforcement pipes of each mooring pile above the reinforcement pipe with concrete, instead of covering with a large-diameter cladding pipe, concrete is packed between the cladding pipe and the mooring pile to be integrated. The mooring pile reinforcing device for a floating pier according to claim 3, 4, 5, or 6.
JP29320297A 1997-10-13 1997-10-13 Mooring pile reinforcement method and apparatus for floating pier Expired - Fee Related JP3852187B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP29320297A JP3852187B2 (en) 1997-10-13 1997-10-13 Mooring pile reinforcement method and apparatus for floating pier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP29320297A JP3852187B2 (en) 1997-10-13 1997-10-13 Mooring pile reinforcement method and apparatus for floating pier

Publications (2)

Publication Number Publication Date
JPH11117225A true JPH11117225A (en) 1999-04-27
JP3852187B2 JP3852187B2 (en) 2006-11-29

Family

ID=17791753

Family Applications (1)

Application Number Title Priority Date Filing Date
JP29320297A Expired - Fee Related JP3852187B2 (en) 1997-10-13 1997-10-13 Mooring pile reinforcement method and apparatus for floating pier

Country Status (1)

Country Link
JP (1) JP3852187B2 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100720038B1 (en) 2005-04-15 2007-05-21 인하대학교 산학협력단 Elevation adjustable bridge column device
KR100720039B1 (en) 2005-04-15 2007-05-21 인하대학교 산학협력단 Inclined level bridge adjustable device
JP2012246717A (en) * 2011-05-31 2012-12-13 Mitsui Eng & Shipbuild Co Ltd Floating pier
CN110792043A (en) * 2019-11-26 2020-02-14 洪飞 Automatic paint supplementing equipment for temporary
CN111778861A (en) * 2020-07-10 2020-10-16 浙江交工金筑交通建设有限公司 Underwater tie beam prefabrication installation construction method
CN111827146A (en) * 2020-08-11 2020-10-27 沈徐彬 Main longitudinal beam reinforced structure for bridge construction
JP2020180450A (en) * 2019-04-24 2020-11-05 エイチ・アール・ディー・シンガポール プライベート リミテッド House floating prevention device, house floating prevention structure using the floating prevention device, and house provided with the floating prevention device or the floating prevention structure

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100720038B1 (en) 2005-04-15 2007-05-21 인하대학교 산학협력단 Elevation adjustable bridge column device
KR100720039B1 (en) 2005-04-15 2007-05-21 인하대학교 산학협력단 Inclined level bridge adjustable device
JP2012246717A (en) * 2011-05-31 2012-12-13 Mitsui Eng & Shipbuild Co Ltd Floating pier
JP2020180450A (en) * 2019-04-24 2020-11-05 エイチ・アール・ディー・シンガポール プライベート リミテッド House floating prevention device, house floating prevention structure using the floating prevention device, and house provided with the floating prevention device or the floating prevention structure
CN110792043A (en) * 2019-11-26 2020-02-14 洪飞 Automatic paint supplementing equipment for temporary
CN111778861A (en) * 2020-07-10 2020-10-16 浙江交工金筑交通建设有限公司 Underwater tie beam prefabrication installation construction method
CN111827146A (en) * 2020-08-11 2020-10-27 沈徐彬 Main longitudinal beam reinforced structure for bridge construction

Also Published As

Publication number Publication date
JP3852187B2 (en) 2006-11-29

Similar Documents

Publication Publication Date Title
US6450734B1 (en) Transportation underwater tunnel system
CN106677258A (en) Installing process of offshore water taking head caisson of power plant
JPH11117225A (en) Reinforcing method and device for mooring pile of floating pier
CN109707002B (en) Device and method for accurately positioning, sinking and installing large water intake head
JPH09268562A (en) Dry working method and working case employed therefor
CN211368578U (en) High stake combination wharf structure of sheet pile
JP2817466B2 (en) Work box
JP2000110153A (en) Sea bottom soft fixed offshore concrete structure
CN210658215U (en) Weighing type ship-leaning component mounting device
JP2566414Y2 (en) Breakwater structure
JP2868725B2 (en) Seawall repair method
JP3776690B2 (en) Jacket structure
JP2827536B2 (en) Sinking method for submerged boxes
JPH1171718A (en) Method for reinforcing construction of underwater part of existing bridge pier
JPS6340024A (en) Pile-type caisson work
JPS5910173Y2 (en) Floating pier mooring device
JP2000249295A (en) Tank construction method
JPS60242208A (en) Straight pile type dolphine landing pier structure
JPH01310094A (en) Sinking method
JPH053542Y2 (en)
JP2001003332A (en) Immersion method for caisson and floater for immersing the caisson
JPS6233822Y2 (en)
JP2002047664A (en) Conveying device and method for jacket structure
JPS6131515A (en) Method of installing hull type caisson
JP2002047666A (en) Reinforcing structure for underwater foundation and installation method for underwater foundation

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20041001

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20060801

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20060815

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20060828

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090915

Year of fee payment: 3

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100915

Year of fee payment: 4

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100915

Year of fee payment: 4

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110915

Year of fee payment: 5

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110915

Year of fee payment: 5

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120915

Year of fee payment: 6

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120915

Year of fee payment: 6

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130915

Year of fee payment: 7

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees